Upload
ledang
View
215
Download
0
Embed Size (px)
Citation preview
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 1
Table of Contents
PRE-FEASIBILITY REPORT ____________________________________________________________________ 3
1. Executive Summary _____________________________________________________________________ 3
2. Introduction of The Project/ Background Information _________________________________________ 4
2.1 Identification of Project Proponent ____________________________________________________ 4
2.2 Brief DescriptionOf Nature Of The Project _______________________________________________ 5
2.3 Need For The Project And Its Importance To The Country And/or Region ______________________ 5
2.4 Demand-Supply Gap ________________________________________________________________ 6
2.5 Imports vs. Indigenous production _____________________________________________________ 6
2.6 Export Possibility ___________________________________________________________________ 6
2.7 Domestic/ Export Markets ___________________________________________________________ 6
2.8 Employment Generation _____________________________________________________________ 6
3. Project Description _____________________________________________________________________ 7
3.1 Type Of Project Including Interlinked And Interdependent Projects, If Any _____________________ 7
3.2 Location (Map showing general location, specific Location, and project Boundary & Project Site
Layout) with Coordinates ___________________________________________________________________ 7
3.3 Details Of Alternate Sites considered and the basis of selecting the proposed site, particularly the
environmental considerations gone into should be highlighted ____________________________________ 9
3.4 Size or Magnitude of Operation _______________________________________________________ 9
3.5 Project Description With Process Details (a schematic diagram/ flow chart showing the project
layout, components of the project etc.) ______________________________________________________ 10
3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area Of Final
Product/S, Mode Of Transport Of Raw Material And Finished Product ______________________________ 11
3.7 Resource Optimization/Recycling And Reuse ___________________________________________ 11
3.8 Availability Of Water Its Source, Energy / Power Requirement & Source _____________________ 11
3.9 Quantity Of Wastes To Be Generated (Liquid And Solid) And Scheme For Their Management/
Disposal ________________________________________________________________________________ 12
3.10 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH GIVE INFORMATION OF EIA
PURPOSE _______________________________________________________________________________ 13
4. Site Analysis __________________________________________________________________________ 13
4.1 Connectivity ______________________________________________________________________ 13
4.2 Landform, Landuse And Land Ownership_______________________________________________ 14
4.3 Topography ______________________________________________________________________ 14
4.4 Existing Land Use Pattern ___________________________________________________________ 14
4.5 Existing Infrastructure ______________________________________________________________ 15
4.6 Soil Classification __________________________________________________________________ 15
4.7 Climatic Data From Secondary Sources ________________________________________________ 15
4.8 Social Infrastructure _______________________________________________________________ 16
5. Planning Brief _________________________________________________________________________ 16
5.1 Planning Concept__________________________________________________________________ 16
5.2 Assessment Of Infrastructure Demand (Physical & Social) _________________________________ 16
5.3 Amenities/Facilities ________________________________________________________________ 16
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 2
6. Proposed Infrastructure ________________________________________________________________ 17
6.1 Industrial Area (Processing Area) _____________________________________________________ 17
6.2 Residential Area (Non Processing Area) ________________________________________________ 17
6.3 Green Belt _______________________________________________________________________ 17
6.4 Social Infrastructure _______________________________________________________________ 17
6.5 Connectivity ______________________________________________________________________ 18
6.6 Drinking Water Management ________________________________________________________ 18
6.7 Sewerage System _________________________________________________________________ 18
6.8 Industrial Waste Management _______________________________________________________ 18
