Upload
lamhuong
View
216
Download
0
Embed Size (px)
Citation preview
Post Opening Project Evaluation (POPE)
A30 Whiddon Down Junction Improvement (formerly Merrymeet roundabout)
Five Years After Study
© GeoPerspectives
Notice
This document and its contents have been prepared and are intended solely for the Highways Agency’s information and use in relation to the Post Opening Project Evaluation of Major Schemes.
Atkins assumes no responsibility to any other party in respect of or arising out of or in connection with this
document and/or its contents.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final i
Contents
Section Page
Executive Summary ii
1. Introduction 1
2. Traffic 6
Forecast vs. Outturn Traffic volumes 16
3. Safety 21
Further Accident Analysis 26
Security 30
4. Economy 32
Scheme costs 33
Benefits 35
Benefit Cost Ratio (BCR) 39
5. Environment 42
6. Accessibility and Integration 64
7. Conclusions 65
Appendices
Appendix A AST and EST 66
Appendix B : Traffic 69
B.1 Further traffic data 69
Appendix C : Statistical Significance Tests on Safety Data 71
C.1 Significance of Difference in numbers of Accidents and Casualties in before and after periods 71
C.2 Significance of changes in Accident numbers Compared with Control site 72
Appendix D : Environment 74
D.1 Sources 74
D.2 Photographic Record of Scheme Including: ES Photomontages and OYA vs FYA comparisons 76
Appendix E : Glossary 82
Appendix F : Tables and Figures in this Report 85
The maps in this document are reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Highways Agency Licence No. 100030649. Published 2012.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final ii
Executive Summary
Scheme description The A30 / A382 Merrymeet Junction improvement was a Highways Agency Major Scheme in
Devon, which opened in December 2006. The scheme was the replacement of a roundabout
between the A30 dual carriageway and the single carriageways of the A382 and C50 at Whiddon
Down, between Exeter and Okehampton in Devon with a two-level, grade-separated junction.
Specific elements of the scheme included:
A new overbridge crossing the A30, just north of the former roundabout where the trunk road lies in a cutting, providing a good ‘fit’ into the landscape.
Four new merge and diverge lanes providing entry and exit for the A30, and allowing all movements.
A realigned link to the minor road C50, which was the former route of the A30 prior to the dualling of the route in the 1970s.
Measures to reduce the impact of the scheme on the local environment, including new planting, earth mound screening and the significant reduction in the overall level of lighting at the junction.
Since opening, the junction has been renamed to Whiddon Down, the name of the nearby village.
This report is part of the Post Opening Project Evaluation (POPE) commission undertaken on
behalf of the Highways Agency (HA). This report has been prepared based on data at the Five
Years After (FYA) stage.
Objectives
Objectives (from Non-technical Summary and Appraisal Summary Table) Objective
Achieved?
Improve safety at the junction by removing problems particularly associated with A30 traffic stopping at the roundabout, including a high rate of fatalities.
Yes
Reduce congestion occurring at the roundabout at peak times, and during the holiday period.
Yes
Reduce journey times for A30 through traffic. Yes
Retain a full movement junction. Yes
Avoid environmental impact on Dartmoor National Park which lies on the highway boundary.
Yes
Reduce environmental effects as far as practicable. Yes
Key findings A30 through traffic now travels straight through the junction without delays.
Scheme has successfully addressed the problem of the accident cluster at the roundabout.
Environmental mitigation measures are establishing satisfactorily.
Summary of Scheme Impacts
Traffic
Since 2008, the A30 has shown traffic growth, unlike the wider trends which have seen traffic on rural A roads and in Devon having fallen year-on-year since 2007.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final iii
There is a clear underlying trend of traffic growth on the A30 both sides of this junction. The net difference between traffic levels east and west of the junction also shows year-on-year increases since 2008.
In 2011, 32,700 vehicles pass through this junction on an average weekday, an increase of 6% since 2005.
On the non-trunk A road which approaches the junction from Whiddon Down village (the A382) there has been an increase of over 1,000 vehicles per day which reflects the improved access to the trunk road network now provided at this junction. This also includes a 50% increase in the number of Heavy Good Vehicles (HGV).
Turning counts show that around three-quarters of traffic passing this junction is A30 through traffic which benefits from no longer needing to give way at the roundabout and can pass through the junction without needing to slow or stop.
August traffic volumes are the highest of the whole year, due to tourism in Devon and Cornwall. These showed no change in 2011 compared to the period before the scheme was built.
The appraisal of the scheme significantly underestimated the traffic volumes on the A30 in the one year after stage, even assuming high growth.
Five years after opening, the low rate of traffic growth in recent years has meant that observed A30 traffic levels were closer to the forecasts.
Although traffic volumes on the A382 which runs though the village were higher than before the scheme was built, they were close to the high growth forecast level.
Safety
In the post opening period there has been an accident saving of one per year compared with the before period.
A road safety audit suggested that soon after opening, some users experienced problems adapting to the new layout of the junction leading to increased accidents at first. Longer term data from 2008 onwards now shows fewer accidents indicating a successful long-term trend.
Mapping of the accidents shows a cluster at the roundabout before the scheme was built. Accidents on the 0.3 mile short section of the A30 and the junction reduced by 63%, representing a saving of nearly 12 accidents in 4.5 years in the area close to the junction.
No pedestrians or cyclists were injured at this location, either before or after opening.
Observed accident savings at the roundabout were 34% lower than predicted.
Forecasts of fatalities saved through the removal of the roundabout were too high. Later data than that used in the scheme appraisal indicates that although there were a high number of accidents before opening, there was not an unusual severity problem.
Environment
Noise: Traffic flows on the A30 are in line with forecasts and it is assumed that noise due to traffic is as expected. On the A382, numbers of HGVs are 49% higher than before the scheme and noise could be worse than expected for the few properties nearby and for Whiddon Down where no noise impacts were expected as a result of the scheme.
Local Air Quality: Although traffic flows are higher than expected on A382 and A30 east of the junction, overall numbers are low and it is unlikely that they would cause any breach in air quality criteria, especially given the rural nature of the area.
Greenhouse Gases: Negligible increase of 1% additional carbon emissions, similar to forecast.
Landscape: Landscape planting is establishing satisfactorily and subject to ongoing maintenance and management, should reach its longer term objectives for visual screening and landscape integration by the design year of 2021.
Biodiversity: Measures have been taken to reduce the effects of the scheme on protected species and new planting mitigates for the loss of vegetation. Dormice are still present around the junction and are breeding, although at this stage favourable conditions for reptiles to recolonise the habitat areas does not appear to have been achieved.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final iv
Heritage: Archaeological mitigation was undertaken as proposed in the Environmental Statement including recording of historic hedgerows and very little of archaeological interest was found.
Water: Mitigation measures have been incorporated into the scheme in accordance with Environment Agency requirements and based on the information available there is nothing to suggest that they are performing other than as intended.
Journey Ambience: Road users’ views are largely unchanged as expected. Driver stress has benefited by reduced delays and improved journey time reliability for through traffic, particularly during peak holiday times. Signing has been improved since the scheme first opened.
Accessibility
The scheme was not expected to have accessibility benefits.
The overbridge route facilitates a better crossing of the A30 for cyclists and pedestrians than the former roundabout. However, there are few of these users here and there was no formal provision except a footway on the bridge although there is space for future improvements.
Integration
Scheme is consistent with policies in place at the time of its construction and there has been no significant change since, hence evaluation is a beneficial impact due to its contribution toward improving transport links to regeneration areas in Cornwall and North Devon.
Summary of Economic Performance
All monetary figures in 2002 Prices and values
Pre-scheme forecast Outturn FYA reforecast
Journey Times £23.6m £27.3m
Safety £24.7m £7.4m
Indirect Tax1 £1.2m £0.9m
Total Present Value Benefits (PVB) £48.4m £34.6m
Present Value Costs (PVC) £8.6m £9.5m
Benefit Cost Ratio (BCR) 5.6 3.6
1 Indirect tax revenue increased as a result of the scheme hence increasing the benefits based on the current approach
The investment cost of the scheme was £10.8m in 2002 prices, which was substantially higher than the predicted cost of £7.6m, when it was appraised in 2004.
Journey time benefits were higher than expected due to traffic levels on the A30 being higher than forecast, despite the economic downturn.
Safety benefits, which had been expected to comprise half the benefits, were evaluated to be much lower than expected. This is because the forecasts were based on the prediction of a continuing long-term problem of a high number of both accidents and fatalities at the roundabout without the scheme in place. The lower outturn benefits were based on an observed reduction in accident numbers, whereas the forecasting was based on an unrealistically high rate of fatal and serious accidents at the roundabout.
Outturn Benefit Cost Ratio (BCR) was lower than forecast, but at 3.6 still represents high value for money.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 1
1. Introduction
Background to Scheme
1.1 The A30 trunk road runs between Exeter in Devon and Penzance in Cornwall. This report
concerns a Highways Agency scheme to improve one of the last at-grade junctions on the
A30 between Exeter and Okehampton.
1.2 The A30/A382 Merrymeet junction scheme was the upgrading of the existing roundabout
junction to a grade-separated junction where the A30 meets the A382 (a single carriageway)
near Whiddon Down village, just to the north of Dartmoor National Park. The new junction
comprises:
A new overbridge crossing the A30, just north of the former roundabout where the trunk
road lies in a cutting, providing a good ‘fit’ into the landscape;
Four new merge and diverge lanes providing entry and exit for the A30, and allowing all
movements; and
A realigned link to the minor road C50, the former route of the A30, pre dualling in the
1970s.
1.3 Access to Whiddon Down village and Okehampton East Service Area has been maintained.
1.4 The Merrymeet scheme was part of the Highway Agency‘s Targeted Programme of
Improvements (now called Major Schemes) and was fully opened to traffic in December
2006. Since the scheme was constructed the name of it has been changed to the Whiddon
Down Improvement.
1.5 This report is the Five Years After post opening study of the scheme.
Location
1.6 The scheme is located in Devon as shown in Figure 1.1 and is located in Highways Agency
Area 1.
Figure 1.1 – Location of A30 Whiddon Down scheme
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 2
Problems prior to the Scheme
1.7 The scheme’s Appraisal Summary Table (AST) summarised the problems at this junction to
be addressed by the scheme as follows:
This is the only roundabout along the A30 Dual Carriageway between Exeter and Okehampton, requiring drivers to slow down and Give Way. The roundabout has an accident problem and suffers frequent delays, particularly during times of peak holiday traffic.
Objectives of the Scheme
1.8 The main objectives of the scheme were to:
Improve safety at the junction by the removal of the roundabout which had a poor
accident record including a high rate of fatalities and its replacement with a
grade-separated junction with better alignments;
Retain a full movement junction between the A30, A382 and the former route of the A30,
north of the junction, the latter two being part of a national high level route;
Relieve the congestion problems at the junction which occurred at peak times and
holiday periods; and
Reduce journey times for A30 through traffic.
1.9 In addition, the scheme’s Environmental Statement (ES) stated that the scheme objectives
were also to reduce as far as practicable the damage to the environment whilst giving due
weight to road safety, engineering design and cost. In particular, the scheme would:
Minimise landtake;
Avoid the Dartmoor National Park, south of the scheme;
Minimise the impact on the Area of Great Landscape Value, north of the scheme; and
Reduce the overall level of street lighting at the junction, compared to the existing
situation, thus reducing the dusk and nighttime impact of this gateway to the national
park.
Scheme description
1.10 The scheme was the improvement of a junction on the A30 and the changes are summarised
in the maps in Figure 1.2.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 3
Figure 1.2 – Scheme Summary
Before junction improvement After junction improvement
Layo
ut
of
jun
cti
on
Desc
rip
tio
n
Prior to the construction of this scheme, this junction was a four-arm roundabout on the A30 linking with the A382 to the south and a minor road (C50) to the north.
The alignments at the roundabout were:
A30 eastbound approach to the roundabout was uphill;
A30 westbound approach was a right-hand downhill bend;
and
The two minor roads both had a downhill approach to the
roundabout.
The roundabout was first constructed as an intermediate point between the first section of A30 dualling in the late 1970s and the next section west of the junction 10 years later. This allowed for changes in the horizontal and vertical alignments of the two schemes.
The scheme comprises a compact grade-separated junction providing all-movements for A30 traffic comprising:
A new overbridge crossing the A30, just north of the former
roundabout where the trunk road lies in a cutting, providing
a good ‘fit’ into the landscape;
Four new merge and diverge lanes providing entry and exit
for the A30, and allowing all movements;
A realigned link to the minor road C50, the former route of
the A30, pre dualling in the 1970s;
Earth banks and tree planting, providing environmental
mitigation; and
Modern lighting.
Access to Whiddon Down village and Okehampton East Service Area (shown as motel on the OS map above) was maintained.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 4
History
1.11 The key dates in the timeline of the scheme are shown in Figure 1.3.
Figure 1.3 – Scheme Key Events Timeline
1.12 The scheme was awarded the HA major projects award for zero reportable accidents in a
year.
Post Opening Project Evaluation (POPE)
Purpose of this Report
1.13 The Highways Agency (HA) is responsible for improving the strategic highway network
(motorways and trunk roads) in England by delivering the Major Schemes programme
(formerly Targeted Programme of Improvements or TPI). At each key decision stage through
the planning process, schemes are subject to a rigorous appraisal process to provide a
justification for the project’s continued development. When submitting a proposal for a major
transport scheme, the Department for Transport (DfT) specifies that an Appraisal Summary
Table (AST) is produced which records the degree to which the five Central Government
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 5
objectives for Transport (Environment, Safety, Economy, Accessibility and Integration)1 have
been achieved2. The contents of the AST allow judgements to be made about the overall
value for money of the scheme. The AST for this scheme is presented in Table A.1 of this
report.
Overview of POPE
1.14 POPE studies are undertaken for all Major Schemes. During the planning process, scheme
effects are based on well informed predictions. However, it is vital to identify the strengths
and weaknesses in the techniques used for appraising schemes so that improvements can
be made in the future. For POPE, this is achieved by comparing information collected before
and after a scheme opens to traffic, with predictions made during the planning process.
Outturn impacts are summarised in an Evaluation Summary Table (EST). The EST
summarises the extent to which the scheme objectives have been achieved and the EST for
this scheme is included in Table A.2 of this report.
Sources
1.15 This study is based on the following sources:
Traffic counts and journey times from the Highways Agency’s TRADS and HATRIS
databases;
Traffic surveys commissioned for this study;
Accident records obtained from Managing Agent Contractor (MAC);
Road Safety Audits of the scheme;
A site visits by a transport planner and a landscape architect; and
Reports appraising the scheme, prior to construction;
- A30 Merrymeet Junction Improvement Report of Surveys and Local Model Validation
Report June 2004;
- A30 Merrymeet Junction Improvement Forecasting and Economic Assessment
Report, November 2004;
- Environmental Statement, 2005; and
- Appraisal Summary Table (from Scheme Assessment Report), January 2003.
1.16 Details of the sources for the environmental evaluation are given in Appendix D.2.
1 Objectives at the time this scheme was appraised were defined by the New Approach to Appraisal (NATA)
2 From April 2011, this approach was revised, however POPE is concerned with evaluation against the
appraisal and as such follows the objectives used at that time.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 6
2. Traffic
Introduction
2.1 In order to assess the traffic impact of the scheme, the following section reports on:
Long term traffic volume trends on the A30 in this area;
Flows on the A30 and the surrounding road network;
Turning movements at the junction;
Comparison of forecast and observed traffic volumes and
Journey times.
Data sources
Timing of Data Collection
2.2 Traffic data was collected for the A30 and other roads close to the location of the junction for
the following time periods:
May 2004/5, March 2005 – before construction started
March/April 2008 – one year after scheme opening (OYA)
March 2012 – five years after (FYA)
August 2004, 2007 and 2011 – to study the summer congestion
2.3 Although the scheme opened in December 2006, the ‘one year after’ data was collected for
April 2008 because the winter period has untypical traffic flows. Tourism is important to the
economy of Devon and Cornwall and has significant impacts on the traffic flows on this part
of the A30. As shown later, there are no true traffic neutral months here. Thus traffic figures
presented have been carefully factored to given annual average and are based on dates
which avoid the Easter period3.
2.4 The A30 in Devon is an important holiday route so data has also been collected for August
which is the busiest period of the year on this road.
Sources of Data
2.5 Observed traffic flow data was obtained from:
Highways Agency’s TRADS database– permanent counts on the A30 for the whole
period, as detailed in Appendix B;
A30 Merrymeet Junction Improvement Report of Surveys and Local Model Validation
Report (LMVR) – source of ‘Before’ data for traffic flows on the minor roads, the before
turning count and the forecast traffic flows;
Temporary surveys on minor roads commissioned for this study:
3 Easter fell in late March in 2005 and 2008 so the OYA before and after data was based on April data, but
as Easter 2012 was in April in 2012, for this FYA study we have used data from the early part of March for A30 data for all these years which has then been annualised.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 7
- Temporary traffic counts on the non-trunk roads in the one and five years after
periods; and
- Manual Classified turning counts at the new junction.
2.6 Forecasts of traffic volumes were obtained from the Forecasting & Economic Assessment
Report (2004). As this scheme was considered to be a straightforward safety upgrade, the
modelling of both the traffic and economic aspects were combined into that single report.
National and Regional Trends in traffic
2.7 Before looking at the traffic impacts of the scheme, it is useful to consider the wider context of
the background of the growth a recent decline in traffic levels on a national and regional basis
According to Office for National Statistics figures, the UK the economy entered recession in
the second half of 2008.
2.8 The wider traffic trends over the past decade are summarised in Figure 2.1 and Figure 2.2
based on published DfT data4 compared against changes in Annual Average Daily Traffic
(AADT) on the A30 east of the scheme since 2003. Note that the variation in A30 AADT in
these graphs is presented here proportionate to the traffic indices.
Figure 2.1 – National and Regional Traffic Trends compared with A30 traffic
2.9 This trend graph shows the following key points regarding wider traffic trends and the A30:
There has been a decline in traffic since 2008 both nationally and in the region and
county which include this scheme.
4 Table TRA8904a Estimated traffic volume for all motor vehicles by region/country: Great Britain: 1993 -
2010 (kilometres), and Table TRA2507 Road traffic in Great Britain by road class: Index numbers (kilometres). These have been used to create indices of growth in traffic since 2000.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 8
On the A30 east of this scheme, traffic flows have continued to grow year-on-year since
2008. Given the importance of tourism in this area, it is likely that trends affecting this
part of the economy during this period are an important driving force behind changes in
A30 traffic levels.
Figure 2.2 – National Traffic Trends by Road Type: Rural roads compared with A30 traffic
2.10 This shows how traffic trends on the A30 differ from national trends for roads in rural areas:
Since 2008, the A30 has shown traffic growth, unlike the wider trend which saw traffic on
rural A roads having fallen year-on-year since 2007.
The pattern on minor rural roads is less clear.
2.11 Permanent count sites on the A30 provide long-term data in this area since 2005. This data
has been used to analyse the trend in two-way daily traffic by month as illustrated in Figure
2.3.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 9
Figure 2.3 – Trends on A30 east and west of the junction-by month
2.12 The key points shown here are:
This highlights the extreme seasonality of the traffic flows, with the maximum daily traffic
occurring in August being double the minimum in January. This pattern is consistent for
every year since 2005.
