25
1 PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804 ( E) DATED 14 TH MARCH, 2017 FOR Baga-Bhalag limestone and shale mine in an area of 331.424 Ha. having initial capacity of 3.10 MTPA [Revised vide Environmental Clearance for expansion from 3.10 MTPA to 5.25 MTPA] at Baga & Bhalag villages, Arki Taluka, Distt. Solan, Himachal Pradesh

PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

1

PRE FEASIBILITY REPORT

APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804 ( E)

DATED 14TH MARCH, 2017

FOR

Baga-Bhalag limestone and shale mine in an area of 331.424 Ha.

having initial capacity of 3.10 MTPA [Revised vide Environmental Clearance for expansion from 3.10 MTPA to 5.25 MTPA]

at Baga & Bhalag villages, Arki Taluka, Distt. Solan,

Himachal Pradesh

Page 2: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

2

Executive Summary

Proposed Project

Baga-Bhalag limestone and shale mine in an area of 331.424

Ha. having initial capacity of 3.10 MTPA [Revised vide

Environmental Clearance for expansion from 3.10 MTPA to

5.25 MTPA] at Baga & Bhalag villages, Arki Taluka, Distt.

Solan, Himachal Pradesh.

VIOLATIONS: Application under the provision of Moef&CC

gazette notification S.O.804 ( E) dated 14th March, 2017 due

to violation in higher production, for certain period, beyond the

limit of Environmental Clearance granted by MoEF&CC, Govt. of

India, vide letter Ref. no: J-11015/11/2006-IAII(M) dated 7th

September, 2006,under the provision of the EIA Notification,

2006 notified under Environment (Protection) Act, 1986.

Violation Period :

Production

(MTPA)

Production

Capacity as

per EC

FY

2010-

11

FY

2011-

12

FY

2012-

13

FY

2013

-14

FY

2014

-15

Limestone 3.10 3.35 3.34 4.33 3.76 3.77

Production

Total Geological Resources as on 01.03.2012

Lime stone -727.15 Million tones

Shale – 45.72 Million tones

Mineable Mineral Resources

Lime stone – 148.18 Million tones

Shale – 30.40 Million tones

Annual Lime stone and shale production- 5.25 MTPA Total land requirement for

the project 331.424 ha

Total Water requirement &

Source

Requirement of water for mining complex is only 250 m3/day,

which shall be met from the plant water supply scheme.

Permission of drawing 3500 m3/day water from Satluj River

(2.5 km from plant site) near the confluence with two nallas

(Trenda & Padiyar) is already in place vide letter ref. No. IPHA-

WA-Jaypee Cement/09-119-20 dated 6th April, 2011.

Manpower [Operation] Manpower requirement is 200 for mine operation

Page 3: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

3

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) Identification of project and project proponent. In case of mining

project, a copy of mining lease/letter of intent should be given project,

(A) Jaypee Himachal Cement Plant :

Jaypee Himachal Cement Plant (JHCP) of M/s Jaiprakash Associates Limited was

taken over by M/s UltraTech Cement Limited with effect from 29th June 2017 as per the

scheme of arrangement approved by National Company Law Tribunal Bench-Mumbai on 15th

February, 2017 in case of UltraTech and National Company Law Tribunal Bench-Allahabad on

2nd March, 2017 in case of Sellers (JAL/JCCL) for the transfer of “JAL Business” and “JCCL

Business to UltraTech on a going concern basis.

1. Jaypee Himachal Cement Plant (JHCP), unit of Jaiprakash Associates Limited (JAL)

had set up an integrated Cement Plant (Line-I) to produce 2.05 MTPA clinker and

2.54 MTPA cement located in Baga village, Arki tehsil, Solan district, Himachal

Pradesh after receiving Environmental Clearance vide letter Ref. no: J-

11011/26/2006-IA II(I) dated 18th May, 2006.

2. Subsequently, the Environmental Clearance was amended for augmentation in clinker

production capacity from 2.05 MTPA to 2.97 MTPA vide letter Ref. no: J-

11011/1216/2007-IA II(I) dated 24th December, 2013.

3. Further, JHCP has proposed to enhance the Clinker Production Capacity from 2.97

MTPA to 3.50 MTPA (Line-I) and installation of additional plant (Line-II) to produce

2.50 MTPA clinker & 1.50 MTPA cement, within the existing premises of cement plant,

located at Baga village, Arki tehsil, Solan district, Himachal Pradesh. The said

application is under process at MoEF&CC.

