Upload
haneef
View
218
Download
0
Embed Size (px)
Citation preview
8/20/2019 Presentation FIDIC Conference
1/53
Copyright © 2012 by K&L Gates LLP. All rights reserved.
Construction as Investment
Kyiv, 20 February 2013
Dispute Avoidance and Resolutionunder FIDIC Rules and Procedure:
Polish Experience
8/20/2019 Presentation FIDIC Conference
2/53
1
ROADMAP OF OUR PRESENTATION
I.Introductory remarks
II. How to process a claim under the FIDIC Conditions?
1. FIDIC Rules and Procedure2. Employer’s & Contractor’s claims3. Time bars in theory and practice
III. Dispute Avoidance and Early Resolution - Dispute Adjudication Board (DAB)
1. DABs – Concept and background2. Models of DABs in FIDIC (standing and ad hoc DABs)
3. Legal effects and enforcement of DAB’s decisions
IV. Arbitration/Litigation
1. Construction arbitration - a growing industry2. Arbitration under FIDIC Conditions
3. Polish experience - XXV Division in the Warsaw High Court- a specialized construction court?
V. Final remarks
8/20/2019 Presentation FIDIC Conference
3/53
2
"Better to prevent than to cure"old French proverb (Mieux vaut prévenir que guérir.)
8/20/2019 Presentation FIDIC Conference
4/53
3
Conflict is a fact of life… and is inevitable
8/20/2019 Presentation FIDIC Conference
5/53
4
Introductory remarks
Dispute Avoidance preferred
The FIDIC Update Task Group recommends the use ofa standing DAB
”The sooner, the better!”
Multi-tier dispute resolution (escalation mechanism):
Engineer
DAB/Mediation
Arbitration/Litigation
8/20/2019 Presentation FIDIC Conference
6/53
5
Effective conflict management
1 2 3Dispute
communicated
to the other
party
Negotiation
Engineer’s
Decision
Consensus-
oriented DR
Method
Enhanced-
negotiation/
Mediation/
Conciliation
Dispute Board
Arbitration/
Litigation
8/20/2019 Presentation FIDIC Conference
7/53
6
Employer’s Claims
The claims ‘available’ to the Employer will depend upon
the specific FIDIC form, since the risk allocation acrossthe FIDIC suite alters considerably; and
the precise contract terms used by the parties, i.a., in theParticular Conditions
The Employer does not have a general right to set-off
Clause 2.5: Notice of Claims
The Employer’s right to make deductions is subject to thegiving of notice “as soon as practicable” after becomingaware of an event or circumstances giving rise to a claim
8/20/2019 Presentation FIDIC Conference
8/53
7
Contractor’s claims (Sub-Clause 20.1)
The Contractor must:
notify a claim not later than 28 days after the Contractorbecame aware or should have become aware of theevent or circumstance;
submit a ‘fully detailed claim and full supporting
particulars’ within 42 days after it became aware (orshould have become aware); and
keep ‘contemporary records’ to substantiate the claimand allow the Engineer to inspect these records and
obtain copies.
8/20/2019 Presentation FIDIC Conference
9/53
8
Contractor’s claims (Sub-Clause 20.1)
The Engineer must:
respond within 42 days of receiving a claim or furtherparticulars either approving the claim or disapproving itwith ‘detailed comments’;
In any determination under Sub-Cl. 3.5,
consult with both parties in an endeavour to reachagreement; and
if agreement cannot be achieved, make a fairdetermination in accordance with the contract
‘taking due regard of all relevant circumstances’
8/20/2019 Presentation FIDIC Conference
10/53
9
Contractor’s claims: Time-Bar Limitation
‘If the Contractor fails to give notice of a claim within such period of 28 days, the Time forCompletion shall not be extended, theContractor shall not be entitled to additional
payment, and the Employer shall be dischargedfrom all liability in connection with the claim ’(Sub-Cl. 20.1)
8/20/2019 Presentation FIDIC Conference
11/53
10
What types of claims are barred?
‘…any extension of the time for Completion and/orany additional payment, under any Clause of theseConditions or otherwise in connection with theContract’ (Sub-Cl. 20.1)
The provision is broad enough to cover most typesof claims
8/20/2019 Presentation FIDIC Conference
12/53
11
Are the FIDIC time bar provisions too onerous?
European International Contractors: ‘unduly harsh’
In theory: Time bars facilitate good claims management,
allowing issues to be aired and settled at the
working level while they are fresh in peoples’minds
They also facilitate effective mitigation,allowing the parties to take action to minimise
the costs and delay of a notified claim
8/20/2019 Presentation FIDIC Conference
13/53
12
Are the FIDIC time bar provisions too onerous?
