Presentation FIDIC Conference

  • Upload
    haneef

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/20/2019 Presentation FIDIC Conference

    1/53

    Copyright © 2012 by K&L Gates LLP. All rights reserved.

    Construction as Investment

    Kyiv, 20 February 2013

    Dispute Avoidance and Resolutionunder FIDIC Rules and Procedure:

    Polish Experience

  • 8/20/2019 Presentation FIDIC Conference

    2/53

    1

    ROADMAP OF OUR PRESENTATION

    I.Introductory remarks

    II. How to process a claim under the FIDIC Conditions?

    1. FIDIC Rules and Procedure2. Employer’s & Contractor’s claims3. Time bars in theory and practice

    III. Dispute Avoidance and Early Resolution - Dispute Adjudication Board (DAB)

    1. DABs – Concept and background2. Models of DABs in FIDIC (standing and ad hoc DABs)

    3. Legal effects and enforcement of DAB’s decisions

    IV. Arbitration/Litigation

    1. Construction arbitration - a growing industry2. Arbitration under FIDIC Conditions

    3. Polish experience - XXV Division in the Warsaw High Court- a specialized construction court?

    V. Final remarks

  • 8/20/2019 Presentation FIDIC Conference

    3/53

    2

    "Better to prevent than to cure"old French proverb (Mieux vaut prévenir que guérir.)

  • 8/20/2019 Presentation FIDIC Conference

    4/53

    3

    Conflict is a fact of life… and is inevitable

  • 8/20/2019 Presentation FIDIC Conference

    5/53

    4

    Introductory remarks

    Dispute Avoidance preferred

    The FIDIC Update Task Group recommends the use ofa standing DAB 

    ”The sooner, the better!” 

    Multi-tier dispute resolution (escalation mechanism):

    Engineer 

    DAB/Mediation

     Arbitration/Litigation

  • 8/20/2019 Presentation FIDIC Conference

    6/53

    5

    Effective conflict management

    1 2 3Dispute

    communicated

    to the other

    party

    Negotiation

    Engineer’s

    Decision

    Consensus-

    oriented DR

    Method

    Enhanced-

    negotiation/

    Mediation/

    Conciliation

    Dispute Board

    Arbitration/

    Litigation

  • 8/20/2019 Presentation FIDIC Conference

    7/53

    6

    Employer’s Claims

    The claims ‘available’ to the Employer will depend upon

    the specific FIDIC form, since the risk allocation acrossthe FIDIC suite alters considerably; and

    the precise contract terms used by the parties, i.a., in theParticular Conditions

    The Employer does not have a general right to set-off 

    Clause 2.5: Notice of Claims

    The Employer’s right to make deductions is subject to thegiving of notice “as soon as practicable” after becomingaware of an event or circumstances giving rise to a claim

  • 8/20/2019 Presentation FIDIC Conference

    8/53

    7

    Contractor’s claims (Sub-Clause 20.1)

    The Contractor must:

    notify a claim not later than 28 days after the Contractorbecame aware or should have become aware of theevent or circumstance;

    submit a ‘fully detailed claim and full supporting

    particulars’ within 42 days after it became aware (orshould have become aware); and

    keep ‘contemporary records’ to substantiate the claimand allow the Engineer to inspect these records and

    obtain copies.

  • 8/20/2019 Presentation FIDIC Conference

    9/53

    8

    Contractor’s claims (Sub-Clause 20.1)

    The Engineer must:

    respond within 42 days of receiving a claim or furtherparticulars either approving the claim or disapproving itwith ‘detailed comments’;

    In any determination under Sub-Cl. 3.5,

    consult with both parties in an endeavour to reachagreement; and

    if agreement cannot be achieved, make a fairdetermination in accordance with the contract

    ‘taking due regard of all relevant circumstances’

  • 8/20/2019 Presentation FIDIC Conference

    10/53

    9

    Contractor’s claims: Time-Bar Limitation

    ‘If the Contractor fails to give notice of a claim within such period of 28 days, the Time forCompletion shall not be extended, theContractor shall not be entitled to additional

    payment, and the Employer shall be dischargedfrom all liability in connection with the claim ’(Sub-Cl. 20.1)

  • 8/20/2019 Presentation FIDIC Conference

    11/53

    10

    What types of claims are barred?