Traffic flows were not impacted by the construction period, despite it being online. This
shows that the disruption during that period was relatively minor for A30 traffic and was
not sufficient to lead to rerouting to the only reasonable alternative of the A38, south of
Dartmoor.
2.13 The extreme variation by month seen in Figure 2.3 obscures traffic growth during this period,
thus we have also looked at the annual figures. Figure 2.4 shows the AADT where there is a
full 12 months of data for the years from 2003 to 2011.
Figure 2.4 – AADT Yearly Trends on A30 east and west from 2003
2.14 Once the seasonal effect is removed, we can see:
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 10
There is a clear underlying trend of traffic growth on the A30 both sides of this junction in
the period between the start of construction in late 2005 and 2011.
Most years show growth compared with the previous year.
In 2006, when this scheme was under construction, traffic was reduced which may be
partially due to some rerouting due to delays during construction, but given that the only
alternative strategic routes are either lengthy (in the case of the A38 east of Dartmoor) or
far from straightforward (via non-trunk single carriageway A roads).
Traffic Volumes at locations around the junction
2.15 Traffic volumes on the four arms of the junction before the start of construction then one year
after and five years after opening are shown in Table 2.1 and mapped in Figure 2.5. The
figures presented here are for weekdays (annual average weekday traffic, AAWT) but due to
the importance to tourism-related traffic flows in this area, the 7-day average flows are very
similar. The equivalent AADT flows are shown in the appendix in Table B.2.
2.16 The data for the A30 is taken from Automatic Traffic Count (ATC) data from the first two
weeks of March for the years 2005, 2008 and 2012. This omits the impact of the Easter
school holiday period in all three years.
Table 2.1 – Average Weekday Traffic volumes around the Junction
Location
Average Weekday Traffic (AAWT) % change
Before One Year
After Five Years
After One Year
After Five Years
After
A30 east of jct 28,600 29,600 30,200 4% 6%
A30 west of jct 25,000 26,300 26,400 5% 6%
A382 west of jct 6,400* 6,600 7,500 3% 17%
Minor rd 1,400* 1,100 1,200 -18% -10%
Total Throughput 34,500 35,800 36,800 4% 6%
* AWT before data for the A382 and the minor road are estimates based on the 12hour manual count
taken in May 2004
2.17 For the minor roads the daily figure for before construction is an estimate based a manual
count undertaken in May 2004. The after period counts are based on ATCs from April 2008
and March 2012, excluding the Easter holiday period. All data is factored to give annual
averages.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 11
Figure 2.5 – Weekday Traffic volumes and Total Flow through Junction
2.18 The key points shown in Table 2.1 and mapped in Figure 2.5 are
On weekdays 32,700 vehicles pass this junction, primarily on the A30 trunk road.
Traffic has increased by 6% since 2005
On the A382 which approaches the junction from Whiddon Down there has been an
increase of over 1,000 vehicles per day which reflects the improved access to the trunk
road network now provided at this junction.
The unclassified minor road north of the junction still has relatively low flows.
Turning Movements at the Junction
2.19 Manual turning counts were undertaken at the roundabout before the scheme construction on
weekdays 5th May 2004 and at the new junction one year after opening on 29
th April 2008
and five years after on 27th March 2012. All counts were taken over a 12 hour period from
07:00 to 19:00. Note that these surveys are based on a single day’s observations and are
therefore potentially less representative than the traffic counts presented elsewhere in this
report.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 12
2.20 The results of the surveys are summarised in Table 2.2 and Table 2.3.
Table 2.2 – 12 Hour Traffic movements at junction
Survey year
A30 east of jct A30 west of jct A382 west of
junction
Unclassified minor road east of
junction
Entering A30
towards Exeter
Exiting A30 from
Exeter direction
Entering A30 towards
Okeham.
Exit A30 from
Okeham.
Towards jct
Away from jct
To jct Away
from jct
2004 1,670 1,770 780 770 2,660 2,500 570 640
2008 1,680 1,800 950 690 2,590 2,720 490 500
Change 0% 2% 22% -11% -2% 9% -14% -22%
2012 1,700 1,730 1,010 740 2,630 2,820 470 500
Change 2% -2% 23% -4% -1% 11% -21% -29%
Table 2.3 – Total 12 hour Traffic flows using junction
Survey year Total entering or exiting the A30
Traffic crossing A30 (between A382-
minor road)
A30 through traffic (passing straight
through jct)5
2004 4,990 690 15,790
2008 5,120 830 over 16,000
Change 3% 21%
2012 5,190 1,010 over 17,000
Change 4% 46%
2.21 The key points from the junction movement details are:
Around 5,000 vehicles enter or exit the A30 trunk road from the local road network at this
junction during the daytime.
Most of this traffic enters or exits the A30 in the direction of Exeter.
The movements to and from the A30 show little change since the scheme was opened.
Traffic crossing over the A30 between the A382 and the unclassified road east of the
junction whilst comprising only a small proportion of traffic using the junction shows a
sharp rise. This is possibly due to this traffic making this movement benefiting from
using the new overbridge rather than needing to cross the A30 traffic at the roundabout
as previously.
Around three-quarters of traffic passing this junction is A30 through traffic which benefits
from no longer needing to give way at the roundabout and can pass through the junction
without needing to slow or stop.
5 Post opening data approximated TRADS data west of junction and turning count data for traffic
entering/exiting from the west.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 13
August Traffic on the A30
2.22 Tourism is an important part of the economy of North Devon and Cornwall and this is
recognised as having a large impact on traffic flows on the A30, particularly on the seasonal
variation.
2.23 The yearly trend analysis in the previous section shows that traffic volumes on the A30 are
much higher during August than any other month of the year. Figure 2.6 shows the daily
traffic volumes in August before and after the scheme opened at the count location on the
A30 near Okehampton, west of the scheme.
Figure 2.6 – August traffic volumes by day of week, by direction, west of jct
2.24 The key points from these August traffic bar charts are:
In August, the highest daily traffic flows in this section of the A30 occur on Fridays and
Saturdays.
The spread of traffic flows across the week and by direction clearly reflects the high level
of tourist traffic in which :
- Weekend traffic (including Fridays) is higher than weekdays; and
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 14
- Traffic tidality patterns show that westbound traffic, i.e. including the outgoing trips
towards holiday locations, is concentrated on Fridays and Saturdays, while the return
trips for these users although again mainly focussed on Fridays and the weekend, is
slightly more spread through the week.
August Saturday traffic shows the highest daily volumes at over 50,000 vehicles daily,
although this is slightly lower than before opening.
There has been negligible change in the overall August daily traffic volumes on the A30
between the before OYA and FYA periods.
Heavy Goods Vehicles (HGVs)
2.25 Traffic volume data on the A30 in TRADS also includes data classified by vehicle length. In
2007, this database recorded vehicles less than or greater than 5.2m (18ft) in length so this
criterion has also been used for 2011 data.
2.26 Figure 2.7 summarises the numbers of HGVs and what proportion they form of all traffic on
the A30 and is based on March data, excluding the holiday periods.
Figure 2.7 – Average Weekday HGVs on A30
2.27 This shows that the absolute number of HGVs on the A30 east and west of the scheme
increased between 2005 and 2012, but the proportion they form of all traffic remained steady
at just above 20%.
2.28 HGV data for the other roads at the junction, the A382 and the minor road is based on a
midweek day’s manual classified count in May 2004 and automatic traffic count in March
2012. These are goods vehicles (OGV1 and OGV2), buses and articulated vehicles. The
results are shown in Table 2.4.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 15
Table 2.4 – Average Weekday HGV daily flow on non-trunk roads
Location Before FYA % difference
A30 east of jct 4,950 5,250 6%
A30 west of jct 4,500 4,750 6%
A382 west of jct 600 890 49%
Minor rd 110 130 18%
2.29 This shows that:
Although growth in the number of HGVs on the A30 is in line with general traffic growth
on the trunk road, there is much greater growth on the two other roads.
While the numbers on the minor road are still low and the increase may be explained by
the limitations of the one day count before, the A382 results do show clear evidence of
increased HGV traffic using that road to access the A30 at the improved junction.
Journey Time Analysis
2.30 This sub-section examines the evidence on the impact of the scheme on journey times
around the junction. Normally the POPE evaluation of this is based upon observed journey
times before and after the scheme opened. However, for this scheme this has not been done
because:
There were no journey time surveys undertaken as a part of the modelling work for
scheme’s appraisal6.
The scheme was completed under Early Contractor Involvement (ECI) which resulted in
it progressing quickly from entering the orders being made to start of construction.
Unfortunately for the purpose of this study, the speed of progression of the scheme
meant that the opportunity to undertake journey times surveys before the start of online
construction work was missed.
As observed earlier, due to the importance of tourism in the area, the daily traffic flows
on the A30 show a very wide variation seasonally and within the same month. As
congestion is clearly related to traffic flows, it is considered that there would be serious
limitations in using journey time data based solely on moving observer surveys on single
days as being representative of the whole or even most of the year.
Limited journey time data for this part of the A30 is currently available for the period
before 2007.
The nearest TRADS site with any period speed data is a mile west of the scheme which
is too far to be able to detect any impact of the improvements at the junction on any
normal conditions.
Inferred benefits:
A30 through traffic should experience improved journey times through the removal of
congestion at peak times and at all times of day through the removal of the need to slow
down for the manoeuvre around the roundabout rather than drive in a straight line. This
is known as geometric delay and occurs irrespective of whether there are any other
vehicles using the roundabout at the time.
6 There is nothing in either the F&EAR or the Report of Surveys and Local Model Validation Report,
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 16
2.31 The POPE evaluation of the impacts on journey times has been based on modelling using
COBA (Cost Benefit Analysis) combined with observed traffic flows. The monetised impacts
of the changes in journey times are detailed in the economy section.
Forecast vs. Outturn Traffic volumes 2.32 Forecast traffic volumes was detailed in the Forecasting and Economic Assessment Report
(T&EAR, November 2004) and the basis of the modelling is detailed in the Report of Surveys
and Local Model Validation Report (June 2004). Forecast of the traffic flows were presented
in detail for the following scenarios and years:
2003 Base Year
2006 Opening Year Do Nothing, low, central and high growth
2006 Opening Year Do Something, low, central and high growth
2021 Design Year Do Nothing, low, central and high growth
2021 Design Year Do Something, low, central and high growth
2.33 Table 2.5 compares the opening year Do Nothing and Do Something forecast traffic volumes
with the observed traffic. As almost all the forecasts were underestimates, only the figures
for high growth (HG) have been shown in this table.
2.34 The Forecasting report states that due to the lack of route choice in the model, future traffic
flows are identical for all roads in the Do Nothing and Do Something scenarios, i.e. it has
been assumed that no reassignment into the corridor or induced traffic will occur.
2.35 Forecast figures for OYA 2008 and FYA 2012 have been proxied based on interpolation
between the 2006 and 2021 forecasts. Flows are shown for traffic in east direction i.e.
eastbound (EB) and westbound (WB).
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 17
Table 2.5 – Post opening: Forecasts vs. Observed traffic volumes (AADT)
Location
Do Nothing
(HG) (2006)
Before Flows
Observed(2005) % diff.
One Year After (2008) Five Years After (2012)
Forecast (HG) Observed % diff. Forecast (HG) Observed % diff.
A30 East of jct
WB 11,000 14,700 34% 11,500 14,700 28% 12,300 15,300 24%
EB 13,600 14,100 4% 14,200 14,700 3% 15,500 15,000 -3%
two-way
24,600 28,800 17% 25,700 29,400 14% 27,800 30,200 9%
A30 West of jct
WB 10,400 12,700 22% 10,800 13,200 23% 11,600 13,300 14%
EB 12,700 12,600 1% 13,300 13,100 -1% 14,500 13,300 -8%
two-way
23,100 25,400 10% 24,100 26,300 9% 26,100 26,600 2%
A382 Whiddon Down
N/A N/A N/A 6,700 6,300 -6% 7,200 7,400 3%
Minor rd north of jct
N/A N/A N/A 1,300 1,000 -23% 1,400 1,200 -14%
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 18
2.36 The key points regarding the comparison of the forecast flows against the observed data are:
This clearly shows that the appraisal significantly underestimated the traffic levels on the
A30 in the one year after, even in the high growth scenario.
Five years after opening, the low rate of traffic growth in recent years has meant that
traffic levels are closer to the high growth forecasts.
A30 forecast flows shows a noticeable imbalance in the flows split by direction unlike the
observed data which shows that flows are fairly evenly split by direction as would be
expected in this location where the are no local alternative routes of the same standard.
A comparison of the Do Nothing forecasts and the Before traffic volumes shows that the
differences between these volumes are very similar to the differences between Do
Something forecasts and observed traffic volumes. Therefore, the inaccuracy of the
forecasts is due to an inaccurate Base model rather than errors in the way the scheme
itself was modelled.
Traffic on the two local roads is close to the predicted levels.
Why did the forecast underestimate traffic?
2.37 In 2004, when the scheme was appraised, there were no permanent counts in the immediate
area around the scheme, even on the trunk road; the nearest counter on the A30 was near
Exeter Tedburn St Mary, 21km east of the roundabout7. Between that location and
Merrymeet, there is a grade-separated junction with the C50 road known as Woodleigh.
2.38 To develop the model for the Merrymeet scheme, 12 hour manual classified counts (MCC)
were undertaken at the roundabout and the junctions in Whiddon Down village between 2002
and 2004. The data from the permanent count at Tedburn was used to develop conversion
factors for the MCC data.
2.39 An analysis of how the MCC data was used to create the forecast suggests the following
weaknesses:
Count data from 12 hours on single Wednesday in May 2004 was the basis for
calculating the A30 flows through the junction. As shown in Figure 2.3, this road has a
very seasonal pattern of traffic strongly indicating to the significance of tourism to traffic
flows on the A30. It could easily be the case that the selected day was untypical and 12
hours was insufficient to adequately model 24 hours flows. This is judged to be the more
likely explanation for the underestimation;
The calculated base year (2003) AADT east of Merrymeet used in the model is 21,829
compared to the observed AADT of 28,189 at Tedburn. The main reason for considering
this to be unlikely is that this would require over 6,000 vehicles accessing/egressing the
A30 from the minor roads at Woodleigh junction and Fingle Glen.
The base flows used in the model have northbound flows as 18% lower than southbound
whereas the observed data shows that the difference is less than 1% which is what
would be expected given the lack of alternative long-distance routes along the corridor.
This discrepancy could indicate the limitation of using only 12 hour flows or possibly a
weakness in the data collection and processing. Examination of the data suggests that
the figures for southbound traffic west of the junction and northbound traffic east of the
junction could have mixed up during data processing.
7 The TRADS site used is 608 and named as Tedburn St Mary, although it is not close to that village.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 19
2.40 It is worth noting that although the traffic forecasting report and scheme modelled only
concerns the annual average daily traffic based on the May survey, that data was also
collected for a day in August for use in the Environment Statement, as shown in the
Environment evaluation in section 5. In the case of the August data, it seems that the
opening year daily traffic was accurate.
2.41 The 12h MCC data from May was converted to a 24 hour annual figures using DMRB
methodology to create factors based on permanent data from the Tedburn site8. The nature
of the seasonality of traffic flows on the A30 at Whiddon down junction as shown earlier,
means that there may have been a problem with the seasonality factoring, but checks against
2008 data shows that the factoring used is still valid9.
Reliability - route stress
2.42 The AST stated that driver stress would remain at 28% in the do minimum and do something
scenarios. The basis for this is unclear. Route stress is a metric defined in the standard
guidance in DMRB which provides a proxy measurement for reliability and is in the range
75% to 125% where 75% is the lowest possible measurement.
2.43 Removal of the roundabout will have reduced the geometric delay and congestion delay at
peak times for the through traffic which forms the majority of vehicles at this location. This
has improved A30 reliability, particularly in the peak periods in the year.
2.44 Traffic making right turns on or off the A30 and traffic crossing over the A30 will also benefit
from improved reliability in peak periods.
8 DMRB gives: Seasonality Index = Average August 2003 Weekday 24-Hour Flow
Average Neutral Month 2003 Weekday 24-Hour Flow 9 In the case of this case of this scheme appraisal, the neutral months were considered to be April, May,
June, September and October.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 20
Key findings from section 2: Traffic
Traffic volumes
Since 2008, the A30 has shown traffic growth, unlike the wider trends which have seen
traffic in Devon and on rural A roads nationally having fallen year-on-year since 2007.
There is a clear underlying trend of traffic growth on the A30 both sides of this junction.
On weekdays 32,700 vehicles pass this junction, an increase of 6% since 2005.
On the A382 which approaches the junction from Whiddon Down village there has
been an increase of over 1,000 vehicles per day which reflects the improved access to
the trunk road network now provided at this junction. This also includes an increase in
HGV numbers of nearly 50%.
Turning counts show that around three-quarters of traffic passing this junction is A30
through traffic which benefits from no longer needing to give way at the roundabout
and can pass through the junction without needing to slow or stop.
August traffic volumes are the highest of the whole year, due to the importance of
tourism to the economy of Devon and Cornwall. These have shown no change in 2011
compared with before the scheme was built.
Forecasting
Scheme appraisal significantly underestimated the average traffic levels on the A30 in
the one year after stage, even in the high growth scenario.
Five years after opening, the low rate of traffic growth in recent years compared to the
forecast has meant that A30 traffic levels are now closer to the forecasts.
Although traffic on the A382 which runs though the village is now higher than before
the scheme was built, it is close to the high growth forecast level.
Journey Times
It was not possible to confirm changes in journey times based on observed data.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 21
3. Safety
Introduction
3.1 This section presents an evaluation of how the scheme is performing against the NATA
safety objective. WebTAG states that this objective is:
To reduce the loss of life, injuries and damage to property resulting from transport accidents and crime
3.2 The Safety Objective has two sub-objectives:
To reduce accidents; and
To improve security.
Sources
3.3 The evaluation of the safety impacts in this section is based on the following sources:
Data on Personal injury accidents (also known as collisions)
STATS19 data from the Area 1 MAC.
3.4 The accident data is based on the records of personal injury accidents recorded in the
STATS19 form collected by the police when attending accidents. The accident data referred
to in this report has not necessarily been derived from the nationally validated accident
statistics produced by the DfT. As such, the data may subsequently be found to be
incomplete or contain inaccuracies. The requirement for up-to-date information and site
specific data was a consideration in the decision to use unvalidated data and, as it is sourced
from Local Processing Units, it is sufficiently robust for use in this report.
3.5 As the numbers of accidents here is fairly low, we have also obtained records of damage-only
accidents where the police attended. These are known to represent only a minority of such
accidents, but are of interest in giving further evidence of trends.
Forecasts of the safety impact
COBA models of low and high growth scenarios (2005)
Further investigations
Road Safety Audits for Stages 1, 2, 3 and 4a and b.
Study Area
3.6 The safety impact of the scheme (together with the economic impact) was modelled in the
DfT’s Cost Benefit Appraisal Program (COBA) for a short section of the A30 and a small
network of the roads including the A382 and A3124. This model forecast no changes to the
accident numbers on the non-trunk roads beyond the vicinity of the junction so for this study
we have focussed solely on the A30 and the junction which covers the overwhelming majority
of the traffic movements, and omits the small number of accidents directly within Whiddon
Down, which are most likely to be linked to factors unconnected with the changes to the
junction.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 22
Accident data before construction and after opening
3.7 STATS19 data was obtained for the following periods:
Five years before start of construction: November 2000 – October 2005
Four years and six months after full opening: January 2007 – June 2011
Normally for an FYA study, we would use five full years of data for the post opening period,
but this data was not yet available at the time of this analysis (June 2012).
