Production Planning and Control(TKI 2409):

5 – Capacity Planning

Page 2: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 2/32

Scopes of PPC

Production

PLANNING CONTROLLING

FORECASTING

 APP

MRP

Schedulingand Sequencing

InventoryManagementCapacity

planning

Page 3: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 3/32

Capacity Planning

z RRP (Resource Requirement Planning)

z RCCP (Rough Cut Capacity Planning)

z CRP (Capacity Requirement Planning)

Page 4: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 4/32

Materials and Capacity

Materials Plan Capacity Plan

ProductionPlan

ResourceRequirement

Plan

Masterproduction

plan

Materials plan

Rough-cutcapacity plan

Capacityrequirement plan

Realistic?

Realistic?

Realistic?

Page 5: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 5/32

Production Plan Details

ProductionPlanResourcePlanning

Masterproduction

scheduling

Rough-cutcapacity plan

Capacityrequirement

planning

Demandmanagement

Detailed materialplanning

Input/output

analysis

Shop-floorsystems

 Vendorsystems

Page 6: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 6/32

Capacity - DefinitionsCapacity is the amount of a system output in any 

given period There are several terms regarding capacity:

Designed Capacity is the maximum capacity that can be

achieved under ideal conditionEffective Capacity is the number of design capacity that isactually expected

 Available Capacity is maximum usable capacity of a

particular facility 

 Available Capacity = Capacity * Utilization * Efficiency

Page 7: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 7/32

Capacity Management

Capacity Management have 4 categories:

1. RRP (Resource Requirements Planning)

2. RCCP (Rough Cut Capacity Planning)

3. CRP (Capacity Requirement Planning)

4. Input/Output Control

Capacity Planning  Æ task of determining  how much

output is needed from plant facilities and fromsupplier.

Capacity Control Æ the comparison between  plannedlevels and actual output achieved and the identification

of significant variances above and below plan.

Page 8: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 8/32

Rough Cut Capacity Planning (1)RCCP is the process of determining if the plan

is feasible (realistic)  with the actual condition(capacity).

It determines whether the organization has

sufficient capacity to carry out the plan.

 The process of RCCP including converting the

production plan and/or MPS into capacityneeds for key resources: manpower,machinery, and (in some case) money.

Page 9: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 9/32

Rough Cut Capacity Planning (2)

Need to see if MPS is feasible

RCCP finds approximate capacity needs in each

 work-center given the MPS

If capacity overloads, redo MPS

Page 10: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 10/32

Rough Cut Capacity Planning (3)In capacity planning, RCCP calculates the critical

 work center capacity requirements for all items onMPS.

It provides an early warning of insufficient capacity 

and the need for capacity actions.

RCCP techniques

Bill of Labor Approach

Resource Profile Approach

Page 11: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 11/32

RCCP (Bill of Labor Approach)Definition (by Conlon, 1977):

Listing by item of the amount of labor required by amajor labor category to produce that item or group of part numbers.

It is not intended to be a routing, but merely a means of 

estimating the capacity requirements for a particular item.

 This approach doesn’t consider lead time offsetsÆ

assumed that all component are built at thesame time.

Page 12: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 12/32

 An example BoL (1)

a11 a12

a21 a22

B11 B12

B21 B22

C11 C12

C21 C22

ProductWork Center Prod 1 Prod 2

WC 1

WC 2

Bill of Labor Master Schedule

Prod 1

Prod 2

ProductMonth

Month 1 Month 2

RCCPMonth

Month 1 Month 2Work Center

WC 1

WC 2

Page 13: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 13/32

 An example BoL (2)

0.3 0.2

1.0 0.7

100 200

300 400

90 140

310 480

ProductWork Center Prod 1 Prod 2

WC 1

WC 2

Bill of Labor Master Schedule

Prod 1

Prod 2

ProductMonth

Month 1 Month 2

RCCPMonth

Month 1 Month 2Work Center

WC 1

WC 2

Page 14: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 14/32

Example BoL (3)

Month Forecast MPS SOH (ribu)

(ribuan) (ribuan) 151 22 15 8

2 8 15 15

3 10 15 20

4 10 15 25

5 20 15 20

6 14 15 21

7 8 15 28

8 8 16 36

9 12 19 43

10 15 19 47

11 30 19 36

12 40 19 15

Bill of Labors

Hours needed

Lamp Assembly 0.1

Base Forming 0.01Plastic Molding 0.05

Socket Assembly 0.02

0.18

197 197Total

Page 15: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 15/32

Example BoL (4)Work Center M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 Total Hours

Lamp Assembly 1500 1500 1500 1500 1500 1500 1500 1600 1900 1900 1900 1900 19700

Base Forming 150 150 150 150 150 150 150 160 190 190 190 190 1970Plastic Molding 750 750 750 750 750 750 750 800 950 950 950 950 9850

Socket Assembly 300 300 300 300 300 300 300 320 380 380 380 380 3940

Total Capacity Req. 2700 2700 2700 2700 2700 2700 2700 2880 3420 3420 3420 3420

Page 16: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 16/32

RCCP Consideration

Since BOL assumes that all components are built inthe same time, thus resource profile technique is the

most detailed rough cut approach.

