Power Distribution Note

Embed Size (px)

Citation preview

  • 8/2/2019 Power Distribution Note

    1/7

    STATE-OWNED ELECTRICITY DISTRIBUTION COMPANIES: Some

    positives, though several concerns remain...

    Anjan GhoshHeadCorporate [email protected]+91-22-30470006

    Sabyasachi [email protected]+91-124-4545304

    Girishkumar [email protected]+91-22-30470032

    ICRA estimates the losses for discoms (before accounting for

    government subsidy) in the country at Rs. 80,000 crore in FY 2012,

    up from around Rs. 63,500 crore in FY 2010. The estimate is based

    on our study of distribution companies (Discoms) functioning in

    eleven Indian states. ICRA expects the overall subsidy support for

    discoms at around Rs. 43,000 crore in FY 2012, which represents

    an increase of 13% y.o.y. from FY 2010.

    Taking the subsidy into account, the total book losses for discoms

    are estimated at Rs. 38,000 crore in FY 2012. As per ICRAsestimates, six states namely Uttar Pradesh, Tamil Nadu, Madhya

    Pradesh, Rajasthan, Punjab and Haryana would account for about

    70% of the total losses in FY 2012. Such losses have largely been

    funded through bank borrowings (mainly short-to-medium term in

    nature) and stretched payments to power creditors, mainly state-

    owned generating companies. However, with increasing concerns

    over the credit quality of discoms, the availability of bank funding

    for such losses has been affected from FY 2012 onwards, thus

    resulting in a stretched liquidity position. This has affected debt

    repayments and resulted in delays in payments to power and fuel

    suppliers. Consequently, debt restructuring is being done for some

    of loans on the books of the discoms in the states of Rajasthan,Haryana and Uttar Pradesh.

    The ruling of the Appellate Tribunal of Electricity (ATE) is aimed at

    regulatory discipline by State Electricity Regulatory Commissions

    (SERCs) for timely and cost-reflective tariff determination. ICRA

    views this as a positive development. The Shungulu Committee

    has suggested measures to improve the viability of the

    distribution segment, which is critical for the entire power sector.

    However, ICRA expects the implementation of the

    recommendations to be particularly challenging, given that

    several stakeholders such as discoms, state governments and

    regulatory entities (SERCs) will have to be involved.

    ICRA has observed that tariff revisions have been carried out for

    discoms across many states for FY 2012. However, the quantum of

    hikes is well short of what is required for full recovery of costs in

    most states and is also accompanied by significant delays. Even

    with respect to tariff petition for FY 2013 and true-up for past

    periods (upto FY 2011), ICRA observes that petitions are yet to be

    filed by discoms in some states, which is against the spirit of the

    ATE ruling. Also, while Fuel & Power Purchase Cost Adjustment

    (FPPCA) principles have been implemented across states, they

    continue to vary with a significant lag period for recovery in some

    of these states, which in turn adversely affects the liquidityposition of the discoms. Nonetheless, ICRA derives comfort from

    the fact that several states, including some of the most vulnerable

    ones, have obtained fairly stiff tariff hikes for FY 2012 or filed for

    ICRA Rating Feature

    MARCH2012

    mailto:[email protected]:[email protected]:[email protected]
  • 8/2/2019 Power Distribution Note

    2/7

    very large tariff hikes in a reasonably timely manner. Thus, the overall trajectory in terms of tariff trends is

    positive.

    Key Trends & Concerns

    We have assessed the key trends in the operating/regulatory environment and the financial position for

    discoms in eleven key states, which approximately contribute to about 82% of the overall power consumptionin the country. These states are Gujarat, Maharashtra, Andhra Pradesh, Karnataka, Punjab, Haryana,

    Rajasthan, Uttar Pradesh, Madhya Pradesh, Tamil Nadu and West Bengal. Overall, the discoms in many states

    continue to face challenges arising from inadequate tariffs as compared with their cost of supply, rising subsidy

    dependence and high operational in-efficiencies.

    Discom losses before accounting for subsidy support estimated at Rs. 80,000 crore for FY 2012

    ICRA expects the overall financial losses (without accounting for subsidy) for the discoms in India to be at

    around Rs. 80,000 crore in FY 2012, which is an increase of 14% over FY 2010. As in the past, losses are

    contributed by several factors such as increasing subsidy dependence; inability to meet distribution loss levels

    as per targets laid by SERCs and rising power purchase expenses, which are not being passed on through tariff

    revision/FPPCA. In ICRAs view, these losses have increased in FY 2011 and FY 2012 as compared to FY 2010because of higher power purchase costs and interest burden without commensurate tariff increases. After

    factoring in subsidy receivable from the respective State Governments, the overall book loss levels for FY 2011-

    12 are estimated at about Rs. 38,000 crore. About 70% of these losses are expected to be contributed by

    discoms in six states, namely, Rajasthan, Tamil Nadu, Uttar Pradesh, Haryana, Punjab and Madhya Pradesh,

    which consume around 40% of power in the country. The main reason for the losses is either limited or

    absence of tariff revision for prolonged periods besides inability to control distribution loss levels in some of

    these states.