    ‘…any extension of the time for Completion and/orany additional payment, under any Clause of theseConditions or otherwise in connection with theContract’ (Sub-Cl. 20.1)

    The provision is broad enough to cover most typesof claims

  • 8/20/2019 Presentation FIDIC Conference

    12/53

    11

    Are the FIDIC time bar provisions too onerous?

    European International Contractors: ‘unduly harsh’

    In theory: Time bars facilitate good claims management,

    allowing issues to be aired and settled at the

    working level while they are fresh in peoples’minds

    They also facilitate effective mitigation,allowing the parties to take action to minimise

    the costs and delay of a notified claim

  • 8/20/2019 Presentation FIDIC Conference

    13/53

    12

    Are the FIDIC time bar provisions too onerous?

    Multiplex Construction (UK) Ltd v Honeywell

    Systems [2007] EWHC 447 (TCC):

    “… Contractual terms requiring a contractor to give

    prompt notice of delay serve a valuable purpose; suchnotice enables matters to be investigated while they arestill current. Furthermore, such notice sometimes givesthe employer the opportunity to withdraw instructionswhen the financial consequences become apparent” 

  • 8/20/2019 Presentation FIDIC Conference

    14/53

    13

    Enforceability of time bars by DABs

    DABs, where appropriate, enforce the time bars

    FIDIC Gold Book 2008 – DAB has discretion to overridethe time bar:

    Sub-Clause 20.1(a):‘…However, if the Contractor considers there arecircumstances which justify the late submission, hemay submit the details to the DAB for a ruling. If the

    DAB considers that, in all the circumstances, it is fairand reasonable that the late submission be accepted,the DAB shall have the authority to overrule therelevant 28 day limit …’ 

  • 8/20/2019 Presentation FIDIC Conference

    15/53

    14

    Enforceability of time bars – Arbitral Tribunals

     Arbitration clause may be ineffective, if contractual prerequisites

    to arbitration have not been fulfilled

    Decision on Jurisdiction by an arbitral tribunal under the Rules of the Court of Arbitration at the Polish Confederation of PrivateEmployers Lewiatan, publ. in Arbitration e-Review no. 1(2009) 

     Award in Hamburg Chamber of Commerce of 14 July 2006 ,2007 SchiedsVZ 55

    ‘ A referral to arbitration is not valid where the DAB procedure

    has not been attempted first ’Glover J., Understanding the New FIDIC Red Book – A

    clause-by-clause commentary , London Sweet&Maxwell2006, p. 390

  • 8/20/2019 Presentation FIDIC Conference

    16/53

    15

    Enforceability of time bars – state courts

    Common law jurisdictions

    Enforceable on the basis of the parties’ agreement

    Skub-clause 20.1 notice is a condition precedent to the rightto recover either time or money

    Einstein J in Aiton Pty Ltd v Transfield Pty (1999) SC NSW

    236; Mr Justice Ramsey in Holloway v Chancery Mead Ltd [2007] EWHC 2495 (TCC)

    The prevention principle?

     A party should not benefit from its own breach of contract

    Civil law jurisdictions 28-day time-limit leading to a loss of a claim may be

    unenforceable due to mandatory statute of limitations rules in civillaws of certain jurisdictions

  • 8/20/2019 Presentation FIDIC Conference

    17/53

    16

    Enforceability of time bars – Example: Germany

    Germany - Section 307 of BGB (German Civil Code)

    ‘(1) Provisions in standard business terms are ineffective if,contrary to the requirement of good faith, they unreasonablydisadvantage the other party to the contract with the user.

    (2) An unreasonable disadvantage is, in case of doubt, to beassumed to exist if a provision is not compatible with essentialprinciples of the statutory provision from which it deviates’ 

    The standard limitation period is three years (Section 195 BGB)

    Is then the 28-day time bar ‘compatible with essentialprinciples of the statutory provision ’?