Accidents and casualty numbers
3.8 These sub-sections analyse the numbers of accidents and casualties in the periods before
and after construction of this scheme. This is based on the STATS19 data. Results here
have also been subjected to statistical significance testing which is detailed in Appendix C,
and the findings are included in the analysis presented here.
3.9 Table 3.1 provides a summary of the number of personal injury accidents within the key
network of roads in the area used in the modelling of the scheme broken down into yearly
periods by severity. Accidents are categorised by the severity of the injury to the worst
casualty resulting from the accident. In the case of this data, no fatal accidents were
recorded.
3.10 As the post opening period is slightly shorter, the savings have been adjusted to allow for
this.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 23
Table 3.1 – Number of Personal Injury Accidents (2km/1.2 mile section centred on Whiddon Down)
Accidents by Severity and 12 month periods
Accident and casualty totals
Category
5 years before
(2000 – 2005)
4.5 years after
(2007 – 2011) 4.5 year saving
total annual total annual total annual
Personal Injury Accidents 26 5.2 20 4.4 3.4 0.8 (15%)
Casualties 38 7.6 30 6.7 4.2 0.9 (12%)
All accidents 60 12.0 34 7.6 20.0 4.4 (37%)
Accident and casualty totals – ignoring first post opening year
Category
5 years before
(2000 – 2005)
3.5 years after
(2008 – 2011) 3.5 year saving
total annual total annual
Personal Injury Accidents 26 5.2 9 2.6 9.2 2.6 (51%)
Casualties 38 7.6 15 4.3 11.6 3.3 (44%)
All accidents 60 12.0 15 4.3 27.0 7.7 (64%)
3.11 The following conclusions can be drawn from the data in Table 3.1.
4.5 years after opening, the numbers of injury accidents and casualties was reduced
compared with the period before (15% and 12%).
The trend in the post opening period is distorted by the first 12 months after opening,
which showed an unusually high level of accidents, compared with the five years before
and the subsequent period in the post opening period. This suggests that a small
minority of drivers were failing to understand the revised road layout. This finding was
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 24
also noted in the first post opening Road Safety Audit (RSA stage 3) which identified a
particular concern that some A382 eastbound drivers appeared to be undertaking unsafe
manoeuvres having missed the junction for the A30 to Exeter, as shown later in this
section. Following the audit, road signing changes were implemented to address the
RSA recommendations.
From 2008 onwards, the annual personal injury accident rate has halved since the five
years before, giving an annual saving of 2.6. Casualties show a similar trend.
Only one serious accident and no fatalities were recorded during the before period,
giving an accident severity level of 5%. All injury accidents in the after period were
slight; hence, all that can be concluded regarding the severity of accidents following the
completion of this scheme is that there is no evidence of a particular problem with
accident severity here.
3.12 We have also looked at a narrower section, centred on 250m of the A30 either side of the
junction. The results are summarised in Table 3.2. All injury accidents in this area were
categorised as slight.
Table 3.2 – Number of Personal Injury Accidents (0.5km/0.3 mile section centred on Whiddon Down)
Accident and casualty totals
Category
5 years before
(2000 – 2005)
4.5 years after
(2007 – 2011) 4.5 year saving
total annual total annual total annual
Personal Injury Accidents 21 4.2 7 1.6 11.9 2.6 (63%)
Casualties 31 6.2 9 2.0 18.9 4.2 (68%)
All accidents 46 9.2 13 2.9 28.4 6.3 (69%)
3.13 The following conclusions can be drawn from the data in Table 3.2.
In this area around the junction, there are clear reductions of around two-thirds for injury
accidents and casualties.
Saving for all accidents, including damage only, shows the same trend.
Compared with the reduction in accidents and casualties noted in Table 3.1, there is a
much greater impact at the junction. This is due to the accident cluster which existed at
the former roundabout, as shown in the following sub-section.
Locations of accidents within scheme area
3.14 Figure 3.1 shows the locations and severity of the accidents on the section of the A30 and
junction as tabulated in Table 3.1 and Table 3.2. The area indicated by the dashed line is the
0.5km/0.3 mile zone around the junction. It should be noted that a number of accidents
occurred at the same locations, so these maps can only show an indication of the spatial
distribution of accidents.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 25
Figure 3.1 – Locations of Personal Injury Accidents 2km/1.2miles and 0.5km/0.3miles around junction
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 26
3.15 The key points shown by these maps is:
The before period showed a clear cluster of accidents at the roundabout.
After completion of the new junction, there were no injury accidents on the overbridge
and only a few at the diverges and merges with the A30. This is a clear improvement
compared with the number recorded at the former roundabout.
On the A30 beyond the area immediately around the junction (0.5km), the maps show
more accidents in the after period than before but no particular clusters. Hence it is likely
to be as a result of the random variation of accidents numbers.
Vulnerable User casualties
3.16 There are few pedestrians, cyclists, and equestrians users of this junction. The collision data
recorded no casualties who were any of these classes of user in either the before or after
time periods.
Further Accident Analysis
Accident Rate Analysis
Accident Rate for A30 improved by scheme compared to National Average
3.17 The number of accidents along a length of road together with its AADT (Annual Average
Daily Traffic) can be used to calculate an accident rate, known as PIA/mvkm (Personal Injury
Accident per million vehicle kilometres). The purpose of measuring the rate is that:
It allows for a change in traffic flows, which is of particular importance when traffic has
increased significantly over the time period under consideration.
It enables comparison between different sections of the A30.
It enables comparison with national average rates both expected and observed.
3.18 Table 3.3 shows the accident rates calculated for the sections of A30 before and after the
scheme, based on average AADTs on the sections over the time periods concerned. The
national average is for an older two-lane dual carriageway, based on data used in COBA is
also shown for the years 2001 and 2009, representing the mid-point years of the before and
after periods. Woodleigh is included here as a control site, as it is a similar standard of road
through a rural area.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 27
Table 3.3 – Accident Rate Five Years Before and After compared to National Average
Section
Period
before:’00-‘05
after:’07-‘11
Length (km)
total PIA Accident
Rate (PIA/mvkm)
2km around Whiddon Down Before
2
26 0.269
After 20 0.218
After (3.5 yrs) 9 0.098
0.5km around Whiddon Down Before 0.5
21 0.869
After 7 0.305
Control area
A30 Woodleigh junction (2km)
Before 2
7 0.068
After 5 0.052
Expected National Average PIA/mvkm for modern dual carriageway no hardshoulder
1
2003 0.160
2009 0.136
Observed national average for rural A roads
2
2009 0.202
1 Based on DMRB Vol 13, Section 1, Part 2, Chapter 4, Table 4/1 ‘link and junction combined’ modern means post 1980
2 Based on DfT data for GB at data.gov.uk/dataset/road-accidents-safety-data/
3.19 The key points to note from Table 3.3 are:
The accident rate on the A30 around Whiddon Down reduced after the completion of this
scheme, and this is most evident in years 2 to 5.
In the narrow area focussed on the junction, the before accident rate was high due to the
roundabout and has dropped by two-thirds in the post opening period.
Compared with the national average, the A30 around the junction has an accident rate
that is now largely as expected, and is clearly better than the worse than normal rate
seen before the scheme was built.
Statistical Analysis
3.20 Appendix C details the statistical tests on the accident and casualty data. The key results
are:
Within 0.5km of the junction there is a statistically significant reduction in numbers of
injury accidents and casualties compared to the period before.
Comparing this section of the A30 including the roundabout with a section of the A30
where there was no junction improvement, there was a greater reduction in accident
numbers over the same period, but this is not statistically significant.
Road Safety Audits
3.21 Post opening road safety audits were undertaken for Stages 3, 4a and 4b (12 months and 36
months after opening).
3.22 The initial post opening study identified the following problems:
Evidence of vehicles overshooting at the end of both A30 diverges.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 28
Some A382 eastbound drivers undertaking unsafe manoeuvres, having missed the
junction for the A30 to Exeter (i.e. eastbound traffic) which uses the overbridge.
3.23 The implementation of remedial signing schemes was recommended in the RSA Stage 3 and
these had been carried out by the time of the Stage 4a and b audits.
3.24 The Stage 4a 12 months after report stated that the collision data suggested that users had
familiarised themselves with the new junction layout but at that time it was too early to make
firm conclusions.
3.25 Three years after opening, the 36 month audit (Stage 4b) found that although there was
some evidence of vehicles colliding with the kerbline, the collision data showed a significant
reduction in accidents with none having occurred at the junction in two years. It concluded
that:
Due to the significant reduction in collisions and the fact that none have occurred in the final two year period of this review, it is recommended that no further monitoring is required at this junction. If further collision problems arise in the future this would appear as a cluster site in the yearly review of collision data.
Forecast vs. Observed Accident Saving
3.26 Details of the modelling for the accident saving is contained within the COBA model produced
for the economic appraisal. The model covered the A30 and a small network of roads and it
predicted both the economic impact of the accident savings and the underlying forecasts of
the numbers of accidents and casualties both with and without the scheme in the opening
year, design year and over the whole appraisal period under forecasts of high and low growth
of both traffic and the economy.
3.27 COBA produces forecasts of the annual savings of accidents in the opening year and the
design year, the 15th year after opening. As shown in Table 3.4, the midpoint between the
low and high growth savings forecasts for these two years is very close, and there is also little
change between the opening year and design year savings. Hence the midpoint provides a
valid annual forecast to compare with the observed average annual saving in the first five
years.
Table 3.4 – Forecast Personal Injury Accident savings
Period Category Low growth High growth Mid-point
2007 (forecast opening year)
Links 0.3 0.3 4.0
Junctions 3.6 3.7
2021 (forecast design year)
Links 0.0 0.0 4.4
Junctions 3.9 4.8
60 years All 243 (including 18
fatalities) 287 (including 21
fatalities) 265
3.28 From Table 3.4, we take the expected saving in the first five years to be 4.2 annually. This is
compared with observed savings in Table 3.5.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 29
Table 3.5 – Forecast vs. Outturn Accident savings
Source Definition Period Annual saving
Forecast Modelled area Average midpoint saving for first 5 years
4.2
Observed
Junction and 2km section
Opening year -5.8
First 4.5 years 0.8
3.5 years after opening year
2.6
Junction and 0.5km section of A30
4.5 years 2.6
3.29 This comparison of the accuracy of the forecasts shows:
In the opening year, the spike in the number of accidents, as shown in Table 3.1, means
that at the OYA stage there was a negative impact.
Now with nearly five years of post-opening data, we can see positive benefits in terms of
accident savings are evident from the second year onwards, and when considering the
area immediately closest to the junction, although this saving is still 34% less than
expected.
As there were no fatalities and only a single serious accident in the time period analysed,
the observed data since late 2000 suggests that the forecast of the numbers of fatalities
saved by this scheme was incorrect.
Further investigation of forecasting
Numbers of PIAs
3.30 Accident benefits (and disbenefits) are modelled in detail by link and node. An examination
of the model’s detailed results showed all the benefits were from the removal of the
roundabout node. The small disbenefits from the new overbridge and associated links and
nodes were clearly outweighed by the removal the roundabout and former approach links.
3.31 As the model forecast the same traffic levels in both the Do Minimum and Do Something
scenarios, we would not expect any changes in the wider area.
3.32 Hence the most meaningful comparison of before accidents with observed saving at five
years after is based on the short section of 0.5km centred around the junction which captures
the majority of the modelled impacts. Our observed finding of 2.6 accidents saved compared
with a forecast of 4.2 shows at the FYA stage shows that the safety impact is one-third lower
than forecast.
Severity
3.33 Safety modelling in COBA used observed accident rates numbers, as is the usual approach.
Unusually, it also took into account atypically high levels of fatal and serious accidents. This
was based on observed data for the five years prior to the appraisal. The Scheme
Assessment Report noted that Personal Injury Accident data for the period 1998 to 2002
showed 20 accidents in the vicinity of the roundabout of which 10% were fatal, while the
Report of Surveys and LMVR showed the data on which the modelling was based on
included 3 fatalities which occurred in 1998 on the A30, two of which were at the roundabout.
On this basis, the modelling included non-default levels casualties per accident at the
roundabout in the Do Minimum scenario. These were:
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 30
9.5% of personal injury accidents at the roundabout in the Do Minimum, including a
fatality instead of default of 0.6% for a junction of this type on a dual carriageway.
Similarly the rate of seriously-injured casualties at the roundabout was set to 14%,
instead of the default 10%.
3.34 Now clearly fatal and serious accidents only form a minority of the injury accidents so
extrapolation of long-term impacts based on a small quantity of data is less certain than for all
accidents, but the data from the period late 2000-2005 does raise concerns about the validity
of the assumptions used in the model. The modelling has a severity rating (i.e. fatal and
serious accidents) of nearly 25%, while five years of observed data (as shown in Table 3.1)
showed only no fatalities and one serious accident, which occurred some distance from the
roundabout, giving a severity rating of 4%. Looking at the accidents recorded at the
roundabout only, and using the data from the Report of Surveys and LMVR, gives two
fatalities in 8 years from 1998 to 2005.
3.35 Although we cannot know how many fatal and serious accidents would have occurred at the
roundabout had the scheme not been built, the observed data for the period 2000-2005 does
not show the same problem with fatalities as the data from the late 1990s. This suggests that
modelling of the roundabout over-estimated the accident fatality rate and hence the saving
following its removal.
Security 3.36 This scheme was not predicted to have much impact on the NATA security sub-objective.
Most of the indicators for security which apply to highways schemes do not apply to this
scheme which is in a rural area. One lay-by was closed, but other facilities for road users
remain.
3.37 No change to any aspect of security has changed since the OYA study, hence our
assessment at FYA remains neutral, as forecast.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 31
Key findings from section 3: Safety
Accident numbers
In the first year after the completion of the scheme, there was an increase in accidents
compared with the before period. This was noted in the OYA and in a post opening
Road Safety Audit which suggested that users were experiencing problems with the
new layout. Some improvements were made to road signing and in the subsequent
period from 2008 onwards there was an annual saving of 2.6 injury accidents and 3.3
casualties, thus showing a successful long-term trend of fewer accidents.
Mapping of the accidents shows a cluster at roundabout before the scheme was built.
Accidents on the 0.3 mile / 0.5km short section of the A30 and the junction reduced by
63%, representing a saving of nearly 12 accidents in 4.5 years.
There were no fatalities and a single serious accident in the before period.
No pedestrians or cyclists were injured before or after.
Forecasts
The removal of the roundabout was forecast to be the source of all the safety benefits
of this scheme, as the replacement overbridge and associated links would have much
lower accident rates.
Observed saving at the roundabout is 34% lower than predicted.
Forecasts of fatalities saved through the removal of roundabout were too high, being
based on observations in the late 1990s, which do not correlate with observations in
the early 2000s. Later data from before the scheme was built indicates that although
there were a high number of accidents, there was not an unusual severity problem.
Road Safety Audits
Road Safety Audits identified problems when the scheme first opened but have noted
that these seem to have been related to road users’ unfamiliarity with the new layout
and concluded at 36 months after opening that there was a significant reduction in
collisions in the final two years.
Security
No impact on security, as expected.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 32
4. Economy
Introduction
4.1 This section presents an evaluation of how the scheme is performing against the NATA
economy objective, which is defined in WebTAG as:
To support sustainable economic activity and get good value for money
4.2 The five sub-objectives are to:
Get good value for money in relation to impacts on public accounts;
Improve transport economic efficiency for business users and transport providers;
Improve transport economic efficiency for consumer users;
Improve reliability; and
Provide beneficial wider economic impacts.
4.3 When a scheme is appraised, an economic assessment is used to determine the scheme’s
value for money. This assessment is based on an estimation of costs and benefits from
different sources:
Transport Economic Efficiency (TEE) benefits (savings related to travel times, vehicle
operating costs and user charges);
Accident costs (savings related to numbers and severity level of accidents); and
Costs to users due to construction and maintenance.
4.4 This section provides a comparison between the outturn costs and benefits and the forecast
economic impact, as well as evaluating reliability and the scheme’s wider economic impacts.
Sources
4.5 The sources of the economic impacts used in this study were obtained from:
A30 Merrymeet Junction Improvement, Forecasting and Economic Assessment Report
(F&EAR), November 2004;
COBA models, Sept 2005;
Outturn costs from the HA finance manager, October 2011; and
AST.
4.6 The economic basis of the benefits in the F&EAR was based on a 60 year appraisal period in
line with the latest guidance. This superseded the 30 year forecasts presented in the
Scheme Assessment Report, (January 2003).
4.7 All the monetary benefit modelling for this scheme was undertaken using Cost Benefit
Analysis (COBA) software.
4.8 Modelling was undertaken for low and high growth scenarios. The differences between low
and high growth results were proportionally quite low and as observed traffic has been above
the high growth forecast, as noted in the traffic section of this report, in this economic
evaluation we have focussed on the high growth forecasts.
4.9 COBA (Cost Benefit Appraisal) was used for the economic analysis of this assessment.
COBA performs a fixed-matrix appraisal and hence assumes that no additional traffic is
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 33
induced by the scheme. This assumption was consistent with the conclusions drawn from
the Induced Traffic Assessment, which stated that due to the limited nature of alternatives to
road transport on the A30 and the location of the site away from major urban areas, there
would be little impact due to induced traffic.
Scheme costs
Introduction
4.10 This section compares the forecast cost of the scheme with the outturn costs. The forecast is
based on the cost given in the T&EAR (November 2004) and the outturn spend profiles for
the scheme was obtained from the HA finance manager in October 2011.
Present Value Costs
4.11 Cost benefit analysis of a major scheme requires the costs to be considered for the whole of
the appraisal period and they need to be expressed on a like-for-like basis with the benefits.
This basis is termed Present Value. Present Value is the value today of an amount of money
in the future. In cost-benefit analysis, values in differing years are converted to a standard
base year by the process of discounting giving a present value10
.
4.12 The forecast Present Value Costs (PVC) for this scheme includes the following types of costs
incurred over the appraisal period, expressed in present value terms:
Investment Costs;
Operating costs; and
Indirect Tax revenue.
Investment Costs
4.13 The investment cost is the cost to the Highways Agency of constructing the scheme and
purchasing the land. As with the approach taken for the OYA study, in this FYA POPE study
we have taken the forecast investment cost from the T&EAR of November 2004. That
document gave the costs at programme entry in 2001 prices.
4.14 Prior to the start of construction, the forecast cost was increased to £8.8m and this figure was
used in the final COBA modelling.
4.15 The forecast and outturn costs are summarised in Table 4.1. For consistency with other
POPE studies we have converted all to 2002 prices.
Table 4.1 – Investment costs
£m, 2002 prices Forecast cost (T&EAR) Outturn cost
(as of Oct 2011)
Investment cost 7.6 10.8
4.16 The key point regarding scheme cost as shown in the table is that the outturn cost was 42%
higher than forecast.
10 Discounting is defined by the Treasury Green Book and under current guidance uses a discount rate of
3.5% for the first 30 years.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 34
4.17 The increased cost was identified prior to construction when this scheme was subject to a
cost challenge workshop in 2004. That identified that the 5% Optimism Bias had been
applied to the original Scheme Brief. However, an addition of 15% would have been
appropriate at the early stage the scheme had reached when it entered the TPI (precursor to
the Major Schemes Programme).
