12
R64 - PAVEMENT MARKING August 1996 DOT Spec R64 1 PROFESSIONAL SERVICES SPECIFICATION T16 PROJECT SPECIFICATION Date JUNE 2012 Department of Infrastructure, Energy and Resources

PROFESSIONAL SERVICES SPECIFICATION · Standard Specification G1 General Provisions, Clause G1.2.1 i.e., Construction or Maintenance, as this influence the Limits of Contract

Embed Size (px)

Citation preview

R64 - PAVEMENT MARKING August 1996

DOT Spec R64

1

PROFESSIONAL SERVICES SPECIFICATION

T16 PROJECT SPECIFICATION Date JUNE 2012

Department of Infrastructure, Energy and

Resources

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 2

Index Page

T16.1 SCOPE 3

T16.2 OBJECTIVE 3

T16.3 REFERENCES 3

T16.4 GENERAL REQUIREMENTS 3

T16.5 PROJECT SPECIFIC DETAILS - GENERAL 4

T16.5.1 Description of Works 4 T16.5.2 Nature of Project 4 T16.5.3 Design Features 4 T16.5.4 Work Not in Project 4 T16.5.5 Contractor Site Facilities/Working Area 5 T16.5.6 Access to Site 5 T16.5.7 Possession of Site 5 T16.5.8 Separable Parts of the Works 5 T16.5.9 Concurrent Work 5 T16.5.10 Order of Work 6 T16.5.11 Materials Supplied by the Principal 6 T16.5.12 Superintendent’s Facilities 6

T16.6 CONTRACT MANAGEMENT 6

T16.6.1 Constraints on Contractor Activities 6 T16.6.2 Use of Bridge by Construction Plant 6 T16.6.3 Use of Public Roads 6

T16.7 SPECIFIC PUBLIC CONTACT REQUIREMENTS 7

T16.7.1 Public Contact Management Plan 7 T16.7.2 Inspection by Visitors 7 T16.7.3 Project Identification Signs 7

T16.8 PUBLIC UTILITY ADJUSTMENTS 7

T16.9 PROPERTY WORKS 8

T16.10 SURVEY OF STRUCTURES 8

T16.11 ENVIRONMENTAL MANAGEMENT 8

T16.11.1 Historic Buildings and Other Aspects of Specific Environmental Features 8 T16.11.2 Aboriginal Archaeological Sites 9

T16.12 TRAFFIC MANAGEMENT 9

T16.13 EARTHWORKS 9

T16.13.1 Indicative Topsoil Stripping Depths 9 T16.13.2 Batter Treatments 10

T16.14 DRAINAGE 10

T16.15 PAVEMENT 10

T16.15.1 Minimum Subgrade CBR permitted 10 T16.15.2 Bituminous Surfacing 10

T16.16 TRAFFIC FACILITES 10

T16.17 LANDSCAPING 10

T16.18 MAINTENANCE RESPONSIBILITES 10

T16.19 PAYMENT 11

T16.20 VARIATIONS TO DIER’S STANDARD SPECIFICATIONS 11

T16.21 HOLD POINTS 11

T16.22 APPENDICES 11

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 3

T16.1 SCOPE

This Specification sets out the minimum requirements for the preparation of Project

Specifications and the relationship to all DIER Standard Specifications for the Design,

Construction and Maintenance of State Roads.

The Project Specification is to contain all the specific requirements of the project.

T16.2 OBJECTIVE

Whilst the objective of this Specification is to provide clear directions on what is expected to be

covered in a project specification it is not an exhaustive document as each project will have

individual requirements however it does contain the minimum topics to be considered when

preparing a Project Specification.

T16.3 REFERENCES

Project Specification development shall be in accordance with all DIER Specifications and

Standards, in particular:

PM1 - General Provisions

PM2 - Consultancy Management Plan

PM3 – Risk Management

PM4 – Permits

D1 – Road Design

D2 – Structure Design

G1 – General Provisions

G2 - Project Management Plan

G3 - Traffic Management

G9 – Quality Product

G10 - Construction Environmental Management Plan

Australian Standards and Guides

AS/NZS ISO 31000 Risk Management, Principles and Guidelines

HB 327 Communication and Consulting

ISO Guide 73 Risk Management, Vocabulary

T16.4 GENERAL REQUIREMENTS

This purpose of a Project Specification is to clearly detail the project scope, relevant payment

provisions and the technical requirements of the project. It will, as far as possible, detail only

the requirements relating to the finished product or desired outcome and not prescribe the

method of delivery.

