Upload
trandat
View
216
Download
0
Embed Size (px)
Citation preview
1
Executive Summary
The Town of Okotoks along with other communities in the Calgary sub-region have experienced
rapid growth in recent years. Increased population projections have led Okotoks to seek out a
long term sustainable source of water. To this end the Town commissioned BSEI to complete a
conceptual water servicing review. This conceptual water servicing study was completed in July
of 2013 and studied three primary water sources:
Treated water from the City of Calgary
Raw water from the Bow River
Raw water from the Highwood River.
For each of these sources the Total Cost of Ownership was investigated for both a supplemental
and standalone water servicing strategy.
On the 21st of November 2013 Okotoks’ council voted to support the City of Calgary
supplemental water supply option as identified in the BSEI study. In November of 2014 the City
of Calgary’s Mayor Naheed Nenshi confirmed that the City is prepared to provide Okotoks with
treated water.
As a next step the Town has completed this predesign study of a potable water pipeline between
the City and Town of Okotoks. Some of the predesign studies main goals are to:
To confirm timing requirements of the potable water pipeline and a Zone 4 reservoir.
To investigate potential and preferred alignment options for a pipeline.
To complete some of the preliminary engineering design of a pipeline.
Confirm some of the assumptions made in the BSEI study.
Some of the major conclusions from this predesign report are as follows:
A water pipeline is required ASAP. With current licenses and production capacity, water
supply shortages may be experienced as soon as 2016. Interim water supply servicing
strategies (including the current water queuing policy) will be required to manage these
shortfalls until a pipeline can be constructed.
The preferred pipeline alignment runs adjacent to Highway 2A from the intersection of
Macleod Trail and 210 Avenue SE to Okotoks’ Zone 3 reservoir.
Negotiations are required with the MD/AT over service road right of way use and access.
From a water storage perspective the construction of Zone 4 North reservoir can be
deferred 5-15 years. For future servicing and system reliability purposes there is an
independent need for a South reservoir that may further defer timing of the Zone 4N
reservoir.
The preferred pipeline material for a 25 year design horizon is 500mm-DIPS DR11
HDPE 4710 or 450mm-DIPS DR18 PVC.
The Town should consider upsizing the pipeline. The material cost difference to upsize
the pipeline by one diameter is less than $1.5M dollars. This represents less than 5% of
the total project cost and a capacity increase of 59% in HDPE and 31% in PVC.
A budgetary estimate for the pipeline is $31.5M.
2
Table of Contents
1. Current and Historical Water Consumption, License Capacity and Production.
1.1. Historical Water Consumption
1.2. License Capacity
1.3. Historical Water Production
2. Regional Waterline Supply Requirements
2.1. Population Projections
2.2. Supplemental Regional Water Pipeline Requirements
2.3. Reservoir Requirements
3. Pipeline Alignment
3.1. Pipeline Okotoks Zone 3N Urban Alignment Options
3.2. Pipeline Line Sizing and Booster Requirements
3.3. Pipeline Material Recommendation
3.4. Pipeline Upsize Recommendation
3.5. Pipeline Control Discussion
3.6. Construction and Design Standards and Specifications.
4. Cost
5. Conclusions
1. Current and Historical Water Consumption, License Capacity and Production.
1.1. Historical Water Consumption
Okotoks has been very proactive when it comes to water use and conservation. The Town
was recognized by the Federation of Canadian Municipalities as the 2015 winner in the water
category for its programs and initiatives to significantly reduce water use. Consumption in
litres per capita per day (Lppd) from Jan 1st, 2010 to Sep 14
th, 2014 is shown in Figure 1
below. The resulting data has been smoothed with a 3 day moving average to minimize any
daily irregularities that can be compensated through reservoir equalization and to assist in
determining the maximum daily design flow as per the Alberta Environment Sustainable
Resources Development (AESRD) Standards and Guidelines for Municipal Waterworks,
Wastewater and Storm Drainage Systems (SGMWWSDS) definition (3 day average). The
average consumption for this period is 266 litres per person per day (Lppd).
Figure 1: Daily Average Consumption per Year
2010 – 274 Lppd
2011 – 262 Lppd
2012 – 288 Lppd
2013 – 247 Lppd
2014 – 260 Lppd
The maximum daily consumption is approximately 450lppd as shown in Figure 2. These
consumption average and maximum peak factors for Okotoks are lower than other
comparable Alberta communities.
3
Figure 2: Daily Consumption per Capita (3 day moving average)
1.2. License Capacity
Okotoks’ Water Treatment Plant (WTP) diverts raw water from the Sheep River tributary of
the South Saskatchewan water basin. Ground Water Under the Direct Influence (GWUDI) of
surface water is pumped with shallow wells into the WTP. Okotoks’ current licensed
maximum diversion rate is 3293Ml/year. Approximately eight percent (8%) of the raw water
is lost to process losses such as backwashing and rinsing the filters leaving a maximum of
3030Ml/year of available treated water from Okotoks’ current licenses.
