  • Project Controls     | Public Involvement     | Technology Services     | Oracle® Gold Partner      

    Primavera Pertmaster

    User CasePresenter: Steve Malaszecki

    Executive VP

    Project Controls     |

    Public Involvement     |

    Technology Services

  • Project Controls     | Public Involvement     | Technology Services 

    We're an end‐to‐end project and construction management firm. 

    We know what's important.

    We understand your needs.

    We have the right tools for the project.

  • Project Controls     | Public Involvement     | Technology Services 

    Envision Consultants, Ltd.

    DBE | SBE | WBE

    www.eclimited.com

    Corporate Overview

    Envision 

    Consultants, 

    Ltd. 

    provides 

    professional 

    project 

    and 

    construction 

    management, 

    as 

    well 

    as 

    technology, 

    GIS, 

    and 

    public 

    outreach 

    services.   Headquartered 

    in 

    southern 

    New 

    Jersey, 

    with 

    offices 

    in 

    Philadelphia, 

    New 

    York, 

    and 

    Baltimore, 

    the 

    firm 

    is 

    certified 

    as 

    DBE/SBE/WBE 

    and 

    has 

    been established for more than 20 years.

    Our 

    commitment 

    to 

    client 

    satisfaction 

    has 

    resulted 

    in 

    the 

    successful 

    completion 

    of 

    diversified 

    construction 

    projects 

    on 

    highways 

    and 

    bridges, 

    transit 

    systems, 

    airports, 

    and 

    other public and private facilities and infrastructure.

    Headquarters 3 Wheatley BoulevardMullica Hill, NJ 08062

    Philadelphia Office30 S. 15th

    Street, Suite 702Philadelphia, PA 19102

    Baltimore Office400 East Pratt Street, 8th Floor

    Baltimore, MD 21202

    New York Office112 W. 34th Street, 18th Floor 

    New York, NY 10120

  • Project Controls     | Public Involvement     | Technology Services 

    Value‐Added Services

    CPM Scheduling 

    Cost Estimating 

    Construction Claims Analysis 

    Claims Avoidance/Dispute Resolution 

    Document Control 

    Project Cost/Change Management 

    Public Involvement

    Community Outreach 

    Risk Assessment/Risk Management

    Enterprise Project Management 

    Software Solutions

    Planning

    Geographic Information Systems

    Technology Services

    Information Security

    IT Assessments

    ORACLE®

    Primavera Value‐Added 

    Reseller/Trainer

    ORACLE®

    Primavera Systems Software 

    Implementation, Training and Consulting 

    Implementing Web‐based Project 

    Management Software Tools

    Time Impact Analysis

    Progress Reporting

  • Project Controls     | Public Involvement     | Technology Services 

    •Validate project schedule and capital cost estimate assumptions;

    • Evaluate the adequacy of schedule and budget contingency levels

    •Identify key areas of project risk

    •Provide a basis for monitoring risk levels and contingency management throughout the project delivery.

    Purpose of  Risk  Assessment Workshop

    •Review any comments from Workshop #3 Report, Addendum to Workshop #2, and any outstanding issues and actions from TCC report.

    •Review results of risk analysis, ranges, and input data with MUNI.

    •Make any agreed changes to the schedule, 10th percentile estimate, and Beta Factors and re-run models.

    •Discuss and agree minimum contingency levels at hold points.

    •Discuss and agree minimum schedule contingency at hold points.

    •Agree secondary mitigation capacity.

    •PMOC Presentation to management of process, results, and conclusions.

    Process  of  Risk  Assessment 

    Workshop 

  • Project Controls     | Public Involvement     | Technology Services 

    Top Ten “Red “ Risks

  • Project Controls     | Public Involvement     | Technology Services 

    Beta Factors Agreed to in Risk Workshop

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Sensitivity Index 

    2%

    2%

    3%

    3%

    3%

    4%

    4%

    4%

    4%

    4%

    6%

    6%

    6%

    7%

    7%

    9%

    10%CTS1200 - CTS Headhouse Final Structure

    STS1100 - Risk #74 /105- Systems testing time too short

    CTS1210 - CTS Excavate Emergency Exit

    STS1080 - STS Systems Startup & Commissioning

    CTS1230 - CTS M/E/P/A

    CTS1010 - CTS Install Secant Pile Walls

    CTS1400 - Risk #54 - Insufficent station fit out time

    CTS1190 - CTS Cross Cut Final Structure

    STS1070 - STS CTS Systems Installation

    CTS1020 - CTS Excavate Headhouse & Bracing to El. +65

    CTS1030 - CTS Temporary Decking

    STU1010 - CSP Pre-Revenue Operations

    CTS1000 - CTS Building Demolition

    CTS1005 - CTS Site Setup

    BUF0030 - Risk #47 - SEM slower than expected

    FDS1795 - Risk #94 - bid Addendum extn and / or protest

    CTS1340 - Risk #52 - Settlement - Install C/Grouting

    Schedule Sensitivity Index

  • Project Controls     | Public Involvement     | Technology Services 

    Milestones and Hold Points

  • Project Controls     | Public Involvement     | Technology Services

    Milestones and Hold Points  Basis

  • Project Controls     | Public Involvement     | Technology Services 

    Validated the project schedule Using 3 Processes:

    1. Detailed review of their schedule2. Parametric (Top Down) analysis based

    FTA guidance (20% float from Entry into FD through Rev Ops

    Date)

    3. Bottom up schedule risk analysis based on the SFMTA schedule and risk register

    Baseline Schedule – FTA calculation of Float

  • Project Controls     | Public Involvement     | Technology Services 

    Minimum Schedule Contingency Levels

  • Project Controls     | Public Involvement     | Technology Services 

    Minimum Cost Contingency Levels

  • Project Controls     | Public Involvement     | Technology Services

    Minimum Schedule Float at Hold Points

  • Project Controls     | Public Involvement     | Technology Services

    Schedule Contingency

    San Francisco Central Subway (SFMTA)Schedule Contingency Graphic

    Contingency Float

    Buffer Float

    Minimum Float

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    2Q08

    4Q08

    2Q09

    4Q09

    2Q10

    4Q10

    2Q11

    4Q11

    2Q12

    4Q12

    2Q13

    4Q13

    2Q14

    4Q14

    2Q15

    4Q15

    2Q16

    4Q16

    2Q17

    4Q17

    2Q18

    4Q18

    Floa

    t in

    Mon

    ths

    Contingency Float Buffer Float Minimum Float

  • Project Controls     | Public Involvement     | Technology Services 

    Project Master Schedule Analysis 

    FTA PMOC Schedule Risk AnalysisFTA PMOC Schedule Risk Analysis

    Latest Rev Ops Date: August 2020Latest Rev Ops Date: August 2020

    Most Likely Rev Ops Date: Most Likely Rev Ops Date: 

    November 2018November 2018

    Earliest Rev Ops Date: March 2017Earliest Rev Ops Date: March 2017

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Analysis: Award Tunnel Contract

    FTA PMOC Schedule Risk AnalysisFTA PMOC Schedule Risk Analysis

    Latest Date: October 27, 2011Latest Date: October 27, 2011

    Most Likely Date: February 10, 2011Most Likely Date: February 10, 2011

    Earliest Date: August 5, 2010Earliest Date: August 5, 2010

    06/Aug/10 14/Nov/10 22/Feb/11 02/Jun/11 10/Sep/11

    Distribution (start of interval)

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    550

    600

    Hits

    0% 05/Aug/10

    5% 05/Oct/10

    10% 26/Oct/10

    15% 10/Nov/10

    20% 24/Nov/10

    25% 08/Dec/10

    30% 21/Dec/10

    35% 04/Jan/11

    40% 14/Jan/11

    45% 28/Jan/11

    50% 10/Feb/11

    55% 24/Feb/11

    60% 10/Mar/11

    65% 24/Mar/11

    70% 07/Apr/11

    75% 20/Apr/11

    80% 05/May/11

    85% 20/May/11

    90% 08/Jun/11

    95% 06/Jul/11

    100% 27/Oct/11

    Cum

    ulat

    ive

    Freq

    uenc

    y

    FDS1386 - Award/Execute Tunnel Contract : Start Date

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Analysis: FTA Execute FFGA

    FTA PMOC Schedule Risk AnalysisFTA PMOC Schedule Risk Analysis

    Latest Date: May 8, 2012Latest Date: May 8, 2012

    Most Likely Date: October 11, 2011Most Likely Date: October 11, 2011

    Earliest Date: March 26, 2011Earliest Date: March 26, 2011

    02/Jun/11 10/Sep/11 19/Dec/11 28/Mar/12

    Distribution (start of interval)

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    240

    Hits

    0% 26/Mar/11

    5% 03/Jun/11

    10% 30/Jun/11

    15% 21/Jul/11

    20% 10/Aug/11

    25% 27/Aug/11

    30% 14/Sep/11

    35% 27/Sep/11

    40% 08/Oct/11

    45% 20/Oct/11

    50% 28/Oct/11

    55% 08/Nov/11

    60% 17/Nov/11

    65% 29/Nov/11

    70% 07/Dec/11

    75% 15/Dec/11

    80% 28/Dec/11

    85% 10/Jan/12

    90% 21/Jan/12

    95% 10/Feb/12

    100% 08/May/12

    Cum

    ulat

    ive

    Freq

    uenc

    y

    MS0002 - FTA Execute FFGA - Project Milestone #2 : Start Date

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Analysis: Demobilize from Tunnel

