104
Program Operations Manual A supplemental document to the Stewardship and Oversight Agreement between FHWA and MDOT. LAST UPDATE: November 2020

Program Operations Manual - Michigan

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Program Operations Manual - Michigan

 

 

Program Operations Manual 

A supplemental document to the 

Stewardship and Oversight Agreement 

between FHWA and MDOT. 

LAST UPDATE: November 2020 

Page 2: Program Operations Manual - Michigan

Table of Contents  

Overview of the Program Operations Manual .......................................................................................... 1 

AIR QUALITY .............................................................................................................................................. 2 

ASSET MANAGEMENT ............................................................................................................................... 9 

BRIDGES AND STRUCTURES .................................................................................................................... 14 

CIVIL RIGHTS ............................................................................................................................................ 19 

CONSTRUCTION AND CONTRACT ADMINISTRATION ............................................................................. 26 

DESIGN .................................................................................................................................................... 30 

EMERGENCY RELIEF PROGRAM .............................................................................................................. 35 

ENVIRONMENT ....................................................................................................................................... 39 

FINANCIAL MANAGEMENT ..................................................................................................................... 48 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS) ..................................................................................... 56 

LOCAL PUBLIC AGENCIES (LPA) ............................................................................................................... 62 

MAINTENANCE AND PRESERVATION ...................................................................................................... 65 

OPERATIONS ........................................................................................................................................... 68 

PAVEMENT AND MATERIALS .................................................................................................................. 70 

PLANNING ............................................................................................................................................... 74 

REAL ESTATE ............................................................................................................................................ 78 

RESEARCH, DEVELOPMENT AND TECHNOLOGY TRANSFER ................................................................... 84 

SAFETY ..................................................................................................................................................... 87 

SPECIFICATIONS ...................................................................................................................................... 90 

UTILITY COORDINATION ......................................................................................................................... 93 

VENDOR PROCUREMENT ........................................................................................................................ 96 

APPENDIX A: Acronyms ......................................................................................................................... 100 

 

 

   

Page 3: Program Operations Manual - Michigan

  1 

Overview of the Program Operations Manual 

 

The Federal Highway Administration‐MI Division (FHWA) and Michigan Department of Transportation (MDOT) have long worked as partners in delivering the Federal‐aid highway program (FAHP) in Michigan in accordance with Federal requirements. The primary document guiding that delivery is the STEWARD‐SHIP AND OVERSIGHT AGREEMENT ON PROJECT ASSUMPTION AND PROGRAM OVERSIGHT BY AND BE‐TWEEN FEDERAL HIGHWAY ADMINISTRATION, MICHIGAN DIVISION AND THE STATE OF MICHIGAN DE‐PARTMENT OF TRANSPORTATION (SOA). The SOA clearly defines which FAHP project actions are dele‐gated to MDOT and which are retained by FHWA. It also includes tables of program responsibilities, ap‐proved manuals and guidance documents, and performance indicators. The Program Operations Manual (POM) supplements the SOA by providing more detailed discussion and guidance on the delivery of indi‐vidual programs. This information is provided for all major program areas to help ensure that the FAHP is delivered in a manner consistent with laws, regulations, policies and good business practices.  

Those using this manual should be familiar with the SOA and its relationship to the POM. In the event of a discrepancy, the SOA takes precedence over the POM. 

 

 

   

Page 4: Program Operations Manual - Michigan

  2 

AIR QUALITY  

Overview 

The Air Quality program is composed of two parts, transportation conformity and the Congestion Miti‐gation and Air Quality Improvement program (CMAQ). Transportation conformity ensures that Federal funding and approval are only given to highway and transit activities that are consistent with Michigan’s air quality goals and that transportation activities will not affect Michigan’s ability to achieve the na‐tional air quality standards. 

Transportation conformity only applies in areas designated nonattainment or maintenance for a trans‐portation‐related pollutant: ozone, particulate matter (particulate sizes 2.5 and 10), nitrogen dioxide, and carbon monoxide and for on‐road sources. Transportation activities that are subject to conformity are regional long‐range transportation plans (LRTPs), Transportation Improvement Programs (TIPs), and non‐exempt projects that receive Federal Highway Administration (FHWA) or Federal Transit Admin‐istration (FTA) funding or approval. 

One means to improve air quality is through the implementation of the Congestion Mitigation and Air Quality Improvement Program. The CMAQ program provides a flexible funding source to state and local governments for transportation projects and programs to help meet the requirements of the Clean Air Act (42 U.S.C. Paragraph 7506 Section 176(c)). Projects or programs funded by CMAQ must show a quantitative reduction in emissions. Projects must be located within or show benefit within a nonattain‐ment, maintenance area, or former nonattainment/maintenance area. 

Background/History 

Transportation Conformity: 

The Clean Air Act (CAA) was established to improve air quality, protect public health, and to protect the environment. The CAA has been amended over the years, most significantly in the 1990s. The Clean Air Act as Amended (CAAA) requires the U.S. Environmental Protection Agency (EPA) to set, review, and pe‐riodically revise the National Ambient Air Quality Standards (NAAQS). There are six NAAQS pollutants: 

Ozone (O3)  Nitrogen dioxide (NO2)  Carbon monoxide (CO)  Lead (Pb)  Sulfur dioxide (SO2)  Particulate matter (PM), is subdivided into particulate sizes: 

o Less than 10 micrometers in diameter (PM10) o Less than 2.5 micrometers in diameter (PM2.5) 

Generators of air pollution are classified into four main types:  stationary sources (industrial, refineries, and electric utilities), area sources (dry cleaners, paints, and solvents), non‐road mobile sources (boats, aircraft, trains, and construction equipment), and on‐road mobile sources (commuter rail and vehicles expected to be on roadways such as cars, trucks, and buses). 

The CAA links together air quality planning and transportation planning through the transportation con‐formity process. Air quality planning is controlled by Michigan’s State Implementation Plan (SIP) which includes the state’s plans for attaining or maintaining the NAAQS. The primary transportation planning tools are the metropolitan Long‐Range Transportation Plan (LRTP) and Statewide and metropolitan 

Page 5: Program Operations Manual - Michigan

  3 

Transportation Improvement Program (STIP/TIP). Transportation conformity ensures that Federal fund‐ing and approval are given to highway and transit activities that are consistent with the SIP and that these activities will not affect Michigan’s ability to achieve the NAAQS.  

 

Transportation activities that are subject to conformity are LRTPs, TIPs, and all non‐exempt federal pro‐jects that receive Federal Highway or Federal Transit Administration funding or approval. The conformity process ensures emissions from implementing the LRTP, TIP, and STIP projects are within acceptable lev‐els specified within the SIP and meet the goals of the SIP. Transportation conformity only applies to emissions from on‐road sources for the following transportation related pollutants: 

Ozone  particulate matter (particulate sizes 2.5 and 10)  nitrogen dioxide  carbon monoxide 

The SIP is a collection of documents developed by air quality partners documenting procedures to moni‐tor, control, maintain, and enforce compliance with NAAQS. According to the CAAA, transportation con‐formity ensures transportation plans, programs, and Federal projects must conform to the purpose of the SIP and will not: 

create new violations of the NAAQS,  increase the frequency or severity of existing violations of the NAAQS, and  delay attainment of the NAAQS. 

The EPA reviews the NAAQS every five years to determine if a new standard is needed. The Michigan Department of Environment, Great Lakes, and Energy (EGLE) uses monitors throughout the state to measure pollutant levels to determine if concentrations exceed the NAAQS. Through a joint process with EPA and EGLE an area is classified as either:  

attainment (under the standard)  nonattainment (area has more pollutant then allowed)  unclassifiable/attainment (insufficient information to support an attainment or nonattain‐

ment classification; conformity requirements are the same as for an attainment area)  

A nonattainment area is given a set amount of time to attain the NAAQS, depending on the level it ex‐ceeded the NAAQS. Once a nonattainment area has attained the standard for three years, the area is re‐designated to attainment and starts a maintenance period of 20 years, these areas are referred to as maintenance areas. Transportation conformity is required for areas designated nonattainment or maintenance.  

Transportation conformity requires Metropolitan Planning Organizations (MPOs) to make a determina‐tion that the LRTP, TIP, and projects conform to the SIP based on the findings of a regional emissions analysis. The determination affirms the regional emissions will not negatively impact the region’s ability 

Air Quality Planning 

(State Implementation Plan)

Transportation Conformity

Transportation Planning

(Long Range Transportation 

Plans and Transportation 

Improvement Program)

Page 6: Program Operations Manual - Michigan

  4 

to meet the NAAQS. Conformity has a two‐step approval process. First, the MPOs must make a formal conformity determination through a resolution that the findings of a conformity analysis conform to the SIP; thus, emissions are at or below the budgets found in the SIP. Then FHWA, jointly with the FTA, after consultation with the EPA, issues a letter of concurrence with the determination.  

Michigan areas currently designated as nonattainment or maintenance are shown in the table below. 

Transportation NAAQS Designations in Michigan (as of August 2020) Pollutant  Designation  Area(s) 2015 Ozone Standard (0.070 ppm) 

Nonattainment  Detroit (7 counties of SEMCOG: Livingston, Macomb, Monroe, Oakland, Saint Clair, Washtenaw and Wayne), single county of Berrien, and partial counties of Allegan and Muskegon 

2008 Ozone Standard (0075 ppm) 

Unclassifiable/ Attainment 

Entire state 

1997 Ozone Standard (0.080 ppm) 

n.a. (see details of South Coast II court decision) 

Orphan maintenance areas (waiting for second maintenance plans): Allegan, Berrien, Cass, Muskegon, Detroit–Ann Arbor (8 counties: Liv‐ingston, Macomb, Monroe, Oakland, Saint Clair, Washtenaw, Wayne and Lenawee) 

Limited orphan maintenance areas (second maintenance plans): Ben‐zie, Flint Area (Genesee and Lapeer), Grand Rapids Area (Ottawa and Kent), Huron, Kalamazoo– Battle Creek Area (Van Buren, Kalamazoo, Calhoun), Lansing–East Lansing (Clinton, Eaton, Ingham), Mason 

2012 Particulate Mat‐ter (PM2.5) 

Unclassifiable/ Attainment 

Entire State 

2006 Particulate Mat‐ter (PM2.5) 

Maintenance  Detroit–Ann Arbor (7 counties of SEMCOG: Livingston, Ma‐comb, Monroe, Oakland, St Clair, Washtenaw and Wayne) 

2010 Nitrogen Dioxide 

Unclassifiable/ Attainment 

Entire Country 

1979 Carbon Monoxide 

Attainment  Maintenance period ended July 2019, Detroit: parts of Ma‐comb, Oakland and Wayne Counties. 

Source:  www.epa.gov/green‐book and www.epa.gov/green‐book/designation‐and‐naaqs‐information‐related‐nitrogen‐dioxide‐1971‐standard 

 

Congestion Mitigation and Air Quality Improvement Program: 

The Congestion Mitigation and Air Quality Improvement program (CMAQ) was created in 1991 to specif‐ically fund transportation projects and programs that will contribute to attainment or maintenance of the NAAQS for ozone, carbon monoxide, and particulate matter. The CMAQ program provides funding for a broad array of tools to accomplish two important goals of the USDOT: improving air quality and re‐lieving congestion. By choosing to fund or sponsor a CMAQ project a State or local government, transit agency, or other eligible project sponsor can improve air quality and make progress toward achieving attainment status and ensuring compliance with the transportation conformity provisions of the CAA. 

MDOT’s CMAQ strategy aligns with the overall purpose of the program by allocating CMAQ funds to eli‐gible counties based on nonattainment/maintenance designations and county populations. Local CMAQ project applicants are required to work with Metropolitan Planning Organizations (MPOs) or Regional Planning Agencies (RPAs) in selecting projects that are the most cost effective in reducing congestion and transportation related emissions. The Moving Ahead for Progress in the 21st Century Act (MAP‐21), and most recently, the Fixing America’s Surface Transportation Act (FAST Act), directs MDOT to use a portion of its CMAQ funds for projects that reduce particulate matter (PM 2.5) in areas designated as nonattainment and maintenance for PM 2.5. 

Page 7: Program Operations Manual - Michigan

  5 

The CMAQ program has three Transportation Performance Management (TPM) performance measures. The requirements of these performance measures include creating two‐year and four‐year performance targets, MPO performance plans, as well as bi‐annual performance reporting. The three CMAQ‐related TPM performance measure are: 

Traffic Congestion 1. PHED Measure:  Annual Hours of Peak Hour Excessive Delay (PHED) Per Capita  2. Percent of Non‐SOV Travel Measure: Percent of Non‐Single Occupancy Vehicle (SOV) 

Travel  On‐Road Mobile Source Emissions 

3. Total Emissions Reduction Measure:  2‐ and 4‐year Total Emission Reductions for each applicable criteria pollutant and precursor for all projects funded with CMAQ funds 

MDOT has the primary program management responsibilities, including day to day operations, working with applicants on questions related to the CMAQ Improvement Program, organizing the Local CMAQ Call for Projects (CFP), as well as the CMAQ CFP Committee (Local CFP) and CMAQ Eligibility Team (Trunkline CFP). The CMAQ CFP Committee and CMAQ Eligibility Team, of which FHWA Michigan Divi‐sion is a member, are responsible for reviewing and determining eligibility of proposed CMAQ projects and all associated duties. 

The CMAQ eligibility determinations follow the process and timeline of the STIP schedule for the Local CMAQ Call for Projects, as well as the annual Trunkline CFP via Transportation Systems Management and Operations (TSMO) templates. The CMAQ CFP Committee and CMAQ Eligibility Team meets to re‐view and discuss proposed CMAQ funded projects and emissions calculations. FHWA Michigan Division staff typically attends the CMAQ Committee when a new type of project is being proposed or per MDOT’s request. FHWA Michigan Division provides risk‐based stewardship and oversight, is available to answer questions, help convey national initiatives or areas of emphasis, and help MDOT ensure the pro‐gram operates efficiently. When needed, FHWA Michigan Division will contact FHWA Headquarters with eligibility or program questions or FTA with transit eligibility questions. 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Transportation Conformity 

Topic  Law Implementing Regulations 

Clean Air Act as Amended  42 USC 7401‐7671  40 CFR 93 Subpart A 

Implementation Plans  42 USC 7401‐7671  40 CFR 51 

Determining conformity of Federal actions to SIP and FIP  42 USC 7401‐7671  40 CFR 93 Subpart A 

Statewide and Metropolitan Transportation Planning, public consultation  

23 USC 134 and 135 

23 CFR 450 

Public Transportation  49 USC 53  49 CFR 613 

Michigan 2016 Memorandum of Agreement for Trans‐portation Conformity SIP  

82 FR 17134 (April 10, 2017) 

n.a. 

Michigan’s Natural Resource and Protection Act  1994 PA 451, MCL 324.5501 

n.a. 

US Court of Appeals for the District of Columbia Circuit in South Coast Air Quality Mgmt. District v. EPA  

n.a.  South Coast II,  882 F.3d 1138 

Page 8: Program Operations Manual - Michigan

  6 

 

Congestion Mitigation and Air Quality Improvement Program: 

Topic  Law Implementing Regulations 

CMAQ Apportionment  23 USC 104  n.a. 

CMAQ Improvement Program  23 USC 149  n.a. 

Federal Share Payable  23 USC 120  n.a. 

Statewide and Metropolitan Planning Process  23 USC 134 & 135  23 CFR 450 

National Goals & Performance Management Measures  23 USC 150  23 CFR 490 

National Performance Management Measures  23 USC 134(h)(2) & 23 USC 135(d)(2) 

23 CFR 490 

Designation of Areas for Air Quality Planning Purposes  42 USC 7401‐7671  40 CFR 81 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Transportation Conformity  Congestion Mitigation and Air Quality Improvement Program  

Approved Procedures, Agreements, and Manuals  

Transportation Conformity 

Procedure, Agreement, Manuals Latest Approval Date/Version 

Anticipated due date  

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

Transportation Conformity Guidance for the South Coast II Court Decision (EPA‐420‐B‐18‐050) 

November 2018  As needed 

Guidance for Implementation of Conformity in 1997 ozone Limited Orphan Maintenance Areas and Orphan Maintenance Areas in Michigan  

May 1, 2020   As needed 

Guidance for Transportation Conformity Implementation in Multi‐jurisdictional Nonattainment and Maintenance Areas (EPA‐420‐B‐12‐046) 

July 2012  As needed 

 

Congestion Mitigation and Air Quality Improvement Program 

Procedure, Agreement, Manuals Latest Approval Date/Version 

Anticipated due date 

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

MDOT CMAQ Improvement Program Guidance  April 1, 2020  As needed 

MDOT Non‐Transit Diesel Retrofit Process  May 1, 2017  As needed 

FHWA CMAQ Interim Program Guidance Under MAP‐21  Nov. 12, 2013  As needed 

FHWA CMAQ Emissions Calculator Toolkit Guidance  Date varies by module  As needed 

Page 9: Program Operations Manual - Michigan

  7 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

 

Transportation Conformity 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action Business Standard 

Remarks 

LRTP Conformity for nonattain‐ment or maintenance areas with TMAs  

23 CFR 450.324(d) and 40 CFR 93 Subpart A 

Concurrent with LRTP updates at least every 4 years or as needed for amendments  

FHWA  Review  Review and make fi‐nal conformity de‐termination w/ FTA 

Up to 30 days for EPA review 

 

LRTP Conformity for nonattain‐ment or maintenance areas with MPOs  

23 CFR 450.324(d) and 40 CFR 93 Sub‐part A 

Concurrent with LRTP updates at least every 4 years or as needed for amendments  

FHWA  Develop   Review and make fi‐nal conformity de‐termination w/ FTA  

Up to 30 days for EPA review 

 

New TIP Conformity for nonat‐tainment or maintenance areas with TMAs  

23 CFR 450.326 and 40 CFR 93 Subpart A 

When new TIPS de‐veloped 

FHWA  Review  Review and make fi‐nal conformity de‐termination w/ FTA  

Up to 30 days for EPA review  

 

New TIP Conformity for nonat‐tainment or maintenance areas with MPOs  

23 CFR 450.326 and 40 CFR 93 Subpart A 

When new TIPS de‐veloped  

FHWA  Develop   Review and make fi‐nal conformity de‐termination w/ FTA  

Up to 30 days for EPA review 

 

S/TIP Amendments in nonattain‐ment or maintenance areas with MPOs, rural areas, TMAs  

23 CFR 450.328 and 40 CFR 93 Subpart A 

As needed  MDOT/ FHWA 

Participate in in‐teragency workgroup. De‐velop conform‐ity if needed in non‐TMA area.  

Participate in inter‐agency workgroup. If new conformity needed make final conformity determi‐nation w/ FTA 

Up to 30 days for EPA review 

 

  

Page 10: Program Operations Manual - Michigan

  8 

Congestion Mitigation and Air Quality Improvement Program:     

Activity  Reference Schedule/Fre‐quency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Manage the CMAQ Lo‐cal Call for Projects 

23 USC 149; 23 USC 134 & 135 

Every three years (aligned with STIP schedule) 

MDOT  Distribute CMAQ Local Call for Pro‐jects Letter and Al‐location Table to MPOs and Local Agencies 

FHWA Division staff available for reviewing unique projects and tech‐nical assistance 

No applicable  CMAQ Program Manager works with MPOs and Local Agencies to provide all infor‐mation needed in eligibility review 

CMAQ Annual Report  23 USC 149 (i) and CMAQ In‐terim Program Guidance (Nov 12, 2013) 

Annually  MDOT  Entire required in‐formation in FHWA UPACS system 

Review project data and approve report 

MDOT com‐pletes project info by Feb 1st; FHWA Divi‐sion approves by March 1st 

Submitted via CMAQ reporting application in FHWA UPACS system. 

CMAQ performance measures 

23 CFR 490  Progress report every 2 years 

MDOT and MPOs 

Develop statewide targets; work with applicable MPOs on CMAQ perfor‐mance report 

Review perfor‐mance measure submittal  

Progress re‐port due Oct 1 of even years 

 

  

Page 11: Program Operations Manual - Michigan

  9 

ASSET MANAGEMENT 

Overview 

Asset management is a strategic and systematic process of operating, maintaining, and improving physi‐cal assets, with a focus on engineering and economic analysis based upon quality information, to iden‐tify a structured sequence of maintenance, preservation, repair, rehabilitation, and replacement actions that will achieve and sustain a desired state of good repair over the lifecycle of the assets at minimum practicable cost.  

Background/History 

FHWA established minimum standards for MDOT to use in developing and operating Bridge and pave‐ment management systems (PMS). PMS should follow the AASHTO Guidelines for Pavement Manage‐ment Systems. 

The asset management plan or Transportation Asset Management Plan (TAMP) must address pave‐ments and bridges on the National Highway System (NHS), but may at the SHA discretion also include all infrastructure assets within the NHS right‐of‐way in their risk‐based asset management plan. The plan includes processes and strategies that lead to a program of projects that would make progress toward achievement of the State targets for asset condition and performance of the NHS. At a minimum the TAMP must include the following processes and sub‐elements: 

Process to complete a performance gap analysis and to identify strategies to close gaps 

A State DOT must establish a process for conducting a performance gap analysis that, at a mini‐

mum, will identify alternative strategies to close the gaps between the current asset condition 

and (1) State DOT 23 U.S.C. 150(d) targets for asset condition for the NHS, and (2) the gaps in 

the performance of the NHS that affect NHS pavements and bridges (23 CFR 515.7(a)). 

Process to complete life cycle planning 

A State DOT must establish a process to estimate the cost of managing an asset class at the net‐

work level (network to be defined by the State DOT) over its whole life with consideration for 

minimizing cost while preserving or improving the asset condition (23 CFR 515.7(b)). 

Process to complete a risk analysis and develop a risk management plan 

A State DOT must establish a process for developing a risk management plan (23 CFR 515.7(c)). 