6.9 Solid Waste Management ___________________________________________________________ 18
6.10 Power Requirement & Supply/ Source _________________________________________________ 18
7. Rehabilitation And Resettlement (R&R) Plan _______________________________________________ 18
8. Project Schedule & Cost Estimates ________________________________________________________ 19
8.1 Likely Date Of Start Of Construction And Likely Date Of Completion _________________________ 19
8.2 Estimated Project Cost Along With Analysis In Terms Of Economic Viability Of The Project ______ 19
9. Analysis Of Proposal (Final Recommendations) _____________________________________________ 19
9.1 Financial And Social Benefits With Special Emphasis On The Benefit To The Local People Including
Tribal Population, If Any, In The Area ________________________________________________________ 19
List of Tables
Table 1 : Manpower requirement ........................................................................................................ 7
Table 2: Geological Reserve in Metric Tones ...................................................................................... 9
Table 3: Water Requirement with Source of Supply ......................................................................... 11
Table 4: Environmental Sensitivity of Project Site ........................................................................... 15
List of Figures
Figure 1:- General Location of Mine Site ............................................................................................. 8
Figure 2: Corner Coordinates Map ....................................................................................................... 8
Figure 3: Schematic Flowchart of Minor Mineral Mining Process ................................................... 10
List of Annexure
Annexure-1 : Letter of Intent Annexure-2 : Toposheet Map Annexure-3 : Joint Inspection Report Annexure-4 : Application for NBWL Clearance Annexure-5 : Application for Forest Clearance
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 3
PRE-FEASIBILITY REPORT
1. EXECUTIVE SUMMARY
Uttarakhand Forest Development Corporation (UKFDC) has proposed project for Extraction of
Sand, Boulder and Bajri (minor minerals) in an area of 40.00 ha. The project site is located at
river bed of Yamuna Nadi Baya Kinara, Dhaula Compart No.1 in Timli Forest Range of Kalsi
Forest Division near village-Timli, Tehsil-Vikasnagar, District-Dehradun in the state of
Uttarakhand. Letter of intent for the proposed project was issued to M/s UKFDC dated 26th May
2015 vide letter no. 425/Khanan/Ashyapatr/Va.Vi.Ni./Bhu-Khani-E/2014-15. (Refer
Annexure-I)
Mine lease lies in reserved forest, hence Forest clearance under section-2 of “Forest
Conservation Act, 1980” has to be obtained from MOEF&CC for which application has already
been submitted (Refer Annexure-V).
Project is categorized as Category-A project due to presence of Kalesar National park & Wildlife
Sanctuary and interstate boundary of Haryana, Uttar Pradesh and Himachal Pradesh within 5km
radius of project site periphery.
Salient Features of the project are given below:
Latitude 30°24'56.29"N to 30°23'58.43"N
Longitude 77°34'46.54"E to 77°34'41.80"E
Topo sheet number 53 F/11
Land use River bed
Minerals of mine Sand/Bajri/Boulder
Life of mine Continuous, being replenished yearly
Proposed annual production of mine 3,60,000 tonnes
Method of mining Opencast Manual
No of working days in a year 270
Water demand 10 KLD
Sources of water Tanker water supply
Man power 400
Nearest railway station Dehradun (45km, SE)
Nearest state highway/national highway NH-72 (3.30km, NE)
Nearest airport Jolly Grant (62 km, SE)
Seismic zone Zone-IV (As per 1893:2002)
Project Cost 1,12,62,720 Crore
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 4
2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
The proposed mining lease, measuring 40.00 hectare (ha) is a forest land that falls in Timli
Forest Range, Kalsi Forest Division near village- Timli, Tehsil-Vikasnagar, District-Dehradun,
Uttarakhand. As per EIA notification, 2006 and its subsequent amendments later, the project
activity has been categorized as Category- ‘A’ due to presence of interstate boundary of
Himachal Pradesh, Haryana &Uttar Pradesh and presence of Kalesar National Park within the
radius of 5Km radius. Proposed capacity of mine for production of sand, bajri & boulder will
be3,60,000TPA.
A large amount of minor minerals (sand, bajri, boulder) has been deposited in the bed of river
Therefore, in order to avoid widening of river, channelize the river course, prevention of floods
and land cutting from nearby agricultural fields & forests; this project has been proposed to
collect minor minerals from an area of 40 ha.
