Upload
lenga
View
214
Download
2
Embed Size (px)
Citation preview
Process Technology and Innovation PTI
Blast Fragmentation Impacts on Downstream Processing at Gold Fields Cerro Corona Kimberly Caron David La Rosa Walter Valery Ronald Diaz Hyder Mamani
© Metso
Project Objective • Goldfields La Cima (Cerro Corona operation) engaged Metso Process Technology and
Innovation (PTI) to conduct a Process Integration & Optimisation (PIO) project for the blasting, crushing and grinding processes.
2
“Maximize the plant throughput when treating the hardest ore ”
© Metso
Rock Mass Characterisation Benchmark Material
3
Polygon 3810007
© Metso 4
Rock Mass Characterisation Rock Structure (RQD)
RQD > 75 high quality massive rock RQD < 50 low quality, jointed/fractured rock
Siro
visi
on
2010
Dril
l Cor
e
RQD ~ 30 %
© Metso 5
Rock Mass Characterisation Rock Strength
Point Load Tests (PLi to estimate UCS)
DWi (Impact breakage)
Finger Axb ta Density Dwi (kWh/m3)
FS 1 76.3 0.52 2.73 3.58
FS 2 87.1 0.72 2.73 3.13
Sample FS 1 (Survey Ore) Results
BWI @ 150 µm closing screen 11.73 kWh/t F80: 2436 µm, P80: 124 µm
BWi (Abrasion breakage)
Overall Hardness Category 4 (50-100 MPa) Moderately Hard Ore
DWi/BWi (resistance of the material to crushing and grinding): Soft to Medium ore for milling
71.2 MPa
© Metso
Brief Description of Overall Process
6
(9)
24’ x 14.5’ 3800 kW
(2)
24’ x 34’ 7600 kW
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01
/20
10
02
/20
10
03
/20
10
04
/20
10
05
/20
10
06
/20
10
07
/20
10
08
/20
10
09
/20
10
10
/20
10
11
/20
10
12
/20
10
01
/20
11
02
/20
11
03
/20
11
04
/20
11
05
/20
11
06
/20
11
07
/20
11
08
/20
11
09
/20
11
10
/20
11
11
/20
11
Cu
mm
ula
tive
Ore
Ble
nd
ing
(%)
Mixed
Supergene
Hypogene
Treated Ore: Hypogene: 80 % (P3810007) Supergene: 12 % Mixed: 8 %
19,200 tpd 6.6 mtpa
© Metso 7
Drill and Blast Audit Benchmarking Phase
Parameter Value
Bench Height (m) 10
Hole Diameter (mm) 200
Burden (m) 5.2
Spacing (m) 6.0
Stemming (m) Drill cuttings/mill scats (m)
4.5 2.0/2.5
Subdrill (m) 1.0
Number of Holes Area (m2)
132 36.6
Explosive Type HA 46/HA 64
Explosive Density (g/cm3) 1.2/1.28
Detonator system Non-electric
Downhole (ms) Inter-hole (ms) Inter-row (ms)
600 17 25
© Metso 8
SmartTagTM Ore Tracking System
Antenna 1
Antenna 2
RFID Tag
© Metso
9
Comminution Circuit Review and Survey Review of Crushing and Grinding Operations
600525450375300225150750
80
70
60
50
40
30
20
10
0600525450375300225150750
kW-CR1
Perce
nt
kW-CR2
N 4059StDev 89.01Mean 129.5
N 4346StDev 96.45Mean 132.5
Histogram of Power Draw - Crushers CR1 & CR2
Nomin
al Pow
er
Nomin
al Pow
er
Available Power Available Power
Hypogene: 800-850 tph
Crushers : •Operating below installed power 225 kW of 373 kW 60 % Grinding Mills: •Wide range of bearing pressure and power levels (overloading) •60 % critical speed
Historical Operational Data
Average Daily Production: •Hypogene tph lower than overall distribution
© Metso 10
Modelling & Simulations Blast Fragmentation Model Calibration
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000 10000Cu
mul
ativ
e %
Pas
sing
Size mm
Blast Model Average ROM
Model Inputs
•Rock mass characterisation data •Audit blast parameters •ROM image analysis (coarse end of the curve) •Primary crusher product belt cut sample (fine end of the curve)
© Metso 11
Modelling & Simulations Blast Model Simulations
*Use 20 mm crushed angular material for the full stemming length
Benchmark P3810007
Simulation Scenario 5
Bench (m) 10 10 Diameter (mm) 200 200 Burden (m) 5.2 4 Spacing (m) 6.0 4.7 Subdrill (m) 1 1 Stemming (m) 4.5 *3.5 Explosive Type HA 46 HA73 Density 1.20 1.30 Primer (Booster) (g) 450 450 Charge/hole (kg) 245.0 306.3 Detonator Non Electric Electronic Surface (holes) 17 20 Surface (holes) 42 100 PF (kg/m³) 0.79 1.63 PF (kg/t) 0.31 0.65 Difference (%) 107
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000 10000
Cum
ulat
ed %
Pas
sing
Size (mm)
Blast Simulations
Benchmark P3810007
Scenario 1
Scenario 2
Scenario 3
Scenario 4
Scenario 5
© Metso 12
Modelling & Simulations Comminution Circuit Model and Simulations
Model •Survey samples were analysed and used to mass balance and model fit. Simulations •Explore the effects of the primary crusher and SAG mill operating conditions. •Assess the effect of modified blast fragmentation. •Combined effect of all changes Primary Crusher Recommendations Improve primary crusher power utilisation by reducing crusher gap (increases thickness of teeth) SAG Mill Recommendations Higher SAG mill ball charge, lower operational speed, run the mill at a stable feed rate. Ball Mill Recommendations Increase ball top size. Increase ball charge to fully utilise the installed power.
