National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Pre-Bid MeetingINTRODUCTION AND UPDATES
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Introduction
Agenda
1 Introduction & Overview
2 Project Site
3 Core and Shell Space Program
4 Schematic Design
5 Special Requirements
2
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Overview
University of the Philippines SystemPremier institution for education and government service
Land Area = 16,000 hectares UP Manila = 14 hectares UP Diliman = 493 hectares UP Los Banos = 15,000 hectares
ManilaHealth Sciences Center Philippine General HospitalNational Institutes of HealthExtension Services
LeyteKoronadalAurora
Los Banos Open University
Diliman Olongapo Pampanga
Baguio Visayas
Cebu Iloilo City Tacloban Miagao
Mindanao
2013 endowment = $238 M
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Overview
Building Project OrganizationUniversity of the Philippine Manila - National Institutes of Health
Special Bids and Awards Committee
(SBAC)
Technical Working Group
(TWG)
Construction Management TeamOn-Site Supervision – Architecture, Engineering, Commissioning Cx
(Public Bidding)
UP Manila National Institutes
of HealthEnd Users
Design and Construction Team for Design-Build Contract
(Public Bidding)
3
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Agenda
1 Introduction & Overview
2 Project Site
3 Core and Shell Space Program
4 Schematic Design
5 Special Requirements
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Dense Urban Site Conditions
West – view of Manila Bay
East – view of LRT and Taft Avenue
North – view of NIH, project site, PGH complex
4
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Dense Urban Site Conditions
Bird’s Eye View – left to right, Manila Bay, Robinson’s, UP Manila and NIH, Light Rail Transit
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Dense Urban Site Conditions
Bird’s Eye View
5
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Existing Site Infrastructure
Bird’s Eye View
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Existing Site Electrical
Bird’s Eye View
6
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Existing Site Sewer and Drainage
Bird’s Eye View
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Project Site
Dense Urban Site Conditions
Front Left Oblique View
Front – Bird’s Eye View Rear– Bird’s Eye View
Right Side – Bird’s Eye View
7
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Core and Shell Space Program
Agenda
1 Introduction & Overview
2 Project Site
3 Core and Shell Space Program
4 Schematic Design
5 Special Requirements
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
TotalOffice and
Office SupportShared
AmenitiesLaboratory
BSL-2Laboratory
BSL-3Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Net Assignable Program Area (SM) 17,755 2,499 11,774 2,639 93 451 110 191Area Type as % of Total 14.1% 66.3% 14.9% 0.5% 2.5% 0.6% 1.1%
Full Fit-Out Construction 11,794 2,499 8,333 652 0 0 0 310Shell Space Construction 5,961
Parking Space 5,508Mechanical Systems 2,165
Horizontal Circulation 6,769Vertical Circulation 2,189
Estimated Gross Floor Area 34,386Building Efficiency 51.63% = Net Area/ Gross Area
NIH Core and Shell Space Program - Summary
8
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
NIH Core and Shell Space Program – Shared Amenities
Office and Office
Support
Shared Amenities
Laboratory BSL-2
Laboratory BSL-3
Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Office of the Vice Chancellor for Research (OVCR) 389National Institutes of Health (NIH)
NIH Offices (Administration, RDITC, IT/Server Rooms) 573 191Conference Rooms, Meeting Rooms, Training Rooms 674Technology Business Incubator (TBI) Space 3,845Central Sample Collection 86Mail Room 12Central Storage Room 60Service Pantry 87Fitness Center 117Clinical Trial Center 738Clinical Research Room 117Central Laboratory 116Laboratory Support Areas 425Lobbies/Lounge Areas 1,912Concessions/ Staff Dining Area 549Auditorium 908Speakers' Lounge 84Breakout Rooms 863Executive Dining Hall 147Roof Deck Garden 576
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Office and Office
Support
Shared Amenities
Laboratory BSL-2
Laboratory BSL-3
Vivarium ABSL-2
Vivarium ABSL-3
Data Center/ IT/ LAN
Institute of Molecular Biology and Biotechnology (IMBB) 109 608 93 113 110Institute of Aging (IA) 63Institute of Child Health and Human Development (ICHHD) 81
Institute of Clinical Epidemiology (ICE) 99
Institute of Health Policy and Development Studies (IHPDS) 81Institute of Herbal Medicine (IHM) 91 263 78Institute of Human Genetics (IHG) 576 1,079Institute of Ophthalmology (IO) 153 138Institute of Pharmaceutical Sciences (IPS) 109 275
Philippine National Ear Institute (PNEI) 109 162National Telehealth Center (NTHC) 153Newborn Hearing Screening Reference Center (NHSRC) 90Newborn Screening Reference Center (NSRC) 398College of Medicine Vivarium 259
NIH Space Program – Dry and Wet Laboratories
9
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Agenda
1 Introduction & Overview
2 Project Site
3 Core and Shell Space Program
4 Schematic Design
5 Special Requirements
