Upload
habao
View
217
Download
0
Embed Size (px)
Citation preview
DRAFT REPORT GEOTECHNICAL STUDY
MISSION BAY SHORELINE PROTECTION PROJECT PORT OF SAN FRANCISCO, CALIFORNIA
Prepared for:
COAST & HARBOR ENGINEERING, INC.
Prepared By: AGS, INC.
JULY 2009
111 New Montgomery Street, Suite 500, San Francisco, CA 94105 Phone (415) 777-2166 Fax (415) 777-2167
DRAFT REPORT GEOTECHNICAL STUDY
MISSION BAY SHORELINE PROTECTION PROJECT PORT OF SAN FRANCISCO, CALIFORNIA
AGS Job No. KI0301
Prepared for:
COAST & HARBOR ENGINEERING, INC.
Prepared By: AGS, INC.
JULY 2009
AGS
1
TABLE OF CONTENTS
1. INTRODUCTION ...................................................................................................... 3
1.1. PROJECT DESCRIPTION ............................................................................ 3
1.2. WORK PERFORMED ................................................................................... 3 1.2.1. Review of Available Data ............................................................................... 4 1.2.2. Field Exploration ............................................................................................ 4 1.2.3. Geotechnical Laboratory Testing ................................................................... 5 1.2.4. Engineering Analyses and Report Preparation .............................................. 5
2. FINDINGS ................................................................................................................ 6
2.1 SITE CONDITIONS AND BACKGROUND .................................................... 6
2.2 GEOLOGY .................................................................................................... 7
2.3 FAULTS AND SEISMICITY ........................................................................... 8
2.4 SUBSURFACE CONDITIONS .................................................................... 11 2.4.1. Previous Exploration .................................................................................... 11 2.4.2. AGS Investigation ........................................................................................ 12
2.5 GROUNDWATER ....................................................................................... 13
3. RECOMMENDATIONS .......................................................................................... 15
3.1 GENERAL ................................................................................................... 15
3.2 SEISMIC DESIGN CONSIDERATIONS ...................................................... 16 3.2.1. Fault Rupture ............................................................................................... 16 3.2.2. Maximum Earthquake.................................................................................. 16 3.2.3. Estimated Earthquake Ground Motions ....................................................... 16
3.2.3.1.Deterministic Methods ......................................................................... 16 3.2.3.2.Probabilistic Methods ........................................................................... 17
3.2.4. Liquefaction Hazard .................................................................................... 17 3.2.5. Consequences of liquefaction ..................................................................... 18
3.2.5.1.Seismically-Induced Settlement ........................................................... 19 3.2.5.2.Lateral Deformation ............................................................................. 20
3.2.6. Liquefaction Mitigation ................................................................................. 21 3.2.7. Seismically-Induced Lateral Earth Pressures .............................................. 24
3.3 EXCAVATION AND EARTHWORK ............................................................. 25 3.3.1. Site Preparation ........................................................................................... 25 3.3.2. Fills and Backfills ......................................................................................... 26 3.3.3. Temporary Excavations ............................................................................... 26
3.4 FOUNDATIONS .......................................................................................... 27 3.4.1. General ........................................................................................................ 27 3.4.2. Renovation Scheme .................................................................................... 28
AGS
2
3.5 SETTLEMENT ............................................................................................. 29
3.6 PERMANENT RETAINING STRUCTURES ................................................ 29
3.7 RESISTANCE TO LATERAL LOADS .......................................................... 30
3.8 EXISTING STRUCTURS ............................................................................. 30
3.9 CONSTRUCTION CONSIDERATIONS ...................................................... 31 3.9.1. General ........................................................................................................ 31 3.9.2. Geotechnical Services During Construction ................................................ 31
4. CLOSURE.............................................................................................................. 33
5. REFERENCES ....................................................................................................... 34 TABLES Table 1 - Historical Earthquakes ..................................................................................... 9 Table 2 - Active Fault Seismicity ................................................................................... 10 Table 3 - Summary of Seismically-Induced Settlements ............................................... 19 Table 4 - Summary of Liquefaction-Induced Lateral Deformations ............................... 21 Table 5 - Summary of Liquefaction Mitigation Techniques ............................................ 24 Table 6 - Estimated Settlements ................................................................................... 29 Table 7 - Allowable Passive Pressures ......................................................................... 30 PLATES Plate 1 - Site Location Map Plate 2 - Subsurface Exploration Location Map Plate 3 - Earthquake Epicenters and Fault Map Plate 4 - Preliminary Design Pressure Data Near Borings B-1 and B-3 Plate 4 - Preliminary Design Pressure Data Near Boring B-2 APPENDICES Appendix A - FIELD EXPLORATION Appendix B - GEOTECHNICAL FIELD AND LABORATORY TESTING Appendix C - LIQUEFACTION POTENTIAL
AGS
3
1. INTRODUCTION
1.1. PROJECT DESCRIPTION
This report presents the results of our geotechnical study for the Shoreline Protection
project at Mission Bay, San Francisco, California. The shoreline location east of Terry
Francois Boulevard and south of Pier 54 is shown on Plate 1 – Site Location Map.
This report presents findings of the subsurface exploration and gives our geotechnical
engineering conclusions and recommendations regarding the proposed project.
Conclusions and recommendations were developed with regard to geoseismic hazards,
seismic design parameters, site improvements, earthwork recommendations, foundation
types, lateral earth pressures, resistance to lateral loads, and construction monitoring. Of
particular importance to the design of the project is an assessment of the liquefaction
potential of the fills behind the seawall and possible lateral deformations and seismically
induced settlements induced from liquefaction.
The conclusions and recommendations presented in this report are based on the
subsurface conditions encountered at the locations of the three borings drilled during field
exploration programs, available geotechnical information obtained by others at the site and
its vicinity, and available geologic and seismologic information for the site vicinity. These
conclusions and recommendations should not be extrapolated to other areas, or used for
other facilities without our prior review.
1.2. WORK PERFORMED
As stated in our April 2009 proposal, the purpose of our study was to explore and evaluate
subsurface conditions. The work performed for this project included the following:
AGS
4
1.2.1. Review of Available Data
Available published geotechnical, geologic, and seismologic data, as well as the existing
unpublished data contained in our files pertinent to the project site and its vicinity were
reviewed. We reviewed the 1996 Trans Pacific Geotechnical Report for Improvements at
Pier 52, the Port of San Francisco Boring Profiles completed from China Basin to 25th
Street (1961), and also the Port of San Francisco Seawall Details (Revised 1957) and
Alternate A Wharf Alteration Pier 54 Drawings (1954). Complete citations are listed in the
References section of this report.
1.2.2. Field Exploration
Following marking of the planned boring locations by AGS, Underground Service Alert
(USA) was notified in order that utility companies mark their buried utilities. Based on the
ground markings, none of the originally planned boring locations required adjustment to
avoid utilities. V&W Drilling Inc. of Lodi, California completed the drilling on June 9 and 10,
2009. The field exploration program was performed under technical supervision of a
qualified geologist from our firm who completed logs of each test boring which document
drilling progress and record the encountered subsurface conditions.
Modified California (MC) samples, Standard Penetration test (SPT) samples, and Shelby
tubes were obtained from each boring, as appropriate for the various soils encountered.
Details of the subsurface exploration, including the Logs of Test Borings, are presented in
Appendix A. Boring locations are shown on Plate 2 – Subsurface Exploration Location
Map.
All three borings were located landward (west) of the seawall and were extended to depths
ranging from 26.5 to 36.5 feet below the existing ground surface (bgs). Each borehole was
backfilled with cement grout. Following backfilling and allowance of settlement the ground
surface at each boring location was restored to grade.
AGS
5
1.2.3. Geotechnical Laboratory Testing
AGS performed a laboratory testing program on selected soil samples obtained during the
field exploration program. The laboratory tests included moisture content, dry density,
sieve analyses, and Atterberg limits as appropriate for the various soils encountered.
Details of the geotechnical laboratory testing program are included in Appendix B -
Geotechnical Laboratory Testing.
1.2.4. Engineering Analyses and Report Preparation
Engineering analyses were performed based on the field and laboratory data to develop
geotechnical conclusions and recommendations for the design and construction of the
proposed project. Our geotechnical findings, conclusions, and recommendations, along
with the supporting field and laboratory data, are presented in this engineering report. The
report addresses the following:
Subsurface soil conditions;
Groundwater elevations;
Local geologic conditions;
Faults and seismicity;
Peak ground surface accelerations for the controlling maximum credible
earthquake;
Geoseismic hazardous including liquefaction potential, seismically-induced
settlements, and seismically-induced lateral deformations;
Liquefaction mitigation and soil improvement recommendations;
Existing foundation capacities;
Lateral loads on the seawall;
Resistance of foundation to lateral loads;
Design criteria for new foundation; and
Construction considerations.
AGS
6
2. FINDINGS
2.1 SITE CONDITIONS AND BACKGROUND
The project shoreline is east of the Mission Bay Redevelopment area, south of China Basin
and north of Central Basin. The project shoreline extends approximately 1,500 feet south
of Pier 54, next to Terry Francois Boulevard north of the Mariposa Street Intersection.
The northern half of the project site shoreline is protected by a concrete seawall which was
originally designed around 1912 and was partially reconstructed around 1954 (FEMA,
2007). According to our discussion with you, the existing seawall is founded on shallow
spread footings. Rip rap, concrete rubble, and debris are used as a wave break in front of
the seawall. The northern reach of the shoreline behind the seawall is paved with concrete
or asphalt and includes a pedestrian / bicycle trail next to Pier 54, abandoned construction
staging area, construction yard and a one-story wood-framed office, and a makeshift
residence. The fill materials were undercut causing large voids beneath the seawall. These
voids were up to 6 feet in length and up to 2 feet in height. The central and southern portion
of the shoreline is dominated by the remains of Pier 64, including the remains of some large
concrete abutments and walls which would have supported the pier. This area is not paved
and is fenced in by an 8-foot high chain link security fence. The south end of the project
shoreline is protected by a wooden seawall and is bounded by Agua Vista Park, where a
fishing pier extends approximately 80 feet offshore.
Mission Bay was once an embayment at the mouth of Mission Creek, at which time the
shoreline was located near the present day alignment of Interstate 280 (U.S. Coast Survey,
1853). Today the Mission Bay area represents one of the largest areas of historical landfill
in San Francisco. During the 19th century a land bridge was constructed to connect the
north and south sides of the bay by railroad in the vicinity of the present day 3rd Street
corridor. The unfilled portion of the former bay west of 3rd Street formed a lagoon centered
approximately ¼ mile west of the project shoreline (1895 and 1899 United States
AGS
7
Geological Survey ,USGS, topographic maps). Following the 1906 earthquake the lagoon
was filled, and by 1915 the USGS topographic map shows the shoreline extended as far
east as it exits at the present time. At that time Pier 54 and the original seawall were
already constructed.
2.2 GEOLOGY
The northern San Francisco peninsula, including the project area, is part of the Coast
Ranges geomorphic province. The province is a seismically active region characterized by
northwest-trending mountains, valleys, and faults. The peninsula is bordered on the east
by San Francisco Bay, a drowned, northwest-trending structural depression. The bay and
much of the peninsula are underlain by the late Mesozoic age rocks of the Franciscan
Complex.
Beneath San Francisco Bay, and along much of its margin, the Franciscan bedrock is
overlain by a young, geologically unconsolidated sedimentary sequence, which, in places,
exceeds 400 feet in thickness. The sequence is often subdivided (Goldman, 1969) into
three "natural" units - Older Bay Mud (or old bay clay), Bay Side Sand, and Younger Bay
Mud. In the area of Mission Bay artificial fill has been placed along the margins of the bay
to claim marshland and land once covered by shallow water.
Along the project shoreline the bedrock surface beneath the Mission Bay Basin is estimated
to occur from 100 to 150 feet below the existing ground surface (Goldman, 1969).
Shallower bedrock is found to the northeast and southwest, in the respective vicinities of
Mission Rock and Potrero Hill. Serpentine rock of the Franciscan Formation is mapped at
the Mission Rock, located approximately 1,400 feet northeast of the Pier 54 abutment.