Multiplex Construction (UK) Ltd v Honeywell
Systems [2007] EWHC 447 (TCC):
“… Contractual terms requiring a contractor to give
prompt notice of delay serve a valuable purpose; suchnotice enables matters to be investigated while they arestill current. Furthermore, such notice sometimes givesthe employer the opportunity to withdraw instructionswhen the financial consequences become apparent”
8/20/2019 Presentation FIDIC Conference
14/53
13
Enforceability of time bars by DABs
DABs, where appropriate, enforce the time bars
FIDIC Gold Book 2008 – DAB has discretion to overridethe time bar:
Sub-Clause 20.1(a):‘…However, if the Contractor considers there arecircumstances which justify the late submission, hemay submit the details to the DAB for a ruling. If the
DAB considers that, in all the circumstances, it is fairand reasonable that the late submission be accepted,the DAB shall have the authority to overrule therelevant 28 day limit …’
8/20/2019 Presentation FIDIC Conference
15/53
14
Enforceability of time bars – Arbitral Tribunals
Arbitration clause may be ineffective, if contractual prerequisites
to arbitration have not been fulfilled
Decision on Jurisdiction by an arbitral tribunal under the Rules of the Court of Arbitration at the Polish Confederation of PrivateEmployers Lewiatan, publ. in Arbitration e-Review no. 1(2009)
Award in Hamburg Chamber of Commerce of 14 July 2006 ,2007 SchiedsVZ 55
‘ A referral to arbitration is not valid where the DAB procedure
has not been attempted first ’Glover J., Understanding the New FIDIC Red Book – A
clause-by-clause commentary , London Sweet&Maxwell2006, p. 390
8/20/2019 Presentation FIDIC Conference
16/53
15
Enforceability of time bars – state courts
Common law jurisdictions
Enforceable on the basis of the parties’ agreement
Skub-clause 20.1 notice is a condition precedent to the rightto recover either time or money
Einstein J in Aiton Pty Ltd v Transfield Pty (1999) SC NSW
236; Mr Justice Ramsey in Holloway v Chancery Mead Ltd [2007] EWHC 2495 (TCC)
The prevention principle?
A party should not benefit from its own breach of contract
Civil law jurisdictions 28-day time-limit leading to a loss of a claim may be
unenforceable due to mandatory statute of limitations rules in civillaws of certain jurisdictions
8/20/2019 Presentation FIDIC Conference
17/53
16
Enforceability of time bars – Example: Germany
Germany - Section 307 of BGB (German Civil Code)
‘(1) Provisions in standard business terms are ineffective if,contrary to the requirement of good faith, they unreasonablydisadvantage the other party to the contract with the user.
(2) An unreasonable disadvantage is, in case of doubt, to beassumed to exist if a provision is not compatible with essentialprinciples of the statutory provision from which it deviates’
The standard limitation period is three years (Section 195 BGB)
Is then the 28-day time bar ‘compatible with essentialprinciples of the statutory provision ’?
8/20/2019 Presentation FIDIC Conference
18/53
17
Enforceability of time bars – Example: Poland
Poland - Article 119 of Polish Civil Code
‘Periods of limitation may not be shortened orprolonged by a legal act.’
Subclause 20.1 time bar (result: loss of the claim)goes even further than the statute of limitation(result: claim exists, but is not enforceable via courtorder)
Since the statute of limitation cannot be contractually
modified, the same should apply to a time bar (aminori ad maius )
Result: Subclause 20.1 time bar null and void?