    FTA PMOC Schedule Risk FTA PMOC Schedule Risk 

    AnalysisAnalysis

    Latest Date: September 22, 2014Latest Date: September 22, 2014

    Most Likely Date: August 27, Most Likely Date: August 27, 

    20132013

    Earliest Date: October 3, 2012Earliest Date: October 3, 2012

    14/Oct/12 02/May/13 18/Nov/13 06/Jun/14

    Distribution (start of interval)

    0

    100

    200

    300

    400

    500

    600

    700

    Hits

    0% 30/Oct/12

    5% 03/Apr/13

    10% 07/May/13

    15% 29/May/13

    20% 13/Jun/13

    25% 28/Jun/13

    30% 12/Jul/13

    35% 25/Jul/13

    40% 05/Aug/13

    45% 15/Aug/13

    50% 27/Aug/13

    55% 09/Sep/13

    60% 18/Sep/13

    65% 01/Oct/13

    70% 14/Oct/13

    75% 28/Oct/13

    80% 11/Nov/13

    85% 02/Dec/13

    90% 27/Dec/13

    95% 31/Jan/14

    100% 22/Sep/14

    Cum

    ulat

    ive

    Freq

    uenc

    y

    TUN1170 - Demobilize from Tunnel : Start Date

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Analysis: UMS Construct Platform

    FTA PMOC Schedule Risk AnalysisFTA PMOC Schedule Risk Analysis

    Latest Date: August 30, 2017Latest Date: August 30, 2017

    Most Likely Date: January 24, Most Likely Date: January 24, 

    20162016

    Earliest Date: December 4, 2014Earliest Date: December 4, 2014

    23/Dec/14 11/Jul/15 27/Jan/16 14/Aug/16 02/Mar/17

    Distribution (start of interval)

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    Hits

    0% 04/Dec/14

    5% 19/May/15

    10% 09/Jul/15

    15% 19/Aug/15

    20% 16/Sep/15

    25% 12/Oct/15

    30% 29/Oct/15

    35% 17/Nov/15

    40% 07/Dec/15

    45% 23/Dec/15

    50% 14/Jan/16

    55% 01/Feb/16

    60% 17/Feb/16

    65% 09/Mar/16

    70% 28/Mar/16

    75% 18/Apr/16

    80% 12/May/16

    85% 10/Jun/16

    90% 18/Jul/16

    95% 07/Sep/16

    100% 30/Aug/17

    Cum

    ulat

    ive

    Freq

    uenc

    y

    UMS1340 - UMS Construct Platform Structure : Start Date

  • Project Controls     | Public Involvement     | Technology Services 

    Schedule Analysis: CTS Headhouse Structure

    FTA PMOC Schedule Risk AnalysisFTA PMOC Schedule Risk Analysis

    Latest Date: August 17, 2018Latest Date: August 17, 2018

    Most Likely Date: March 1, 2017Most Likely Date: March 1, 2017

    Earliest Date: September 4, 2015Earliest Date: September 4, 2015

    27/Jan/16 14/Aug/16 02/Mar/17 18/Sep/17 06/Apr/18

    Distribution (start of interval)

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    550

    600

    Hits

    0% 04/Sep/15

    5% 03/May/16

    10% 20/Jun/16

    15% 28/Jul/16

    20% 25/Aug/16

    25% 26/Sep/16

    30% 21/Oct/16

    35% 14/Nov/16

    40% 09/Jan/17

    45% 06/Feb/17

    50% 01/Mar/17

    55% 15/Mar/17

    60% 28/Mar/17

    65% 11/Apr/17

    70% 28/Apr/17

    75% 23/May/17

    80% 19/Jun/17

    85% 18/Jul/17

    90% 28/Aug/17

    95% 02/Nov/17

    100% 17/Aug/18

    Cum

    ulat

    ive

    Freq

    uenc

    y

    CTS1200 - CTS Headhouse Final Structure : Start Date

  • Project Controls     | Public Involvement     | Technology Services

    Conclusions‐

    Validate the Project Schedule & Capital Cost Estimate

    Track Project Milestones to Ensure Project is on Schedule

    Review Contingency float to Verify Meeting Revenue Service Date

    Expedite FFGA

    Build Tunnel Launch Box Prior to FFGA

    Accelerate Final Design

    Top Down for China town Station

    Shut Down Stockton Street (for construction of the UMS Station)

    Accelerate Testing & Commissioning

    Accelerate Pre‐Revenue Activities

  • Project Controls     | Public Involvement     | Technology Services     | Oracle® Gold Partner      Project Controls     |

    Public Involvement     |

    Technology Services

    Any QuestionsAny Questions……

  • Project Controls     | Public Involvement     | Technology Services

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24