Sandstone, shale, siltstone and serpentine of the Franciscan Formation are mapped across
the northeastern slope of Potrero Hill, located more than 1100 feet west and southwest of
the southern end of the project shoreline (Graymer et al, 2006). Mission Bay Basin is
bounded to the west by the historical delta of Mission Creek, where two small creek
systems once flowed into San Francisco Bay near the present day alignment of Interstate
AGS
8
280 (U.S. Coastal Survey, 1853). Underneath the project shoreline the artificial fill of
Mission Bay is underlain by the previously discussed young, geologically unconsolidated
sequence of alluvium. This includes areas of very soft Younger Bay Mud which are
estimated to form an approximately 20 to 40 foot thick layer beneath the artificial fill
(Goldman, 1969).
2.3 FAULTS AND SEISMICITY
The project area is located in a seismically active region which has been subjected to
several strong earthquakes during historic time. Active faults in the area are shown on
Plate 3 – Earthquake Epicenters and Fault Map.
The San Andreas Fault, which is situated about 12.7 km southwest of the site, dominates
the tectonics, geology, and physiography of the San Francisco Bay region. The Hayward
Fault is situated about 16 km northeast of the site. Other major active faults, which could
cause significant shaking at the project site, are the San Gregario, Mount Diablo Thrust,
Concord, Calaveras, and Rodgers Creek Faults. Active faults that are pertinent to the site
and historic earthquakes attributed to each fault are listed in Table 1 - Historical
Earthquakes.
AGS
9
TABLE 1 HISTORICAL EARTHQUAKES
Date
Magnitude Fault Epicenter Area
June 10, 1836 6.51, 6.84 San Andreas San Juan Bautista
June 1838 7.51, 7.04 San Andreas San Juan Bautista
Nov. 26, 1858 6.254 Calaveras San Jose Area
October 8, 1865 6.32, 6.54 San Andreas South Santa Cruz Mountains
October 21, 7.02,4 Hayward Berkeley Hills, San Leandro
February 17, 6.04 San Andreas Los Gatos
April 19, 1892 6.54 Uncertain Vacaville
April 21, 1892 6.254 Uncertain Winters
June 20, 1897 6.254 Calaveras Gilroy
March 31, 1898 6.54 Uncertain Mare Island
May 19, 1889 6.254 Uncertain Antioch
April 18, 1906 7.93 San Andreas Golden Gate
July 1, 1911 6.62, 6.54 Calaveras Diablo Range, East of San Jose
October 22, 6.14 San Gregorio? Monterey Bay
April 24, 1984 6.14 Calaveras Morgan Hill
October 17, 7.14 San Andreas Loma Prieta, Santa Cruz
(1) Borchardt & Toppozada (1996) (2) Toppozada et al (2000) (3) Petersen (1996) (4) Ellsworth, W.L. (1989)
The maximum moment magnitude earthquake (Mmax) is defined as the largest earthquake
that a given fault is considered capable of generating. The Mmax on the San Andreas
Fault would be a magnitude 7.9 event occurring approximately 12.7 km from the project site
(USGS, 2008). The Mmax on the Hayward Fault would be a magnitude 7.1 event occurring
approximately 16 km from the project site (USGS, 2008). The Mmax given for the Hayward
Fault is based on a rupture of the entire length of the fault. The seismicity associated with
each pertinent fault, including estimated slip rates, is summarized below in Table 2 - Fault
Seismicity.
AGS
10
TABLE 2 ACTIVE FAULT SEISMICITY
Fault Name
Distance to Site1
(Km)
Maximum Moment
Magnitude2
Contributing Segments
Slip Rate 2
(mm/year)
San Andreas
12.7 7.9 SAO, SAN, SAP, SAS 24 3
Hayward
16 7.1 HN, HS 9 2
San Gregorio
19 7.3 SGN, SGS 7 3
Mount Diablo Thrust
33 6.6 MTD 2 1
Calaveras
33 6.8 CN, CC, CS 15 3
Rodgers Creek
35 7.0 RC 9 2
Concord-Green Valley
38 6.7 CCD, GV) 4 2
Monte Vista-Shannon
39 6.8 MVS 0.4 0.3
Point Reyes
44 7.0 1 0.5
West Napa
45 6.5 WN 1 1
Greenville
50 7.0 GN, GS 2 1
Great Valley (segment 5)
66 6.5 CVS5 1.5 1
Great Valley (segment 4)
72 6.6 GVS4 1.5 1
Great Valley (segment 7)
76 6.7 GVS7 1.5 1
Hunting Creek -
Berryessa
77 7.1 HCB 6 3
Zayante Vergeles
83 7.0 ZV 0.1 0.1
Monterey Bay -
Tularcitos
96 7.3 MBT 0.5 0.4
1. Jennings (1994), Nearest Approach
2. WGCEP (2008), Working Group on California Earthquake Probabilities.
AGS
11
2.4 SUBSURFACE CONDITIONS
2.4.1. Previous Exploration
The locations of past subsurface exploration both onshore and offshore relative to the
project shoreline are shown on Plate 2. During the 1960s the Port of San Francisco
completed soundings along the entire shoreline, including in the area south of Pier 54 (Port
of San Francisco, 1961). Soundings involved recording the depths to which a pipe sank
under its own weight and also under a weight of 3000 pounds. In the project vicinity,
soundings were recorded at three locations immediately offshore of the seawall, at
respective distances of approximately 50 feet, 250 feet, and 500 feet south of Pier 54
(Locations 120, 119, and 118). Findings were that the mudline occurred from 24 to 28 feet
beneath mean lower low water (MLLW) and also that there was an approximately 14 to 20
foot thick layer of very soft mud beneath the mudline. Soundings further indicated that the
very soft mud is underlain by stiff clay 500 feet south of Pier 54 but that in the northward
direction there is a thickening sequence of underlying soft clay or loose to medium-dense
sand which was penetrated to a depth of 63.5 feet beneath the MLLW level 50 feet south of
Pier 54.
Onshore conditions reflect the accumulation of a thick fill sequence both placed and
apparently sunk on top of the underlying native unconsolidated alluvial sequence. The
closest nearby available recent boring information that was reviewed was obtained by
Trans Pacific Geotechnical Consultants (1996) in an area next to Pier 52, approximately
300 feet north of the project shoreline. Trans Pacific Geotechnical Consultants (1996)
drilled four borings onshore, Borings B-1 through B-4. In those borings they encountered a
very thick sequence of fill consisting of loose to very dense sandy and clayey gravel with
boulders that continued to as deep as 71 to 74.5 feet below the existing ground surface
(bgs). Native dense to very dense clayey gravel was penetrated beneath the fill to depths
of 110.5 to 114 feet bgs and stiff silty clay (Older Bay Clay) was penetrated beneath. Trans
Pacific Geotechnical Consultants (1996) also completed four offshore borings, Borings B-5
through B-8. In the offshore borings very soft to soft silty clay (Younger Bay Mud) was
AGS
12
penetrated to depths ranging from 24 to 36.5 feet below the mudline, with concrete rubble
and rock fill penetrated to 56 feet below the mudline. Gravelly fill was encountered beneath
the rubble and rock fill extending to a depth of 75 feet. Deeper than 75 feet to 99 feet
native dense to very dense gravel with sand was encountered. Stiff silty clay (Older Bay
Mud) was encountered deeper than 99 feet.
Past subsurface explorations indicate that the project shoreline occupies an area of thick
fill, where there was once 20 to 30 feet of water underlain by 20 to 40 feet of very soft to
soft mud and loose sand. In the area north of Pier 54 the water and much of the softer
underlying soils appear to have been displaced by the typically coarse overlying fill soils to
as deep as 70 to 75 feet below the existing ground surface. In the area of the project
shoreline further south, near the remains of Pier 64, there is little available subsurface data,
but soundings indicate the bay is shallower and consequently fill is likely to be thinner.
2.4.2. AGS Investigation
AGS drilled three borings east of Terry Francois Boulevard, along the Mission Bay
Shoreline south of Pier 54 and north of Mariposa Street. Boring B-1 was drilled next to the
seawall inside the vacant lot north of the contractor’s yard at 559 Terry Francois Boulevard.
Boring B-2 was drilled next to the seawall inside the contractor’s yard, approximately 150
feet south of Boring B-1. Boring B-3 was drilled along the shoreline approximately 570 feet
south of Boring B-2. Borings B-1, B-2 and B-3 were drilled, sampled, and logged to
respective depths of 26.5, 36.5 and 27.5 feet below the existing ground surface (bgs). Both
Borings B-1 and B-2 penetrated through a surface layer of asphalt from 2 to 3-inches thick
and also indicate that an aggregate base layer consisting of dense reddish-brown silty
gravel with sand underlies the surface asphalt to a depth of approximately 2 feet bgs.
Fill was encountered beneath the aggregate base layer to maximum depths of exploration
in Borings B-1 and B-2, and to approximately 15 feet in Boring B-3. In Boring B-1, fill
consisted of 5 feet of medium-dense silty, clayey gravel with sand and with a few cobbles.
Typically, coarse poorly graded gravel with silt and sand were penetrated from 5 to 12.5
AGS
13
feet, while apparent cobbles and boulders were penetrated from 12.5 to nearly 15 feet bgs.
Deeper than 15 feet bgs in Boring B-1 older fill consisting of medium-dense well-graded
sand with gravel was encountered from 15 to 21 feet, with very dense poorly graded gravel
and cobble fill penetrated from 21 feet to the bottom of the hole at 26.5 feet, where practical
drilling refusal was met.
In Boring B-2, fill consisted of 2 to nearly 20 feet of dense to medium-dense silty, clayey
sand with gravel and cobbles underlain by dense to medium-dense well-graded sand with
silt and a few gravelly layers to the bottom of the hole at 36.5 feet. These soils appear to
represent older fill similar to that found in Boring B-1, but with fewer coarse gravel or
cobbles.
In Boring B-3 silty, fill consisted of approximately 15 feet of sandy gravel; poorly graded
gravel with silt and sand; and silty, clayey gravel with sand, cobbles, and concrete rubble
underlain by loose to medium-dense silty, clayey sand with gravel. Loose, medium and
coarse-grained silty sand was encountered from 15 to 16.5 feet. Very soft silty fat clay with
a trace to few coarse sand or fine gravel “Younger Bay Mud” was penetrated from 16.5 feet
to the bottom of the hole at 27.5 feet bgs.
Generally, the Borings indicate that 15 to 20 feet of gravelly and cobbly soils, including
areas of concrete rubble and small boulders (rip rap) occur beneath the surface behind the
seawall. In Borings B-1 and B-2 the layer of coarse fill soils is underlain by a relatively thick
well-graded sandy and gravelly layer of older fill, the bottom of which was not penetrated.
In Boring B-3 a thin layer of native sand and then a thick layer of very soft Bay Mud occur
beneath the layer of coarse fill soil.
2.5 GROUNDWATER
Water was observed in each test boring drilled for this study. Water was observed at
depths ranging from approximately 6.2 to 9.8 feet below the existing ground surface and
appears to coincide with the tidal water levels east of the seawall. Generally, the ground
AGS
14
surface elevation and top of seawall elevation of approximately 10 feet (San Francisco City
Datum) gives approximately 3 feet of freeboard above the maximum high tide elevation of
nearly 7 feet. When groundwater elevations were measured the tides were at intermediate
or low levels. Groundwater is expected to rise closer to the ground surface during periods
of very high tide, and could occur as shallow as 2 feet.
Variations in the water level at the site are likely to occur due to the variations of the water
level in the Bay, changes in precipitation, temperature, and other factors not evident at the
time of this study. The quality of the water was not evaluated as part of this study.
AGS
15
3. RECOMMENDATIONS
3.1 GENERAL
Based on the results of our field exploration and laboratory testing programs it is our
opinion that the proposed shoreline protection repair is feasible from a geotechnical point of
view, provided the recommendations presented in this report are incorporated in the design
and construction of the project. The existing loose to medium dense sandy, gravelly fill and
loose to medium dense native soils extending to top of the Younger Bay Mud at the site
have liquefaction potential when subjected to significant earthquake shaking. The
consequences of liquefaction include seismically induced settlements, additional lateral
loads on the seawall, localized lateral deformation of fill materials, and floatation of buried
structures.