Generally the Project Specification is not to contain clauses relating to items covered in the

Conditions of Contract, such as liability matters, time provisions or liquidated damages.

The Project Specification shall reference all relevant DIER Standard General, Roadwork’s and

Bridgeworks Specifications, including number, title and issue date. Any approved project-

specific amendments to the General, Roadworks and Bridgeworks Specifications shall be

clearly detailed, ideally in the one location for ease of reference.

Wherever possible, terminology used in the Project Specification shall be consistent with the

terminology used in the relevant DIER Standard Specifications.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 4

The Project Specification shall not contain references to products, particularly proprietary

products.

The Project Specification shall not contain references to Australian Standards or other

publications that are referenced in DIER Standards Specifications unless there is a need to

address specific project requirements. Where such references are required they shall be

specific to the relevant clause(s) shall not be a general reference.

All DIER standard General, Roadworks and Bridgeworks Specifications referenced in the Project

Specification shall be the current, approved versions downloadable from DIER’s internet site.

Draft standard specifications may only be referenced when there is a specific need to do so

(e.g. trials of products or introduction of developing/evolving standards) and then only on

approval from DIER.

T16.5 PROJECT SPECIFIC DETAILS - GENERAL

The specific details of the Project Specification shall be prepared individually for each project.

T16.5.1 Description of Works

This item should provide a detailed description of the work in the project, including the

location, type, extent and limits of the work.

The description of work should include a general overview of the locality of the project and

refer to the relevant DIER Link Map contained in an appendix to the Project Specification.

The description of work should define what the general type of work is, in accordance with

Standard Specification G1 General Provisions, Clause G1.2.1 i.e., Construction or Maintenance,

as this influence the Limits of Contract. The Limits of Contract for a construction project

should be shown on the Drawings or described in detail in the Project Specification.

The clause should include a broad description of construction activities that define the scope,

such as earthworks, traffic control, flexible pavement construction, drainage, sprayed

sealing/asphalt, guard fence/WRSF, gabion wall construction etc.

The description of work should cover all elements of the work required to deliver the project.

T16.5.2 Nature of Project

This Clause should indicate whether the Project is Schedule of Rates, Lump Sum or a hybrid of

both.

T16.5.3 Design Features

For road works, this clause describes the principal design features e.g. lane/carriageway

configuration, medians, wire rope safety fence separation, grade separation of intersections

etc. For bridgeworks, this clause would describe the design features of the work including type

of structure, width and lane configuration, span lengths, fixed and/or movable expansion

joints, substructure, horizontal and vertical alignment.

Design features need not be detailed but should provide sufficient detail to convey to the

Contractor the design elements which may have an influence on the construction methodology.

T16.5.4 Work Not in Project

This clause should identify those items of work which are shown on the Drawings or are

directly associated with the project but which are not included in the project.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 5

This may include such works as traffic signal construction or installation of Intelligent Transport

System (ITS) infrastructure.

Works not in Project should be noted on the Drawings.

T16.5.5 Contractor Site Facilities/Working Area

The Working Area is usually not specified in the Project Specification but is generally defined in

Standard Specification G1 General Provisions Clause G1.5.2. However, with some projects,

there may be a need to define a specific area which may have benefits to the Projector and

may reduce cost to the Principal (e.g. the Principal may make available a house and environs

which has been purchased as part of the project and scheduled for demolition but which is

being made available to the Projector as a Projector Site facilities for the duration of the

project).

The Project Specification shall define the area available to the Contractor for use during the

construction of the works. A detailed sketch may be required to adequately define the

Working Area or it may be shown on the Drawings. In either case, the Contractor should be

referred to the Drawings or to an Appendix to the project specification.

T16.5.6 Access to Site

The provisions of site access are generally covered in Standard Specification G1 General

Provisions Clause G1.2.2.

Specific details should be included if there are any special restrictions that may apply to the

method, timing and/or locations of access to the site, available to the Contractor during the

construction of the works. A sketch may be required for this purpose. This sketch should be

included as an appendix to the Project Specification.

A statement including whether the Contractor is responsible for maintaining any access roads

outside the Limits of the Work during the project should also be included.

T16.5.7 Possession of Site

Specific details are required whenever there are limits or conditions, beyond that which are

articulated in the General Conditions of Contract (ref Cl 27 AS2124 and AS4300), giving the

Contractor possession of all or part of the site e.g. part of a site for a bridge viaduct may not

be available until a building on it is demolished by others.

Any such limits or conditions must be carefully considered and must be clearly specified. All

deviations from the General Conditions of Contract are to be approved by DIER.