This process must identify risks that can affect the NHS condition and performance, including 

risks associated with current and future environmental conditions, such as extreme weather 

events, climate change, seismic activity, and a summary of the evaluations of facilities repeat‐

edly damaged by emergency events, as defined in 23 CFR Part 667. The summary must discuss, 

at a minimum, the results relating to the existing pavements and bridges on the NHS in the 

State, and (if available) results for any other pavement or bridge included in the TAMP at the 

option of the State DOT. In addition, this process should include, at a minimum, an explanation 

of how risks are assessed, evaluated, and prioritized. The top priority risks must be identified 

along with a mitigation plan and monitoring approach. 

Process to develop a financial plan covering at least a 10‐year period 

Page 12: Program Operations Manual - Michigan

  10 

A State DOT must establish a process for the development of a financial plan (23 CFR 515.7(d)). 

A financial plan within the context of asset management means a plan spanning 10 years or 

longer that presents a State DOT’s estimates of projected available financial resources and pre‐

dicted expenditures in major asset categories; can be used to achieve State DOT targets for as‐

set condition during the plan period; and highlights how resources are expected to be allocated 

based on asset strategies, needs, shortfalls, and agency policies (23 CFR 515.5). 

Process to develop investment strategies 

A State DOT must establish a process for developing investment strategies meeting the require‐

ments in 23 CFR 515.9(f) (23 CFR 515.7(e)‐(f)). State DOT decisions about TAMP investment 

strategies will involve trade‐offs amongst TAMP assets based on the results of the required 

TAMP analyses (such as performance gap, life cycle plan, and risk management analyses) (23 

CFR 515.7(e) and 515.9(g)). A State DOT must clearly demonstrate how its selected investment 

strategies were influenced by the analyses done using TAMP processes. Any adjustment to the 

selected strategies, or rebalancing funds amongst strategies, is an amendment to the TAMP that 

is subject to the same requirement (23 CFR 515.13(c)). 

Process for obtaining necessary data from NHS owners other than the State DOT 

The processes established by State DOTs shall include a provision for the State DOT to obtain 

necessary data from other NHS owners in a collaborative and coordinated effort (23 CFR 

515.7(f)). State DOTs must use the best available data to develop their TAMPs (23 CFR 515.7(g)). 

Process for ensuring the TAMP is developed with the best available data and that the State DOT uses bridge and pavement management systems meeting the requirements in 23 CFR 515.17 to analyze NHS bridge and pavement conditions 

State DOTs must use the best available data to develop their TAMPs and must analyze the con‐

dition of NHS pavements and bridges for developing the TAMP by using bridge and pavement 

management systems that meet the requirements in 23 CFR 515.17. 

In 1997, the Michigan State Transportation Commission (STC) approved 10‐year aspirational condi‐tion goals for Michigan’s freeway (95 percent good/fair) and non‐freeway (85 percent good/fair) state trunkline systems, based on pavement health. A year later, the STC approved similar goals for Michigan freeway and non‐freeway bridges. Figure 3 from the TAMP displays these goals.  

 

In addition, Figure 46 from the TAMP displays MDOT’s state of good repair (SOGR) pavement goals, us‐ing a blend of adopted targets and rating systems for meeting the adopted national and state goals. 

Page 13: Program Operations Manual - Michigan

  11 

 

 

 

 

 

 

 

 

 

 

 

MDOT’s TAMP was certified by FHWA in 2019 and received consistency status in 2020. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law Implementing Regulations 

Performance Measures  23 USC 150  23 CFR 490 

Transportation Asset Management Plans (TAMP)  23 USC 119  23 CFR 515 

HPMS  23 USC 315  23 CFR 1.5 23 CFR 420.105(b) 23 CFR 490 23 CFR 500 

Michigan’s Transportation Asset Management Council (TAMC) 

Michigan P.A. 499 of 2002 (original enabling legislation; modifications since then) 

not applicable 

Key Program Areas 

These are the key program areas within the program or related to the program.  

TAMP   HPMS  MDOT Pavement and Bridge Condition  Pavement Data Collection  Transportation Asset Steering Committee (TASC)  TAMC administration 

Page 14: Program Operations Manual - Michigan

  12 

Approved Procedures, Agreements, and Manuals  

Procedure, Agreement, Manuals Latest Approval Date/ Version (if applicable) 

Anticipated due date (if applicable)  

HPMS Field Review Guidelines;  Continuous Process Improvement Model for HPMS 

June 2001; February 2003 

n.a. 

TAMP  August 2019  April 2022 

Performance Measures – states reporting in UPACS  October 2020  October 2022 

 

]

Page 15: Program Operations Manual - Michigan

  13 

Project and Program Monitoring and Approval Chart 

 

Activity  Reference  Schedule/Frequency Responsible Agency 

MDOT Action  FHWA Action  Business Standard 

TAMP  23 CFR 515  Updated every 4 years; consistency demonstra‐tion annually 

MDOT  Document how invest‐ments have been con‐sistent with current TAMP. Update TAMP every 4 years. 

Review and concur with consistency demonstra‐tion. Review and concur with TAMP update.  

FHWA notifies MDOT of ad‐equacy of their consistency determination by July 31 each year. 

HPMS  23 CFR 1.5 23 CFR 490 23 CFR 500 

April 15 for NHS; June 15 for non‐NHS facilities 

MDOT  Submit data.   Submitted to FHWA HQ; Division provides support in MDOT development. 

April 15 – MDOT submits Interstate pavement data; June 15 full data is due 

Performance Measures 

23 CFR 490  Submit in UPACS every two years. 

MDOT  Set targets and report on progress. Coordi‐nate target setting with MPOs.  

Review and concur with development of targets and progress. 

State DOTs submit data in UPACS every 2 years.  

 

Page 16: Program Operations Manual - Michigan

  14 

BRIDGES AND STRUCTURES  

 Overview 

Key program operations activities serve to ensure structures are designed, constructed, inspected, eval‐uated, and maintained in accordance with sound engineering practices with the goal of ensuring the continued life safety of the public. Some activities are required by state/federal statute, regulation or FHWA policy. Other beneficial activities, which are not necessitated by law or regulation, are encour‐aged subject to a risk‐based approach, and resource availability.  

 

Background/History 

MDOT: 

MDOT created the Bureau of Bridges and Structures, with specific focus on elevation the importance of 

the bridge functions. As part of this new Bureau, a vision, mission and values were developed as follows: 

Vision: 

“To be well‐regarded as spanning and connecting lives, safely and efficiently” 

Mission: 

The Bureau of Bridges and Structures is devoted to the efficient and innovative design, construc‐tion, and active preservation of transportation structural assets, inspired by safety, resiliency, and mobility. 

Values: 

Proficient – Possessing exceptional competence, knowledge, and expertise, thus creating in‐fluence, and credibility 

Supportive – Being responsive, reliable and dedicated to adding value, and creating trust with our customers and stakeholders 

Accountable – Providing clarity of expectations, and consistently holding ourselves and each other to high standards 

Agile – Integrating flexibility, and being nimble with appropriately holding to standard in the profiling of risk 

Considerate – Showing careful thought, understanding, and attentiveness, in stewardship of public safety and managing transportation structural assets 

FHWA: 

The FHWA Division Office provides oversight of the design, construction, maintenance and inspection of highway bridges in an effort to ensure public safety, enhance quality and improve efficiency and econ‐omy. The Division Bridge Engineer has overall responsibility to ensure actions taken by the state comply with federal regulation, policy and guidance, the Assistant Bridge Engineer supports the Division Bridge Engineers efforts. 

 

Page 17: Program Operations Manual - Michigan

  15 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law  Implementing Regulations 

Project approval and oversight  23 USC 106   

Standards  23 USC 109   

Surface Transportation Block Grant Program  23 USC 133   

National bridge and tunnel inventory and inspection standards  23 USC 144   

Bicycle transportation and pedestrian walkways  23 USC 217   

Highway improvements strategically important to national defense  23 USC 311   

Management and Monitoring systems    23 CFR 500 

Projects of National and Regional Significance Evaluation and Rating    23 CFR 505 

Asset Management Plans    23 CFR 515 

Engineering    23 CFR 620 

Design Standards for Highways    23 CFR 625 

Value Engineering    23 CFR 627 

Preconstruction Procedures    23 CFR 630 

Construction and Maintenance    23 CFR 635 

Construction Inspection and Approval    23 CFR 637 

Railroads    23 CFR 646 

Bridges, Structures, and Hydraulics    23 CFR 650 

Truck Size and Weight, Route Designations – Length, Width and Weight Limitations 

  23 CFR 658 

Indian Reservation Road Bridge Program    23 CFR 661 

Environmental Impact and Related Procedures    23 CFR 771 

General Highway Law  MCL Chapters 220 – 224   

Highways  MCL Chapters 247, 249, 250, 252 

 

Grade Crossings  MCL Chapter 253   

Bridges  MCL Chapter 254   

Unclassifiable/ Attainment Key Program Areas 

These are the key program areas within the program or related to the program.  

The National Bridge Inspection Program   The National Tunnel Inspection Program  The NHPP and STBG Program   Bridge and Structure Design/Construction/Evaluation/Management   Hydraulic Design  Geotechnical Design  Innovative Construction Practices 

 

Page 18: Program Operations Manual - Michigan

  16 

Approved Procedures, Agreements, and Manuals  

Procedure, Agreement, Manuals  Version/Edition  Update cycle 

FHWA/MDOT Stewardship and Oversight Agreement     

AASHTO Policy on Geometric Design of Highways and Streets  Seventh Edition   

AASHTO Policy on Design Standards – Interstate System     

AASHTO Standard Specifications for Highway Bridges  Seventeenth Edition   

AASHTO LRFD Bridge Design Specifications  Eighth Edition   

AASHTO LRFD Bridge Construction Specifications  Forth Edition   

AASHTO LRFD Movable Highway Bridge Design Specifications  Second Edition   

AASHTO Standard Specifications for Structural Supports for High‐way Signs, Luminaires, and Traffic Signals 

Sixth Edition   

AASHTO LRFD Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signs 

First Edition   

AASHTO Manual for Bridge Evaluation  Third Edition   

AWS D1.1 Structural Welding ‐ Steel     

AWS/AASHTO D1.5 Bridge Welding Code     

MDOT Bridge Design Manual     

MDOT Bridge Design Guides     

MDOT Bridge Analysis Guide     

MDOT Standard Plans     

MDOT Special Details    Varies 

MDOT Drainage Manual     

MDOT Soils Manual     

MDOT Structural Fabrication Quality Manual     

Michigan Structure Inspection Manual     

Michigan Bridge Element Inspection Manual     

Evaluating Scour at Bridges (HEC‐18)  Fifth Edition   

Stream Stability at Highway Structures (HEC‐20)  Fourth Edition   

Bridge Scour and Stream Instability Countermeasures (HEC‐23)  Third Edition   

Ground Anchors and Anchored Systems (GEC‐4)     

Shallow Foundations (GEC‐6)     

Design and Analysis of Laterally Load Deep Foundations (GEC 9)     

Drilled Shafts: Construction and Design Methods (GEC‐10)     

Design and Construction of Mechanically Stabilized Earth Walls and Reinforced Soil Slopes (GEC‐11) 

   

Design and Construction of Driven Pile Foundations (GEC‐12)     

FHWA Recording and Coding Guide for the Structure Inventory and Appraisal of the Nation’s Bridges 

  Varies 

FHWA Bridge Inspector’s Reference Manual    Varies 

Tunnel Operations, Maintenance, Inspection and Evaluation    Varies 

Specifications for the National Tunnel Inventory    Varies 

Applicable Guide Specifications as approved by the AASHTO Com‐mittee on Bridges and Structures 

   

Applicable technical briefs/Advisories/Technical Manuals issued by FHWA 

   

 

Page 19: Program Operations Manual - Michigan

  17 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action Business Standard 

Remarks 

Reduction of Expenditures for Off‐System Bridges 

23 USC 133    MDOT/ FHWA 

Evaluate/ Request 

Review/Provide Recommendation to FHWA Adminis‐trator 

  The FHWA Administrator may re‐duce the requirement for ex‐penditures for off‐system bridges if the FHWA Administrator deter‐mines that the State has inade‐quate needs to justify the ex‐penditure. 

Design Standards, Policies, and Procedures 

23 CFR 625  

Ongoing  MDOT/ FHWA 

Develop/ Maintain/ Update 

Review/Approve     

Preliminary Engineering Stud‐ies and Project Scopes 

23 CFR 625  

Ongoing  MDOT/ FHWA 

Develop  Review/Approve*  FHWA review within 14 cal‐endar days 

 

Structure design plans and specifications  

23 CFR 630  Ongoing  MDOT/ FHWA 

Develop  Review/Approve*  FHWA review within 14 cal‐endar days 

 

Structure quality control and assurance procedures (Design, Construction and Inspection) 

23 CFR 625 23 CFR 635 23 CFR 637 23 CFR 650 

Ongoing  MDOT  Develop/ Maintain/ Update 

Review    FHWA to ensure QC/QA program is thorough, effective, docu‐mented and followed. 

Type, Size and Location Study (Structure Studies) 

23 CFR 625 23 CFR 650 

Ongoing  MDOT/ FHWA 

Develop  Review/Approve*  FHWA review within 14 cal‐endar days 

 

Page 20: Program Operations Manual - Michigan

  18 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action Business Standard 

Remarks 

Critical findings for all trunkline and local agency bridges/tunnels 

23 CFR 650  Ongoing  MDOT/ FHWA 

Identify/ Address/ Notify  

Review and Rec‐ord in the Na‐tional Critical Finding Database 

Notify FHWA Within 24 hours of iden‐tification 

 

Critical findings for all trunkline and local agency bridges/tunnels 

23 CFR 650  Quarterly  MDOT/ FHWA 

Report In‐termedi‐ate/Final Actions 

Review and Up‐date National Crit‐ical Finding Data‐base 

Report to FHWA by the 15th of Janu‐ary, April, July, October 

 

Requests for Action  23 CFR 650  Ongoing  MDOT  Develop/ Monitor/ Address 

Review     

NBI/NTI Program  23 CFR 650  Ongoing  MDOT/ FHWA 

Manage/ Ensure Compli‐ance with the NBIS/ NTIS 

Review/Report Compliance with NBIS/NTIS and Provide Guidance 

   

Every Day Counts Innovation Deployment 

    FHWA/ MDOT 

Imple‐ment/Adopt 

Promote/Moni‐tor/Assist 

Within 24 months 

 

Exempt Bridge from Coast Guard permit requirements 

23 CFR 650     FHWA  Re‐view/De‐termine 

    Determination shall be made at an early stage of project devel‐opment so that any necessary coordination can be accom‐plished during environmental processing. 

*For Projects of Division Interest (PoDI) 

 

Page 21: Program Operations Manual - Michigan

  19 

CIVIL RIGHTS 

Overview 

The Federal Highway Administration (FHWA) works with MDOT and local departments of transportation to design, construct and maintain our public highway systems. Together we ensure fair and equitable delivery of our programs and services.   Therefore, public transportation agencies must comply with civil rights requirements established for these purposes. These requirements primarily include Title VI, Disad‐vantaged Business Enterprise (DBE), and the Americans with Disabilities Act Section 504, or ADA/Section 504. 

Continual emphasis and monitoring of Civil Rights programs by FHWA and MDOT occurs on a regular ba‐sis. The purpose of MDOT’s Civil Rights programs is to protect the rights of those employed in, benefit‐ing from, or affected by the FHWA or the programs, policies and activities of its recipients, or contrac‐tors. Every Federal‐Aid highway project/program must be in compliance with some aspect of Civil Rights laws, statutes, and/or executive orders regardless of whether the program service, or activity is Feder‐ally funded. 

Background/History 

The Civil Rights Program stewardship and oversight includes various reports, conducting program re‐views, providing technical assistance, attending periodic and regularly scheduled meetings, participating in workgroups and/or committees, advising Division Leadership on significant findings, and responding to inquiries from Headquarters, Congress, and other interested parties.   

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the Federal and state laws, regulations, and orders per‐taining to this program. 

Topic  Law  Implementing Regulations 

Disadvantaged Business Enterprise (DBE) 

DBE Uniform Awards and Commitment Report    49 CFR 26, Appendix B 

Annual Analysis and Corrective Action Plan (if necessary)    49 CFR 26.47(c) 

State DBE Program Goals    49 CFR 26.45(f)(1) 

DBE SS Quarterly Update    23 CFR 230.204(g)(6) 

DBE SS Annual Report    23 CFR 230.204(g)(6) 

On‐The‐Job Training Program (OJT) 

OJT SS Quarterly Update    23 CFR 230.121(e) 

OJT SS Annual Report    23 CFR 230.121(e) 

OJT Training Goals and Accomplishments    23 CFR 230.111(b) 

State Internal EEO/Contractor Compliance 

Annual Federal‐Aid Highway Construction Employment Data Report (FHWA‐1392) 

 23 CFR 230.121(a); Appendix D to Subpart A, Part 230, General Information and Instructions 

Annual EEO Program Update (AAP Workforce Data) with Accomplishment Report 

  23 CFR 230.311 

Contractor Compliance review reports    23 CFR 230.413 

Page 22: Program Operations Manual - Michigan

  20 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Disadvantaged Business Enterprise Program (DBE) o Good Faith Efforts approvals o Commercial Useful Function approvals o Michigan Unified Certification Program 

On‐the‐Job Training Program (OJT)  ADA/504 Program  Title VI Program  Title VII Program  EEO Contractor Compliance Program  504(e) Programs 

o Youth Development Mentoring Program (YDMP) o TRAC Internship/Pipeline Program o Y‐Achievers Program o Transportation and Civil Engineering Program o Veteran Internship Program o Recruitment, Outreach, and Career Fairs  o National Summer Transportation Institute o Conference of Minority Transportation Officials/Careers in Transportation for Youth o Federal Construction, State Construction, and Project Technical Training o Transportation Diversity Recruitment Programs 

 

 

Topic  Law  Implementing Regulations 

Title VI 

Title VI Plans, Accomplishment Reports & Goals    23 CFR 200.9(b)(11) 

Title VI Quarterly Report    23 CFR 200.9(b)(11) 

Discretionary Grant Program Funding 

OJT and DBE Supportive Services fund requests and An‐nual Accomplishment Reports 

 23 CFR 230.113 23 CFR 230.204 

National Summer Transportation Institute (NSTI) Proposals 

Return of unexpended funds used for Summer Transpor‐tation Institutes 

  23 CFR 230.117(2) 

Request for National Summer Transportation Institute (STI) Proposals 

23 USC 140(b)   

Report for NSTI  23 USC 140(b)   

Americans with Disabilities Act (ADA/504) 

ADA Transition Plan Section 504 of the Rehabilitation Act of 1987 

23 CFR 652   

Page 23: Program Operations Manual - Michigan

  21 

Approved Procedures, Agreements, and Manuals  

 

Procedures, Agreements, Manuals Latest Approval Date/ Version (if applicable) 

Anticipated due date (if applicable) 

DBE Program Procedures  September 06, 2019  As needed 

On‐the‐Job Training Program  March 22, 2018  As needed 

EEO Contractor Compliance Manual  January 01, 2018  As needed 

MDOT Title V1 Nondiscrimination Plan  November 01, 2019  October 1st 

MDOT Limited English Proficiency Plan  October 01, 2019  As needed 

MDOT Standard Assurances (FHWA 1273)  February 2012  As needed 

MDOT Internal Equal Employment Opportunity (EEO) Plan (Ti‐tleV11) 

May 14, 2018  May 2021 

MDOT ADA Transition Plan  May 2009  December 2020 

MDOT Environmental Justice Document (Completed by Planning)     

504(e) Programs  Periodically through‐out the year 

As needed 

On‐the‐Job Training SOW/DBE SOW  Periodically through‐out the year 

As needed 

National Summer Transportation Institute (NSTI) Proposals  January  As needed 

 

 

Page 24: Program Operations Manual - Michigan

  22 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement. 

Activity  Reference Schedule/ Frequency 

Responsible Agency MDOT 

MDOT Actions  FHWA Action Business  Standard 

Remarks 

Prepare / Review Title VI Plan Accom‐plishments and Next Year's Goals 

23 CFR 200.9(b)(10)  Annually Equal Employment Opportunity Officer/  Title VI Specialist 

Documentation devel‐oped by MDOT 

Division office reviews and comments. and 

approve 2 Weeks   

Prepare / EEO Contractor Compliance Plan accomplishments and next year's 

goals 

23 CFR 230, Subpart C, Ap‐pendix A, Part I, III 

Annually Office of Business 

Development Documentation devel‐

oped by MDOT Division office reviews 

and comments. 2 Weeks 

  

Prepare / Review State Internal EEO Affirmative Action Plan (Title VII) Ac‐

complishments and Goals 

23 CFR 230.311  Annually Equal Employment Opportunity Officer/ Title VI Specialist 

Documentation devel‐oped by MDOT 

Courtesy copy to HQ.     

Review DBE Program Revisions  49 CFR 26.21(b)(2)  As needed Office of Business 

Development Documentation devel‐

oped by MDOT 

Division sends to HCR for review and ap‐proval as needed 

   

Prepare / DBE Uniform Awards and Commitment Report 

49 CFR 26, Appendix B  Semi‐Annual Office of Business 

Development Documentation devel‐

oped by MDOT Division Office reviews 

and sends to HCR 1 Week   

Prepare / Annual Analysis and Correc‐tive Action Plan (if necessary) 

49 CFR 26.47(c) Annual 

(as necessary) Office of Business 

Development Documentation devel‐

oped by MDOT 

Division Office ap‐proves sends copy to 

HCR 2 Weeks   

Prepare / State DBE Program Goals  49 CFR 26.45(f)(1)  Triennial Office of Business Development 

Documentation devel‐oped by MDOT 

Division reviews and approves; sends copy 

to HCR  

HCC provides legal sufficiency review and approval. 