(B) Linked Limestone & Shale Mine

1. In order to meet the raw material requirement of existing plant, Baga-Bhalag

Limestone & Shale mine was proposed in an area of 331.424 Ha with mining capacity

of 3.10 MTPA i.e. 2.8 MTPA Limestone & 0.3 MTPA Shale. Environmental Clearance to

this effect was granted by MoEF&CC vide letter Ref. no: J-11015/11/2006-IA II(M)

dated 7th September, 2006.

2. Baga-Bhalag Limestone & Shale mine (3.10 MTPA) is operational upon receiving NOC

/ Consent to Establish from HP State Environment Protection and Pollution Control

Board vide their letter dated 15.12.2006 and Consent to Operate issued by HP State

Environment Protection and Pollution Control Board on 29.01.2010.

3. Subsequently, to meet the raw material requirement of proposed enhancement of

clinker capacity, the capacity of existing Baga-Bhalag Limestone & Shale mine was

proposed to increase from 3.10 MTPA to 5.25 MTPA. For enhanced capacity (5.25

MTPA), Environmental Clearance was granted by MoEF&CC vide letter Ref. no: J-

11015/105/2013-IA II(M) dated 26th May, 2016.

4. Consent to Establish for enhanced capacity (5.25 MTPA) was granted by HPSPCB vide

ref. No. PCB[130] M/s JPH Mining/14118/2016-/3347-51 dated 15.10.2016 upon

Page 4: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

4

receiving Environmental Clearance vide letter ref. No: J-11015/105/2013-IA II(M)

dated 26th May, 2016 and Consent to Operate was issued by HPSPCB for the

enhanced capacity (5.25 MTPA) vide ref. No. PCB[130] M/s JPH Mining/14118/2016-

132-36 dated 03.04.2017.

2.1 Purpose of Resubmission

Existing operating Baga – Bhalag Limestone & Shale mine (331.424 Ha.) comes

under the violation due to higher production, for certain period, beyond the limit of

Environmental Clearance granted by MoEF&CC vide letter Ref. no: J-11015/11/2006-

IA II(M) dated 7th September, 2006, under the provision of the EIA Notification,

2006 notified under Environment (Protection) Act, 1986, for production of 3.10 MTPA

Limestone & Shale.

Below mentioned table shows the production data of limestone since the

commissioning of Mine.

TABLE-1

PRODUCTION DETAILS

Production

(MTPA)

Production

Capacity as

per EC

FY 2010-

11

FY 2011-

12

FY 2012-13

FY 2013-

14

FY 2014-

15

FY

2015-16

FY

2016-17

Limestone 3.10 3.35 3.34 4.33 3.76 3.77 3.04 2.49

Therefore, in order assess the ecological damage due to said violation and to prepare

Environmental Management Plan comprising remediation plan and natural and

community resource augmentation plan, the proposal is submitted under the

provision of MoEF&CC Gazette Notification S.O.804 (E) dated 14th March, 2017,

(ii) Brief description of nature of the project

The lime stone and shale falls in schedule 1(a) of category ‘A’. The lime stone mine

lease area is 331.424 ha.

(III) Need for the project and its importance to the country and or region

The Baga-Bhalag limestone deposit was identified by Geological Wing, Department of

Industries, and Government of Himachal Pradesh for establishing of a large sized

cement plant. By growing demand in northern region, JAL had setup a large cement

plant in such an extremely rugged topography and poor infrastructure.

(IV) Demand- Supply Gap

M/s Jaypee Himachal Cement Plant (JHCP) a unit of Jaiprakash Associates

Ltd., JAL has been one of the leading companies of India engaged in cement

manufacturing. JHCP have been operating cement plant to produce 2.97 MTPA

clinker and 2.54 MTPA cement at Baga & Bhalag Villages, Arki Taluka, Solan District,

Himachal Pradesh State. To build the gap between demand and supply, JHCP has

planned to enhance the production capacity of clinker plant (Line –I) up to 3.5 MTPA

Page 5: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

5

based on Baga-Bhalag Limestone Mine in Solan district, Himachal Pradesh. As a

result, the raw material limestone and shale requirement increased to 5.25 MTPA

from the existing mine lease area.

(v) Imports vs. Indigenous production

India is self sufficient to meet the demands of the market with the GDP projected at

7 % in the coming decades and in view of the infrastructure. Facilities going across

the region the growth rate of demand will increase to meet the expansion of new

proposal are muted.

(VI) Employment Generation (Direct and Indirect) due to the project

The mining establishment presents vast opportunities of employment to various

posts and under various cadres (management, supervisory, highly skilled, skilled,

semi-skilled and unskilled workmen, casual workmen, petty contractors, etc.). 200

numbers of staff, officers, managers and workmen are deployed at mine to achieve

the desired objective. In addition, indirect employment to the tune of 50 persons by

way of horticultural activities, petty contracts etc. are there.