2.1 IDENTIFICATION OF PROJECT PROPONENT
Uttarakhand Forest Development Corporation (UKFDC) is a statutory body constituted by the
State Government of Uttarakhand. The Corporation was formed for the better preservation,
supervision and development of forest also for better exploitation of forest produce within the
State and for matters connected there with.
The Corporation has been progressing forward not only in its financial aspect but also has taken
a big leap in the direction of diversification of its activities.
The Corporation has added the collection and disposal of minor minerals from the rivers
situated inside reserved forest areas, collection and marketing of medicinal plants and Eco
tourism in its works apart from the removal of dead, dying and uprooted trees as allotted by the
Forest department.
Collection and marketing of sand, boulder and Bajri from the river beds of reserved forest areas
has been undertaken in order to protect the forest lands, agricultural crops, inhabitations from
the havoc of floods. The collection and marketing system is being converted from volume base
to weight basis for the disposal of minor minerals, in the Gaula, Sharda, Nandhaur, Kosi, Dabka,
Ganga, Yamuna, Song and Gunna rivers of the State. The implementation of advanced
computerized technique of minor mineral weighing system is a step towards advancement and
use of new technology.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 5
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
The project has been proposed for an annual production of 3,60,000 tonnes of
Sand/Bajri/Boulder by open cast manual extraction method in river bed. The lease area is
totally under the forest land. The total lease area of40 ha is mineable as per approved Site
inspection committee report comprising of officer from UKFDC, sub divisional Forest officer
Kalsi, Divisional Forest development manager, Dehradun, Tehsildar & SDM Tehsil Vikasnagar
District Dehradun on dated 10.06.2013.
There is practically no soil cover on top profile of river bed section proposed for mining,
however, if some soil is available it will be removed and carefully stored for use in plantation
purpose.
Hardly any vegetation is present in the river bed. But the vegetation is present at both the river
banks with a Vegetation Density of 0 to 10 with predominantly species of trees like Khair,
Shisham, Arjun, Kanju, Haldu, jamun, Eucalyptus etc.
No solid waste other than negligible quantity of silt/silty clay, which gets deposited as crust
material on the bed profile, shall be scrapped and carefully utilized for plantation purpose.
During monsoon season, when the river reaches high stage, Yamuna Nadi Baya Kinara has
significant catchment area and it transports bed load material and sediments which gets
aggraded at such stretch which has wider river width and has concave banks. The mined out
area gets replenished annually after monsoon, thus it does not require any backfilling. The
rehabilitation/reclamation of such lease area which has been secluded for mining being close to
the bank in the form of upper terraces will be done by way of tree plantation along lease
boundary. Green barriers will be created by plantation as per CPCB Guidelines.
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND/OR REGION
Due to heavy rainfall annually and flooding of the river in the past years, a large amount of
minor minerals (sand, bajri, boulder) has been deposited in the bed of river Yamuna, which has
widened the course of river and in-turn is responsible for cutting of nearby agricultural and
forest land causing heavy degradation in the form of soil erosion and loss of vegetation along
the river course. Keeping in view the environmental consideration for the river it is essential to
remove sand, Bajri, Boulder from the river bed.
Therefore, in order to avoid widening of river, channelize the river course, prevention of floods
and land cutting from nearby agricultural fields & forests; this project has been proposed to
collect minor minerals from an area of 40 ha.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 6
It will not only benefit in meeting the huge demand of construction material and also provide
direct employment to about 400 persons including skilled, semi-skilled & unskilled laborers.
Additional jobs are created by way of transportation.
2.4 DEMAND-SUPPLY GAP
Due to ban on illegal mining and with increase in infrastructure industries, demand of sand,
bajri & boulder (construction material) has increased by almost 50%, hence the excavation of
river bed material will not only help in saving the river from diversion and wideningof its
course but will also cater increased demand of river bed material in construction activities like
building, infrastructure facilities, construction and expansion of existing road and highways etc.
2.5 IMPORTS VS. INDIGENOUS PRODUCTION
Import does not apply in the present case as minor minerals (Sand, Bajri, and Boulder) are
indigenously available at number of mines under operation in Uttarakhand.