  • 8/20/2019 Presentation FIDIC Conference

    18/53

    17

    Enforceability of time bars – Example: Poland

    Poland - Article 119 of Polish Civil Code

    ‘Periods of limitation may not be shortened orprolonged by a legal act.’ 

    Subclause 20.1 time bar (result: loss of the claim)goes even further than the statute of limitation(result: claim exists, but is not enforceable via courtorder)

    Since the statute of limitation cannot be contractually

    modified, the same should apply to a time bar (aminori ad maius )

    Result: Subclause 20.1 time bar null and void?

  • 8/20/2019 Presentation FIDIC Conference

    19/53

    18

    Enforceability of time bars: Poland – Case Law

     Appellate Court in Warsaw (30.05.2011, I ACz 700/11)

    FIDIC notice requirement is a contractual time bar and not amodification to a statute of limitations rules

    FIDIC is commonly used in the industry, and constitutes anintegral part of the parties’ freedom of contract

    Notice of claim requirement - as a precondition to arbitration -is not contrary to the Polish public policy

    Regional Court in Warsaw (7.03.2012, XXV C 249/11)

    Subclause 20.1 given full effect

    Claims notified after the agreement has been performed are

    time barred a ‘fully detailed claim’ includes a specific calculation of

    damage, not a mere assertion of extra costs incurred

  • 8/20/2019 Presentation FIDIC Conference

    20/53

    19

    Enforceability of time bars: Poland – Case Law

    Regional Court in Warsaw (13.07.2011, XXV C 701/10)

    28-day time bar contradicts the Civil Code provisions on thestatute of limitations and is null and void in this respect

     A contractor, despite lack of notice, does not lose its claims. It ishowever contractually liable for breach of contract (breach of aSubclause 20.1 condition)

    FIDIC Conditions are of a common law origin and must beadjusted to mandatory laws of a given jurisdiction

    Regional Court in Warsaw (11.06.2012, XXV C 567/11)

    Similar arguments and conclusion as above

    The law is not settled as the Supreme Court has not yet spoken onthis issue

  • 8/20/2019 Presentation FIDIC Conference

    21/53

    20

    Engineer’s determination under scrutiny -

    the Dispute Adjudication Board

  • 8/20/2019 Presentation FIDIC Conference

    22/53

    21

    DAB Procedure

    under the FIDIC Red Book (Clause 20)

    Step 1: Referral of a “dispute” to a DAB

    Step 2: DAB must decide within 84 days by a “binding”

    decision

    Step 3: Notice of dissatisfaction within 28 days or else

    “final and binding”

    Step 4: Maximum of 56 days for amicable settlement

    Step 5: If not settled by above steps, international arbitration

  • 8/20/2019 Presentation FIDIC Conference

    23/53

    22

    Overview of FIDIC dispute resolution provisions

    DAB to give

    notice of

    decision

    Notice of

    dissatisfaction

    Arbitration

    can be

    commenced

    84 days

    28 days

    If Engineer’s Decision

    becomes final and binding

    but a Party fails to comply

    Arbitration can

    be commenced

    56 days

    Amicable

    Settlement

    Referral of matters

    in dispute to DAB

  • 8/20/2019 Presentation FIDIC Conference

    24/53

    23

    Dispute Boards

    Specifically designed and developed for large construction

    contracts; known under different names as: Dispute Review Boards (DRB)

    issues recommendations with no binding effect

    Dispute Adjudication Boards (DAB) issues decisions which are binding on an interim basis

    Combined Dispute Boards (CDB)

    Standing (or ad hoc ) panels of impartial experts who support parties in reaching consensus

    provide recommendations or

    render decisions

  • 8/20/2019 Presentation FIDIC Conference

    25/53

    24

    Dispute Boards - Historical background

    First developed in the 1970s and 1980s in the US

    Eisenhower Tunnel (Colorado), the Mount Baker Ridge HighwayTunnel (Seattle, Washington), and the Chambers Creek Tunnel(Tacoma, Washington)

    In 1981, the El Cajon Hydroelectric Project in Hondurasthe first large international construction contract where a DisputeBoard was effectively utilized

