Upload
ankit-grover
View
57
Download
0
Embed Size (px)
Citation preview
Low Head Wind Farm
Ankit Grover
Byoungmo KangCecilia M. Ferreira
Liang Zhao
Feasibility study
Tasmania has a great wind resource known as the roaring forties.
Why investing in a Tasmanian wind farm is a good idea?
Two-thirds of Tasmanian electricity generation comes from Hydro-electricity. There is a need for balance!
Use the Basslink to sell electricity to the mainland when demand is high.
Office of the Economic Regulator, 2014
Site characterization
• Area: 15.7 km2
• 6 km to George Town Airport
• 7.2 km to BoM Weather Station
• 10 km to George Town Substation (220 kV)
• Wind speed: 8.68 m/s ( at hub - 94 m)
• Wind Direction: Southly and Westly
• Terrain slope: 2.3% and 1.2%
• Land usage: Crown land and freehold land (SFM Environmental Solutions Pty Ltd, 2005)(Transend Networks, 2014)
Wind Resource Analysis• Low Head Station
- Speed and Distribution -
• Gradient Height 250 m• Surface Roughness: 30 mm
(Robertson & Gaylord, 1980)
Wind Resource Analysis• Selected Site
- Speed and Distribution -
• Gradient Height 400 m• Surface Roughness: 700 mm
(Robertson & Gaylord, 1980)
Wind Resource Analysis - Speed and Distribution -
Height [m]
Surface roughness [m]
Gradient
height [m]
Mean wind speed [m/s]
Standard
deviation
BoM Station
10 0.03 250 7.24 3.036
Wind farm site
94 0.70 400 8.68 3.642
• IEC 61400 – 1 : Wind class II
Wind Resource Analysis - Speed and Distribution -
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 340%
2%
4%
6%
8%
10%
12%
14%
Weibull PDF
Actual data
Wind speed [m/s]
Prob
abilit
y [m
/s]
Wind Resource Analysis - Speed and Distribution -
0 1000 2000 3000 4000 5000 6000 7000 8000 90000
5
10
15
20
25
30
Velocity-duration chart
Duration [hours]
Win
d sp
eed
[m/s]
Wind Resource Analysis - Directionality -
Wind Resource Analysis - Correlation with demand -
0:00
2:24
4:48
7:12
9:36
12:00
14:24
16:48
19:12
21:36 0:0
00
200400600800
100012001400
0102030405060
Daily summer profile
TAS Demand Wind farm output
Time of day
Dem
and
[MW
h]
Elec
tricit
y ge
nera
ted
[MW
h]
0:00
2:24
4:48
7:12
9:36
12:00
14:24
16:48
19:12
21:36 0:0
00
200400600800
1000120014001600
0102030405060
Daily winter profile
TAS Demand Wind farm output
Time of day
Dem
and
[MW
h]
Elec
tricit
y ge
nera
ted
[MW
h]
• Demand data from AEMO(Australian Energy Market Operator, 2015)
𝑉𝑜𝑙𝑢𝑚𝑒 h𝑤𝑒𝑖𝑔 𝑡𝑒𝑑𝑝𝑟𝑖𝑐𝑒=$ 29.14 / h𝑀𝑊
Wind Turbine Selection
Using this Information we selected the:
VESTAS V112 3.3MW
Vestas Online
Turbine Placement
8D
8D
Spacing: roughly 850m in both directions to reduce array losses.
45 turbines in a 2x2 grid formation.
Energy Output
Energy output Farm output – 743GWh
Ideal output – 1300GWh
Capacity Factorbefore losses – 57%
Losses – 20.6%
Capacity Factorafter losses – 45%
Farm outputafter losses – 590GWh
Construction
Sea Transport
Transportation
Vestas V112 - Macarthur wind farm
Port of Bell Bay is 27km from wind farm site. Deep Waters in the Tamar River. Current crane tonnage – 19tonnes, will need to
be increased. Road Transport
3 temporary roadblocks will need to be set.
3 difficult left turns to maneuver.
Soldiers Settlement road.
Soil Analysis
Light green (Kl) – Soils developed from recent calcareous sands on stabilized dunes and beach ridges , load bearing tests needed.
Reconnaissance Soil Map Series of Tasmania For Beaconsfield – George Town
Closest sub station is the George Town Sub Station.
Proposed 10km of 110kV HVAC transmission lines.
Use same transmission corridor as the Basslink overhead lines.