Prepare / Review On‐the‐ Job‐Training (OJT) goals & accomplishments 

23 CFR 230.111(b)  Annually Office of Business Development 

Documentation devel‐oped by MDOT 

Division office reviews and comments. 

1 Week   

Approval of OJT and DBE Supportive Services fund requests 

23 CFR 230.113 & 23 CFR 230.204 

Annual Office of Business Development 

Documentation devel‐oped by MDOT 

Division recommends approval submits to HCR for final approval 

2 Weeks   

Return of any unused discretionary grant program funding 

23 CFR 230.117(2)  Annual Office of Business Development 

MDOT Finance works with FHWA finance 

Division works with HCR and CFO 

   

Prepare / Review of Report on Sup‐portive Services (OJT & DBE) 

23 CFR 230.113(g), 230.121(e), 230.204(g)(6) 

Quarterly Office of Business Development 

Documentation devel‐oped by MDOT 

Division office reviews and comments. 

2 Weeks   

               

Page 25: Program Operations Manual - Michigan

  23 

 

 

Activity  Reference Schedule/ Frequency 

Responsible Agency MDOT 

MDOT Actions  FHWA Action Business  Standard 

Remarks 

Prepare/Review Annual Contractor Employment Report (Construction 

Summary of Employment Data (Form PR‐1392) 

23 CFR 230.121(a); Appendix D to Subpart A, Part 230, General Infor‐mation and Instructions 

Annually Office of Business Development 

Documentation developed by MDOT 

Recommendation sent to HQ for approval. 

2 Weeks   

Prepare / Review Annual Federal Projected Awards Reports ‐ Histori‐cally Black Colleges & Universi‐ties/Tribal Colleges & Universi‐ties/Hispanic Serving Institutes, 

American Indian Alaskan Native, Asian Pacific & American Is‐

lander. 

 Presidential Executive 

Orders: 13230, 13256,13270, 13361, 

13515 

Annual Office of Business Development 

Documentation developed by MDOT 

Divisions submit data to HCR who prepares 

report for DOCR 1 Week   

Prepare / Review ADA Complaint Re‐ports of Investigation 

28 CFR 35.190  As needed Equal Employment Opportunity Officer/ Title VI Specialist 

Investigation report developed by MDOT 

Division office reviews, FHWA HQ approves and issues finding. 

   

Review Americans with Disabilities Act (ADA) 

/Sec. 504 Program Plan accomplish‐ments and next year's goals 

49 CFR 27.11(c), EO 12250 

Annually Equal Employment Opportunity Officer/ Title VI Specialist 

Documentation developed by MDOT 

Division office reviews and comments. 

2 Weeks   

Return of unexpended funds used for Summer Transportation Institutes 

23 CFR 230.117(2)  Annual Office of Business Development 

MDOT Finance works with FHWA finance 

Divisions work with HCR and CFO 

   

Prepare / Review Request for National Summer Transportation Institute 

(NSTI) Proposals (SOWs) 23 USC 140(b)  Annual 

Office of Business Development 

Documentation developed by MDOT 

Divisions recommend approval. HCR gives fi‐

nal approval 2 Weeks   

Prepare / Review NSTI Report (ques‐tionnaire) 

23 USC 140(b)  Annual Office of Business Development 

Documentation developed by MDOT 

Divisions provide to HCR 

1 Week   

Page 26: Program Operations Manual - Michigan

  24 

Performance Measures and Indicators  

We will track and measure MDOT’s Civil Rights Program effectiveness with the following performance indicators and determine compliance. This is in addition to the monitoring activities noted above. 

 

Office of Business Development‐Disadvantaged Business Enterprise Performance Measures 

Due Responsible Agency 

Percent of DBE participation on Federal‐aid contracts  May 25 and November 23 

MDOT 

Number of DBE firms certified, graduated, and decertified   Annually  MDOT 

Number of DBE Commercially Useful Function (CUF) re‐views performed and outcomes  

Ongoing  MDOT 

Number of pre‐qualified DBEs   Annually  MDOT 

Number of projects with DBE Goal   Annually  MDOT 

DBE program race‐neutral participation   Annually  MDOT 

Number and type of DBE Supportive Services activities, i.e., training, conferences, contractor consultations  

Annually  MDOT 

Note: MDOT is the responsible agency to gather the various reports from the sub‐recipients and submits them to FHWA. The FHWA Civil Rights Specialist is responsible for reviewing the reports and forwarding them to HCR. 

 

Office of Business Development – Contractor Compliance Per‐formance Measures 

Due Responsible Agency 

Number of complaints received (formal/informal) regarding prompt payment/return of retainage and actions taken  

Annually  MDOT 

Number of EEO Contractor Compliance reviews performed and percent with violations  

Annual Report  MDOT 

Number of contractors in deficiency status and type of deficiency   Annual Report  MDOT 

Number of contractor training sessions on FHWA 1273   Annual Report  MDOT 

Office of Business Development – On‐the‐Job Training (OJT) Per‐formance Measures 

Due Responsible Agency 

Number of OJT trainees by race and gender  November 15  MDOT 

Number of contractors utilized in the OJT Program  November 15  MDOT 

Number of OJT training hours  November 15  MDOT 

Number and type of Supportive Service activities, i.e., training, TRAC, Summits 

Annually  MDOT 

MDOT Civil Rights Programs Unit (Internal) – Title VII Perfor‐mance Measures 

   

Submission and approval of a comprehensive and valid EEO Plan   As needed  MDOT 

Page 27: Program Operations Manual - Michigan

  25 

Number of complaints, lawsuits filed, actions taken to resolve, or accommodations made  

Included in Annual Report 

MDOT 

Underutilization analysis and goals to eliminate underutilization when discrimination has been determined to be the reason for the underutilization  

Included in Annual Report 

MDOT 

Number of training sessions and the number of participants in the prevention of discriminatory harassment  

Included in Annual Report 

MDOT 

Number of managers and supervisors trained in the effective im‐plementation of equal employment opportunity and non‐discrim‐ination policies  

Included in Annual Report 

MDOT 

MDOT Civil Rights Programs Unit‐(Internal/External) ‐ Title VI Performance Measures 

Due Responsible Agency 

Submission and approval of a comprehensive and valid Title VI Plan 

Included in  Annual Report 

MDOT 

Number of Title VI reviews; deficiencies noted and corrections recommended 

Included in  Annual Report 

MDOT 

Number of Title VI Training sessions (internal employees and sub‐ recipients) 

Included in  Annual Report 

MDOT 

Number and type of Title VI complaints filed, and actions taken to resolve, or accommodations made 

Included in  Annual Report 

MDOT 

Submission and approval of a comprehensive and valid Title VI Plan 

Included in  Annual Report 

MDOT 

Number of Title VI reviews; deficiencies noted and corrections recommended 

Included in  Annual Report 

MDOT 

Number of Title VI Training sessions (internal employees and sub‐ recipients) 

Included in An‐nual Report 

MDOT 

MDOT Civil Rights Programs Unit‐(Internal/External) – ADA Per‐formance Measures 

Due Responsible Agency 

Number of ADA complaints (Internal and External)  Included in Annual Report 

MDOT/FHWA 

Number of projects completed to ensure ADA compliance as listed in the MDOT Transition Plan  

Included in Annual Report 

MDOT 

 

   

Page 28: Program Operations Manual - Michigan

  26 

CONSTRUCTION AND CONTRACT ADMINISTRATION  

Overview 

To protect the public investment in Federal‐aid highway projects, FHWA provides program and risk‐based project oversight in order to help ensure compliance with Federal‐aid contract provisions on all state and local projects that utilize Federal‐aid funds.  A variety of specific Federal‐aid contract provi‐sions are required to be included on all state and local projects that utilize Federal‐aid funds. FHWA is also responsible for concurrence with MDOT’s advertisement, award procedures and project quality controls/quality assurance processes. Some processes and procedures are required by state/federal statute, regulation, or policy. Support of transportation agencies also includes providing technical assis‐tance and sharing best practices. 

 

Background/History 

The common goal of MDOT and FHWA is to administer transportation improvement projects efficiently and effectively. This goal supports the state transportation department (STD) program. The FHWA Mich‐igan Division Office may review and approve various construction specifications, submissions, and con‐tract changes. They may also participate in preconstruction meetings, progress meetings, claim meet‐ings, and Dispute Review Board meetings and hearings. FHWA staff determine the eligibility of Federal‐aid participation in accordance with the Stewardship and Oversight Agreement and the FHWA Project of Division Interest (PoDI) Agreement.  

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law Implementing Regulations 

Value Engineering    23 CFR 627 

Preconstruction Procedures    23 CFR 630 

Required Contract Provisions    23 CFR 633 

Construction and Maintenance    23 CFR 635 

Design – Build Contracting    23 CFR 636 

Construction Inspection and Approval    23 CFR 637 

Emergency Relief Program    23 CFR 668 

Project Approval and Oversight  23 USC 106  23 CFR 172 

Standards  23 USC 109  23 CFR 625 

   

Page 29: Program Operations Manual - Michigan

  27 

Key Program Areas 

Below are key program areas.  

Buy America  Contract Specifications and Provisions  Contract Administration  Quality Control and Assurance   Contractor Claims   Contract Modifications (including FHWA 1365)   Contractor Payments  Extensions of Time   Liquidated Damages  Subcontracting  Prevailing Wage Compliance  Work Zone and Project Site Safety  

 

Approved Procedures, Agreements, and Manuals  

FHWA‐specific construction monitoring responsibilities include, but are not limited to: 

Quality Control and Assurance  Major Contract Modifications   Extensions of Time  Liquidated Damages   Contractor Claims  Dispute Review Board   Innovative Construction Practices 

 

Procedure, Agreement, Manuals Latest Approval Date/ Version 

Anticipated due date 

FHWA/MDOT Stewardship and Oversight Agreement  May 2015   

MDOT Standard Specifications for Construction  2012  2020 

MDOT Materials Quality Assurance Procedures Manual  August 2020    

MDOT Construction Manual  Online  As Needed 

MDOT Work Zone Safety and Mobility Manual  January 2020   

MDOT Capital Preventive Maintenance Manual  April 2010   

MDOT Density Testing and Inspection Manual  November 2018   

MDOT HMA Production Manual  January 2020   

MDOT Manual for Michigan Test Methods  2019   

MDOT Procedures for Aggregate Inspection  2019   

MDOT Materials Source Guide  August 2020   

MDOT Soil Erosion and Sedimentation Control Manual  April 2006   

 

 

Page 30: Program Operations Manual - Michigan

  28 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities, see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action Business Standard 

Remarks 

Quality Assurance Program  23 CFR 637.205  As‐Needed  FHWA  Administer  Review and approve.     

Central Laboratory accredited by AASHTO Accreditation Program or FHWA approved comparable program 

23 CFR 637.209  As Needed  MDOT  Administer  Monitor     

Non‐STD designated lab performing Inde‐pendent Assurance sampling, used in dis‐pute resolution, and testing accredited by AASHTO Accreditation Program or FHWA approved comparable program 

23 CFR 637.209  As‐Needed  MDOT  Administer  Monitor     

Independent Assurance Annual Report  23 CFR 637.207  Annually, March 1 

FHWA  Administer  Review     

Labor Compliance ‐ Prevailing Wage Rate  23 USC 113  As‐Needed  FHWA  Administer  Monitor     

Work Zone Significant Project Determina‐tion 

23 CFR 630.1010  As‐Needed  MDOT  Administer  Review and approve.     

Exceptions to Work Zone Procedures for Interstate Projects 

23 CFR 630.1010  As‐Needed  FHWA  Submit  Review and approve.     

Work Zone Policy and Procedures Con‐formance Review 

23 CFR 630.1014  At Appropri‐ate Intervals 

FHWA  Submit  Review and approve.     

Process Review of Work Zone Safety and Mobility Procedures 

23 CFR 630.1008, 23 USC 109(e)(2), 23 USC 112(g) 

Every 2 years 

MDOT  Submit  Review and approve.     

Changes and extra work  23 CFR 635.120  As‐Needed  MDOT  Administer  Review and approve per PoDI action plan. 

   

Page 31: Program Operations Manual - Michigan

  29 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action Business Standard 

Remarks 

Contract time extensions  23 CFR 635.120  As‐Needed  MDOT  Administer  Review and approve per PoDI action plan. 

   

Use of mandatory borrow/disposal sites  23 CFR 635.407  As‐Needed  MDOT  Administer  Review and approve per PoDI action plan. 

   

Materials certifications  23 CFR 637.207  As‐Needed  MDOT  Administer  Review and approve per PoDI action plan. 

   

Settlement of contract claims  23 CFR 635.124  As‐Needed  FHWA  Administer  Review and approve.     

Termination of construction contracts  23 CFR 635.125  As‐Needed  MDOT  Administer       

Buy America Waivers  23 CFR 635.410  As‐Needed  FHWA  Submit  Review and approval.    Requires FHWA HQ approval. 

Final inspection/acceptance of completed work 

23 USC 114(a)  As‐Needed  MDOT  Administer  Review and approval per PoDI action plan. 

   

 

 

Page 32: Program Operations Manual - Michigan

  30 

DESIGN 

 Overview 

MDOT and FHWA support a Design Program that implements innovative tools during the development, review, and delivery of projects. The goal of both agencies is to develop safe, cost‐ efficient designs that address the purpose and need of the project, while considering the needs of all users and minimizing or mitigating environmental impacts.  

The FHWA Michigan Division Office reviews and approves various engineering related submissions, par‐ticipates in project development decisions and determines eligibility of Federal‐aid participation in ac‐cordance with the Stewardship and Oversight Agreement and the jointly determined project level over‐sight agreement.  

At the program level, MDOT provides training and outreach to staff on new programs and initiatives, and creates a seamless cooperation between the Bureaus and Regions. FHWA provides guidance on the implementation of, and conformance to, federal laws, regulations and policies pertaining to preliminary and detailed design activities. FHWA and MDOT staffs jointly conduct concentrated program reviews and risk assessments to monitor the effectiveness of the program.  

 

Background/History 

MDOT develops a road program averaging $962,000,000 annually spread among many templates to achieve a mix of fixes to best manage the MDOT infrastructure. Projects are scoped, designed and man‐aged by the Bureaus, Regions and associated Transportation Service Centers around the state. The De‐sign Division supports the development of the program through specific development tasks, Project Manager support and technology support.  

The Quality Assurance Section of the Design Division is integral to the delivery of the program by provid‐ing support for standards, manuals, and processes to ensure compliance with federal requirements. Spe‐cifically, the Road Design Manual (RDM) contains policies, practices, and processes to complete the de‐velopment process, including Chapter 14 which is a comprehensive resource for development pro‐cesses. This is a resource for Project Managers and Designers statewide. 

The Design Services Section supports designers and many other areas of the department with software, surveys and ProjectWise. The Section also manages the Development Guide (Design Wiki) which pro‐vides guidance on 3D modeling deliverables. 

FHWA provides project level oversight on Projects of Division Interest (PODI). These projects are identi‐fied by FHWA Division Office and the MDOT Regions collaboratively based on a variety of risk factors an‐ticipated within programmed projects.  

When projects are selected for FHWA oversight, specific project risks and FHWA approval actions will be identified. A project may have FHWA oversight throughout the life of the project, from planning through construction closeout, or only over specific tasks or phases of the project. FHWA may also choose to have oversight on tasks that have been delegated to MDOT through the Stewardship and Oversight Agreement. 

Page 33: Program Operations Manual - Michigan

  31 

The level of oversight will be documented on a PODI Approval Actions form from FHWA and be saved in the ProjectWise Supporting Documents folder. As the project evolves, FHWA oversight may change and will be evaluated as needed based on changing risks.  

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Regulations 

Program Efficiencies   23 USC 102 (b)  23 CFR 630 

Project Approval and Oversight  23 USC 106   

Design Standards for Highways   23 USC 109  23 CFR 625 

Letting of Contracts  23 USC 112   

Procurement, Management, and Administration of Engineering and Design Related Services 

  23 CFR 172.7 

Management and Monitoring systems    23 CFR 500 

Projects of National and Regional Significance    23 CFR 505 

Engineering    23 CFR 620 

Value Engineering  23 USC 106, 23 USC 120(c)(3)  23 CFR 627 

Preconstruction Procedures    23 CFR 630 

Utilities    23 CFR 645 

Railroads     23 CFR 646 

Bridges, Structures, and Hydraulics    23 CFR 650 

Bicycle Transportation and Pedestrian Walkways  23 USC 217(g)   

Truck Size and Weight, Route Designations – Length, Width and Weight Limitations 

  23 CFR 658 

Indian Reservation Road Bridge Program    23 CFR 661 

General Highway Law  MCL Chapters 220 – 224   

Highways  MCL Chapters 247, 249, 250, 252   

Grade Crossings  MCL Chapter 253   

Bridges  MCL Chapter 254   

Americans with Disability Act     42 USC 12101  28 CFR 35 

Rehabilitation Act  29 USC 794  34 CFR 104 

Highways strategically important to the National Defense 

23 USC 311   

Buy America  23 USC 313   

NEPA    23 CFR 771 

 

 

 

 

Page 34: Program Operations Manual - Michigan

  32 

Key Program Areas 

These are the key program areas within the program or related to the program.  

 

National Highway Performance Pro‐gram (NHPP) 

Surface Transportation Block Grant (STBG) Program  

Geometric Design   Consultant Services  Performance Based Practical Design   Value Engineering  Bridge and Structure Design    Hydraulic Design  Utilities  

Landscaping and/or Rest Area   Geotechnical Design  Innovative Contracting Process  Design Standards  Special Provisions  Work Zone  Real Estate  Traffic and Safety  Finance (for timely obligation of con‐

struction phase)  

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/ Version (if applicable) 

Update Cycle (if applicable) 

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

AASHTO: A Policy on Geometric Design of Highways and Streets 

6th edition  As needed 

MDOT Road Design Manual    As needed 

MDOT Standard Plans    As needed 

MDOT Special Details    As needed 

MDOT Drainage Manual  January 2006  As needed 

MDOT Design Survey Manual    As needed 

Guidelines for Stakeholder Engagement  January 2009  As needed 

Alternate Pavement Bidding Process     As needed 

Innovative Construction Contracting Guide  March 2015  As needed 

Development Guide    As needed 

Scoping Manual  June 2019  As needed 

As needed updates with substantive changes to policy will be shared with FHWA in draft form prior to requesting approval from the Engineering Operations Committee. Minor updates will be discussed in the regular Design‐FHWA update meetings and distributed via listserv subscription 

 

.

Page 35: Program Operations Manual - Michigan

  33 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. Refer to other POM sections for additional monitoring and approval activities related to the program.  

 

Activity  Reference  Schedule/Frequency Responsible Agency 

MDOT Action  FHWA Action  Business Standard  Remarks 

Adoption of De‐sign Standards (National Highway System, including Interstate 

23 CFR 625, 23 USC 109(b), 23 USC 109(c)(2), 23 USC 109(o) 

As needed  FHWA  MDOT adopts Design stand‐ards 

FHWA HQ reg‐ulatory action to adopt NHS standards 

Transition timing is based on complexity and inclusion in PS&E for letting 

 

MDOT Standard Specifications  

23 CFR 625.3  As needed. Full re‐is‐sue edition roughly every 6 to 7 years. In‐terim updates issued by supplemental specifications or spe‐cial provisions. 

FHWA  MDOT shall re‐quest approval  

FHWA Division office reviews and approves 

Supplemental specifi‐cations and special pro‐visions approved by FHWA within 14 calen‐dar days (with excep‐tions as needed). 

 

Design Excep‐tions* 

23 CFR 625.3  As needed  MDOT         

Design Standard Plans 

23 CFR 625.3  As needed  FHWA  MDOT Develops and maintains Standard Plans 

FHWA ap‐proves new and updated Standard Plans 

FHWA will review and approve Standard Plans within 30 business days. 

 

Value Engineering (VE) Policy and Procedures 

23 CFR 627.1(b) & (c), 23 CFR 627.7, FHWA Order 1311.1B 

As needed  MDOT  MDOT publishes and maintains VE policy and procedures in the Road Design Manual. 

FHWA ap‐proves VE pol‐icy and proce‐dures. 

FHWA approves VE pol‐icy changes withing 30 business days. 

 

Page 36: Program Operations Manual - Michigan

  34 

Activity  Reference  Schedule/Frequency Responsible Agency 

MDOT Action  FHWA Action  Business Standard  Remarks 

Value Engineering Annual Report 

23 CFR 627.7, FHWA Order 1311.1B 

Annual  FHWA  MDOT submits annual report including cost and savings data. Data is shared with MDOT manage‐ment and staff.  

FHWA submits report to HQ to compile na‐tionally. 

Annual report is sub‐mitted by MDOT by the requested due date 

FHWA Division Office collects, reviews, and submits to HQ for review and reporting 

Plans, Specifica‐tions and Esti‐mates (PS&E) * 

23 CFR 630    MDOT         MDOT Project Manager ap‐proves on Certi‐fication Ac‐ceptance (CA) form 

* Any approval action that FHWA has delegated to MDOT could be retained by FHWA as part of the PODI Approval Actions form. Both FHWA and MDOT should coordinate on review times to meet project schedules. 

 

Page 37: Program Operations Manual - Michigan

  35 

EMERGENCY RELIEF PROGRAM 

 Overview 

Emergency Relief (ER) is a special program that uses funds from the Highway Trust Fund for the repair or reconstruction of Federal‐aid Highways and of roads on Federal lands that have suffered serious damage from natural disasters or catastrophic failures from external causes. This program supplements the com‐mitment of resources by states, their political subdivisions, or other Federal agencies to help in the re‐pair of facilities damaged by eligible events.  

 

Background/History 

ER funds are not intended to cover all damage repair costs or interim emergency repair costs that will be necessary to restore a facility to pre‐disaster conditions. Disasters must be considered extraordinary and/or widespread to be considered for ER funding. The estimated federal portion of the eligible dam‐age must meet a threshold of $700,000 (Federal share). Individual sites must have estimated repairs greater than $5,000 to be eligible. 