8/20/2019 Presentation FIDIC Conference
19/53
18
Enforceability of time bars: Poland – Case Law
Appellate Court in Warsaw (30.05.2011, I ACz 700/11)
FIDIC notice requirement is a contractual time bar and not amodification to a statute of limitations rules
FIDIC is commonly used in the industry, and constitutes anintegral part of the parties’ freedom of contract
Notice of claim requirement - as a precondition to arbitration -is not contrary to the Polish public policy
Regional Court in Warsaw (7.03.2012, XXV C 249/11)
Subclause 20.1 given full effect
Claims notified after the agreement has been performed are
time barred a ‘fully detailed claim’ includes a specific calculation of
damage, not a mere assertion of extra costs incurred
8/20/2019 Presentation FIDIC Conference
20/53
19
Enforceability of time bars: Poland – Case Law
Regional Court in Warsaw (13.07.2011, XXV C 701/10)
28-day time bar contradicts the Civil Code provisions on thestatute of limitations and is null and void in this respect
A contractor, despite lack of notice, does not lose its claims. It ishowever contractually liable for breach of contract (breach of aSubclause 20.1 condition)
FIDIC Conditions are of a common law origin and must beadjusted to mandatory laws of a given jurisdiction
Regional Court in Warsaw (11.06.2012, XXV C 567/11)
Similar arguments and conclusion as above
The law is not settled as the Supreme Court has not yet spoken onthis issue
8/20/2019 Presentation FIDIC Conference
21/53
20
Engineer’s determination under scrutiny -
the Dispute Adjudication Board
8/20/2019 Presentation FIDIC Conference
22/53
21
DAB Procedure
under the FIDIC Red Book (Clause 20)
Step 1: Referral of a “dispute” to a DAB
Step 2: DAB must decide within 84 days by a “binding”
decision
Step 3: Notice of dissatisfaction within 28 days or else
“final and binding”
Step 4: Maximum of 56 days for amicable settlement
Step 5: If not settled by above steps, international arbitration
8/20/2019 Presentation FIDIC Conference
23/53
22
Overview of FIDIC dispute resolution provisions
DAB to give
notice of
decision
Notice of
dissatisfaction
Arbitration
can be
commenced
84 days
28 days
If Engineer’s Decision
becomes final and binding
but a Party fails to comply
Arbitration can
be commenced
56 days
Amicable
Settlement
Referral of matters
in dispute to DAB
8/20/2019 Presentation FIDIC Conference
24/53
23
Dispute Boards
Specifically designed and developed for large construction
contracts; known under different names as: Dispute Review Boards (DRB)
issues recommendations with no binding effect
Dispute Adjudication Boards (DAB) issues decisions which are binding on an interim basis
Combined Dispute Boards (CDB)
Standing (or ad hoc ) panels of impartial experts who support parties in reaching consensus
provide recommendations or
render decisions
8/20/2019 Presentation FIDIC Conference
25/53
24
Dispute Boards - Historical background
First developed in the 1970s and 1980s in the US
Eisenhower Tunnel (Colorado), the Mount Baker Ridge HighwayTunnel (Seattle, Washington), and the Chambers Creek Tunnel(Tacoma, Washington)
In 1981, the El Cajon Hydroelectric Project in Hondurasthe first large international construction contract where a DisputeBoard was effectively utilized
In 1995, the World Bank made DRBs mandatory for all IBRD-financed
projects over US$50m
In 1997 the Asian Development Bank and EBRDfollowed with similar decisions
8/20/2019 Presentation FIDIC Conference
26/53
25
FIDIC Dispute Adjudication Boards
In 1995, FIDIC started with the introduction of the use of Dispute
Boards in the Orange Book
In 1996, Dispute Boards were incorporated into the 1992 FourthEdition of the Red Book though its Supplement
In 1999, the suite of FIDICs three major contracts, the 1999 RedBook, the 1999 Yellow Book and the 1999 Silver Book, have alladopted this concept as the first step in the dispute resolutionmechanism, albeit in different forms
8/20/2019 Presentation FIDIC Conference
27/53
26
8/20/2019 Presentation FIDIC Conference
28/53
27
8/20/2019 Presentation FIDIC Conference
29/53
28
Eisenhower Tunnel (Colorado, US)
the Eisenhower Tunnel, completed in 1979, remains
the highest vehicular tunnel in the US first broadly discussed case in which Dispute Board
was effectively used
Source: www.wikipedia.com
8/20/2019 Presentation FIDIC Conference
30/53
29
Ertan Project (China)
8/20/2019 Presentation FIDIC Conference
31/53
30
Hong Kong International Airport
A HK$50 billion investment, HKIA has been one of
the largest engineering and architectural projects inthe world
One of the largest hubs: in 2011, 53.9 millionpassengers used HKIA and some 3.9 million tonnesof air cargo passed through HKIA
8/20/2019 Presentation FIDIC Conference
32/53
31
Channel Tunnel Rail Link Project
a US$5 billion concession project in the UK on which constructionstarted in October 1998
two panels:
a technical panel comprising engineers (construction relateddisputes) and
a finance panel comprising accountants and financiers (disputes
concerning the financial provisions of the concession agreement)
8/20/2019 Presentation FIDIC Conference