4.18 Since this scheme was appraised in the early part of the last decade, HA procedures for
scheme implementation including cost control measures have been significantly altered
through the introduction of the Project Control Framework.
Indirect Tax
4.19 Indirect tax revenue is the expected change in indirect tax revenue to the Government due to
changes in the transport sector as a result of the scheme over the appraisal period. For the
highways scheme in this study, the tax impact is derived primarily from the monetisation of
forecast of the changes in fuel consumption over the 60 years period. A scheme may result
in changed fuel consumption due to:
Changes in speeds resulting in greater or lesser fuel efficiency for the same trips;
Changes in distance travelled; or
Increased road use through induced traffic or the reduction of trip suppression.
4.20 For this scheme, the indirect taxation assessment was forecast together with the benefits
using the COBA model. The POPE approach in evaluating this impact has been based on
using COBA similar to that adopted for journey time benefits later in this section. Table 4.2
shows the forecast of the net change indirect tax based on 60 years.
Table 4.2 – Indirect tax impact
£m, 2002 prices and values Forecast (high
growth, HG) FYA Outturn
reforecast
Net increase in indirect tax revenue over 60 years
£1.18m £0.90m
4.21 The forecasts showed that indirect tax was predicted to increase as a result of the scheme
and the outturn reforecast gives a similar but slightly lower impact.
Present Value
4.22 The overall calculations for the costs to public accounts expressed as present value costs
(PVC) is summarised in Table 4.3.
4.23 The expected increase in indirect tax revenue reduces the cost of the scheme to the public
accounts. At the time this scheme was appraised, the present value cost figure included the
indirect tax impact within the costs figure11
. In the case of this scheme, this approach means
that the cost to public accounts is reduced.
11 Treatment of indirect tax as part of the benefits rather than costs became the official guidance in April
2011.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 35
Table 4.3 – Present Value Costs
£m, 2002 prices discounted to 2002 Forecast Outturn
Investment cost (i.e. PVC based on costs to the Highways Agency (no indirect tax impact)
£8.6m £9.5m
Indirect Tax (additional tax raised for public accounts) -£1.2m -£0.9m
PVC £7.4m £8.6m
4.24 The purpose of the PVC figure in this economic evaluation is in the calculation of the benefit
costs ratio as shown later in this section.
Benefits 4.25 The monetary benefits of the scheme were assessed in accord with the latest guidance on
assessment methodology for capital projects. The benefits were assessed for a 60 year
period and expressed in terms of present value with a 3.5% discount rate. This use of
discounting of monetary benefits over a long period gives Present Value Benefits (PVB),
which can be compared with the Present Value Costs in cost benefit analysis.
4.26 The appraisal of this scheme considered the PVB of the following impacts:
Time and vehicle operating cost benefits; and
Safety benefits (COBA).
4.27 The spread of the forecast benefits are summarised in Figure 4.1.
Figure 4.1 – Forecast benefits
4.28 This shows that the forecast benefits were split almost evenly between journey times and
safety and that consistent benefits were expected to be seen over the long-term.
Time and vehicle operating cost benefits (Transport
Economic Efficiency)
Forecast of Transport Economic Efficiency benefits
4.29 Transport Economic Efficiency (TEE) i.e. journey time savings and vehicle operating costs
(VOC) were appraised using COBA.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 36
Journey Times
4.30 When evaluating the post opening benefits in POPE, we normally use observed changes in
journey times on a comparable basis with the forecast to determine the outturn benefits.
However, in the case of this scheme, this approach has not been possible for the following
reasons:
Modelling showed that more than 99% of the journey time benefits were from the
removal of junction delays at the roundabout. The impact on the links was negligible.
As noted in the traffic section, there is no observed data on the journey times
experienced by traffic using the roundabout before the construction of this scheme, so it
is not possible to make comparisons between the congested conditions at the
roundabout with journey times in the post opening period12
.
4.31 Thus, as with the OYA evaluation, we have derived the outturn benefits by using the original
COBA model combined with observed traffic flow data for the A30 and all the links
immediately around the junction layout, old and new.
4.32 As noted earlier, the A30 here shows very seasonal patterns of traffic flow, thus it was
important to validate the approach used in the COBA model. The seasonality index used in
the modelling was 1.25, which is above the default for this type of road. The model was
based on seasonality in 2003 on the A30, as described in the LMVR. We have checked this
against the 2011 seasonality i.e. comparing August with the traffic neutral months and
confirmed it remains valid, thus have used this in the reruns of COBA.
4.33 Table 4.4 shows the 60 year benefits of the scheme for Transport Economic Efficiency as
originally forecast against the re-evaluation of these benefits at the one and five years after
stages (OYA and FYA). The original appraisal included both low and high growth versions,
but as shown previously that the observed traffic is higher than was modelled, only the high
growth model results are shown here.
Table 4.4 – 60 year Economic Benefits (£m, 2002 prices, discounted)
Transport Economic Efficiency (TEE)
User Category Forecast
POPE Re-forecast based on observed outturn flows
OYA FYA
Travel time Consumer £14.9m £17.0m £14.3m
Business £10.9 £16.8m £14.1m
Vehicle operating costs
Consumer -£1.4m -£0.2m £-0.5m
Business -£0.8m -£0.2m £-0.6m
Total £23.6m £33.3m £27.3m
4.34 This shows that:
At FYA, the scheme delivers substantial travel time benefits for consumer and business
users. There is a slight disbenefit in terms of vehicle operating costs; this is due to a
small increase in fuel used.
12 In recent years it has become possible to analyse before and after journey times around a junction such
as this using sat-nav data, but we are not able to take this approach here because the before period, predates the availability of such data.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 37
Total TEE benefits are higher than forecast, because the traffic flows are higher than
forecast. The reduced assessment at FYA compared with OYA is due to the low traffic
growth observed in that time
Accident benefit modelling
4.35 For the purpose of assessing the economic impacts of road schemes, changes in safety as
measured by changes in accident numbers and severity are monetised. Forecasts are
generated using the methods and accident rates contained in the COBA Manual (DMRB
Volume 13, Section 1) and embodied in the computer program COBA.
4.36 The original COBA model used a non default setting for the accident severity on the A30 and
at the roundabout, based on observed data in 1998. At that time, there had been an
abnormally high severity rate in the area around the existing roundabout. In monetised
terms, reducing the numbers of fatalities and seriously-injured casualties has a greater
economic benefit hence the modelled severity rating is important.
4.37 As discussed earlier in the Safety section, in subsequent years the severity rate was much
reduced. Table 4.5 summarises the assumptions made in the model compared to the
defaults for the link and junction types and the observed data collected for this study covering
the 3 years prior to scheme construction.
Table 4.5 – Casualty severity modelling
Severity
Number and Severity of Casualties per Accident
A30 Whiddon Down roundabout Observed on A30 and
nearby links As modelled (1998)
Default (2000)
As modelled (1998)
Default (2000)
(2000-2005) (2007-2011)
Fatal 0.25 0.0314 0.095 0.006 0 0
Serious 0.5 0.2005 0.143 0.1019 0 0
Slight 0.25 1.312 1.429 1.214 1.476 1.286
%KSI13
75% 15% 14% 8% 0% 0%
4.38 This table shows that the A30 and the roundabout were modelled with considerably higher
severity rates for casualties than is normal for the road type and was observed in the area in
three years before the scheme was constructed.
4.39 For the purpose of the post opening evaluation of the long-term accident benefit, it is
considered that:
The original modelling of accident severity, especially the 75% KSI on the A30 links and
the 9.5% fatalities at the roundabout, was very high and has been contradicted by more
recent data;
It is clearly not reasonable to assume that the observed rate of 0% killed and seriously
injured can be taken as a long-term basis but it does indicate that the long-term trend is
likely to be low.
Therefore, to model the 60 year impacts, the default COBA modelling of severity has
been assumed.
13 %KSI is the proportion of casualties who are killed or seriously injured.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 38
4.40 As for the economic efficiency benefits, the high growth model has been used for the
evaluation here. The results of the COBA modelling for accidents are summarised in Table
4.6.
Table 4.6 – 60 year Safety Benefits
60 Year benefits Original Forecast
(high growth)
Re-forecast from COBA model re-run with observed flows, observed 5 years
before accidents at roundabout and default accident severity rates
OYA FYA
Monetised Safety benefits
(£m 2002 prices discounted at 3.5%) £24.7m £6.9m £7.4m
Forecast accident saving 287 257 266
Forecast casualty saving
21 fatalities
19 seriously injured
443 slightly injured
1 fatality
13 seriously injured
322 slightly injured
1 fatality
14 seriously injured
335 slightly injured
4.41 The comparison of the original forecasts with the re-forecast of the 60m year safety benefits
based on observed traffic and the assumptions detailed above shows:
60 year safety benefits are now expected to be only a third of the original forecast in
terms of monetary value.
The re-forecast saving of accident numbers is slightly lower than predicted, but the more
important change is in the savings in the numbers of casualties killed or
seriously-injured.
This reduction in the forecast of the numbers of casualties killed or seriously injured in
the accidents saved is the main reason why the monetised value of the accident
reduction over 60 years is only a quarter of that forecasted.
The reduction in the safety benefit is despite there being higher traffic flows observed
than were modelled.
4.42 It is also noted that, as may be expected, virtually all the benefits of this scheme are derived
from the reduction in junction accidents.
Delay during Construction
4.43 The scheme appraisal calculated that delays during construction would have a negative
impact on journey times. Using the QUADRO software, this disbenefit was monetised at
£1.0m for high growth14
. This is low relative to the other costs and benefits and has not been
evaluated in this study. The original figure has been used as a reasonable estimate for the
purpose of overall cost benefit analysis.
Summary of Monetised Benefits
4.44 The benefits forecast and re-forecast based on outturn data as discussed in the previous
sections are summarised in Table 4.7.
14 A30 Merrymeet Junction Improvement, Forecasting and Economic Assessment Report, Table 8
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 39
Table 4.7 – Summary of Present Value Benefits
Summary of Benefits
Costs in £m 2002 prices discounted to 2002 at 3.5%
Forecast (high growth)
Re-forecast with observed flows
OYA FYA
TEE £23.6m £33.3m £27.3m
Safety benefit £24.7m £6.9m £7.4m
Delay During Construction -£1.0m -£1.0m -£1.0m
Total Present Value Benefits (PVB) £47.3m £39.3m £33.7m
4.45 The above summary table shows that overall present value benefits (PVB) over 60 years is
now forecast to be £34million, which is 29% below that forecasted. As seen at OYA, the
additional benefits from journey times due to additional traffic are outweighed by the
reduction in the forecast safety benefits.
Benefit Cost Ratio (BCR) 4.46 The benefit-cost ratio (BCR) is an indicator used in the cost-benefit analysis of a road
scheme that attempts to summarize the overall value for money of a project or proposal. The
BCR is the ratio of the benefits of a project or proposal, expressed in monetary terms, relative
to its costs, also expressed in monetary terms. All benefits and costs are expressed in
present values as detailed in the above sub-sections.
4.47 As discussed earlier, the most recent guidance on indirect tax impacts is to include these as
a benefit rather than a reduction in the cost. This means that when a scheme leads to
increased fuel consumption and hence increased tax revenue, the PVB is increased rather
than the PVC being decreased. The impact on the PVB of adding the indirect tax impact is
summarised in Table 4.8.
Table 4.8 – Present Value Benefits with indirect tax impact
Benefits over 60 years (£m) Forecast Outturn reforecast
Present Value Benefits (PVB) £47.3m £33.7m
Indirect Tax impact £1.2m £0.9m
PVB adjusted for indirect tax £48.4m £34.6m
4.48 A comparison of how the costs and benefits have been used to produce the BCR for the
forecasts and the BCR from the POPE evaluation discussed in this section are given in Table
4.9 with the indirect tax treated via the two alternatives. All benefits are over 60 years, post
opening.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 40
Table 4.9 – Benefit Cost Ratio
All monetary figures in 2002 prices and values
Forecast FYA Outturn reforecast
Present Value Benefits (PVB) £47.3m £33.7m
Present Value Costs (PVC) £7.4m £8.6m
BCR = PVB / PVB 6.3 3.9
Indirect tax as benefit
PVB £48.4m £34.6m
PVC £8.6m £9.5m
BCR 5.6 3.6
4.49 The key points regarding the BCR as evaluated at this stage are:
As the benefits are lower than forecast and costs higher, the BCR is lower than forecast.
According to DfT guidance15
, a scheme is classified as high value for money if its BCR
lies between 2.0 and 4.0, which is clearly achieved in this case.
The effect of including the Indirect tax impact in the benefits (an increase) rather than the
costs (a decrease) has only a marginal lowering effect on the overall BCR.
4.50 It should be noted that the BCR ignores non-monetised impacts. In the former NATA
assessment and its replacement, the Transport Business Case, the impacts on wider
objectives must be assessed but are not monetised. The evaluation of the environmental,
accessibility and integration objectives is covered in the following sections.
Wider Economic Impacts
4.51 The AST states that the scheme is not located in a regeneration area and no development
was dependent on the scheme, hence the impact on this sub-objective was neutral. The
junction lies in a rural area directly abutting the Dartmoor National Park and thus is not likely
to be considered a suitable location for development in the future.
4.52 Areas of Cornwall and north Devon are served by the A30 and these are categorised as
regeneration areas. Hence improving access to these areas by reducing journey times for
trunk road traffic through the Whiddon Down junction as provided by the improvement to this
part of the A30 does contribute towards the goals of regeneration.
15 At the time of this study, this is currently under revision.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 41
Key findings from section 4: Economy
Costs and Benefits
The investment cost of the scheme was £10.8m in 2002 prices, which was
substantially higher than the predicted cost of £7.6m when it was appraised in 2004.
This had made insufficient allowance for optimism bias for the stage when it entered
the programme of schemes.
Journey time benefits were higher than expected due traffic levels on the A30 being
higher than forecast, despite the economic downturn.
Safety benefits, which had been expected to comprise half the benefits, were
evaluated to be much lower than expected. This is because the forecasts were based
on the prediction of a continuing long-term problem of a high number of both accidents
and fatalities at the roundabout without the scheme in place. The lower outturn
benefits was based on an observed reduction in accident numbers and the assumption
of a typical rate of fatal and serious accidents at the roundabout had the scheme not
been built.
Outturn Benefit Cost Ratio (BCR) was lower than forecast but at 3.6 still represents
high value for money.
Wider Economic Impact
None to immediate area near the junction which is not a development area, but there
are slight benefits to regeneration areas in Cornwall and north Devon.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 42
5. Environment
Introduction
5.1 This section documents the evaluation of the environmental sub-objectives, focussing on
those aspects not fully evaluated at the OYA stage, or where suggestions were made for
further study.
5.2 When the ES was written, the junction was called Merrymeet and since the OYA evaluation
the name has been changed to Whiddon Down, both names are used in this section as
appropriate.
Summary of OYA Evaluation Recommendations
The OYA evaluation identified a number of areas where further analysis was required at the FYA stage to confirm the longer term impacts of the scheme on the surrounding environment, these are summarised as follows:
Landscape –successful establishment of the landscape planting and seeding would be re-evaluated at the FYA stage.
Biodiversity –monitoring of reptiles and dormice was expected to be carried out and results would be reviewed as part of the FYA report. It was too early to evaluate the success of the methodology for establishment of species rich grassland and ongoing establishment should be evaluated as part of the FYA study.
Heritage – At OYA publication of an article written for the Devon County Archaeological Journal was not confirmed and the site archive had not been presented for permanent storage at the Royal Albert Memorial Museum in Exeter. Devon County Council had not received a copy of the scheme archaeology report.
Physical Fitness – At OYA Devon County Council was concerned about the safety of cyclists using the junction and that there was no signage which would indicate to cyclists that there were alternative quieter long-distance parallel routes available by using the ‘old’ pre-1970s A30.
Journey Ambience – Anecdotally concerns were raised at OYA by people living locally and commuters about what they considered to be poor advance signage of the junction.
5.3 The Environmental Statement (ES) noted that the scheme’s objectives for Environment
included:
To deliver an environmentally acceptable scheme that protects the natural environment.
The scheme would minimise and mitigate the environmental impacts on areas within and
adjacent to the junction, specifically adjoining Dartmoor National Park.
5.4 The scheme would incorporate appropriate mitigation measures to minimise
environmental effects. Key aspects of the scheme aimed at reducing environmental
impacts would include the following:
Avoiding the Dartmoor National Park;
Minimising landtake and effects on farm holdings, providing replacement farm access
tracks where appropriate;
Minimising the effects on nearby properties, providing earth mounds screening and new
planting where appropriate;
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 43
Reducing the overall level of street lighting compared with the existing situation;
Incorporating drainage treatment areas to minimise the risk of pollution to surrounding
watercourses;
Minimise disturbance to wildlife and take measures to reduce the effects on protected
species;
Maintaining and improving provision for pedestrians; and
Recycling and reusing material where practicable.
5.5 The following environmental sub-objectives were appraised in the ES and in the AST
according to NATA guidance at that time (2002):
Noise;
Local Air Quality;
Greenhouse Gases;
Landscape;
Heritage;
Biodiversity;
Water Environment;
Physical fitness; and
Journey Ambience
5.6 For each of these environmental sub-objectives, the evaluation in this Section assesses the
environmental impacts predicted in the scheme’s AST (Appraisal Summary Table) and ES
against those observed five years after opening.
5.7 The AST stated that Townscape was not applicable to this scheme and it has therefore been
scoped out of this evaluation.
5.8 In the context of the findings from the OYA evaluation, and using new evidence collected five
years after opening, this section presents:
An evaluation of the ongoing effectiveness of the mitigation measures implemented as
part of the scheme;
An updated summary of key impacts against all of the nine environment WebTAG sub
objectives, with particular focus on assessment of sub-objectives where it was too early
to conclude at the OYA evaluation stage; and
Additional analysis relevant to close out issues or areas for further study, as identified at
the OYA stage to for consideration at the FYA stage.
Methodology
5.9 This section focuses on those aspects not fully evaluated at OYA, or where at OYA,
suggestions were made for further study and also any issues that have arisen since the OYA
evaluation. The detail of the OYA study is not repeated here, and reference should be made
to the OYA report where required, although key points are incorporated into this five years
after (FYA) report where appropriate to provide contextual understanding.
5.10 No new modelling or survey work has been undertaken for this FYA evaluation.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 44
Data Collection
5.11 The following documents have been used for the FYA:
AST (Appraisal Summary Table) for the scheme (Scheme Assessment Report, January
2003 version) ;
A30 Merrymeet Junction Improvement Environmental Statement February 2005 Volume
1 Text, Volume 2 Figures and Non-Technical Summary (NTS);
As-Built Drawings;
A30 Merrymeet Junction Improvement Maintenance Manual and Appendices;
A30 Merrymeet Dormouse Monitoring 2011 and 2012 Final Report (May 2012);
A30 Merrymeet Reptile Mitigation Monitoring 2011 and 2012 Final Report (May 2012);
The A30 Merrymeet Junction Improvement Archaeological Assessment Report July
2006;
A30 Whiddon Down Junction Improvement Handover Site Inspection Record 29.9.11;
and
A30 Whiddon Down Junction Improvement Handover Environmental Management Plan
(HEMP) November 2011.
5.12 A full list of the background information requested and received to help with the compilation
of this report is included in Appendix D.1.