1.3. Historical Water Production
Okotoks’ WTP currently has limited production capacity. Specifically the WTP has limited
raw water capacity. Well gross daily production in cubic meters from 2010 to 2014 is shown
in Figure 3 below.
Net production capacity (less process losses) of the WTP from 2011 to 2014 is shown in
Figure 4. The current operational maximum WTP production capacity is 12Ml/day based on
peak single day actual production of the water treatment plant as shown in figure 4. A peak
capacity of 12Ml/day is optimistic as historically the plant does not have a history of
sustaining this rate for multiple days. It is assumed that with continued well maintenance and
operational improvements that this peak capacity can be sustained throughout the design
horizon.
150
200
250
300
350
400
450
500
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Co
nsu
mp
tio
n (
lpp
d)
2010 2011 2012 2013 2014
4
Figure 3: Daily Total Well Production
Figure 4: Net Daily Total Water Treatment Plant Production
3,000
5,000
7,000
9,000
11,000
13,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
We
ll P
rod
uct
ion
(m
3/d
ay)
2010 2011 2012 2013 2014
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
12,000
13,000
14,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Ne
t P
rod
uct
ion
(m
3/d
ay
2011 2012 2013 2014
5
2. Regional Waterline Supply Requirements
Due to limited current water supply the Town is targeting having a pipeline operational as
soon as possible. Allowing some time for approvals, funding and construction the town is
targeting an operational pipeline in 2018.
A 25 year design horizon has been selected for the regional water pipeline to align with the
SGMWWSDS and the Alberta Municipal Water/Wastewater Partnership (AMWWP) Water
for Life grant requirements. The pipeline ultimate design year will be 2043.
2.1. Population Projections
Two independent studies have been recently completed and both make growth projections.
The Conceptual Water Servicing Review, BSEI July 28, 2013 reviewed population
projections and assumed a linear growth rate of 1271.5 persons per year. The Town of
Okotoks Growth Study and Financial Assessment, O2 Planning and Design February 2014
assumed that the Town of Okotoks would receive a constant 4% share of the growth in the
Calgary Regional Partnership (CRP) region. Both models have been plotted in the Figure 5
below. At the end of our design horizon the projections lie within 10% of each other. As
these models do not differ significantly, this report will assume the more conservative linear
growth of 1271.5 persons per year.
Figure 5: Comparison of growth rates of 1271.5 persons/year and 4% of CMP growth
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
1990 2000 2010 2020 2030 2040 2050
Pro
ject
ed
Po
pu
lati
on
Year
1271.5 persons/year 4% of CRP growth
6
2.2. Supplemental Regional Water Pipeline Requirements
Figure 6 below projects water requirements from 2014 to 2043 based on the following:
Okotoks’ population in the 2014 municipal census was 27,331 persons. Population
growth is projected at1271.5 persons/year throughout the 2014-2043 period.
Total yearly water use is determined by multiplying population by 266 Lppd + 5% for
yearly variation = 279 Lppd.
Required Pipeline Yearly Supplement is determined by subtracting yearly water use from
current Maximum licensed yearly WTP production.
Maximum daily water demand is determined by multiplying population by 450lppd.
Pipeline daily Supplement is determined by subtracting Maximum WTP Daily
Production from Maximum Daily Water Demand.
Pipeline Instantaneous Supplement assumes 90% utilization of the pipeline. This is to
account for operational imperfections and any errors between theoretical and actual
pipeline performance.
As shown in Figure 6 below, if growth projections are met yearly current license capacity will
begin to be exceeded in 2016. Interim water solutions including the current water queuing policy
are being explored to bridge the gap in license capacity and raw water WTP capacity between
now and an operational pipeline. Some investigation of the costing for interim servicing options
has indicated that there are substantial costs associated with interim solutions. Specifically it is
becoming more difficult to drill additional wells that yield decent production capacity. It has
been suggested that interim servicing costing could greatly exceed $1million/year costs. Due to
the costing and short term complexity it is recommended that a pipeline is constructed as soon a
possible.
7
Figure 6: Yearly and Instantaneous Projected water requirements
Year Pop.
Total Yearly Water
Use
Maximum WTP
Licensed Water
Production
Required Pipeline Yearly
Supplement
Maximum Daily
Water Demand
Maximum WTP Daily Prod.
Pipeline Daily
Supplment Req'd
Pipeline Instant.