T16.5.8 Separable Parts of the Works

If a part or parts of the works are required to be completed and handed over prior to the

completion of the whole of the Works, details defining the separable part(s) are to be provided.

T16.5.9 Concurrent Work

Detail of any other Work which is being carried out either within or adjacent to the work site,

by either the Principal, Utility Authorities or other Contractors are to be provided.

This is particularly important where major utility relocations have been arranged to be

undertaken by either the Utility Authority or its agent.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 6

T16.5.10 Order of Work

For projects in which the order of all, or part of the Works, is required to follow a particular

sequence, e.g. the construction of an access road across a severed property is to be completed

and opened to traffic before access across the highway is denied are to be included.

T16.5.11 Materials Supplied by the Principal

When the Principal is supplying materials to the project the Project Specification shall define

where the materials are currently stored and arrangements for the Contractor to access these

materials. The clause should also identify when the Contractor becomes responsible for care

of the materials.

The Project Specification shall define how material supplied by the Principal complies fully with

DIER’s Standard Specifications and evidence of such compliance.

Examples of this might be the issue of compliance certificates for bridge girders or details of

“as constructed” levels, compaction and moisture content on earthworks produced on a

previous project.

T16.5.12 Superintendent’s Facilities

The requirements for the provision of the Superintendent’s facilities are described in Standard

Specification G1 General Provisions.

The Project Specification needs to confirm that this is required or when the requirements vary

from that outlined.

T16.6 CONTRACT MANAGEMENT

T16.6.1 Constraints on Contractor Activities

The project Specification shall detail any constraints on Contractor’s construction and

management activities including:

working hours and working days that vary from those provided in the General

Conditions of Contract and associated Annexures

restrictions on the use of particular equipment

limitations on the use of various construction methodologies.

These details should contain only those constraints not otherwise covered by the General

Conditions, Special Conditions of Contract and the provisions of the Standard Specifications.

If working hours are to be outside the requirements of Schedule 7 of the Environmental

Pollution Control (Noise Mitigation) Regulations, approval from the Director Environmental

protection Authority is required.

T16.6.2 Use of Bridge by Construction Plant

The requirements of Standard Specification G1 General Provisions Clauses G1.13 and G1.14

shall be considered when preparing the Project Specification.

Details should be included where it is likely that a Contractor may intend to use existing bridge

structures and the author is aware of structural deficiencies which would prevent access to

these structures without strengthening.

T16.6.3 Use of Public Roads

The requirements of Standard Specification G1 General Provisions Clauses G1.6.4 and G1.6.5

are to be assessed when preparing the Project Specification. It is applicable if public roads

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 7

(not in the ownership of DIER) may to be used for haulage or any other work under the

project.

This clause should be included if there are specific requirements arising out of conditions of the

Development Approval.

It should outline issues such as:

restrictions on the time when roads can be closed

any vehicle type, load or dimension restrictions on public roads or bridge structures

not conforming to the current Tasmanian Road Vehicle Regulations.

T16.7 SPECIFIC PUBLIC CONTACT REQUIREMENTS

T16.7.1 Public Contact Management Plan

The requirements of Standard Specification G2 Contract Management Plan Clause G2.10 Public

Contact are to be assessed when preparing the Project Specification. Descriptions of any

particular requirements of the Contractor in respect of any of the tasks of the Project

Stakeholder Management Plan developed in accordance with Standard Specification T7

Stakeholder Engagement Plan such as:

reporting of stakeholder enquiries

management requirements of particular stakeholder information events

open days

inspection by members of the public and other 3rd parties.

T16.7.2 Inspection by Visitors

Details shall be provided where the project is of such scale and interest to the community that

it is anticipated a number of inspections by third parties, not involved in the project, will occur.

Details shall indicate the likely frequency and duration of visitations and clearly assign

responsibility for arranging and accommodating visitors.

T16.7.3 Project Identification Signs

The requirements of Standard Specification G1 General Provisions Clause G1.11 are applicable

to most projects.

Details shall be include where there is variance from Clause G1.11 on where signs are to be

located, when they can be erected and when they are to be removed.

Sign message details will be provided by DIER.

A drawing of a typical information board should be attached in an Appendix.

T16.8 PUBLIC UTILITY ADJUSTMENTS

Details are required whenever there are particular public utilities which are to be adjusted,

relocated or protected within the work site. These details should clearly identify the public

utilities affected, the extent of the adjustment and what Work is required to be carried out by

the Contractor.

Standard Specification G1 General Provisions Clause G1.4.1 outlines the Contractor’s

responsibilities to liaise with utility owners and arrange for adjustments as necessary.