Site Visit
5.13 As part of the FYA evaluation, a site visit was undertaken in May 2012. This included the
taking of photographs to provide comparison with material produced at the appraisal stage
and at OYA (see Appendix D.2).
Consultations
5.14 Two statutory environmental organisations (Natural England and the Environment Agency),
Devon County Council and West Devon Borough Council, the Dartmoor National Park
Authority and the Parish Council were contacted as part of the FYA evaluation regarding their
views on the impacts they perceive the scheme has had on the environment. The responses
received are summarised in Table 5.1.
Table 5.1 – Summary of Environmental Consultation Responses
Organisation Field of Interest
Comments at OYA Comments at FYA
Natural England (NE)
Landscape & Biodiversity
Commented on Badger licence. Unable to provide any other comments as NE had no after opening monitoring data on which to base a response
Would possibly be able to comment on Dormouse monitoring but required the details of when and how the report was forwarded to NE to be able to locate it in their system.
English Heritage Heritage Unable to comment as no designated sites affected and suggested contacting the local authority
Not re-contacted
Environment Agency (EA)
Water Not aware of any problems – as expected
Again stated that it was not aware of any problems.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 45
Organisation Field of Interest
Comments at OYA Comments at FYA
Devon County Council (DCC)
General PROW (concerned about safety of cyclists, disappointed that no signage directing cyclists to quieter long distance routes)
Drainage (not aware of any problems)
Biodiversity (hedge-banks as expected, no major habitat loss, scheme seems to be
establishing satisfactorily)
Landscape (works blend into local environment and this will improve as planting matures, improvement in light pollution, successful enhancement of local environment)
Heritage (not been provided with a copy of the archaeological report and is therefore not in a position to comment on the impact of the scheme on archaeology and Historic Landscape at this time)
Heritage - DCC records show that a copy of the archaeological report has been provided. Suggested contacting the Archaeological consultant to close out other issues.
General – not aware of any outstanding general environmental issues. Handover of ongoing responsibility for landscape areas to DCC expected to take place June 2012.
Countryside Team provided a response on the slow development of species rich grasslands and potential for gorse to colonise unless treated.
PROW – Whiddon Down interchange is one of the options DCC are considering for managing the Cycle West route from Exeter to Okehampton.
The Road Safety Audit team considered the scheme safe, convenient and comfortable due to its open landscaping
West Devon Borough Council
General Air Quality (beneficial)
Noise (not aware of any issues)
Local signage
Landscape (pleased with extent and type of planting)
Confirmed that local air quality remains good and it is not aware of any complaints relating to noise due to traffic.
Dartmoor National Park Authority
Dartmoor National Park
(DNP)
Junction works avoided any physical encroachment into DNP, planting should in time help assimilate junction into the landscape and lighting is a marked improvement and reduces impact on DNP.
No issues raised since OYA and no further comments to add.
Drewsteignton Parish Council
General Not consulted with in line with methodology at the time
No response received.
Archaeological Consultant
Heritage Provided copy of Archaeological Assessment Report
Confirmed that it currently holds the site archive and that the article which has been written will be forwarded for publication in the Devon County Archaeological Journal
5.15 No information relating to Part 1 Claims was included in the OYA report. At FYA the
Highways Agency Part 1 Team has been contacted regarding Part 1 claims and it is
understood that there have been 4 claims, none of which were successful. The reasons for
the claims being made are not known as the District Valuer is no longer available.
5.16 The area’s Managing Agent Contractor (MAC) has provided animal mortality data which is
included in the Biodiversity section of this chapter.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 46
Traffic Forecast Evaluation
5.17 Three of the environmental sub-objectives (noise, local air quality and greenhouse gases) are
directly related to traffic flows. No new noise or air quality surveys are undertaken for POPE
and an assumption is made that the level of traffic and the level of traffic noise and local air
quality are related. Therefore, if the observed level of traffic is as forecast at the appraisal
stage it can be assumed that the traffic noise and local air quality impacts after the opening of
the scheme are as expected.
5.18 The ES noted that the annual average daily traffic (AADT) two-way flow in the ‘base year
2003’ on the A30 Merrymeet roundabout was 21,800 vehicles to the east of the roundabout
and 20,400 to the west. Approximately 10% were HGVs.
5.19 The ES included traffic forecasts which where used as the basis of the AQ assessment. This
gave forecasts of flows for the opening year of 2006 and design year of 2021 for the
following:
Annual average daily traffic (AADT);
August ADT, as this is the busiest month of the year; and
Saturdays in August.
5.20 As the scheme was forecast to have no impact on route choice or result in any induced
traffic, the forecast are identical for the Do Nothing and Do Something scenarios. To assess
the accuracy of the forecasts against observed data for the OYA and FYA studies, we have
created proxy forecasts for the same years using a straight-line interpolation between the
opening and design year forecasts.
5.21 The comparisons between the High Growth (HG) and observed data are shown below in
Table 5.2 and Table 5.3 .
Table 5.2 – Traffic Forecasts used in AQ Assessment vs. Outturn Flows
Location
AADT
One Year After (2008) Five Years After (2012)
Proxy ES HG Forecast
Observed %diff Proxy ES
HG Forecast Observed %diff
A30, East of Jct 25,700 29,400 14% 27,800 30,200 9%
A30, West of jct 24,100 26,300 9% 26,000 26,600 2%
A382 between services & A30
6,700 6,300 -6% 7,200 7,400 3%
Minor rd 1,300 1,000 -23% 1,400 1,200 -14%
Table 5.3 – August Traffic Forecasts used in AQ Assessment vs. Outturn Flows
Location
August Traffic – Five Years After (2012)
August Daily August Saturdays
Proxy ES HG Forecast
Observed %diff Proxy ES
HG Forecast Observed %diff
A30, East of Jct 45,900 40,600 -12% 64,300 52,400 -19%
A30, West of jct 42,900 37,400 -13% 60,200 50,200 -17%
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 47
5.22 August traffic flows were overestimated by over 10% when compared to observed. However
August traffic is clearly subject to greater levels of variation from tourism demand. The Met
Office reported that summer 2011 was colder and wetter than average.
5.23 Based on information within the Traffic section of this report HGV numbers (compared to the
situation before the scheme) have increased as follows:
On the A30 by 6%;
On the C50 minor road by 18%; and
On the A382 west of the junction by 49%.
5.24 With regard to traffic speeds, as noted in section 2 of this report, POPE has no information to
enable any pre- and post scheme comparison.
Five Year after Assessment
5.25 Included in this section is a brief summary of statements from the AST, ES and OYA
evaluations (including close out / key issues identified for further reporting at the FYA stage)
which have been included to provide the context for the FYA evaluation.
Noise
5.26 The AST did not assess noise levels as there was expected to be a less than 25% change in
traffic levels as a result of the scheme.
5.27 The ES stated that the scheme would lead to an increase in traffic noise levels at six
receptors within the study area. However, these increases would be below the levels at which
short and long-term changes were perceptible and were therefore considered to be
insignificant.
5.28 The ES also reported that a low noise surface would be used at the junction.
5.29 At the OYA stage it was stated that:
The scheme Maintenance Manual stated that the works carried out in the reshaping of
Narroway Farm Improvement act as a noise barrier to provide environmental benefits to
Whiddon Down village. The manual also stated that the earthworks on the south western
side of the A382 loop provide environmental benefits to the Travelodge site.
The scheme itself had not led to an increase in traffic on the A30, the traffic counts
between 2005 (before the scheme) and 2007 after opening indicated a 4 to 5% increase
in traffic due to normal traffic growth.
Consultation
5.30 West Devon Borough Council confirmed that it is not aware of any complaints or issues
relating to noise due to traffic in the vicinity of the junction.
Evaluation
5.31 There was no requirement for the HA to undertake noise surveys. A low noise surface has
been used at the junction as expected; prior to the junction improvements the carriageway
was a combination of areas of concrete and Hot Rolled Asphalt (HRA), however, the HRA
was replaced with SMATex (Thin Surface Coating System), which is quieter.
5.32 Based on the before scheme and FYA observed traffic data it can be assumed that in line
with POPE methodology noise due to traffic is as expected for the A30 and C50 i.e. the
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 48
changes in flow are no more than +25% (increase) or -20% (decrease) than forecast,
including HGVs.
5.33 For the A382 west of the junction overall traffic is 21% greater than expected, however, HGV
numbers have increased by 49% and it is possible therefore that noise due to traffic could be
worse than expected for the 3 properties and Travelodge within 300m of this route. For the
village of Whiddon Down where it was not expected in the ES that any noise impacts would
occur, noise due to traffic is assumed to be worse than expected for properties on the A382
due to the increase in HGV numbers.
Local Air Quality
5.34 The AST did not assess local air quality as there were not expected to be changes in traffic
flows of 10% or more.
5.35 The ES concluded that considering that the local air quality was good and that no significant
changes in traffic conditions were expected as part of the scheme. UK national air quality
objectives would not be breached as a result of the scheme.
5.36 A small increase in total emissions was predicted with the scheme in operation due to the
predicted higher average traffic speeds for the ‘Do Something’ scenario.
5.37 At the OYA stage it was stated that based on no significant changes in observed traffic flows,
it was likely that local air quality impacts were as expected. An EST score was not provided.
Consultation
5.38 West Devon Council confirmed that air quality was very good in its area, and that the closest
monitoring point is in Chagford - too far away to be representative.
Evaluation
5.39 A comparison of the observed before and after traffic volumes shows that there has been no
significant change in traffic flows as a result of the scheme. A comparison of the forecasts
that were made also shows that no change in traffic volume was expected as a result of the
scheme and this forecast appears to be accurate.
5.40 However, there is a significant difference between the forecast and observed traffic volumes.
The traffic model underestimated the traffic volume on many links, by up to 9% on the A30 at
FYA, but this occurred in all scenarios, i.e. it was due to inaccuracies within the Base model
rather than in the way the scheme was modelled.
5.41 In addition, assuming HGVs were forecast to be 10% of AADTs, the A382 was observed to
have over 200 more HGVs than forecast (890 compared with 610).
5.42 There are no properties within 200m of the A30 east of the junction, and only 1 property, Mill
Farm, within 200m of the A382. As traffic flows on the A382 are relatively low (less than
10,000 AADT), it is unlikely that the higher observed traffic and HGVs would cause any
breach in air quality criteria, especially given the rural nature of the area. Air quality is
therefore likely to still be as expected.
Greenhouse Gases
Context
5.43 The AST and the ES Air Quality chapter both gave the same forecast for the net impact of the
scheme on the Greenhouse Gas sub-objective as 416 tonnes Carbon Dioxide emissions.
The AST assessed this as slightly adverse while the ES stated that the effect would be
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 49
negligible compared to the total UK emissions from road vehicles hence the impact would be
neutral.
5.44 The ES states that the impact was forecast using the DMRB air quality spreadsheet based on
200metres each side of the junction. The ES states that average speeds on the A30 as
observed in 2003 and in the Do Minimum (DM) scenario are below 100km/h whereas in the
Do Something (DS) scenario they are above 106km/h. At these relatively high speeds,
carbon emissions tend to increase for higher speeds which explains the higher total
emissions predicted for the DS.
FYA Evaluation
5.45 Since this scheme was evaluated, greenhouse gas emissions are now measured in terms of
tonnes of Carbon rather than CO2. Also, the COBA modelling software has been enhanced
and now provides estimates of the carbon impact of the modelled scheme.
5.46 For the purpose of this post opening evaluation, the latest version of COBA16
was used to
calculate carbon emissions for DM and DS scenarios as follows:
to recalculate a forecast of the net change using the original pre-construction scheme
model of the DM and DS; and
to calculate an estimate of the net difference in emissions in the opening year based on
the observed traffic volumes for the DS and the DM (assuming that overall flows and
strategic routing would not have altered if the scheme had not been built).
5.47 The carbon results from the COBA model are detailed in Table 5.4. Additionally the figures
from the ES have been converted from CO2 to carbon are shown. These figures would have
been calculated using the DMRB air quality spreadsheet and probably for a smaller network
of links than that modelled in COBA.
Table 5.4 – Carbon Emissions (tonnes in year)
Scenario ES Forecast Appraisal model re-run
with latest COBA
Model updated with outturn Flows run with latest COBA
Opening year OYA (2008) FYA (2012)
Do Minimum / without scheme (DM)
1,053 1,626 2,090 2,064
Do Something /with scheme (DS)
1,166 1,665 2,093 2,080
Net increase 113 39 3 16
% change 11% 2% 0% 1%
5.48 The key points regarding the greenhouse gases impacts are:
When observed outturn data is added to the COBA model, the DM and DS emissions
are both higher than in the original COBA model but this is due to underestimates of the
A30 traffic regardless of the scheme. This was detailed previously in Chapter 2.
The main finding at OYA was that the net increase in carbon in the opening year which
had been forecast as about 10% as a result of the scheme, was evaluated to be
negligible in proportion to the overall carbon emissions at the junction.
16 COBA v11 R7
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 50
At FYA, the impact is also assessed to be a negligible increase.
5.49 The assessments here show that given the available data we evaluate the scheme impact on
greenhouse gas emissions to be neutral, as expected. As with noise and air quality, the
outcome of this evaluation is consistent with the changes in traffic volumes reported
elsewhere in this document.
Landscape
5.50 The A30 at the location of the junction was already within a deep cutting. The AST stated that
there would be some loss of established highway planting but some attenuation of the notch
effect of the A30 cutting seen from the North West. New planting, reduced lighting and the
new bridge would redress the balance. A neutral impact was assessed overall.
5.51 The ES stated that the design of the scheme aimed to integrate the improved junction into the
landscape as far as possible. It would avoid encroaching into the neighbouring Dartmoor
National Park, but would encroach further into the Tedburn St Mary part of the Area of Great
Landscape Value to the north. Redundant lengths of road would be landscaped. There would
be some loss of existing hedge banks and more recent tree and shrub planting on highway
land. This would be mitigated by new planting.
5.52 Visual impacts would be limited to a few properties. It was seen as an advantage that the
new bridge would span a deep cutting, thereby minimising the need for embankments on the
approach roads. The layout would minimise visual impact.
5.53 On completion of the scheme it was expected that the visual impact of the new junction and
its traffic would progressively diminish as the new tree planting became established. Removal
of lighting columns associated with the existing roundabout would reduce the impact at dusk
and night time at this Gateway to the Dartmoor National Park.
5.54 Some changes to the landscape scheme with regard to the successful integration of surplus
material were discussed at OYA.
5.55 The OYA report stated that:
Planting appeared to be establishing satisfactorily apart from some of the light standard
trees scattered through the plots.
Some spreading shrubs had been planted in too narrow shelters and were developing a
‘lollipop’ form. This was being addressed with wider shelters being provided by winter
2008.
As expected the overbridge did appear to close the ‘notch’ in the A30 cutting when
viewed from a distance.
The earthworks and ground modelling had successfully reduced views of traffic using the
new overbridge as predicted, and also blocked the headlights of vehicles crossing the
bridge towards the Travelodge hotel. Visual impacts were considered to be as expected
for footpaths, the service area and residential properties.
Impacts on Dartmoor National Park had been minimised e.g. retention of existing
planting, new planting and by significant reduction in lighting.
5.56 Based on the information available it was assumed that the impacts on the landscape
sub-objective were as expected.
Consultation
5.57 Devon County Council confirmed at FYA that the scheme was considered to be establishing
satisfactorily. Some shrub plots with intermittent trees will be handed over to DCC for ongoing
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 51
management from June 2012. At the pre-handover site meeting in September 2011 it was
expected that all tree and shrub guards in plots to be handed over to DCC would be removed
before handover.
5.58 The Dartmoor National Park Authority had no new comments to make since OYA.
Evaluation
5.59 A Handover Environmental Management Plan (HEMP) has been issued. This confirms that:
Landscape maintenance operations have been carried out during the 5 year maintenance
period, including grass cutting, removal of gorse, weed control in hedges and around
individual trees and shrubs and noxious weed control.
A joint site meeting held in September 2011 between HA, Devon CC, MAC,
Environmental Co-ordinator and Contractor concluded that subject to appropriate
maintenance being carried out and any defects dealt with between then and June 2012,
there were no significant defects which would prevent transfer of responsibility to any
party in June 2012.
5.60 The HEMP includes strategies for regular maintenance of environmental areas in the future
on a plot by plot basis.
5.61 Based on the FYA site visit planting, including the larger trees (light feathered), is generally
establishing satisfactorily and it would appear that plots have been well maintained during the
aftercare period see Figure 5.1 below. As would be expected there is some variation in
growth depending on species, but subject to ongoing development, planting should fulfil its
longer term screening and integration functions by the design year 2021.
Figure 5.1 – Illustrating generally satisfactory plant establishment, weed free circles and grassland
free from noxious weeds
5.62 Individual shelters were still in place at the FYA site visit in May and as noted at OYA some
plants have developed a ‘lollipop’ form due to the use of narrow width shelters and their
shape would benefit from removal of the shelters. However, it is understood from the
Handover Site Inspection Record that it has been agreed with HA that shelters should remain
in place in the plots to be maintained by the MAC until plants are at least 1.2m tall due to
problems with browsing by animals Figure 5.2 and Figure 5.3 below illustrate narrow
shelters restricting growth at OYA and the situation at FYA. Devon CC had also expected that
all the tree and shrub shelters on the plots they were taking over to have been removed prior
to handover.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 52
Figure 5.2 – (left) Plants developing ‘lollipop’ form in narrow shelters at OYA
Figure 5.3 – (right) At FYA plants will not be able to develop a more natural shape until shelters are
removed
5.63 Nighttime lighting at the junction was considered by consultees at OYA to have been
successfully reduced by the scheme changes. Figure 5.4 and Figure 5.5 below compare the
night time impact at FYA as seen on the A382 approaching the junction, to the ‘before’
situation as illustrated in the NTS to the ES and it is considered that beneficial impacts are as
expected.
Figure 5.4 – (left) Existing night time lighting before the improvement works at the junction
Figure 5.5 – (right) At FYA
Biodiversity
5.64 The AST stated that some species rich Devon hedgebanks would be partially lost, together
with some areas of species rich grassland, although both would be largely mitigated by new
planting. Some minor impact is likely on habitats for reptiles, badgers, Dormice and breeding
birds, although these would be largely mitigated within the scheme design. The impact was
assessed as slight adverse overall.
5.65 The ES noted that the scheme would not affect any designated sites. There would, however,
be some effects on habitats and species.
5.66 The scheme would result in some loss of parts of some of the Devon hedge-banks, although
scheme design minimised this loss and ensured the retention of the better quality lengths.
Reuse of the removed material in new hedgerow planting would provide some mitigation for
the loss. Other vegetation losses, such as grassland, scrub and tree cover would be
mitigated by areas of seeding and planting using native species.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 53
5.67 Measures would be taken to reduce the effects of the scheme on protected species including
badger, dormouse, birds and reptiles. This would include, for example, the capture and
relocation of some species before construction commenced.
5.68 The OYA report concluded that new and replacement habitats had been created within the
highway boundary as expected. It was too early to evaluate the success of the methodology
for establishment of species rich grassland and ongoing establishment should be evaluated
as part of the FYA study. It was noted that gorse had seeded in a few areas, which can be
problematic if allowed to colonise. Clover was present in the verges and central reserve
which was not specified in the Devon CC mix.
5.69 With regard to protected species the OYA report stated that:
Dormice - clearance of habitat was undertaken in accordance with the agreed method
statement. From the monitoring information at OYA it appeared that Dormice were still
present in habitat around the junction. Further monitoring was expected and this would
be reported on at FYA.