Supplement Req'd
(ML/yr) (ML/yr) (ML/yr) (ML/day) (ML/day) (ML/day) L/s
2014 27331 2786 3,030 - 12.3 12.0 0.3 3.8
2015 28603 2916 3,030 - 12.9 12.0 0.9 11.2
2016 29874 3045 3,030 16 13.4 12.0 1.4 18.6
2017 31146 3175 3,030 146 14.0 12.0 2.0 25.9
2018 32417 3305 3,030 275 14.6 12.0 2.6 33.3
2019 33689 3434 3,030 405 15.2 12.0 3.2 40.6
2020 34960 3564 3,030 534 15.7 12.0 3.7 48.0
2021 36232 3694 3,030 664 16.3 12.0 4.3 55.4
2022 37503 3823 3,030 794 16.9 12.0 4.9 62.7
2023 38775 3953 3,030 923 17.4 12.0 5.4 70.1
2024 40046 4082 3,030 1,053 18.0 12.0 6.0 77.4
2025 41318 4212 3,030 1,183 18.6 12.0 6.6 84.8
2026 42589 4342 3,030 1,312 19.2 12.0 7.2 92.1
2027 43861 4471 3,030 1,442 19.7 12.0 7.7 99.5
2028 45132 4601 3,030 1,571 20.3 12.0 8.3 106.9
2029 46404 4731 3,030 1,701 20.9 12.0 8.9 114.2
2030 47675 4860 3,030 1,831 21.5 12.0 9.5 121.6
2031 48947 4990 3,030 1,960 22.0 12.0 10.0 128.9
2032 50218 5119 3,030 2,090 22.6 12.0 10.6 136.3
2033 51490 5249 3,030 2,220 23.2 12.0 11.2 143.7
2034 52761 5379 3,030 2,349 23.7 12.0 11.7 151.0
2035 54033 5508 3,030 2,479 24.3 12.0 12.3 158.4
2036 55304 5638 3,030 2,608 24.9 12.0 12.9 165.7
2037 56576 5768 3,030 2,738 25.5 12.0 13.5 173.1
2038 57847 5897 3,030 2,868 26.0 12.0 14.0 180.4
2039 59119 6027 3,030 2,997 26.6 12.0 14.6 187.8
2040 60390 6156 3,030 3,127 27.2 12.0 15.2 195.2
2041 61662 6286 3,030 3,256 27.7 12.0 15.7 202.5
2042 62933 6416 3,030 3,386 28.3 12.0 16.3 209.9
2043 64205 6545 3,030 3,516 28.9 12.0 16.9 217.2
In order for the City of Calgary to assess whether they could provide Okotoks with treated water
they requested Okotoks to submit projected water demands. They were provided with projected
demands of 767ML/year and 4.6ML/peak day in 2021 and 2954ML/year in 2038 (these demands
are slightly skewed as end of calendar year population projections were used vs. census May
populations).
8
2.3. Reservoir Requirements
Okotoks currently has three reservoirs and a total of 21Ml of reservoir storage. SGMWWSDS
outlines the minimum required reservoir storage for municipalities with a WTP capable of
satisfying the maximum daily design flow with the following formula:
S = A + B + (the greater of C or D)
Where S = Total storage requirement, m3
A = Fire storage, m
3
B = Equalization storage (approximately 25% of projected maximum daily design
flow), m3
C = Emergency storage (approximately 15% of projected average daily design flow),
m3
D = Disinfection Contact Time (T10) storage to meet the CT requirements, m3
When looking at the three reservoirs as a system the emergency storage requirement is greater
than the Disinfection CT requirement. Thus, if fire storage is subtracted from the total available
storage we will be left with the volume available for equalization and emergency storage. A
detailed evaluation of fire flow requirements in the town of Okotoks is beyond the scope of this
report, however a flow rate of 225l/s will be assumed as this rate is typical for the Town’s
commercial districts. Fire Underwriters Water Supply for Public Fire Protection 1999, tabulates
fire flow requirements vs. the required duration of fire flow. For a flow rate of 225l/s
approximately 3h of storage is required, yielding 2430m3 of fire storage required per reservoir.
Figure 7 below outlines the current total available storage for emergencies and equalization. The
clear well volume has not been included in the available storage as a portion of the South
Reservoir is not available for distribution due to hydraulic pumping complexities in the system
with respect to delivering water to the Zone 2 reservoir.
Figure 7: Current Reservoir Storage
Volume
Fire Storage
Volume for emergency and equalization
South Stage 1 Clearwell 1,031
- m
3
South Reservoir
5,903 2,430 3,473 m3
Zone 2N Reservoir
6,983 2,430 4,553 m3
Zone 3N Reservoir
7,115 2,430 4,685 m3
Total Volume
21,032 7,290 12,711 m3
Storage Available for emergency and Equalization 12,711 m3
The SGMWWSDS reservoir storage formula does not fully apply to a supplemental supply
servicing strategy as it is intended to be used in municipalities that are only supplied by a WTP.