Grid Connection
Proximity to load centers, Bell Bay Aluminum Smelter
Basslink opportunities
Grid Connection
Office of the Economic Regulator, 2014
Avian Fauna
Land clearance
Waste management
Environmental impact
Avian Fauna
https://thewindenergysolution.wordpress.com/4-concessionrefutation/
According to Dr. Cindy Hall number of collisions decreasing in Tasmania
Most common : Brown Thornbill and Silver Gull
Avian Fauna
Site is composed with free hold land and crown land owned by the government. (The Crown)
Can be bought or Leased
Small amount of Land clearance required
Land
(SFM Environmental Solutions Pty Ltd, 2005)
Possible waste produced from construction
No harmful or hazardous waste during operation
Cleanest energy source
Disposal of wind turbine after lifespan
Recycle in thermal and mechanical uses
Waste management
http://www.holcim.com/en/referenceprojects/disused-rotor-blades-can-now-be-utilized-in-cement-production.html
Visual Impact
Noise Impact
Local and government opinions
Social Impact
Social Impact
Located near coastline – Possible destructive coastal view
Distance from housings are far enough
No SHADOW FLICKER (Range of 550m)
Wind turbines are recognized as symbol of renewable energy
Visual Impact
Wind farm noise – the biggest problem for local residents
Noise level of wind farm 103 dB
Allowed noise level 35 dB at housing
Presence of trees and direction of wind blowing away from the housing
Noise Impact
Tasmanian government-the premier Will Hodgman "Tasmania as a renewable energy state has tremendous capacity, I believe, into the future”
Previous wind farms in TAS were supported by local communities
Employment and local business development
Possible opposition group (NIMBY)
Opinions
Financial ModelingElectricity
Revenue in
Discounted
O&M cost per year
Annual interest
Total Discounted Total
Initial cost
Tax
Capital cost
Annual required revenue
×Electricityproduced × Discount
factor
× Tax rate
DF
×Capacity Cash
𝑁𝑃𝑉 𝑖+ (Initial NPV equal to the
negative initial cost)
High revenue scenario
Medium revenue scenario
Low revenue scenario
Capital costs (million AU$/MV)
1.7 2.35 2.53
Life time (years)
20 20 20
Discount rate 10% 10% 10%Inflation rate 0.024 0.024 0.024Construction time (years)
1 1 2
Total O&M per year ($/MW)
10297682.74
10297682.74
10297682.74
Electricity price (AU$/MWh)
110.00 90.00 39.056(in 2017)
Capacity factor 45.38% 45.38% 45.38%O&M Cost $10297682.74 $10297682.74
$10297682.74
Tax rate 0.03 0.03 0.03
NPV of project $308002166.50 $61451272.20 -$97643477.50IRR 25.34% 12.95% 7.58%LCE(AU$/MWh) 60.81288773 77.0976962 81.60733547
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-300000000
-200000000
-100000000
0
100000000
200000000
300000000
400000000
High Revenue Scenario
NPV in high revenue scenario Cashflow in high revenue scenario
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
-700000000
-600000000
-500000000
-400000000
-300000000
-200000000
-100000000
0
100000000
Low Revenue Scenario
Cashflow in low revenue scenario" NPV in low revenue scenario
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-800000000-700000000-600000000-500000000-400000000-300000000-200000000-100000000
0100000000200000000
Medium Revenue Scenario
Cashflow in medium revenue scenarioNPV in medium revenue scenario
Conclusion
Main advantages: Strong wind resource Good correlation with demand and possibility to sell to Victorian
market Proximity to a port, a substation as well as to a load center Existence of a road connecting the site
What is necessary to move forward with the project: Do wind measurements at the site to substitute the use of
projected data Do soil and geography analysis to choose the foundation type Do further fauna assessments (as this is a site specific issue) Study the effect of blade glint on road users Check the availability of the Crown Land and if the other
landlords will be willing to lease their land
Conclusion
The construction of a 148.5 MW wind farm will be able to generate 590 [GWh] per year.However, It will be necessary to do a Power Purchase Agreement to make the project financially viable. Therefore it became an interesting investment with:
Medium revenue ($90/MWh) NPV: $ 61,451,272.20 IRR: 12.95% SPB: 12 years
High revenue ($110/MWh) NPV: $ 308,002,166.50 IRR: 25.34% SPB: 7 years
The Low Head Wind Farm is the right Choice!
