Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
PPP as a tool to use bridging
fiscal gap in countries
4th South Asia Region Public Procurement Conference
“Electronic Government Procurement (e-GP) in South Asia Achievments, Opportunities and Challanges”
20th – 23rd Feburary , 2017Mr Rajneesh Kapoor
Superintending Engineer
Ministry of Road Transport & Highways
Govt of India
Ministry of Road Transport & Highways (MORTH) is
an apex organization under the Central Government is
primarily responsible for development and maintenance
of National Highways.
India has about 5.472 million Kilometer of road network
out of which NHs are only 1,03,933 Km.
National Highway comprises only 2% of total road
network in India but carries about 40% of the road
traffic.
Road Transport is considered to be one of the most cost
effective and preferred mode of transport in India, both
for freight(60%) and passengers(87%).
INTRODUCTION
Road Network in India
The road network in India is second largest in World after
USA.
Details of road in India is as under:
Road Network of India Length (Km)
National Highway (NH) 1,03933
State Highway (SH) 1,61,487
Other Roads (MDR, ODR &
VR)
52,07,044
Total Length 54,72,464
Implementation modes for NH Projects in
India
• National Highways Authority of India (NHAI)
• State Works Dept (PWD)/ State Road Development Corporations
• Border Roads Organization (BRO)
• National Highways Infra Dev Corp Ltd. (NHIDCL)
Implementation agencies for NH projects
•Build Operate Transfer (BOT) Toll (PPP)
•BOT Annuity (PPP)•Hybrid Annuity (PPP)•EPC (Public funded)
Implementation modes for NH projects
NHDP (National Highways Development Project)- 48298 km
SARDP–NE(Special program for North East) -7611 km
LWE (Left Wing & Extremist affected areas) -1770 km
National Highway Interconnectivity Improvement
Programme (NHIIP) under World Bank
Loan Assistance - 1120 km
Total 58799 Km
Development of remaining NHs of length 45134 Km are
taken up under NH(O) scheme through Budgetary support
of Govt of India
Programme for road development in India
NHDP Phase-I: approved in Dec 2000 at the cost of Rs30300 cr.
NHDP Phase-II: approved in 2003 at the cost of Rs 34339cr.
NHDP Phase-III: approved in Dec 2006 at the cost Rs80626 cr
NHDP Phase-IV: approved in Dec 2006 at the cost of Rs41210 cr.
NHDP Phase-V: approved in October 2006 at the cost ofRs 41210 cr.
NHDP Phase-VI: approved in Nov 2006 at the cost Rs16,680 cr
NHDP Phase-VII: approved in Dec 2007 at the cost Rs16,680 cr
Phases of NHDP
Map of NHDP-I (GQ) & II (NS&EW)
7
Status of NHDP
NHDP
Phase
Mode Length
(Km)
Awarded/
under implementation
(Km)
To be
awarded
(Km)
Approved
cost (Rs
in Cr)
Phase I EPC 7522 7521 1 30,300
Phase II EPC/
BOT
6647 6399 248 34339
Phase III EPC/
BOT
12109 10430 1679 80626
Phase IV EPC/
BOT
20000 15829 4171 27800
Phase V BOT 6500 3457 3043 41210
Phase VI BOT 1000 166 834 16680
Phase VII BOT 700 120 580 16680
Total 54478 43922 10556 247,635
To meet with the massive requirement of funds, innovativemeans of financing have been adopted by Govt of India.
Special financing strategies are needed, as raising adequateresources from budgetary resources alone is very difficult.
The details of fund raised from various sources is as under:
Cess on diesel and petrol: A cess of Rs 6 per liter is levied forroad development.
NHAI (Toll Remittance)-Toll to be collected from completedstretches
Market borrowings on the strength of future inflow incess/Toll: Funds are raised from Bonds issued by NHAI
Avail long term external loans from the World Bank, ADB& JICA.