Municipalities that are supplied by a regional pipeline are typically sized for a specific number of
9
emergency days storage. The number of days storage is typically enough to repair a pipeline
break on the waterline during a maximum demand day period. Typically sizing is based on an
acceptable risk profile and the repair timeline of a broken pipeline. This is typically between 1-3
days storage. The supplemental supply strategy that has been selected reduces the operational
risk of a WTP failure or a pipeline break as an alternate service is available to supply partial
demand through either failure event.
As two sources are available and standard process design for municipal waterworks excludes
double jeopardy failures, reservoir storage should be sufficient to cover the larger of the
SGMWWSDS supply requirements or a sufficient number of days storage of the supplemental
pipeline maximum daily volume requirement.
Figure 8 outlines the minimum AESRD SGMWWSDS reservoir storage requirements and the
number of days of maximum supplemental supply storage available based on current reservoir
capacity. It is clear that currently there is enough current storage capacity to satisfy
SGMWWSDS minimum capacity requirements until 2043. Additional reservoir capacity is
required between 2022 and 2035 to satisfy the requirement for multiple days of pipeline
supplemental storage. Reservoir storage should be designed to a much shorter design horizon ie.
10 years and constructed in phases to mitigate operational issues as outlined in SGMWWSDS.
It is suggested that an additional north reservoir as outlined in the BSEI report is not required at
the time of pipeline construction. Until the Zone 4N reservoir is required the pipeline could tie
into the existing Zone 3N Reservoir.
Ultimately a Zone 4N reservoir will be required and the pipeline should be designed to fill this
future Reservoir. Timing of the construction of the Zone 4N reservoir will have to be
coordinated with other additional reservoirs in the updated 10 year capital plan. This
coordination would include the requirements for a future reservoir on the South End of Okotoks
(required to service future annexed growth areas and for distribution network reliability). The
additional storage gained in the South Reservoir may further defer the timing requirements of a
north reservoir.
10
Figure 8: Reservoir Timing and Sizing Requirements Year Pop. Average
Daily Water
Demand
Maximum Daily
Water Demand
AENV Current Emerg +
Equil. Storage
AENV Required Emerg +
Equil. Storage
Maximum WTP Daily Prod.
Pipeline Daily
Supplment Req'd
Days of Pipeline
Capacity in Storage
(ML/day) (ML/day) (ML/day) (ML/day) (ML/day) (ML/day) days
2018 32,417 9.1 14.6 12.7 5.0 12.0 2.6 4.9
2019 33,689 9.4 15.2 12.7 5.2 12.0 3.2 4.0
2020 34,960 9.8 15.7 12.7 5.4 12.0 3.7 3.4
2021 36,232 10.1 16.3 12.7 5.6 12.0 4.3 3.0
2022 37,503 10.5 16.9 12.7 5.8 12.0 4.9 2.6
2023 38,775 10.8 17.4 12.7 6.0 12.0 5.4 2.3
2024 40,046 11.2 18.0 12.7 6.2 12.0 6.0 2.1
2025 41,318 11.5 18.6 12.7 6.4 12.0 6.6 1.9
2026 42,589 11.9 19.2 12.7 6.6 12.0 7.2 1.8
2027 43,861 12.3 19.7 12.7 6.8 12.0 7.7 1.6
2028 45,132 12.6 20.3 12.7 7.0 12.0 8.3 1.5
2029 46,404 13.0 20.9 12.7 7.2 12.0 8.9 1.4
2030 47,675 13.3 21.5 12.7 7.4 12.0 9.5 1.3
2031 48,947 13.7 22.0 12.7 7.6 12.0 10.0 1.3
2032 50,218 14.0 22.6 12.7 7.8 12.0 10.6 1.2
2033 51,490 14.4 23.2 12.7 7.9 12.0 11.2 1.1
2034 52,761 14.7 23.7 12.7 8.1 12.0 11.7 1.1
2035 54,033 15.1 24.3 12.7 8.3 12.0 12.3 1.0
2036 55,304 15.4 24.9 12.7 8.5 12.0 12.9 1.0
2037 56,576 15.8 25.5 12.7 8.7 12.0 13.5 0.9
2038 57,847 16.2 26.0 12.7 8.9 12.0 14.0 0.9
2039 59,119 16.5 26.6 12.7 9.1 12.0 14.6 0.9
2040 60,390 16.9 27.2 12.7 9.3 12.0 15.2 0.8
2041 61,662 17.2 27.7 12.7 9.5 12.0 15.7 0.8
2042 62,933 17.6 28.3 12.7 9.7 12.0 16.3 0.8
2043 64,205 17.9 28.9 12.7 9.9 12.0 16.9 0.8
3. Pipeline Alignment
The Town has met with the City of Calgary’s water resources department to discuss an
appropriate tie-in location for a regional water pipeline. The most appropriate tie-in location
is between the roadway and property line on the NE corner of the intersection of Macleod
Trail and 210 Avenue SE. The absolute static pressure of this tie in location is at 1115.6m
when the elevated storage is full and 1112.6m at the reserved storage level.