TABLE-2

MANPOWER REQUIREMENT

3.0 PROJECT DESCRIPTION

(i) Types of project including interlinked and interdependent project, if any.

Exiting Baga Bhalag Limestone & Shale Mine linked to existing integrated Cement

Plant (Line-I) to produce 2.05 MTPA clinker and 2.54 MTPA cement located in Baga

village, Arki tehsil, Solan district, Himachal received Environmental Clearance vide

letter Ref. no: J-11011/26/2006-IA II(I) dated 18th May, 2006. Subsequently, the

Environmental Clearance was amended for augmentation in clinker production

capacity from 2.05 MTPA to 2.97 MTPA vide letter Ref. no: J-11011/1216/2007-IA

II(I) dated 24th December, 2013.

JHCP has proposed to enhance the Clinker Production Capacity from 2.97 MTPA to

3.50 MTPA (Line-I) and installation of additional plant (Line-II) to produce 2.50 MTPA

clinker & 1.50 MTPA cement, within the existing premises of cement plant, located at

Baga village, Arki tehsil, Solan district, Himachal Pradesh. Project is under

consideration for Environmental Clearance at MoEF&CC. The said project is under

process at MoEF&CC.

Sr.No Designation Total

1 Managerial 27

2 Supervisory 27

3 Operations 80

4 Maintenance 30

5 Secretarial 18

6 Crusher 18

Total 200

Page 6: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

6

Subsequently, to meet the raw material requirement of proposed enhancement of

clinker capacity (Line-I), the capacity of existing Baga-Bhalag Limestone & Shale

mine was proposed to increase from 3.10 MTPA to 5.25 MTPA. For enhanced capacity

(5.25 MTPA), Environmental Clearance was granted by MoEF&CC vide letter Ref. no:

J-11015/105/2013-IA II(M) dated 26th May, 2016.

(ii) Location (map showing general location, specific location, and project

boundary & project site layout with coordinates.

Public Road: A village road connecting Kharsi to Kandhar which is also the main

access road for the villages spread across the ML area passes, along the outer

periphery of the area. Kharsi, which is approximately 13 km from Bhalag, lies on a

link road connecting Derla on NH-88 to Beri on NH-21.

Railway Line: No railway line exists at present near the deposit. The nearest broad

gauge railhead is at Kiratpur (on BG section of North Rly) in the neighboring state of

Punjab and is located at a distance of about 92 km to the west, south-west of the ML

area. Shimla, the state capital is linked with Kalka by a narrow gauge railway line

and it lies at a distance of 78 km to the south west of the deposit.

The index map of the site is given in Annexure 1. The location map is shown with the

10 km radius from the periphery of the plant boundary in Annexure-2. The entire

project area falls in Survey of India (SOI) Toposheet No. 53 A/15, A/16 & E/3.

(III) Details of alternate sites considered and the basis of selecting the

proposed site, particularly the environmental considerations gone into

should be highlighted.

The mining project is site specific project as it is related to occurrence of limestone

and shale in the mother earth. Hence no alternative sites were studied.

(IV) Size or magnitude of operation

The mine life of limestone is about 60 years and shale – 55 years and the production

per year will be 5.25 MTPA. The mine lease area is 331.424 Ha.

Geological reserves as on 01.03.2012

Lime stone -727.15 Million tones & Shale – 45.72 Million tones

Mineable Mineral reserves

Lime stone – 148.18 Million tones & Shale – 30.40 Million tones

(V) Project description with process details (a schematic diagram/flow

chart showing the project layout, components of the project etc. should be

given.

The mine will be worked by Mechanized Opencast Method of working. The height of

the bench will be kept of 10 meters and width of the bench will be kept more than 15

meter at least.

Page 7: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

7

The blast holes of 150-165 mm dia using DTH drill machine. The blast holes will be

drilled in staggered pattern keeping burden of 3.6 Meter and spacing of 4.8 Meter. In

the mine square/ rectangular/ staggered grid, multi row pattern or extended V

pattern shall be adopted and later on based on experience gained the pattern to be

adopted in future shall be standardized. Long/ short (ms) delays shall be used. This

will help in reduction of ground vibrations, back break, fly-rock, air blast etc.

The charge per delay shall be kept around 432 kgs to start with. This shall be

modified in due course, based on experience gained and after conducting scientific

studies for determining peak particle velocity and other related parameters to keep

ground vibrations, air blast, fly-rock etc. within optimum limits.