    Subsidy dependence for discoms estimated at about Rs. 43,000 crore in FY 2012

    ICRA expects the overall

    subsidy dependence fordiscoms on an all-India basis

    at about Rs. 43,000 crore in

    FY 2012, which represents an

    increase1

    of 13% from FY

    2010. Also, the overall

    subsidy dependence as a

    percent of revenues

    approved by SERCs for FY

    2012 is significant at about

    20%. However, this varies

    widely across the states :

    from a low of 5% in WestBengal to a high of 50% in

    Rajasthan. Given such high

    subsidy dependence for

    discoms, ICRA notes that

    timely and adequate receipts of subsidy from State Governments remains extremely critical for the liquidity

    profile of the discoms. There have been delays in many states such as Rajasthan, Punjab, Karnataka and

    Andhra Pradesh, which in turn, has adversely affected the financial and liquidity position of the discoms in such

    states. Given that the extent of subsidy declared by the State Governments towards certain consumer

    categories is unlikely to come down, timely receipt of subsidy would be a key factor in terms of liquidity

    profile.

    1This is mainly contributed by continued power supply at either heavily subsid ised rate or free power (as per the State Governments directives) to

    agriculture category and certain small sections of domestic category and rising fuel and power purchase costs.

  • 8/2/2019 Power Distribution Note

    3/7

    ICRA Rating Feature

    3

    Large-scale restructuring expected

    The losses of discoms have largely been funded through bank borrowings (typically short-to-medium term in

    nature) apart from delaying payment to power and fuel creditors with state owned gencos typically bearing

    the brunt of these delinquencies on creditors. ICRA expects the discoms in the most vulnerable states of UP,

    Tamil Nadu, Rajasthan, MP, Punjab and Haryana to account for over 70% of the total debt of discoms in India.

    However, with increasing concerns over the credit quality of discoms, the availability of bank funding for suchlosses was adversely affected from FY 2012, resulting in stretched liquidity situation, which in turn has led to

    increased levels of delays on payments to power and fuel suppliers. Consequently, debt restructuring is being

    done for some of the loans on the books of discoms in the states of Rajasthan, Haryana and Uttar Pradesh.

    ICRA believes that in some of the most vulnerable discoms, financial restructuring is thus inevitable, whereby,

    debt restructuring and support from State Government for cleaning up the balance sheets would be required

    apart from operational efficiency measures and timely tariff revisions for maintaining the sustainability of state

    utilities.

    Tariff revisions in several states in FY 2012, although with delays

    As may be seen in Chart 2, several

    states have seen tariff revision inFY2011. While this is a positive,

    ICRA notes that the bulk of these

    tariff revisions (for FY 2011-12)

    happened well after the due date

    which is 31 March 2011. Further, in

    some of the states such as Uttar

    Pradesh, West Bengal,

    Maharashtra, Karnataka and

    Madhya Pradesh, tariff/ARR

    petitions for FY 2012-13 and true-

    up petitions for FY 2010-11 (as per

    MYT regulatory framework) are yetto be filed with SERCs, whereas the

    same should have been filed by 30

    November 2011. There have also

    been instances of roll-back of

    previous tariff-hike during FY 2012,

    as observed in the state of West

    Bengal, which led to adverse

    impact on the financial and liquidity position of its distribution utility. Such regulatory uncertainties cannot be

    ruled out for other states in the future. Also, the extent of tariff revision has been varied from as low as 0.4%

    to 24%; and is inadequate to meet the actual cost of supply in many states, thus resulting in large, uncovered

    revenue deficits.