The major geotechnical concern for this project is the stability of the existing seawall under
a major earthquake and localized lateral deformation of fill materials. It is our opinion that
the existing seawall is founded in the liquefiable material and it will undergo deformation
(both translational and rotational) due to loss of passive resistance. Therefore a new
seawall with or without a ground improvement program is needed to resists lateral forces
induced by a liquefaction event. The ground improvement program may consist of
compaction grouting and/or vibro-replacement methods. We understand that the Port of
San Francisco has instructed the design team to improve the existing seawall to resist
active and earthquake pressures knowing that the improved seawall will fail during a
liquefaction event.
The results of our liquefaction potential evaluations indicate that the seismically-induced
settlements at the site will range from 4 to 6 inches from a 475-year return period
earthquake. The results of our lateral spread analyses indicates that liquefaction-induced
lateral deformation at the site will be about 1 to 3 feet and will cause serious damage to the
existing seawall during an earthquake with moment magnitude of M7.9 on San Andreas
AGS
16
Fault. The existing buildings at the site may experience damage due to seismically induced
settlements and lateral deformation.
3.2 SEISMIC DESIGN CONSIDERATIONS
3.2.1. Fault Rupture
The site is not located within an Alquist-Priolo Special Study zone. No known or suspected
faults occur at the Mission Bay Shoreline Protection project site, therefore surface fault
rupture is considered to be very low.
3.2.2. Maximum Earthquake
The Maximum Moment Magnitude (Mmax) earthquake is the largest reasonable
earthquake that a given fault appears capable of generating in the current tectonic setting.
The controlling Mmax earthquake that could affect the project site would be a magnitude
7.9 seismic event occurring on the San Andreas fault, with a seismogenic source (focus of
seismic energy at depth) located about 8 miles (12.7kilometers) southwest the site. Values
of Mmax earthquakes on other faults in the region are shown in Table 2. The locations of
active faults, as adopted by California Geological Survey (2002), and the epicenters of
historical earthquakes within 50 kilometers of the site are shown on Plate 3.
3.2.3. Estimated Earthquake Ground Motions
Ground surface accelerations were estimated using both deterministic methods and
probabilistic methods.
3.2.3.1. Deterministic Methods
Correlations between distance from a causative fault and mean values of the peak
horizontal acceleration, developed by Abrahamson and Silva (1997), Campbell (1997),
Boore et al. (1997), and Sadigh et al (1997), were used to estimate the mean value of the
peak horizontal acceleration resulting from the Mmax earthquake on the San Andreas fault.
AGS
17
Based on the maximum result from these relationships, the Mmax 7.9 earthquake occurring
on the San Andreas fault is estimated to generate a mean peak horizontal acceleration of
0.42g at the site.
3.2.3.2. Probabilistic Methods
The probabilistic seismic hazard analyses were performed using the FRISKSPWIN
computer software package Version 4. Three levels of peak horizontal ground
accelerations were developed at the site for average earthquake return periods of 72, 475,
and 950 years, using attenuation relationships developed by Abrahamson and Silva (1997),
Campbell (1997), Boore et al. (1997), and Sadigh et al (1997.) These earthquake return
periods correspond to approximately 50 percent probability of being exceeded in 50 years
(72-year earthquake), 10 percent probability of being exceeded in 50 years (475-year
earthquake), and 10 percent probability of being exceeded in 100 years (950-year
earthquake). The average peak horizontal accelerations at the site calculated from the
above-referenced attenuation relationships for the three earthquake return periods are as
follows.
72-year earthquake, peak horizontal acceleration is 0.27g
475-year earthquake, peak horizontal acceleration is 0.50g
950-year earthquake, peak horizontal acceleration is 0.60g
3.2.4. Liquefaction Hazard
Soil liquefaction is a phenomenon in which saturated (submerged) cohesionless soils lose
their strength due to the build-up of excess pore water pressure, especially during cyclic
loadings such as those induced by earthquakes. In the process, the soil acquires mobility
sufficient to permit both horizontal and vertical movements, if not confined. Soils most
susceptible to liquefaction are loose, clean, uniformly graded, fine-grained sands. Silty and
clayey sands may also liquefy during strong ground shaking.
AGS
18
The nature of liquefaction depends greatly on the characteristics of the soils. In loose soils,
liquefaction results in significant loss of soil strength, which can lead to large deformations.
In dense soils, although a condition of liquefaction can be initiated, the tendencies for loss
of strength and deformations are resisted by dilation of the soils. Deformations in dense
soils result in a tendency for soil volume increase (dilation), which in turn results in
reduction of pore water pressures, increase in effective stresses, and increased resistance
to further deformations.
The liquefaction potential of soils at the site was evaluated using a simplified, analytical,
and empirical procedure that is correlated with the liquefaction behavior of saturated sands
during historic earthquakes (Youd, 2001; and Idriss and Boullanger, 2008). The primary
data utilized in the analysis consisted of standard penetration test (SPT) and modified
California (MC) sampler blow counts, which were obtained from the three borings drilled at
the site. The SPT and MC blow counts recorded in the field were corrected for various
factors to obtain corrected N-values, which were used in the liquefaction analysis. The
factors used to obtain corrected N-values, included the effects of overburden pressure, rod
length, sampler type and size, and fines content.
The liquefaction analysis was conducted using the following parameters.
• Magnitude 7.9 earthquake
• Peak horizontal acceleration of 0.50g (475-year return period)
• Depth to groundwater at 2 feet.
Based on the results of the liquefaction analysis, the Mission Bay site is considered to have
a high potential for liquefaction.
3.2.5. Consequences of liquefaction
The main effects of liquefaction at the site include settlement of the ground surface and
utilities, lateral deformation, development of excess pore water pressure, buoyancy effects
on the below groundwater structures, loss of allowable bearing pressure, and increased
lateral pressures on utilities and foundations extending below the groundwater table.
AGS
19
3.2.5.1. Seismically-Induced Settlement
Seismically-induced settlements were estimated for two scenarios. On the first scenario, we
estimated the seismically-induced settlements using maximum depth of explorations at
each boring. In the second scenario, we assumed that medium dense fill extends to
maximum depth of 50 feet in Boring B-1 and B-2. This assumption is based on the Trans
Pacific Geotechnical Consultants (1966) report which stated that the fill extends to depth of
71 to 74.5 feet. Typically, medium dense soils below 50 feet do not Liquefy. In Boring B-3,
we assumed that either Younger Bay Mud extends to depth of 50 feet or native soils are
dense and will not liquefy. The results of the liquefaction analysis conducted for each boring
is included in Appendix E and summarized in Table 3.
The estimated seismically-induced settlements presented in Table 3 are absolute values. It
is the opinion of AGS that differential seismically-induced settlements along 100 feet of
length are about half of the absolute values.
TABLE 3 SUMMARY OF SEISMICALLY-INDUCED SETTLEMENTS
Boring ID Seismically Induced Settlement at the Existing
Ground Surface (to the bottom of the boring)
(inches)
Seismically Induced Settlement at the Existing
Ground Surface (to maximum depth of 50 feet)
(inches)
B-1 2.5 3.5
B-2 2.0 5.0
B-3 6.0 6.0
AGS estimates that settlements up to 6 inches may occur during seismic events. If the
anticipated seismically-induced settlements are not acceptable to the designer, AGS
recommends that if a seawall design is desired to resist liquefaction effect, either the
proposed improvements should be supported on a deep foundation system, such as pile
foundation, or a soil improvement method, as discussed in Section 3.2.7, be used to reduce
liquefaction consequences to an acceptable level.
AGS
20
3.2.5.2. Lateral Deformation
Seismically-induced lateral deformation is also another phenomenon which could occur
during a seismic event. The continuity/discontinuity of potentially liquefiable soil layers is a
key consideration in evaluating the potential for lateral deformation. We evaluated the
potential for lateral spreading of the soil behind the seawall using an empirical relationship
developed by Youd et al. (2002) and Zhang et al. (2004). The relationship by Youd et al.
(2002) incorporates the thickness of the liquefiable layer, the fines content and mean grain-
size diameter of the liquefiable soil, the magnitude and distance of the earthquake from the
site, the slope of the ground surface, and boundary conditions, such as a free face, to
estimate the horizontal ground movement.
Based on the predictive relationship for lateral deformation by Youd et al. (2002), liquefiable
soil layer with blow count of 15 and less may exhibit lateral deformation. The test borings
indicates that the potentially liquefiable soil layers with blow count of 15 and less are
present between depths of 2 to 12.5 feet in Boring B-1 and 2 to 16.5 feet in Boring B-3. For
significant lateral deformation to occur, a continuous layer of potentially liquefiable soil
extending for a considerable distance (on the order of several hundred feet) would be
required. Since the test borings and recorded lateral deformation events within the vicinity
indicate the presence of such a layer, it is the opinion of AGS that the potential for lateral
deformation at this site would be moderate to high.
During lateral spreading, surficial soil displaces along a shear zone that has formed within
an underlying liquefied layer. The surficial soil is transported downslope or in the direction
of a free face, such as a channel slope, by earthquake and gravitational forces.
For our analysis, we used two different boundary conditions; one with free face of and one
with gentle sloping ground. For free face boundary condition, we assumed free face height
of 25 feet based on data from offshore sounding. For sloping ground condition, we
assumed a sloping ground gradient of 0.8 percent. Mean grain sizes of 0.6 millimeters
(mm) were used for the fills; the. fines content of the fill was varied from 6 to 12 percent.
AGS
21
The results of the liquefaction-induced lateral deformation analysis based on the predictive
relationship for lateral deformation by Youd et al. (2002) and Zhang (2004conducted for
each boring is summarized in Table 4
TABLE 4
SUMMARY OF LIQUEFACTION-INDUCED LATERAL DEFORMATIONS Boring ID Youd et al.
(feet) Zhang et al.
(feet)
Sloping Ground Free Face Sloping Ground Free Face
B-1 0.5-1.0 1.2-2.3 1.0 2.0
B-2 - - 2.0 5.5
B-3 3.0-6.0 6.0-8.0 1.5 4.5
The presence of rock fill along the alignment of the seawall in Mission Bay site would likely
reduce the potential liquefaction-induced lateral deformation that may occur behind the
seawall. We judge this factor could reduce the amount of liquefaction-induced lateral
deformation to about one to three feet.
Liquefaction of soils underlying the existing seawall may also induce temporary buoyant
uplift pressures. The magnitude of such pressures is difficult to estimate, because of the
variability in materials that may be used and construction techniques. However, given that
potentially liquefiable soils are likely only present in continuous layers between depths of 2
to 16.5 feet, it is opinion of AGS that such buoyant uplift pressures would be relatively low.
3.2.6. Liquefaction Mitigation
Seismically-induced settlements of up to 6 inches and lateral deformation up to 3 feet were
estimated at the site, as discussed previously. The designers should either design for such
settlements and lateral deformations, or where estimated seismically-induced settlements
and lateral deformations cannot be tolerated, they should be mitigated through a program
of ground improvement. This section provides several feasible options for liquefaction
mitigation measures. Due to presence of coarse gravel, cobble and concrete pieces within
the existing fill materials, pre-drilling may be required.
AGS
22
Ground improvement should be performed in areas where the total calculated seismically-
induced settlement exceeds the structurally acceptable level, and be designed to reduce
total liquefaction-induced deformation to a tolerable level. The soil zone to be improved
includes those soils which are at depth of 2 to 16.5 feet. The total thickness of the zone to
be improved depends both on the actual thickness of the soil layer and the desired
reduction in predicted settlement. AGS anticipates that after improvement of soils between
depths of 2 to 16.5 feet, the seismically-induced settlement will reduce to of 1-inch or less.