    In 1995, the World Bank made DRBs mandatory for all IBRD-financed

    projects over US$50m

    In 1997 the Asian Development Bank and EBRDfollowed with similar decisions

  • 8/20/2019 Presentation FIDIC Conference

    26/53

    25

    FIDIC Dispute Adjudication Boards

    In 1995, FIDIC started with the introduction of the use of Dispute

    Boards in the Orange Book

    In 1996, Dispute Boards were incorporated into the 1992 FourthEdition of the Red Book though its Supplement

    In 1999, the suite of FIDICs three major contracts, the 1999 RedBook, the 1999 Yellow Book and the 1999 Silver Book, have alladopted this concept as the first step in the dispute resolutionmechanism, albeit in different forms

  • 8/20/2019 Presentation FIDIC Conference

    27/53

    26

  • 8/20/2019 Presentation FIDIC Conference

    28/53

    27

  • 8/20/2019 Presentation FIDIC Conference

    29/53

    28

    Eisenhower Tunnel (Colorado, US)

    the Eisenhower Tunnel, completed in 1979, remains

    the highest vehicular tunnel in the US first broadly discussed case in which Dispute Board

    was effectively used

    Source: www.wikipedia.com

  • 8/20/2019 Presentation FIDIC Conference

    30/53

    29

    Ertan Project (China)

  • 8/20/2019 Presentation FIDIC Conference

    31/53

    30

    Hong Kong International Airport

     A HK$50 billion investment, HKIA has been one of

    the largest engineering and architectural projects inthe world

    One of the largest hubs: in 2011, 53.9 millionpassengers used HKIA and some 3.9 million tonnesof air cargo passed through HKIA

  • 8/20/2019 Presentation FIDIC Conference

    32/53

    31

    Channel Tunnel Rail Link Project

    a US$5 billion concession project in the UK on which constructionstarted in October 1998

    two panels:

    a technical panel comprising engineers (construction relateddisputes) and

    a finance panel comprising accountants and financiers (disputes

    concerning the financial provisions of the concession agreement)

  • 8/20/2019 Presentation FIDIC Conference

    33/53

    32

    Nature of the DAB in the FIDIC forms

    Clause 20 of the Yellow Book:

    20.4 Obtaining Dispute Adjudication Board’s Decision

    “If a dispute (of any kind whatsoever) arises betweenthe Parties in connection with, or arising out of, theContract or the execution of the Works … then after a

    DAB has been appointed pursuant to Sub-Clauses 20.2[Appointment of the Dispute Adjudication Board] and20.3 [Failure to Agree Dispute Adjudication Board],either Party may refer the dispute in writing to the DAB

    for its decision, with a copy to the other Party …

  • 8/20/2019 Presentation FIDIC Conference

    34/53

    33

    Principal features of the DAB in the FIDIC forms

    Express duty of independence and impartiality on the DAB members

    DAB’s decision obtainable within a relatively short time – 84 daysfrom reference

    Decision binding on the Parties “unless and until it shall be revised in

    an amicable settlement or arbitral award” (SC 20.4)

  • 8/20/2019 Presentation FIDIC Conference

    35/53

    34

    Nature of the DAB in the FIDIC forms

    Two different models:

    ‘Standing’ – as provided for in Red & Gold Book GeneralConditions

    ‘Ad hoc’ – as provided for in Yellow & Silver Book GeneralConditions

    Models are alternatives – but both include dispute adjudicationrole

    Most appropriate model depends on particular project

    Fees split equally between Parties

  • 8/20/2019 Presentation FIDIC Conference

    36/53

    35

    Standing DAB

    DAB appointed by Parties at outset of the Contract, and operatesthroughout its currency

    DAB visits the site regularly

    Many disputes resolved amicably before they require decision ofDAB

    Parties can jointly request opinions

    If dispute arises, referral can be made immediatelyWhen making a decision, DAB will have read the Contract, willneed less time to familiarise itself with issues, and can draw onactual knowledge of conditions on the Site