The maximum number of holes to be blasted in a round shall be kept at 50-60. This

shall however depend on the length of face that can be made available and modified

in future depending on result of scientific studies to be done as referred above. Each

round shall yield about 23,760 tons of limestone and shale. 4-5 such rounds of holes

shall be fired per week, subject to suitable length of faces being made available. It

will give about 1,05,000 tons of blasted material. This is considered to be adequate

to feed the crusher for a week. Considering the nature of strata/ deposit and height

of the bench, no decking shall be resorted to. The booster charge shall be kept at the

bottom of the hole followed by column charge. However, in future, decking may be

adopted if considered necessary to improve powder factor, blasting efficiency and

reduce vibrations/ flyrock.

Surface plan is shown in Figure-1, Geological Plan and sections Figure 2 and

Conceptual Plan is shown in Figure-3.

Page 8: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

8

Page 9: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

9

FIGURE-1

SURFACE PLAN

Page 10: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

10

FIGURE-2

GEOLOGICAL PLAN

Page 11: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

11

FIGURE-2 (A)

GEOLOGICAL SECTION

Page 12: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

12

FIGURE-3

CONCEPTUAL PLAN

The block wise and category wise summary of geological limestone and shale

reserves estimated and their category as per UNFC is given in the table below.

Baga Block

Bhalag Block

The mineable reserves have been estimated giving due allowance of 10%, 30% &

50% for mineable proved, probable and possible categories respectively for errors of

estimation, mining losses etc and the reserves to be blocked for formation of

benches has also been taken into account for arriving at the mineable reserves which

are summarized as per UNFC.

Summary of Reserves

Baga Block

Bhalag Block

Page 13: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

13

The recoverable limestone reserves have been further reduced giving due uniform

allowance of 10% for all categories on account of screen losses except in the shale

reserves.

Baga Block

Bhalag Block

The total recoverable reserves of all categories in both the Baga and Bhalag blocks

are summarized below: -

The qualitative behavior of the limestone from the two blocks is given in the table

below:-

Page 14: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

14

Topography and Drainage

The area for mining lease forms part of the Lesser Himalayan Ranges, which are

characterized by extremely rugged topography comprising of high peaks, steep

slopes and deep incised valleys. No flat plain except on the top of the Baga block is

seen in and around the area of mining lease. The mountain that hosts the limestone

deposit gains its elevation from the banks of river Satluj that meanders between

inter mountainous valleys and the recorded elevation at river Satluj is 610 mRL.

The highest elevation in the Baga block is 1647 mRL whereas the highest elevation in

the Bhalag block is 1450 mRL and lowest 830 mRL. As compared to Baga, the Bhalag

block is marked by the presence of conical elongated ‘tongues’ that have greater

width at the base as compared to the top which have less width and are steeper. The

Baga block on the other hand occurs in the form of a single large elongated platform

having steep slopes. The approximate crow fly distance (nearly 1.5 km) between the

two blocks is also characterized by undulating mountain peaks that are composed of

dolomite.

River Satluj, which flows at a distance of about 2.5 km from the deposit, controls the

drainage of the area and its surroundings. A few seasonal nala particularly the

Bhalag nala (running parallel to the ML boundary and a small part flows within ML

area at 862 mRL to 835 mRL) and Baga nala (entering ML area at 1255 mRL and

exists at 1088 mRL) flows from the higher reaches of the mountains, drain the areas

along their way before finally merging into river Satluj. Several seasonal nalas flow

within the ML area and present dendritic pattern of drainage in the area during rainy

season.

Blasting

The limestone and shale rock being hard category requires drilling and blasting for

excavation. To maintain a bench height of 10 meters, drilling by 150-165 mm dia

DTH drill machine, is recommended as a guide line to start with. Powder factor on an

average is kept as 6 tones per kg of explosive in the initial stages. However in future

effort will be made to improve upon it. Blasting frequency is recommended as twice

in every six days (i.e. twice a week). Benches shall be kept sloped at an angle of 15o

from the vertical. (i.e. 75o from the horizontal). Same angle of slope shall be

maintained for drill blast holes also. With 10 m. high benches, sloped at an angle of

Page 15: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

15

15o to vertical, the bench slope height shall be 10.3 m and with sub-grade drilling of

1.0 m. the depth of shot holes to be drilled shall be 11.3 m.

Various types of explosives such as ANFO, slurry, emulsion etc. will be used for

blasting. Since ANFO is economical, it will be used as much as possible except in

rainy season. Delay detonators or NONEL detonating fuse will be used since multi

row system of firing will be carried out so as to reduce the ground vibration, noise,

fly rock etc. due to blasting. Sequential blasting techniques using sequential blasting

machine shall be used to reduce explosive charge per delay to a minimum to reduce

ground vibration.

