Air Conditioning & Mechanical VentilationSystem installation at Clifford Pier Development
Presented by : abc
Site Location Plan
AddressNo - 80 Collyer Quay, Singapore 049326
Project Outline -Building/Development
The Clifford Pier Development Project - a luxury boutique hotel.- including entertainment outlets, F&B with casual family-oriented restaurants as well as fashion inspired retail shops.- a stylish rooftop bar, rooftop swimming pool with 360° views of the Marina Bay waterfront and famous Singapore skyline.
Application of ACMV System
Central Air Conditioning System 1- Water-cooled chiller 2- Cooling tower 3- Air Handling Unit/Fan coil unit Mechanical Ventilation System 1- Kitchen Exhaust ventilation 2- Plant room ventilation
Central Air Conditioning SystemChilled water chillers are used to produce chilled water to AHU and FCU which cool the air in its respective space(s), and then the chilled water is re-circulated back to the chiller to be cooled again.
Indoor conditions of AC space for comfort cooling
Design dry bulb temperature 23 ° C – 26 °CMin dry bulb temperature 22 ° CDesign relative humidity 55 %– 70 %Air movement 0.15m/s – 0.50m/sMax air movement 0.7 m/s
How is air circulation in the AC space
Typical installation of Equipments
AHU installation- Installation
involved with piping, ducting & control wiring.
Typical installation of Equipments
Chilled water pump installation
- Pump installation involved with inertia block, electrical power supply, etc.
Problem encountered
Insufficient Air Flow
High friction loss=Less CFM(volume) When less air is
delivered, the system has to run longer to achieve the desired comfort level.
Problem encountered
Lower cost and ease of installation have made flex quite popular particularly.
SS 553- (ACMV) have revised & restricted maximum flexible duct length from 4meter to 2 meter.
Problem encountered
Generating Noise from Equipment and fittings
- AHU return inlet is too close to the wall.
- Required width 750 mm width; instead , only 550 mm.
Due to carelessly installation, lack of supervising & poor coordination.
550
Problem encountered
This caused two acoustical problems: unstable fan operation leading to surge and rumble, direct exposure of inlet noise to the mechanical room wall.
wall
THANK YOU
Without the need for thermal
comfort, there will be no need for
Buildings…