19
MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012 1 1 1 Preliminary Ladder Testing Results At IPHC MS, XS, LG

Preliminary Ladder Testing Results

  • Upload
    howard

  • View
    34

  • Download
    0

Embed Size (px)

DESCRIPTION

Preliminary Ladder Testing Results. At IPHC MS, XS, LG. Outline. Ladders Testing Goals Voltage, power and temperature on ladder Baseline comparisons to probe test results Sensor performance in ladder configuration Issues What we have learned? Future testing. Ladders. - PowerPoint PPT Presentation

Citation preview

Page 1: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

111

Preliminary Ladder Testing Results

At IPHCMS, XS, LG

Page 2: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

222

Outline

Ladders Testing Goals Voltage, power and temperature on ladder Baseline comparisons to probe test results Sensor performance in ladder configuration Issues What we have learned? Future testing

Page 3: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

333

Ladders Thin and thick sensor ladders.

Large bypass caps at either end, no small bypass caps (pads area available for VDDA, VDDD, VCLP).

Hand assembled quickly from probe tested sensors that function but have not been extensively characterized and are not necessarily optimum.

Tested at LBNL for JTAG function, test mode line pattern, normal mode readout was checked for proper header pattern. Ladders were then shipped to IPHC.

Probe system used primarily test modes. Normal RDO mode implemented(mostly) at IPHC.

Page 4: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

444

Testing goals

Validate the cable design– Cable design driven by

mechanical requirementsTest results from Phase-1 sensor laddersExpected large power consumption at startup

– Basic funcitonality (JTAG, Power distribution, etc.)– Characterization of sensor performance

Test modeNormal readout modeAs a function of bypass capacitance

Page 5: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

555

Voltage, power and temperature on ladder

Page 6: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

666

Voltage, power and temperature on ladder

Thin Sensor Cable HIGH threshold settings LOW threshold settings One sensor

@ regulator 3.97 3.97 3.5Driver sectionGND on the cable 67 mV 73 mV 12mVSensor power 3.583 3.546 3.448Driver power 3.471 3.467 3.48Begin low mass sectionGND 153 mV 170 mV 23 mVPower 3.478 3.427 3.435End of ladder power 3.459 3.406 3.433End of ladder GND 172 mV 190 mV 23 mV

Thin Sensor Cable HIGH threshold settings LOW threshold settings

One sensor

Beginning of ladder 3.325 3.257 n.a.End of ladder 3.287 3.216 n.a.

Thick Sensor Cable HIGH threshold settings LOW threshold settings

One sensor

Beginning of ladder 3.256 3.172 n.a.End of ladder 3.213 3.122 n.a.

Page 7: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

777

Voltage, power and temperature on ladder

Cooling liquid @ 22.5 °C

Page 8: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

888

Baseline comparisons to probe test results

No damage during shipping – JTAG and basic functionality

Sensor damage during construction:– 1 sensor on the “thick” ladder (L1)– 2 senosrs on the “thin” ladder (L2)

We suspect VCLP failure – to be tested later

Page 9: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

999

Baseline comparisons to probe test results

00.5

11.5

22.5

33.5

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49

sensors 1-10, sub-arrays A,B,C,D

nois

e (m

V)

L2 one sensorL2 probe tests

0

0.2

0.4

0.6

0.8

1

1.2

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49

sensors 1-10 sub arrays A,B,C,D

FPN

(mV)

L2 one sensorL2 probe tests

Page 10: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

1010

Page 11: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

111111

Sensor performance in ladder configuration

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49

sensors 1-10, sub-arrays ABCD

sqrt

( noi

se^2

+FPN

^2 )

(mV)

L2 one sensorL2 HIGH thresholdsL2 LOW thresholds

Page 12: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

121212

Issues: threshold shiftd_offset (3.3 - 3.0)

0

5

10

15

20

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49

sensors 1-10 sub-arrays A,B,C,D

DA

C Vref2 = 105Vref2 = 110

-10

-5

0

5

10

15

20

25

30

35

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49

sensors 1-10, sub-arrays ABCD

DA

C

ONE - HIGH thresholdsONE - LOW thresholdsHIGH - LOW

Page 13: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

1313

Issues: self-induced noise

13

5× -1 mV -2 mV

A 60 60 11.5 k

B 95 1.3 k 1.9 M

C 0.5 k 3.7 k 64 k

D 1.5 k 10.0 k 0.2 M

Page 14: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

141414

Issues: missing header/trailer bits

Page 15: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

151515

What we have learned?

We need to work on our probe testing to be sure that we are getting good results.

We need to be more careful of ESD during ladder construction.

The voltage drop on the ladders appears to be manageable. The threshold baseline shifts with applied VDD and noise. Self induced sensor noise is possible. The noise observed without any bypassing capacitors in the

sensor array is significant. Additional testing is needed

Page 16: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

161616

Future testing

Add bypass capacitors Retest existing ladders In parallel, design split-power cable Assemble split-power ladder in Berkeley Continue intensive testing at LBL

Page 17: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

171717

Discussion points

Additional measurments

An onboard regulator may help with the threshold shifts and with noise immunity, but at the cost of power dissipation

Page 18: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

181818

Back up slides

Page 19: Preliminary Ladder Testing Results

MS, LG, XS PXL ladder tests at IPHC, May 1-7, 2012

191919

Issues: ladder induced noise