Potential alignments between the intersection of Macleod trail and 210 Avenue SE and the
Town of Okotoks Zone 3N Resevoir were investigated. Five alignments were explored as
11
shown in Figure 9 and a summary of the pros and cons of each alignment is outlined in
Figure 10.
Alignment options along 32nd
Street East and 32nd
Street west options were discarded
because of the additional distance required to route a pipeline along these routes and because
the presence of other buried cable right-of-ways along 32nd
Street East.
An alignment adjacent to the rail road was also explored to see if it would be possible to
eliminate the need for a booster station by following the more gradually graded rail road.
This rail road alignment was discarded because it did not eliminate the need for a booster
station and introduced the requirements for additional rail road crossings and travel through
environmentally sensitive lands.
The three remaining alignments were shortlisted for further comparison as displayed in
Figure 11.
The Highway 2A alignment proposes to follow the highway service road corridor
between the two tie-in locations.
The high pressure gas alignment proposes to run adjacent to the existing high pressure
gas line between Calgary and Okotoks.
The Range Road 295 alignment proposes to follow the Range Road 295 right of way,
much of which presently does not have a road constructed in.
A digital elevation model (DEM) consisting of topographic light detection and ranging
(LiDAR) information was purchased from AltaLIS with 15m post spacing / 30cm accuracy
and is underlain in a colour gradient in the backgrounds of Figure 9 and 11. The LiDAR
DEM data was extrapolated along each of the shortlisted alignments and elevation profiles of
these alignments are shown in Figure 12. Fine tuning of the alignments and survey data will
be required at the detailed design phase of this project. It is expected that field survey data
and alignment adjustments may differ somewhat from the LiDAR DEM, but for the purposes
of predesign the LiDAR data is likely sufficient.
Through examining Figure 12 a few generalized conclusions can be made about each route as
summarized in Figure 10:
The HWY 2A route is the smoothest and has the least elevation gain.
The RR295 is the longest and has several abrupt changes in elevation. Field survey
of the RR295 route reveals that this route has the most challenging terrain and has
some difficult site access issues.
The high pressure gas line alignment bisects and crosses multiple parcels - land
owner consultation is expected to be the most difficult with this option adding
concerns over project timing and the cost of land acquisition.
When reviewing Figure 10 the HWY 2A option emerges as the preferred option.
12
Figure 9: Conceptual Pipeline Alignments
Legend HWY 2A (Preferred) High Pressure Gas RR295 32nd Street East/West Rail Road
13
Figure 10: Alignment Pro and Con Summary
Route Pro Con
Hwy 2A
(Preferred Alignment) Distance ~ 16.5km
Good equipment access
Dealing Primarily with
one jurisdiction for
Right of way acquisition.
Potentially limited
additional fees for land
acquisition.
High Pressure Gas Distance ~ 16.2km
Complex Landowner
Negotiation with
potential concerns over
widening bisected
parcels.
Extended Period for land
acquisition.
High land acquisition
costs.
Right of way must be
wide enough for site
access
RR295 Distance ~ 18km
Dealing Primarily with
one jurisdiction for
Right of way acquisition
Challenging terrain and
site access. (Increased
costs).
32nd
Street East/West Distance > 21km
Buried Cable Utility
ROW on 32nd
Street
East.
High parcel
fragmentation on 32nd
Street East.
Rail Road Distance > 20km
Multiple RR crossings
Environmental
Senstivity
Complex Terrian
River Crossing
14
Figure 11: Shortlisted Conceptual Pipeline Alignments
Legend HWY 2A (Preferred) High Pressure Gas RR295
Calgary Tie In
Okotoks Zone 3N Tie In
Future Zone 4N Reservoir (Potential Location)
15
Figure 12: Elevation profiles of shortlisted conceptual Pipeline Alignments (Proposed Construction Profile)
1000
1050
1100
1150
1200
0 2500 5000 7500 10000 12500 15000 17500 20000
Ele
vati
on
(m
)
Length (m)
HWY 2A - Preferred RR295 High Pressure Gas
16
3.1. Pipeline Okotoks Zone 3N Urban Alignment Options
Several conceptual alignment options exist to tie into the Zone 3N Reservoir within the Town of
Okotoks as shown in Figure 13 below. All alignments will disrupt traffic and residents on the
Bannister Gate/Drive or Milligan corridors. Selection of the ultimate alignment within the town
boundary will be part of the detailed design exercise and will take into account several factors
including: available space in the roadway, coordination with other required utility upgrades, cost,
technical feasibility and impact to residents.