2.6 EXPORT POSSIBILITY
Export possibility is neither plausible nor there is any such demand of Sand, Boulder and Bajri.
2.7 DOMESTIC/ EXPORT MARKETS
The proposed mining activity is for obtaining sand/bajri/boulder for indigenous consumption
and also for sale to nearby cities and towns located in the state of uttarakhand as well as uttar-
pradesh.
2.8 EMPLOYMENT GENERATION
About 400 workers including skilled, semi-skilled & unskilled labors shall be engaged through
project proponent for extraction of and loading and handling of mineral in mining area, besides,
watch and ward and plantation activity with proper maintenance.
Breakup of manpower is given as follows:
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 7
Table 1 : Manpower requirement
S. No. Type of Manpower Number
1 Skilled 5
2 Semi-skilled 40
3 Unskilled Labourers 355
Total 400
3. PROJECT DESCRIPTION
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY
The project has been proposed for an annual production of 3,60,000TPA of sand, boulder & bajri
by open cast manual extraction method in river bed. The lease area (40.00ha) is a forest land.
The project has no other interlinked project. Sand, bajri boulder from the site will be
transported to different vendors and crusher units for further activities.
3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT
BOUNDARY & PROJECT SITE LAYOUT) WITH COORDINATES
The minor mineral mining lease, measuring 40.00 ha is a forest land and falls in Timli Forest
Range of Kalsi Forest Division, Dehradun. Mine site is located near village- Timli, Tehsil-
Vikasnagar, District-Dehradun Uttarakhand. Geographical location of mine stretch is given
below:
Latitude 30°24'56.29"N to 30°23'58.43"N
Longitude 77°34'46.54"E to 77°34'41.80"E
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 8
Figure 1: General Location of Mine Site
Project boundary with site layout and geographical corner coordinates along the mine site is
shown in satellite image.
Figure 2: Corner Coordinates Map
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 9
3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED
SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE
HIGHLIGHTED
The proposed site shall be mined for the purpose of preventing land cutting during heavy
rainfall and floods and also to channelize the river course to the middle. The area has been
examined and approved for proposed mining project by Joint Inspection Committee.
3.4 SIZE OR MAGNITUDE OF OPERATION
Total available area of the river is 40.00 ha, which falls under Kalsi Forest Division, Uttarakhand.
The collection of minor minerals will be carried out from the 50% of the total area i.e.
approximately 20 ha, after leaving 25% area on either side of the river bank for better
channelization of the water during monsoon. Hence, total capacity of mine is estimated as
3,60,000 tonnes per annum.
Mineral Reserves during the Lease Period
The total reserve is divided into three categories
1. Proved: Reserves available up to the depth of 9 meters below the ground level are
proved reserves.
2. Probable: Reserves available up to the depth of 6 meters below the proved reserve
level are probable reserves.
3. Possible: Reserves available up to the depth of 3 meters below the probable reserve
level are possible reserves.
Geological reserves available in study zone of 18m depth below ground level are given below in
Table-2.
Table 2: Geological Reserve in Metric Tones
Geological Reserve in Metric Tones
Proved 4242390.98
Probable 2828260.87
Possible 1414130.11
TOTAL 8484781.96
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 10
Production Parameters
Leaving 25% area on both the banks of the river from the lease boundary would not use for
exploration of mineral. Yearly production of mine is estimated 3,60,000tonnes per year.The
mine will be worked in the day shift only. The average number of working days in the year
would be 270. The proposed annual target production has been worked out on the basis of
mineable area with maximum mining depth of 1.5m. On the basis of the nature of RBM (River
Borne Material) in the boulder reach of the river, the matrix comprises of the bed load, mainly
comprising of boulder, pebble, cobble, bajri and sand.
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/ FLOW CHART
SHOWING THE PROJECT LAYOUT, COMPONENTS OF THE PROJECT ETC.)