As these can significantly affect the Contractor’s works, consideration should be given to

specifying in the Project Specification:

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 8

those utilities which are known to exist on site

the approximate location of known utilities should be shown on the drawings

where utilities have been relocated prior to project award, the previous and new

locations of known utilities should be shown on the drawings

advice of any nominated sub contractors for any utility adjustments

a general description of any nominated sub contract works

specific requirements for liaison with nominated sub contractors (e.g. meetings

including minutes and follow up).

The Project Specification should also detail:

the period of notice to be given to the Utility Authority in advance of site adjustments

(if the author is aware of special notice requirements),

whether the responsibility is with the Contractor or the Superintendent to notify the

Utility Authority of site access, and

the contact person/position at the Utility Authority together with telephone and

facsimile numbers should be contained in an appendix.

T16.9 PROPERTY WORKS

Details of adjustments to boundaries following acquisition or are made available temporarily

for public or projector access, storage, or other requirements are to be in the project

specification. All details of property owners, their addresses and other contact details are to

be included. Descriptions of the extent of the adjustment Works and what Works are required

to be carried out by the Contractor in establishing the site; effecting the physical adjustments;

maintaining the site; and (if necessary) re-establishing works prior to repossession by

landowner.

Details of fencing, access adjustments, gates to be supplied and installed as well as any

property specific adjustments such as dam construction, cattle yard reconstruction etc are to

be covered.

The Property Works must be supported with signed landowner agreements. The Project

Specification should relate whether or not the landowner agreements form part of the project.

This part of the Project Specification should also detail:

any conditions pre-arranged with the landowner

defined periods during which the adjustments are to be carried out; and during which

the project or may be denied possession of the property

the period of notice to be given to the landowner or contact person in advance of

property adjustments.

T16.10 SURVEY OF STRUCTURES

Standard Specification G1 General Provisions Clause G1.6.8 provides the requirements for

managing potential damage to property from construction activity.

Whilst referencing Clause G1.6.8, the author should also provide a schedule of landowners,

including their contact details, who would be affected by blasting, pile driving or vibratory

rollers. This should be included as an Appendix to the Project Specification.

T16.11 ENVIRONMENTAL MANAGEMENT

T16.11.1 Historic Buildings and Other Aspects of Specific Environmental Features

The Contractor’s obligations for Environmental Management are outlined in the requirements

of Standard Specification G10 Construction Environmental Management Plan.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 9

Details in the Project Specification are required if specific environmental management is

required to protect historic buildings, threatened flora and/of fauna, any infrastructure of

European or Aboriginal cultural heritage value etc. It may also relate special treatments

required to manage contaminated runoff, hazardous substances and weeds.

The Project Specification should identify the environmental issues to be managed and outline

the details of any specific management approach. An example would be the requirements of a

Conservation Management Plan for the preservation of an historic building.

T16.11.2 Aboriginal Archaeological Sites

The requirements for protection, removal or covering up of any Aboriginal artefacts or other

commitments as identified by Standard Specification T5 Environmental Investigations and

Reporting shall be provided in the Project Specification.

T16.12 TRAFFIC MANAGEMENT

The requirements of Standard Specification G3 Traffic Management shall be considered in the

Project Specification.

The Project Specification shall describe the general traffic environment including of number of

carriageways, number of lanes, whether or not peak and off peak traffic volumes occur at the

site and heavy vehicle movements.

Details of constructability requirements identified in the Consultants risk assessment shall be

provided.

It shall also outline particular requirements for the management of traffic Including:

during working hours

outside of working hours

pedestrians and disabled persons

public transport

heavy and high productivity vehicles

The Consultant shall relate any specific requirements for pedestrian access during the project

e.g. a project in the vicinity of a school or hospital may require specific facilities for high

volume pedestrian movements or particular facilities for disabled access.

The Consultant shall also relate any particular requirements to be provided for ongoing access

to school bus or general passenger transport services over the duration of the Project. It is

also prudent to identify the operator of a particular passenger transport service and note the

owner and contact details in an Appendix.

Annexure G3.A- Traffic Management Details must be completed together with the most recent

traffic volumes. These shall be included in an Appendix.

T16.13 EARTHWORKS

T16.13.1 Indicative Topsoil Stripping Depths

Indicative topsoil stripping depths identified by T6 Geotechnical and Site Investigations and

Reporting and used in the calculation of quantities shall be provided.

Details of constructability requirements identified in the Consultants risk assessment shall be

provided in particular whether or not stripping is required under embankments and topsoiling

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 10

requirements noting that no topsoil is to be imported or removed from site unless there is

insufficient capacity within the worksite and the potential quantities of topsoil for reuse.