Figure 13 – Pipeline C Urban Alignment Options
Bannister Gate
Good Shepard
Zone 3 Reservoir
Milligan Drive
17
3.2. Pipeline Line Sizing and Booster Requirements
Pipelines are typically designed for a number of parameters including but not limited to fluid
velocity, working/surge pressures and cyclic loading. An iterative design approach calculating
pressure losses at available pipe sizes was taken to arrive at a final minimum pipe ID of 439mm
(17.3”). The Design Parameters at this sizing are shown in Figure 14. Figure 14 assumes that
the HWY 2A alignment is selected and is designed to the ultimate future scenario, which would
be to fill the future Zone 4N reservoir. The design flow rate of 217 L/s is the instantaneous
supplement requirement from Figure 6 in 2043. The highlights of Figure 14 include a 1.4m/s
flow velocity and a pressure boost of 102.2m of water required at approximately 5.5km from the
Calgary tie in location.
Figure 14 – Pipeline Design Parameters.
Description METRIC UNITS IMPERIAL UNITS
Instantaneous Flow 217 l/s 3443 USGPM
Hazen-Williams Coefficient of Pipe [PVC = 150] 150
150 Internal Diameter of pipe 439.4 mm 17.3 in
Pipe Flow Velocity 1.4 m/s 4.7 (ft/s)
Linear Pressure drop 3.2 m of H2O/km 1.4 (psi/1000ft)
Pressure at Beginning of Pipeline (ASL) 1112.6 m 3650.3 ft Length to pipeline to future Reservoir (HWY2A Alignment) 15.5 km 50852.9 ft
Pressure drop 49.8 m of H20 163.2 ft of water
Elevation of Final Reservoir 1165 m 3822.2 ft
Booster Requirement 102.2 m of H20 335.3 ft of water
Proposed Booster Location (from Calgary Tie In) 5.5 km 18045 ft
Figure 17 displays the conceptual future pipeline profiles to a future Zone 4 reservoir along with
a hydraulic gradeline of a 439.4mm/17.3” ID pipeline at design conditions. A teed-off valve
would be included in the design to accommodate this future installation of this reservoir.
3.3. Pipeline Material Recommendation
Pipelines materials and wall thickness are selected to operate within the design pressures of a
pipeline. Figure 18 displays the gauge pressure of a pipeline along the HWY 2A alignment in
PSI. Figure 15 displays the calculated operating pressures and the expected surge pressure or
“water hammer” expected from a rapidly closing valve or pump failure. In the predesign study a
single pressure surge event has been contemplated. The detailed pipeline design should include
analysis of transient effects along the pipeline and cyclic loading.
Although calculation for surge pressure is included in the design all efforts in the final design
should be made to eliminate the opportunity for hammer as it adds risk to the system and
sometimes reduces the lifespan of the pipeline. These reductions should include some if not all
18
of the following: variable frequency drives (VFD’s) on booster pump motors, surge tanks,
control systems, slow closing valves, pressure reliefs, maximum flow rate control and
installation of combination air/vacuum release valves.
Figure 15: Highway 2A alignment material allowable pressures
Description METRIC UNITS IMPERIAL UNITS
Material PVC HDPE 4710 PVC HDPE 4710
Size 450mm - DR18 500mm - DR11 18" - DR18 20" - DR11
Instantanous Dynamic Modulus of Pipe (kPa , PSI) 2,757,903 1,034,214 400,000 150,000
Pipe Internal Diameter (mm , inches) 439 443 17.30 17.44
Thickness (mm , inches) 27.4 49.9 1.08 1.96
Pipe Flow Velocity (m/s , ft/s) 1.4 1.4 4.7 4.6
Wave Velocity (m/s , ft/s) 394 328 1292 1076
Surge Pressure (kPa , PSI) 563 462 82 67
Maximum Operating Pressure (kPa , PSI) 1,133 1,133 164 164
Allowance for control shutdown (kPa , PSI) 138 138 20 20
Surge Pressure + Operating (kPa , PSI) 1,834 1,732 266 251
Allowable Pressure (kPa , PSI) 1,620 1,379 235 200
Allowable Recurring Surge Pressure (kPa , PSI) 448 689 65 100
Total allowable Recurring Surge Pressure (kPa , PSI) 2,068 2,068 300 300
High Density Polyethylene (HDPE type 4710) is considered as an alternate potential material to
Polyvinyl Chloride (PVC) in Figure 15. Due to differences in internal diameter a 500mm HDPE
pipe sized with Ductile Iron Pipe Standards (DIPS) is equivalent in internal dimensions to a
450mm PVC pipe. Table 15 summarizes that for the pressures expected a minimum size class of
DR11 should be selected for HDPE and a minimum size class of DR18 should be selected for
PVC.