    May be paid retainer for ‘doing nothing’ substantive if there are nodisputes

  • 8/20/2019 Presentation FIDIC Conference

    37/53

    36

    Ad hoc DAB

    DAB only appointed after the dispute has arisen

     Allows Parties to chose member(s) with expertise most suited toissues involved in the dispute

    Only visits the Site after the dispute has arisen

    Less familiar with the Project

    But only paid when there are disputes

    No power to issue an opinion

    Deprives DAB of principal benefit of dispute board concept: ongoinginvolvement during course of contract

  • 8/20/2019 Presentation FIDIC Conference

    38/53

    37

    Appointment of the DAB – Sub-Clauses 20.2 20.3

    Default: three members

    Exceptions for Large Projects

    Hong Kong Airport: DRB of six members plus a convener dealing with themajor contracts awarded by the Airports Authority. When disputes arose, apanel comprising either one or three members was chosen to hear thedispute depending on its size and nature.

    Boston Big Dig: a three-member panel for each contract with disciplinary-specific expertise and dispute resolution/DRB experience. This was fixed atten years for a panel member and fifteen years for the Chairman. The paneldealt with 30 submissions with amounts in dispute ranging from US$100,000to US$20m.

    Independent, ‘suitably qualified’ professionals

    DAB members should not be employees of the Employer, the

    Contractor or the Engineer

  • 8/20/2019 Presentation FIDIC Conference

    39/53

    38

    Appointment of the DAB – Sub-Clauses 20.2 20.3

    Members are appointed by agreement of the Employer and

    Contractor  Tripartite Dispute Adjudication Agreement

    DAB may comprise of either one or three members

    If the DAB is to comprise three persons, each party shall nominateone member for the approval of the other party

    The Chairman is generally chosen by the parties in consultationwith the party-appointed members

  • 8/20/2019 Presentation FIDIC Conference

    40/53

    39

    Failure to agree on the DAB – Sub-Clause 20.3

    If the parties fail to agree on the sole member of the DAB, fail tonominate their members to a three-person DAB, or fail to agreeupon the appointment of the chairman resort to the appointing entity named in the Appendix toTender 

    Even when there are no further specific rules, appointingauthorities have their own regulations and preferences:

    ICC will usually appoint a chairman who is not a national ofthe country of origin of either Party

    The Dispute Board Federation usually appoints theChairman first and then select the other two members inconsultation with him/her 

  • 8/20/2019 Presentation FIDIC Conference

    41/53

    40

    Failure to agree on the DAB

    Polish experience

    Supreme Court (12.01.2012, IV CSK 219/11) Failure to agree on a new Dispute Adjudication

    Board is not a valid reason to terminate the

    contract under FIDIC Subclauses 16.2 (b) or (d)

  • 8/20/2019 Presentation FIDIC Conference

    42/53

    41

    Nature of a DAB decision

    Clause 20 of the Yellow Book:

    20.4 Obtaining Dispute Adjudication Board’s Decision

    “… Within 84 days after receiving such reference … or

    within such other period as may be proposed by theDAB and approved by both Parties, the DAB shallgive its decision … .

    … If either Party is dissatisfied with the DAB’s

    decision, then either Party may, within 28 days afterreceiving the decision, give notice to the other Partyof its dissatisfaction.”

  • 8/20/2019 Presentation FIDIC Conference

    43/53

    42

    Nature of a DAB decision

    Decision binding “unless and until it shall be revised

    in an amicable settlement or arbitral award”

    Parties must “promptly give effect” to decision

    Decision becomes final and binding unless one Party givesthe other Party notice of dissatisfaction within28 days

    Once final, decision cannot be challenged at arbitration

  • 8/20/2019 Presentation FIDIC Conference

    44/53

    43

    Enforcement of a DAB’s decision - arbitration

    If no notice of dissatisfaction is given, a Party may refer the failure ofthe other Party to comply with the decision directly to arbitration (SC20.7)

    No need to refer the failure back to the DAB

    No need to attempt amicable settlement or wait for 56 days

    If notice of dissatisfaction is given:

    Party may include in an arbitration commenced under Sub-Clause 20.6 a claim for an interim award to enforce the decisionof the DAB

     Also possible support from the courts

  • 8/20/2019 Presentation FIDIC Conference

    45/53

    44

    Enforcement of a DAB’s decision

    There is a debate about the binding status of DAB’sdecision

    local law: ‘final and binding decision’ reserved for arbitralawards

    Singapore High Court in PT Perusahaan Gas Negara(Persero) TBK v CRW Joint Operation [2010] SGHC 202

    DAB’s decision, though binding on the parties, non-enforceable through arbitration

    Many Civil Codes encourage the Parties to resolves thedisputes within the Contract and through ADR procedures -DAB decision as a facilitated settlement?