Resource profile approach considers each work stationor process is associated with a specific time period,

reflecting the lead time of the part produced.

Page 17: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 17/32

RCCP Tables

 A112  A111  A110

 A212  A211  A210

B11 B12 B13

B21 B22 B23

C11 C12 C13

C21 C22 C23

Time to due date

2 1

Resource Profile Master Schedule

Prod 1

Prod 2

Product MonthMonth 1 Month 2

RCCPMonth

Month 1 Month 2Work Center

WC 1

WC 2

Month 30

 A122  A121  A120

 A222  A221  A220 Month 3

Prod 1

Prod 2

Product

Prod 1

Prod 2

Page 18: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 18/32

Example Resource Profile (RP)

Work Center M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 Total Hours

Lamp Assembly 1500 1500 1500 1500 1500 1500 1500 1600 1900 1900 1900 1900 19700

Base Forming 150 150 150 150 150 150 160 190 190 190 190 0 1820

Plastic Molding 750 750 750 750 750 800 950 950 950 950 0 0 8350

Socket Assembly 300 300 300 300 300 300 320 380 380 380 380 0 3640

Total Capacity Req. 2700 2700 2700 2700 2700 2750 2930 3120 3420 3420 2470 1900

2 1 0Lamp Assembly 0 0 0.1

Base Forming 0 0.01 0

Plastic Molding 0.05 0 0

Socket Assembly 0 0.02 0

Month before due date

Page 19: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 19/32

RCCP Decisions (1)

In deciding whether the capacity planning is realistic,then we need to examined the actual capacity

available for the process.

By this mean, there must be adjustment for calculating the available capacity 

 Available Capacity = Capacity * Utilization * Efficiency

Page 20: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 20/32

RCCP Decisions (2)•  When regular capacity is inadequate, there are four

basic options available to increase capacity to meetthe capacity:

1. Overtime

2. Subcontracting 

3. Adding personnel

4. Alternate routing 

Page 21: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 21/32

Capacity Requirement Planning

Definition (APICS dictionary) :“The function of establishing, measuring, and adjusting limits or levels of capacity; the process of determining how much labor and machine resources are required to

accomplish the task of production”

Planned Order (Release and Receipt) are the input

to CRP, which ‘translated’ into hours of work, by  work center, by work period.

Page 22: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 22/32

CRP Logic

MPS is exploded via MRP system

Planned order releases are taken from the MRPsystem and used to perform a deterministicsimulation that uses lead times to determine the

time each order passes through each work station.

From this simulation, the machine load report

for each work station is produced Then, the load will be compared to capacityavailable at that workstation.

Page 23: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 23/32

An Example

 #3

 (1)

Level Part Qty/parent description

0 100 1 Finished Good

1 110 2 SubAssembly  

2 121 6 Comp A

2 122 10 Comp B

 Work Center Setup time/lot un Time/Piece

Part 100 1 30 min 2.5 min

Part 110 2 10 min 0.75 min

1 15 min 0.5 min

Part 121 3 15 min 0.3 min

1 25 min 0.25 min2 15 min 0.25 min

Part 122 2 25 min 0.75 min

3 30 min 0.15 min

1 75 min 0.5 min

3 30 min 0.75 min

 Work Center Available Utilization Efficiency1 2500 mins 100% 100%

2 2500 mins 100% 100%

3 2500 mins 100% 100%

4 2500 mins 100% 100%

Bill of Material

Routing Files

Item Master Record As of Saturday, July 01

 Work Center Master Files

1 2 3 4

Quantity 250 200 250 150

5 6 7

Quantity 200 300 150

 Week 

 Week 

MPS Files

Page 24: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 24/32

 An Example #3 (2)

 Work Center 1 2 3 4 5 6 7 Average

1 2,604 2,083 2,604 1,562 2,083 3,125 1,562 2,232

2 2,657 2,125 2,657 1,594 2,125 3,118 1,594 2,267

3 2,734 2,187 2,734 1,640 2,187 3,281 1,640 2,343

 Week 

0

500

1,000

1,500

2,000

2,500

3,000

3,500

1 2 3 4 5 6 7

WC1 WC2 WC3

RCCP

Page 25: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 25/32

 An Example #3 (3)Item 100

Lot Size L4L Lead Time 1 week  

0 1 2 3 4 5 6 7Gross Requirement 250 200 250 150 200 300 150

Scheduled Receipt 250

Projected on Hand 0 0 0 0 0 0 0 0

Planned Order Received 200 250 150 200 300 150

Planned Order Release 200 250 150 200 300 150 250

Item 110

Lot Size 400 Lead Time 2 weeks

0 1 2 3 4 5 6 7

Gross Requirement 400 500 300 400 600 300 500

Scheduled Receipt 400

Projected on Hand 500 100 0 100 100 0 100 0

Planned Order Received 400 400 500 400 400Planned Order Release 400 400 500 400 400 400 400