References
Australian Energy Market Operator. (2015). Aggregated Price and Demand Data Files. Retrieved April 25, 2015, from http://www.aemo.com.au/Electricity/Data/Price-and-Demand/Aggregated-Price-and-Demand-Data-Files
Economic Regulator. (2014, February). Energy in Tasmania - Performance Report 2012-13. Retrieved April 30, 2015, from http://www.economicregulator.tas.gov.au/domino/otter.nsf/LookupFiles/Energy_in_Tasmania_Performance_Report_2012-13_FINAL_140212.pdf/$file/ Energy_in_Tasmania_Performance_Report_2012-13_FINAL_140212.pdf
Robertson, L. E., & Gaylord, E. H. (1980). Section 3.3.2 - Properties of the Mean Wind. In Tall building: criteria and loading (pp. 161 - 162). New York: American Society of Civil Engineers.
SFM Environmental Solutions Pty Ltd. (2005, October). George Town Coastal Management Plan. Retrieved April 7, 2015, from http://georgetown.tas.gov.au/coastal-reserve-management-lan?fd=pP%25F8%25F0%252F%25B5%25E7%25D D%25A3%25EDJ%2588%25B4r%25FC%25F6d%25DC%25CEO%252FI%253A%253FN5D%25CD%25F3%252FMA26%253F
Transend Networks. (2014, June 30). Annual Planning Report: 2014. Retrieved April 1, 2015, from http://www.tasnetworks.com.au/TasNetworks/media/pdf/Transend-Annual-Planning-Report-2014.pdf
Office of the Tasmanian Economic Regulator. (2014). Energy in Tasmania - Performance Report 2012/13. Department of Primary Industries, Parks, Water and Environment. RECONNAISSANCE SOIL MAP SERIES OF TASMANIA BEACONSFIELD-GEORGE TOWN.
Appendix 1 - OLS of George Town Airport -
Appendix 2
In order to translate the wind measurements from the BoM station to hub height at the proposed wind farm site, firstly, it is necessary to calculate the free stream speed,, at the BoM station from its measured wind velocity, . Using the logarithmic law, this can be done with the following equation:
As it is reasonable to assume that the free stream speed is the same in both sites, it is possible to scale down the wind speed from gradient to hub height at the wind farm site, , using again the logarithmic law:
- Scaling Wind Speeds -
Appendix 3
The Weibull distribution is used to approximate the distribution of wind speeds for a certain location. It uses two parameters: k, called shape factor, and c, called scale factor. Which can be calculated using the mean wind speed, , and the standard deviation, σ, of a dataset with the following equations:
With this parameters, it is possible to calculate the Weibull Probability Density Function (PDF) which is the relative likelihood in [m/s] of having wind at speeds of U [m/s]:
And the Weibull Cumulative Distribution Fuction (CDF) which is the probability of having wind speeds below U [m/s]:
Therefore, it is possible to calculate the probability of finding wind speed within a range of velocities by:
This can be used to calculate the number of hours per year that the wind blows within that range of speeds and the energy output. (Manwell, McGowan, & Rogers, 2004)
- Weilbul Distribution -
Appendix 4 - Transport Route -
Appendix 5 - Wind Turbine Selection -
Our site is characterized as a class IIa (IEC standards)
Low to medium turbulence due to trees and small hills
Average wind speed of 8.68m/s
Appendix 6 - Losses -
Losses – Array Losses – 13% (Katics Model) Electrical Efficiency Losses – 4% (Informed assumption) Soiling losses – 2% (informed assumption) Machine downtime losses – 2% (informed assumption) Other losses – 1%, e.g wind direction hysteresis
(informed assumption) Total loss percentage – 20.6%
Appendix 7
Volume weighted price
- Volume weighted price -
Where: – Electricity produced during the ith 30min
interval – Electricity price during the ith 30min interval – Total Electricity produced during the year
Appendix 8 - Demand -
• Tasmania • Victoria
(Economic Regulator, 2014)
Appendix 9 - Distance from turbine to road -
250 m
Appendix 10
Initial cost: The O&M cost could calculate by:= ×C × 8760(NOTE, C is the capacity factor.) O&M cost per year = Calculation of:PV=A, PV= the initial cost; A is annual required revenue A= PV/ →=
- Financial Modeling -
Discount Factor :(
= The discounted total (Initial NPV equal to the negative initial cost) Levelised cost of electricity is calculated by:LCOE= +
• BoM Weather Station: Low Head Lighthouse
• Datasets: Hourly wind data from 6 June 2000 to 16
February 2011
And half-hourly wind measurements from 1 January 2011 to 4 July 2012.
Appendix 11 - Wind data -