In order to avoid fly rocks and other blasting hazards the secondary blasting is not

recommended. However for secondary breakage of oversized boulders hydraulic rock

breaker shall be utilized.

At present only one time blasting is being practiced in a day in Baga–Bhalag

limestone and shale mine. Total no. of holes to be drilled is 25-35 in 2 -3 no. of rows

for fragmentation of limestone and shale per day. Blasting parameters for limestone

as well as waste having 10 m average height are given in Table-3.

TABLE-3

BLASTING PARAMETERS FOR LIMESTONE, SHALE AND MIXED BENCHES

Page 16: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

16

Mining Equipment’s

The list of Machinery and Miscellaneous/ Ancillary Equipment available at Mine Site is

provided in Table-4.

TABLE-4

MACHINERY AND MISCELLANEOUS/ ANCILLARY EQUIPMENT

AVAILABLE AT MINE SITE

Mine Drainage

The area exhibits a typically rugged undulating topography. The proposed mining

area forms a plateau in some parts with the flanks dipping steeply forming practically

vertical scarps.

The drainage of the mines area is influenced by the perennial Satluj river, which has

a meandering flow from the north to the west approximately 2.5 km away from the

mining lease area. There are several seasonal nalas within the lease area. All the

nalas recharge during the rainy season and ultimately merge with the Satluj river.

Page 17: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

17

No wells or water bodies exists in and around the area of mining lease. Seepage of

rainwater along the bedding planes and joints give rise to nala. These nalas dry up

over a period of time after monsoon to be recharged only with a fresh spell of

rainwater from these nala flows down along the nala to river Satluj. No springs

within the area of mining lease. A few tube wells exist alongside the road near village

Baga. Water in these tube wells has been encountered at the depth of nearly 50 m

below the surface. The surface level at these points is nearly 1100 m above MSL.

The mining operations shall commence from an elevation of 1400 m above MSL and

the ultimate pit limit at depth for the mining operations at present is envisaged at

1100 m above MSL, which is well above the existing water table in the area. Thus,

the water table is not likely to be encountered in the course of mining operations.

Hence, no adverse impact on the water table is envisaged while mining during the

ensuing mine plan period and at the abandonment of mine.

The sub-surface/ ground water shall not be encountered in the present and

conceptual mine plan period because the workings would always remain above the

ground. There is no mine water discharge from the said mining lease as there is no

use of water for the purpose of washing of mining machines at mine site.

(VI) Raw material required along with estimated quantity, likely source,

marketing area of final products/s, mode of transport of raw material and

finished product.

The quantity of excavation is 5.25 MTPA of limestone and shale with no reject. In

view of two monsoons per annum in this area and very rugged terrain, operating

days per annum are estimated at 350 only. With 350 working days per annum the

daily requirement of limestone and shale to be raised comes to 15000 tones. With a

powder factor of 9, the requirement of explosives per day shall be around 15000/9 =

1667 kgs. With 25% being NG explosive, its requirement per day will be 432

kg/hole.

The company already has established two Explosive Magazines of capacity 9 tones

each.

Jaiprakash Associates Limited has entered into a contact on renewable basis with

CIMFR (Central Institute of Mining & Fuel Research, Dhanbad) for day to day

monitoring of blasting operations.

Precautionary Measure adopted during the blasting of rock mass are: -

1. Controlled & Scientific blasting

2. Blasting is being carried out by competent person

3. Blasting is being done by latest and ecofriendly technique i.e. NONEL

4. Blasting is being done in presence of CIMFR representative

5. Vibration of each blast is being monitored on day to day basis

(VII) Resources optimization/ recycling and reuse envisaged in the project,

if any, should be brief outlined.

None

Page 18: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

18

(VIII) Availability of water its sources, Energy /power requirement and

sources should be given

Water

Water shall be required for mining to cater for drinking purposes, dust suppression at

faces and a long haul roads, cleaning and plantation/ greenbelt etc. No water shall

be required for processing. The requirement of water for the above purposes is

estimated at 250 m3 per day. The source of water shall be from the Satluj river that

flows at a distance of about 2.5km from the ML area. Water is being stored in the

overhead tanks and from there supplied through pipe lines to the site. Water

spraying along the haulage roads shall be done using the tankers.

Spraying of water at the faces, haul roads is not generated any waste water as the

same would evaporate or percolate to lower levels through the strata below (which

are normally porous). There shall be no recycling of water on this account. No waste

water is being generated as there is no workshop at mine site.

Power

Power requirement shall be met from existing power supply of cement plant.