As per Environmental Impact Assessment guidance manual for - Mining of Minerals released by
MoEF - the project is a surface mining. Typical operations involved in a surface mining is shown
in the figure given below:
Figure 3: Schematic Flowchart of Minor Mineral Mining Process
Method of Mining
The project will be accomplished by fully manual opencast method of mining that does
not involve any processes such as overburden removal, drilling, blasting and
beneficiation.
The extraction of river bed material from the bed of the river will be made by leaving
25% width on either side of river
Site Preparation
Extraction of minor mineral (by manual opencast method)
Loading of mineral
Transportation of mineral to the destined places
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 11
The mining process of opencast manual method involves collection of material by simple
hand tool such as shovel, pans and sieves.
This is followed by sorting and manual picking, stacking and loading into trucks/
tractor–trolley for transporting.
The pits from where the material will be picked would not be deeper than 1.5 meter and
shall follow the normal channel direction of the river. These get replenished during
monsoon.
The only waste is silt/clay which is stored and used for plantation.
The material will be transported through tipper (9.0-10.2 MT Capacity), Tractor trolley
small (3MT capacity) and Tractor trolley big (6 MT capacity) to the destined
users/places outside mining lease.
Blasting
No blasting is proposed to be done.
3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE,
MARKETING AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND
FINISHED PRODUCT
No raw material is required for extraction of minerals.
3.7 RESOURCE OPTIMIZATION/RECYCLING AND REUSE
Not applicable in the present case as all size of minerals will be extracted and transported to
various crusher units outside the mine lease area for sorting & grading proposes.
3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT & SOURCE
Water Requirement
Water requirement for human consumption, plantation and dust suppression is 10KLD, which
shall be met from tanker supply. Breakup of water requirements is as given below:
Table 3: Water Requirement with Source of Supply
S. No. Description of requirement Water requirement (KLD) Source
1. Domestic 3.00 Tanker water
supply 2. Dust Suppression 2.00
3. Green Belt Development 5.00
TOTAL REQUIREMENT 10.00
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 12
Power
No electrical power shall be required for operations as the mining will be worked out during
day time only. Minimal power required for office shall be taken from general electric supply of
area.
3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR
MANAGEMENT/ DISPOSAL
Solid Waste Generation & its Disposal
No solid waste other than negligible quantity of silt/silty clay, which gets deposited as crust
material on the bed profile. The same will be scrapped and utilized in the upper terraces
earmarked for plantation.
Liquid Effluent
There will be no waste water generation from mining activities.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 13
3.10 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING
WHICH GIVE INFORMATION OF EIA PURPOSE
Figure2: Schematic flowchart of EIA process
4. SITE ANALYSIS
4.1 CONNECTIVITY
The mining site is well connected through rail & road network.
Mine site at Yamuna Nadi Baya Kinara River Timli Range is approachable by NH-
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 14
72 at a distance of 3.30 km.
Dehradun railway station is located at a distance of 45km.
The nearest airport is Jolly Grant around 62 km away from the mining area.
4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP
Landform
The mine lease area is in river bed of Yamuna Nadi Baya Kinara River, Timli Forest Range of
Kalsi Forest Division, Dehradun.
Land-Use
The land use of the mine lease area is classified as river body in forest land.
Land Ownership
The designated mine area is forest land and belongs to Timli Forest range of Kalsi Forest
Division and has been allotted to UKFDC for the purpose of mining.
4.3 TOPOGRAPHY
The mine lease area lies in the river bed and is a part of foothills of Siwalik range region of
Uttarakhand. Highest and lowest elevation in the ML area is 367.5 m AMSL and 363 m AMSL
creating a level difference of4.5 m.
The terrain around Dehradun is full of minor ridges and valleys. A prominent ridge runs north-
south. Western part is washed by the river tons, Noon Nadi and Asan, tributaries of Yamuna,
flowing towards southeast and eastern segment are drained by the WNW- ESE flowing river
Suswa, a tributary of Ganga.
Topography will not change during running of mine and on its abandonment at the end of the
proposed mining, due to digging of shallow pits and consequent annual deposition during high
floods.