Budgetary resources of Govt of India
public private partnership (PPP)
FINANCING OF VARIOUS PROGRAMMES
Public Private Partnership in India
• Build Operate Transfer (BOT) Toll (PPP)
• BOT Annuity (PPP)
• Hybrid Annuity (PPP)
• EPC (Public funded)
Implementation modes for NH projects
• BOT(Toll) is the Default Mode
• Earlier, the projects not viable on BOT(Toll) were taken up on BOT Annuity (PPP).
• Now Govt has adopted a new Model HAM in 2015.
• Projects not viable on BOT(Toll) are taken up on Hybrid Annuity Model(HAM)
• When no response is received on BOT(toll) and HAM then projects are taken up on EPC Mode.
Preference of Mode
Public Private Partnership in India-BOT (Toll) Concessionaire construct the road and recovers the cost
through collection of toll revenue during concession
period maximum upto 30 year.
Viability Gap Funding (VGF) maximum up to 40% of Total
Project cost (TPC) paid to concessionaire by Authority
during construction period in 5 installments linked to
project milestones.
Remaining project cost is recovered by concessionaire
through collection of toll revenue during operation period
Concessionaire maintains the road during operation
period.
11
BOT(Toll) Project
VGF support upto
40% of TPC by Govt.
Balance Project Cost
to be arranged by
Concessionaire for
Financial Close
COD
1. Toll revenue to be retained by
concessionaire
2. Interest payments (on reducing
balance @ Bank Rate + 2.5%)
Construction Period
Operations Period
Toll collection
by
Concessionair
e
O&M by
Concessionaire
BOT(Toll)Model
Bid Parameter – VGF quoted
Concession Period
Public Private Partnership in India-BOT(Annuity) Concessionaire construct the road and recovers the cost
through Annuities paid semi annually after completion of
construction and during operation period (maximum upto
17.5 year).
Construction risk with concessionaire.
Authority collects toll.
O&M responsibility is with concessionaire.
Authority has to pay annuities during operation period
hence payment liability deferred during construction and
paid in installment during operation period.
13
BOT(Annuity) Project
No Construction
Support by Govt.
100% of Project Cost
arranged by
Concessionaire for
Financial Close
COD
1. Annuity payments (biannually)
for 15 years
2. Interest payments (on reducing
balance @ Bank Rate + 2 %)
Construction Period
Operations Period
Toll collection
by Govt.
O&M by
Concessionaire
BOT(Annuity) Model
Bid Parameter–Semi Annuity quoted
Concession Period
The Model
▪ This is a new Model Adopted by Govt In 2015.
▪ 40% of Project Cost paid to Concessionaire by Authority during
construction period in five equal instalments linked to project
milestones.
▪ Balance 60% of Project Cost to be brought in by Concessionaire
▪ Investment recovered by Concessionaire through Annuity payments
over 15 years along with interest @ Bank Rate + 3 %.
▪ O&M responsibility is with Concessionaire, who receives O&M
payments bi-annually along with Annuity payments.
▪ Authority collects toll and Concessionaire remains insulated from Toll
Revenue Collection Risk.
▪ Project payments are inflation indexed.
Hybrid Annuity Model
This is a new innovative Model in which Annuities paid to
concessionaire are not equal but increases with time.
This helps to reduce the pressure on budgetary
resources initially since annuity amount increased
with time to match the budgetary resources (2.1% to
4.75% of balance cost).
Separate provisions exist for O&M payments to the
concessionaire from the Authority.
Toll collection shall be the responsibility of the Authority.
As of now 30 projects are awarded on HAM mode out of
which 9 has achieved financial close, which will be
started shortly .
