Preventive Maintenance order ZPM1 Scenario:
Hierarchy:
Equipment (with partner Functions)
Plant – 2150 (BRAY)
Task List (IA03)
Maintenance Plan – Ip03
Schedule overview: IP24
Lets run the IP30 manually for future dates, to simulate the Preventive Maintenance orders.
Preventive Maintenance Order - 9021339 Generated.
Let go and release the Order 9021339 (IW32)
ZPM1 – Preventive Maintenance Order
Order Release, Material Comitted. Now Goods Issue(GI) to the order via MIGO.
Lets do the confirmation of the order – IW41
Operation – 0010 has been confimed. Lets see the order status as PCNF (Partial Confirmed)
See operation 0010 has been greyed out, As this has been completed in the Order Operations.
Lets confim remaining operation 0020,0030,0040.
After confimration of all the operation – We see the order status as CNF.
Now we can TECO – Technically complete the order.
Order got CNF TECO in the status.