33/53
32
Nature of the DAB in the FIDIC forms
Clause 20 of the Yellow Book:
20.4 Obtaining Dispute Adjudication Board’s Decision
“If a dispute (of any kind whatsoever) arises betweenthe Parties in connection with, or arising out of, theContract or the execution of the Works … then after a
DAB has been appointed pursuant to Sub-Clauses 20.2[Appointment of the Dispute Adjudication Board] and20.3 [Failure to Agree Dispute Adjudication Board],either Party may refer the dispute in writing to the DAB
for its decision, with a copy to the other Party …
8/20/2019 Presentation FIDIC Conference
34/53
33
Principal features of the DAB in the FIDIC forms
Express duty of independence and impartiality on the DAB members
DAB’s decision obtainable within a relatively short time – 84 daysfrom reference
Decision binding on the Parties “unless and until it shall be revised in
an amicable settlement or arbitral award” (SC 20.4)
8/20/2019 Presentation FIDIC Conference
35/53
34
Nature of the DAB in the FIDIC forms
Two different models:
‘Standing’ – as provided for in Red & Gold Book GeneralConditions
‘Ad hoc’ – as provided for in Yellow & Silver Book GeneralConditions
Models are alternatives – but both include dispute adjudicationrole
Most appropriate model depends on particular project
Fees split equally between Parties
8/20/2019 Presentation FIDIC Conference
36/53
35
Standing DAB
DAB appointed by Parties at outset of the Contract, and operatesthroughout its currency
DAB visits the site regularly
Many disputes resolved amicably before they require decision ofDAB
Parties can jointly request opinions
If dispute arises, referral can be made immediatelyWhen making a decision, DAB will have read the Contract, willneed less time to familiarise itself with issues, and can draw onactual knowledge of conditions on the Site
May be paid retainer for ‘doing nothing’ substantive if there are nodisputes
8/20/2019 Presentation FIDIC Conference
37/53
36
Ad hoc DAB
DAB only appointed after the dispute has arisen
Allows Parties to chose member(s) with expertise most suited toissues involved in the dispute
Only visits the Site after the dispute has arisen
Less familiar with the Project
But only paid when there are disputes
No power to issue an opinion
Deprives DAB of principal benefit of dispute board concept: ongoinginvolvement during course of contract
8/20/2019 Presentation FIDIC Conference
38/53
37
Appointment of the DAB – Sub-Clauses 20.2 20.3
Default: three members
Exceptions for Large Projects
Hong Kong Airport: DRB of six members plus a convener dealing with themajor contracts awarded by the Airports Authority. When disputes arose, apanel comprising either one or three members was chosen to hear thedispute depending on its size and nature.
Boston Big Dig: a three-member panel for each contract with disciplinary-specific expertise and dispute resolution/DRB experience. This was fixed atten years for a panel member and fifteen years for the Chairman. The paneldealt with 30 submissions with amounts in dispute ranging from US$100,000to US$20m.
Independent, ‘suitably qualified’ professionals
DAB members should not be employees of the Employer, the
Contractor or the Engineer
8/20/2019 Presentation FIDIC Conference
39/53
38
Appointment of the DAB – Sub-Clauses 20.2 20.3
Members are appointed by agreement of the Employer and
Contractor Tripartite Dispute Adjudication Agreement
DAB may comprise of either one or three members
If the DAB is to comprise three persons, each party shall nominateone member for the approval of the other party
The Chairman is generally chosen by the parties in consultationwith the party-appointed members
8/20/2019 Presentation FIDIC Conference
40/53
39
Failure to agree on the DAB – Sub-Clause 20.3
If the parties fail to agree on the sole member of the DAB, fail tonominate their members to a three-person DAB, or fail to agreeupon the appointment of the chairman resort to the appointing entity named in the Appendix toTender
Even when there are no further specific rules, appointingauthorities have their own regulations and preferences:
ICC will usually appoint a chairman who is not a national ofthe country of origin of either Party
The Dispute Board Federation usually appoints theChairman first and then select the other two members inconsultation with him/her
8/20/2019 Presentation FIDIC Conference
41/53
40
Failure to agree on the DAB
Polish experience
Supreme Court (12.01.2012, IV CSK 219/11) Failure to agree on a new Dispute Adjudication
Board is not a valid reason to terminate the
contract under FIDIC Subclauses 16.2 (b) or (d)
8/20/2019 Presentation FIDIC Conference
42/53
41
Nature of a DAB decision
Clause 20 of the Yellow Book:
20.4 Obtaining Dispute Adjudication Board’s Decision
“… Within 84 days after receiving such reference … or
within such other period as may be proposed by theDAB and approved by both Parties, the DAB shallgive its decision … .
… If either Party is dissatisfied with the DAB’s
decision, then either Party may, within 28 days afterreceiving the decision, give notice to the other Partyof its dissatisfaction.”