If seismically-induced settlement of up to 1 inch is not acceptable to the designer, the
unsaturated soils should also be mitigated. AGS recommends that the transition area
(areas with and without soil improvement) be subexcavated at least 2 feet below subgrade
level of the utilities and recompacted with two layers of geogrid to provide a gentle
transition of settlement and minimize the occurrence of differential settlement.
There are several techniques available for soil improvement which may be applicable to
this site: vibro-replacement stone columns and grouting techniques. Alternatively, the
liquefaction-induced settlement can be minimized by supporting the seawall on driven piles.
A low-vibration piling system (such as Screw-in Piling or Press-in Piling) may be used
where vibration due to pile driving activities can not be tolerated. In these low-vibration
systems, a pile is screwed or pushed into the strata, with the resulting skin friction and end
bearing capacities similar to driven piles.
The vibro-replacement stone column technique of ground treatment has proven successful
in reducing the liquefaction potential of sands and low plasticity silt. Stone columns are
used for loose silty sands having greater than about 15 percent fines. Cohesive, mixed and
layered soils generally do not densify easily when subjected to vibration alone, therefore,
the vibro-replacement stone column technique was developed specifically for these soils,
effectively extending the range of soil types that can be improved with the deep vibratory
process.
Grouting techniques (compaction, permeation, deep mixing, chemical, and jet grouting) of
soil improvement have also proven successful in reducing the liquefaction potential of
sandy material. The grouting techniques become less efficient with increased fines
AGS
23
content, such as silt and clay. Of these grouting techniques, jet grouting appears to be the
most efficient method for the site. Essentially, in jet grouting, the injection of an ultra high
pressure fluids or binders at high velocity. These binders break up the soil structure
completely and mix the soil particles in-situ to create an homogenuous mass which in turn
solififies. Other grouting techniques, such as deep mixing, involve the use of large augers
both to introduce cement grout and to mix it with the soil, producing a treated soil cement
column.
Dynamic deep compaction can densify and reduce the liquefaction potential of sandy soils.
This method becomes less effective with high groundwater level and increased fines
content in soils, but has relatively low costs compared to other methods. However, due to
the effects of vibrations on the adjacent properties, it is the opinion of AGS that this method
is not applicable for this site.
The soil improvement design will depend on the costs of performing the work as well as the
technical specifics of the work, and is beyond the scope of this study.
The practical applications of many of these measures have been presented in the literature
(Hryciw 1995; Stewart et al. 1997; Boulanger et al. 1997; Mitchell et al. 1998b) and
summarized in Table 5.
AGS
24
TABLE 5 SUMMARY OF LIQUEFACTION MITIGATION TECHNIQUES
Liquefaction
Mitigation
Technique
Advantages Disadvantages Relative Cost
Vibro-Replacement Stone Column
Effective and economical method in many situations. Able to reach depths unattainable by other methods.
Ineffective for densifying soils with greater than 20% fine contents. The liquefiable soil should have a minimum thickness for this method to be effective. Waste spoils disposal is required.
Moderate
Grouting compaction grouting
Pinpoint treatment, Speed of installation, Wide applications range. Can be performed in very tight access and low headroom conditions, Non-hazardous, no waste spoil disposal. Able to reach depths unattainable by other methods.
Not effective at depths with low confining pressure (<15 feet). Ground surface heave due to grout pressure. Very low reinforcing effects of the compaction grout bulbs/columns.
Low to
moderate
deep mixing grouting
Wide applications range (even with high fine contents), Cost savings over deep foundation designs. Installation methods are customized for the site conditions.
Waste spoils disposal is required. Significant overhead clearance is required. Pinpoint treatment is not applicable. Very low reinforcing effects of the compaction grout columns.
High
permeation grouting
Minimum disturbance of the native soil. Can be performed in very tight access and low headroom conditions. Pinpoint treatment.
Construction process is complex. Very costly. limited to clean sands and ineffective in soils with fines.
High
chemical grouting
Minimum disturbance of the native soil. Can be performed in very tight access and low headroom conditions. Pinpoint treatment.
Construction process is complex. Very costly. limited to clean sands and ineffective in soils with fines.
High
jet grouting Nearly all soil types groutable. Most effective method of direct underpinning of structures and utilities. Safest method of underpinning construction. Ability to work around buried active utilities, can be performed in limited workspace, treatment to specific subsurface locations, no harmful vibrations. Much faster than alternative methods.
Soil erodibility plays a major role in predicting geometry, quality and production. Cohesionless soils are typically more erodible than cohesive soils. Pinpoint treatment is not applicable. Very low reinforcing effects of the compaction grout bulbs/columns.
High
3.2.7. Seismically-Induced Lateral Earth Pressures
Horizontal accelerations during seismic events will momentarily increase lateral earth
pressures on underground structures. The existing seawall will experience seismically-
induced earth pressures from a major earthquake on the regional faults. The seismically-
induced earth pressures are in addition to the static lateral earth pressures and should be
AGS
25
considered in combination with the static lateral earth pressures. For a simplified analysis,
we recommend using an equivalent seismically-induced earth pressure with a rectangular
pressure distribution of F xH psf, where the coefficient F depends on the magnitude of the
ground acceleration and H is the depth to the bottom of the wall in feet. The resultant
seismic force would act at 0.5H above the base of the wall. The seismic earth pressures
are in addition to the static earth pressures and should be considered in design of the wall.
We recommend that a value of 16 be used for F to calculate the magnitude of the
seismically-induced earth pressure resulting from a 475-year return period earthquake. The
choice of the value of F to be used at the site depends on the level of risk accepted by the
designer. This level of risk involves the probability of occurrence of the design earthquake,
the consequences of distress/damage to the seawall, and other factors.
The magnitude of seismically induced earth pressures was calculated based on the
simplified procedures developed by Seed and Whitman (1970) and Ebeling and Morrison
(1992) and incorporated a reduction factor on the order of 25 percent to judgmentally
account for possible effects of wave scattering or passage, the transient nature of
earthquake ground motions, and possible wall-soil interaction effects.
3.3 EXCAVATION AND EARTHWORK 3.3.1. Site Preparation
Prior to site grading, pavements, existing slabs, piles, and decks should be removed and
debris should be disposed of outside the construction limits. Existing underground or under
the pier deck utilities located within the proposed construction areas, if affected by
construction activities, should be relocated prior to excavation. Debris generated from the
demolition of underground utilities, including abandoned pipes, should be removed from the
site as construction proceeds.
AGS
26
3.3.2. Fills and Backfills
Utility trench backfills and below pavement granular base course materials will be placed
during construction of this project.
Fills and backfills may either be structural or nonstructural. Structural fills and backfills are
those defined as providing support to foundations, slabs, and pavements; nonstructural fills
and backfills include all other fills such as those placed for landscaping, and not planned for
future structural loads. Structural fills and backfills should be compacted to at least 95
percent of the maximum dry density as determined per ASTM D-1557; nonstructural fills
and backfills should be compacted to at least 90 percent of this criteria.
Structural fill and backfill materials should be placed in lifts not exceeding approximately 8
inches in loose thickness, brought to near-optimum moisture content and compacted using
mechanical compaction equipment. Nonstructural fills and backfills may be placed in lifts
not exceeding 12 inches in loose thickness and compacted in a similar manner.
Import fill may be necessary to achieve the design grades and should be placed and
compacted under the full time inspection and testing of the project geotechnical engineering
firm. Material to be used as compacted fill and backfill should be predominantly granular,
less than 3 inches in any dimension, free of organic and inorganic debris, and contain less
than 20 percent of mostly nonplastic fines passing the No. 200 sieve. The fill and backfill
soils should have a liquid limit less than 35 and plasticity index less than 12. Samples of fill
and backfill materials should be submitted to the geotechnical engineer prior to use for
testing to establish that they meet the above criteria.
3.3.3. Temporary Excavations
Excavations must comply with the current requirements of OSHA or Cal-OSHA, as
applicable. Additionally, all cuts deeper than 5 feet should be sloped or shored. Some of
the excavations may need to be shored; however, shallow excavations above the
AGS
27
groundwater level may be sloped if space permits. It is our opinion that temporary
excavations to the west of the seawall may be sloped at 1H:1V (horizontal to vertical) or
flatter and 1.5H:1V or flatter above and below the groundwater level, respectively. The
groundwater is estimated to be as shallow as 2 feet below the existing ground surface;
however, it is the responsibility of the contractor to maintain safe and stable slopes or
design and provide shoring during construction. Flatter slopes will be required if clean or
loose sandy soils are encountered along the slope face.
Heavy construction equipment, building materials, excavated soil, and vehicle traffic should
not be allowed within 7 feet of the top of excavations.
Based on the results of our field exploration program and our review of available
subsurface data, it is our opinion that the majority of the proposed excavations can be
made using conventional equipment. However, in some locations obstructions may be
encountered.
3.4 FOUNDATIONS
3.4.1. General
The Port of San Francisco has instructed the project design team to prepare a seawall
design which is stable statically. The proposed renovation shall also make the existing
seawall withstand dynamic earth pressure due to a 475-year earthquake. . The Port does
not seek a renovation scheme which withstands pressures generated during a liquefaction
event. Recommendations provided in this section do not take into consideration
liquefaction-induced pressures. If liquefaction-induced pressure should be taken into
consideration in design of the project, it is recommended that either soil improvement
should be performed or the existing seawall should be founded on deep foundation system.
AGS
28
3.4.2. Renovation Scheme
We understand that foundation grouting with full height revetment will be used for
renovation of the existing seawall.
Voids below the existing seawall should be filled completely with grout to provide intimate
contact between the entire seawall foundation and the bearing soils beneath the seawall.
The contact between the grout and seawall and between the grout and underlying soils
should be verified by the Geotechnic a Engineer. The Contractor is responsible to make
sure that grout does not leak into the Bay.
The most desirable type of revetment is rock riprap. We recommend using plated or keyed
riprap. Plated riprap is placed on the bank with a skip and then tamped into place using a
steel plate, thus forming a regular, well organized surface. Experience indicates that during
the plating operation, the larger stones are fractured, producing smaller rock sizes to fill
voids in the riprap blanket.
The median riprap particle size should be determined using the average velocity of flow,
rock riprap specific gravity of 2.65, and the riprap material's angle of repose of 40 degrees
and not less than Light Class as described in Section 72 of Caltrans Standard
Specifications.. we recommend using bank slope of 1.5H:1V or gentler.
After grouting beneath the existing seawall, a design allowable bearing pressure of 2,000
pounds per square feet may be used at the base of the seawall. The allowable bearing
pressure is a net value. Therefore, the weight of the foundation and the backfill over the
foundation may be neglected when computing dead loads. The bearing pressure applies to
dead plus live load and includes a calculated factor of safety of three. The allowable value
may be increased by one-third for dead plus live plus seismic loading conditions. If a
liquefaction event occurs, a significant loss of bearing pressure and subsequently bearing
failure is expected.
AGS
29
3.5 SETTLEMENT
The primary consolidation of the Younger Bay Mud underlying the site is estimated to be
complete, therefore, settlements of the Younger Bay Mud under its own weight and the
weight of the existing fill are expected to be negligible. It is estimated that additional
settlements will occur as a result of placing additional rock riprap in front of the existing
seawall. The majority of the static settlements will be time dependent and will result from
consolidation of the Younger Bay Mud. The magnitude and time rate of the settlements will
depend upon thickness of the existing fill and the Younger Bay Mud. Our estimated
settlements are presented in Table 6.
TABLE 6
ESTIMATED SETTLEMENTS
Boring
No.
Estimated Bay Mud
Thickness (ft)
Settlement (in) Elapsed Time to
complete 90 percent of
primary consolidation
Thickness of Rock Riprap
1 ft 2 ft 3 ft
B-1 32 3 6 8 15 yr
B-2 20 2 5 7 5 yr
B-3 15 1 4 6 2 yr
If the estimated static settlements described above are not acceptable, we recommend that
the proposed grading plan be adjusted to limit the lateral extent and thickness of additional
fill required. Surcharging with or without wick drains before construction may be used to
reduce the amount of time-dependent settlements.
