Production Planning and Control(TKI 2409):
5 – Capacity Planning
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 2/32
Scopes of PPC
Production
PLANNING CONTROLLING
FORECASTING
APP
MRP
Schedulingand Sequencing
InventoryManagementCapacity
planning
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 3/32
Capacity Planning
z RRP (Resource Requirement Planning)
z RCCP (Rough Cut Capacity Planning)
z CRP (Capacity Requirement Planning)
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 4/32
Materials and Capacity
Materials Plan Capacity Plan
ProductionPlan
ResourceRequirement
Plan
Masterproduction
plan
Materials plan
Rough-cutcapacity plan
Capacityrequirement plan
Realistic?
Realistic?
Realistic?
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 5/32
Production Plan Details
ProductionPlanResourcePlanning
Masterproduction
scheduling
Rough-cutcapacity plan
Capacityrequirement
planning
Demandmanagement
Detailed materialplanning
Input/output
analysis
Shop-floorsystems
Vendorsystems
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 6/32
Capacity - DefinitionsCapacity is the amount of a system output in any
given period There are several terms regarding capacity:
Designed Capacity is the maximum capacity that can be
achieved under ideal conditionEffective Capacity is the number of design capacity that isactually expected
Available Capacity is maximum usable capacity of a
particular facility
Available Capacity = Capacity * Utilization * Efficiency
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 7/32
Capacity Management
Capacity Management have 4 categories:
1. RRP (Resource Requirements Planning)
2. RCCP (Rough Cut Capacity Planning)
3. CRP (Capacity Requirement Planning)
4. Input/Output Control
Capacity Planning Æ task of determining how much
output is needed from plant facilities and fromsupplier.
Capacity Control Æ the comparison between plannedlevels and actual output achieved and the identification
of significant variances above and below plan.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 8/32
Rough Cut Capacity Planning (1)RCCP is the process of determining if the plan
is feasible (realistic) with the actual condition(capacity).
It determines whether the organization has
sufficient capacity to carry out the plan.
The process of RCCP including converting the
production plan and/or MPS into capacityneeds for key resources: manpower,machinery, and (in some case) money.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 9/32
Rough Cut Capacity Planning (2)
Need to see if MPS is feasible
RCCP finds approximate capacity needs in each
work-center given the MPS
If capacity overloads, redo MPS
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 10/32
Rough Cut Capacity Planning (3)In capacity planning, RCCP calculates the critical
work center capacity requirements for all items onMPS.
It provides an early warning of insufficient capacity
and the need for capacity actions.
RCCP techniques
Bill of Labor Approach
Resource Profile Approach
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 11/32
RCCP (Bill of Labor Approach)Definition (by Conlon, 1977):
Listing by item of the amount of labor required by amajor labor category to produce that item or group of part numbers.
It is not intended to be a routing, but merely a means of
estimating the capacity requirements for a particular item.
This approach doesn’t consider lead time offsetsÆ
assumed that all component are built at thesame time.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 12/32
An example BoL (1)
a11 a12
a21 a22
B11 B12
B21 B22
C11 C12
C21 C22
ProductWork Center Prod 1 Prod 2
WC 1
WC 2
Bill of Labor Master Schedule
Prod 1
Prod 2
ProductMonth
Month 1 Month 2
RCCPMonth
Month 1 Month 2Work Center
WC 1
WC 2
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 13/32
An example BoL (2)
0.3 0.2
1.0 0.7
100 200
300 400
90 140
310 480
ProductWork Center Prod 1 Prod 2
WC 1
WC 2
Bill of Labor Master Schedule
Prod 1
Prod 2
ProductMonth
Month 1 Month 2
RCCPMonth
Month 1 Month 2Work Center
WC 1
WC 2
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 14/32
Example BoL (3)
Month Forecast MPS SOH (ribu)
(ribuan) (ribuan) 151 22 15 8
2 8 15 15
3 10 15 20
4 10 15 25
5 20 15 20
6 14 15 21
7 8 15 28
8 8 16 36
9 12 19 43
10 15 19 47
11 30 19 36
12 40 19 15
Bill of Labors
Hours needed
Lamp Assembly 0.1
Base Forming 0.01Plastic Molding 0.05
Socket Assembly 0.02
0.18
197 197Total
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 15/32
Example BoL (4)Work Center M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 Total Hours
Lamp Assembly 1500 1500 1500 1500 1500 1500 1500 1600 1900 1900 1900 1900 19700
Base Forming 150 150 150 150 150 150 150 160 190 190 190 190 1970Plastic Molding 750 750 750 750 750 750 750 800 950 950 950 950 9850
Socket Assembly 300 300 300 300 300 300 300 320 380 380 380 380 3940
Total Capacity Req. 2700 2700 2700 2700 2700 2700 2700 2880 3420 3420 3420 3420
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 16/32
RCCP Consideration
Since BOL assumes that all components are built inthe same time, thus resource profile technique is the
most detailed rough cut approach.