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
10
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
1
11
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
2
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
31
12
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
4
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
5
13
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
6
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
7
14
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
8
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
9
15
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
10
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
11
16
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
12
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
13
17
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
14
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
15
18
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
19
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
20
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
21
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
1 Introduction & Overview
2 Project Site
3 Core and Shell Space Program
4 Schematic Design
5 Special Requirements
Agenda
22
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Architecture Energy Saving Exterior Building Shell Low VOC and Chemically Resistant Interior Finishes Code Requirements for Mixed-Uses, i.e. Separations Wall and door partition schedule UL fire-rated partition systems Wall partition type for STC 65 acoustical rating
Building setback requirements Accommodations for the disabled Full fit-out of Auditorium + Conference Ctr for 500 p. Full fit-out of Institute offices Fit-out of Laboratories with Institute Requirements Above-ground or Underground Parking for 140 cars
Special Requirements
Architectural, Engineering and Construction Specialties
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
Engineering Construction within occupied campus Geotechnical report will impact structural design HVAC and Building Services provided for future fit-out 100% Exhaust for Laboratories and Vivariums Reliable electrical systems Effluent decontamination for laboratories Septic holding tank prior to entry to Manila sewer
23
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
SUPPLY AIR 100% outside air variable air volume air
handling units supplying conditioned air to a manifolded supply air distribution system
conditioned supply air delivered to each laboratory space maintains the required directional airflow requirements, space temperature and humidity conditions, and building pressurization.
100% outside air variable volume air handling unit(s) located in the Penthouse.
conditioned supply air will be distributed to the floors and individual air terminal units for occupied rooms.
Core+ShellHVAC system for laboratory areas
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
EXHAUST AIR Exhaust from each space, is required to
maintain either a defined air change rate or to remove contaminants,
Exhaust is removed via an exhaust airflow control device that is connected to an exhaust manifold.
Exhaust manifold is then exhausted by roof mounted laboratory grade exhaust fans.
Both the variable air volume air handling units and the exhaust fans will be sized to provide 100% redundant capacity for animal areas and 60% redundancy for non-critical laboratory areas.
Core+ShellHVAC system for laboratory areas
24
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
COOLING OF OUTSIDE AIR
Cooling of the outside air for laboratory areas and for outside air for building ventilation will be provided by a chilled water plant located in the Penthouse.
The chillers will be centrifugal water cooled chillers with variable speed primary chilled water pumps and variable speed condenser water pumps.
The chillers will reject heat to cooling towers mounted on the roof.
Core+ShellHVAC system for laboratory areas
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
RE-HEAT AND ENERGY EFFICIENCY
Hot water for reheat purposes in the laboratory areas will be provided by condensing type gas-fired boilers located in the Penthouse.
Energy efficiency technologies will be utilized to minimize loads to the maximum extent reasonably possible without compromising system reliability.
Core+ShellHVAC system for laboratory areas
25
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Engineering Requirements
Infrastructure for Future Vivarium and Biosafety Level 3
Future BSL-3, ABSL 2, ABSL 3 Level 13
Mechanical Penthouse HEPA filters, electrical, plumbing, water tanks
14th Level
MEP / Effluent Treatment for 13th and Future BSL-2
Levels 6-12
Roof TopSmoke Stacks / Scrubbers
15th Level
Full Fit-out Offices and
ConferencingLevels 3-10 Full Fit-out
Auditorium (500p)
Levels 3-5
Full Fit-out Parking(140 c)
Levels 1-3
Effluent Treatment and Fit-out BSL-2
Levels 6-12
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
2013 Laboratory of the YearNational Research Foundation, Campus for Research Excellence and Technological Enterprise (CREATE), Singapore.
