Upload
manisha-sharma
View
217
Download
0
Embed Size (px)
Citation preview
7/31/2019 Ppp Cases Pvr May07
1/51
Financing InfrastructureProjects
An Analysis of Issues and
Cases
7/31/2019 Ppp Cases Pvr May07
2/51
2
Presentation Structure
Project Finance Transactions
Issues in Infrastructure Finance
Case Studies
7/31/2019 Ppp Cases Pvr May07
3/51
IDFC : A Summary
7/31/2019 Ppp Cases Pvr May07
4/51
4
Who We Are
Established by the GoI in 1997
Lead private capital to commercially viable infrastructure
projects; promote public-private partnerships
Bring innovation to private financing in Indian
infrastructure
Provide policy advice to encourage private financing in
infrastructure
We are a specialty financial institution focused only on infrastructure funding
With a balance sheet size in excess of Rs. 17,000 Crore, and NIL NPAs, IDFC ranks amongst thelargest financial institutions focused on financing Indian infrastructure
7/31/2019 Ppp Cases Pvr May07
5/51
Project Finance Transactions
7/31/2019 Ppp Cases Pvr May07
6/51
6
Financing a Project
Project Finance doesnt meanfinancing a project!
7/31/2019 Ppp Cases Pvr May07
7/517
Financing a Project 2
How does Joe Blo Inc. finance a chemical factory?
Joe Blo Inc.
Lenders
ChemFac
Equity
Equity
Returns
Debt
Debt
Repayment
7/31/2019 Ppp Cases Pvr May07
8/518
Financing a Project 3
Such financing is also called:
Balance Sheet Financing, orRecourse Financing
Here the project Lenders have a low levelof due-diligence on the project itself, but a
high level of due diligence on Joe Blo Inc.!
7/31/2019 Ppp Cases Pvr May07
9/519
Project Finance
How does Joe Blo Inc. finance an airport?
Joe Blo Inc.
Lenders
Airport
Equity
EquityReturns
Debt
Debt
Repayment
Other Equity
Investors
Other Lenders/Bondholders
7/31/2019 Ppp Cases Pvr May07
10/5110
Project Finance Defined
Raising of funds to finance aneconomically separable
capital investment project inwhich the providers of funds
look primarily to cash flow
from the project to servicetheir debt and providereturns on their equity
7/31/2019 Ppp Cases Pvr May07
11/5111
Emergence of ProjectFinancing:
Appropriate techniques for projects with high
capital requirements and a complex risk profile
Payouts are based only on the projects own assets
and cash flows stream
Creditors rely on the ability of the project for
repayment of related debt obligations, non-
recourse debtMulti-source financing: syndicated commercial
banks, bonds, ECAs, multilaterals
7/31/2019 Ppp Cases Pvr May07
12/51
12
Why Project Finance?
Isolate Risk
Project Transparency
Greater Leverage
Control/ Ownership issues
7/31/2019 Ppp Cases Pvr May07
13/51
13
Characteristics of Project Finance
Complex contractual arrangements
Limited or non-recourse financing
Risk management strategies and techniques
Changing perceptions, new innovations
7/31/2019 Ppp Cases Pvr May07
14/51
14
Demand Supply Gap
Annual investment needs in UrbanInfrastructure alone are about Rs.
400 billion*as against an availabilityofRs. 50 billion, (excluding new mass
transit and township development
projects)
*give or take a few hundred billion!
7/31/2019 Ppp Cases Pvr May07
15/51
15
Equity
Sponsor/ Corporate
Equity Funds
Financial Institutions
Multi-lateral InstitutionsWorld Bank, IFC
Public
7/31/2019 Ppp Cases Pvr May07
16/51
16
Debt
Banks
FIs
Debt Funds
Multilateral Institutions
World Bank, ADB, IADBExport Credit Agencies (ECA)
Public
7/31/2019 Ppp Cases Pvr May07
17/51
17
Principles of Risk Management
Allocate project-specific risks to parties best
able to bear them
Control performance risks through incentivecontracts
Use market-hedging instruments (derivatives)
for covering market-wide risks (interest andexchange rate fluctuations)
7/31/2019 Ppp Cases Pvr May07
18/51
18
Risk Management
7/31/2019 Ppp Cases Pvr May07
19/51
19
Risk Management
Base
Value2
2
0
5.184802
13.600926
0.15
Goods Traffic Growth Scenario
Tariff Growth Scenario
Project Cost Sensitivity Factor
Variable Operating Expenses as per KRC norms (per MT)
Fixed Operating Expenses as per KRC norms
Percentage of Traffic Startup
Min DSCR, with DSRA
0.0 0.3 0.6 0.9 1.2 1.5 1.8 2.1 2.4 2.7 3.0
Base Value: 1.1
1 3
1 3
0.1 0.1
4.89606 4.89606
13.600926 12.981576
0 0.3
7/31/2019 Ppp Cases Pvr May07
20/51
20
7/31/2019 Ppp Cases Pvr May07
21/51
21
Oh What A Web!Concession Agreement
Government & Project SPV
SHA
Equity Investors
Equity Investment Agreements
With Pvt Equity Investors
Construction/O&M Contracts
Project SPV & Contractors/ Operators
DLA/ Substitution
Project SPV, Promoters,
Lenders, Government
State Support Agreement
Government & Project SPV
Loan Agreements
Lenders & Project SPV
Inter-Creditor Agreements
Inter-se the LendersPledges & Hypothecations
Lenders & Promoters Site Lease AgreementProject SPV & Land Owner
TRA Agreement
Trustee Bank, SPV, Lenders
Bank Guarantees etc
7/31/2019 Ppp Cases Pvr May07
22/51
Issues in InfrastructureFinance
7/31/2019 Ppp Cases Pvr May07
23/51
23
Service Provision Options
Infrastructure
Services
Status Quo:
Govt creates assets
& provides services
Privatization:
Private Sector
creates assets &
provides services
Commercialization:
Govt creates assets
& hands over to
Pvt Sector to
provide services
PPP/ PFPI
7/31/2019 Ppp Cases Pvr May07
24/51
24
How Much Time Did They Take?