    Tariff hike required to cover existing revenue gap itself is on higher side; Further, unsustainable

    levels of regulatory assets cause concern in some of the states

  • 8/2/2019 Power Distribution Note

    4/7

    ICRA Rating Feature

    4

    ICRA has observed that SERCs have not allowed full recovery of costs (including arrears for past years and

    return on equity (RoE) element) in several states in order to avoid tariff shock to consumers, which in turn has

    resulted in continued deficits. This uncovered revenue deficit, which is however recognised by SERCs and

    proposed to be covered through future tariff hikes, is also termed as regulatory asset (RA)2. As seen above in

    Table 1, tariff hike required so as to cover the existing revenue gap (i.e. gap between revenue requirement and

    cost of supply even without considering recovery of outstanding regulatory assets) for utilities remains onsignificantly higher side for discoms in states such as Tamil Nadu

    3, Rajasthan

    4and Madhya Pradesh. As per

    provisions of the EA and ATE ruling, such RAs ought to be recovered over a three-year period. There has been

    substantial regulatory asset build-up for discoms in many states such as Tamil Nadu, Rajasthan, Punjab, Uttar

    Pradesh, Haryana, Delhi and West Bengal, resulting in huge debt burden to fund the deficits. Should SERCs

    provide for this, overall tariff-hike requirement would be even higher for FY 2013 than the above estimates

    resulting in a tariff shock. Under these circumstances, ICRA believes that recovery of RA is likely to be

    staggered over a much longer time horizon. In our opinion, this poses a challenge for SERCs for adequate tariff

    determination in these states, given the critical need for tariff revision to improve the financial position of the

    utilities, and also in view of the interests of the consumers to avoid any tariff shock.

    ATEs directive to SERCs for timely tariff determination: a key positive development

    The Appellate Tribunal for Electricity5

    (ATE) issued a judgement in its order dated 11 November 20116

    and in

    its judgement has directed all SERCs to initiate suo-moto proceedings for tariff determination in case of delays

    by the utilities in filing their tariff petitions. The key features of ATEs directive are mentioned in Box 1.

    We note this as a very positive development on the regulatory front for the power distribution sector.

    However, the impact of this judgement by ATE on the financial position of the utilities will hinge upon its

    implementation by SERCs in an independent manner without any kind of influence from the state

    government/utility. In addition, poor data availability, given the significant delays in the finalisation of

    accounts as well as operational in-efficiencies in energy audit system, in some cases, could constrain initiation

    of such tariff proceedings by SERCs.

    2 Regulatory asset is cost item (as approved by SERC) which is allowed to be recovered in future tariff determination. The cost of carrying of the

    regulatory asset is also an allowed expense for estimation of ARR or cost of supply.3For the distribution utility in Tamil Nadu, the accumulated losses till end of FY 2010 will be treated (as notified by State Government) as part of

    financial restructuring in the final transfer scheme associated with transferring the assets and liabilities of erstwhile TNEB to successor entities (i.e.

    TANGEDCO, TANTRANSCO and TNEB Limited). (Source: Tariff Petition dated November 15, 2011). Regulatory asset estimate is for FY 2011 and FY

    2012, as estimated by TNERC in its tariff order dated July 2011.4For the discoms in Rajasthan, unrecovered revenue deficits pertaining till FY 2009 are funded as agreed by State Government and hence, not

    considered in estimation of regulatory asset by SERC ( Source : Tariff Order dated September 8, 2011). Regulatory asset estimate is thus for FY 2010,

    FY 2011 and FY 2012.

    5 In line with the provision of Electricity Act (EA) 2003, the Central Government has established an Appellate Tribunal to be known as the

    Appellate Tribunal for Electricity to hear appeals against the orders of the adjudicating officer or the Appropriate Commission. As per the section121 of EA-2003, The Chairperson of the Appellate Tribunal shall exercise the general power of super-intendance and control over the

    Appropriate Commission.

    6 A suo-moto request petition was initiated by the Ministry of Power, Government of India to ATE in January 2011 so that ATE can exercise its

    regulatory authority under section 121 of the EA-2003 to provide directions to all SERCs.

    Box 1: Salient Features of ATEs Order dated 11 November 2011

    It should be the endeavour of every State Commission to ensure that the tariff for the financial year is

    decided before 1st

    April of the tariff year, for which tariff petition should be filed by the end of November of

    the previous year. Truing-up should also be an annual exercise.

    In the event of any delay in filing the ARR, truing-up and Annual Performance Review, one month beyond

    the scheduled date of submission of the petition, the State Commission must initiate suo-moto proceedings

    for tariff determination.

    The recovery of the Regulatory Asset (RA) should be time-bound and within a period not exceeding threeyears at the most and preferably within the control period. The carrying cost of the RA should be allowed to

    the utilities in the ARR of the year in which the RA are created to avoid the problem of cash flow to the

    distribution licensee.

    Fuel and Power Purchase cost is a major expense of the distribution company, which is uncontrollable. The

    Fuel and Power Purchase cost adjustment should preferably be on a monthly basis but in no case exceed a

    quarter. Any State Commission that does not already have such a formula/mechanism in place must put in

    place such a formula/ mechanism within 6 months of the date of this order.