Resource profile approach considers each work stationor process is associated with a specific time period,
reflecting the lead time of the part produced.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 17/32
RCCP Tables
A112 A111 A110
A212 A211 A210
B11 B12 B13
B21 B22 B23
C11 C12 C13
C21 C22 C23
Time to due date
2 1
Resource Profile Master Schedule
Prod 1
Prod 2
Product MonthMonth 1 Month 2
RCCPMonth
Month 1 Month 2Work Center
WC 1
WC 2
Month 30
A122 A121 A120
A222 A221 A220 Month 3
Prod 1
Prod 2
Product
Prod 1
Prod 2
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 18/32
Example Resource Profile (RP)
Work Center M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 Total Hours
Lamp Assembly 1500 1500 1500 1500 1500 1500 1500 1600 1900 1900 1900 1900 19700
Base Forming 150 150 150 150 150 150 160 190 190 190 190 0 1820
Plastic Molding 750 750 750 750 750 800 950 950 950 950 0 0 8350
Socket Assembly 300 300 300 300 300 300 320 380 380 380 380 0 3640
Total Capacity Req. 2700 2700 2700 2700 2700 2750 2930 3120 3420 3420 2470 1900
2 1 0Lamp Assembly 0 0 0.1
Base Forming 0 0.01 0
Plastic Molding 0.05 0 0
Socket Assembly 0 0.02 0
Month before due date
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 19/32
RCCP Decisions (1)
In deciding whether the capacity planning is realistic,then we need to examined the actual capacity
available for the process.
By this mean, there must be adjustment for calculating the available capacity
Available Capacity = Capacity * Utilization * Efficiency
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 20/32
RCCP Decisions (2)• When regular capacity is inadequate, there are four
basic options available to increase capacity to meetthe capacity:
1. Overtime
2. Subcontracting
3. Adding personnel
4. Alternate routing
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 21/32
Capacity Requirement Planning
Definition (APICS dictionary) :“The function of establishing, measuring, and adjusting limits or levels of capacity; the process of determining how much labor and machine resources are required to
accomplish the task of production”
Planned Order (Release and Receipt) are the input
to CRP, which ‘translated’ into hours of work, by work center, by work period.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 22/32
CRP Logic
MPS is exploded via MRP system
Planned order releases are taken from the MRPsystem and used to perform a deterministicsimulation that uses lead times to determine the
time each order passes through each work station.
From this simulation, the machine load report
for each work station is produced Then, the load will be compared to capacityavailable at that workstation.
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 23/32
An Example
#3
(1)
Level Part Qty/parent description
0 100 1 Finished Good
1 110 2 SubAssembly
2 121 6 Comp A
2 122 10 Comp B
Work Center Setup time/lot un Time/Piece
Part 100 1 30 min 2.5 min
Part 110 2 10 min 0.75 min
1 15 min 0.5 min
Part 121 3 15 min 0.3 min
1 25 min 0.25 min2 15 min 0.25 min
Part 122 2 25 min 0.75 min
3 30 min 0.15 min
1 75 min 0.5 min
3 30 min 0.75 min
Work Center Available Utilization Efficiency1 2500 mins 100% 100%
2 2500 mins 100% 100%
3 2500 mins 100% 100%
4 2500 mins 100% 100%
Bill of Material
Routing Files
Item Master Record As of Saturday, July 01
Work Center Master Files
1 2 3 4
Quantity 250 200 250 150
5 6 7
Quantity 200 300 150
Week
Week
MPS Files
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 24/32
An Example #3 (2)
Work Center 1 2 3 4 5 6 7 Average
1 2,604 2,083 2,604 1,562 2,083 3,125 1,562 2,232
2 2,657 2,125 2,657 1,594 2,125 3,118 1,594 2,267
