Beisel Road Paving Presented By Kyle L. Nash Director of Public Works Newberry County

Presented By Kyle L. Nash Director of Public Works Newberry County

Embed Size (px)

Citation preview

Beisel Road PavingPresented ByKyle L. Nash

Director of Public WorksNewberry County

Beisel Road - Overview0.8 mile dirt and gravel road off a major state

road (Mt. Bethel Garmany Rd.)Dead-end at USFS property31 different parcels on this road or accessed

from it

Beisel Rd – Aerial View

Beisel Road - History In 1981, non-exclusive easement acquired by USA for a

portion of what is now Beisel Rd In 1990, through a land exchange USA conveyed property

to William C. Sullivan, but retained ingress-egress rights along what was designated Forest Service System Road FSSR-1011

Subsequently, a cooperative agreement was made between USFS and Newberry County for maintenance along FSSR-1011 (Beisel Rd)

In 2009, residents requested paving of Beisel Rd through USFS and Newberry County, however, the road was not a County road

USFS supported the County assuming full maintenance of the road

By Ordinance, Newberry County no longer accepts new roads into its system that are not paved

Beisel Road – History (continued)Newberry County Council amended its Road

Paving Ordinance to allow the acceptance of unpaved roads that have been maintained continuously for at least 3 years by a government authority

In August 2010, 100% of property owners on Beisel Rd granted right-of-way required for Newberry County to accept the road and make it eligible for paving

October 20, 2010 Newberry County Council unanimously accepted Beisel Rd into its road system

Paving of Beisel RdWiden and Pave with Triple Treatment

20 ft driving surface6 ft shoulders6 in stone basePavement markings: lines and reflectors

Proposed Project CostsEngineering $39,000Construction $232,900TOTAL $271,900

Paving of Beisel RdProposed Source of Funds

USFS Title II Grant $135,950.00CTC C-Funds $135,950.00TOTAL $271,900.00

CTC has already committed $39,000 to initiate the engineering portion of this

project

Beisel Road – Program Oversight & Schedule

Newberry County will manage procurement & oversee construction in conjunction with a CTC Consultant

All payments, reimbursements, & recordkeeping will be processed by the Newberry County Finance Director

Proposed Schedule:Schedule Item Start Finish Duration

Engineering Phase 3/1/2011 5/1/2011 2 monthsAdvertise Construction Solicitation 5/1/2011 6/1/2011 1 month

Construction Bid Opening 6/1/2011 6/1/2011 0 days

Bid Award By County Council 6/1/2011 6/1/2011 0 days

Construction 7/1/2011 9/1/2011 2 months

Project Completion 9/1/2011 9/1/2011 0 days

ConclusionNewberry County requests USFS Title II

grant funding of $135,950 toward this projectBalance will be paid with C-FundsThis proposed project will provide a durable,

low-maintenance access road to USFS property

Questions?