Hybrid Annuity Model – salient features
Annuity payment schedule – Pre
determinedAnnuity following
the COD
Percentage of Balance
Completion Cost
1st Annuity 2.10%
2nd Annuity 2.17%
3rd Annuity 2.24%
4th Annuity 2.31%
5th Annuity 2.38%
6th Annuity 2.45%
7th Annuity 2.52%
8th Annuity 2.60%
9th Annuity 2.68%
10th Annuity 2.76%
11th Annuity 2.84%
12th Annuity 2.93%
13th Annuity 3.02%
14th Annuity 3.11%
15th Annuity 3.20%
Annuity following
the COD
Percentage of Balance
Completion Cost
16th Annuity 3.30%
17th Annuity 3.40%
18th Annuity 3.50%
19th Annuity 3.61%
20th Annuity 3.72%
21st Annuity 3.83%
22nd Annuity 3.94%
23rd Annuity 4.06%
24th Annuity 4.18%
25th Annuity 4.25%
26th Annuity 4.25%
27th Annuity 4.44%
28th Annuity 4.71%
29th Annuity 4.75%
30th Annuity 4.75%
100%
Hybrid Annuity Project
40% of Project Cost
(Construction
Support) by Govt.
60% of Project Cost
arranged by
Concessionaire for
Financial Close
COD
1. Annuity payments (biannually)
for 15 years
2. O&M payments
3. Interest payments (on reducing
balance @ Bank Rate + 3%)
Construction Period
Operations Period
Toll collection
by Govt.
O&M by
Concessionaire
Hybrid Annuity Model
Bid Parameter – NPV of the quoted
Bid Project Cost + NPV of the O&M
Cost for the entire Operations period
All the 3 modes of PPP is very useful in bridging the
fiscal gap in budget of country.
In BOT(Toll) Mode, government has to pay only 40% of
project cost and project will be constructed and
maintained by concessionaire for maximum period of 30
year.
In HAM mode, government has to pay only 40% of
project cost during construction period and remaining
as semi annual annuities during 15 year operation
period and project will be constructed and maintained
by concessionaire for period of 17.5 year.
In BOT(Annuity) mode, government has to pay semi
annual annuities during 15 year operation period and
project will be constructed and maintained by
concessionaire for period of 17.5 year.
PPP as a tool to use bridging
fiscal gaps in countries
Road Development on PPP in India Putting investment through PPP is enabling reduced
dependence on public expenditure for infrastructure projects.
In India, 30% (approx) funds for NHs are being raised through
PPP and 30% through (approx) Internal borrowing like NHAI
Bonds.
Highway sector in India has effectively used the PPP route and
presently, 39000 Km length of National Highways are being
developed on PPP basis in India.
259 projects with a length of 22225 Km is already awarded on
PPP basis.
The details are as under:Total projects awarded 259 No.
Total Length awarded 22225 Km
Length Completed 7566 Km
Length under Implementation 14659 Km
Total Project cost of awarded project US$ 28.84 Billion
Allocation/Expenditure for NHs
Financing Scheme Funds Raised
(2014-15)
Funds Raised
(2015-16)
Expenditure
upto Jan 17
(2016-17)
Cess on diesel and petrol Rs 15923 cr Rs 34257cr Rs 25001 cr
NHAI (Toll Remittance) Rs 5448 cr Rs 6500 cr Rs 7500 cr
Avail long tern external
loans from the World Bank,
ADB & JICA.
Rs 138 cr Rs 547 cr Rs 171cr
Budgetary resources of
Govt of India under NH(O)
Rs 5292 cr Rs 4216cr Rs 4010 cr
Market borrowings on the
strength of future inflow in
cess/Toll
Rs 3343cr
(7%)
Rs 23281cr
(23%)
Rs 27831cr
(36%)
public private partnership
(PPP)
Rs 19232 cr
(38%)
Rs 29770 cr
(30%)
Rs 11277 cr
(15%)
Total investment for NH in
India
Rs 49376 cr Rs 98571 cr Rs 75790 cr
Advantages of PPP
Timely Completion
Value for Money
Whole life asset performance
o Private entity takes responsibility & assumes
risk for the performance of the asset and
delivery of service over a long term
22
Delhi Gurgaon- PPP Project
BOT (Toll)
Jammu-Udhampur PPP Project-
BOT(Annuity)
25