Airports:Started in 1998-99
Bidder identified in 2001
SHA in 2002
Concession/ FC in 2005
7/31/2019 Ppp Cases Pvr May07
25/51
25
How Much Time(2)
(Industrial) Water Supply:Started in 1995-96
Bidder identified in 1997
Concession in 2003
FC in 2004
7/31/2019 Ppp Cases Pvr May07
26/51
26
How Much Time(3)
Commercial Complex:Started in May 2002
Bidder identified in June 2004Government approval June 2005
Concession/ FC just now
SEZ:Started in 2002
Bidder identified in 2003
Approvals not yet in place
7/31/2019 Ppp Cases Pvr May07
27/51
27
How Much Time(4)
Industrial RoadsStarted in 2002
Bidder identified in 2005
Concession/ FC just now
7/31/2019 Ppp Cases Pvr May07
28/51
28
How Much Time(5)
How many large (> Rs. 500 Cr) projectshave reached financial closure, and work
commencedLast 8-10 years of PPP4 Airports1 Water supply projectNumber of Road (NHAI/ MORTH only)
Number of Telecom/ Power ProjectsAnd how many are completed
In round figures noneExcept in Roads, Telecom, Power
7/31/2019 Ppp Cases Pvr May07
29/51
29
Why are the projects delayed?
Possible Reasons?Finance
Inadequate Project DevelopmentHasten to bid?
Approval structures/ processes not being inplace
Plug-and-play approach?Social/ Environmental reasons
LAND
7/31/2019 Ppp Cases Pvr May07
30/51
30
Then why PPP?
PPP ProjectsTake more time, more effort, and are also prima-facie
more cost BUTShortage of budgetary funds
Improvement in levels of service to users
Innovation in designs, project management and
implementation of projectsLong-term operations and maintenance of assets
Focus on service to users not just asset creation
7/31/2019 Ppp Cases Pvr May07
31/51
31
Are Funds an Issue?
Yes and No
YES
Project Development FundsEquity
Debt in Urban Infra (water, city roads, metrotransport projects, sanitation, solid waste)
NOCommercial debt (sectors other than mentionedabove)
7/31/2019 Ppp Cases Pvr May07
32/51
32
Inadequate Project Development
Hasten to set up project/ bid
Bidders/ lenders then start askingfor data/ studies
Thin slice method to get all the DPRsdone
Re(negotiation) of project andcontract parameters along the way
7/31/2019 Ppp Cases Pvr May07
33/51
7/31/2019 Ppp Cases Pvr May07
34/51
34
Approval Process/ Structures (2)
Since there are no replicable frameworksEach project is a stand-alone experiment
Rarely is precedent used. Bangalore and Hyderabadairports are rare instances of projects usingprecedent
Infra Acts/ Polices have enough flexibility toEnable frequent by-pass of their intent!
Transparency conditions are applied regardlessof whether they are regular Contracts orBOT Projects
7/31/2019 Ppp Cases Pvr May07
35/51
35
Key Lessons - Roads
Bypasses on national highways and river bridges havedemonstrated reasonable success Common sense approach to traffic forecasting along
with statistical analysis
Emphasis on getting base year traffic right Small state highway projects have also done well in
states such as Maharashtra, MP
Developed by local promoter groups with a strong ears to the groundphilosophy
Certain large projects such have not been able togenerate the expected numbers in the early years
High project cost, competing routes, service roads, higher growthrate expectations being the primary reasons
7/31/2019 Ppp Cases Pvr May07
36/51
36
Key Lessons - Telecom
Limited mobility not sustainable leading tomigration to full mobility. Mass-market model for the sector (based on
high penetration and low ARPUs).