Over the past several years the Michigan Department of Transportation has experienced multiple eligi‐ble ER events. The eligible costs and the number of resources required to manage the events has in‐creased, creating the need for more efficient processes, communication and outreach.  

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Regulations 

Periodic Evaluation of Facilities Repeatedly Requiring Repair and Reconstruction Due to Emergency Events 

  23 CFR 667 

Federal Share Payable  23 USC 120   

Emergency Relief  23 USC  125  23 CFR 668 

Environmental Impact and Related Procedures    23 CFR 771 

Funding Flexibility for Transportation Emergencies  23 USC 170   

FHWA Emergency Relief Program Responsibilities    FHWA Order 5182 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Road Design  Bridge and Structure Design  Hydraulic Design  Geotechnical Design  Construction  

Emergency Management  Innovative Construction Practices  Local Agency Programs  Contract Services  

 

Page 38: Program Operations Manual - Michigan

  36 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As Needed 

MDOT Emergency Relief Program Outline  June 2017  Annually 

FHWA Emergency Relief Manual  May 2013   

FHWA Standard Operating Procedure for Quick Release Funds  August 2020   

Emergency Relief Data Portal System User Guide  April 2020   

  

Page 39: Program Operations Manual - Michigan

  37 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

 

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Business Stand‐ard 

Remarks 

Damage Assessment  23 CFR 688  After eligible event  MDOT  Determine severity of damage as soon as practical after event 

Support MDOT in assessment of damages 

FHWA responds to eligibility sup‐ported by dam‐age survey re‐port within 14 business days 

Should be sub‐mitted at least 6 weeks after let‐ter of intent 

Letter of Intent (LOI) and Acknowledge‐ment Letter  

  After proclamation and/or declaration that an event has occurred 

MDOT/ FHWA 

MDOT submits letter to FHWA requesting the use of ER Funds for an eligible event 

Makes determina‐tion, sends letter to MDOT and no‐tifies HQ 

FHWA responds within 3 busi‐ness days 

Submit LOI as soon as practical after event oc‐curs 

Quick Release (QR) Funds 

  Based on immedi‐ate need and avail‐ability of funding 

MDOT/ FHWA 

Provide information documenting event threshold will be met  

If QR is warranted funds will be obli‐gated after Presi‐dent’s or Gover‐nor’s declaration 

MDOT requests as soon as possi‐ble after eligible event 

Requests typi‐cally made within 6 weeks of event 

MDOT Initial Request and FHWA Finding 

  After Governor’s declaration  

MDOT/ FHWA 

Submit request letter including declaration and list of damaged locations 

Makes determina‐tion and sends let‐ter to MDOT 

FHWA responds within 3 busi‐ness days 

Includes event estimate of dam‐ages 

Detailed Damage In‐spection Reports (DDIR’s) form 1547 

23 USC 120  Complete within 3 months of event 

MDOT/ FHWA 

Complete DDIR’s ‐clas‐sify damage as emer‐gency or permanent repairs  

Determine if eligi‐bility is limited to the cost of compa‐rable facility. Per‐form site assess‐ments 

Complete all eli‐gible DDIR’s within 3 months of event 

FHWA Area Engi‐neer Approves (or FHWA ER Pro‐gram Manager) within 5 business days 

Page 40: Program Operations Manual - Michigan

  38 

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Business Stand‐ard 

Remarks 

Coordination with FEMA 

44 CFR 206, 23 CFR 668.109 

As needed based on eligibility 

MDOT  Track costs associated with debris removal based on FEMA or ER Program eligibility 

Request and re‐view FEMA deter‐mination to en‐sure debris re‐moval is eligible under ER Program 

   

Construction Monitor‐ing 

  As needed based on Division Risk Based Oversight processes 

MDOT/ FHWA 

Submits projects for authorization with ap‐proved DDIR’s, sub‐mits 1365’s for in‐creases greater than 20% 

FHWA reviews and approves 

FHWA responds to authorization requests within 7 business days 

 

ER Application  23 USC 125  No later than 2 years after the dis‐aster start date 

MDOT  Compile list of eligible sites and costs sup‐ported by completed DDIR’s 

FHWA reviews to confirm eligibility 

  Funds for emer‐gency repairs only valid for 180 days after event 

Project Closeout  2 CFR 200.343 

           

 

 

Page 41: Program Operations Manual - Michigan

  39 

ENVIRONMENT  

Overview 

In accordance with the National Environmental Policy Act of 1969 (NEPA), FHWA is required to consider the social and natural environment prior to making any decisions on projects having Federal involve‐ment; that is, Federal funding or involving Federal action (e.g., permitting by a Federal agency). FHWA has a direct oversight role in implementing NEPA. FHWA and MDOT will work together to ensure social, environmental, and economic factors are given proper consideration along with engineering factors in program and project decision‐making.  

 

Background/History 

In general, under environmental actions:  

FHWA’s primary role is to provide guidance and independent oversight of the NEPA process involving all transportation projects funded through the Federal Aid Program. FHWA also provides guidance and oversight for Federal Aid‐funded projects covered by other Federal laws and regulations on the natural and human environment, including, but not limited to, Section 4(f) of the Department of Transportation Act, the Endangered Species Act, the National Historic Preservation Act, the Clean Air Act, the Clean Wa‐ter Act, etc.  

MDOT is responsible for ensuring compliance with Federal environmental law and regulations for all Federal aid transportation projects in the state inclusive of local agency projects. MDOT will maintain qualified professional staff to ensure compliance and conduct analyses. 

MDOT maintains documentation of environmental activities.  

FHWA assures appropriate analyses are conducted, approval actions are timely, and public involvement is an element of MDOT’s environmental program.  

FHWA and MDOT will continue to work together to streamline the environmental process.  

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Reg‐ulations 

Antiquities Act, 1906  16 USC 431‐433  36 CFR 251.50‐64 42 CFR 3 

American Indian Religious Freedom Act, 1978  42 USC 1996  N/A 

 American with Disabilities Act, 1990   42 USC 126  16 USC 1271‐1287 

Archeological and Historic Preservation Act, 1974   16 USC 469  36 CFR 66 

Archeological Resources Protection Act, 1980  16 USC 470  43 CFR 7 18 CFR 1312 32 CFR 79 36 CFR 229 36 CFR 296 

Page 42: Program Operations Manual - Michigan

  40 

Topic  Law Implementing Reg‐ulations 

Section 106 of the National Historic Preservation Act of 1966 (54 U.S.C. 300101 et seq.; NHPA) 

  36 CFR 800 

Bald and Golden Eagle Protection Act, 1940   16 USC 668  N/A 

Title VI of the Civil Rights Act, 1964  42 USC 2000d et seq.  49 CFR 21 and 23 CFR 200 

Civil Rights Restoration Act, 1987  20 USC 1681 et seq.  N/A 

Clean Air Act, 1970  42 USC 7401 et seq. 42 USC 7509, 75219(a) 23 USC 109(J) 

23 CFR 771 40 CFR 51 & 93 

Clean Water Act, 1972  33 USC 1251 et seq.  33 CFR 26 40 CFR 122‐124 

Coastal Zone Management Act, 1972  16 USC 1451  15 CFR 923‐930 

Comprehensive Environmental Response, Compensa‐tion, and Liability Act, Superfund Amendments and Reauthorization Act, 

42 USC 9601 et seq.  40 CFR 300 43 CFR 11 

Department of Transportation Act, Section 4 (f), 1966  49 USC 303 23 USC 138 

23 CFR 774 

Endangered Species Act, 1973  16 USC 1531 et seq.  7 CFR 335; 50 CFR 17, 23, 81, 222, 225‐227, 402, 424, 450, 453 

Executive Order 11991, Protection and Enhancement of Environmental Quality, 1970  

N/A  N/A 

Executive Order 11988, Floodplain Management  N/A  23 CFR 650, 771; 44 CFR 59‐62, 64‐68, 70‐71, 75‐77 

 Executive Order 11990, Protection of Wetlands  N/A  DOT Order 5660.1A 

23 CFR 777 

Executive Order 13166, Limited English Proficiency 2000 

N/A  Federal Reg. Vol. 60, No. 125, pp. 33896–33903 FR Vol. 59, No. 32 

EO 13807: Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure Projects (2017) 

N/A  23 CFR 771 

Wild and Scenic Rivers Act, 1968  16 USC 1271‐1287  36 CFR 251, 297; 43 CFR 8350 

National Environmental Policy Act, (NEPA), 1969  42 U.S.C. 4321 et seq.  40 CFR parts 1500–1508 (“CEQ regula‐tions” or “NEPA reg‐ulations”); 23 CFR 771 FHWA NEPA regulations 

 

Page 43: Program Operations Manual - Michigan

  41 

Key Program Areas 

These are the key program areas within the program or related to the program.  

National Environmental Policy Act of 1969 as amended;   Update to the Regulations Implementing the Procedural Provisions of the National Environ‐

mental Policy Act June 30, 2020  (hereinafter CEQ NEPA Regulations)  Planning and Environmental Linkages  Parks, Recreation areas, Wildlife and waterfowl refuges, and Historic Sites (Section 4(f) & 

6(f))  Environmental Justice and Title VI  Historic and Archeological Preservation (Section 106), Tribal Consultation & Cultural Re‐

sources  Public Involvement & Community Impact  Noise Abatement  Wetland Mitigation  Floodplains Mitigation  Threatened and Endangered Species; Habitat and Ecosystems  Air Quality   Water Quality, Watershed & Stormwater Mitigation and Management  Context Sensitive Solutions  Visual Impacts  Interagency Coordination  

Approved Procedures, Agreements, and Manuals  

FHWA and MDOT have put into place several procedures, agreements, and a manual to both govern and streamline the NEPA process. The MDOT Environmental Procedures Manual provides the most compre‐hensive guidance document. Other guidance documents and streamlining agreements are listed below. 

Procedure, Agreement, Manuals Latest Approval Date/Version 

Anticipated due date 

Programmatic Categorical Exclusion Agreement  September 30, 2019 

September 30, 2024 

FHWA/ACHP/MDOT/SHPO Section 106 Agreement  July 25, 2011  July 25, 2021 

Environmental Procedures Manual  January 5, 2012  As needed 

MDOT Highway Noise Analysis and Abatement Handbook  July 2011  As needed 

MDOT Public Involvement and Public Hearings Procedures for Federal Aid Project Development 

November 2002; October 1, 2020 amended 

As needed 

USFWS Biological Opinion Programmatic Agreement—Bats  October 16, 2019  As needed 

USFWS Biological Opinion Programmatic Agreement—Eastern Massassauga Rattlesnake 

November 5, 2019 

As needed 

Michigan Freshwater Mussel Survey Protocols and Relocation Procedures 

February 2018  As needed 

FHWA/USFWS/MDOT Liaison Agreement  November 21, 2019 

November 21, 2024 

Section 106 Letter of delegation for Local Agencies to initiation consultation with SHPO 

October 16, 2020  As needed   

Page 44: Program Operations Manual - Michigan

  42 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by ac‐tivity and provides information about the relative responsibilities for both FHWA and MDOT. For addi‐tional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

The FHWA will monitor compliance with environmental requirements using project‐by‐ project approval steps and, periodic quality assurance reviews of the environmental process.  

MDOT has been delegated programmatic approval authority for specific categorical exclusions.   MDOT has been delegated programmatic approval authority for specific Section 4(f) evaluations.  MDOT has been delegated programmatic approval authority for Section 106 determinations and 

specific consultation actions.  MDOT also acts as an FHWA non‐federal representative for informal Section 7 ESA consultation.   MDOT acts as an FHWA non‐federal representative for tribal consultation  MDOT public involvement procedures have been approved by FHWA (November 2002).  

As early as practicable in a project’s development, the FHWA and MDOT will collaborate on the proper environmental (NEPA) classification for a project:  

Class I = EIS   Class II = CE   Class III = EA  

For all projects that require an action be taken by FHWA, FHWA and MDOT will work together in the project pre‐engineering phase to ensure compliance with NEPA and other applicable laws before an al‐ternative is selected. The level of involvement is commensurate with the level of environmental impacts or project complexity.  

FHWA will review and approve Level 4 Categorical Exclusions and associated Programmatic Section 4(f) Evaluations, EA, EIS, Section 4(f) Individual Evaluations, net benefit Section 4(f) evaluations, and Section 4(f) De Minimis determinations which are prepared by MDOT.  

FHWA is also an active member of individual project teams and helps guide the project plan‐ning.  

All documents requiring legal sufficiency review (final EIS and final Section 4(f) Evaluations) are sent 

to the FHWA Office of the Chief Counsel in Matteson, Illinois by the FHWA Michigan Division Office 

prior to approving these documents. The goal is to provide legal sufficiency review comments to the 

FHWA Michigan Division Office within 30 business days after receipt of the document. Environmen‐

tal document re‐evaluations are conducted through informal consultation and formal written docu‐

mentation when appropriate. 

 

Page 45: Program Operations Manual - Michigan

  43 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Level 1, 2, or 3 Categorical Ex‐clusion (CE) (23 CFR 771.117 (a),(b), and (c)) 

CE  Programmatic  Agreement 

Ongoing  MDOT  Prepare and Ap‐prove 

Periodic Audit    MDOT has  delegation to  approve 

Level 4 CE (Individual CE) (23 CFR 771.117 (d)) 

CE  Programmatic  Agreement 

Ongoing  MDOT & FHWA 

Prepare, approve and submit to FHWA for  approval 

Approve CE or  instructions for  revisions 

30 business days 

 

Letter of Initiation  Environmental Procedures Manual 

Ongoing  MDOT & FHWA 

Prepare a letter of initiation request‐ing concurrence on NEPA classifi‐cation for an EA or EIS. 

Concur with NEPA classification 

15 business days. 

Starts the clock for completing the NEPA docu‐ment in required timeframe. 

Draft Environmental Assess‐ment 

23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT  Prepare and sub‐mit to FHWA for comment 

Review and Com‐ment  

30 business days 

Written Com‐ments 

Environmental Assessment  23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare, approve and submit to FHWA for ap‐proval 

Approve EA for circulation or re‐turn for revision 

15 business days 

Approved EA or instructions for revision 

Finding of No Significant Impact (FONSI) 

23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare FONSI re‐quest and submit to FHWA 

Prepare and Issue FONSI or notify MDOT of need for EIS 

30 business days 

FONSI or consid‐ered NOI for EIS 

Informal Consultation with  Resource Agency (State and Federal) 

Environmental Procedures Manual 

As needed  MDOT  Review and deter‐mine if potential for adverse effect 

Acknowledge and file 

NA  Verify any re‐quired mitigation is contained with Individual CE, EA or EIS 

Page 46: Program Operations Manual - Michigan

  44 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Cooperating and Participating Agency Request Letters 

Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare and dis‐tribute request letters to state, and local agencies 

Prepare and dis‐tribute request letters to Federal agencies 

15 business days 

Cooperating & Participating Agencies identi‐fied and notified of action 

Notice of Intent (NOI) for  Environmental Impact State‐ment (EIS); (23 CFR 771.123) 

23 CFR 771, Env. Proce‐dures Manual 

As needed  MDOT & FHWA 

Prepare and send NOI package to FHWA 

Enter NOI into the Federal Register 

15 business days 

 

Draft EIS  23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare, approve, and submit to FHWA for ap‐proval 

Approve DEIS and upload to eNEPA for Federal Regis‐ter or return for revision  

30 business days 

DEIS approved and in Federal Register or in‐structions for re‐vision 

Draft Final Environmental Im‐pact Statement (FEIS) 

23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT  Prepare and sub‐mit to FHWA for review 

Review and com‐ment 

30 business days 

Written Comments 

FEIS Legal Sufficiency  23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare and sub‐mit to FHWA for review 

Request Legal  Sufficiency review 

30 business days 

FEIS Legal Suffi‐ciency deter‐mined 

Final EIS  23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare, approve, and submit to FHWA for ap‐proval  

Approve FEIS and upload to eNEPA for Federal Regis‐ter or return for revision 

30 business days 

FEIS approved and published in Federal Register or instructions for revision 

Record of Decision (ROD) or Combined FEIS/ROD 

23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare a Draft ROD or Combined FEIS/ROD and sub‐mit to FHWA 

Review, Revise, and issue ROD or Combined FEIS/ROD issued d upload to eNEPA 

30 business days 

ROD or Com‐bined FEIS/ROD issued and pub‐lished in Federal 

Page 47: Program Operations Manual - Michigan

  45 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

for Federal Regis‐ter or return for revisions 

Register or in‐structions for re‐vision 

Draft Re‐evaluation EA or EIS (Including Section 4(f) if needed) 

23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT   Prepare and sub‐mit to FHWA for review  

Review and Com‐ment 

20 business days 

Written com‐ments 

Final Re‐evaluation EA or EIS  23 CFR 771,  Environmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare, approve, and submit to FHWA for ap‐proval 

Approve Re‐evalu‐ation or return for revision 

20 business days 

Re‐evaluation ap‐proved or in‐structions for re‐visions 

Notice of Limitation (NOL) for Statue of Limitation (SOL) 

23 CFR 771,  Environmental Procedures Manual 

As needed  FHWA  N/A  Prepare, approve, and submit thru FHWA Chief Coun‐cil’s office for Fed‐eral Register 

10 business days from ROD 

NOL issued and 150 days for SOL begins 

Major Projects (total cost ≥ $500 million) – Project Man‐agement Plans (PMP) 

  Ongoing  FHWA & MDOT 

Prepare Project  

Management Plans (PMP) in ac‐cordance with SAFETEA‐  

LU and FHWA HQ Project Manage‐ment Plan Guid‐ance. PMPs must be completed and approved prior to issuing ROD or FONSI and prior to issuing request for authorization of Federal aid funds 

Review and ap‐prove 

30 business days 

Approved PMP 

Page 48: Program Operations Manual - Michigan

  46 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

for right‐ of‐way acquisition or con‐struction. 

Programmatic Section 4(f) Eval‐uation with Level 1, 2, or 3 CE (Temporary 4(f) use) 

CE Program‐matic Agree‐ment 

Ongoing  MDOT  Prepare and ap‐prove 

No action re‐quired unless FHWA objects. 

FHWA Michi‐gan Division can object to MDOT’s ap‐proval within 15 business days 

Approved Pro‐grammatic Sec‐tion 4(f) evalua‐tion 

Draft Programmatic Section 4(f) Evaluation with Level 4 CE, EA or EIS (De Minimis Section 4(f))  

CE Program‐matic Agree‐ment 

As needed  MDOT & FHWA 

Prepare and sub‐mit for FHWA ap‐proval 

Approve Program‐matic Section 4(f) Evaluation or re‐turn for revision 

15 business days 

Approved Pro‐grammatic Sec‐tion 4(f) Evalua‐tion or instruc‐tions for revision 

Final Individual Section 4(f) Evaluation & Section 4(f) Legal Sufficiency 

23 CFR 774, En‐vironmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare and sub‐mit for FHWA ap‐proval 

FHWA review and approve or return for revisions; FHWA will request Legal Sufficiency Review  

45 business days:  30 busi‐ness days for Legal Suffi‐ciency and 15 business days for FHWA ap‐proval or re‐turn for revi‐sions 

Final Section 4(f) Evaluation ap‐proval with Legal Sufficiency or in‐structions for re‐visions 

Section 106 Adverse Effect De‐termination Final Section 4(f) Evaluation 

36 CFR 800 and 23 CFR 774, En‐vironmental Procedures Manual 

As needed  MDOT/SHPO & FHWA 

Makes determina‐tion; secures SHPO concur‐rence; submits to FHWA 

FHWA concurs with Adverse Ef‐fect and submits e106 request to ACHP regarding participation. 

15 business days 

  ACHP determine if they will partic‐ipate in MOA 

Page 49: Program Operations Manual - Michigan

  47 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Section 106 Adverse Effect De‐termination Memorandum of Agreement (MOA) Section 106. (Legal Review required) 

36 CFR 800 and 23 CFR 774, En‐vironmental Procedures Manual 

As needed  MDOT & FHWA 

Prepare draft MOA; coordinate with FHWA, SHPO and ACHP, as ap‐plicable. Submit Draft to FHWA and MDOT for Le‐gal review. Pre‐pare Final MOA; secure MDOT and SHPO signatures 

Comment on Draft MOA; Coordinate with ACHP as ap‐plicable; submit draft for FHWA le‐gal review. Sign Fi‐nal and Submit to ACHP thru e106 for signature as applicable. 

Depends on Complexity; 15 days for each step. 

 

Biological Assessment (BA) for Federally listed Threaten & En‐dangered Species ‐ USFWS 

Endangered Species Act, En‐vironmental Procedures Manual 

As needed  MDOT & FHWA 

MDOT Prepares and submits BA for FHWA review. 

After review, FHWA request consultation on BA with USFWS under Section 7 and requests a Bi‐ological Opinion or BO 

USFWS has 90 days to con‐sultant on BA and 45 days to issue BO (135 days total) 

 

NEPA Administrative Record for All CE, EA and EIS 

Environmental Procedures Manual 

On‐going  MDOT & FHWA 

MDOT maintains official Adminis‐trative Record in accordance with FHWA guidelines 

FHWA maintains critical approval documents as part of the backup to the Administrative Record. 

On‐going for all NEPA ac‐tions. 

 

 

 

Page 50: Program Operations Manual - Michigan

  48 

FINANCIAL MANAGEMENT 

Overview 

Financial Management includes both stewardship and oversight of Federal‐aid Highway Program funds. Finance Management Program objectives include ensuring compliance with Federal and state require‐ments, protecting public investment, and ensuring accountability. The FHWA Michigan Division and MDOT Finance staff share a vision that the Finance Program will use innovative finance techniques and leverage information technology systems to ensure all Federal‐aid funds are used efficiently while main‐taining effective funds management and sound internal controls. Among other roles and responsibilities, the Financial Management Program oversees project authorization, obligation, reimbursement process, and final closeout for all Federal‐aid projects in Michigan.  