  • 8/2/2019 Power Distribution Note

    5/7

    ICRA Rating Feature

    5

    Implementation of FPPCA principles being observed in more states

    In our sector comment tiled State Owned Electricity Distribution Companies : Key Performance Indicators &

    Credit Perspective, dated January 2011, we had highlighted the concern arising from inconsistency in FPPCA

    framework and delays in filing of FPPCA petitions, which in turn strain the liquidity profiles of discoms. Regular

    pass-through of FPPCA in retail tariff (and in the case of agriculture consumption, through increased subsidyfrom the state government) remains very crucial for discoms from their credit/liquidity perspective. Table 2

    presents the current status of FPPCA mechanism applicable across discoms:

    Table 2: Status on FPPCA Mechanism available for Discoms across States

    FPPCA Mechanism Remarks

    Gujarat Yes, Quarterly Approved @ 96 paise/unit w.e.f. February 2012

    Maharashtra Yes, Monthly Capped at 10% of the prevailing energy charge

    Andhra Pradesh Yes, Quarterly Significant delays in filing for FPPCA petition by discoms; Order for FPPCA for Q4-FY'10

    and Q4- FY'09 was issued by APERC on 17 January, 2012 based on FAC petition filed on

    25 August 2011; e.g. FPPCA admitted for January March 2010 is allowed to be

    recovered between November 2012 and January 2013, reflecting a lag period of 35

    months.

    Karnataka No Considered by SERC at the time of APR and Final true-up

    Tamil Nadu No

    FPPCA framework is now suggested by TANGEDCO in its tariff petition submitted to

    TNERC in November 2011

    Rajasthan Yes, Quarterly As per the regulations dated January 2009, FPPCA is capped at 10% of the energy

    charge or any other ceiling as stipulated by SERC. However, there is no petition filed

    for claim of FPPCA by discoms so far.

    Punjab Yes, Quarterly Subject to approval by SERC based on filings by discom. FPPCA for Q3-FY 11 is

    approved by SERC in ARR approved for FY 2012 vide Tariff Order dated 9 May 2011.

    Haryana Yes, Monthly Issued in May 2010; however, capped at 10% of approved energy charge; last tariff

    order for FY 12 dated May 2011 allowed FPPCA of an average of 30 paise/unit in the

    tariff.

    Uttar Pradesh No Commission has directed UPPCL to suggest FSA mechanism in its tariff order dated

    March 2010

    Madhya Pradesh No Considered by SERC at the time of True-up of ARR

    West Bengal Yes; Monthly Introduced in April 2011 and discontinued in May 2011, which subsequently was made

    operational in January 2012; currently, FPPCA is admitted at 82 paise/unit.

    Delhi Yes; Quarterly Introduced in August 2011; subsequently, 5% surcharge on applicable tariff for Fuel &

    Power Purchase Adjustment has been allowed recently (in February 2012) by DERC for

    discoms

    Source: ICRA Research, SERC Regulations across States

    Among the states as mentioned in Table 2, FPPCA is well operationlised in Gujarat and helps the discoms to

    maintain healthy liquidity profiles. However, in states such as in Uttar Pradesh, Karnataka, Madhya Pradesh &

    Tamil Nadu, this mechanism has been absent so far. While ATE has given the direction to SERCs, which do not

    already have such a formula/mechanism in place, to put in place the same by June 2012, it is to be noted that

    timely filing for FPPCA petition by utilities also remains important. Further, there is no suo-moto direction

    available for determination/approval of FPPCA to SERCs in case of delays in filing of such petitions. Also, as

    observed in the state of West Bengal, FPPCA mechanism, although introduced by SERC in April 2011, could not

    be operationalised by the discom for a prolonged period of about 9 month during FY 2011-12 and such riskcannot be ruled out in other states.

    Implementation of the recommendations of Shungulu Committee could be challenging

    A high level panel headed by Shri. V. K. Shungulu, former CAG, appointed by the Planning Commission in July

    2010 (with the objective of study to suggest measures for improvement in the commercial viability of the

    distribution sector) issued the report7

    on the financial position of distribution utilities in December 2011. The

    implementation of the recommendations of the Shungulu Committee could be particularly challenging, given

    that several stakeholders such as discoms, state governments and regulatory entities (SERCs) need to be

    involved. Further, the Shungulu Committee has recommended that banks could sell loans under stress to a

    new SPV, which is proposed to be 76% held by RBI. However, there is no clarity on RBIs view on the same.