HDPE has some advantages to PVC pipe as it is typically fused with few joints, is tougher (ie.
has increased tensile elongation prior to breaking, better impact resistance, better rapid creep
resistance, surge and cyclic resistance) experiences slightly less surge pressures, can be
directionally drilled/pulled and can potentially be installed straight-cut reducing ROW and
excavation requirements. Initial cost comparisons have shown some potential for cost savings
for HDPE construction.
Ultimately pipe material selection is part of the pipeline detailed design. Final pipe selection will
be affected by the final design details, preferred installation method and cost of material at the
time of construction. HDPE should be considered as an alternate to PVC at the detailed design
phase of this project.
19
3.4. Pipeline Upsize Recommendation
It is worth considering upsizing the pipeline to accommodate a potential for additional future
regional users and/or growth beyond the 25 year design horizon. A comparison of flow rates and
the populations that can be serviced by a pipeline upsized one nominal pipe diameter is
summarized in Figure 16 below. For the purpose of evaluation the pressure drop is held
approximately constant for the upsized diameter and flow rates are increased.
Figure 16: Comparison of flow rates and equivalent populations that can be serviced by
pipeline upsized one nominal pipe diameter.
Pipe Type HDPE 4710 HDPE 4710 PVC PVC Pipe Size 500mm-DIPS 600mm-DIPS 450mm - DIPS 500mm - DIPS Pressure Class DR11 DR11 DR18 DR18 Instantanious Flow 217 345 217 285 L/s
Population Equivalent* (450LPPD @ 90% utilization) 37538 59616 37498 49248 Persons
Hazen-Williams Coefficient 150 150 150 150 Internal Diameter of pipe 442.9 529.0 439.4 487.7 mm
Pipe Flow Velocity 1.4 1.6 1.4 1.5 m/s
Linear Pressure drop 3.09 3.06 3.20 3.19 m of H2O/km
*Population Equivalent reflects the population that can be served solely by the pipeline.
The material cost difference to upsize the pipeline by one diameter is less than $1.5M dollars.
This represents less than 5% of the total project cost and a capacity increase of 59% in HDPE
and 31% in PVC.
3.5. Pipeline Control Discussion
Although control of the pipeline is part of the detailed design, this report will briefly explore two
control strategies that can be used for the pipeline and booster station. The first control strategy
would have an open pipe into the receiving reservoir and to turn the booster station pumps on/off
with remote control based on the receiving reservoir level. The second control strategy would be
to run the booster station on VFD pressure control independent of the reservoir and to open/close
an independent slow moving valve at the receiving reservoir based on reservoir level. There is
the possibility of doing a hybrid option but the predesign will focus on discussion of the two
different control strategies.
In the first scenario the pipeline after the highpoint will drain (or be on vacuum) after pump
shutdown. One of the advantages of this control design is that the pressure in the pipeline will
on average be lower after the system highpoint and that the system does not in normal operation
have to worry about rapid valve closures. However this control design has a few inherent
weaknesses. These weaknesses include the following:
20
The system is dependent on the communications link. If there is a communication or
power failure the system may not run properly leading to manual operation or reservoir
overfill/low level.
On shutdown or pump failure the pipeline could experience vacuum conditions and
collapse the pipeline. Pipelines typically do not have good resistance to vacuum
conditions. This collapse risk is somewhat analogous to a straw – if someone plugs the
end of the straw and blows, it is hard to burst, however if they suck the straw may
collapse. A slow pump ramp-down will be required and transient analysis may
recommend installation of a fly-wheel (non-standard pump design) to mitigate the effects
of pump/power failure. Failure of a vacuum/combination valve could also lead to
similar vacuum conditions
Large volumes of air increases hammer risk. The exhaust of air rate needs to be
controlled. Joints are often designed to prevent the escape of water. Air can escape
from joints at higher rates than water leading to hammer when the water reaches the leak
location. Also air is compressible and can introduce new dynamics to transient analysis.
Risk of contamination. When the pipeline drains the vacated space is filled with air and
at zero gauge pressure. Although the introduction of air poses a very minor risk a larger
risk presents itself if there is a small pipeline leak (such as at a flange or gasket) and
groundwater is present. It is possible that contaminated groundwater could enter the
pipeline.
In the second scenario the valve will close and the pressure will gradually build up from the
valve to the booster station until the pumps reach their programmed shut down pressure.
Although this system will experience higher pressures and cyclic loading, this design is superior.
Some of the highlights of this design include:
An independent somewhat simplified control system. This system is not sensitive to
communication failure or power failure. The actuated valve at the reservoir should be
designed to be normally closed.