Consolidation in the sector.
7/31/2019 Ppp Cases Pvr May07
37/51
37
Key Lessons - Power It is essential to first fix the leakybucket
Competitiveness of tariff essential to ensure viability of ageneration project.
Retail tariffs to ultimately mirror the cost of supply.
Factors to attract private sector participation in the sector:
Regulatory confidence longer term regulatory tariff regime (NoMoving Goal Post)
Legal and Administration support freedom and support fromGovernment to disconnect consumers
Government credit risk mitigation appropriate mechanism for deliveryof subsidy to be developed
Credible business plan to meet transition period funding requirementspast unfunded liabilities to be taken over by Government
Credible base line data
7/31/2019 Ppp Cases Pvr May07
38/51
7/31/2019 Ppp Cases Pvr May07
39/51
39
Way Forward?
Not to rush into a Project bid/ implementapproach
Get frameworks/ approvals/ funds in placebefore doing soCapacity building and reform should go aheadNow there is enough project experience/expertise to set up a precedent basis
Adequate project preparationFunding required to do soNot too many money bags waiting to investinto infrastructure
7/31/2019 Ppp Cases Pvr May07
40/51
40
Small
Number Of
ProfitableProjects
BOT
Larger
Number Of
MarginallyProfitable
Projects
Govt. Leveraged
Privatisation
Unprofitable,
But Imperative
Projects
Budgetary
Allocation
Maintenance
Works
Dedicated
Funds (Road
Fund)
Way Forward (2)
7/31/2019 Ppp Cases Pvr May07
41/51
41
Concept of PFPI
Traditional ApproachAsset creation funded through governmentborrowings
Service provision and maintenance of assets bypublic sector
PFI ApproachAsset creation funded by private finance
Service provision and maintenance of assets byprivate sectorFundamental Tenets
Value for MoneyRisk Transfer to Private Sector
7/31/2019 Ppp Cases Pvr May07
42/51
7/31/2019 Ppp Cases Pvr May07
43/51
43
What PFPI is not .. What it is (2)
This means that Governmentno longer builds roads, it purchases miles of
maintained highwayno longer builds hospitals, it buys healthservices
no longer buys computers and software, but
pays for managed IT services
7/31/2019 Ppp Cases Pvr May07
44/51
Case Studies
Experiences in Project Finance
7/31/2019 Ppp Cases Pvr May07
45/51
7/31/2019 Ppp Cases Pvr May07
46/51
46
A Road Project
66%
17%17%
Debt
Sub-Debt
Equity
7/31/2019 Ppp Cases Pvr May07
47/51
47
Case Study - Waste to Energy
7/31/2019 Ppp Cases Pvr May07
48/51
48
Case Studies - 12
Garbage to GoldEasy for any self-respecting alchemist?!
Technically superior, but also moreexpensive
Can the returns (financial or economic)
justify the higher costs?Obviously cannot be termed as the cost-equivalent of a regular power plant
7/31/2019 Ppp Cases Pvr May07
49/51
49
Case Study - The SWERF Project at LucknowProject to generate about 5 MW of power from MSW
Project to offer a MSW Management solution to the cityAbout 1000 TPD; of this about 750-800 Tons lifted the same day
Projected population of 25 lac in 2001
Present disposal practices are far from being sanitary
Waste composition would be heterogeneous in most respects
Project had its Award process satisfactoryLoI issued on August 1996 thro competitive bidding
Waste Supply Agreement in Feb 1997, PPA signed on July 1998, LandLease agreement in March 1999, GoUP Guarantee in Feb 2000
Project enjoyed the commitment of its Stakeholdersthe LNN, UPPCL, MNES, local community, Pollution Control Board etc.
7/31/2019 Ppp Cases Pvr May07
50/51
50
Case Study - Structuring The ProjectFinancial closure achieved through tie-up of
Equity (Rs 20.00 crs); Senior Debt (Rs 26.50 crs); DeferredCredit (Rs 11.50 crs);Capital Subsidy (Rs 15.00 crs)
Contractual structure completed thro execution ofWaste Supply Agreement by LNN
Power Purchase Agreement with UPPCL
Equipment Supply & Know-how provision agreements with Entec/IUT/ Janbacher
EPC arrangements with Jurong/ Jeevitha/ L&T
O&M arrangements with Haustle
Commercial tightness ensured thro provisions ofContracts - Defect Liability provisions, Financial Gtee backedperformance, & LDs
Offtake agreement - LCs and Government Guarantee
7/31/2019 Ppp Cases Pvr May07
51/51
Thank You