    7The report has assessed a) the financial position of distribution utilities between FY 2005 and FY 2010, b) electricity tariff determination process

    including roles of State Government, SERCs and utilities, c) system improvement measures & operational issues and d) action plan to achieve the

    financial viability for the distribution sector by 2017.

  • 8/2/2019 Power Distribution Note

    6/7

    ICRA Rating Feature

    6

    Box 2 gives the key recommendations of the Shungulu Committee:

    Box 2: Key Recommendations of the Shungulu Committee

    SPV to be set up as a corporate entity (76% held by the RBI and the balance by PFC and REC), which will be

    entitled to purchase loans (which are likely to be restructured) of the banks, subject to certain conditions.

    o These conditions include a) banks to negotiate with the state government/utility for the revisedpayment schedule and b) state government to agree upon regular tariff increase, operational plan

    to meet certain technical/ operational performance parameters and implementation of capital

    expenditure for system improvement as a first priority.

    o RBI would provide a line of credit to SPV for purchase of loans from the banks. In case of non-

    compliance of terms set by SPV, the state government undertaking should be available to RBI

    that the amount defaulted would be debited to the State Governments account with the RBI.

    Thus, intentional default or non-adherence to the action plan would be unlikely.

    Recommendations on the process of tariff determination are reiterated as per the directives of ATEs

    judgement

    In addition to the basic tariff (which is fixed taking into account the targeted loss levels by SERCs), a loss

    surcharge should also be levied, which can vary area-wise within the license area so as to bring consumer

    awareness and improve the accountability of the utilitys staff.

    Selection committee for SERC should be broad-based so as to make the selection process fair, objectiveand independent. Also, a person who has worked during the preceding five years with the state

    government or any of its undertaking should not be eligible for appointment as a member or chairman of

    the commission in the same state. Committee1

    to be appointed for oversight of the functioning as well as

    periodic evaluation of the performance by the SERCs , with the main objective to ensure the accountability

    of the regulators.

    Distribution Franchisee Modelwould be the way forward on an urgent basis for the utilities to bring down

    their distribution loss levels significantly, given the advantages over the public-private partnership model

    and successful implementation of the franchisee model for the Bhivandi Circle in Maharashtra. This should

    be extended to the states during the next few years to at least 255 towns, which account for over 40% of

    the consumption.

    R-APDRPscheme is a key step taken by the Central Government to reduce distribution losses; and should

    be extended to the next Plan period with applicability to all towns above a population of 30,000 based on

    Census 2011.

    Utilities need to have a core team of IT experts in-house to work with IT consultants appointed under R-

    APDRP; also, there is a need for skilled professionals in the human resource development and Finance

    departments.

  • 8/2/2019 Power Distribution Note

    7/7

    ICRA Rating Feature

    7

    ICRA Limited

    An Associate of Moodys Investors Service

    CORPORATE OFFICEBuilding No. 8, 2nd Floor, Tower A; DLF Cyber City, Phase II; Gurgaon122002

    Tel.: +(91 124) 4545 300; Fax: +(91 124) 4545 350

    REGISTERED OFFICEKailash Building, 11th Floor; 26, Kasturba Gandhi Marg; New Delhi110001

    Tel.: +(91 11) 2335 7940-50; Fax: +(91 11) 2335 7014, 2335 5293 Email: [email protected] Website: www.icra.in

    Branches: Mumbai: Tel.: + (91 22) 24331046/53/62/74/86/87, Fax: + (91 22) 2433 1390 Chennai: Tel + (9144) 2434 0043/9659/8080, 2433 0724/ 3293/3294, Fax + (91 44) 2434 3663 Kolkata: Tel + (91 33) 22870450, 2240 6617/8839, 2280 0008, Fax + (91 33) 2287 0728 Bangalore: Tel + (91 80) 2559 7401/4049 Fax +(91 80) 559 4065 Ahmedabad: Tel + (91 79) 2658 4924/5049/2008, Fax + (91 79) 2658 4924 Hyderabad:Tel +(91 40) 2373 5061/7251, Fax + (91 40) 2373 5152 Pune: Tel + (91 20) 2552 0194/95/96, Fax + (91 20)2553 9231

    Copyright, 2012, ICRA Limited. All Rights Reserved.

    Contents may be used freely with due acknowledgement to ICRA.

    All information contained herein has been obtained by ICRA from sources believed by it to be accurate and reliable.Although reasonable care has been taken to ensure that the information herein is true, such information is provided asis without any warranty of any kind, and ICRA in particular, makes no representation or warranty, express or implied,as to the accuracy, timeliness or completeness of any such information. All information contained herein must beconstrued solely as statements of opinion, and ICRA shall not be liable for any losses incurred by users from any use of

    this publication or its contents.