Badgers – an artificial sett was constructed and the existing sett closed under licence
from English Nature. The sett was monitored and the level of activity indicated that it was
being used on a regular basis and it was expected that the new sett would provide a
suitable long-term refuge for badgers excluded from the sett which was closed. No
further monitoring of badger activity at the artificial sett was required. As expected in the
ES, no other badger mitigation measures were considered necessary. Based on animal
mortality data at OYA the scheme did not appear to have affected badger casualties. No
further monitoring was required.
Reptiles - The translocation of reptiles from the footprint of the scheme and erection of
exclusion fencing was undertaken as expected. Monitoring of the reptile population was
specified and this would be reported on at FYA.
5.70 Based on the information available it was assumed that the impacts on the biodiversity
sub-objective were as expected.
Consultation
5.71 Devon County Council confirmed that two of the plots it will be taking over (plots 19 and 22)
contain species rich grassland and at the time of the joint site visit in September 2011 plot 19
and the verge of plot 22 had not developed a full closed sward and more time was required to
allow for the colonisation of wildflower species and the formation of a closed sward. At the
time DCC noted that the need for additional reseeding (with the same seed mix as originally
used) could be assessed if the closed sward fails to evolve prior to handover.
5.72 DCC has not visited the site recently and although not suggesting or requesting that remedial
steps be taken, it would like some reassurance from the HA that this issue has been
appropriately considered.
5.73 DCC also noted with regard to self-seeded gorse that it was agreed at the joint site visit that
where gorse had established it would be treated prior to handover. Unless treated there is a
risk that gorse encroachment could compromise the original design objectives.
Evaluation
A copy of the HEMP has been provided to POPE and this includes recommendations for
future management regimes taking biodiversity into account;
Hedgerow maintenance would avoid harm to Dormice and nesting birds, including special
care being taken to avoid damage to Dormouse nest boxes and tubes that are located in
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 54
established hedgerows and woodland areas that were retained undisturbed beyond
construction areas.
Species-rich grassland should be allowed to develop and be maintained – invading scrub
should be controlled. The level of cutting will depend upon how well the grassland
establishes.
As required by the Dormouse licence, the management requirements for woodland areas
have been set out in the HEMP.
Dormouse monitoring would continue in 2011 and until May 2012 with results provided to
Natural England and the Devon Biodiversity Records Centre. In addition, Dormouse nest
tubes would be placed in the new vegetation in May 2012.
Monitoring of the reptile population would be undertaken in September 2011 and May
2012 to determine the success of the project. The records would be sent to the Devon
Biodiversity records Centre.
5.74 At OYA, it was considered too early to evaluate the establishment of species rich grassland.
The HEMP states that a particular feature of the design of the scheme was not to spread
topsoil on areas to be grassed. This was to allow the natural recolonisation of native species
and to encourage the growth of wildflower species that would otherwise be out-competed by
rank grasses. A low maintenance seed mix was chosen to reduce the amount of cutting
necessary. The HEMP notes that the grassland areas established very slowly in the early
years and that maintenance of grassland outside verges and visibility splays during the five
year aftercare period has included cutting once per year in September with gorse removal
identified to be carried out prior to handover in June 2012. Figure 5.6 illustrates that this has
happened, although some gorse was evident during the FYA site visit in the central reserve
and in the vicinity of the attenuation pond (see Figure D.8 in Appendix D.2).
Figure 5.6 – Example of gorse control, with spray drift also affecting adjacent grassland
5.75 Based on the FYA site visit, grassland areas have generally become established although
this is noticeably slower on some of the cutting/embankment slopes and verges (Figure 5.7
below).
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 55
Figure 5.7 – Example of bare substrate on cutting slope which vegetation is slowly beginning to
colonise and in time is likely to increase through natural regeneration
5.76 The grass seed mix was agreed with Devon CC and included Fescues, Bents and Meadow
Grass. No specific information has been made available to POPE which would confirm the
current status of species diversity within the grassland areas.
5.77 With regard to Dormice, for monitoring purposes, 20 Dormouse nest tubes were installed in
June 2007 in the retained vegetation adjoining the newly planted vegetation around the
junction. The 17 Dormouse nest boxes were concentrated in the woodland and high value
hedgerows north-east and south-west of the junction and in the retained vegetation alongside
the A30 where signage works were completed in 2006.
5.78 The final Dormice monitoring report has been provided to POPE which concludes that
“Dormice are still present around the Merrymeet junction and are breeding. Nests have been
found in both boxes and tubes across all areas of the site in all types of suitable vegetation.
The fact that Dormice have been recorded in all types of suitable habitat surrounding the
junctions suggests that once the newly planted vegetation has become more established it is
likely that Dormice will also use this”. It also notes that “The nest boxes and nest tubes
installed as mitigation are of benefit to the species by providing additional nesting
opportunities”.
5.79 With regard to reptiles, two years of monitoring was required as part of the mitigation strategy
to assess the success of the mitigation and the Final Reptile Monitoring Report has been
provided to POPE. It notes that reptiles were recorded on only one of the seven survey visits
in 2011(August and September) and this was a Common Lizard. Common Toads were
recorded on every visit. It was noted on the third visit that much of the road verges had been
cut by machine which rendered the habitat less suitable for reptiles. The report considered
that this constraint may have affected the survey results thereafter.
5.80 The Reptile Monitoring report concludes that “while reptiles still inhabit the monitoring area,
albeit in low numbers, there is little evidence to suggest that at this stage in the regeneration
of habitat that favourable conditions have been achieved. It is likely that as the habitat
matures there will be a natural colonisation of reptiles to the affected areas, but at this stage it
appears that this has not yet happened to any great extent”.
5.81 At OYA the MAC provided animal mortality data for the A30 Merrymeet junction. Although
this might not be exhaustive, it showed one badger casualty in 2004 prior to the scheme,
none during construction and after opening one in 2007 and one up to May 2008, indicating
that the scheme did not appear to have affected badger casualties.
5.82 The situation remains the same at FYA with animal mortality data from May 2008 up to
January 2012 in the immediate vicinity of the junction showing one badger casualty in 2009.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 56
5.83 It is considered at FYA that impacts on Biodiversity are as expected; measures have been
taken to reduce the effects of the scheme on protected species including badger, dormouse,
birds and reptiles. Dormice are still present around the junction and are breeding, although at
this stage favourable conditions for reptiles to recolonise the habitat areas does not appear to
have been achieved. New planting has mitigated for the loss of existing vegetation and with
continued management grasslands are likely to develop some species diversity as expected.
Heritage
5.84 The AST stated that the no nationally important archaeological sites or buildings would be
affected by the proposals. There would be loss of potential archaeological deposits identified
by geophysical survey and approximately 170m of historically ‘important’ hedgerows would
be removed.
5.85 The ES noted that the study area contained no scheduled monuments, conservation areas,
registered parks and gardens or historic battlefields. The granite gateposts of Narraway
House to the north of Whiddon Down are Grade II listed these would not be affected by the
scheme.
5.86 There would be some loss of historically important hedge-banks in an area where previous
road improvements have already affected the field pattern.
5.87 A programme of monitoring and investigation during construction would be carried out to
record any significant archaeological deposits or features which might be encountered. Any
significant archaeological finds would be analysed and the results published.
5.88 The OYA report noted that:
The Grade II listed gateposts at Narraway House which were considered to be of local
importance were not affected by the scheme as expected.
It was confirmed that recording of the removal of historically important hedgerows was
undertaken and a copy of the archaeology report was provided.
The site archive would be presented for permanent storage at the Royal Albert Memorial
Museum in Exeter. At OYA it was understood that the archive would be deposited
before the end of the year (2008).
A short note had been produced for the Devon County Archaeological Journal but at
OYA it was not certain if it had been printed, this was being checked by the Contractor
and if necessary it would be resubmitted for the 2009 journal.
As the Devon County Archaeologist had not received a copy of the archaeological report
it was suggested that they be provided with a copy.
Consultation
5.89 Devon County Council has confirmed at FYA that a copy of the archaeology report has been
provided for its records.
5.90 The Archaeological consultant explained that the Royal Albert Memorial Museum in Exeter
has a moratorium on accepting archives for long-term storage and that they (the
Archaeological Contractor) is holding the archive for this scheme pending a decision from the
Museum on new accessions.
5.91 With regard to the article for the Devon County Archaeological Journal, having checked the
records it would appear that this has not been submitted yet and will be for the next
proceedings which will be the 2013 issue.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 57
Evaluation
5.92 The Archaeological Assessment Report notes that a series of former field boundaries were
recorded and correspond to boundaries illustrated on 19th century tithe maps. Several
hedgebanks considered to be of historical importance were breached during the development
work and only one revealed any dating evidence; a damaged base of a hand blown glass
bottle of probably 17- 18th century date (the reports says that this would not be retained).
5.93 One undated length of an earlier field boundary ditch, not related to the Tithe field pattern,
was the only additional archaeological feature recorded.
5.94 At FYA impacts are considered to be as expected.
Water Quality and Drainage
5.95 The AST stated that environment surface water drainage from new carriageway areas would
use the existing surface water drainage system and that additional paved area would be
mitigated by additional attenuation/ interception. A neutral impact was assessed overall.
5.96 The ES noted that the scheme crosses high ground at the headwaters of the River Teign.
When open to traffic, the majority of the road drainage would be directed to an attenuation
pond, the remainder would discharge to existing outfalls. The pond would intercept
accidental spillage of pollutants and control rate of discharge to the local watercourse. The
flow regime of existing watercourse would not be affected by the scheme.
5.97 The OYA report concluded that, as expected, road drainage for the central section of the
scheme was directed to the new attenuation pond, with the remainder discharging to existing
outfalls. Rates of discharge were attenuated and pollution control measures had been
incorporated into the attenuation pond.
5.98 At the request of the Environment Agency (EA), the central reserve was seeded and not hard
paved. The drainage system incorporated various surface and ground water collecting types
including open drainage channels at the top of cuttings and combined filter/carrier drain within
the eastbound loop.
5.99 Stone filled Counterfort drains incorporated into the steeper cutting slopes to prevent erosion
and soil slippage were visually prominent at OYA. Slopes were stabilised using geotextile
mat on slopes steeper than 1:3, with the grass mix hydraseeded.
5.100 Based on the information available and confirmation from the Environment Agency that the
scheme had been constructed in accordance with EA requirements, it was assumed that the
impacts on the water sub-objective were as expected at OYA.
Consultation
5.101 The EA confirmed that in 2012, it was not aware of any problems with the scheme.
Evaluation
5.102 The Counterfort drains are still conspicuous at FYA (Figure 5.8 below); although where they
are located within planting plots, once planting reaches canopy closure the stoned surface
will be concealed. Figures D.15 and Figure D.16 in Appendix D.2 illustrate the attenuation
pond at FYA compared to OYA.
5.103 No new information has been made available to POPE that would indicate that drainage is
performing other than as expected and it is assumed that the impacts on the water
sub-objective remain neutral as expected.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 58
Figure 5.8 – View from A30 overbridge to counterfort drains alongside east bound carriageway
Journey Ambience
5.104 The AST stated that there would be no change to Traveller Care Indicators and views would
be largely unchanged. Stress would remain low with the scheme in place. The impact was
assessed as neutral overall.
5.105 The ES stated that the traveller views from the A30, A382 and C50 would be largely
unchanged as a result of the scheme; restricted in close proximity to the junction in cutting
and more open on the A30 further east and west. There would be new views to the
southwest from the Merrymeet overbridge.
5.106 Driver stress would be reduced due to improved safety, reduced delays and improved
journey time reliability. The quantified assessment showed driver stress to be low for both the
Do Minimum and Do Something scenarios.
5.107 Traveller facilities would still be accessible at Whiddon Down Services. The existing A30
lay-by located 500m west of the existing roundabout would be closed to avoid conflict of
vehicle movements. Other existing lay-bys on the A30 outside the scheme limits would
remain.
5.108 At the OYA stage it was considered that the impact of the scheme on journey ambience was
generally as expected for driver views, driver stress and traveller facilities. Anecdotally, it was
understood that people living locally and commuters had raised concerns about what they
considered to be poor advance signage of the junction.
Consultation
5.109 No responses received.
Evaluation
5.110 Due to the significant variation in traffic flows during the summer months and at holiday
weekends compared to other times of the year, the benefits of the scheme vary throughout
the year, and at the busiest times the long traffic queues at the roundabout are now avoided
as the roundabout been removed.
5.111 Since OYA the advanced directional signs on the A30 have been changed the junction name
to Whiddon Down to avoid confusion with other Merrymeet Junctions.
5.112 Traveller care remains neutral as at OYA.
5.113 Overall at FYA it is considered that impacts are better than expected in the summer months
and at holiday weekends, and as expected at other times of the year.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 59
5.114 Table 5.5 summarises the evaluation of the scheme’s impact on journey ambience.
Table 5.5 – Summary of the schemes impacts on Journey Ambience
Traveller Factor Score FYA evaluation
Views Neutral Traveller views from the A30, A382 and C50 are largely unchanged as a result of the scheme; restricted in close proximity to the junction in cutting and more open on the A30 further east and west. As expected there are new views to the southwest from the Merrymeet overbridge, although these will become more restricted as planting matures.
Stress – (frustration, fear of accidents and route uncertainty)
Beneficial / Neutral depending upon season
The replacement of the roundabout with the junction and overbridge
has reduced delays and improved journey time reliability for through
traffic, which will have reduced the frustration element for drivers. The
removal of the roundabout and associated long delays during the
summer months and holiday weekends will have reduced the fear of
potential accidents for drivers.
Signing has been improved since OYA with local destinations now identified. The junction is also now known as Whiddon Down and the advanced directional signs have been changed to reflect this, which has helped avoid potential confusion with other Merrymeet junctions in the South West.
Care Neutral The Whiddon Down services remain accessible from the A30 and are
signed off the dual carriageway. There is no evidence to suggest that
the closing of the lay-by has been problematic for drivers.
Summary Score Beneficial/Neutral
Beneficial for summer months and holiday weekends.
Neutral at other times of year.
Physical Fitness
5.115 The AST stated that there would be no change in the number of trips by pedestrians or
cyclists with a neutral impact assessed.
5.116 The ES stated that there were no existing facilities for pedestrians, cyclists or equestrians to
cross the A30 at the existing roundabout. The volume and speed of traffic meant that
crossing was very hazardous. As there was no evidence of significant demand, no provision
would be made for additional facilities.
5.117 A wider verge would be provided on the loop road and overbridge, which could provide a safe
route for pedestrians. The ES suggested that this verge could be upgraded to a segregated
route should a demand be identified after the scheme was opened. Cyclists and equestrians
would be encouraged to use the new carriageway over the A30.
5.118 At OYA Devon CC commented that reports received from cycle users indicated that they
welcomed the new junction as it was safer than the previous roundabout as the severance
issues were reduced. Signage warning drivers that cyclists use the area would have been
helpful, as would signage indicating to cyclists that there were alternative quieter
long-distance parallel routes available, by using the ‘old’ pre-1970s A30.
5.119 No information was made available with regard to pedestrian or equestrian use of the
overbridge.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 60
Consultation
5.120 DCC stated that Whiddon Down interchange is one of the options they are considering for
managing the Cycle West route from Exeter to Okehampton.
5.121 The DCC Road Safety Audit team considered the junction safe, convenient and comfortable
due to its open landscaping
Evaluation
5.122 At OYA eight cyclists were observed crossing the A30 via the overbridge in the 12 hour
manual count period. At FYA twelve cyclists were observed in the 12 hour count period. This
would suggest that the opportunity presented by the overbridge for safe crossing is still being
taken albeit by small numbers of users.
5.123 As at OYA, no information on pedestrian or equestrian use of the overbridge has been made
available for this evaluation. The wide grass verges have been maintained and continue to
allow access via the loop roads to the overbridge (see Figure 5.9 below). There is only a
narrow hard paved area across the bridge itself.
5.124 It would appear that there has been insufficient demand post opening for the facilities to be
upgraded to a segregated route and impacts are considered to be neutral as expected.
Figure 5.9 – Grass verge at edge of loop road carriageway, providing safe crossing of the A30
Summary of Evaluations
5.125 The following table represents a summarised evaluation of the effects of the scheme on the
current WebTAG environment sub objectives. The forecast score of the AST is compared
against the evaluation at this FYA stage.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 61
Table 5.6 – Summary of Environment Sub-objectives Evaluations
Origin of
Assessment AST
(Forecast)
EST (OYA
Evaluation)
EST (FYA Evaluation)
Sub Objective Summary Assessment
Noise Not significant Not
summarised
Based on the before scheme and FYA observed
traffic data it can be assumed that in line with POPE
methodology noise due to traffic is as expected for
the A30 and C50 i.e. the changes in flow are no
more than +25% (increase) or -20% (decrease)
than forecast, including HGVs
For the A382 west of the junction overall traffic is
21% greater than expected, however, HGV
numbers have increased by 49% and it is possible
therefore that noise due to traffic could be worse
than expected for the 3 properties and Travelodge
within 300m of this route, and for the village of
Whiddon Down where it was not expected in the ES
that any noise impacts would occur.
Not significant As Expected for
A30 and C50
Worse than Expected for
A382
Local Air Quality Not significant Not
summarised
Observed traffic flow has not changed significantly
as a result of the scheme. There are no properties
within 200m of the A30 east of junction, and only 1
property within 200m of the A382. As traffic flows
on the A382 are relatively low it is unlikely that the
higher observed traffic and HGVs would cause any
breach in air quality criteria, especially given the
rural nature of the area.
Not significant
As Expected
Greenhouse
Gases (Carbon
tonnes / year)
Slightly
adverse
Opening Year
+ 39
Better than
expected
Using the observed flows and latest version of
COBA total Carbon emissions are much higher than
expected because observed traffic flows are much
higher than expected. However, the Base flows
were also much higher so the net change in Carbon
emissions is much lower than expected at +3
tonnes/year in 2008 and +16 tonnes per year in
2012.
Not significant
Better than
expected
Landscape Neutral As expected
Landscape planting is establishing satisfactorily and
subject to ongoing maintenance and management
should reach its longer term objectives for visual
screening and landscape integration by the design
year.
Neutral As
Expected
Townscape Not significant N/A N/A
Biodiversity Slight adverse As expected
Measures have been taken to reduce the effects of
the scheme on protected species including
badgers, dormice, birds and reptiles. Dormice are
still present around the junction and are breeding,
although at this stage favourable conditions for
reptiles to recolonise the habitat areas does not
appear to have been achieved. Limited loss of
some parts of ancient Devon hedge banks as
expected. New planting has mitigated for the loss of
existing vegetation and with continued management
grasslands are likely to develop some species
diversity.
Slight Adverse
As Expected
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 62
Origin of
Assessment AST
(Forecast)
EST (OYA
Evaluation)
EST (FYA Evaluation)
Sub Objective Summary Assessment
Heritage Slight adverse Not assessed
Archaeological mitigation was undertaken as
proposed in the ES including recording of
historically important hedgerows. One undated
length of pre 19thC field boundary ditch was the
only additional archaeological feature recorded. At
FYA outstanding reporting issues have been
resolved.
Slight Adverse
As Expected
Water Neutral As expected
Mitigation measures have been incorporated into
the scheme in accordance with EA requirements
and there is no information available to POPE
which would indicate that they are performing other
than as intended.