3.6 PERMANENT RETAINING STRUCTURES
Lateral earth pressures for level backfill condition may be calculated using the values
presented on Plates 4 and 5. The pressures should be computed for the height of the wall
bearing against the soil, except that for passive pressures the upper 1 foot should be
ignored.
AGS
30
The presented values include hydrostatic forces. In addition, surcharge loads should be
considered where appropriate. Where traffic surcharge loads cannot be accurately
anticipated, a nominal uniform lateral surcharge pressure of 150 psf per foot may be used
for the full height of the walls, to a maximum depth of 20 feet.
To prevent excessive lateral forces from being applied to walls, heavy construction
equipment should not be allowed within 7 feet of the tops of the walls.
3.7 RESISTANCE TO LATERAL LOADS
Lateral resistance may be provided by passive pressure against foundations and by
frictional resistance against the bottoms and sides of those elements. Allowable passive
pressure in front of the seawall for different revetment geometry may be taken as
equivalent to the pressure exerted by unit fluids weighing presented in Table 7:
TABLE 7 ALLOWABLE PASSIVE PRESSURES
Revetment Geometry equivalent fluid unit weight (pcf
10 feet level bench changing to 1.5H:1V 400
2H:1V rock slope from the top of the revetment 140
3H:1V rock slope from the top of the revetment 180
At least 5 feet level bench changing to 1.5H:1V 270
Friction along the bottoms and sides of the foundations may be used in combination with
the above allowable passive resistance. The frictional resistance can be estimated by
using a coefficient of friction of 0.40. The net downward load on the foundations should be
used to estimate the base friction.
3.8 EXISTING STRUCTURS
The existing buildings are immediately underlain by uncontrolled fill and potentially
liquefiable soils. Some settlements and cracking may result from differential seismically-
AGS
31
induced settlements of liquefiable soils during an earthquake and could damage the
building foundations. We recommend that either the existing structures be founded on
driven piles extending below liquefiable soils, or soil improvement be utilized at the
perimeters of the building to improve their performance against a liquefaction event.
3.9 CONSTRUCTION CONSIDERATIONS
3.9.1. General
Although the information in this report is primarily intended for the design engineers, data
from our borings will also be useful to the contractor. However, it is the responsibility of the
bidders and contractor to evaluate soil and groundwater conditions independently and to
develop their own conclusions and designs regarding soil densification, excavation,
grading, shoring, foundation construction, and other construction or safety aspects.
Extreme care should be exercised by the Contractor to avoid excessive deflections of the
existing seawall during repair, due to lateral deformation as the excavations are made in
front of the seawall. Where the existing fill in front of the existing seawall are removed, the
excavated area should not excess 10 feet in width, with 20 feet clear between the
excavated area; thus 3 increments of excavation and replacement would be required.
3.9.2. Geotechnical Services During Construction
AGS, Inc. should review project plans and specifications prior to construction to ascertain
that the geotechnical aspects of the project are consistent with the intent of the
recommendations presented herein. AGS should also be retained during construction to
observe the following items.
Site preparation and earthwork; Excavations for the working pits; Grouting and soil improvement; and Placement and compaction of fills, if any, and backfills.
AGS
32
Our presence during construction will allow us to provide consultation regarding the
geotechnical aspects of the project. Our representative will observe the soil conditions
encountered during construction, verify the applicability of the recommendations presented
in this report to the soil conditions encountered, and recommend appropriate changes in
design or construction procedures, if the conditions differ from those described herein. In
addition we will take field density tests during the placement and compaction of engineered
fill and backfill.
AGS
33
4. CLOSURE
This report has been prepared in accordance with generally accepted professional
geotechnical engineering practice for the exclusive use of Port of San Francisco and the
design team for the proposed Mission Bay Renovation project in San Francisco, California.
No other warranty, express or implied, is made.
The analyses and recommendations submitted in this report are based upon the data
obtained from three borings drilled for this study. The nature and extent of variations
between the borings may not become evident until construction. In the event variations
occur it will be necessary to reevaluate the recommendations of this report.
It is the responsibility of the owner or its representative to ensure that the applicable
provisions of this report are incorporated into the plans and specifications and that the
necessary steps are taken to see that the contractor carry out such provisions.
Respectfully submitted,
AGS, Inc.
Bahram Khamenehpour, Ph.D. Geotechnical Engineer 2104
Kamran Ghiassi, Ph.D. Geotechnical Engineer 2792
AGS
34
5. REFERENCES
Abrahamson, N.A. and Silva, W.J., 1997, Empirical Response Spectral Attenuation Relations for Shallow Crustal Earthquakes, Seismological Research Letters, vol. 68, no.1, January February, pp. 94-127.
Anderson, J.G., 1979, Estimating the Seismicity from Geological Structure for Seismic-Risk
Studies, Bulletin of the Seismology Society of American, V. 69, 163-158. Anderson, R.G., and Luco, S.E., 1983, Consequences of Slip Rate Constraints on
Earthquake Recurrence Relations: Bulletin of the Seismological Society of America, v. 73, no. 2, 471-496.
Bernhardt, G., and Toppozada, T.R., Relocation of the A1836 Hayward Fault Earthquake@
to the San Andreas Fault, Transactions of the American Geophysical Union, vol. 77, no. 46 (supplement), 1996.
Boore, D.M., Joyner, W.B., and Fumal, T.E., 1997, Equations for Estimating Horizontal
Response Spectra and Peak Acceleration from Western North American Earthquakes: A Summary of Recent Work, Seismological Research Letters, vol. 68, no. 1, January February, pp. 127-153.
Campbell, K.W., 1997and 2000, Empirical Near-Source Attenuation Relationships for
Horizontal and Vertical Components of Peak Ground Velocity, and Pseudo-Absolute Acceleration Response Spectra, Seismological Research Letters, vol. 68, no. 1, January February, pp. 153-179.
Clough, G. and T. O'Rourke, 1990. "Construction Induced Movements of Insitu Walls",
Design and Performance of Earth Retaining Structures, ASCE Geotechnical Special Publications, 25: 439-470.
Cornell, C.A., 1968, AEngineering Seismic Risk Analysis@, Bulletin of the Seismology
Society of America, v. 58, no. 5, 1583-1606. Federal Emergency Management Agency, 2007, Coastal Structures Form, Certified by Port of San Francisco, December 5, 2007. Goldman, H.B., 1969, Geologic and Engineering Aspects of San Francisco Bay Fill, CA.
Division of Mines and Geology Special Report 97, pp 11-29. Harding Lawson Associates, 1983, South Beach Small Boat harbor and Park, Piers 40
through 46A, San Francisco, California, HLA Job No. 2222,041.04
AGS
35
Harding Lawson Associates, 1992, Final Report Liquefaction Study of North Beach, Embarcadero Waterfront, South Beach, and Upper Mission Creek Area, San Francisco, California, HLA Job No. 17952,041.04
Hayward Fault Paleo-earthquake Group, 1997, The Northern Hayward fault, California;
preliminary timing of paleo-earthquakes, American Geophysical Union Fall 1997 Conference Abstracts, San Francisco.
Idriss, I.M., 1985, Evaluating Seismic Risk in Engineering Practice, in Proceedings,
Eleventh International Conference on Soil Mechanics and Foundation Engineering, San Francisco, v. 4, p. 255-320.
Idriss, I.M., 1987, Earthquake ground motions, Lecture notes, Course on Strong Ground
Motion, Earthquake Engin. Res. Inst., Pasadena, Calif., April 10-11, 1987. Ishihara, K., and Yoshimine, M. 1992, Evaluation of settlements in sand deposits following
liquefaction during earthquakes, soils and foundations, vol. 32, no. 1, pp. 173-188. Jennings, C.W., 1992, Preliminary Fault Activity Map of California, Cal Div. Mines &
Geology Open-File Report 92-03. Joyner, W.B. and Boore, D.M., 1988 Measurement Characterization, and Prediction of
Strong Ground Motion , Earthquake Engineering and Soil Dynamics II, Proceedings of the Specialty Conference Sponsored by the Geotechnical Engineering Division of the American Society of Civil Engineers.
McGuire, R.K., 1976, FORTRAN Computer Program for Seismic Risk Analysis, U.S.
Geotechnical Survey, Open-File Report 76-67. Newmark, N.M., 1967, Problems in Wave Propagation in Soil and Rock, International
Symposium on Wave Propagation and Dynamic Properties of Earth Materials, Albuquerque, N.M.
Petersen, M.D., Bryant, W.A., Cramer, C.H., Cao, T., and Reichle, M.S., 1996, Probabilistic
Seismic Hazard Assessment for the State of California, Cal Div. of Mines & Geology Open-File Report 96-08; USGS Open-File Report 96-706.
Real, C.R., Toppozada, T.R., and Parke, D.L., 1978, Earthquake Epicenter Map of
California; California Division of Mines and Geology, Map Sheet 39, Scale 1:1,000,000. San Francisco Port Authority, 1961, Port of San Francisco Department of Engineering, China Basin to 25th Street, Borings and Test Piles, Drawing No. 6799-415 to 420A, Sheets 3 of 3.
AGS
36
San Francisco Port Authority, 1957, Port of San Francisco Department of Engineering, Seawall Details, Drawing No. 6699-418-22, Sheets 2 of 2. San Francisco Port Authority, 1954, Port of San Francisco Department of Engineering, Alternate A, Wharf Alteration Pier 54, (Drawing No. Not Legible), Dated 3-5-54, Sheet 1 of 1. Seed, H.B., and Idriss, I.M., 1982, Ground Motions and Soil Liquefaction During
Earthquakes, Earthquake Engineering Research Institute Monograph. Seed, H.B., Ugas, C., and Lysmer, J., 1976, ADepartment Spectra for Earthquake
Resistant Design@, Bulletin of the Seismological Society of America, v. 66, no. 1, 221-243.
Seed, H.B., Tokimatsu, K., Harder, L.F., and Chang, R.M., 1984, Influence of SPT
Procedures in Soil Liquefaction Resistance Evaluation, Rep# UCB/EERC 84/15, Earthquake Engineering Research Center, University of California, Berkeley, CA.
Shah, H.C., Mortagt, C.P., Kiremedjian, A.S., and Zsutty, T.C., 1975, AA Study of Seismic
Risk for Nicaragua, Part I@, The John A. Blume Earthquake Engineering Center, Technical Report No. 11, Department of Civil Engineering, Stanford University.
Shamoto, Y., Zhang, J.M., and Tokimatsu, 1998, Methods for Evaluating Post-liquefaction
Ground Settlement and Horizontal Displacement, Soils and Foundations Special Issue No. 2, September 1998
Sun, J.I., Golesorkhi, R., and Seed, H.B., 1998, Dynamic Soil Moduli and Damping Ratios
for Cohesive Soils, Rep# UCB/EERC 88/15, Earthquake Engineering Research Center, University of California, Berkeley, CA.
Tokimatsu, Hohji, and H. Bolton Seed, 1987, Evaluation of Settlements in Sands Due to
Earthquake Shaking, J. of Geotechnical Engineering, V. 113, No. 8. Toppozada, T.R., 1984, History of Earthquake Damage in Santa Clara County and
Comparison of 1911 and 1984 Earthquakes, in the 1984 Morgan Hill, California Earthquake, California Division of Mines and Geology Special Publication 68.
Toppozada, T.R., Real, C.R., and Park, D.L., 1981, Preparation of Isoseismal Maps and
Summaries of Reported Effects for pre-1900 California Earthquakes; CDMG Open-File Report 81-11 SAC.
Trans Pacific Geotechnical Consultants, Inc., 1996, “Progress Report No. 2, Geotechnical
Engineering Services Proposed Public Boat Ramp Café / Bait Shop and Public Access Pier 52, San Francisco, California”, for the Port of San Francisco, December 3, 1976.
AGS
37
United States Geological Survey, 1989, Lessons Learned from the Loma Prieta, California Earthquake of October 17, 1989, Circular 1045.
Vucetic, M. and Dobry, R. Effect of Soil Plasticity on Cyclic Response, Journal of
Geotechnical Engineering, American Society of Civil Engineers, vol. 117, #1.