8/20/2019 Presentation FIDIC Conference
43/53
42
Nature of a DAB decision
Decision binding “unless and until it shall be revised
in an amicable settlement or arbitral award”
Parties must “promptly give effect” to decision
Decision becomes final and binding unless one Party givesthe other Party notice of dissatisfaction within28 days
Once final, decision cannot be challenged at arbitration
8/20/2019 Presentation FIDIC Conference
44/53
43
Enforcement of a DAB’s decision - arbitration
If no notice of dissatisfaction is given, a Party may refer the failure ofthe other Party to comply with the decision directly to arbitration (SC20.7)
No need to refer the failure back to the DAB
No need to attempt amicable settlement or wait for 56 days
If notice of dissatisfaction is given:
Party may include in an arbitration commenced under Sub-Clause 20.6 a claim for an interim award to enforce the decisionof the DAB
Also possible support from the courts
8/20/2019 Presentation FIDIC Conference
45/53
44
Enforcement of a DAB’s decision
There is a debate about the binding status of DAB’sdecision
local law: ‘final and binding decision’ reserved for arbitralawards
Singapore High Court in PT Perusahaan Gas Negara(Persero) TBK v CRW Joint Operation [2010] SGHC 202
DAB’s decision, though binding on the parties, non-enforceable through arbitration
Many Civil Codes encourage the Parties to resolves thedisputes within the Contract and through ADR procedures -DAB decision as a facilitated settlement?
8/20/2019 Presentation FIDIC Conference
46/53
45
Effectiveness of Dispute Boards
“the statistics show that if there is an operational Dispute
Board in existence on a project close to 99% of alldisputes referred to it will be successfully resolved withinless than 90 days and at a cost of about 2% of theamount of the dispute”
Dr. Cyril Chern, Dispute Board Federation
C. Chern , The Dispute Board Federation and the Role of Dispute Boards in Construction –
Benefits without Burden, Revista del Club Español del Arbitraje , Volume 2010, Issue 9, p. 5
8/20/2019 Presentation FIDIC Conference
47/53
46
International Arbitration and FIDIC
8/20/2019 Presentation FIDIC Conference
48/53
47
Construction Arbitration
Construction disputes represent a large share of arbitrationmarket
ICC: ‘In 2010 (…) Construction and engineering disputesaccounted for almost 17% of the total caseload ’
ICC International Court of Arbitration Bulletin
Vol 22/Number 1-2011
The highest volume of cases of any industry sector
Similarly in 2009 - 15%ICC International Court of Arbitration Bulletin - Vol. 21/1 - 2010
8/20/2019 Presentation FIDIC Conference
49/53
48
International Arbitration in the FIDIC forms -
model clause
20.6 Arbitration
“
Unless settled amicably, any dispute in respect of which the DAB’s
decision if any) has not become final and binding shall be finally
settled by international arbitration. Unless otherwise agreed by both
Parties:
a) the dispute shall be finally settled under the Rules ofArbitration of the International Chamber of Commerce,
b) the dispute shall be settled by three arbitrators appointed in
accordance with these Rules, and
c) the arbitration shall be conducted in the language for
communications defined in Sub-Clause 1.4 [Law and Language].
…
”
No default option for seat of arbitration and procedural law
8/20/2019 Presentation FIDIC Conference
50/53
49
International Arbitration in the FIDIC forms
International Arbitration is the final stage in the disputeresolution process
Arbitration may be commenced during or after completion of theWork:
Where notice of dissatisfaction has been given in respectof a DAB’s decision and after the 56-day amicablesettlement period
Immediately if no DAB in place (SC 20.8)
Parties are bound by the obligations in the Contract, eventhough arbitration has commenced
Arbitral Tribunal issues a binding arbitral award which may beenforced internationally
8/20/2019 Presentation FIDIC Conference
51/53
50
Construction litigation in Poland
High Court in Warsaw, XXV Civil Division - Polish TCC?
The General Directorate of National Roads and Motorways(GDDKiA) has its seat in the court’s district
A natural process of specialisation of the Court’s judges has followed,together with logistic concerns such as…truckloads of files which
sometimes take an hour to be moved to the court room
Amounts in dispute reach over 1 billion PLN in a single case
Judges admit that arbitration is a better mode to hear such disputes.However, GDDKiA consistently deletes arbitration clauses from theFIDIC Clause 20 in favour of domestic litigation
8/20/2019 Presentation FIDIC Conference
52/53
51
Concluding remarks
8/20/2019 Presentation FIDIC Conference
53/53
52
K&L Gates Jamka sp.k.
Al. Jana Pawła II 25
00-854 Warsaw
tel: +48 22 653 4200www.klgates.com
Please visit our blog: www.disputeresolutionpoland.com