Neutral As Expected
Journey Ambience Neutral Slightly worse
than expected
Traveller views largely unchanged
Driver stress benefited through reduced delays and
improved journey time reliability for through traffic
particularly during peak holiday times
Signing has been improved since OYA
The services remain accessible closing the lay-by
does not appear to have been problematic.
Better than
expected peak
holiday times
Neutral As
Expected other
times of year
Physical Fitness Neutral As expected Cyclists continue to use the overbridge as a safe
means of crossing the A30. No specific information
available for pedestrian or equestrian usage and it
would appear that there has been insufficient
demand post opening for the facilities to be
upgraded to a segregated route, however. the wider
grass verges are maintained allowing pedestrian
access via the loop roads as expected.
Neutral As Expected
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 63
Key Findings on Section 5: Environment
Noise
At FYA traffic flows on the A30 are in line with forecasts and it is assumed that noise
due to traffic is as expected. On the A382, HGV numbers are 49% higher than before
the scheme and noise could be worse than expected for the few properties nearby and
for Whiddon Down where no noise impacts were expected as a result of the scheme.
Local Air Quality
Although traffic flows are higher than expected on A382 and A30 east of the junction,
overall traffic changes due to the scheme are low and it is unlikely that they would
cause any breach in air quality criteria, especially given the rural nature of the area.
Greenhouse Gases
Negligible increase of 1% additional carbon emissions with scheme at FYA, similar to
forecast.
Landscape
Landscape planting is establishing satisfactorily and subject to ongoing maintenance
and management should reach its longer term objectives for visual screening and
landscape integration by the design year.
Biodiversity
Measures have been taken to reduce the effects of the scheme on protected species
and new planting mitigates for the loss of vegetation. Dormice are still present around
the junction and are breeding, although at this stage favourable conditions for reptiles
to recolonise the habitat areas does not appear to have been achieved.
Heritage
Archaeological mitigation was undertaken as proposed in the ES including recording of
historic hedgerows and very little of archaeological interest was found.
Water
Mitigation measures have been incorporated into the scheme in accordance with EA
requirements and based on the information available there is nothing to suggest that
they are performing other than as intended.
Journey Ambience
Traveller views are largely unchanged as expected.
Driver stress has benefited by reduced delays and improved journey time reliability for
through traffic particularly during peak holiday times. Signing has been improved since
OYA.
The services remain accessible and closing the lay-by does not appear to have been
problematic for drivers.
Physical Fitness
Cyclists continue to use the overbridge as a safe means of crossing the A30. It would
appear that there has been insufficient demand post opening for the facilities for
pedestrians to be upgraded to a segregated route although ongoing maintenance of
the wider verges allows continued pedestrian access to the overbridge.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 64
6. Accessibility and Integration
Accessibility
Severance
6.1 The AST forecast no direct severance effects from this scheme.
6.2 The only specific provision for vulnerable users in the scheme is the inclusion of a footway on
the western side of the overbridge follow recommendation by the Road Safety Audit.
However, there is no footpath on the approaches to the junction and overbridge.
6.3 As noted in the OYA report, the new overbridge at the junction enables pedestrians and
cyclists to cross the A30 dual carriageway potentially more safely and with reduced delays.
6.4 Counts of cyclists using the junction were included in the 12hour manual classified counts
undertaken for the one and five years after studies. These showed that:
In the 12 hour period on the weekday survey dates there were eight cyclists in 2008 and
in 2012 there were 12.
All surveyed cyclists travelled between the A382 and the minor roads north of the
junction using the overbridge.
6.5 Given that there are few houses and no services on the northern side of the A30 at this
location it is very likely that the number of pedestrians using the route is also low.
Integration
6.6 The OYA study concludes that the forecasts for the impact of this scheme on the integration
sub-objectives were all as expected.
6.7 There was a beneficial impact forecast on Land-use Policy and the OYA study found the
scheme was consistent with a number of regional and local policies which supported the
scheme specifically or its contribution to the general objective to improve the region’s
transport network.
6.8 At the FYA stage, there has been no change to the land use policy of the rural area within
which the junction is located, hence that impact is neutral while the wider policies which
support schemes to maintain and enhance the trunk road network remain broadly similar,
thus the evaluation of beneficial impact observed at OYA remains valid.
Key findings from section 6: Accessibility and Integration
Accessibility
The scheme was not expected to have accessibility benefits.
The overbridge route provides a better crossing of the A30 for cyclists and pedestrians
than the former roundabout. However there are few of these users here and there is no
formal provision except a footway on the bridge.
Integration
At OYA it was confirmed that the scheme was consistent with policies in place at the
time of its construction and there has been no significant change since, hence
evaluation is a beneficial impact due to its contribution toward improving transport links
to regeneration areas in Cornwall and North Devon.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 65
7. Conclusions 7.1 To conclude this report, this section summarises the scheme’s success in meeting its specific
objectives, and assesses the scheme’s impacts against those forecast.
Success against Objectives
7.2 Objectives can be categorised as follows:
NATA (New Approach to Appraisal) objectives: Impacts are assessed against the
Government’s five objectives for Transport; environmental impact, safety, economy,
accessibility and integration; and
Scheme specific objectives.
7.3 The success of the scheme measured against the NATA objectives is presented in Appendix
A, in the form of an Evaluation Summary Table (EST).
Scheme Specific Objectives
7.4 Drawing upon information presented in this report, a summary of the scheme’s success
against the scheme specific objectives listed previously in the Introduction of this report is
provided in Table 7.1 below. .
Table 7.1 – Success against Scheme specific Objectives
Objectives (from Non-technical Summary and Appraisal Summary Table) Objective
Achieved?
Improve safety at the junction by removing problems particularly associated with A30 traffic stopping at the roundabout, including a high rate of fatalities.
Yes
Reduce congestion occurring at the roundabout at peak times, and during the holiday period.
Yes
Reduce journey times for A30 through traffic. Yes
Retain a full movement junction. Yes
Avoid environmental impact on Dartmoor National Park which lies on the highway boundary.
Yes
Reduce environmental effects as far as practicable. Yes
7.5 In summary, the results in Table 7.1 show that based on the data available at this Five Years
After (FYA) stage, the junction improvement at Whiddon Down on the A30 has achieved all of
its specific objectives.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 66
Appendix A AST and EST
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 67
Table A.1 – Appraisal Summary Table (Scheme Assessment Report, January 2003)
Option
Grade Separated Junction
Description: Existing junction on A30 at Merrymeet grade separated by removing the roundabout and providing a free flowing A30 with associated merge and diverge lanes and a
connecting bridge.
Problems: This is the only roundabout along the A30 Dual Carriageway between Exeter and Okehampton, requiring drivers to slow down and Give Way. The roundabout has
an accident problem and suffers frequent delays, particularly during times of peak holiday traffic.
Present Value of Costs to Government: £6.5m
OBJECTIVE
SUB-OBJECTIVE QUALITATIVE IMPACTS QUANTITATIVE ASSESSMENT ASSESSMENT
Environment
Noise Noise levels not assessed as change in traffic levels < 25% Not assessed. Not significant
Local Air Quality No changes in traffic flows of 10% or more are expected as a result of the Published Scheme. Local Air Quality has therefore been scoped out from the appraisal as per guidance in TAG Unit 3.3.1
Not assessed. Not significant
Greenhouse Gases For both 2006 and 2021 scenarios, the total CO2 emissions predicted with the Scheme in operation (Do-Scheme) are slightly higher than those predicted for the Do-Minimum scenario.
The effect of Scheme is therefore considered to be slightly adverse.
CO2 – tonnes per year
DO MINIMUM
Present (2003) = 3,543
Do-Minimum 2006 = 3,860
Do-Minimum 2021 = 4,366
DO SOMETHING
Do Something 2006 = 4,276
Do Something 2021 = 4,760
CO2 – tonnes per year (Change)
2006 (DM - DS) = + 416.01
2021 (DM - DS) = + 394.82
Landscape Some loss of established highway planting but some attenuation of notch effect of A30 seen from NW. New planting, reduced lighting and new bridge would redress the balance.
Neutral
Townscape Not applicable Not significant
Heritage of Historic Resources
No nationally important archaeological sites or buildings will be affected by the proposals. There would be a loss of potential archaeological deposits identified by geophysical survey and approximately 170m of historically ‘important’ hedgerows also would be removed.
Slight adverse
Biodiversity Some species rich Devon hedgebanks would be partially lost, together with some areas of species rich grassland, although both would be largely mitigated by new planting. Some minor impact is likely on habitats for reptiles, badgers, dormice and breeding birds, although these are largely mitigated within the scheme design.
Slight Adverse
Water Environment Surface water drainage from new carriageway areas to utilise existing surface water drainage system and additional paved area mitigated by additional attenuation/interception.
Neutral
Physical Fitness No change in number of trips by pedestrians or cyclists Neutral
Journey Ambience No change to Traveller Care Indicators, views would be largely unchanged. Stress would remain as Low with the scheme in place.
Not applicable Neutral
Safety
Accidents Total Accident Impact identified at this stage Decrease 243 PIA (60yr Low Growth)
Decrease 287 PIA (60yr High Growth)
PVB £21.1m Low Growth
PVB £24.7m High Growth
Security Reduced congestion, large reduction in traffic slowing down. Neutral
Economy
Transport Economic Efficiency
Reduced congestion and improved journey times as a result of new layout. NPV £32.0m - £39.7m
BCR 5.1-6.3
Consumer Users PVB £10.6m-£12.7m
Business Users PVB £8.2m-£9.9m
Public Accounts PVC £7.9m-£7.5m
Reliability Scheme causes slight improvements in journey times through junction. Driver Stress – Do Min 28%. Do Something 28%
Neutral
Wider Economic Impacts
Not designated Regeneration Area – However does serve Devon and Cornwall Regeneration Area
Development depends on scheme
No
Accessibility
Option Values Not applicable for road schemes N/A
Severance No direct severance effects Neutral
Access to the Transport System
No provisions for the increase of routes or frequency of public transport Neutral
Integration
Transport Interchange None N/A N/A
Land-use Policy Facilitation of national, regional and local transport and economic policies outweighs hindrance of regional and local polices on protection of agricultural land, landscape and cultural heritage
Beneficial
Other Government Policies
Complies with relevant Government policies Neutral
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 68
Table A.2 – Evaluation Summary Table (EST)
OBJECTIVE
SUB-OBJECTIVE
QUALITATIVE IMPACTS QUANTITATIVE ASSESSMENT
ASSESSMENT
Environment
Noise The change in traffic flow due to the scheme has been small (<10%), as forecast, so the impact on noise is not significant. There has been a larger increase on the A382 to the West of the junction, especially in HGV numbers, so there could be a slight impact along this route.
N/A Neutral, as expected for A30 and C50. Worse than expected on
A382
Local Air Quality Changes in traffic flow as a result of the scheme have all been small (<10%), as forecast, so the impact on local air quality is not significant. There has been a larger percentage increase in traffic on the A382 through Whiddon Down village but the numbers of vehicles is relatively low and it is unlikely that the additional traffic and HGVs would cause any breach in air quality criteria.
N/A Neutral. As expected
Greenhouse Gases Carbon emissions are much higher than expected because observed traffic flows are much higher than expected. However, the Base flows were also much higher so the net change in Carbon emissions is actually much lower than expected at +3 tonnes/year in 2008 and +16 tonnes per year in 2012.
Forecast (using latest guidance) +39 tonnes
Outturn (2008) +3 tonnes
Outturn (2012) +16 tonnes
Not significant
Better than expected
Landscape Landscape planting is establishing satisfactorily and subject to ongoing maintenance and management should reach its longer term objectives for visual screening and landscape integration by the design year.
N/A Neutral. As Expected
Townscape Not applicable N/A Neutral. As Expected
Heritage of Historic Resources
Archaeological mitigation was undertaken as proposed N/A Slight adverse. As expected
Biodiversity There have been adverse impacts but mitigation measures have been put in place. Hedgebanks have been lost but new planting has been provided and managed
N/A Slight adverse. As expected
Water Mitigation measures were incorporated into the scheme and there is no evidence that they are not working as expected N/A Neutral. As Expected
Physical Fitness Cyclists use the new overbridge but overall volumes of vulnerable users is low N/A Neutral. As Expected
Journey Ambience Traveller views are largely unchanged and driver stress has reduced. Signing improvements have been made since the OYA study and the removal of the lay-by has not caused a problem
N/A Neutral. As Expected
Safety
Accidents There has been a Personal Injury Accident saving of 2.6 per year after an initial accident increase in the first year since opening. The accident saving is one-third less than expected.
Decrease 266 PIA over 60yr PVB £7.4m
Security No change N/A Neutral. As Expected
Economy
Transport Economic Efficiency
Reduced congestion and improved journey times as a result of new layout. Better than forecast NPV 25.1m
BCR 3.6
Consumer Users PVB £13.8m
Business Users PVB £13.5m
Public Accounts PVC £9.5m
Reliability Removal of geometric delay benefits particularly A30 through traffic and right turning movements at peak times N/A beneficial (better than expected)
Wider Economic Impacts
No local impact but will slightly benefit regeneration areas elsewhere served by the A30 N/A Neutral. As Expected
Accessibility
Option Values Not applicable to road schemes N/A N/A
Severance Bridge reduces severance for small number of users, but no formal provision except footway on overbridge. N/A Neutral. As Expected
Access to the Transport System
No impact N/A Neutral. As Expected
Integration
Transport Interchange
None N/A N/A
Land-use Policy General policies unchanged since OYA N/A Beneficial. As expected
Other Government Policies
General policies unchanged since OYA N/A Neutral. As Expected
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 69
Appendix B : Traffic
B.1 Further traffic data
Sources of A30 traffic data
B.1.1 Figure B.1 summarises the TRADS data sites used in this report for A30 traffic data.
Figure B.1 – TRADS sites on A30
Table B.1 – TRADS sites on A30
Site ref Location Period producing
data
1/607 and 1/608 West of the A377, west of Exeter urban area 1995-2005
1/30012532
1/30012533 West of the scheme
2005- current
1/30012538
1/30012539
West of the scheme
between the A382 and the B3250 (Okehampton)
2005- current
B.1.2 Although the sites 607 and 608 are not in the same location as 30012532/3 there are no
junctions other than with minor roads between, thus these two pairs of sites can be
considered directly comparable. Figure B.2 shows the long-term trend from these sites.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 70
Figure B.2 – Long term trend on A30
B.1.3 To supplement the average weekday traffic figures given in Table 2.1, the equivalent average
daily figures are presented in Table B.2.
Table B.2 – Average Daily Traffic volumes around the Junction
Location
Average Daily Traffic (AADT) % change
Before One Year
After Five Years
After One Year
After Five Years
After
A30 east of jct 28,800 29,400 30,200 2% 5%
A30 west of jct 25,400 26,300 26,600 4% 5%
A382 Whiddon Down 6,500 6,300 7,400 -3% 14%
Minor rd 1,400 1,000 1,200 -24% -10%
Total through jct 31,000 31,500 32,700 2% 6%
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 71
Appendix C : Statistical Significance Tests
on Safety Data
This appendix details the statistical significance testing undertaken on the accident data used in the safety section 3 of this report.
C.1 Significance of Difference in numbers of
Accidents and Casualties in before and after
periods Chi-square Tests by Time period
C.1.1 The Chi-Square test is a statistical test which can be used to test whether the difference in
accident numbers in the two five year periods is significant or not compared to the null
hypothesis that there is no change in the accident rate over the two periods. This test was
used on the accident and casualty numbers as shown in section 3 of the main report Table
3.1 to 3.4 to determine whether the number of occurrences in the five years after period was
significantly different to the number in the five years before period. This tests the likelihood
that the figures could have occurred by chance or are really different using a confidence level
of 95%.
C.1.2 The results of the tests are shown in Table C.1.
Table C.1 – Statistical Significance Tests on Changes in numbers of Accidents and Casualties before
and after
Area Test: Change in numbers of Conclusion
A30 2km around Whiddon Down junction
Personal Injury Accidents Reduction is not significant
Personal Injury Accidents (considering only 3.5 years since 2008)
Reduction is not significant
Casualties Reduction is not significant
All accidents including damage only Reduction is significant
Narrow area 0.5km around Whiddon Down junction
All Accidents Reduction is significant
All Casualties Reduction is significant
All accidents including damage only Reduction is significant
C.1.3 It can be seen from Table C.1 that the reductions in personal injury accident and casualties
are statistically significant only within the 0.5km area focussed around the junction.
C.1.4 These findings indicate that it is likely that there is a real reduction in the number of accidents
and casualties rather than it having occurred by chance alone. Thus we can infer that the
scheme is responsible for the reduced accident and casualty numbers in the post opening
period. However, it is widely recognised that national statistics on road accidents show a
long-term trend towards a reduction in road accidents17
. Hence, at least some of the
17 Reported Road Casualties Great Britain, DfT
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 72
reduction in accidents can be attributed to national trends so we now consider further tests to
compare the trend observed in the area around the scheme with a comparable rural section
of the A30 between the Whiddon Down junction and Exeter, namely a section including the
Woodleigh junction near Cheriton Bishop. This is examined in the sub-section below.
C.2 Significance of changes in Accident numbers
Compared with Control site C.2.1 It is widely recognised that accidents numbers generally are declining over time. For this
reason DfT guidance on monitoring the effectiveness of read schemes recommends the use
of a control site18
. The control site needs to share all the characteristics of the scheme site.
C.2.2 The two statistical tests recommended in DfT guidance19
using a control site are:
The Tanner k test can be used to show how the accident numbers at a site change
relative to control data.
The chi-squared test can be used to determine whether the change in accidents was
produced by the treatment or whether this occurred by chance. This test thus determines
whether the change is statistically significant.
C.2.3 In the scope of this study, the control site is taken as a section of the A30 which is similarly
rural in nature having the national speed limit and including an all-movements
grade-separated junction.
C.2.4 The accident numbers at the control section of the A30 and the narrow scheme extent used
in these tests are shown in Table C.2.
Table C.2 – Accident numbers in before and after periods on scheme section and at control section
Five Year Period
Number of Accidents on A30
Total 0.5km around Whiddon Down
jct
A30 near Woodleigh jct
Before (a) 21 (c) 7 (g) 28
After (b) 7 (d) 5 (h) 12
Total (e) 28 (f) 12 (n) 40
Tanner k test
C.2.5 The Tanner k test is used to show how the accident numbers at a site change relative to
control data. In the case of this scheme, we have compared the accident rate on the section
of the A30 including Whiddon Down junction with the improvement on the section of the A30
near the Woodleigh junction which has not been subject to any significant safety
improvements within this time period.
C.2.6 Table C.3 shows how this has been calculated based on the figures in Table C.2 and the
conclusions which are drawn.
18 A Road Safety Good Practice Guide for Highway Authorities 2
nd edition, DfT
19 Ibid, Appendix B
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 73
Table C.3 – Tanner k test results on accident numbers within scheme area only
Formula Data Result Conclusion
k = b/a
d/c Accidents 0.47
as k < 1 there has been a decrease in accidents numbers relative to the control.
The decrease is 53 %
C.2.7 The results of the Tanner k test shown in Table C.3 show that the change in accident
numbers on this narrow section around the junction is statistically significant, representing a
real saving of 53% when compared with the reduction in numbers observed on a control
section of the A30 during the same period.