Period

Period

MRP

Page 26: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 26/32

Item 121

Lot Size 2400 Lead Time 3 weeks

0 1 2 3 4 5 6 7

Gross Requirement 1200 1200 1500 1200 1200 1200 1200

Scheduled Receipt 2400

Projected on Hand 1500 300 1500 0 1200 0 1200 0

Planned Order Received 2400 2400 0

Planned Order Release 2400 0 2400 0 2400 2400 0

Item 121

Lot Size 600 Lead Time 3 weeks

0 1 2 3 4 5 6 7

Gross Requirement 2000 2000 2500 2000 2000 2000 2000

Scheduled Receipt 6000

Projected on Hand 2500 500 4500 2000 0 4000 2000 0

Planned Order Received 6000

Planned Order Release 6000 0 0 6000 0 0 0

Period

Period

An Example #3 (4)MRP (Cont’d)

Page 27: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 27/32

 An Example #3 (5)

Part 1 2 3 4 5 6 7

100 200 250 150 200 300 150 250

110 400 400 500 400 400 400 400

121 2400 0 2400 0 2400 2400 0

122 6000 0 0 6000 0 0 0

 Week 

Planned Order Release

Page 28: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 28/32

 An Example #3 (6)

Part 1 2 3 4 5 6 7

 WC 1 100 30 30 30 30 30 30 30110 0 15 15 15 15 15 15

121 0 25 0 25 0 25 25

122 0 0 75 0 0 75 0

30 70 120 70 45 145 70

 WC 2 100 0 0 0 0 0 0 0

110 10 10 10 10 10 10 10

121 0 0 15 0 15 0 15

122 25 0 0 25 0 0 0

35 10 25 35 25 10 25 WC 3 100 0 0 0 0 0 0 0

110 0 0 0 0 0 0 0

121 15 0 15 0 15 15 0

122 0 30 0 30 30 0 30

15 30 15 30 45 15 30

 Week 

CRP Computation1. Setup Time Matrices

Page 29: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 29/32

 An Example #3 (7)

Part 1 2 3 4 5 6 7

 WC 1 100 500 625 375 500 750 375 625110 0 200 200 250 200 200 200

121 0 600 0 600 0 600 600

122 0 0 3000 0 0 3000 0

500 1425 3575 1350 950 4175 1425

 WC 2 100 0 0 0 0 0 0 0

110 300 300 375 300 300 300 300

121 0 0 600 0 600 0 600

122 4500 0 0 4500 0 0 0

4800 300 975 4800 900 300 900 WC 3 100 0 0 0 0 0 0 0

110 0 0 0 0 0 0 0

121 720 0 720 0 720 720 0

122 0 900 0 4500 900 0 4500

720 900 720 4500 1620 720 4500

 Week 

CRP Computation2. Run Time Matrices

Page 30: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 30/32

 An Example #3 (8)

1 2 3 4 5 6 7

 WC 1 530 1,495 3,695 1,420 995 4,320 1,495

 WC 2 4,835 310 1,000 4,835 925 310 935

 WC 3 735 930 735 4,530 1,665 735 4,530

 Week 

Part WC Week Setup Time Run Time Total Run Time Total Time

100 1 1 30 250 x 25 625 655

110 2 1 10 400 x 0.75 300 310110 1 2 15 400 x 0.5 200 215

121 1 1 25 2400 x 0.25 600 625

121 2 2 15 2400 x 0.25 500 515

122 1 1 75 6000 x 0.5 3000 3075

122 3 2 30 6000 x 0.75 4500 4530

Capacity Requirement of Planned Order Release

Capacity Required by Released Order

Page 31: PPC 5 - Capacity Planning (1)

7/30/2019 PPC 5 - Capacity Planning (1)

http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 31/32

 An Example #3 (9)

 Week 1 Week 2

 WC 1 4355 215

 WC 2 310 515

 WC 3 0 4530

1 2 3 4 5 6 7 WC 1 4,885 1,710 3,695 1,420 995 4,320 1,495

 WC 2 5,145 825 1,000 4,835 925 310 925

 WC 3 735 5,460 735 4,530 1,665 735 4,530

Week 

Released Order Capacity Requirement (Summary)