4.4 EXISTING LAND USE PATTERN
The existing land use pattern of mine lease area belongs to landuse category “River body” in
reserved forest area and shall continue to be so even after the current mining project is over.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 15
Environmental Sensitivity
Table 4: Environmental Sensitivity of Project Site
S.No. Sensitive Ecological Features Name Aerial Distance (in
km.) from Mine
Lease boundary
1. Habitat for migratory birds Asan Conservation
Reserve
7.78 km SE
2. Stream/Rivers Mine is located in the
bed of Yamuna Nadi
Baya Kinara
-
3. Mountains/Hills Project lies in the
foothills of Siwalik
range
-
4. Airports Jolly Grant 62 km SE
5. Railway Lines Dehradun 45km SE
6. National / State Highways NH-72 3.30 km NE
7. Important worship place GurudwaraShriPaonta Sahib
5 km NE
8. National Park Kalesar National Park 1.5 km SW
4.5 EXISTING INFRASTRUCTURE
There is no existing infrastructure, however during mining temporary rest shelters for
workers will be provided.
4.6 SOIL CLASSIFICATION
The inherent fertility of the soil is good as indicated by the sand and clay mineralogy of the
soil and the biotite and feldspar together with the mica is an important source of nutrients
for the vegetation in the soils of the Doon valley.
4.7 CLIMATIC DATA FROM SECONDARY SOURCES
The district has within its limits lofty peaks of the Outer Himalayas as well as the Dun Valley
with climatic conditions nearly similar to those in the plains.
Climate: The climate of the district, in general, is temperate. The temperature depends
on the elevation. In Doon Valley, the heat is often intense. The temperature drops below
freezing point during the winters. The summer starts by March and lasts up to mid of
June when the monsoon sets in. Generally, the month of May and early part of June is
hottest. Winter starts from November and continue upto February.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 16
Temperature: The temperature depends on the elevation. Mean temperature shoots
upto 36.20c at Dehradun during summers and the maximum temperature rises to over
420C. The mean daily maximum temperature during winter is 19.1
0C and the mean daily
minimum temperature in January is 6.10C. In association with the cold waves arising in
the wake of the western disturbance which travels East wards, the minimum
temperature goes down to about 1.8° and at times leads to frosts.
Rainfall: The climate of the district, in general, is temperate. The temperature depends
on the elevation. Doon Valley is characterized by humid climate with moderate
temperature. Rainfall and luxuriant vegetation. The average annual rainfall in the area is
2073.32 mm. Maximum rainfall seems during July and August.
4.8 SOCIAL INFRASTRUCTURE
The social infrastructure like educational facilities (primary and higher secondary schools,
Degree College), drinking water supply, post & telegraph, public transportation and hospitals by
and large are available in the study area.
5. PLANNING BRIEF
5.1 PLANNING CONCEPT
Opencast manual mining method will be adopted for Sand/Bajri/Boulder mining. Project will
annually produce Sand/Bajri/Boulder @360,000tonnes, which will be used for meeting the
huge demand of construction material like coarse and fine aggregate required in building
construction and infrastructure works, road material for construction and maintenance of
roads/highway; elastic ballast material for rail tracks in the state of Uttarakhand and nearby
cities and towns of Uttar Pradesh.
5.2 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL)
Adequate infrastructure facilities are available in the vicinity of mine lease area; no extra
infrastructure over and above the existing infrastructure is required.
5.3 AMENITIES/FACILITIES
Proper site services such as First Aid, Rest Shelter and Drinking Water will be provided to mine
workers.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 17
Mines Office, Workshop etc.: Provision of mine office, workshop along with
weighbridge facility is proposed during mining operation.
Rest Shelter: Rest shelter along with first-aid station complying with all the provisions
of Mines Rules shall be provided by project proponent.
Water Supply: A total of 10 KLD Water will be required for the purpose of human
consumption, dust suppression and plantation. Water shall be supplied by tanker supply
from authorized vendor.
