Upload
others
View
1
Download
1
Embed Size (px)
Citation preview
Humboldt Bay Power PlantDecommissioning Progress Update
EPRI 2016 Conference
Presented by Kerry Rod, P. E.Decommissioning Manager
June 20, 2016
Pacific Gas and Electric Company
2Presentation Objectives Learn how PG&E has adapted to the challenges involved
in decommissioning a nuclear power plant and hear about some of the innovative solutions we've applied
Assess the major achievements that have been made during the decommissioning program at Humboldt Bay this past year including: License Termination Plan approved by the U.S. Nuclear
Regulatory Commission May 2016 PG&E Sibley Award received at HBPP for Safety May 2016 PG&E Final Site Restoration permit approved by the California
Coastal Commission April 2016
3
PG&E Site Overview
Close to the community Very small foot print Many projects at same time Adjacent to Humboldt Bay Remote Northern CA
4HBPP: A Unique Decommissioning
The reactor vessel is located inside the drywellbelow grade within the Refueling Building
5
And Close Proximity to the Bay
6First and Foremost Safety at HBPP
Continue making safety the #1 priority
Twice completed more than 1,000 Safe Work Days
Recipient of PG&E’s Sibley award for 2008, 2009, 2010, 2014 and 2015
7Understanding Our Safety Culture
PRINCIPALS Everyone is responsible Making the work place a safe place Preemptive in lieu of reactive Stop work authority
DEMONSTRATE Management briefing prior to badging Senior leadership walk downs Posters of our family throughout site Walk the talk
EXPERIENCE Continuity across successful projects Bring right resources at right time Planning the work is essential Supervision and Oversight
ASSESSMENT Benchmarking Management Observation Program Adverse Trending Continually Evaluate Risk
8
One Permanent Building Remaining
Tremendous progress being made in the field – and its all about the team
9Project Planning Process
10Discharge Canal Remediation
11Turbine Building Substructure Removal
2012 - 2013 2015 - 2016
12East Yard Pre-Trench Concrete Removal
Timely execution to allow continual CSM wall installation at the east end
of the Refueling Building
13Liquid Radwaste Building Demolition
Performed high risk high contamination demo early in lieu of at end of project RP monitoring established baseline to allow open air demo of RFB and caisson LRW demo demonstrated that the theoretical open air demo procedure was
very conservative Limits were raised based on the effectiveness of water sprays Based on the empirical data, eliminated over 21 locations in the RFB that were
designated to be shaved or scabbled before open air demo
14
The Last Active Operating Systems
Stack Monitoring and
Building Ventilation
15Refuel Building Prep and Demolition
West and North Scaffolding
West and North ready for Asbestos Contaminated Material (ACM) Removal
Commence RFB Demo
RFB 75T Bridge Crane
Demo Stack Base
16Completed CSM Wall Installation 255 Panels
DEEPEST APPLICATION OF CSM DRILLING EVER PERFORMED IN THE
WORLD USING KELLY BAR EQUIPPED MACHINERY
17
Cutter Soil Mix Operations
Starting the First Panel
18Key Caisson Removal Mitigation Tasks Execute Strong Contract Management Transition to Civil Works Project Implement Stringent OversightOptimize Health and Safety Performance Job Specific Activity Hazards AnalysisObtain Relevant Subject Matter ExpertiseOptimize Excavation StabilityDesign Verification Top Lander/Spotter Logistics Coordination Plan
19Truck and Rail Shipping Campaigns
SWEETS – Solid Waste Efficiency and Expediency Test Shipments
To evaluate alternate means and methods to further reduce the risk of
a traffic accident or incident associated with the preparation,
loading, and transportation of solid waste from HBPP
20HBPP Insights and Key Strategies Always work toward earn value Be flexible - things change ∙ opportunities arise Having the right resources and bandwidth Understand work control and oversight Do not underestimate site infrastructure needs Well vet your decommissioning cost estimates Establish a good regulatory and community relationships Mock-ups do work and are a prudent investment Deliver on promise, communications and alliance
21Person-Rem for Various U.S. Plants
0
100
200
300
400
500
600
700
800
900
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
Haddem Neck
Main Yankee
Big Rock Point
Trojan
San Onofre I
Rancho Seco
HBPP
PG&E anticipates that the total decommissioning exposure will be less than 80 Person-Rem, setting a very high standard for future decommissioning total exposures
REACTOR SHELL SEGMENT
THANK YOU
SAFETY FIRST