AGS
PLATES
AGS, Inc.CONSULTING ENGINEERS
PLATE 1
MISSON BAY SHORELINE PROTECTION PROJECT
SAN FRANCISCO, CALIFORNIA
JOB NO. Ki0301 DATE: 07/09
SITE LOCATION MAPN
PROJECT LOCATION
SITE
AGS, Inc.CONSULTING ENGINEERS
PLATE 2
Mission Bay Shoreline Protection Project
San Francisco, CA
JOB NO. KI0301 DATE: JUN 2009
SUBSURFACE EXPLORATION LOCATION MAP0 150 300 ft
USGS, courtesy of terraserver-usa.com2004, Aerial Photo
N
B-1
B-2
B-3
4
1-3
5-8
x
x
x
x
x
x
x
x
x
118
119
120
121
Trans Pacific Borings (1 through 8; 1996)
xx
x
x
x
x
x
x
122
123124
140
139
138137
136
135
134
133
132
Pier 54
Pier 64
Remains
AGS Borings (B-1, B-2, B-3; 6-9,10-09)
x Port of San Francisco Borings and Soundings (1961)
Mission Bay Shoreline
Protection Area Project
Area
Pier 52
153
Reference USGS Web Site
http://pubs.usgs.gov/sim/2004/2848/:
EARTHQUAKE EPICENTERS
AND FAULT MAPAGS, Inc.
CONSULTING ENGINEERS
MISSION BAY SHORELINE PROTECTION PROJECT
SAN FRANCISCO, CALIFORNIA
DATE: 7/09 PLATE 3PROJECT NO.: KI0301
SCALE
0 5 10 MILES
SITE
PLATE 4
MISSION BAY SHORELINE PROTECTIONS PROJECT
SAN FRANCISCO, CALIFORNIA
JOB NO. KI0309 DATE: 06/09
PRELIMINARY DESIGN PRESSURE DATA
NEAR BORINGS B-1 AND B-3
NOTES:
1. Add surcharge pressure to active pressures. If surcharge is kept 40 feet behind seawall,
lateral surcharge will be negligible.
2. Earth pressures include hydrostatic pressures.
3. Earth Pressures represents liquefaction condition of the existing fill.
4. .Hp is equal to 2 feet for loose rock riprap and 1 foot for plated rock riprap.
LEGEND:
H = DEPTH TO GROUNDWATER, IN FEET
Z =DEPTH BELOW EXISTING GROUND SURFACE, IN FEET
w
F
ZF
Existing
Seawall
H
ACTIVE
RESISTING PRESSURES
(psf)
DRIVING PRESSURES
(psf)
1
EQUATIONS (VARIABLES IN FEET, RESULTS IN PSF)
AGS, Inc.CONSULTING ENGINEERS
2
SEISMICALLY -INDUCED
EARTH PRESSURE
FINISHED GRADE
Hw=2 ft
Bay Mud
Fill
16.5 ft5
3
4
1 35Hw
3
2
Active Pressure
4
80Z -20Hwf
80Z -45Hwf
At-Rest Pressure
50Hw
140Z -90Hwf
122Z -72Hwf
Seismically-Induced Earth Pressure
16H
5
Passive Pressure
See Table 7 of the text
Hp
Zp
PLATE 5
MISSION BAY SHORELINE PROTECTION PROJECT
SAN FRANCISCO, CALIFORNIA
JOB NO. KI0309 DATE: 06/09
PRELIMINARY DESIGN PRESSURE DATA
NEAR BORING B-2
NOTES:
1. Add surcharge pressure to active pressures. If surcharge is kept 40 feet behind seawall,
lateral surcharge will be negligible.
2. Earth pressures include hydrostatic pressures.
3. Hp is equal to 2 feet for loose rock riprap and 1 foot for plated rock riprap.
LEGEND:
H = DEPTH TO GROUNDWATER, IN FEET
Z =DEPTH BELOW EXISTING GROUND SURFACE, IN FEET
w
F
ZF
Existing
Seawall
H
ACTIVE
RESISTING PRESSURES
(psf)
DRIVING PRESSURES
(psf)
1
EQUATIONS (VARIABLES IN FEET, RESULTS IN PSF)
AGS, Inc.CONSULTING ENGINEERS
2
SEISMICALLY -INDUCED
EARTH PRESSURE
FINISHED GRADE
Hw=2 ft
Fill
min 35 ft5
3
4
1 35Hw
2
Active Pressure
4
78Z -43Hwf
At-Rest Pressure
50Hw
87Z-37Hwf
Seismically-Induced Earth Pressure
16H
Hp
Zp
Passive Pressure
See Table 7 of the text5
AGS
APPENDIX A
FIELD EXPLORATION AND TESTING
AGS
AppendixAcover.doc July 2009
A-1
A.1 EXPLORATION
Field work was performed by AGS in June of 2009, including reconnaissance mapping and
marking of prospective boring locations, utility clearance, and drilling. Prior to drilling, the
ground surface at each proposed boring location was marked in white paint in order that
Underground Service Alert (USA) members could mark the locations of their respective
subsurface utilities. Locations of the borings are shown on Plate 2 – Subsurface
Exploration Location Map.
Drilling was performed by V&W Drilling, Inc. of Stockton, California on June 9 and 10, 2009
under the supervision of a qualified geologist experienced with area subsurface conditions.
Borings were drilled and sampled to depths ranging from 26.5 to 36.5 feet below the
existing ground surface. Following completion of drilling and sampling, each boring was
backfilled with cement-bentonite grout. The ground surface at the locations of Boring B-1
and B-3 was patched with quick-setting concrete, while the top of Boring B-2 was backfilled
with a 6-sack portland cement and pea gravel concrete mixture to avoid risk of future
subsidence in a sinkhole area. Backfilling was monitored by the San Francisco Department
of Public Health Inspector.
The subsurface conditions encountered in the borings were continuously logged in the field
during drilling operations by a geologist from AGS. Plates A-1.1 through A-1.3 - Log of
Borings B-1 through B-3, respectively, give descriptions and graphic representations of the
materials encountered, the depths at which samples were obtained, and the laboratory
tests performed. The legend to the logs is shown on Plate A-2 - Soil Classification Chart
and Key To Test Data.
AGS
AppendixAcover.doc July 2009
A-2
A.2 SAMPLING
Samples of the soils, as appropriate for the various earth materials encountered, were
obtained by AGS with a modified California (MC) sampler, Standard Penetrometer (SPT)
sampler, or Shelby tube. The Shelby tubes were pushed with the drill rig. The MC and
SPT samplers were driven with a 140-pound hammer, falling 30 inches for an 18-inch
penetration, where possible. The hydraulic pressure or blow counts required for advancing
the samplers were recorded for each 6 inch interval of sample and are shown on the Log of
Borings (Plates A-1.1 through A-1.3). Relatively undisturbed soil samples were collected in
2.5 by 6-inch stainless steel tubes from the MC sampler, plastic Ziploc bags from the SPT
sampler, or inside 3 by 24-inch steel Shelby tubes. The tubes were immediately capped,
sealed with tape, and labeled. The tubes were kept upright and cushioned from shock. All
samples were preserved in a cool, dark area until delivery to the AGS laboratory
3
SA(6)
103
110
105
7
12
14
19
2A B
5
LBG
X
KI0
301.
GP
J 6
/25/
09
NR
7A B
81119
358 4 710
31013 5
50/6"
1011 9
81330
1027
50/6"
1A B
6
ASPHALT PAVEMENT: 2-inches thick, poor condition. [FILL - AC]SILTY GRAVEL WITH SAND (GM), slightly moist, reddish-brown,medium dense, gravel is mainly fine, subangular, few coarse gravel.[FILL - AB]SILTY, CLAYEY GRAVEL WITH SAND (GC-GM) moist, dark brownand gray, medium dense, mostly fine subangular gravel, tracecobbles, some fine- to coarse-grained sand. [FILL]POORLY GRADED GRAVEL WITH SILT AND SAND (GP-GM) wet,brown, medium dense, few cobbles.
SILTY GRAVEL WITH SAND (GM) wet, yellowish-brown,medium-dense, mostly fine and coarse subangular gravel, tracecobbles, some fine- to coarse-grained sand. [FILL]
COBBLES AND BOULDERS (GP), wet, mainly sandstone. [FILL]
WELL-GRADED SAND WITH GRAVEL (SW) wet, medium dense, fineand coarse subrounded to subangular gravel. [FILL]
change to dense
POORLY GRADED GRAVEL (GP) very dense, wet, few cobbles.[FILL]
Boring completed to 26.5 feet below ground surface (bgs).Groundwater measured at depth of 6.20 feet bgs at 2:12 PM, duringdrilling.Boring backfilled with cement grout, pavement patched with asphalt.
TE
ST
S
DRILLING METHOD: 8-Inch Hollow-Stem & Rotary Wash
PROJECT: Mission Bay Shoreline Protection
HAMMER TYPE: 140-lb, falling 30 inches
DE
PT
H (
FE
ET
)
SA
MP
LE T
YP
E
DR
Y D
EN
SIT
Y
(PC
F)
MO
IST
UR
E
SA(12)
PLA
ST
ICIT
Y
4A
CHECKED BY: DH
SA
MP
LE N
O.
IND
EX
(%
)
AD
DIT
ION
AL
5
10
15
20
25
30
35
40
GEOTECHNICAL DESCRIPTION AND CLASSIFICATIONB
LOW
CO
UN
T
GR
AP
HIC
LO
G
LIQ
UID
LIM
IT (
%)
CO
NT
EN
T (
%)
BORING
B-1
PLATE A-1.1
LOG OF
SHEET 1 OF 1
SA(2)
JOB NO. KI0301
LOGGED BY: JF
DATUM:
SURFACE ELEVATION: ftDRILLING DATE: 6/9/09
DRILL RIG TYPE: CME 75
SA(2)
105
117
97
13
9
6
16
1A B
2A
3
4
6
8A B
LBG
X
KI0
301.
GP
J 6
/25/
09
10
92726
2256/6"
6 512
3 323
51217
122335
81527
4 711
12 912
SA(31)
5
9A B
ASPHALT PAVEMENT: 2 to 3" thick, poor condition. [FILL - AC]SILTY GRAVEL WITH SAND (GM) moist, reddish-brown, dense,gravel is mainly fine, subangular, few coarse gravel. [FILL - AB]SILTY, CLAYEY SAND WITH GRAVEL AND COBBLES (SC-SM)moist, yellowish-brown, black and greenish-gray, dense, some fine- tomedium-grained sand, few coarse-grained sand, some fine subangulargravel, trace cobbles. [FILL]
change to medium-dense, wet.
change to dense.
POORLY GRADED GRAVEL AND COBBLES (GP) wet,yellowish-brown and gray, medium dense, mostly coarse subangulargravel to 3-inch diameter, few cobbles, trace fine- to coarse-grainedsand. [FILL]
WELL-GRADED SAND WITH SILT (SW-SM) wet, darkyellowish-brown, dense, mostly medium- to coarse-grained sand, tracefine subrounded gravel. [FILL]cuttings sample indicates sand continues.
change to medium-dense.
Boring completed to 36.5 feet below ground surface (bgs).Groundwater measured at depth of 9.82 feet bgs at 11:30 AM, duringdrilling.Boring backfilled with cement grout to approximately 6 feet bgs.Top backfilled with 6-sack concrete mix poured to grade on 6/11/09.
TE
ST
S
DRILLING METHOD: 8-Inch Hollow-Stem & Rotary Wash
PROJECT: Mission Bay Shoreline Protection
HAMMER TYPE: 140-lb, falling 30 inches
DE
PT
H (
FE
ET
)
SA
MP
LE T
YP
E
DR
Y D
EN
SIT
Y
(PC
F)
MO
IST
UR
E
LIQ
UID
LIM
IT (
%)
SA(9)
IND
EX
(%
)
AD
DIT
ION
AL
PLA
ST
ICIT
Y
GR
AP
HIC
LO
G
BLO
W C
OU
NT
GEOTECHNICAL DESCRIPTION AND CLASSIFICATION
5
10
15
20
25
30
35
40
CHECKED BY: DH
CO
NT
EN
T (
%)
SA
MP
LE N
O.