 

Background/History 

Within the FHWA Michigan Division, the Finance Team is under the Executive Coordination Unit. The Fi‐nance Team consists of a Financial Manager and two Financial Specialists. Within MDOT, the Financial Operations Division is under the Bureau of Finance and Administration. The key MDOT Finance contacts include Financial Operations Division Administrator and the Project Accounting and Financial Support Section Manager.  

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the Federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law Implementing Regulations 

Highways  23 USC  23 CFR 

Transportation  49 USC  49 CFR 

Surface Transportation Act  Authorization Act   

Department of Transportation Appropriations Act  Appropriations Act   

Uniform Administration Requirements, Cost Princi‐ples, and Audit Requirements for Federal Awards 

  2 CFR 200 

Federal Acquisition Regulation    48 CFR 

FHWA Risk‐Based Financial Management Oversight Program 

  FHWA Order 4560.1C – Financial Integrity Re‐view and Evaluation (FIRE) Program 

Establishment and maintaining internal controls and to annually evaluate and report on the control and fi‐nancial systems that protect the integrity of Federal programs. 

Federal Managers’ Financial Act (FMFIA) of 1982 

 

Page 51: Program Operations Manual - Michigan

  49 

Topic  Law Implementing Regulations 

Establishing and assessing internal control related to financial reporting. Preparation and audit of financial statements. 

Chief Financial Of‐ficer Act of 1990 

 

Process for transferring funds to the States  Cash Management Improvement Act (CMIA) of 1990 

 

Management’s Responsibility for Internal Controls    Office of Management and Budget (OMB) Cir‐cular A‐123 

Office of Inspector General Audit and Investigation Report Findings, Recommendations, and Follow‐up Action, establishes Office of Inspector General (OIG) reporting requirements 

  Department of Trans‐portation (DOT) Order 8000.1C 

Identification and recover of improper payment to prevent payment error, waste, fraud, and abuse.  

Payment Integrity Information Act of 2019 (PIIA); for‐merly known as IP‐ERIA 

 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Funds Management  Project Authorization and Obligation  Project Closeout  Improper Payment Testing  Single Audit Compliance  Internal Control Testing and Review  Financial Monitoring and Reporting  Financial Management System Compliance  Innovative Finance 

 

 

 

 

 

 

 

 

 

Page 52: Program Operations Manual - Michigan

  50 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

MDOT Advance Construction Guidelines  August 2018  As needed 

MDOT Subrecipient Single Audit Report Monitoring  October 2019  As needed 

MDOT SIGMA FHWA Project Obligation and Accounting  July 2017  As needed 

MDOT SIGMA Security Roles and Access  August 2020  As needed 

MDOT Guidance Document: Updating Phase Schedule End Dates for All Federally Funded Projects 

February 2016  As needed 

FHWA Project Funds Management Guide for State Grants  December 2019  As needed 

Federal‐aid Non‐Federal Matching Requirement Guidance  May 2019  As needed 

At‐Risk Project Pre‐Agreement Authority for Preliminary Engi‐neering (PE) 

April 2019  As needed 

Financial Management Improvement (FMI) Initiative Project Work Plan – In‐Kind Match Test and Evaluation  

February 2019  As needed 

Scope of Work Guidance for Federal‐aid Project Agreements in the Fiscal Management Information System (FMIS) 

October 2018  As needed 

Gordie Howe International Bridge (GHIB) In‐Kind Match Credit MOU 

February 2019  As needed 

Project Authorization of Work: Review and Approval SOP  February 2018  As needed 

Current Bill Project Billing SOP  May 2018  As needed 

FHWA Billing Review/Improper Payment Review Process SOP  May 2014  As needed 

Project Closeout SOP  April 2018  As needed 

Manual Project Billing (PR‐20) SOP  May 2018  As needed 

Fund Transfer Request Procedures SOP  August 2012  As needed 

 

 

Page 53: Program Operations Manual - Michigan

  51 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Current Bill Reimburse‐ment Requests 

23 USC 121; CMIA 

Weekly/ As Re‐quested 

Both  Submit electronically and in‐clude reason for credit transac‐tions 

Act upon within estab‐lished deadline 

Source Documentation will be randomly sam‐pled and reviewed by FHWA 

Project Authoriza‐tions/Agreement and Modifications 

23 USC 106; 23 CFR 630 Subpart A 

On‐going  Both  Prepare and submit as needed in accordance with Project Funds Management Guide for State Grants  Communicate priority project through MDOT Finance 

Review, respond, and/or act upon within 3 business day  Act on priority project within 1.5 business days 

 

Federal‐aid Billing Transaction Review 

23 USC 106  As re‐quested 

Both  Respond to requests for infor‐mation and documentation to validate Federal‐aid billing trans‐actions within 5 business days 

Provide a listing of trans‐action being reviewed. Upon completion of re‐view, provide results of re‐view 

Results used to support FMFIA, FIRE, PIIA 

State Infrastructure Bank 

23 USC 610  Annual  Both  Prepare annually report within 90 days from end of Fiscal Year; Update SIB Database by end of FY 

Review report and review and approve database submission 

 

Toll Credits  23 USC 120  Annual   Both  Update Toll Credit Database An‐nually  Calculate the amount of eligible toll credit and submit for ap‐proval 

Review and approve Toll Credit database submis‐sion  Review and approve the request as appropriate 

 

Page 54: Program Operations Manual - Michigan

  52 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Inactive Project Review  23 CFR 630  Quarterly   Both  Provide justification for inactive projects 

Review and take appropri‐ate action on project justi‐fications 

 

Fund Transfer Requests  23 USC 126, 

23 USC 

132, and 

FHWA Or‐

der 

4551.1 

As re‐quested 

Both  Prepare and submit Fund Trans‐fer Requests as needed 

Review and take appropri‐ate actions within 5 busi‐ness days 

 

MDOT (State of Michi‐gan) Single Audit 

2 CFR 500  Annual  Both  Ensure MDOT is included in the annual Statewide Single Audit and copies are submitted by June 30 every year 

Review and take action to ensure findings are re‐solved 

 

MDOT Sub‐Recipient Single Audit 

2 CFR 330, 500 

An‐nual/on‐going 

Both  Review and take action to en‐sure findings are resolved; sub‐mit summary listing to FHWA 

Review and take action to ensure compliance 

 

Apportionments, Allo‐cations, and other Funding Notices 

31 USC 

1341(a)(1)(A

) & 

(B); 31 USC 

1517(a); 

23 USC 

118(b), 23 

USC 121 

On‐going  Both  Monitor apportionment, alloca‐tions, and obligations to ensure all funding is used efficiently within each quarter and use all Obligation Authority (OA) by the end of the year 

Ensure apportionments, allocations, and funding notices are provided to MDOT in a timely manner 

 

Indirect Cost Allocation Plans (ICAP), Equip‐ment Rate, Labor Addi‐tive Rate 

2 CFR 200.400 & Appendix V, VII 

Annual  Both  Certify that the ICAP and other applicable rates were prepared in accordance with require‐ments 

Review and take appropri‐ate action in a timely man‐ner 

 

Page 55: Program Operations Manual - Michigan

  53 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Audit Coordina‐tion/FHWA Financial Statement Audit/State External Audit Re‐views/State Internal Audit Reviews 

2 CFR 200. 500 

As needed  Both  Ensure corrective action is taken to resolve audit findings 

Monitor activities to en‐sure implementation 

 

Review of MDOT’s Fi‐nancial and Pro‐ject/Program Manage‐ment System(s) 

2 CFR 200  Annual  Both  Maintain compliant systems and sound internal controls safe‐guarding funds 

Review systems and pro‐vide recommendations to MDOT 

 

Review Adequacy of Sub‐recipients Project Delivery Systems and Sufficiency of Account‐ing Controls to Manage Federal‐aid Funds 

23 USC 106; 2 CFR 330   

Annual  Both  Ensure sub‐recipients maintain adequate project delivery sys‐tems and have sufficient ac‐counting control to manage Fed‐eral‐aid funds 

Provide assistance as re‐quested in reviewing sub‐recipients project delivery systems 

 

Approval of Increased  Federal Share Agree‐ment (Sliding Scale)  

23 USC 120(b)(2) 

  Both  Prepare agreement for use of the increased Federal share and demonstrate compliance with statute and agreement  

Review agreement and take appropriate action  

 

Audit of Toll  Facility Records and  Certification of Ade‐quate  Maintenance ‐ Report  Submittal  

23 USC 129  Annual  Both  Submit reports to FHWA  Review reports and take appropriate actions 

 

Page 56: Program Operations Manual - Michigan

  54 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Highway Statistics Re‐ports (FHWA Reports 531, 532, 534, 536, 541, 542, 543, 536, 539, 562, 561, 566, 571, 556)  

23 USC 420.105; 23 CFR 1.5 

Annual  Both  Submit required reports.   

Ensure reports are submit‐ted in timely  

 

Motor Fuels Report and Oversight Review  

23 USC 420.105; 23 CFR 1.5 

Monthly/Annual 

FHWA/ Michigan Department of Treasury  

Submit required reports  Ensure reports are submit‐ted in timely  

Michigan Department of Treasury 

Review of Biennial – Toll Facilities in the United States   

23 USC 129  Every 2 years 

  Assist FHWA in conducting re‐view  

   

Heavy Vehicle Use Tax (HVUT) – Certification of  verifying proof‐of‐pay‐ment of HVUT  

23 USC 141; 23 CFR 669 

Annual  FHWA/ Michigan Department of State 

  Submit certification to FHWA HQ  

Governor or a designee (Secretary of State) must certify Michigan verifies HVUT was paid before issuing/renew‐ing registrations for heavy vehicles 

Heavy Vehicle Use Tax (HVUT) – Triennial re‐view of State program   

23 USC 141; 23 CFR 669 

Every 3 years 

FHWA / Michigan Department of State 

  Perform a review every 3 years of the State’s HVUT compliance   

Review performed with Michigan Department of State  

GHIB In‐Kind Match Credit Report 

GHIB In‐Kind Match Credit MOU 

Annual  Both  MDOT will provide an annual re‐port within 60 days of fiscal year end 

Review report and take appropriate action 

 

Page 57: Program Operations Manual - Michigan

  55 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Major Projects (total cost>$500 million) – Fi‐nancial Plans and Cost Estimates   

23 USC 106(h) 

As needed/ Annual 

Both  Prepare financial plans and cost estimates in accordance with re‐quirements. Financial plans are to be completed prior to re‐quest for authorization of Fed‐eral‐aid funds for construction   

Review and approve as appropriate   

Some Financial Plans in this category will re‐quire FHWA HQ ap‐proval   

Other Projects (total cost between $100 mil‐lion & $500 million)  – Financial Plans Pro‐ject Funds Manage‐ment  

23 USC 106(i) 

As needed/ Annual  

  Prepare financial plans in ac‐cordance requirements. Finan‐cial plans are to be completed prior to request for authoriza‐tion of Federal‐aid funds for construction  

Review financial plans as part of stewardship and oversight responsibility   

 

 

 

Page 58: Program Operations Manual - Michigan

  56 

INTELLIGENT TRANSPORTATION SYSTEMS (ITS)  

Overview 

FHWA works in cooperation with MDOT in the development and implementation of Intelligent Transpor‐tation Systems (ITS) initiatives in Michigan. MDOT has established a multi‐disciplinary ITS Steering Com‐mittee, of which FHWA is a member, to provide technical screening, strategic direction, and oversight at the program level.  

FHWA and MDOT work cooperatively with Metropolitan Planning Organizations and Rural Task Force Committees to promote ITS planning, regional architecture use, and adoption and integration of ITS at the local level. MDOT and FHWA will work cooperatively to assure that ITS projects are consistent with the national ITS architecture, incorporate ITS standards, and are fully integrated. 

FHWA and MDOT have formed partnerships in support of safety and congestion relief initiatives with other local, state, and international transportation agencies, including fire and law enforcement.  

Background/History 

MDOT has been deploying and pioneering intelligent transportation systems (ITS) since the 

1960s. Early on, the systems included loop detectors, ramp metering, dynamic message signs (DMS) (also referred to as changeable message signs, or CMS), motorist aid telephones, highway advisory radio (HAR), and closed‐circuit television (CCTV) surveillance systems. 

Today, the Program is in control of nearly 6,000 devices statewide, including over 600 CCTVs and over 200 DMSs. The diversified list of devices includes equipment for road weather information systems (RWIS), an active traffic management (ATM) corridor, microwave vehicle detection systems (MVDS), connected vehicle (CV) deployments, truck parking information and management systems (TPIMS), and communications infrastructure. These ITS devices are operated from MDOT’s three transportation oper‐ation centers (TOCs) and the Blue Water Bridge Operations Center (BWBOC) to actively monitor MDOT’s roadways and manage traffic incidents 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Regulations 

National ITS Program Plan  23 USC Code 512   

ITS Architecture and Standards    23 CFR Part 940  

Real‐Time System Management Information Program 

  23 CFR Part 511 

Autonomous Vehicle (AV) Operations  MCL 257; 2016 PA 332   

Remove AV Research and Test Only Restriction  MCL 257.665b; 2016 PA 333   

Mobility Research Centers  MCL 257.601a; 2016 PA 334   

AV Mechanic Liability  MCL 600.2949b; 2016 PA 335   

* Any approval action that FHWA has delegated to MDOT could be retained by FHWA as part of the PODI Approval Actions form. Both FHWA and MDOT should coordinate on review times to meet project schedules. 

Page 59: Program Operations Manual - Michigan

  57 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Statewide ITS Field Network and Device Maintenance  Statewide ITS Asset Management Program  Development and Maintenance of ITS Standards/Specification/Details  ITS Program Strategic Planning  ITS Capital Program Call for Projects (CFP) Process Administration  ITS Capital Template Management  ITS Operations Template Management  Regional and Statewide ITS Architecture and Deployment Plans  Systems Engineering Review/Oversight  Advanced Traffic Management System (ATMS) Software   Transportation Operations Centers (TOC) Management and Support  Freeway Courtesy Patrol Strategies and Support  Connected and Automated Vehicle (CAV) Program Administration  Inter‐Departmental Coordination (DTMB, FHWA, FAA, FCC)  Industry Participation and Leadership (AASHTO, SAE, ITE, ITS America)  Michigan Partner Support (MEDC, UMTRI, Mcity, ACM, ITS Michigan)  Public Outreach (Mi Drive Traveler Information Website)  Statewide Video Sharing System  Innovative Technology Deployment Types: 

o Active Transportation and Demand Management (ATDM) Systems o Truck Parking Information and Management System (TPIMS) o Wrong‐Way Driver Warning System o Border Wait Time Information System o Weather Responsive Traveler Information System (Wx‐TINFO) o Over‐Height Warning Systems o Integrated Corridor Management (ICM) o Connected and Autonomous Vehicles (CAV) o Curve Speed Warning System 

 

 

 

 

 

 

 

 

 

 

Page 60: Program Operations Manual - Michigan

  58 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

FHWA/MDOT Stewardship and Oversight Agreement    As needed 

MDOT ITS Strategic Plan  May, 2018  As needed 

MDOT Connected and Automated Vehicle Program (CAV) Stra‐tegic Plan 

January, 2018  As needed 

MDOT Regional ITS Architectures and Deployment Plans for: 

the Bay Region;  

the Grand Region;  

the North Region;  

the Southeast Michigan Council of Governments (SEM‐COG) including Livingston County;  

the Southwest and University regions except Living‐ston County;  

the Superior Region;  

the Grand Valley Metropolitan Council; 

and the Tri‐county Regional Planning Commission 

November, 2014  As needed 

MDOT Manuals, Guides, and System Operations Advisories (SOA) (As Applicable)  

Various  As needed 

National ITS Architecture (US DOT Research and Innovative Technology Administration – ITS Joint Program Office) 

October, 2019  As needed 

Regional ITS Architecture Guidance (FHWA/FTA)  October, 2019  As needed 

     

MDOT Transportation Systems Management & Operations (TSMO) Implementation and Strategic Plan 

January, 2020  As needed 

MDOT Active Traffic Management (ATM) Strategies and Con‐cepts Guide 

October, 2016  As needed 

 

 

Page 61: Program Operations Manual - Michigan

  59 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action 

Business Standard  Remarks 

Plans, Specifications and Estimates for major ITS and PoDI Projects 

23 CFR 630  Ongoing  MDOT  Develop‐ment 

Approve     

Plans, Specifications and Estimates for non‐major ITS and non‐PoDI Projects 

  Ongoing  MDOT  Develop‐ment 

     

Technical Assistance    Ongoing  FHWA        FHWA will provide ongoing tech‐nical assistance in the use of re‐gional ITS architectures, systems engineering analysis, and ITS standards, include these areas in routine risk assessment evalua‐tions, and work cooperatively with MDOT to use process re‐view techniques to assess and improve processes and proce‐dures. 

Steering Committees    Ongoing  MDOT/ FHWA 

      FHWA will participate in project steering committees or other ongoing oversight processes for all major ITS projects and Con‐gressionally‐ designated ITS pro‐jects. 

Page 62: Program Operations Manual - Michigan

  60 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action 

Business Standard  Remarks 

Regional Architecture    Ongoing  MDOT      MDOT will provide FHWA with copies of ITS re‐gional architectures or amendments within 30 business days of adop‐tion. If the owners of the regional architectures choose to have FHWA concur in the architec‐ture, FHWA will be al‐lowed 21 business days, from receipt date, to re‐view and act on the doc‐ument. 

 

Earmarks and Discretion‐ary Grants 

  Ongoing  MDOT/ FHWA 

    FHWA will follow pre‐scribed processing re‐quirements for ITS “ear‐mark” projects as defined in specific implementa‐tion processes issued by FHWA Headquarters for each appropriation cycle. 

Discretionary grants or earmarks (i.e., Integrated Mobile Observa‐tions program) are normally non‐construction projects and will be advanced and/or ap‐proved on a case‐by‐case basis. Typically, the projects are desig‐nated by earmark in appropria‐tions acts, or provided as part of a larger US DOT program, with specific implementation pro‐cesses issued by FHWA head‐quarters for each appropriations cycle. 

Construction Inspections  FAPG G 6042.8  Ongoing  MDOT         

Page 63: Program Operations Manual - Michigan

  61 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action 

Business Standard  Remarks 

Systems Engineering Re‐view 

  Ongoing  MDOT/ FHWA 

    MDOT will provide FHWA with copies of ITS Project Systems Engineering Doc‐uments within 30 busi‐ness days of adoption. MDOT may choose to have FHWA concur with the Systems Engineering documents, and FHWA will be allowed 21 busi‐ness days, from receipt date, to review and act on the documents. 

 

 

Page 64: Program Operations Manual - Michigan

  62 

LOCAL PUBLIC AGENCIES (LPA) 

Overview 

The MDOT Local Agency Program allows eligible Local Public Agencies (counties, cities, villages, and tribes) to partially administer Federal‐aid projects as sub‐recipients per (23 USC 106 (g)(4) and CFR 635.105(c)). LPAs are responsible for project design and construction engineering. MDOT provides over‐sight to ensure the LPA maintains compliance with all applicable Federal and State laws and require‐ments by performing project development reviews, confirms local projects are on the State Transporta‐tion Improvement Plan (STIP), requests federal obligation, advertises and awards projects, and provides limited construction oversight review and assistance.  

Background/History 

MDOT:  

Michigan has a history of sharing Federal‐aid funds with LPAs since Public Act 51 of 1951 was signed into law. Funds are shared via distributions and formulas contained within PA 51. Annually, MDOT lets ap‐proximately 500 LPA projects valued at over $350 million. 

The relationship between FHWA and MDOT has evolved over the years from prescribed full oversight to a more efficient Risk Based model. FHWA and MDOT have worked together to identify programs of high and low threats and opportunities to best manage a growing system while working within increasingly limited resources. Risk Based Stewardship and Oversight (RBSO) has helped meet the challenges of ever‐changing transportation responsibilities. 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Regulations 

Project Approval and Oversight  23 USC 106   

Standards  23 USC 109   

Management and Monitoring systems    23 CFR 500 

Design Standards for Highways    23 CFR 625 

Value Engineering    23 CFR 627 

Preconstruction Procedures    23 CFR 630 

Railroads    23 CFR 646 

Bridges, Structures, and Hydraulics    23 CFR 650 

Pedestrian and Bicycle Accommodations and Projects    23 CFR 652 

Truck Size and Weight, Route Designations – Length, Width and Weight Limitations 

  23 CFR 658 

Indian Reservation Road Bridge Program    23 CFR 661 

Project End Date    2 CFR 200 

Qualification Based Consultant Selection    23 CFR 172 

State Trunk Line Highway System  MCL 247  PA 51 of 1951 

Amendment to Act 51 ‐ warranties    PA 175 of 2015 

Page 65: Program Operations Manual - Michigan

  63 

Key Program Areas 

These are the key program areas within the program or related to the program. 