  • 8/20/2019 Presentation FIDIC Conference

    46/53

    45

    Effectiveness of Dispute Boards

    “the statistics show that if there is an operational Dispute

    Board in existence on a project close to 99% of alldisputes referred to it will be successfully resolved withinless than 90 days and at a cost of about 2% of theamount of the dispute” 

    Dr. Cyril Chern, Dispute Board Federation

    C. Chern , The Dispute Board Federation and the Role of Dispute Boards in Construction – 

    Benefits without Burden, Revista del Club Español del Arbitraje , Volume 2010, Issue 9, p. 5

  • 8/20/2019 Presentation FIDIC Conference

    47/53

    46

    International Arbitration and FIDIC

  • 8/20/2019 Presentation FIDIC Conference

    48/53

    47

    Construction Arbitration

    Construction disputes represent a large share of arbitrationmarket

    ICC: ‘In 2010 (…) Construction and engineering disputesaccounted for almost 17% of the total caseload ’

    ICC International Court of Arbitration Bulletin

    Vol 22/Number 1-2011

    The highest volume of cases of any industry sector 

    Similarly in 2009 - 15%ICC International Court of Arbitration Bulletin - Vol. 21/1 - 2010

  • 8/20/2019 Presentation FIDIC Conference

    49/53

    48

    International Arbitration in the FIDIC forms -

    model clause

    20.6 Arbitration

    Unless settled amicably, any dispute in respect of which the DAB’s

    decision if any) has not become final and binding shall be finally

    settled by international arbitration. Unless otherwise agreed by both

    Parties:

     a) the dispute shall be finally settled under the Rules ofArbitration of the International Chamber of Commerce,

     b) the dispute shall be settled by three arbitrators appointed in

    accordance with these Rules, and

     c) the arbitration shall be conducted in the language for

    communications defined in Sub-Clause 1.4 [Law and Language].

    No default option for seat of arbitration and procedural law

  • 8/20/2019 Presentation FIDIC Conference

    50/53

    49

    International Arbitration in the FIDIC forms

    International Arbitration is the final stage in the disputeresolution process

     Arbitration may be commenced during or after completion of theWork:

    Where notice of dissatisfaction has been given in respectof a DAB’s decision and after the 56-day amicablesettlement period

    Immediately if no DAB in place (SC 20.8)

    Parties are bound by the obligations in the Contract, eventhough arbitration has commenced

     Arbitral Tribunal issues a binding arbitral award which may beenforced internationally

  • 8/20/2019 Presentation FIDIC Conference

    51/53

    50

    Construction litigation in Poland

    High Court in Warsaw, XXV Civil Division - Polish TCC?

    The General Directorate of National Roads and Motorways(GDDKiA) has its seat in the court’s district

     A natural process of specialisation of the Court’s judges has followed,together with logistic concerns such as…truckloads of files which

    sometimes take an hour to be moved to the court room

     Amounts in dispute reach over 1 billion PLN in a single case

    Judges admit that arbitration is a better mode to hear such disputes.However, GDDKiA consistently deletes arbitration clauses from theFIDIC Clause 20 in favour of domestic litigation

  • 8/20/2019 Presentation FIDIC Conference

    52/53

    51

    Concluding remarks

  • 8/20/2019 Presentation FIDIC Conference

    53/53

    52

    K&L Gates Jamka sp.k.

     Al. Jana Pawła II 25

    00-854 Warsaw

    tel: +48 22 653 4200www.klgates.com

    [email protected]

    [email protected]

    Please visit our blog: www.disputeresolutionpoland.com