7
BORING
B-2
SHEET 1 OF 1
LOG OF
PLATE A-1.2
DRILL RIG TYPE: CME 75
DRILLING DATE: 6/10/09
JOB NO. KI0301
LOGGED BY: JF
DATUM:
SURFACE ELEVATION: ft
57
SA(12)
81
4452
60
8
15
38
65
9169
95
1
3
LBG
X
KI0
301.
GP
J 6
/25/
09
5
6
NR
545
102
6 311
315111
SA(8)
80
4A B
SILTY, SANDY GRAVEL (GM), dry, yellowish-brown, loose, gravel isfine and coarse, subangular [FILL].POORLY GRADED GRAVEL WITH SILT AND SAND (GP-GM) moist,black and dark brown, loose, few organics, trace shell fragments,mostly fine subangular gravel, few coarse gravel and pieces ofconcrete rubble, some fine- to coarse-grained sand. [FILL]SILTY, CLAYEY GRAVEL WITH SAND, COBBLES, CONCRETERUBBLE (GC-GM) moist, brown, very loose, fine and coarsesubangular gravel, few concrete blocks from 1 to 2 foot diameter.[FILL]
SILTY, CLAYEY SAND WITH GRAVEL (SC-SM) wet,yellowish-brown, greenish-gray and black, loose to medium dense,some fine gravel. [FILL]
SILTY SAND (SM) wet, loose, fine- to medium-grained, tracecoarse-grained sand, few shell fragments. [Bayside Sand]SILTY FAT CLAY (CH) wet, dark gray, very soft. [Bay Mud]
change to stiff
(No sample recovery with pushed Shelby Tube.)
Boring completed to 27.5 feet below ground surface (bgs).Groundwater measured at depth of 8.32 feet bgs, at 9:35 am, duringdrilling.Boring backfilled with cement grout.
TE
ST
S
DRILLING METHOD: 8-Inch Hollow-Stem & Rotary Wash
PROJECT: Mission Bay Shoreline Protection
HAMMER TYPE: 140-lb, falling 30 inches
DE
PT
H (
FE
ET
)
SA
MP
LE T
YP
E
DR
Y D
EN
SIT
Y
(PC
F)
SA(12)
LIQ
UID
LIM
IT (
%)
2
AD
DIT
ION
AL
MO
IST
UR
E
GR
AP
HIC
LO
G
BLO
W C
OU
NT
GEOTECHNICAL DESCRIPTION AND CLASSIFICATION
5
10
15
20
25
30
35
40
CHECKED BY: DH
CO
NT
EN
T (
%)
SA
MP
LE N
O.
IND
EX
(%
)
PLA
ST
ICIT
Y
UC(.07)WA(99)UC
(.48)
PLATE A-1.3
B-3BORINGLOG OF
SHEET 1 OF 1JOB NO. KI0301
LOGGED BY: JF
DATUM:
SURFACE ELEVATION: ftDRILLING DATE: 6/9/09
DRILL RIG TYPE: CME 75
COARSE FRACTION
ML
WITH LITTLECLEAN SANDS
OVER 12% FINESGRAVELS WITH
NO FINESWITH LITTLE ORCLEAN GRAVELS
LIQUID LIMIT GREATER THAN 50
LIQUID LIMIT LESS THAN 50
SANDS WITHIS SMALLER THAN
OVER 12% FINES
MORE THAN HALF
NO. 4 SIEVEIS LARGER THANCOARSE FRACTIONMORE THAN HALF
Pt
OH
CH
MH
OL
NO. 4 SIEVE
OR NO FINES
SC
INORGANIC SILTS AND VERY FINE SANDS, ROCK FLOUR,
CLAYEY SANDS, POORLY GRADED SAND-CLAY MIXTURES
SILTY SANDS, POOORLY GRADED SAND-SILT MIXTURES
POORLY GRADED SANDS, GRAVELLY SANDS
WELL GRADED SANDS, GRAVELLY SANDS
MIXTURESCLAYEY GRAVELS, POORLY GRADED GRAVEL-SAND-CLAY
MIXTURESSILTY GRAVELS, POORLY GRADED GRAVEL-SAND-SILT
POORLY GRADED GRAVELS, GRAVEL-SAND MIXTURES
WELL GRADED GRAVELS, GRAVEL-SAND
CL
TYPICAL NAMES
SM
SP
SW
GC
GM
GP
GW
HIGHLY ORGANIC SOILS
SILTS AND CLAYS
SILTS AND CLAYS
GRAVELS
MAJOR DIVISIONS
SANDS
R-Value
SOIL CLASSIFICATION CHART AND KEY TO TEST DATA
eveis 002# < flaH naht ero
MSLI
OS
DE
NIA
RG
ENIF
eveis 002# > flaH naht ero
MSLI
OS
DE
NIA
RG
ES
RA
OC
Water Level after Drilling(with date measured)
Water Level at Time of Drilling
(with % Passing No. 200 Sieve)
Wash Analysis
(Shear Strength, ksf)
Unconfined Compression
Torvane Shear
Unconsolidated Undrained Triaxial
Cyclic Triaxial
Swell Test
KI0301 PLATE A-2.1
Terry Francois Boulevard, San Francisco, California
DATEJOB NO. June 2009
PP
INORGANIC CLAYS OF HIGH PLASTICITY, FAT CLAYS
Sieve Analysis
Pitcher Barrel
Standard Penetration Test
Modified California
ADDITIONAL TESTS AND KEY TO TEST DATA
UNIFIED SOIL CLASSIFICATION SYSTEMPEAT AND OTHER HIGHLY ORGANIC SOILS
NX Core Barrel
ORGANIC CLAYS OF MEDIUM TO HIGH PLASTICITY,
Bulk Sample
SANDY OR SILTY SOILS, ELASTIC SILTSINORGANIC SILTS, MICACEOUS OR DIATOMACIOUS FINE
PLASTICITYORGANIC CLAYS AND ORGANIC SILTY CLAYS OF LOW
LEAN CLAYSGRAVELLY CLAYS, SANDY CLAYS, SILTY CLAYS,INORGANIC CLAYS OF LOW TO MEDIUM PLASTICITY,SLIGHT PLASTICITYSILTY OR CLAYEY FINE SANDS, OR CLAYEY SILTS WITH
ORGANIC SILTS
TX
PM
DS
CP
CN
CA
(20)
WA
(1.2)
TV
TC
SW
SA
RV
Pocket Penetrometer
Permeability
Direct Shear
Compaction
Consolidation
Chemical Analysis
Sample Attempt with No Recovery
UC
Mission Bay Shoreline Protection Project Geotechnical Study
AGS
APPENDIX B
GEOTECHNICAL LABORATORY TESTING
AGS
AppendixBcover.doc July 2009
B-1
B.1 GENERAL
Preliminary visual soil classifications were made by AGS in the field in accordance with
ASTM D-2488 -93, Standard Practice for Description and Identification of Soils (Visual-
Manual Procedure). Upon completion of drilling, the samples collected from each boring
were taken to AGS’ laboratory or other testing laboratory for examination and analyses.
The soil classifications were verified by observation of the samples in the laboratory and by
completion of a testing program in accordance with ASTM D-2487 -93, Standard
Classification of Soils for Engineering Purposes (Unified Soil Classification System).
Geotechnical field and laboratory tests were performed on selected soil samples in order to
evaluate the engineering properties of the materials and to corroborate their classification.
Tests were completed for particle size, moisture content and density, Atterberg limits, and
unconfined compressive strength in accordance with the ASTM Standards discussed
below.
B.2 FIELD TESTING
The blows required to drive the MC and SPT samplers, using a 140-pound hammer falling
30 inches for an 18-inch penetration, were used to assist in classifying the relative density
of cohesionless soil deposits, and the stiffness of cohesive soil deposits. Blow counts
recorded by AGS in the field for each 6-inch interval of the 18-inch penetration are shown
on the Log of Borings.
AGS
AppendixBcover.doc July 2009
B-2
B.3 AGS LABORATORY TESTING
The laboratory tests were performed using the techniques and procedures discussed
below.
B.3.1 Moisture and Density Tests
Moisture content and density tests were performed on selected samples to evaluate their
consistencies and the moisture variation throughout the explored profile. The moisture
content was evaluated in accordance with ASTM D-2216 -92, Standard Test Method for
Laboratory Determination of Water (Moisture) Content of Soil and Rock, and was
considered to represent the moisture content of the entire sample for dry density
evaluation. The test results are presented on the Log of Borings at the appropriate sample
depth.
B.3.2 Particle Size
Particle size analyses were conducted on selected samples in accordance with ASTM D-
422-63, Standard Test Method for Particle Size Analysis of Soils or ASTM D-1140 -97,
Standard Test Method for Amount of Material in Soils Finer than the No. 200 (75-µm)
Sieve. The results of the particle size analyses are presented on Plates B-1.1through B-
1.2. The weight percent passing the No. 200 sieve are shown on the Log of Borings.
AGS
AppendixBcover.doc July 2009
B-3
B.3.3 Atterberg Limits Tests
Atterberg limits were evaluated on selected cohesive, fine-grained soil samples to assist in
their classification. Liquid limits, plastic limits, and plasticity indices were evaluated in
accordance with ASTM D-4318, Standard Test Method for Liquid Limit, Plastic Limit, and
Plasticity Index of Soils. The results of the Atterberg limits tests are shown on Plate B-2.
Liquid limits and plasticity indices are also shown on the Logs of Borings.
B.3.4 Unconfined Compressive Strength Tests
Unconfined compressive strength tests were performed on selected cohesive soil samples
to evaluate their strength characteristics. The tests were conducted in accordance with
ASTM D-2166, Standard Test Method for Unconfined Compressive Strength of Cohesive
Soil. The unconfined compressive strength test results are shown on Plates B-3.1 and B-
3.2.