(IX) Quantity of wastes to generated (liquid and solid) and scheme for their

Management/disposal.)

Dumping area for limestone/ shale boulders is not being provided for since the entire

production is being planned commensurate with expected rate of consumption with a

view to avoid re-handling the same and cost thereof. Crushed limestone/ shale shall

be taken to the crusher by dumpers.

Topsoil, if any shall be utilized to develop plantation on periphery and parts of non-

mineralized barren land, within the lease hold area to reduce impact of air-borne soil

dust.

No Sub-grade limestone is generated and hence no arrangement is required for

stacking.

4.0 SITE ANALYSIS

(I) Connectivity

Public Road: A village road connecting Kharsi to Kandhar which is also the main

access road for the villages spread across the ML area passes, along the outer

periphery of the area. Kharsi, which is approximately 13 km from Bhalag, lies on a

link road connecting Derla on NH-88 to Beri on NH-21.

Railway Line: No railway line exists at present near the deposit. The nearest broad

gauge railhead is at Kiratpur (on BG section of North Rly) in the neighboring state of

Punjab and is located at a distance of about 98 km to the west, south-west of the ML

area. Shimla, the state capital is linked with Kalka by a narrow gauge railway line

and it lies at a distance of 78 km to the south west of the deposit.

(II) Land form, land use and land ownership

Page 19: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

19

Land use pattern (Forest, Agricultural, Grazing, Barren etc.)

The entire land of 331.424 hectares is granted to the company and under possession

of JHCP. Present land use of mine comprises of:

(III) Existing land use pattern (agriculture, non-agriculture, forest, water

bodies (including area under CRZ)), shortest distances from the periphery

for the project to periphery of the forests, national park, wild life sanctuary,

eco sensitive areas, water bodies (distance form the HFL of the river), CRZ.

In case of notified industrial area, a copy of the Gazette notification should

be given)

A. LANDUSE BREAK-UP (Study Area) BASED ON IRS RESOURCESAT 2 L4FMX

(5 M RESOLUTION) DATA–21st NOVEMBER 2013

Sr. No. Level-I Level-II Area

(Hectares)

Area

(%)

1 Built-up Land

1.1 Settlements 1461 4.00

1.2

Industry/Institutional

Land 261 0.72

2 Forest Protected/Reserved

2.1 Dense/Open Forest 3737 10.23

2.2 Degraded Scrub Land 753 2.06

2.3 Forest Blank 143 0.39

Others

2.4 Dense/Mixed Jungle 345 0.94

3

Agricltural

land

3.1 Plantation 6 0.02

3.2

Agriculture Land/Single

Crop 2072 5.67

3.3 Fallow Land 5539 15.17

4 Waste Land

4.1 Land with/without Scrub 21515 58.92

4.2

Rocky/Stony/Barren

Land 24 0.07

4.3 Quarry/Mining Land 249 0.68

5 Water Body

5.1 Stream/River 410 1.12

Page 20: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

20

Sr. No. Level-I Level-II Area

(Hectares)

Area

(%)

5.2 Tank/Reservoir/Pond 1 0.00

Total 36515 100.00

A. Wild life sanctuaries within 10 km from the ML area

Bandhi Wildlife Sanctuary (8.5 km, N)

Majathal Wildlife Sanctuary (4.5 km, SE)

The project was recommended by standing committee of NBWL during its 31st

meeting held on 12th– 13th August, 2014. NOC was issued by PCCF (WL)-cum-Chief

Wildlife Warden, Shimla, H.P. vide its letter no: WL (Misc.)-Jaypee

Cement/WLM/6684 dated 9th March, 2016.

(B) List of Protected forest within 10 km from the ML area

(IV) Existing infrastructure

The following infrastructures facilities are available in the vicinity and around the ML area: Facilities available in the core zone:

1. Primary school at Baga and Sahnali villages,

2. Telephone Exchange at Bhalag village,

3. Electric and telephone line at Baga, Bhalag and Sahnali villages,

Sr. No Forest Distance /Direction

1 Khatrul PF Adjacent to SE

2 Siarli PF 0.3 km, ESE

3 Baga PF 0.65 km, N

4 Bajarail PF 1.0 NE

5 SuinMarora PF 1.4 km, ENE

6 Matrech PF 1.6 km, SE

7 Sangan PF 2.2 km, NW

8 Bana PF 2.4 km, SE

9 Trohat PF 3.5 km, E

10 Uira PF 4.4 km, NE

11 Skor PF 4.4 km, ESE

12 Mungrani PF 4.50 km, W

13 Badi PF 5.5 km, N

14 Chhabiawan PF 5.7 km, NNW

15 GaiharuPF 6.0 km, NNE

16 Bunga PF 7.2 km, NE

17 Ghamru PF 7.2 km, E

18 Kuftha PF 7.6 km, E

19 Mundlidhar PF 7.7 km, NE

20 Gate PF 9.1 km, SSW

21 Vuryans PF 9.1 km, NW

22 Bahadurpur PF 9.8 km, SSW

Page 21: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

21

4. Water supply scheme by IPH at Baga village,

5. Primary Health Centre at Baga and Kandhar villages

Facilities available around the ML area:

1. JP Guest House at Baga – 1.5 km

2. Police Station at Baga – 1.0 km

3. PWD Dak Bungalow at Bilaspur – 42km

4. Dak Bungalow (Forest Deptt.) at Darlaghat – 26 km

5. Post-Graduation College at Bilaspur – 42 km

6. NH-88 at Darlamore – 21 km

7. NH-21 at Nauni – 42 km

8. Railway Station at Kirathpur (Punjab) – 92 km

9. Civil Hospitals at Solan, Shimla and Bilaspur – 103, 76 and 42 km respectively

(V) Social Infrastructure available

All infrastructure facilities such as education, health facilities and other social

facilities are adequate at district headquarter. These facilities are also available in

company premises also.

5.0 PLANNING BRIEF

(I) Planning Concept (types of industries, facilities, transportation etc)

Town and Country planning/Development authority Classification

The existing road will be strengthened in and around the mine for transportation of

lime stone from mine. This will also enhance the transportation facilities of the area.

(II) Population projection

No impact on human settlement

(III) Land use planning (breakup along with green belt etc)

All Values in Ha

Total

(a) Pits & Quarries 171.32

(b) Dumps of ore, waste, topsoil & O.B. -

(c) Infrastructure including of office, Tar Road,

Haulage, Foot Track

11.68

(d) Habitation Nil

(e) Others (intact)

(i) Govt. land

(ii) Agriculture land

(iii) Forest land

-

76.6562

68.2058

3.5620

Total occupied area 331.424

(IV) Amenities/ Facilities

It is an operating mine and hence infrastructure facilities have been developed by

JHCP. However infrastructure facilities such as education, health facilities and other

social facilities are adequate at district headquarter.

Page 22: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

22

6.0 PROPOSED INFRASTRUCTURE

(I) Industrial Area (Processing Area)

Infrastructures required for mining activities with allied facilities have already been

developed by JHCP.

(II) Residential Area (Non Processing Area)

Not applicable

(III) Green belt

Plantation Programme

The main aim of plantation in and around the mine areas is to stabilize the land to

protect it from rain and wind erosion. As the leftover working area shall contain

broken material and fine particles, stabilization against wind erosion is also a must.

The plantation scheme broadly covers the following areas:

Plantation around peripheral portions of mine and other built up structures;

Afforestation of barren areas in the lease hold;

Gardens, parks and haul road plantation;

Plantation by way of reclamation /rehabilitation of mined out blocks and waste

dumps; and

Improving the conditions of catchment areas and to prevent erosion.

It is proposed to plant around 1000 plants per ha. The plantation will be done around

ultimate periphery of the pit, road. At the end of the life of mine total 20.0 ha area

will be covered under plantation. Phase wise plantation Schedule till end of mine life

is given in Table-5.

TABLE-5

All protection measures like provision of garland drain, afforestation and stabilization

will be taken care on year to year basis as per the requirement. A final mine closure

plan incorporating time schedule for abandonment shall be submitted before one

year of its closure as per rule.

(IV) Social Infrastructure

M/s Jaypee Himachal Cement Plant (JHCP) has well-defined CSR policy to

carryout social development and welfare measures in the surrounding villages. Under

CSR activity JHCP has already initiated community development projects, in the

Page 23: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

23

fields of health, education and environmental preservation, in the study area around

the mine lease area and same activities will be further strengthened.

(V) Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways

etc)

Public Road: A semi-metalled village road connecting Kharsi to Kandhar which is also

the main access road for the villages spread across the ML area passes, along the

outer periphery of the area. Kharsi, which is approximately 13 km from Bhalag, lies

on a link road connecting Derla on NH-88 to Beri on NH-21.

Railway Line: No railway line exists at present near the deposit. The nearest broad

gauge railhead is at Kiratpur (on BG section of North Rly) in the neighboring state of

Punjab and is located at a distance of about 98 km to the west, south-west of the ML

area. Shimla, the state capital is linked with Kalka by a narrow gauge railway line

and it lies at a distance of 70 km to the south west of the deposit.