26
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
Roof mounted units and central utility plant Centers for Disease Control (CDC), Atlanta, GA
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
Concept Design for HVAC Systems, Zoning and Access
27
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
Concept Design for HVAC Systems, Zoning and Access
Roof mounted exhaust stacks100% laboratory exhaust
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
Concept Design for HVAC Systems, Zoning and Access
Main Electrical Room Service Corridor and Utility Access
28
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Architectural, Engineering and Construction Specialties
HEPA filter bank and mechanical service area above vivarium and containment
Concept Design for HVAC Systems, Zoning and Access for Maintenance
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Requirements
Laboratory Hazard Survey + Risk Assessment
29
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Chemical:Flammables, acids, corrosives, reactive chemicals, carcinogens, mutagens, teratogens, toxins, compressed gases
Radiological:Radionuclides and equipment that produces ionizing radiation
Physical:Lasers, magnetic fields, moving parts, high voltage, high noise, ultraviolet light, extreme heat or cold, high pressure vessels
Biological:Etiologic agents, material containing etiologic agents, organisms with recombinant DNA, toxins, allergens
Special Building Features
Laboratory Hazards
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Administrative - Public
Clerical - Semi Public
Laboratory - Restricted Access
Lab Support - Restricted Access
NonHazardous
Hazardous
Public &Personnel
SpecimensMail &Deliveries
Receiving & Accessioning
WasteHolding
Processing
SampleStorage
Media PrepSupplies
DisposalControl
Control
Special Building Features
Mixed-Used Building Planned for Safe Circulation
Control
30
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Open Laboratory Concept
100% Laboratory Exhaust Air
Variable Air Volume System
LEED /Labs 21 Energy Saving Strategies
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Flexibility
Fume Extraction for Instrument Laboratories
31
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Flexibility
Equipment Zones with Supplemental Air Units
Sterilizers with Canopy Hoods
Local Gas Storage Rooms with Safety Alarms
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Lighting Views and Daylight Lighting Levels Glare Control
Ventilation Temperature Control Air Movement and Ventilation Humidity Control Air Quality
Structure Contamination Control Vibration Isolation Noise Attenuation
Quality of Space Facilitation of Interaction Attracting and Retaining Staff Multidisciplinary Facility Flexible and Adaptable
Special Building Features
Quality Environment
32
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Quality Environment – Containment Devices
Future Vivarium exhaust hood Future Vivarium downdraft table
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Quality Environment – Training Labs and Classrooms
Laboratory exhaust in Training Laboratories
33
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Temperature & Humidity Control
• Equipment heat locally controlled with dedicated exhaust arms
• Room level temperature and humidity controls
Mock-up of selected laboratory casework materials and furnishings prior to rapid installation schedule.
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Airflow design according to ventilation guidelines
Example 1:
Incorrectly Modified Canopy Hood
Example 2:
Air Supply grille too near biosafety cabinet
34
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Strategies for Flexibility Overhead Utility Carriers and Mobile Tables
Metal casework & epoxy resin benchtopsLaboratory mock-ups are required
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Building Utilities – More Power and Data
Shell Laboratories 20 watts/ sq. meter? Reliable power?
35
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Construction cost savings strategies
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Special Building Features
Consider sustainable design goals
• Office space can benefit from natural ventilation; cool air travels in through operable windows and out through the garden space.
• Light shelves reflect light from western exposure.
• PV panels can collect prominent solar radiation, and store it’s energy for later use during blackouts.
Rainwater collection for irrigation and toilet flushing.
36
National Institutes of Health – UP ManilaDesign and Construction Pre-Bid Meeting 1
7 November 2013
Questions?
Site Visit Schedule: To be arranged with Secretariat
SBAC NIH Secretariat Assistance for Eligibility Documents: Nov 27
Deadline for Bidder’s Questions: Nov 18
Last Bid Bulletin: Nov 21
Bid Submission Deadline: Nov 28
Oral Presentations: Nov 29