Planning Program  Design Program  Construction Program  Finance Program  Real Estate Program  Environmental Program  Consultant Procurement Program  Civil Rights Program  Innovative Contracting Program 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if applicable) 

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

AASHTO: A Policy on Geometric Design of Highways and Streets  Seventh Edition  As needed 

AASHTO Standard Specifications for Highway Bridges  Seventeenth Ed.  As needed 

AASHTO LRFD Bridge Design Specifications  Eighth Edition  As needed 

AASHTO LRFD Bridge Construction Specifications  Fourth Edition  As needed 

MDOT LAP Development Manual/Website  Varies/Electronic  As needed 

MDOT Road Design Manual  Varies/Electronic  As needed 

MDOT Bridge Design Manual  Varies  As needed 

MDOT Bridge Design Guides  Varies/Electronic  As needed 

MDOT Standard Specifications for Construction  2020  As needed 

MDOT Standard Plans  Varies  As needed 

MDOT Special Details  Varies  As needed 

MDOT Drainage Manual  January 2006  As needed 

MDOT Geotechnical Manual  December 2018  As needed 

MDOT Construction Manual  Varies/Electronic  As needed 

MDOT Density Testing and Inspection Manual  2003 Revised November 2018 

As needed 

MDOT HMA Production Manual  January 2020  As needed 

MDOT Materials Quality Assurance Procedures (MQAP) Manual  October 2019  Annual 

MDOT Materials Source Guide  March 2020  Bi‐Annual 

MDOT Soil Erosion and Sedimentation Control Manual   April 2006  As needed 

MDOT Work Zone Safety & Mobility Manual  2018  As needed 

MMUTCD Part 6  September 2013  As needed 

MDOT Field Manual for Pile Welding  September 2012  As needed 

MDOT Field Manual for Structural Bolting  April 2014  As needed 

 

Page 66: Program Operations Manual - Michigan

  64 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by ac‐tivity and provides information about the relative responsibilities for both FHWA and MDOT. For addi‐tional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement. Although there are many activities that are listed as MDOT responsibility, MDOT is encouraged to seek FHWA guidance when questions arise. 

Activity – Including SOA Activities Schedule/ Frequency 

Responsible Agency 

MDOT Action FHWA Action See (4) 

LPA Oversight  Ongoing  MDOT     

Grade Inspection  Ongoing   MDOT     

NEPA clearance  Ongoing  FHWA  See (1)  See (1) 

ROW certification  Ongoing  MDOT     

PS&E Approval  Ongoing  MDOT  See (2)  See (2) 

Authorization/Obligation  Ongoing  FHWA  To request   To approve 

Advertising/Award  Ongoing  MDOT     

Construction Oversight  Ongoing  MDOT  See (2)  See (2) 

Final Closeout and Acceptance  Ongoing  MDOT     

Contract Modifications  As Needed  MDOT  See (2)  See (2) 

Specification Review and Approval  As Needed  MDOT  See (3)  See (3) 

Third Party Agreement Review  As Needed  MDOT     

Guideline/Manual Updates  As Needed  MDOT  Prepare and recom‐mend for approval 

Concur in approval 

Consultant Contract Selection   As Needed  MDOT     

Design Standard Exceptions  As Needed  MDOT     

(1) Categorical Exclusion to be approved by MDOT through Programmatic Agreement. EA or EIS to be approved by FHWA. 

(2) MDOT to conduct/approve unless identified on Project of Division Interest (PoDI) Action Plan as a FHWA conduct/approval. 

(3) MDOT to conduct/approve unless controversial or other reason to seek FHWA review, com‐ment, approval. 

(4) Topics of a sensitive nature may necessitate FHWA review and approval regardless of whether FHWA is required to take action. 

 

 

Page 67: Program Operations Manual - Michigan

  65 

MAINTENANCE AND PRESERVATION  

 Overview 

Title 23 USC defines maintenance as, “…the preservation of the entire highway, including surface, shoul‐ders, roadsides, structures, and such traffic‐control devices as are necessary for safe and efficient utiliza‐tion of the highway.” Title 23 further requires a state transportation department to maintain each pro‐ject constructed with Federal aid funds until such time that it no longer constitutes a part of the Federal aid system. FHWA is responsible for ensuring that maintenance of Federal aid projects is adequate and providing technical assistance in disseminating information on successful maintenance techniques.  

Routine maintenance is not eligible for Federal aid funds. Preventive maintenance activities are eligible for Federal aid funds provided MDOT demonstrates to FHWA satisfaction that the activity is a cost‐effec‐tive means of extending the useful life of a Federal aid highway.  

This section of the Agreement pertains to maintenance activities and the management of maintenance activities that are required to be accomplished by MDOT (or caused to be accomplished by MDOT) to fulfill its obligation under Title 23. 

 

Background/History 

As a condition of receipt of federal funds, MDOT is required to maintain or cause to be maintained, the federally funded roadways and associated appurtenances in the state of Michigan. FHWA will review road and bridge maintenance through a sampling of field observations, process reviews, program re‐views, and Quality Improvement Reviews. Any specific instances of inadequate maintenance or concerns regarding MDOT’s overall maintenance program will be brought to the attention of MDOT by FHWA. 

MDOT is directly responsible for the performance of maintenance operations for 20 counties. Mainte‐nance operations for the remaining 63 counties are performed by the respective counties under con‐tract by MDOT. The contract oversight is the responsibility of the regions to ensure that maintenance operations are adequate for preservation of the National Highway System and projects constructed with Federal aid funds. 

There are no reporting or approval actions associated with maintenance activities or the management of maintenance activities that are required to be accomplished by MDOT (or caused to be accomplished by MDOT). 

Preventive Maintenance eligibility determinations will be made by FHWA. MDOT demonstrates that pre‐ventive maintenance is a cost‐effective means of extending the useful life of the system and therefore eligibility for Federal aid funds through the application of the MDOT asset management program and the guidelines established in the Capital Preventive Maintenance Manual. 

FHWA approval is not required on a project level for maintenance activities unless special or unusual cir‐cumstances exist. The maintenance agreement, which is part of the project agreement, is a project‐level agreement in which MDOT agrees to maintain the constructed facility. 

 

Page 68: Program Operations Manual - Michigan

  66 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law  Implementing Regulations 

Maintenance  23 USC 116   

Maintenance    23 CFR 1.27  

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Interstate: FHWA/MDOT/Locals  State Highways: FHWA/MDOT/Locals  Local Highways: MDOT/Locals 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

FHWA/MDOT Stewardship and Oversight Agreement     

MDOT Local Agency Programs Guidance on Roadway Preven‐tive Maintenance Projects 

   

MDOT CPM Manual     

 

 

Page 69: Program Operations Manual - Michigan

  67 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action 

FHWA may assess MDOT’s Preventive Maintenance Program through construction inspections on FHWA oversight projects, as well as process reviews. 

23 CFR 1.27  Ongoing  MDOT  Develop and Deliver 

As Needed Process Re‐views 

FHWA may assess the cost effectiveness of the Preventive Maintenance Program at extending the life of the system through periodic review of MDOT’s asset management program. 

23 CFR 1.27  Ongoing  MDOT  Monitor and Manage 

As Needed Process Re‐views 

Changes to MDOT’s Capital Preventive Manual (CPM) Manual  23 CFR 1.27  As Needed  MDOT  Develop and Im‐plement 

Review and Approve 

Local Agency Preventive Maintenance Guidelines    Ongoing  MDOT  Develop/Up‐date and imple‐ment 

Review and make recom‐mendations for considera‐tion (as necessary) 

FHWA may inform MDOT of instances of inadequate maintenance or concerns of MDOT’s overall maintenance program. 

23 CFR 1.27  As Needed  MDOT    Inform MDOT as necessary 

MDOT shall advise the FHWA of any major updates or changes to the MDOT maintenance program, or significant maintenance policy changes. 

23 CFR 1.27  As Needed  MDOT  Monitor and Re‐port 

Assess and Respond as Necessary 

FHWA will review and respond within 30 business days to MDOT for sub‐stantive changes to the Capital Preventive Maintenance Manual. 

23 CFR 1.27  As Needed  MDOT  Identify, De‐velop, and Re‐port 

Review and Respond 

Local Agency Preventive Maintenance guidelines are periodically re‐viewed by FHWA 

  As Needed  MDOT    As Needed, Review and Report 

Project Level Approvals – Project‐level changes to CPM Manual on FHWA Oversight Projects 

23 CFR 1.27  As Needed  MDOT  Develop and Deliver 

Review and Approve 

Project Level Approvals – Non‐FHWA Oversight Projects    As Needed  MDOT  Approve, De‐velop, Deliver 

No Action Needed 

Project Level Approvals – Non‐Standard, Pilot or Experimental Projects  23 CFR 1.27  As Needed  MDOT  Develop and Deliver 

Review and Approve 

 

Page 70: Program Operations Manual - Michigan

  68 

OPERATIONS  

Overview 

Traffic Operations is a cross‐functional program area that considers a variety of elements of the highway program. Traffic Operations contributes to project planning, development, and delivery through engi‐neering analysis of freight, vehicle, pedestrian, bicyclist, and other modal movements that are needed to produce sound project‐level decisions affecting safe and efficient highway and non‐motorist operations. The Traffic Operations program supports operations of highway facilities by providing operational tech‐niques, procedures, processes, guidance, and data analysis.  

 

Background/History 

Within the MDOT Division of Transportation Systems Management and Operations (TSMO), the Conges‐tion and Reliability Unit manages one funding template (recently combined the Freeway and Non‐Free‐way operations templates):  The Operations template ($50 M/yr.). This template provides funding for an integrated program to optimize the performance of existing infrastructure by implementing systems, services, and projects to maximize capacity and improve the safety and reliability of the transportation system. MDOT Regions and TSCs submit candidate projects to be scored in competition with other pro‐jects by MDOT’s Operations Selection team, which is composed of people from various central office dis‐ciplines and multiple regions. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Implementing Regulations 

Interstate and non‐interstate NHS travel time reliability measures  23 CFR 490.105 

Level of Travel Time Reliability  23 CFR 490.511 

Truck Travel Time Reliability Index  23 CFR 490.211 and 490.513 

National Performance Management Research Data Set  23 CFR 490.609 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Traffic and Safety Program   ITS Program  Signals Program   CMAQ program  Traffic Incident Management 

Page 71: Program Operations Manual - Michigan

  69 

Approved Procedures, Agreements, and Manuals  

FHWA will conduct routine project and final inspections of Traffic Operations aspects on FHWA Oversight projects. For all other projects, FHWA may conduct process reviews.  

FHWA will conduct routine evaluation of the maintenance of traffic on active Federal aid pro‐jects to assure Traffic Operations components are being adequately maintained.  

FHWA will provide ongoing technical assistance in Traffic Operations, will include this area in routine risk assessment evaluations, and will work cooperatively with MDOT to use process re‐views to assess and improve processes and procedures.  

 

Procedure, Agreement, Manuals Latest Approval Date/ Version (if applicable) 

Anticipated due date (if applicable) 

Electronic Traffic Control Device Guidelines  11/29/2017  As needed 

MDOT VISSIM Protocol – v1.0  1/2/2020  As needed 

Operations Project Submittal Manual – v2.3  2/19/2020  As needed 

 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by ac‐tivity and provides information about the relative responsibilities for both FHWA and MDOT. For addi‐tional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

 

Activity Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action 

Business Standard 

Report Travel Time Reliability Performance Measures 

2 and 4 yr cycles 

MDOT  Prepare and Approve 

   

Call for Projects project selection 

Annual  MDOT  Prepare and Approve 

   

Interchange/Access Modification 

As Needed  MDOT  Prepare and Submit 

Approve  Response Times from date of for‐mal request: Division Approvals only: 30 days HQ Approvals: 45 days   

 

 

Page 72: Program Operations Manual - Michigan

  70 

PAVEMENT AND MATERIALS 

Overview 

Pavements: 23 CFR 626 requires that pavements be designed in accordance with current and predicted traffic needs in a safe, durable, and cost‐effective manner. The regulations do not specify the proce‐dures to be followed to meet this requirement. MDOT is expected to use an appropriate design proce‐dure.  

Materials: Subsection (a) of 23 USC 109 requires that the FHWA ensure that the plans and specifications for all proposed Federal aid highway projects provide for facilities that will adequately serve the existing and planned future traffic in a manner that is conducive to safety, durability, and economy of mainte‐nance. To fulfill this requirement for all Federal aid highway projects, the FHWA Michigan Division Office prime objectives are to:  

Maintain a close working relationship with MDOT pavement management and design, mate‐rials, and construction staff.  

Promote improvements when new approaches or technologies are developed and where deficiencies are identified.  

Using a risk‐based approach, ensure that the materials incorporated in the construction work are of sufficient quality to help ensure the final product performs and provides the ex‐pected service life to the public. 

 

Background/History 

FHWA is required, by means of an approved quality assurance program, to assure the quality of materi‐als incorporated into Federal aid highway projects on the NHS. For Federal aid projects on the NHS, FHWA uses a risk‐based approach to:  

Ensure that the materials incorporated in the construction work, and the construction oper‐ations controlled by sampling and testing, are in conformity with the approved plans and specifications.  

Provide oversight of construction materials and compliance with federal requirements on a statewide basis.  

Ensure adequate and qualified staff to maintain MDOT’s Quality Assurance responsibility as part of its Acceptance Program.  

Ensure adequate and qualified staff to maintain MDOT’s Independent Assurance responsibil‐ity as part of its Acceptance Program.  

Ensure compliance with, and assist in, maintaining the MDOT Laboratory and Technician Qualification Program. 

 

 

 

Page 73: Program Operations Manual - Michigan

  71 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law Implementing Regulations 

Project Approval and Oversight  23 USC 106   

Standards  23 USC 109   

Construction  23 USC 114   

Management and Monitoring systems    23 CFR 500 

Design Standards for Highways    23 CFR 625 

Pavements    23 CFR 626 

Construction and Maintenance    23 CFR 635 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Hot Mix Asphalt (HMA)  Portland Cement Concrete  Aggregates  Laboratory and Technician Qualification  Warranties  Buy America 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/ Version (if applicable) 

FHWA/MDOT Stewardship and Oversight Agreement  2015 

MDOT Pavement Selection Manual  2019 

MDOT HMA Production Manual  2020 

MDOT Procedures for Aggregates Inspection  2019 

MDOT Quality Assurance Procedures Manual (MQAPM)  2019 

MDOT Specifications (2012)  2012 

MDOT Standard Plans   

MDOT Special Details   

MDOT Drainage Manual   

MDOT Soils Manual   

 

 

Page 74: Program Operations Manual - Michigan

  72 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement. 

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Business Standard 

All NHS ‐ Quality Assurance Program Acceptance Require‐ments, Materials test methods, Field Sampling and Testing 

23 CFR 637.205  Ongoing  MDOT  Develop, Main‐tain, and Imple‐ment  

Review and Report   

Non‐NHS ‐ Quality Assurance Program Acceptance Re‐quirements, Materials test methods, Field Sampling and Testing 

23 CFR 637.205  Ongoing  MDOT  Develop, Main‐tain, and Imple‐ment 

Review, report and make recommendations as neces‐sary 

 

All NHS & Non‐NHS ‐ Buy America Provisions and Waivers  23 CFR 635.410  Ongoing  MDOT  Implement Reg‐ulation 

Review and assist   

All NHS ‐ Laboratory and Technician Certification Pro‐grams. Assure Central Laboratory accredited by AASHTO Accreditation Program or FHWA approved comparable program. Assure Non‐STD designated lab used in dispute resolution accredited by AASHTO Accreditation Program or FHWA approved comparable program. 

23 CFR 637.209  As Needed  MDOT  Develop and im‐plement 

Review, report and make recommendations as neces‐sary 

 

Non‐NHS ‐ Laboratory and Technician Certification Pro‐grams 

23 CFR 637.209  As Needed  MDOT  Develop and im‐plement 

No Action   

All NHS ‐ Material or Product Selection: proprietary prod‐ucts, recycled materials, public interest findings (23 CFR 635.411) 

23 CFR 637.205  Ongoing  MDOT  Evaluate and Accept 

Review on FHWA Oversight projects only 

 

Non‐NHS ‐ Material or Product Selection: proprietary products, recycled materials, public interest findings (23 CFR 635.411) 

23 CFR 637.205  Ongoing  MDOT  Evaluate and Accept 

No Action   

Program Approval Actions – when significant changes are made to the Acceptance Program 

23 CFR 637.205  As Needed  MDOT  Develop and Prepare 

Approve ‐ FHWA will review and respond to MDOT for substantive changes in its Acceptance Program. 

NHS & non‐NHS 

Page 75: Program Operations Manual - Michigan

  73 

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Business Standard 

Program Approval Actions – MDOT Standard Specification  23 CFR 625.3  As Needed  MDOT  Develop and Prepare 

Approve  NHS & non‐NHS 

Program Approval Actions – MDOT Supplemental Specifi‐cations and Frequently Used Special Provisions 

23 CFR 625.3  As Needed  MDOT  Develop and Prepare 

Approve  NHS & non‐NHS 

Project Approval Actions ‐ Changes in Project Specifica‐tions for Materials on FHWA Oversight Projects 

23 CFR 625.3  As Needed  MDOT  Develop and Prepare 

Approve  NHS & non‐NHS 

Project Approval Actions – Project Specific Special Provi‐sions on FHWA Oversight Projects 

23 CFR 625.3  As Needed  MDOT  Develop and Prepare 

Approve  NHS & non‐NHS 

Project Approval Actions – Final Inspection/Acceptance and Certification Report on FHWA Oversight Projects 

23 CFR 625.3  As Needed  MDOT  Develop and Prepare 

Approve  NHS & non‐NHS 

Program Monitoring – Acceptance Program  23 CFR 637.205  As Needed  MDOT  Develop and Im‐plement 

FHWA may monitor MDOT’s Acceptance Program through construction inspec‐tions on FHWA oversight projects, as well as through process reviews. 

 

Program Monitoring – Materials Testing and Acceptance  23 CFR 637.205  As Needed  MDOT  Develop and Im‐plement 

FHWA may monitor the ac‐ceptance and testing of ma‐terials in accordance with MDOT’s Construction and Material Specifications and the MDOT Quality Assurance Procedures Manual on Fed‐eral aid projects through construction inspections and process reviews. 

 

Program Monitoring – Acceptance Programs Independent Assurance Activities 

23 CFR 637.207  Annually  MDOT  Develop, Imple‐ment, and will report annually to FHWA. 

Review and monitor   

 

 

Page 76: Program Operations Manual - Michigan

  74 

PLANNING 

Overview 

Transportation planning plays a fundamental role in a state, region, or community’s vision for its future. It includes a comprehensive consideration of possible strategies; an evaluation process that encom‐passes diverse viewpoints; the collaborative participation of relevant transportation‐related agencies and organizations; and open, timely, and meaningful public involvement. 

Transportation planning is a cooperative process designed to foster involvement by all users of the sys‐tem, such as businesses, community groups, environmental organizations, the traveling public, freight operators, and the general public, through a proactive public participation process. 

 

Background/History 

The MDOT Bureau of Transportation Planning (BTP) is divided into three distinct divisions. The Statewide Transportation Planning Division is charged with the MPO coordination, the MDOT Trunkline Call for Projects, and transportation demand modeling and several other duties. The Data Inventory and Inte‐gration Division handles traffic counting, HPMS, GIS and many additional duties. The Policy and Asset Management Division covers transportation policy development and review, asset management, and non‐motorized planning among their activities. The BTP works together to ensure that all federal and state regulations regarding planning are followed to maintain federal aid eligibility. 

Note that the air quality/CMAQ and asset management programs each have their own program over‐sight manuals.  

 

Applicable Laws, Regulations, and Orders 

 

Topic  Law Implementing Regulations 

Statewide and non‐metropolitan planning  23 USC 135  23 CFR 450.200 

Metropolitan planning  23 USC 134  23 CFR 450.300 

Environmental Justice  Executive Order 12898   

Transportation performance management  23 USC 150  23 CFR 490 

Freight planning  23 USC 167, 23 USC 117   

Traffic monitoring    23 CFR 500 

Certification of public road mileage  23 USC 402(c)  23 CFR 460 

MIRE fundamental data elements    23 CFR 924.17 

      

Page 77: Program Operations Manual - Michigan

  75 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Work Programs for SPR and MPO UPWPs  Statewide Planning including STIP and the State Long Range Plan  Metropolitan Planning including TIP and Metropolitan Long‐Range Plans  Traffic monitoring   Highway Performance Monitoring System (HPMS)  Certification of Public Road Mileage  Federal Aid Highway Systems  Transportation Performance Measures (TPM)  Pavement condition forecasting  MDOT Trunkline Call for Projects  Transportation demand modeling  Geographic Information Systems (GIS)  Federal aid management and distribution  Bike and pedestrian planning  Freight planning  Transportation policy development  Transportation Asset Management Plan (TAMP)  Model Inventory Road Elements (MIRE) Data Collection 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/ Version (if applicable) 

Anticipated due date (if applicable) 

JobNet web‐based STIP management program  Ongoing updates  As needed 

General Program Accounts Guidance Document  June 7, 2018  As needed 

Planning agreements between MDOT and MPOs  dates vary  As needed 

Redesigned TIP Amendment process  May 14, 2018  As needed 

 

 

Page 78: Program Operations Manual - Michigan

  76 

Project and Program Monitoring and Approval Chart 

Additional detail can be found in Appendix B of the Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Planning funds distribution formula 

23 CFR 420.109  As needed  MDOT  Develop formula.  Approval.  Not applicable.   

State public involvement procedures 

23 CFR 450.210  As needed  MDOT  Develop proce‐dures. 

Review.  Not applicable.   

Consultation process for non‐metropolitan local offi‐cials.  

23 CFR 450.210  As needed  MDOT  Develop proce‐dures.  

Receipt of pro‐cedures.  

Not applicable.   Provided to FHWA for infor‐mational pur‐poses. 

Statewide long‐range trans‐portation plan. 

23 CFR 450.216  As needed  MDOT  Develop plan.  Review for compliance. 

Not applicable.   

Statewide Transportation Improvement Program up‐date. 

23 CFR 450.218; 23 CFR 450.220; 23 USC 135(g) 

At least every 4 years 

MDOT and MPOs 

Develop STIP for non‐metro areas. Include TIPs by reference for metro areas.  

Review and ap‐prove STIP and TIPs (with FTA). 

Not applicable.    

STIP/TIP amendments.  23 CFR 450.220  As needed.  MDOT and MPOs 

Review proposed amendments.  

Amendment approval. 

7 business days re‐view period except when there is a con‐formity demonstra‐tion.  

 

Finding of consistency of planning process 

23 CFR 450.220  Concurrent with STIP approval 

MDOT and MPOs 

Submittal of STIP/TIP 

Develop plan‐ning finding with FTA 

Not applicable.   