© Metso 13
Combined Predicted Results Modelling & Simulations
145
150
155
160
165
170
175
720
740
760
780
800
820
840
860
880
900
920
Fina
l Pro
duct
P80
, µm
SAG
Thro
ughp
ut, t
ph
Throughput
P80
Powder factor increased to
1.4kg/m3
Powder factor increased to
1.6kg/m3
Optimised SAG milling
Optimised ball milling
Base Case
+8.3%
+12.1%
+15.9% +15.9%
Blast Scenario 5
Blast Scenario 4
© Metso
Recommendations for the Validation Trial Drilling and Blasting Recommendations //~ Implement larger diameter holes Implementation of Electronic Detonators Decrease the stemming length from 4.5 m to 3.5m Use 20 mm crushed angular material for the full stemming length Avoid using drill cuts for stemming; if crushed material is unavailable use mill scats Use explosive HA 73 with 1.3 g/cm³ in all holes Use parameters PF: 1.6 kg/m³, Burden: 4 m, Spacing: 4.7 m, HD:200 mm ~ Use delays of 20 ms between holes and 100 ms between rows. Primary Crusher Recommendations Increase primary crusher power utilisation by reducing the crusher gap SAG Mill Recommendations Higher SAG mill ball charge and lower operational speed Run the mill at a stable feed rate. Ball Mill Recommendations Increase ball top size to compensate the increased ball mill feed size. Increase ball charge to 35 % to fully utilise the installed power.
Implemented Not implemented Partially implemented ~
© Metso 15
Validation Trial Rock Mass Characterisation Overall Rock strength: Moderately Hard Ore P3800017: Similar strength to benchmark P3800018: Higher range of ore hardness Rock structure: Low quality, jointed/fractured rock Breakage Characteristics: Soft to medium ore for milling (very similar)
© Metso 16
Validation Trial Blast Design Parameters
Polygon 3800017
• Reduced stemming in only soft lithology holes
• Reduced PF
Polygon 3800017 & 3800018
• GF’s preferred use of HA55/HA64 for dry/wet holes
• Stemming plugs
• Electronic detonators
• 25 ms and 83 ms
*Stemming plugs used in both validation trial polygons
Benchmark P3810007
Simulated Scenario 5
Validation P3800017
Validation P3800018
Burden (m) 5.2 4 4 4 Spacing (m) 6 4.7 4.7 4.7 Stemming (m) 4.5 3.5 *3.5/4.5 *3.5/4.5 Explosive HA 46 HA 73 HA 55/64 HA 55/64 Density (g/cm3) 1.2 1.3 1.28/1.3 1.28/1.3
Powder Factor (kg/m3) 0.79 1.63 1.31 1.62 Powder Factor (kg/t) 0.31 0.65 0.52 0.65 Detonator Non Electric Electronic Electronic Electronic Inter-hole (ms) 17 20 25 25 Inter-row (ms) 42 100 83 83
© Metso 17
Validation Trial
Polygon 3800017 •More fines •Lower range hardness levels •Lower PF Polygon 3800018 •Higher range of ore hardness
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000 10000
Cum
ulat
ive
% P
assi
ng
Size, mm
Validation P3800018 Validation P3800017Benchmark P3810007 PTI Recommendations
Fragmentation for Benchmarking and Validation Polygons
© Metso 18
Validation Trial Fragmentation Impact on Crushing and Grinding
ValidationBenchmark
1200
1100
1000
900
800
700
600
500
Project Phase
SAG
Mill
Thro
ughp
ut (t
ph)
928.95
808.935
Comparison of SAG Mill Throughput for the Specific Ore Type
+ 14.84%
P80: 154 µm
P80: 141 µm
SAG Feed: % F80: Very similar % Fines Increase: 18 % Avg tph increase: 14.8 % Specific Energy Reduction: 9.2 % Ball Mill: Reduced final product P80 = 141 µm
0
10
20
30
40
50
60
70
80
90
100
0.1 1 10 100 1000
cum
ulat
ive %
pas
sing
size (mm)
Validation survey, July 2012
Benchmark survey, Oct 2011
Crushing:
•Increased tph due to finer blast fragmentation
• Reduced wear on crusher
• Increased power utilisation (scope to improve)
© Metso 19
Metso PTI’s PIO methodology demonstrated that Cerro Corona may increase the plant throughput by 14.8 % (same ore type as in validation trial) and at least 5.7 % for all ore types.
Knowledge and understanding of ore properties is critical during execution of PIO projects.
Optimised blast design produced finer ROM fragmentation therefore finer feed to primary crusher which impacted the plant throughput.
By combining the optimised blast design and optimised comminution processes it is possible to increase the plant throughput and reduce energy and costs.
An integrated process integration and optimisation approach from mine to mill results in highest impact and benefits in terms of operational efficiency and profitability.
Conclusions
© Metso
Metso PTI would like to thank everyone at Cerro Corona who assisted in this project.