Power Supply: The mine will work in day time only.So, no lighting arrangement will be
required. Hence, this project does not need any power supply.
Transport of Men and Material: By and large only local personnel shall be deployed
for mining. Either by foot or with the help of bicycle, they will reach the site. During
operation phase, trucks/tractors shall be used for the transportation of river bed
material (mention type of rbm) from the site to destined locations.
Communication: Mobile phones & walky talky shall be used for communication.
Security Arrangements: Appropriate security arrangement shall be made.
6. PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (PROCESSING AREA)
Temporary arrangements like site office, rest shelters & approach roads etc. shall be provided.
No permanent infrastructure is proposed.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA)
As local person shall be employed, no residential building/housing are proposed.
6.3 GREEN BELT
The proposed mine site is a part of river bed lying in the forest land. The area of 80 Ha is
proposed for compensatory afforestation in which approximately 3,20,000 no. of saplings are
proposed for plantation.
6.4 SOCIAL INFRASTRUCTURE
In-line with the Social Responsibility Activities at other operational sites, relevant
developmental assistance shall be rendered depending on the local needs identified through
studies.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 18
6.5 CONNECTIVITY
Site is well connected to existing road and rail network. There is no proposal to develop new
road and rail links.
6.6 DRINKING WATER MANAGEMENT
Water requirement for drinking and other operations will be 10.0 KLD, which will be met from
tanker supply.
6.7 SEWERAGE SYSTEM
Domestic sewage shall be disposed off into septic tank followed by soak pits.
6.8 INDUSTRIAL WASTE MANAGEMENT
Not applicable.
6.9 SOLID WASTE MANAGEMENT
Separate bins shall be provided for solid waste generated by daily human activities i.e.
wrappers, aluminum foils, leftover food materials etc.
6.10 POWER REQUIREMENT & SUPPLY/ SOURCE
The mining shall be carried out manually with the help of hand implements during day time
hence, power requirement is not needed.
7. REHABILITATION AND RESETTLEMENT (R&R) PLAN
As per the primary site survey & latest census data available, the mine lease area is designated
as river bed in reserve forest has no habitation & therefore displacement of population is not
applicable therefore no Rehabilitation & Resettlement is envisaged. However a detailed analysis
on socio-economic aspects of the study area is proposed to be carried out during EIA study of
the proposed mine.
SAND/BOULDER/BAJRI MINING PROJECT OF YAMUNA NADI BAYA KINARA RIVER DHAULA COMPART NO.1, TIMLI FOREST RANGE (AREA 40.00 HA)
PRE-FEASIBILITY REPORT PAGE 19
8. PROJECT SCHEDULE & COST ESTIMATES
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION
No construction activity is involved under the project activity. The mining operations shall
commence after getting all the regulatory compliance including environmental clearance as
applicable.
8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF
THE PROJECT
The project cost of proposed project is Rs. 1,12,62,720 (Capital cost of Rs. 1,06,62,720 Crore and
recurring cost of Rs. 6 Lakh). Project is economically viable.
9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT TO THE
LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE AREA
The proposed project is found to have both financial and social benefits as listed below:
The project will provide direct & indirect employment to local people in different
activities such as mining, sizing (sieving) transportation and plantation activities.
This project will provide protection to the nearby habitation from submergence
which is caused due to flood in monsoon season.
The revenue generated from the production and sale of mineral, will also add to
the exchequer of government, which in turn will help in the growth of state
economy.
As the proposed mine area lies in the river bed, hence the removal of extracted
material will minimize the chances of flood disaster in the area.
With the emergence of fast growing construction industry of Uttarakhand and
other nearby states, excavated material will also cater the huge increasing
demand of mineral to be used as raw material for construction.
The project is not expected to have any major adverse impact on the environment and whatever
impacts are anticipated during the EIA study will be minimized with the help of suitable
mitigation measures. Hence it is concluded that the project is economically feasible and
financially beneficial to the local people as well as to the country.
************