22
Humboldt Bay Power Plant Decommissioning Progress Update EPRI 2016 Conference Presented by Kerry Rod, P. E. Decommissioning Manager June 20, 2016 Pacific Gas and Electric Company

Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

  • Upload
    others

  • View
    1

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

Humboldt Bay Power PlantDecommissioning Progress Update

EPRI 2016 Conference

Presented by Kerry Rod, P. E.Decommissioning Manager

June 20, 2016

Pacific Gas and Electric Company

Page 2: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

2Presentation Objectives Learn how PG&E has adapted to the challenges involved

in decommissioning a nuclear power plant and hear about some of the innovative solutions we've applied

Assess the major achievements that have been made during the decommissioning program at Humboldt Bay this past year including: License Termination Plan approved by the U.S. Nuclear

Regulatory Commission May 2016 PG&E Sibley Award received at HBPP for Safety May 2016 PG&E Final Site Restoration permit approved by the California

Coastal Commission April 2016

Page 3: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

3

PG&E Site Overview

Close to the community Very small foot print Many projects at same time Adjacent to Humboldt Bay Remote Northern CA

Page 4: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

4HBPP: A Unique Decommissioning

The reactor vessel is located inside the drywellbelow grade within the Refueling Building

Page 5: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

5

And Close Proximity to the Bay

Page 6: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

6First and Foremost Safety at HBPP

Continue making safety the #1 priority

Twice completed more than 1,000 Safe Work Days

Recipient of PG&E’s Sibley award for 2008, 2009, 2010, 2014 and 2015

Page 7: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

7Understanding Our Safety Culture

PRINCIPALS Everyone is responsible Making the work place a safe place Preemptive in lieu of reactive Stop work authority

DEMONSTRATE Management briefing prior to badging Senior leadership walk downs Posters of our family throughout site Walk the talk

EXPERIENCE Continuity across successful projects Bring right resources at right time Planning the work is essential Supervision and Oversight

ASSESSMENT Benchmarking Management Observation Program Adverse Trending Continually Evaluate Risk

Page 8: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

8

One Permanent Building Remaining

Tremendous progress being made in the field – and its all about the team

Page 9: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

9Project Planning Process

Page 10: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

10Discharge Canal Remediation

Page 11: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

11Turbine Building Substructure Removal

2012 - 2013 2015 - 2016

Page 12: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

12East Yard Pre-Trench Concrete Removal

Timely execution to allow continual CSM wall installation at the east end

of the Refueling Building

Page 13: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

13Liquid Radwaste Building Demolition

Performed high risk high contamination demo early in lieu of at end of project RP monitoring established baseline to allow open air demo of RFB and caisson LRW demo demonstrated that the theoretical open air demo procedure was

very conservative Limits were raised based on the effectiveness of water sprays Based on the empirical data, eliminated over 21 locations in the RFB that were

designated to be shaved or scabbled before open air demo

Page 14: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

14

The Last Active Operating Systems

Stack Monitoring and

Building Ventilation

Page 15: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

15Refuel Building Prep and Demolition

West and North Scaffolding

West and North ready for Asbestos Contaminated Material (ACM) Removal

Commence RFB Demo

RFB 75T Bridge Crane

Demo Stack Base

Page 16: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

16Completed CSM Wall Installation 255 Panels

DEEPEST APPLICATION OF CSM DRILLING EVER PERFORMED IN THE

WORLD USING KELLY BAR EQUIPPED MACHINERY

Page 17: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

17

Cutter Soil Mix Operations

Starting the First Panel

Page 18: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

18Key Caisson Removal Mitigation Tasks Execute Strong Contract Management Transition to Civil Works Project Implement Stringent OversightOptimize Health and Safety Performance Job Specific Activity Hazards AnalysisObtain Relevant Subject Matter ExpertiseOptimize Excavation StabilityDesign Verification Top Lander/Spotter Logistics Coordination Plan

Page 19: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

19Truck and Rail Shipping Campaigns

SWEETS – Solid Waste Efficiency and Expediency Test Shipments

To evaluate alternate means and methods to further reduce the risk of

a traffic accident or incident associated with the preparation,

loading, and transportation of solid waste from HBPP

Page 20: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

20HBPP Insights and Key Strategies Always work toward earn value Be flexible - things change ∙ opportunities arise Having the right resources and bandwidth Understand work control and oversight Do not underestimate site infrastructure needs Well vet your decommissioning cost estimates Establish a good regulatory and community relationships Mock-ups do work and are a prudent investment Deliver on promise, communications and alliance

Page 21: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

21Person-Rem for Various U.S. Plants

0

100

200

300

400

500

600

700

800

900

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

Haddem Neck

Main Yankee

Big Rock Point

Trojan

San Onofre I

Rancho Seco

HBPP

PG&E anticipates that the total decommissioning exposure will be less than 80 Person-Rem, setting a very high standard for future decommissioning total exposures

REACTOR SHELL SEGMENT

Page 22: Progress in Decommissioning the Humboldt Bay Power Plant · 2016-06-17 · Humboldt Bay Power Plant Decommissioning Progress Update. EPRI 2016 Conference. Presented by Kerry Rod,

THANK YOU

SAFETY FIRST