The Contractor shall be made aware of expected stripping depths, soil types and the potential

for variability associated with these estimations.

T16.13.2 Batter Treatments

The requirements of Standard Specification R22 Earthworks shall be considered in the Project

Specification.

T16.14 DRAINAGE

Details shall include descriptions if existing culverts shall be extended, what inspections are

required, if they are to be lined and maintenance requirements such as whether or not all

culverts are to be cleaned prior to achieving Practical Completion.

The location and type of subsoil drains shall also be provided.

T16.15 PAVEMENT

T16.15.1 Minimum Subgrade CBR permitted

The minimum subgrade CBR permitted for all or parts of the works based on the pavement

design parameters shall be nominated.

It may also be given in the Notes on the Drawings.

T16.15.2 Bituminous Surfacing

The requirements of Standard Specifications T15 Pavement Design, G7 Asphalt Production,

R51 Sprayed Bituminous Surfacings and R55 Asphalt Placement shall be included in the Project

Specification.

These include the sprayed seal types and tender application rates and asphalt mix design with

test levels.

Details on constraints or, constructability issues particularly timing of works shall be

considered and provided.

T16.16 TRAFFIC FACILITES

The requirements of Standard Specifications R61 Road Safety Barrier Systems, R62 Guide

Posts and Delineators, R63 Signs and R64 Pavement Marking shall be included in the Project

Specification.

Details shall include the type and location of barrier, post, sign and marking.

T16.17 LANDSCAPING

Details to be provided include grassing, seeding, plantings and paving requirements.

T16.18 MAINTENANCE RESPONSIBILITES

The requirements of Standard Specification G1 General Provisions Clause G1.21 shall be

included in the Project Specification in particular the Schedule of rates items listed are to be

included so that the Contractor is fully aware of maintenance responsibilities.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 11

T16.19 PAYMENT

If any of the clauses in the Project Specification require the Contractor to perform work which

is otherwise not covered by a standard rate or item in the Schedule of Rates or Bill of

Quantities, then relevant details shall be provided that identifies:

the Work that the pay item relates to

the method by which that Work will be measured

the pay item no. in the schedule.

Pay Items shall always be referred to as “Schedule of Rates Item No. XX” or “Bill of Quantities

Item No. XX”.

When preparing the Schedule of Rates/Bill of Quantities the requirements of the Standard

Specification payment clauses shall be followed in particular Clause G1.7.5 Payment for

Records, Clause G1.18.3 Basis of Payment, Clause G3.16 Payment (Traffic Management) and

Clause G10.9 Payment (Environmental Management including Audit).

T16.20 VARIATIONS TO DIER’S STANDARD SPECIFICATIONS

If any Project Specific amendments are required to one or more of DIER’s Standard

Specifications, details of all clauses and amendments are to be listed. The amendments must

identify the specific wording of the standard specification clause referenced, together with the

specific rewording of the amendment. All amendments are to be approved by DIER’s in

accordance with its policy.

T16.21 HOLD POINTS

Hold Points shall be identified, as necessary, in the narrative of any of the Clauses in the

Project Specification.

A Hold Point should be included whenever it is considered prudent that the Superintendent

inspect a deliverable or witness a process which may be critical to the ongoing successful

performance of the Works. An example might include specific requirements for construction of

a property access prior to re-fencing.

The Consultant shall not replicate Hold Points that are noted in the Standard Specifications.

All Hold Points shall by listed in a schedule at the end of the Project Specification and indicate

what works shall not proceed prior to release of the Hold Point.

Table 1 – Schedule of Holdpoints

Description of Hold

Point

Nominated Work Not to

Proceed Evidence of Compliance

T16.22 APPENDICES

Appendices shall include as a minimum:

DIER Link Map or locality Plan

Sketch of possible location for Contractor Sites Facilities

Sketch depicting permitted access to Site

Schedule of Public Utility representative persons and their contact details

Schedule of Landowners and their contact details who may be affected by structurally

damaging construction activities

Annexure G3A – Traffic Management details.

DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

TASMANIA

PROFESSIONAL SERVICES SPECIFICATION

T16 – Project Specification

June 2012

T16 Project Specification Page 12

TRAFFIC AND INFRASTRUCTURE

BRANCH

Roads and Traffic Division

Department of Infrastructure,

Energy and Resources

GPO Box 936, Hobart 7001

Ph: 1300 135 513

Email: [email protected]

Visit: www.dier.tas.gov.au