95
0
5
10
15
65
30
35
40
45
50
20
60
100
70
75
80
85
90
55
1 0.0010.110100
25
0.01
267.8
Poorly Graded Gravel (GP)
12
14
19
13
6
3.32
1.72
1.46
PARTICLE SIZE ANALYSIS
25.8
Silty Gravel with Sand (GM)
2.6
3.7
B-1 @
B-1 @
B-1 @
B-2 @
B-2 @
6.5'
12.0'
2.21
B-1 @
Silty, Clayey Sand with Gravel (SC-SM)
B-1 @
Poorly Graded Gravel (GP)B-1 @
B-2 @
B-2 @
6.5'
12.0'
26.5'
3.5'
16.0'
Poorly Graded Gravel with Silt and Sand (GP-GM)
16.0'
Mission Bay Shoreline, Terry Francois Blvd., San Francisco
26.5' 1.4
42.2
5.0
6.2
12.1
2.2
31.4
1.8
34.0
Jun 2009
93.1
JOB NO. DATE
Mission Bay Shoreline Protection
KI0301
2.846
%Clay
19.00
25.00
37.50
19.00
37.50
7.93
13.13
26.43
28.8
26.57
3.5'
1.053
19.815
20.481
0.3072
10.1770
7.1365
59.9
59.1
96.4
26.41.45
103 2 1.5 1 3/4 1/2 3/8 3 4
8
HYDROMETER
14 16646
PERCENT
FINER
BY
WEIGHT
U.S. SIEVE OPENING IN INCHES
GRAIN SIZE IN MILLIMETERS
U.S. SIEVE NUMBERS
PL
SILT OR CLAYcoarse fine coarse medium fine
SAMPLE SOURCE
SAMPLE SOURCE
CLASSIFICATION
GRAVEL
LL
COBBLES
PI Cc Cu
D100 D60 D30 D10 %Gravel %Sand %Silt
MC%
PLATE B-1.1
SAND
20 30 40 50 70 100 140 200
1100
100
60
65
70
75
80
85
95
45
0.0010.010.110
90
10
55
5
50
15
20
25
30
35
40
0
1.37
Poorly Graded Gravel with Silt and Sand (GP-GM)
Silty, Clayey Sand with Gravel (SC-SM)
Silty Sand (SM)
16
8
15
38
1.48
26.5'
1.9110.0'
16.6
94.8
88.7
7.5
B-2 @
B-3 @
B-3 @
0.78
%Gravel %Sand %Silt %Clay
PARTICLE SIZE ANALYSIS
Well-graded Sand with Silt (SW-SM)
16.0'
B-2 @
B-3 @
B-3 @
B-3 @
26.5'
3.0'
3.0'
50.0
87.9
8.7
8.1
12.1
12.1
KI0301 Jun 2009
B-3 @ 0.0
JOB NO. DATE
Mission Bay Shoreline ProtectionMission Bay Shoreline, Terry Francois Blvd., San Francisco
0.551
10.0'
16.0'
9.50
25.00
19.00
4.75
1.84
10.99 34.2
0.45
89.6
1.000
0.624
0.193
0.1112
0.1160
1.7
57.7
37.9
D60
4.25
102 1.5 1 3/4 1/2 3/8 3 4
D10
86 14 16634
PERCENT
FINER
BY
WEIGHT
U.S. SIEVE OPENING IN INCHES
GRAIN SIZE IN MILLIMETERS
U.S. SIEVE NUMBERS HYDROMETER
SAMPLE SOURCE
SAMPLE SOURCE
COBBLESGRAVEL SAND
SILT OR CLAYcoarse fine coarse
140
fine
100
CLASSIFICATION MC% LL PL PI Cc Cu
D100
PLATE B-1.2
medium
D30
20020 30 40 50 70
12040 1008060
30
00
20
20
40
50
60
70
80
10
CH
MH or OH
ML or OL
38 57
PL
AS
TIC
ITY
IND
EX
(P
I)
KI0301 Jun 2009
CL
95
JOB NO. DATE
Mission Bay Shoreline Protection
99
Mission Bay Shoreline, Terry Francois Blvd., San Francisco
LIQUID
PLASTICITY CHART
SAMPLE SOURCE
CL-ML
LIQUID LIMIT (LL)
PLATE B-2
LIMIT (%)
PLASTIC
LIMIT (%)
PLASTICITY
INDEX (%)
% PASSING
#200 SIEVE
B-3 @ 20.5' Silty Fat Clay (CH)
CLASSIFICATION
200
0
50
150
400
250
500
450
300
350
100
UNCONFINED COMPRESSIVE STRENGTH
Strain
(%)
DryDensity
(pcf)
MoistureContent
(%)
B-3 @ 21.0' Silty Fat Clay (CH) 14 52
UC = Unconfined Compression
Ultimate
KI0301 Jun 2009
Mission Bay Shoreline, Terry Francois Blvd., San Francisco
JOB NO. DATE
Mission Bay Shoreline Protection
69.1
0
PLATE B-3.1
4 8 12 16 20
(psf)
UC
Type of TestClassificationSample Source
UN
CO
NF
INE
D C
OM
PR
ES
SIV
E S
TR
EN
GT
H (
psf
)
71
Strength
STRAIN (%)
200
0
50
150
400
500
450
250
300
350
100
UNCONFINED COMPRESSIVE STRENGTH
Strain
(%)
DryDensity
(pcf)
MoistureContent
(%)
B-3 @ 22.5' Silty Fat Clay (CH) 7 60
UC = Unconfined Compression
Ultimate
KI0301 Jun 2009
Mission Bay Shoreline, Terry Francois Blvd., San Francisco
JOB NO. DATE
Mission Bay Shoreline Protection
79.9
0
PLATE B-3.2
4 8 12 16 20
(psf)
UC
Type of TestClassificationSample Source
UN
CO
NF
INE
D C
OM
PR
ES
SIV
E S
TR
EN
GT
H (
psf
)
478
Strength
STRAIN (%)
AGS
APPENDIX C.docx C-1 July/2009
APPENDIX C
LIQUEFACTION POTENTIAL AND
SEISMICALLY-INDUCED SETTLEMENT
AGS
APPENDIX C.docx C-2 July/2009
C.1 LIQUEFACTION POTENTIAL
Appendix C presents the results of our liquefaction potential evaluation for the proposed
The Shoreline Protection Project at Mission Bay in San Francisco. The liquefaction
potential evaluation was based on the results of our field exploration program, whereby
blow counts were recorded by driving the California Modified (MC) and Standard
Penetration Test (SPT) samplers. The measured blow counts were later corrected for
various factors, as discussed below, and used in the liquefaction analyses for two levels
of design earthquake.
Peak horizontal ground surface accelerations were estimated using probabilistic
analyses, for events with return periods of 72 years, 475 years and 975 years as
discussed in Section 3.2.3 of the main text. A moment magnitude of 7.9 was assumed
for a 475-year return period event, corresponding to a horizontal ground surface
acceleration of 0.50g. Magnitude assumptions were made for the purpose of
performing the liquefaction analyses. Our liquefaction evaluations were made using the
procedure developed by National Center for Earthquake Engineering (NCEE),1996,
Youd (2001), AND Idriss and Boulanger (2008).
A comprehensive collection of site conditions at various locations where some evidence
of liquefaction was known to have or to have not taken place was collected by Seed and
others (1984). These data on sandy soils with a fines content less than 5 percent under
magnitude 7.5 earthquake conditions can be presented as relationships between field
values of average cyclic stress ratio, τav/σ'o (where: τav = average horizontal shear stress
induced by an earthquake; and σ'o = initial effective overburden pressure on the soil
element), and the SPT blow counts corrected for certain effects. For an earthquake of
magnitude 7.9, the cyclic shear stress ratio necessary to cause liquefaction in Seed’s
curve was corrected by a factor of 0.94.
For the first step in estimating liquefaction potential, the measured SPT blow counts
should be corrected for various factors using the method proposed by Seed and others
AGS
APPENDIX C.docx C-3 July/2009
(1984). The raw SPT blow count, N, is corrected to obtain the modified penetration
resistance, (N1)60. The modified penetration resistance is computed as follows:
(N1)60 = N x Cm x Cz x Ch x Cs x Cn (C.1)
where:
N: rawSPT or Mod Cal blow count (blows/ft)
Cm : a factor to correct for the larger size of the modified California sampler.
Raw blow counts using a modified California sampler were multiplied by 0.55
Cz: a factor that depends on the length of the drive rods; the following Cz factors may
be used for various depths:
Depth Cz
20 < x <30 ft 1.0
13 < x <20 ft 0.95
10 < x <13 ft 0.85
<10 ft 0.75
Ch: a factor that accounts for the hammer efficiency used in the field, where the blow
count is multiplied by a factor of 0.75;
Cs: a factor that depends on the sampling tube; for a split-spoon sampler without
liner (ID = 1.5" and OD = 2.0"), the following Cs factors may be used:
Raw Blow Count, N CS
< 10 1.0
> 10 1.2
Cn: a factor that depends on the effective overburden pressure at the depth when
the penetration test was conducted.
As presented by NCEE (1996), another correction factor, (N1)60, should be added to
(N1)60 to account for fine contents as follows:
(N1)60 Fine = (N1)60 + (N1)60
AGS
APPENDIX C.docx C-4 July/2009
The average cyclic stress ratio, τav/σ'o, at a specific depth can be estimated from
dynamic site response analyses. It also can be estimated with reasonable accuracy
from the following equation as discussed by Seed and Idriss (1982).
τav/σ'o=0.65 x amax/g x σo/σ'o x rd (C.2)
where:
amax: maximum acceleration at the ground surface
σo : total overburden pressure on sand layer
σo’: effective overburden pressure on sand layer
rd : a stress reduction factor.
Based on the magnitude of the design earthquake, and the peak ground acceleration
generated by that earthquake, the cyclic stress ratio was calculated using Equation C.2.
The cyclic stress ratio was then corrected to account for an earthquake magnitude other
than 7.5.
As Plates C-1 through C-3 show, the results of our analyses indicate a significant
potential for liquefaction of the upper fill and loose to medium dense on-site materials.
The Bay Mud, a silty clay, is not considered liquefiable, however there were thin, loose
sand lenses observed in the samples. These sand lenses should be considered
liquefiable, however they are mostly less than 6 inches thick and likely to be lenticular,
and are confined by the surrounding clay. The thin, lenticular nature of these sands and
the clay confinement should greatly reduce or eliminate potential ground surface
deformation due to liquefaction of these materials. The dense to very dense silty sand
and sand immediately below the Bay Mud would have a very low liquefaction potential
under a significant earthquake. The fill materials are also likely to lead to seismically-
induced settlement, as discussed in the following section.
AGS
APPENDIX C.docx C-5 July/2009
C.2 SEISMICALLY-INDUCED SETTLEMENT
We have estimated volumetric strain of liquefiable and non-liquefiable sandy soils using
different empirical methods based on the performance of liquefied sites in previous
earthquakes. The three methods of analyses include Tokimatsu & Seed (1987),
Ishihara & Yoshimine (1992), Based on the results of our evaluation, it is estimated that
the medium dense to dense sandy soils at the site could experience significant vertical
strain. Based on the estimated thicknesses of the sandy soils, the estimated
seismically-induced areal settlement of the site would range from approximately 2.0 to
6.0 inches.
18 110 35
7 120 517 120 5
14 120 514 120 5100 120 12
20 120 2
26 120 2
47 120 2
20 120 2
Silty Clayey Gravel
Gravel
Gravel With Sand
Sand With Gravel
Gravel
Liqu
efyP
ro
C
ivilT
ech
Softw
are
USA
w
ww
.civ
iltec
h.co
m
AGS, Inc.
LIQUEFACTION ANALYSISMISSION BAY SHORELINE RENOVATIONS
SAN FRANCISCO, CA Plate C-1
Hole No.=B-1 Water Depth=2 ft Magnitude=7.9Acceleration=0.5g
Raw Unit FinesSPT Weight %(ft)
0
10
20
30
40
50
60
70
Shear Stress Ratio
CRR CSR fs1Shaded Zone has Liquefaction Potential
0 1Soil Description Factor of Safety
0 51Settlement
SaturatedUnsaturat.
S = 3.12 in.
0 (in.) 10
fs1=1
32 110 31
100 120 3117 120 31
26 120 31
29 120 2
58 120 9
26 120 9
11 120 9
21 120 9
21 120 9
Silty Gravel
Clayey Sand
Gravel
Sand With Silt
Liqu
efyP
ro
C
ivilT
ech
Softw
are
USA
w
ww
.civ
iltec
h.co
m
AGS, Inc.
LIQUEFACTION ANALYSISMISSION BAY SHORELINE RENOVATIONS
SAN FRANCISCO, CA Plate C-2
Hole No.=B-2 Water Depth=2 ft Magnitude=7.9Acceleration=0.5g
Raw Unit FinesSPT Weight %(ft)
0
10
20
30
40
50
60
70
Shear Stress Ratio
CRR CSR fs1Shaded Zone has Liquefaction Potential
0 1Soil Description Factor of Safety
0 51Settlement
SaturatedUnsaturat.
S = 4.76 in.
0 (in.) 10
fs1=1
9 110 8
2 110 8
14 110 12
4 110 122 84 NoLq2 84 NoLq
6 84 NoLq
2 84 NoLq
2 84 NoLq
Silty Clayey GravelGravel
Clayey Gravel
Clayey Sand
Silty SandFat Clay
Liqu
efyP
ro
C
ivilT
ech
Softw
are
USA
w
ww
.civ
iltec
h.co
m
AGS, Inc.
LIQUEFACTION ANALYSISMISSION BAY SHORELINE RENOVATIONS
SAN FRANCISCO, CA Plate C-3
Hole No.=B-3 Water Depth=2 ft Magnitude=7.9Acceleration=0.5g
Raw Unit FinesSPT Weight %(ft)
0
10
20
30
40
50
60
70
Shear Stress Ratio
CRR CSR fs1Shaded Zone has Liquefaction Potential
0 1Soil Description Factor of Safety
0 51Settlement
SaturatedUnsaturat.
S = 5.43 in.
0 (in.) 10
fs1=1