SPR part I work program de‐velopment 

23 CFR 420  Annual  MDOT  Develop and sub‐mit work pro‐gram to FHWA Division. 

FHWA Division reviews/ap‐proves. 

Work program ap‐proved prior to start of upcoming FY. 

 

Page 79: Program Operations Manual - Michigan

  77 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

MPO Work programs devel‐opment 

23 CFR 420  Annual  MPOs  MDOT review and submittal to FHWA Division. 

FHWA Division reviews/ap‐proves. 

Work programs are approved prior to start of upcoming FY. 

 

MPO work program perfor‐mance reports 

23 CFR 420.117  Annual   MDOT with MPOs 

MDOT submittal to FHWA 

FHWA is just in receipt of re‐port. 

Reports are due 90 days after end of FY for annual report. 

Annual unless deemed neces‐sary more fre‐quently. 

Metropolitan planning area boundary. 

23 CFR 450.312  As needed  MPOs in co‐operation with MDOT 

Boundary files provided to FHWA HQ 

Provided to FHWA for in‐formational purposes. 

Not applicable.   

MPO designation and re‐designation 

23 CFR 450.310  As needed  MPO  No action re‐quired.  

No action re‐quired.  

Not applicable.   Agreement re‐quired between Governor and lo‐cal governments   

Metropolitan Transporta‐tion Plan updates and amendments 

23 CFR 450.324  MTP up‐dates: at least every 4 yrs in non‐attainment and mainte‐nance areas; every 5 yrs in attain‐ment areas 

MPO  Review and sub‐mit to FHWA/FTA. 

Review/ap‐proval with FTA.  

Not applicable.   

Revision of highway func‐tional classification 

23 CFR 470.105  As needed  MDOT  Manage process.   Review/ap‐proval of changes.  

Not applicable.    

Urban area boundaries  23 CFR 470.105  As needed  MDOT  Manage process.   Review/ap‐proval.  

Not applicable.   

 

 

Page 80: Program Operations Manual - Michigan

  78 

REAL ESTATE 

Overview 

Real Estate activities ensure that necessary property rights are uniformly acquired for MDOT to certify legal and physical possession of all Right‐of‐Way (ROW) required for construction of transportation pro‐jects and management of property interests. MDOT is also responsible for ensuring local agencies meet Federal aid requirements prior to ROW certification. Real Estate activities also include project develop‐ment, real property management and outdoor advertising. 

Real Property Acquisition 

Real property transactions for acquiring permanent (fee, easement) and temporary (consent) property rights for Federal aid projects involve unique processes:  

Authority to begin real property acquisition   Process for acquiring real property (Uniform Act)  ROW Certification  

FHWA and MDOT approval activities are related to the business process rather than the type of high‐way, i.e. ‐ Interstate system, National Highway System (NHS), and non‐NHS. The activities relating to real property acquisition are under full MDOT oversight. MDOT is responsible to assure local agency compli‐ance with all requirements of state and federal laws, regulations and policies related to real property acquisitions. 

Project Development 

Early acquisition, Federal reimbursement for hardship acquisition and protective buying, and functional replacements, require prior FHWA approval for all Federal Aid projects.  

Real Property Management 

Property management activities in the Interstate Limited Access ROW including all disposal, uses or changes in access control, require FHWA prior approval. Disposal of property rights purchased with Fed‐eral aid funds for less than fair market value, federal land transfer, and relinquishment of Federal aid fa‐cilities also require FHWA prior approval.  

Highway Beautification/Outdoor Advertising 

The administration of the Highway Advertising Program by MDOT is mandated by Highway Advertising Act, Public Act (PA) 106 of 1972, as amended and is the responsibility of the Utility Coordination, Permits and Agreements Section. This administration includes the responsibility for: 

Generate annual renewal notifications, process permit applications, notify sign owners of viola‐tions, track violations 

Represent the department at formal administrative hearings  Assess and recommend solutions to resolve highly political matters  Serve as the department’s statewide highway advertising program liaison with various depart‐

ment divisions, regions and TSC’s, legislators, billboard industry, local municipalities and the general public regarding the department’s highway advertising program’s state law, federal law and regulations, policies and procedures 

Manage, develop and prepare guidance materials for the statewide billboard inventory  Interpret existing and proposed laws, policies, and procedures, and make recommendations as 

they relate and/or impact the highway advertising program 

Page 81: Program Operations Manual - Michigan

  79 

Analyze the overall program operations: o Independently conduct surveys or special studies to determine the needs of the highway 

advertising program o Lead in planning, evaluation and implementation of program improvements and changes o Implement modifications to policies and procedures to achieve greater efficiency and effec‐

tiveness  Evaluate documents, statute, and procedures to assess structure of the statewide program  Maintain the billboard GIS database, which includes updating points with permit changes (new 

permits, cancelations, new owners); communicate with the GIS team on updates (new layers, update fields, improvements for a more user‐friendly map) 

Junkyard Control and Acquisition 

MDOT has the responsibility to control junkyards within 1000 feet of the nearest edge of the state high‐way right‐of‐way, primary or secondary highway as stipulated in Title 23 USC 136, Title 23 CFR 751.1 to 751.25, and Control of Junkyards Adjacent to Highways, Public Act (PA) 219 of 1966, as amended. How‐ever, due to a lack of federal beautification funds, an active screening or acquisition program is not in effect. 

According to PA 219 of 1966, permits are required for the following: 

All junkyards established after July 11, 1966, adjacent to Interstate and primary highways  Junkyards established after January 1, 1973, adjacent to secondary highways  The contiguous expansion of both nonconforming and legally permitted junkyards  Junkyards being reestablished after losing nonconforming status. These junkyards shall be con‐

sidered new junkyards  All new or expanded junkyards adjacent to state highway Right‐of‐Way or county primary road 

right‐of‐way 

 

Background/History 

FHWA, in coordination with MDOT, revisited activities that could be delegated back to MDOT per 23 USC 106. Changes in the delegation of authority to MDOT for certain ROW Program activities, previously re‐tained by FHWA within the 2015 SOA and POM, are outlined here. All changes have been included in the FHWA approved MDOT Real Estate Procedures Manual. 

ROW Certification (23 CFR 635 Subpart C): 

Conditional ROW Certification feasibility/practicality ‐ MDOT is responsible for determining the feasibility/practicability for allowing authorization of construction prior to completion of ROW clearance, utility, and railroad work. FHWA retains approval for designated PoDI Projects.  

Public Interest Finding for Conditional ROW Certification ‐ MDOT is responsible for preparing the Public Interest Finding on whether they can proceed with bid advertisement prior to completion of ROW acquisition/relocation activities.  FHWA retains approval for designated PoDI Projects. MDOT will be responsible for determining compliance with the provisions stated in 23 CFR 635.309(c)(3).  

Conditional ROW Certification Approval ‐ MDOT is responsible for approving conditional Certifi‐cation Acceptance for Federal‐aid projects (except as specified in the project PoDI Agreement) where the ROW has not been cleared/certified prior to the authorization and/or award of a con‐struction project.  

Page 82: Program Operations Manual - Michigan

  80 

o MDOT is responsible for providing appropriate notification in the bid proposals identifying the ROW clearance status and required construction coordination.  

o MDOT is responsible for costs associated with contractor delay/claims if MDOT is unable to comply with the tract provisions as specified in the bid proposal (as amended).  

Real Property Management ‐ Use and Change of Access Control (23 CFR 710 Subpart D):  

Disposal of Property Rights ‐ MDOT is responsible for approving disposal at fair market value of federally funded right‐of‐way, including disposals of access control; FHWA retains approval for all Interstates within the approved ROW limits. MDOT will request FHWA’s concurrence on con‐troversial non‐Interstate disposals, including disposals of access control.  

Non‐Interstate Use Agreements ‐ MDOT is responsible for approving non‐highway use and occu‐pancy agreements federally funded right‐of‐way for non‐Interstate. FHWA retains approval for Interstates within the approved ROW limits. MDOT will request FHWA’s concurrence on contro‐versial non‐Interstate proposed use and occupancy.  

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

Topic  Law  Implementing Regulations 

Project Approval and Oversight  23 USC 106   

Acquisition of rights‐of‐way‐ Interstate System  23 USC 107   

Advance Acquisition of Real Property  23 USC 108   

Standards  23 USC 109   

Agreements Relating to Use of and Access to Right‐of‐Way – Interstate System 

23 USC 111   

Control of Outdoor Advertising  23 USC 131  23 CFR 750 

Donations and Credits  23 USC 323   

Uniform Relocation Assistance and Real Property  Acquisition Policies Act of 1970, as amended 

42 USC 4601   

Right of Way    23 CFR 1.23 

Relinquishment of Highway Facilities    23 CFR Part 620, Subpart B 

Project Authorization and Agreements    23 CFR 630, Subpart A (630.102‐112) 

Physical Construction Authorization    23 CFR 635, Subpart C  

Accommodation of Utilities    23 CFR Part 645, Subpart B 

Railroad‐Highway Projects    23 CFR Part 646, Subpart B 

Right‐of‐Way and Real Estate    23 CFR Part 710 

Highway Beautification    23 CFR 750 

Junkyard Control and Acquisition    23 CFR 751 

Uniform Administrative Requirement for Grants and Co‐operative Agreements to State and Local Governments 

  49 CFR Part 18 

Uniform Relocation Assistance and Real Property Acqui‐sition for Federal and Federally‐Assisted Programs 

  49 CFR Part 24, Subpart G Certification 

 

Page 83: Program Operations Manual - Michigan

  81 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Acquisition  Appraisal  Demolition  Disposal of Real Property Interests  Program Management  Property Management  Relocation  Outdoor Advertising  Junkyard Control  Utility Accommodation 

 

Approved Procedures, Agreements, and Manuals  

Procedure, Agreement, Manuals  Latest Approval Date/Version 

Anticipated due date 

MDOT Real Estate Procedure Manual  08/23/2018  Every 5 years thereafter 

MDOT Highway Advertising Procedure and Desk Operating Manual  2018  As needed 

MDOT Outdoor Advertising Enforcement Procedures  2020  As needed 

 

MDOT Real Estate Procedure Manual:  

MDOT is responsible for maintaining a manual describing its Real Estate organization, policies and procedures. MDOT functions and procedures shall be described for all phases of the real estate program, including appraisal and appraisal review, waiver valuation, negotiation and emi‐nent domain, property management, relocation assistance, administrative settlements, legal settlements and oversight of subgrantees (local agencies) and contractors. 

Changes to the manual will be made on an annual basis or on an interim basis if significant changes, e.g. new regulations or corrective actions mandate a change. Changes based on new FHWA requirements or changes in state law, etc., will be sent to FHWA for approval. Manual up‐dates involving grammar and language clarity revisions will be sent to FHWA for informational purposes and do not require FHWA approval.  

In accordance with 23 CFR 710.201(c), MDOT’s Chief Operation Officer shall certify to the FHWA every five years after August 23, 2018, that the Real Estate Procedure Manual conforms to exist‐ing practices and contains necessary procedures to ensure compliance with federal and state real estate laws and regulation.  

MDOT Highway Advertising Procedure and Desk Operating Manual:  

This procedure manual is formally revised or updated as federal or state statutes and regula‐tions change. Revisions require FHWA approval prior to implementation.  

 

Page 84: Program Operations Manual - Michigan

  82 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action  Business Standard 

Remarks 

Determine feasibility/practicability for al‐lowing authorization of construction prior to completion of ROW clearance, utility, and railroad work (Conditional Right‐of‐Way Certification) 

23 CFR 635.309(b) 

As needed  MDOT  Approve  Approve – desig‐nated PODI pro‐

jects only 

ROW Certifi‐cation 

FHWA retains ap‐proval for desig‐nated PODI pro‐

jects  

Prepare public interest finding for MDOT to proceed with bid advertisement prior to completion of ROW acquisition/reloca‐tion activities  

23 CFR 635.309(c)(3) 

As needed  MDOT  Approve  Approve ‐ desig‐nated PODI pro‐

jects only 

ROW Certifi‐cation 

FHWA retains ap‐proval for desig‐nated PoDI pro‐

jects 

Ensure compliant ROW certificate is in place 

23 CFR 635.309(c) 

As needed  MDOT  Approve  Approve ‐ desig‐nated PODI pro‐

jects only 

ROW Certifi‐cation 

FHWA retains ap‐proval for desig‐nated PoDI pro‐

jects 

Approve Hardship and Protective Buying  23 CFR 710.503  As needed  FHWA  Request  Review, Approve, Authorize 

Hardship Ac‐quisition and Protective Buying 

This action cannot be delegated to 

the State 

Approve Interstate Real Property Interest Use Agreements for non‐highway use and occupancy (which are not covered by Utility Accommodation Policy per 23 CFR 645) 

23 CFR 710.405  As needed  FHWA  Request  Review, Approve, Authorize 

Interstate Use Agree‐ments 

This action cannot be delegated to 

the State 

Page 85: Program Operations Manual - Michigan

  83 

Activity  Reference  Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action  Business Standard 

Remarks 

Approve Non‐Interstate, including all lim‐ited access ROW for non‐highway use and occupancy 

23 CFR 1.23(c)  As needed  MDOT  Approve  Concurrence ‐ controversial non‐Interstate proposed use and occupancy 

Non‐Inter‐state Use 

Agreements 

FHWA can be re‐quested to concur or even approve controversial pro‐posed uses espe‐cially for non‐In‐terstate LA ROW.  

Approve disposal at less than fair market value of federally funded right‐of‐way, in‐cluding disposals of access control 

23 U.S.C. 156  As needed  FHWA  Request  Review, Approve  Disposal of Property Rights 

This action cannot be delegate to the 

State 

Approve disposal at fair market value of federally funded right‐of‐way, including disposals of access control 

23 CFR 710.409  As needed  MDOT  Approve‐

Non‐In‐

terstate 

Approve – all within Interstate 

ROW Concurrence – controversial non‐Interstate 

disposals 

Disposal of Property Rights 

Disposal of Access control (LA ROW) on Interstates cannot be dele‐

gated to the State. 

Request credit toward the non‐Federal share of construction costs for early ac‐quisitions, donations or other contribu‐tions applied to a project 

23 CFR 710.501, 23 CFR 710.505 

As needed  FHWA  Request  Review, Approve, Authorize 

Early Acquisi‐tion 

This action cannot be delegated to 

the State 

Federal land transfers  23 CFR 710, Subpart F 

As needed  FHWA  Request  Review, Approve  Federal Land Transfer 

This action cannot be delegated to 

the State 

Functional replacement of property   23 CFR 710.509  As needed  FHWA  Request  Review, Approve  Functional Replacement 

This action cannot be delegated to 

the State 

  

Page 86: Program Operations Manual - Michigan

  84 

RESEARCH, DEVELOPMENT AND TECHNOLOGY TRANSFER 

Overview 

The purpose of this program is to implement the provisions of 23 USC 505 State Planning and Research (SPR) for effectively utilizing FHWA SPR funds by undertaking research and development activities that have a direct bearing on improving Michigan’s transportation program. A primary element of 23 CFR Part 420—Planning and Research Program Administration is to utilize SPR Part II funds for developing and implementing the Research, Development, and Technology Transfer Program. Through the estab‐lishment of this program:  

An annual work program and budget is established.   Research, development, and technology transfer activities are monitored.  Program performance and expenditure reports are submitted.   Peer exchanges are conducted.   Research and development management process is established.   Research deliverables are incorporated into MDOT’s transportation program processes (manu‐

als), materials, and/or best practices.  Research final reports are posted to the MDOT/Research website to make available and  share 

research results with other state DOTs and FHWA. 

MDOT is responsible for coordinating and monitoring the SPR Part II Program that operates based on the state’s fiscal year. MDOT may process amendments and revisions to the annual work program and budget as necessary. M2D2 (Multi Modal Development and Delivery) is supported in the MDOT Re‐search Program by inclusion of the multiple modes within our Research Advisory Committee Structure and incorporation of multiple projects related to the various transportation modes. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program. 

Topic  Law  Implementing Regulation 

State Planning and Research (SPR)  23 USC 505  23 CFR 420 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Annual research program   Research, development, and technology transfer activities   Peer exchanges   Research and development management process   Research deliverables   STIC/EDC coordination 

Page 87: Program Operations Manual - Michigan

  85 

Approved Procedures, Agreements, and Manuals  

Procedure, Agreement, Manuals Latest Approval Date/Version 

Anticipated due date 

FHWA/MDOT Risk Assessment  9/2020  Annually 

Research and Implementation Manual  12/2018  As needed 

University Transportation Center Administration Manual   10/4/2013  As needed 

Annual Research Work Program  8/2019  Annually 

Annual Expenditure and Accomplishment Report   12/2019  Annually 

 

 

Page 88: Program Operations Manual - Michigan

  86 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Research Annual Program   23 USC 505 and 23 CFR 420 

Annually  FHWA  Develop & Submit   Approve Pro‐gram 

Approved prior to start of each Fiscal Year, in time for ob‐ligation of funds 

MDOT Develop and FHWA ap‐prove 

Program Amendment Process  23 USC 505 and 23 CFR 420 

As needed  FHWA  Develop & Submit   Approve Amendment 

n.a.  MDOT Develop and FHWA ap‐prove 

Annual Expenditure and Accom‐plishment Report Submittal  

23 USC 505 and 23 CFR 420 

Annually  MDOT  Compile & Submit   File  90 days following end of reporting pe‐riod (Fiscal Year) 

MDOT submit to FHWA 

FHWA/MDOT Risk Assessment Process 

n.a.  Annually  MDOT/ FHWA 

Develop with FHWA  

Develop with MDOT 

n.a.  MDOT and FHWA develop collabo‐ratively 

Research and Implementation Manual Updates 

n.a.  As needed  MDOT  Update & Submit  File  n.a.  MDOT submit to FHWA 

University Transportation Center Administration Manual Updates 

n.a.  As needed  MDOT  Update & Submit  File  n.a.  MDOT submit to FHWA 

 

 

Page 89: Program Operations Manual - Michigan

  87 

SAFETY  

Overview 

Key safety program activities serve to ensure the safety of Michigan’s roadways is monitored to ensure roadway and crash types of higher risk are identified and addressed as part of the annual Highway Safety Improvement Program (HSIP). This is a data‐driven, strategic approach to improving highway safety on all public roads with a focus on performance to achieve a significant reduction in traffic fatali‐ties and serious injuries. Some activities are required by state/federal statute, regulation or FHWA pol‐icy. Other beneficial activities, which are not necessitated by law or regulation, are encouraged subject to a risk‐based approach, and resource availability.  

 

Background/History 

The general structure of the HSIP is to select cost‐effective safety improvements, as identified in Michi‐gan's Strategic Highway Safety Plan (SHSP), to address locations with correctable fatality (K) and serious injury (A) crashes. Projects are selected and identified during the annual Call for Projects process for lo‐cal and non‐local roadways. The selected projects are designed and implemented via the Region offices and Local Agency Programs oversight. Before and After studies are conducted to evaluate the effective‐ness of a countermeasure. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law Implementing Regulations 

Standards  23 USC 109   

Design Standards for Highways    23 CFR 625 

Highways  MCL Chapters 247, 249, 250, 252 

 

Highway Safety Improvement Program (HSIP)  23 USC 148, 924  23 CFR 490 Sub‐part B, 23 CFR 924 

Crash/Safety Data Collection  23 USC 148   

Strategic Highway Safety Plan (SHSP)  23 USC 148, 23 USC 150  23 CFR 924 

Railroad‐Highway Crossings Program  23 USC 130  23 CFR 646 Sub‐part B 

Safety Performance Targets  23 USC 150, 490   

Safe Routes to School  23 USC 402   

FHWA Bicycle and Pedestrian Policy  23 USC 217   

High Risk Rural Roads  23 USC 148   

  

Page 90: Program Operations Manual - Michigan

  88 

Key Program Areas 

These are the key program areas within the program or related to the program.  

The Highway Safety Improvement Program   Trunkline Crash Surveillance Program  Local Safety Initiative   Data Driven Safety Analysis   Non‐Motorized Safety  Road Safety Audits  High Risk Rural Roads 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

FHWA/MDOT Stewardship and Oversight Agreement  May 2015   

AASHTO: A Policy on Geometric Design of Highways and Streets 

6th Edition, 2011   

MDOT Standard Plans    As needed 

MDOT Special Details    As needed 

HISP Annual Report    Annually, September 30 

State Strategic Highway Safety Plan  December 2019   

Annual Safety Performance Targets  2021  Annually 

Manual on Uniform Traffic Control Devices  2009   

Michigan Manual on Uniform Traffic Devices  2011   

AASHTO, Roadside Design Guide  4th Edition, 2011   

Highway‐Rail Crossing Handbook  3rd Edition 2019   

 

 

Page 91: Program Operations Manual - Michigan

 

  89 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

HSIP Annual Report  23 USC 148  Annually  MDOT  Submit draft report to FHWA by August 31. Finalized HSIP report to FHWA by Septem‐ber 24. 

FHWA provide MDOT comments on draft report 

5 business days 

 Division sends report to Office of Safety by Septem‐ber 30. 

Strategic Highway Safety Plan  23 USC 148  Every four years 

MDOT  Submit draft plan  FHWA review and approve process used to develop SHSP updates  

14 business days 

Division will provide copy of SHSP approval letter to HQ.  

Annual Safety Performance Tar‐gets (TPM) 

23 USC 134, 148 150, 490 

Annually  MDOT  Submit targets to FHWA by August 31 

    MPOs have an additional 180 days to report their targets to MDOT. 

Review Drug Offender Driver’s Li‐cense Suspension Law & Enforce‐ment Certification (section 159) 

23 USC 159 23, CFR 192.5 

Annually   MDOT  Submit targets to FHWA by January 1 

FHWA sends letter to MDOT 

   

Review Safety Belt Compliance Status 

23 USC 153, 23 CFR 1215.6 

Annually  MDOT         

High Risk Rural Roads (HRRR) Special Rule 

23 USC 148(g)(1)  Annually  FHWA        After the final FARS & HPMS data are available, FHWA HQ will inform the States if the HRRR Special Rule applies for the following FY. 