Chi-square Tests on Accident Numbers within scheme area only compared with control
site
C.2.8 We now test how confident we can be that the greater reduction in accidents around the
junction compared to the control section of the A30 is due to chance, or is likely to be directly
as result of the scheme. For this we use the chi-square in which the null hypothesis is that
the reduction in the accident rate between the before and after periods within the scheme
extent of the A30 is the same as that observed at the control section of the A30. The
chi-square formula gives a figure here which is compared with the standard table to give a
significance level. It is normal to consider a level of 95% significance represents a real
change; this requires a chi-square result of greater than 3.84.
C.2.9 Table C.4 shows how this has been calculated based on the figures in Table C.2.
Table C.4 – Chi-square test results
Formula Data Chi-
square Result
Conclusion
Accidents 0.46
The reduction in accidents around the Whiddon Down junction compared with the control section is no better than could have occurred by chance alone, based on a 95% confidence level.
C.2.10 The findings of the statistical tests presented in this appendix are discussed in the main
safety section of this report.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 74
Appendix D : Environment
D.1 Sources D.1.1 Standard list of information required to evaluate the environmental sub-objective.
Environment Specific Requirements OYA FYA
Environment Statement (ES) or if not a scheme requirement the latest Scheme Assessment Report (SAR).
A30 Merrymeet Junction Improvement Volumes 1, 2 and NTS February 2005
As at OYA
AST AST January 2003 As at OYA
Any amendments, updates or addendums to the ES/SAR or any relevant further studies or reports. Any significant changes to the scheme since the ES.
No amendments / significant changes to the scheme since the ES
As at OYA
As built drawings for landscape/biodiversity/environmental mitigation measures/drainage/ fencing/ earthworks etc.
Maintenance Manual and Appendices for Roadworks and Structures on CD including; Specification Appendices.
Planting As-Built
Landscape Design Environmental Masterplan Ecological Design )
As at OYA
Construction Environment Management Plan (CEMP)
Environmental
Management Plan (May
2007) is Appendix N of
the Roadworks
Maintenance Manual
which is included on the
CD.
As at OYA
Landscape and Ecology Aftercare Plan (LEAP).
Not produced for this scheme
H& S File – environment information Not available
Handover Environmental Management Plan (HEMP).
HEMP November 2011 and Handover Site Inspection Record for Environmental Mitigation 29.9.11
Relevant Contact Names for consultation. Provided As at OYA
Archaeological Reports (popular and academic).
Archaeological Assessment Report July 2006
As at OYA
The Road Surface Influence (RSI) value of any low noise surface installed
Provided
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 75
Environment Specific Requirements OYA FYA
The insulation performance properties of any noise barriers installed (The BS EN 1794-2 result provided by the noise barrier manufacturer)
N/A N/A
List of properties eligible for noise insulation. None eligible As at OYA
List of Part 1 Claims regarding noise/air quality/lighting
Provided
Reports for any pre/post opening survey and monitoring work e.g. for noise, biodiversity, water quality).
Report on Dormouse Monitoring (June 2008).
Final Dormouse Monitoring Report May 2012
Reptile monitoring to commence in September 2008.
Final Reptile Survey and Monitoring Report May 2012
A Combined Site Completion Report is being prepared for the works at Narraway Farm. These were improvement works to an adjacent field raising its quality from grade 5 to grade 3b and also addressing environmental concerns in respect of the disposal of the surplus materials to landfill.
Not provided
Animal mortality data Provided by the MAC for period 2004 to May 2008
Provided by the MAC for period May 2008 to January 2012
Post opening Non-motorised User (NMU) Audit or Vulnerable User Survey
The scheme predated NMU (Vulnerable) pre & post scheme surveys, this was not required under the contract & therefore none were carried out.
Any information regarding environmental enhancements to streetscape/townscape for bypassed settlements.
N/A N/A
Employers Requirements Works Information – environment section
Some information provided on CD – see above
Provided
Scheme Newsletters /publicity material/Award information for the scheme.
Newsletters obtained from the HA website.
Not aware of any awards
As at OYA
Other Area Road Users Satisfaction
Surveys June 2006 to May 2007 (during the road works)
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 76
D.2 Photographic Record of Scheme Including: ES Photomontages and OYA
vs FYA comparisons
ES Photomontage comparisons
Figure D.1 – View westwards from Whiddon Down Services, looking across the Troney Valley to Livaton and the A3124 overbridge (Figure D.2 completes
the panorama to the right).
Figure D.2 – FYA May 2012 similar view (taken from new A30 overbridge) with Narraway Farm to left of view
Narraway Farm
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 77
Figure D.3 – ES : View eastwards towards Merrymeet from the A3124 overbridge
Figure D.4 – FYA May 2012 looking along the A30 east towards the Whiddon Down junction and overbridge across the cutting
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 78
One Year After / Five Year After Comparison Photos
Figure D.5 – OYA (July 2008) Looking south (with C50 in foreground) to
the new junction with the A30, new planting and seeding on the cutting
slopes. A30 overbridge top right of view.
Figure D.6 – FYA (May 2012) Looking from A30 overbridge towards
C50 and planting on embankment slopes illustrating generally satisfactory establishment.
Figure D.7 – OYA (July 2008) Looking west from overbridge – the pale
green field in the middle foreground (left of the white van) has been
re-profiled with surplus soil and integrates well into the local landscape
Figure D.8 – FYA (May 2012) central reserve grassland slow to establish
as expected on substrate but clear of weeds although gorse establishing
between the barriers. Planting establishing satisfactorily.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 79
Figure D.9 – OYA (July 2008) Looking towards Narroway Farm
from earth mounding adjacent to approach road to the
overbridge. Travelodge is behind trees on left
Figure D.10 – FYA (May 2012) well established planting and no
evidence of noxious weed
Figure D.11 – OYA (July 2008) Looking east along the A30 with
overbridge on horizon visually closing the ‘notch’ in the cutting
Figure D.12 – FYA (July 2012) planting has not yet matured
sufficiently to visually reduce the width of the bridge
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 80
Figure D.13 – OYA (July 2008) Wide verge on approach to
Whiddon Down services from the A30
Figure D.15 – OYA (July 2008) View of attenuation pond, dry at time of
site visit, with distant views to Dartmoor National Park beyond.
Textmour reinforced soil slope was use
Figure D.14 – FYA (May 2012) Grass verge at edge of loop road
carriageway, providing safe crossing of the A30
Figure D.16 – FYA (May 2012) Vegetation including Gorse will require
cyclical maintenance and management to ensure attenuation pond
continues to function as intended.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 81
Figure D.17 – OYA (July 2008) Looking from A382. Counterfort
drains visible on cutting slope.
Figure D.18 – FYA (May 2012) similar view with Counterfort drains
still visible. Slow grassland establishment visible on verge in
foreground. Good plant growth in small island planting (to left of
mobile sign).
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 82
Appendix E : Glossary
Term Meaning
AADT Annual Average Daily Traffic. Average of 24 hour flows, seven days a week, for all days within the year.
AAWT Annual Average Weekday Traffic. As AADT but for five days, (Monday to Friday) only.
Accessibility Accessibility can be defined as ‘ease of reaching’. The accessibility objective is concerned with increasing the ability with which people in different locations, and with differing availability of transport, can reach different types of facility.
AST Appraisal Summary Table. This records the impacts of the scheme according to the Government’s five key objects for transport, as defined in DfT guidance contained on its Transport Analysis Guidance web pages, WebTAG
BCR Benefit Cost Ratio
This is the ratio of benefits to costs when both are expressed in terms of present value i.e. PVB divided by PVC
CO2 Carbon Dioxide, for transport, this is the main greenhouse gas
COBA COst Benefit Analysis – a computer program which compares the costs of providing road schemes with the benefits derived by road users (in terms of time, vehicle operating costs and accidents), and expresses the results in terms of a monetary valuation. The COBA model uses the fixed trip matrix unless it is being used in Accident-only mode.
DfT Department for Transport
Discount Rate The percentage rate applied to cash flows to enable comparisons to be made between payments made at different times. The rate quantifies the extent to which a sum of money is worth more to the Government today than the same amount in a year's time.
Discounting Discounting is a technique used to compare costs and benefits that occur in different time periods and is the process of adjusting future cash flows to their present values to reflect the time value of money, e.g. £1 worth of benefits now is worth more than £1 in the future. A standard base year needs to be used which is 2002 for the appraisal used in this report.
DMRB Design Manual for Roads and Bridges
DNP Dartmoor National Park
Do Minimum (DM) / Do Nothing (DN)
In scheme modelling, this is the scenario which comprises the existing road network plus improvement schemes that have already been committed.
In the case of this scheme, there were no other improvement schemes, so this was referred to in the appraisal as Do Nothing
Do Something (DS) In scheme modelling, this is the scenario detailing the planned scheme plus improvement schemes that have already been committed
EA Environment Agency
EN English Nature
EST Evaluation Summary Table. In POPE studies, this is a summary of the evaluations of the TAG objectives using a similar format to the forecasts in the AST.
FYA Five Years After
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 83
Term Meaning
HA, Highways Agency
An Executive Agency of the Department for Transport, responsible for operating, maintaining and improving the strategic road network in England.
HATRIS Highways Agency Traffic Information System The Highways Agency (HA) currently maintains, operates and develops three traffic databases and associated applications. The Traffic Flow Data System (TRADS) holds information on traffic flows at sites on the network. The Journey Time Database (JTDB) system holds information on journey times and traffic flows for links of the network. These two databases are known collectively as the HA Traffic Information System (HATRIS).
HEMP Handover Environmental Management Plan
HGV Heavy Goods Vehicle. In the context of this report, the precise definition of the term is dependent on the way that traffic is being measured. Currently, traffic flow data as measured by ATCs uses a length based classification – the term HGV is used to refer to vehicles greater than 5.2m. Shorter vehicles are classified as ‘light’.
KSI Killed or Seriously Injured KSI is the proportion of casualties who are killed or seriously injured and is used as a measure of accident severity
LMVR Local Model Validation Report
MAC Managing Agent Contractor – organisation normally contracted in 5-year terms for undertaking the management of the road network within a HA area.
MCC Manual Classified Count
NATA New Approach to Transport Appraisal was the basis of the standard DfT appraisal approach when this scheme was appraised.
NE Natural England
NO2 Nitrogen Dioxide
NRTF National Road Traffic Forecast. This document defines the latest forecasts produced by the Department of the Environment, Transport and the Regions of the growth in the volume of motor traffic. At the time this scheme was appraised, the most recent one was NRTF97, i.e. dating from 1997.
NTS Non-technical Summary of the Environmental Statement Describes the Published Scheme proposals and summarises the Environmental Statement in non-technical language.
OYA One Year After
Part 1 claims This is financial compensation which can be claimed by people who own and also occupy property that has been reduced in value by physical factors caused by the use of a new or altered road.
PIA Personal Injury Accident. A road traffic accident in which at least one person required
medical treatment.
POPE Post Opening Project Evaluation, before & after monitoring of all major highway schemes in England.
PM10 Particulate Matter measuring less than 10µm. This is the generally accepted measure of particulate material in the atmosphere likely to be inhaled by humans
Present Value Present Value is the value today of an amount of money in the future. In cost-benefit analysis, values in differing years are converted to a standard base year by the process of discounting giving a present value.
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 84
Term Meaning
PROW Public Right of Way
A public right of way is a way (a route over which people go) over which all members of the public have a right of passage. Public rights of way include footpaths, carriageways, bridleways
PVB Present Value Benefits Value of a stream of Benefits accruing over the appraisal period of a scheme expressed in the value of a Present Value
PVC Present Value Cost As for PVB but for a stream of costs associated with a project
RSA Road Safety Audit
STATS19 A database of injury accident statistics recorded by police officers attending accidents
T&EAR Traffic & Economic Assessment Report
In the case of this scheme, the appraisal of traffic and economic impacts were presented in this single report
TEE Transport Economic Efficiency
TEMPRO Trip End Model Program This is a PC program which provides access to the Department for Transport’s national Trip End Model projections of growth in travel demand, and the underlying car ownership and planning data projections.
TPI Targeted Programme of Improvements. Formerly, this was the title of Highways Agency’s programme of investment in improvements to the Trunk road and Motorway road network comprised of a number of major schemes each costing more than £5m. Now called Major Schemes and is for schemes over £10m.
TRADS Traffic Flow Data System
vpd Vehicles Per Day
VOC Vehicle Operating Costs These are costs to the user of the fuel and maintaining the vehicle.
webTAG Department for Transport’s website for guidance on the conduct of transport studies at http://www.webtag.org.uk/
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 85
Appendix F : Tables and Figures in this
Report List of Tables
Table 2.1 – Average Weekday Traffic volumes around the Junction 10
Table 2.2 – 12 Hour Traffic movements at junction 12 Table 2.3 – Total 12 hour Traffic flows using junction 12
Table 2.4 – Average Weekday HGV daily flow on non-trunk roads 15
Table 2.5 – Post opening: Forecasts vs. Observed traffic volumes (AADT) 17 Table 3.1 – Number of Personal Injury Accidents (2km/1.2 mile section centred on Whiddon Down) 23
Table 3.2 – Number of Personal Injury Accidents (0.5km/0.3 mile section centred on Whiddon Down) 24
Table 3.3 – Accident Rate Five Years Before and After compared to National Average 27
Table 3.4 – Forecast Personal Injury Accident savings 28 Table 3.5 – Forecast vs. Outturn Accident savings 29
Table 4.1 – Investment costs 33
Table 4.2 – Indirect tax impact 34
Table 4.3 – Present Value Costs 35 Table 4.4 – 60 year Economic Benefits (£m, 2002 prices, discounted) 36
Table 4.5 – Casualty severity modelling 37
Table 4.6 – 60 year Safety Benefits 38
Table 4.7 – Summary of Present Value Benefits 39 Table 4.8 – Present Value Benefits with indirect tax impact 39
Table 4.9 – Benefit Cost Ratio 40
Table 5.1 – Summary of Environmental Consultation Responses 44
Table 5.2 – Traffic Forecasts used in AQ Assessment vs. Outturn Flows 46
Table 5.3 – August Traffic Forecasts used in AQ Assessment vs. Outturn Flows 46
Table 5.4 – Carbon Emissions (tonnes in year) 49
Table 5.5 – Summary of the schemes impacts on Journey Ambience 59 Table 5.6 – Summary of Environment Sub-objectives Evaluations 61
Table 7.1 – Success against Scheme specific Objectives 65
List of Figures
Figure 1.1 – Location of A30 Whiddon Down scheme 1 Figure 1.2 – Scheme Summary 3
Figure 1.3 – Scheme Key Events Timeline 4
Figure 2.1 – National and Regional Traffic Trends compared with A30 traffic 7
Figure 2.2 – National Traffic Trends by Road Type: Rural roads compared with A30 traffic 8
Figure 2.3 – Trends on A30 east and west of the junction-by month 9
Figure 2.4 – AADT Yearly Trends on A30 east and west from 2003 9
Figure 2.5 – Weekday Traffic volumes and Total Flow through Junction 11
Figure 2.6 – August traffic volumes by day of week, by direction, west of jct 13 Figure 2.7 – Average Weekday HGVs on A30 14
Figure 3.1 – Locations of Personal Injury Accidents 2km/1.2miles and 0.5km/0.3miles around junction 25
Figure 4.1 – Forecast benefits 35
Figure 5.1 – Illustrating generally satisfactory plant establishment, weed free circles and grassland free from
noxious weeds 51
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 86
Figure 5.2 – (left) Plants developing ‘lollipop’ form in narrow shelters at OYA 52
Figure 5.3 – (right) At FYA plants will not be able to develop a more natural shape until shelters are removed52 Figure 5.4 – (left) Existing night time lighting before the improvement works at the junction 52
Figure 5.5 – (right) At FYA 52
Figure 5.6 – Example of gorse control, with spray drift also affecting adjacent grassland 54
Figure 5.7 – Example of bare substrate on cutting slope which vegetation is slowly beginning to colonise and
in time is likely to increase through natural regeneration 55
Figure 5.8 – View from A30 overbridge to counterfort drains alongside east bound carriageway 58 Figure 5.9 – Grass verge at edge of loop road carriageway, providing safe crossing of the A30 60
APPENDICES
List of Tables
Table A.1 – Appraisal Summary Table (Scheme Assessment Report, January 2003) 67
Table A.2 – Evaluation Summary Table (EST) 68
Table B.1 – TRADS sites on A30 69
Table B.2 – Average Daily Traffic volumes around the Junction 70 Table C.1 – Statistical Significance Tests on Changes in numbers of Accidents and Casualties before and
after 71 Table C.2 – Accident numbers in before and after periods on scheme section and at control section 72
Table C.3 – Tanner k test results on accident numbers within scheme area only 73
Table C.4 – Chi-square test results 73
List of Figures
Figure B.1 – TRADS sites on A30 69 Figure B.2 – Long term trend on A30 70
Figure D.1 – View westwards from Whiddon Down Services, looking across the Troney Valley to Livaton and
the A3124 overbridge (Figure D.2 completes the panorama to the right). 76
Figure D.2 – FYA May 2012 similar view (taken from new A30 overbridge) with Narraway Farm to left of
view 76 Figure D.3 – ES : View eastwards towards Merrymeet from the A3124 overbridge 77
Figure D.4 – FYA May 2012 looking along the A30 east towards the Whiddon Down junction and overbridge
across the cutting 77
Figure D.5 – OYA (July 2008) Looking south (with C50 in foreground) to the new junction with the A30, new
planting and seeding on the cutting slopes. A30 overbridge top right of view. 78 Figure D.6 – FYA (May 2012) Looking from A30 overbridge towards C50 and planting on embankment
slopes illustrating generally satisfactory establishment. 78
Figure D.7 – OYA (July 2008) Looking west from overbridge – the pale green field in the middle foreground
(left of the white van) has been re-profiled with surplus soil and integrates well into the local
landscape 78
Figure D.8 – FYA (May 2012) central reserve grassland slow to establish as expected on substrate but clear
of weeds although gorse establishing between the barriers. Planting establishing
satisfactorily. 78
Figure D.9 – OYA (July 2008) Looking towards Narroway Farm from earth mounding adjacent to approach
road to the overbridge. Travelodge is behind trees on left 79
Figure D.10 – FYA (May 2012) well established planting and no evidence of noxious weed 79
Figure D.11 – OYA (July 2008) Looking east along the A30 with overbridge on horizon visually closing the
‘notch’ in the cutting 79
Figure D.12 – FYA (July 2012) planting has not yet matured sufficiently to visually reduce the width of the
bridge 79
Figure D.13 – OYA (July 2008) Wide verge on approach to Whiddon Down services from the A30 80
Post Opening Project Evaluation
A30 Whiddon Down junction improvement – Five Years After
5106230/POPE _ A30 Whiddon Down FYA final 87
Figure D.15 – OYA (July 2008) View of attenuation pond, dry at time of site visit, with distant views to
Dartmoor National Park beyond. Textmour reinforced soil slope was use 80
Figure D.14 – FYA (May 2012) Grass verge at edge of loop road carriageway, providing safe crossing of the
A30 80
Figure D.16 – FYA (May 2012) Vegetation including Gorse will require cyclical maintenance and
management to ensure attenuation pond continues to function as intended. 80 Figure D.17 – OYA (July 2008) Looking from A382. Counterfort drains visible on cutting slope. 81
Figure D.18 – FYA (May 2012) similar view with Counterfort drains still visible. Slow grassland
establishment visible on verge in foreground. Good plant growth in small island planting (to
left of mobile sign). 81