Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Project and Technical Overview
Victor Krabbendam LSST Project Manager
LSST All Hands Meeting
August 13 - 17, 2012
2
LSST design is solid and teams are preparing for final design and a construction start
The LSST scope, requirements, and design are well understood
– Prototypes are reducing risk and refining designs
– Major subsystem requirements and ICDs are in place
– Diverse and experienced team working to develop LSST
LSST design maturity supports robust cost, risk, and schedules
– Sufficient for CD-1, PDR, and May Cost Review
Now we need to focus on next steps
– DOE CD-3a for long lead procurement authorization
– NSF Final Design Review
– NSF Construction Authorization in July 2014
3
7 year 3 month schedule developed to align with camera delivery to summit in July 2019
4
LSST Total Federal Construction Budget
PMO: $41M 7%
DM: $121M 19%
Camera: $113M 18%
T&S: $174M 28%
EPO: $12M 2%
Commissioning: $32M
5%
Contingency: $133M
21%
Base Budget $ 492.70 M
NSF Contingency $ 86.2 M
DOE Contingency $ 47.0 M
$ 625.9 M
5
Systems Engineering continues to organize the technical baselines
SRD LPM-17
LSST System Requirements
LSE-29
Obs. System Specifications LSE-30
Subsystem Requirements
LSST System Engineering is a successful collaboration of project and subsystem level support
The Joint Interface and Management Review was a great success in May
Current challenge is continuing the progress and balance individual subsystem efforts
Adding a System Engineer to Project team is high priority
Subsystem Interface Definition
6
Operation Simulator continues to investigate scheduling algorithms and system performance
Developing survey performance metrics has been a successful multi-year effort
NOAO has provided Abi Saha to be Op Sim Scientist
Technical group continues to enhance the code and simulate surveys
More than 18,000 square degrees with more than 825 visits on each patch of sky, Median visit counts by filter: u: 57, g: 80, r: 184, i: 184,
z: 160, y: 160
7
Image Simulator with photon level fidelity supporting science inquiry and DM
A simulated sky Observing an LSST simulation Producing a simulated image
Pointing, Filter, Airmass, Time and Atmosphere from Op Sim
Custom instance of field of view
1010 photons per CCD Separate amplifiers
Many breakouts this week:
– Parameter discussions with Engineering teams
– Status / using the tools
8
Data Management development continues with data challenges every 6 months
Summer 2012 half completed
– SDSS data Strip 82 reprocessed and available this week
– Simulated Image Sim data is next: • ~3000 LSST visits (Wide, Medium, Deep Survey)
• 1.1 million CCDs = 36 TB of images
Image Sim Data production nearly complete
– Computational time: 2.5 hours / CCD
– A recent addition is a Google award of 100 million CPU hours
9
DM architecture developments involve details of data release and alert production
Processing Center
Data Release Production at IN2P3
MOU in place – Technical
details pending
Establishing the details of moving the alert production from the Base to the Archive center
10
LSST Corporation invested non-federal funds for early site leveling in 2011
Initial summit leveling completed – ~4,000 kg of explosives
– 12,500 m3 removed on main site
First production blast: March 8th 2011
11
LSST Corporation invested non-federal funds for early site leveling in 2011
12
Mirror designs are advanced - Private funding enabled early start of both reflective optics
• Primary-Tertiary cast in 2008.
• Fabrication underway at the Steward Observatory Mirror Lab - completion in Fall 2013.
• Secondary substrate fabricated by Corning in 2009.
• Currently in storage waiting for construction.
13
Secondary mirror final design completed and ready for fabrication procurement this month
Mirror Back Surface
Tangent Links: 6 each at 60 deg intervals
Axial Actuators: 72 each distributed in 3 rings
Inner Loop Controllers (1 for each Actuator)
Mounting surface for Hexapod Assembly
14
LSST wavefront prototype pipeline being tested on WYIN One Degree Imager
15 2012
Telescope design is ready for procurement
later this year
16
Design is well advanced and many breakouts to address details of the
Filter
L1 Lens
Utility Trunk—houses support electronics and utilities
Cryostat—contains focal plane & its electronics
Focal plane
L2 Lens
L3 Lens
Camera ¾ Section
1.65 m (5’-5”)
17
LSST has been working with multiple vendors to develop sensor
Fully operable 4K x 4K devices delivered
– In house testing shows requirements are being met
– Flatness: < 5 µm P-V
– Good QE and noise as well
Request for proposals for production prototyping has been released
Device test dewar at Brookhaven
18
Camera risks being addressed – many with prototypes and brassboards
Cryostat w/ CCD & ASPIC II cold
CCD
Front End+ Back End + Raft Control Module
19
Camera risks being addressed – many with prototypes and brassboards
Filter Mechanism clamps
Mixed-refrigerant system (-130°C) prototype
Clamp Status Sensor Unlocking
Cable
Filter Pin
20
Planning for the 2-yr Commissioning is advancing incrementally
Commissioning starts in 2019 but planning is required to support Project Budget and Schedule development
– System Engineering is working with subsystems to define integration sequence and tests
– Tools will be available this week to engage Science collaborations on Science verification tests
Commissioning
21
EPO is planning products and tools to meet the public user where they are
User Interface Design: Sharing UML Domain Model with DM
Formal requirements and documentation
Building Sustainable Partnerships: Outreach Advisory Board, Potential Collaborators.
22
LSST is now “Preparing for Construction”
Highest Priority is Preparing for next Agency Reviews
– CD3a and FDR next year
– Update/upgrade PMCS
Prolonged D&D to “Time is money” construction
– Maintain excellent scientific ties
– Track progress toward plan
Staffing Additions
Business System Updates
– $10M/yr to $100M/yr organization
– “Routine”, “Robust”, and some case “enhance”
Continue Technical Progress and Risk reduction