There is little air introduced to the system after commissioning.
Easier detection of minor leaks. If pumps are cycling when the line is shut in, this is
indicative of a leak (likely a leak could be from a check valve but it could also be a valve
or the pipeline itself).
Sensitivity to rapid valve closure will have to be mitigated with high quality control
valves, VFD Pump control, surge tanks and pressure reliefs.
Control for chlorine monitoring and trim should also be contemplated and designed into the
pipeline booster station or receiving reservoir. Long water transmission times within the pipeline
could lead to reduced free chlorine residuals at the receiving reservoir. Pipeline design should
accommodate chlorine residual testing and addition, if required.
21
3.6. Design and Construction Standards and Specifications
The Town of Okotoks uses the 2014 City of Calgary Standard Specifications for Waterworks
Construction. Detailed design and construction will need to conform to these standards.
In addition the following standards must be adhered to within the Town of Okotoks municipal
boundary:
2013 Town of Okotoks General Design and Construction Specifications
2012 City of Calgary Standard Specifications for Roads
2012 City of Calgary Landscape Construction Guidelines.
3.7. Conservation and Reclamation Study
This pipeline is a Class I pipeline and under Alberta Environment Environmental Protection
Guidelines it requires a Conservation and Reclamation (C&R) approval prior to any surface
disturbance. Obtaining this approval is beyond the scope of this predesign report.
Figure 17: Future Elevation Profiles and Pipeline Hydraulic Gradeline (439.4mm/17.3” ID) to future Zone 4 Reservoir (Ultimate Design Condition)
1000
1050
1100
1150
1200
0 2500 5000 7500 10000 12500 15000 17500 20000
Ele
vati
on
(m
)
Length (m)
HWY 2A - Preferred RR295 High Pressure Gas Absolute Pipeline Pressure
Tee-in location for future Zone 4 Reservoir fill pipeline
23
Figure 18: Operating Guage Pressure Profile in PSI of Highway 2A alignment to Future Zone 4 Reservoir (Ultimate Design Condition)
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
180.0
200.0
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
Pre
ssu
re (
PSI
)
Horizontal Distance (m)
Tee-in location for future Zone 4 Reservoir fill pipeline
4. Cost
Updated budgetary cost projections for a potable water pipeline are included below. This table
includes some additional costs not included in previous estimates such as urban pipeline
construction, reservoir tie in (included in urban costs), metering stations, potential directional
drilling and land acquisition costs. There is some uncertainty over land acquisition, directional
drilling requirements and additional Municipal District (MD) / Alberta Transportation (AT)
design considerations as negotiations with the MD/AT over pipeline alignment have not yet
begun. As such this estimate is still a high level budgetary estimate. Additional budgetary cost
refinement is required at the detailed design stage of this project.
Figure 19: Pipeline budgetary cost projections
Quantity Unit Cost Subtotal
Pipeline Rural Cost 15000 m 1,100$ $/m 16,500,000$
Pipeline Urban Cost 1500 m 2,100$ $/m 3,150,000$
Booster Station 1 ea 2,000,000$ $/ea 2,000,000$
Metering Station 1 ea 700,000$ $/ea 700,000$
Land acquisition (if required) 76 acres 40,000$ $/acre 3,040,000$
Subtotal 25,390,000$
Professional Services (Consulting, C&R, Land Agents etc.) 8% 2,031,200$
Contingency 15% 4,113,180$
Total Budget 31,534,380$
25
5. Conclusions
Some of the major conclusions from this predesign report are as follows:
A water pipeline is required ASAP. With current licenses and production capacity, water
supply shortages may be experienced as soon as 2016. Interim water supply servicing
strategies (including the current water queuing policy) will be required to manage these
shortfalls until a pipeline can be constructed.
The preferred pipeline alignment runs adjacent to Highway 2A from the intersection of
Macleod Trail and 210 Avenue SE to Okotoks’ Zone 3 reservoir.
Negotiations are required with the MD/AT over service road right of way use and access.
From a water storage perspective the construction of Zone 4 North reservoir can be
deferred 5-15 years. For future servicing and system reliability purposes there is an
independent need for a South reservoir that may further defer timing of the Zone 4N
reservoir.
The preferred pipeline material for a 25 year design horizon is 500mm-DIPS DR11
HDPE 4710 or 450mm-DIPS DR18 PVC.
The Town should consider upsizing the pipeline. The material cost difference to upsize
the pipeline by one diameter is less than $1.5M dollars. This represents less than 5% of
the total project cost and a capacity increase of 59% in HDPE and 31% in PVC.
A budgetary estimate for the pipeline is $31.5M.
Prepared By: Third Part Review By:
Senior Engineer Principal / Project Engineer
Town of Okotoks BSEI Consulting
)