(VI) Sewerage system

The machinery shall be maintained and washed in plant workshop so no generation

of water/ waste water is envisaged from the ML area.

No rainwater shall accumulate on the face. The rainwater shall flow down the slopes

or through the seasonal streams. No pollutant is anticipated from limestone as no

harmful ingredient has been analyzed within limestone. No adverse impact is

anticipated as ground water in this area is considered to be potable and suitable for

cultivation/ industrial purposes. No special treatment of such water envisaged.

Anticipated as ground water in this area is considered to be potable and suitable for

cultivation/ industrial purposes. No special treatment of such water envisaged.

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

No R&R issues involved

Page 24: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

24

ANNEXURE–1

SITE LOCATION MAP

ML Area

Page 25: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/13_Sep_2017... · PRE FEASIBILITY REPORT APPLICATION UNDER THE PROVISIONS OF MOEF&CC NOTIFICATION S.O.804

25

ANNEXURE–II

STUDY AREA MAP

Malokhar

Basla

Charahu

Aslu

Chakoh

Parnu

Tansi

Matrech Jhadowi

Ghanna

Cheran

Samlehu

Baga GhawraiBeri

10 KM

Thach

76° 55'76° 50' 77° 00'

NH-88 31°

15'

31°

20'

76° 55'76° 50'

31°

15'

31°

20'

31°

25'31°

25'

Gari

Daroba

Harnora

Dhar

Ghagas

Sandauli

Ban

Rawa

Changar

Kandar

Malothi

JajarPanali

Sahnali

PauriBholang

Tepra

Mamau

Hawoni

Cholog

Dabar

Kathpur

Bamla

Dunglu

Dagsech

Bag

Behli

Barnun Pasaya

Silha

Rajghat

Shyari

Daseran

Bhanda

Bandla

Chanalag

Magrot

Dades

Juras

Deoli

RopaSamdhar

Kasol

Daudi

Jartu

Bohi

Pata

Kolthi

Ratheh

Siarli

Mandno

Sabar Baadu

Bartha

Kuphar

Cheori

BadnuPati

Ghamru

HalogdaSamal

Bagra

Chouri

Balag

Majhali

Keri

LalagDhara

Kathla

Dal

Badi

Gagal

Barmanan

Panjgain

Suli

SulangSamana

Matianj Kalan

Matianj Khurd

Chamrol

Ropa

Talwand

Ghiyana

Dhar

Gaiharu

Nagri

Sanihan

Barech

Suin

Marora

Chamba

Karyad

Chida

Niholog

Sohra Bhyan

Kian

Kalsua

Dhawahal

Dharsi

Kol Huwani

77° 00'

TROHATP.F

SKOR P.F

SIARLI P.F

KHATRUL P.F

MATRECHP.F

BANAP.F

GATE P.F

GHAMRU P.F

SUIN

MARORA P.F

BAJARIALP.F

Ujra P.F

BUNGA P.F

MUNDLIDHARP.F

GAIHAR P.F

BADI P.FCHHABIAWAN

P.F

BURYANS P.F

SANGAN P.F

MUNGRANIP.F

P.F

MAJHATAL WILDLIFE

SANCTUARY

BANDLI WILDLIFE

SANCTUARY

SCALE

1 0 1 2 Km

Topo Sheet No. 53 A/15, A/16 & E/3

KUFT

HU P

.F

Kufthu

NH-8

8

Balog

Aina Padyar

Nyu

Mohlar

Naugaon

Janed

Panjel

Panjag

Jabal

Kutal

Sahrah

PariahKagriPardhot

BarpatRopri

Sia

Panjeli

Soldha

Kirfa

Loongari

Torti

ML Area-Existing

LEGEND

Cement Plant Area Road

River / Nala

Village

Forest Boundary

Wildlife Sanctuary Area

Kharsi

SATLUJ R

IVER

ALI KHAD

Sagithi

Sargohri

Parnali

Kharoti

BadsourA

F

D

E

Bahairari

CB

4

5

1

2

3

Khad

Plant Site Coordinates

1 : 31°20'17.0" N, 76°53'1.9" E

2 : 31°19'47.8" N, 76°54'4.5" E

3 : 31°19'26.2" N, 76°53'10.4" E

4 : 31°19'41.2" N, 76°53'4.0" E

5 : 31°19'57.4" N, 76°53'25.0" E

Existing ML Area Coordinates

A : 31°19'49" N, 76°53'40" E

B : 31°20'25" N, 76°53'38" E

C : 31°20'43" N, 76°53'51" E

D : 31°20'11" N, 76°54'47" E

E : 31°19'01" N, 76°54'31" E

F : 31°18'58" N, 76°54'06" E