Older Drivers and Pedestrians Special Rule 

23 USC 148  As needed  MDOT/SHSP  Include strategies to address increases in subsequent SHSP up‐dates 

Coordinate with MDOT to include strategies in SHSP update 

   

 

Page 92: Program Operations Manual - Michigan

 

  90 

SPECIFICATIONS 

Overview 

Specifications provide for the basis of payment and facilitate the administration of contracts. Specifica‐tions delineate the materials, equipment, and performance parameters for the work, establish levels of acceptability, and serve as the basis for project decisions. In summary, specifications serve as the basis for delivering the highway product to the end user. Specifications include:  

MDOT Standard Specifications for Construction   Supplemental Specifications   Frequently Used Special Provisions  Project Specific/Inserted Special Provisions   Local Agency Special Provisions  

 

Background/History 

Regulations require that the Plans, Specifications, and Estimates (PS&E) for Federal aid highway projects on the National Highway System (NHS) be approved on a project‐by‐project basis prior to advertisement of the project. Standard specifications, supplemental specifications, and frequently used special provi‐sions are not regulated documents, but are approved by the FHWA to simplify the PS&E review process. Once approved, standard specifications can be used on Federal aid projects without further review. In the absence of pre‐approved standard specifications, all the required specification information would have to be included and approved as part of the PS&E package for each project.  

MDOT does not differentiate between NHS and non‐NHS projects. When it comes to the development and implementation of standard specifications, a single set of standard specifications is used. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program. This list is not exhaustive and other Federal and State laws, regulations and or‐ders may also apply. 

Topic  Law Implementing Regulations 

Project Approval and Oversight  23 USC 106   

Standards  23 USC 109   

Design Standards for Highways    23 CFR 625 

Value Engineering    23 CFR 627 

Preconstruction Procedures    23 CFR 630 

Construction and Maintenance    23 CFR 635 

Design‐Build Contracting    23 CFR 636 

Utilities    23 CFR 645 

Railroads    23 CFR 646 

Bridges, Structures, and Hydraulics    23 CFR 650 

Pedestrian and Bicycle Accommodations and Projects    23 CFR 652 

Page 93: Program Operations Manual - Michigan

 

  91 

Topic  Law Implementing Regulations 

Traffic Operations    23 CFR 655 

Carpool and Vanpool Projects    23 CFR 656 

Indian Reservation Road Bridge Program    23 CFR 661 

Emergency Relief Program    23 CFR 668 

Landscape and Roadside Development    23 CFR 752 

Intelligent Transportation System Architecture and Standards    23 CFR 940 

General Highway Law  MCL Chapters 220 – 224 

 

Highways  MCL Chapters 247, 249, 250, 252 

 

 

Key Program Areas 

These are the key program areas within the program or related to the program.  

Standard Specifications for Construction  Special Provisions  Design Standards 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Version/Edition (as available) 

Update cycle (if applicable) 

FHWA/MDOT Stewardship and Oversight Agreement  2015   

MDOT Standard Specifications for Construction  2012  2020 

MDOT Road Design Manual     

MDOT Bridge Design Manual     

MDOT Bridge Design Guides     

MDOT Standard Plans     

FHWA, Technical Advisory: Development and Review of Specifica‐tions, March 24, 2010 

2010   

 

 

Page 94: Program Operations Manual - Michigan

 

  92 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action 

FHWA Action 

FHWA may assess the performance of individual specifications via program, process, and project reviews conducted in accordance with this Agreement. 

23 CFR 625  As Needed  MDOT  Administer  Review and  Approve 

FHWA will participate, to the extent practicable, on the various revision com‐mittees for the complete revision of the Standard Specifications for Construc‐tion. 

  As Needed  MDOT  Administer  Review and  Approve 

Final review timeframe and approval of the Standard Specifications for Con‐struction will be negotiated prior to the activity. 

  As Needed  MDOT  Administer  Review and  Approve 

FHWA will review and respond to MDOT for Frequently Used Special Provi‐sion approval within 14 calendar days of receipt or as agreed upon. 

  As Needed  FHWA  Administer  Review and  Approve 

The MDOT Standard Specifications for Construction Supplemental  Specifications are approved by FHWA on a program basis to facilitate project approvals; with the exception of the errata supplemental specification. 

23 CFR 625  As Needed  MDOT  Administer  Review and  Approve 

Non‐standard Construction and Material Specifications or Project  Specific Special Provisions and Previously Approved Project Special Provisions are approved on a project‐by‐project basis at the time of PS&E in accordance with the agreed level of Project of Division Interest (PoDI) project oversight. 

23 CFR 625  As Needed  MDOT  Administer  Review and  Approve 

 

 

Page 95: Program Operations Manual - Michigan

 

  93 

UTILITY COORDINATION 

Overview 

Utility Coordination involves communicating and coordinating MDOT’s highway improvement projects with utilities, identifying conflicts and finding resolutions in order to meet the scheduled letting date and to alleviate project construction phase utility impacts which may result in project extras and/or delays. Some activities are required by state/federal statute, regulation or FHWA policy. Utility coordination best practices, such as subsurface utility engineering, the use of a utility conflict matrix and utility part‐nering meetings, which are not necessitated by law or regulation, are encouraged but subject to re‐source availability. 

 

Background/History 

MDOT and FHWA have and continue to recognize the importance of managing utility conflicts through successful communication, coordination, and cooperation. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program. 

 

Topic  Law Implementing Regulations 

Public Act 368 of 1925  (Highway Obstructions and Encroachments; Use of Highway by Public Utilities)  

MCL 247.171   

Public Act 174 of 2013  (MISS DIG Underground Facility Damage Pre‐vention and Safety Act) 

MCL 460.721   

Standards  23 USC 109   

Relocation of Utility Facilities  23 USC 123   

Construction and Maintenance    23 CFR 635 

Utility Relocations, Adjustments and Reimbursement    23 CFR 645 (A) 

Accommodation of Utilities    23 CFR 645 (B) 

Executive Order on Accelerating Broadband Infrastructure Deploy‐ment 

   

 

Key Program Areas 

No key program areas within MDOT’s Utility Coordination program or related to the program.  

 

 

 

Page 96: Program Operations Manual - Michigan

 

  94 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Version/Edition (as available) 

Update Cycle (if applicable) 

FHWA/MDOT Stewardship and Oversight Agreement  May 2015  As needed 

AASHTO A Policy on the Accommodation of Utilities within Freeway ROW 

October 2005   

AASHTO A Guide for Accommodating Utilities within Highway ROW 

October 2005   

MDOT Road Design Manual     As needed 

MDOT Utility Accommodation Policy  March 2011  As needed 

MDOT Utility Coordination Procedural Manual    As needed 

ASCE Standard Guideline for the Collection and Depiction of Exist‐ing Subsurface Utility Data (38‐02) 

2002   

FHWA Program Guide Utility Relocation and Accommodation on Federal Aid Highway Projects 

January 2003   

Buy America Issues to Consider for Utility Contracts and Agree‐ments 

December 2012   

 

 

Page 97: Program Operations Manual - Michigan

 

  95 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement. 

Activity  Reference Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action  Remarks 

Utility Coordination Procedural Manual 

  As Needed  MDOT  Develop and Maintain 

None   

MDOT’s Utility Reimbursement Pro‐cedure 

23 CFR 645 Sub‐part A 

As Needed   MDOT  Develop and Maintain 

Approval Needed  Re‐writing Current Procedures for Sub‐mittal 

Approval of Utility Agreement / Al‐ternate Procedure 

23 CFR 645.119  As Needed  MDOT  Develop and Maintain 

Approval Needed   

Utility Accommodation Policy  23 CFR 645.215, 23 USC 109(l), 23 USC 123 

As Needed  MDOT  Develop and Maintain 

Approval Needed   

MDOT’s Certification Acceptance for Utility Coordination 

  All Projects  MDOT  Certify  None   

Pursue Innovative Opportunities e.g. STIC, EDC, SHRP and Other Programs for Utility Coordination 

  When Available  MDOT/FHWA  Employ   Promote and Sup‐port 

 

Utility Research Grants    When Available  MDOT  Create / Apply  Review / Approve   

Utility Coordination Meeting    Quarterly & As Needed 

MDOT/FHWA  Participate  Participate  Discuss Issues and Opportunities 

 

 

Page 98: Program Operations Manual - Michigan

 

  96 

VENDOR PROCUREMENT 

Overview 

MDOT uses Federal aid funds to procure consultant/vendor services. In accordance with the FHWA/MDOT Stewardship and Oversight Agreement, Attachment A, FHWA is responsible for approving MDOT’s consultant/vendor procurement guidelines and major changes such as modified or new proce‐dures, and exceptions. FHWA has direct oversight of the consultant/vendor procurement on major pro‐jects with construction valued over $500 million. 

Typically, Local Public Agencies (LPA) do not use federal aid funding for the design of their projects, how‐ever when they do, MDOT utilizes separate guidelines for procurement of those services and utilizes third‐party agreements. 

In addition to approving MDOT and LPA consultant/vendor procurement guidelines, FHWA is responsi‐ble for periodic program/process review to assure compliance with the approved selection guidelines. This review generally occurs every three years and applies to the both MDOT’s and the Local Agency Program consultant/vendor procurement/selection processes.  

 

Background/History 

MDOT Administered Projects: 

MDOT uses several methods for procuring consultant/vendor services: a qualification‐based selection (QBS) process, a low‐bid process, and a best value process. Request for Proposals (RFP) for all services greater than $250,000 are posted on MDOT’s Web site. 

“Brooks Act” or Qualification Base Selection (QBS) services for projects valued at $250,000 or more, are defined as professional services of an architectural or engineering nature, as defined by State law, if ap‐plicable, which are required to be performed or approved by a person licensed, registered, or certified to provide such services as described as: 

professional services of an architectural or engineering nature performed by contract that are associated with research, planning, development, design, construction, alteration, or repair of real property 

other professional services of an architectural or engineering nature, or incidental services in‐cluding: studies, investigations, surveying and mapping, tests, evaluation, consultations, com‐prehensive planning, program management, conceptual designs, plans and specifications, value engineering, construction phase services, soils engineering, drawing reviews, preparation of op‐erating and maintenance manuals, and other related services. 

Some services, whether QBS, low bid, or best value, will require a consultant/vendor to be MDOT prequalified to be eligible to participate in the selection. For these services, the RFP will clearly state what prequalification classification(s) are required. The only exception to prequalification is the MDOT Small Business Development Program. 

MDOT’s current trunkline approved process is comprised of three tiers: 

Tier I Services (Services Estimated less than $250,000)   Tier II (Greater than $250,000 to $1,500,000)   Tier III (Greater than $1,500,000)  

Page 99: Program Operations Manual - Michigan

 

  97 

In addition, MDOT also has the option of utilizing an Expedited contracting process when the project is being funded by 100% state funding. 

Tiers II and III must comply with QBS and the Brooks Act, if the selection involves professional engineer‐ing or architectural services as noted above and use Federal‐aid. 

Local Agency Administered Projects: 

MDOT’s Local Agency Program employs an FHWA approved process for its oversight of LPA consultant selections. The engineering or architectural contract is a third‐party contract between the LPA and the LPA consultant. This third‐party contract is required to be in place as part of the cost sharing agreement, between MDOT and the LPA, and an agreement is executed for each phase of the project. The MDOT Local Agency Program (LAP) unit periodically updates and revises the LPA consultant selection document to meet current requirements in accordance with the FHWA/MDOT Stewardship and Oversight Agree‐ment, Attachment A; whereas, major changes in the document are approved by FHWA. 

MDOT LAP approved process includes: 

Services less than $100,000 follow small purchase procedures  Service greater than $100,000 follow the Brooks Act requirements including QBS. 

 

Applicable Laws, Regulations, and Orders 

The following table is a collection, by topic, of the federal and state laws, regulations, and orders per‐taining to this program.  

 

Topic  Law Implementing Regulations 

Project Approval and Oversight  23 USC 106   

Letting of Contracts  23 USC 112   

Construction  23 USC 114 (a)   

State Transportation Department  23 USC 302   

Mapping  23 USC 306   

Rules, regulations and recommendations  23 USC 315   

Highway Safety Program  23 USC 402   

Selection of Architects and Engineers (Brooks Act)  40 USC 1101   

Public Contracts, Definitions, Simplified Acquisition  41 USC 403(11),   

Engineering Services    23 CFR 1.11 

Conflicts of Interest     23 CFR 1.33 

Procurement, Management, and Administration of Design Re‐lated Services 

  23 CFR 172 

Administrative Requirements, Cost Principles, and Audit    2 CFR 200 

Non‐procurement suspension and disbarment    2 CFR 1200‐1201 

Contract Cost Principles and Procedures    48 CFR 31 

Office of the Chief Information Officer    49 CFR 1.48(b) 

Participation by Disadvantaged Business Enterprises In De‐partment Of Transportation Financial Assistance Programs 

  49 CFR 26 

 

Page 100: Program Operations Manual - Michigan

 

  98 

Key Program Areas 

This is the key program area within the program or related to the program.  

Consultant Management related to Procurement, management, and administration of Engi‐neering and design related services 

 

Approved Procedures, Agreements, and Manuals  

 

Procedure, Agreement, Manuals Latest Approval Date/Version (if applicable) 

Anticipated due date (if ap‐plicable)  

Selection Guidelines for Service Contracts  03/10/2020  As needed 

 MDOT Local Agency Program (LAP) Policies & Procedures for Procurement, Management and Administration of Preliminary Engineering, Construction Engineering or Testing Related Ser‐vices Using State or Federal Funds 

10/31/2017  As needed 

Conflict of Interest Guidance For Consultant Services on Lo‐cal Agency Federal‐Aid Projects 

03/30/2020  As needed 

Third Party Template for Local Agencies  06/15/2016  As needed 

Dispute Resolution Process  01/06/2000  As needed 

 

 

Page 101: Program Operations Manual - Michigan

 

  99 

Project and Program Monitoring and Approval Chart 

This table describes how FHWA and MDOT will conduct program related business. It is organized by activity and provides information about the relative responsibilities for both FHWA and MDOT. For additional information about all Program Responsibilities see Attachment B of the May 2015 Stewardship and Oversight Agreement.  

Activity Schedule/ Frequency 

Responsible Agency 

MDOT Action  FHWA Action Business Standard 

Remarks 

Review period to approve or deny an excep‐

tion to procedures and requests relating to a 

major project consultant selection. 

Ongoing  FHWA  Review and vet requests; submitting those recom‐mended for FHWA approval 

Approve   5 Business Days 

 

Manual or major policy updates  Ongoing  FHWA  Prepare and submit for FHWA Approval 

Approve  21 Business Days 

 

Tier assignment and selection, non‐ Major Pro‐ject 

Ongoing  MDOT  Approve  Approve excep‐tions to policy 

3 Business Days 

 

RFP & RFQ scope and advertisement, non‐Ma‐jor Project  

Ongoing  MDOT  Approve  Review as re‐quested 

5 Business Days 

 

RFP for Consultant’s Acting in a Management Role 

Ongoing  FHWA  Prepare and submit for FHWA Approval 

Approve  Complexity Dependent 

May require coordination with FHWA HQ 

Federal Funding authorization   Ongoing  FHWA  Prepare and submit for FHWA Approval 

Approve  3 Business Days 

 

Amendments and extension to contracts  Ongoing  MDOT  Approve  Approve excep‐tions to policy 

3 Business Days 

 

Non‐competitive selection approval  Ongoing  FHWA  Prepare and submit for FHWA Approval 

Approve  2 Business Days 

Emergency Relief (ER) non‐competitive FHWA approval is handled with the approval of qualifying ER Event 

All activities related to Major Projects, ap‐proval of RFI, RFQ, RFP, all amendments and extension to the contract 

Ongoing  FHWA  Prepare and submit for FHWA approval 

Approve  5 Business Days; Com‐plexity De‐pendent  

 

Contract Settlements  Ongoing  FHWA  Prepare and submit for FHWA approval 

Approve  Complexity Dependent 

 

 

Page 102: Program Operations Manual - Michigan

 

  100

APPENDIX A: Acronyms 

AASHTO  .......... American Association of State Highway and Transportation Officials ACHP  ............... Advisory Council on Historic Preservation ADA  ................. Americans with Disabilities Act BOBS  ............... Bureau of Bridges and Structures BOHIM  ............ Bureau of Highways Instructional Memos BPD  ................. Base Plan Date CAP .................. Compliance Assessment Program CE  .................... Categorical Exclusion CFR  .................. Code of Federal Regulations CMAQ  ............. Congestion Mitigation and Air Quality CPG  ................. Consolidated Planning Grant CPM  ................ Capital Preventative Maintenance DBE  ................. Disadvantaged Business Enterprise DBE/SS  ............ Disadvantaged Business Enterprise/Supportive Services DEIS  ................. Draft Environmental Impact Statement DOT  ................. State Department of Transportation EA  .................... Environmental Assessment EEO  ................. Equal Employment Opportunity EIS  ................... Environmental Impact Statement EO  ................... Executive Order EPA  .................. Environmental Protection Agency ER  .................... Emergency Relief ESA  .................. Environmental Site Assessment FAA  .................. Federal Aviation Administration FAHP  ............... Federal aid Highway Program FAPG  ............... Federal aid Policy Guide FAST  ................ Fixing America’s Surface Transportation Act FHWA  .............. Federal Highway Administration FHWA‐HQ  ....... Federal Highway Administration Headquarters (D.C) FIRE  ................. Financial Integrity Review and Evaluation FMIS  ................ Federal Management Information FONSI  .............. Finding of No Significant Impact FTA  .................. Federal Transit Administration GARVEE  ........... Grant Anticipation Revenue Vehicle System GIS  ................... Geographic Information System GTSAC  ............. Governor’s Traffic Safety Advisory Commission HOT  ................. High Occupancy Toll HOV  ................. Highway Occupancy Vehicle HPMS  .............. Highway Performance Monitoring System HRRR  ............... High Risk Rural Roads HSIP  ................. Highway Safety Improvement Program HVUT  ............... Heavy Vehicle Use Tax IACR  ................ Interstate System Access Change Request IAJR  ................. Interstate System Access Justification Reports  ICAP ................. Indirect Costs Allocation Plans 

Page 103: Program Operations Manual - Michigan

 

  101

ISACR  ............... Information System Access Change Request ISTEA ................  Intermodal Surface Transportation Efficiency Act of 1991 ITS  ................... Intelligent Transportation Systems L&D  ................. Location & Design LAP  .................. Local Agency Program LPA  .................. Local Public Agency LRFD  ................ Load and Resistance Factor Design LTAP ................. Local Technical Assistance Program MAP‐21 ............ Moving Ahead for Progress in the 21st Century MDNR  ............. Michigan Department of Natural Resources MDOT  .............. Michigan Department of Transportation MDPS  .............. Michigan Department of Public Safety MFOS  .............. MAP Financial Obligation System MIOSHA  .......... Michigan Occupational Safety and Health Administration MMUTCD  ........ Michigan Manual on Uniform Traffic Control Devices MOA  ................ Memorandum of Agreement MOU  ............... Memorandum of Understanding MPL  ................. Metropolitan Planning Funds MPO  ................ Metropolitan Planning Organization MUTCD ............ Manual on Uniform Traffic Control Devices NAAQS  ............ National Ambient Air Quality Standards NBI  .................. National Bridge Inspection NBIS  ................ National Bridge Inspection Standards NEPA  ............... National Environmental Policy Act of 1969 NHS  ................. National Highway System NHTSA  ............. National Highway Traffic & Safety Administration NOI  .................. Notice of Intent NSTI  ................. National Summer Transportation Institute NTIS  ................. National Tunnel Inspection Standards OHSP  ............... Office of Highway Safety Planning OIG USDOT  ...... Office of Inspector General OJT  .................. On‐the‐Job Training OJT/SS  ............. On‐the‐ Job Training/Supportive Services OMB  ................ U.S. Office of Management and Budget OPI  .................. Organizational Performance Indicators POA  ................. Plans of Action PMP  ................ Project Management Plans PoDI  ................ Projects of Division Interest PS&E  ............... Plans, Specifications, and Estimate  RAC  ................. Research Advisory Committee RASPS ............... Rapid Approval State Payment System RDC  ................. Rail Development Commission RFP  .................. Request for Proposal RHCP  ............... Railroad Highway Crossing Program ROD  ................. Record of Decision ROW  ................ Right‐Of‐Way RWIS  ............... Road Weather Information System S&O  ................. Stewardship and Oversight Agreement 

Page 104: Program Operations Manual - Michigan

 

  102

SAFETEA‐LU ..... Safe, Accountable, Flexible, Efficient, Transportation Equity Act: A Legacy for Users SEP  .................. Special Experimental Projects SHPO  ............... State Historic Preservation Office SHSP  ................ Strategic Highway Safety Plan SIP  ................... State Implementation Plan SLRTP  .............. State Long‐Range Transportation Plan SOP  ................. Standard Operating Procedure SOW  ................ Statement of Work SPR  .................. Statewide Planning and Research SRTS  ................ Safe Routes to School STIP  ................. Statewide Transportation Improvement Program STRAHNET  ....... Strategic Highway Network TIFIA  ................ Transportation Infrastructure Finance and Innovation Act TIP  ................... Transportation Improvement Plan TEA‐21  ............. Transportation Equity Act for the 21st Century TMA  ................ Transportation Management Area TMP  ................. Transportation Management Plans TOC .................. Traffic Operations Center TPM ................. Transportation Performance Management TRAC ................ Transportation Review Advisory Council TRCC ................. Traffic Records Coordinating Committee TS&L Type Size and Location TSC ................... Transportation Service Center UPWP ............... Unified Planning Work Program USACE .............. United States Army Corps of Engineer USC .................. United States Code USFWS ............. United States Fish and Wildlife Service VE ..................... Value Engineering