3 2,734 2,187 2,734 1,640 2,187 3,281 1,640 2,343
Week
0
500
1,000
1,500
2,000
2,500
3,000
3,500
1 2 3 4 5 6 7
WC1 WC2 WC3
RCCP
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 25/32
An Example #3 (3)Item 100
Lot Size L4L Lead Time 1 week
0 1 2 3 4 5 6 7Gross Requirement 250 200 250 150 200 300 150
Scheduled Receipt 250
Projected on Hand 0 0 0 0 0 0 0 0
Planned Order Received 200 250 150 200 300 150
Planned Order Release 200 250 150 200 300 150 250
Item 110
Lot Size 400 Lead Time 2 weeks
0 1 2 3 4 5 6 7
Gross Requirement 400 500 300 400 600 300 500
Scheduled Receipt 400
Projected on Hand 500 100 0 100 100 0 100 0
Planned Order Received 400 400 500 400 400Planned Order Release 400 400 500 400 400 400 400
Period
Period
MRP
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 26/32
Item 121
Lot Size 2400 Lead Time 3 weeks
0 1 2 3 4 5 6 7
Gross Requirement 1200 1200 1500 1200 1200 1200 1200
Scheduled Receipt 2400
Projected on Hand 1500 300 1500 0 1200 0 1200 0
Planned Order Received 2400 2400 0
Planned Order Release 2400 0 2400 0 2400 2400 0
Item 121
Lot Size 600 Lead Time 3 weeks
0 1 2 3 4 5 6 7
Gross Requirement 2000 2000 2500 2000 2000 2000 2000
Scheduled Receipt 6000
Projected on Hand 2500 500 4500 2000 0 4000 2000 0
Planned Order Received 6000
Planned Order Release 6000 0 0 6000 0 0 0
Period
Period
An Example #3 (4)MRP (Cont’d)
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 27/32
An Example #3 (5)
Part 1 2 3 4 5 6 7
100 200 250 150 200 300 150 250
110 400 400 500 400 400 400 400
121 2400 0 2400 0 2400 2400 0
122 6000 0 0 6000 0 0 0
Week
Planned Order Release
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 28/32
An Example #3 (6)
Part 1 2 3 4 5 6 7
WC 1 100 30 30 30 30 30 30 30110 0 15 15 15 15 15 15
121 0 25 0 25 0 25 25
122 0 0 75 0 0 75 0
30 70 120 70 45 145 70
WC 2 100 0 0 0 0 0 0 0
110 10 10 10 10 10 10 10
121 0 0 15 0 15 0 15
122 25 0 0 25 0 0 0
35 10 25 35 25 10 25 WC 3 100 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
121 15 0 15 0 15 15 0
122 0 30 0 30 30 0 30
15 30 15 30 45 15 30
Week
CRP Computation1. Setup Time Matrices
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 29/32
An Example #3 (7)
Part 1 2 3 4 5 6 7
WC 1 100 500 625 375 500 750 375 625110 0 200 200 250 200 200 200
121 0 600 0 600 0 600 600
122 0 0 3000 0 0 3000 0
500 1425 3575 1350 950 4175 1425
WC 2 100 0 0 0 0 0 0 0
110 300 300 375 300 300 300 300
121 0 0 600 0 600 0 600
122 4500 0 0 4500 0 0 0
4800 300 975 4800 900 300 900 WC 3 100 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
121 720 0 720 0 720 720 0
122 0 900 0 4500 900 0 4500
720 900 720 4500 1620 720 4500
Week
CRP Computation2. Run Time Matrices
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 30/32
An Example #3 (8)
1 2 3 4 5 6 7
WC 1 530 1,495 3,695 1,420 995 4,320 1,495
WC 2 4,835 310 1,000 4,835 925 310 935
WC 3 735 930 735 4,530 1,665 735 4,530
Week
Part WC Week Setup Time Run Time Total Run Time Total Time
100 1 1 30 250 x 25 625 655
110 2 1 10 400 x 0.75 300 310110 1 2 15 400 x 0.5 200 215
121 1 1 25 2400 x 0.25 600 625
121 2 2 15 2400 x 0.25 500 515
122 1 1 75 6000 x 0.5 3000 3075
122 3 2 30 6000 x 0.75 4500 4530
Capacity Requirement of Planned Order Release
Capacity Required by Released Order
7/30/2019 PPC 5 - Capacity Planning (1)
http://slidepdf.com/reader/full/ppc-5-capacity-planning-1 31/32
An Example #3 (9)
Week 1 Week 2
WC 1 4355 215
WC 2 310 515
WC 3 0 4530
1 2 3 4 5 6 7 WC 1 4,885 1,710 3,695 1,420 995 4,320 1,495
WC 2 5,145 825 1,000 4,835 925 310 925
WC 3 735 5,460 735 4,530 1,665 735 4,530
Week
Released Order Capacity Requirement (Summary)
Capacity Requirement Planning