41
Post-Construction Evaluation of Forecast Accuracy December 8, 2008 Pavithra Parthasarathi David Levinson University of Minnesota

Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Post-Construction Evaluation of Forecast

AccuracyDecember 8, 2008

Pavithra ParthasarathiDavid Levinson

University of Minnesota

Page 2: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Presentation Outline

Research objectives

Data collection

Analysis of forecast data

Identifying reasons for forecast inaccuracy

Conclusions

Questions?

Page 3: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Research Objectives• Evaluate the accuracies of MnDOT demand

forecasts

Identify and estimate the inaccuracies in roadway traffic forecasts

• Identify reasons for presence of inaccuracies

• Provide recommendations

Page 4: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Data Collection• 9 months of project time

• 211 project reports scanned

• 108 reports used in the final database

5,158 roadway segments with forecast data

2, 984 of 5,158 roadway segments have actual traffic data (AADT)

• The same information was collected from all forecast reports to ensure consistency

Page 5: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

DAKOTA

ANOKA

HENNEPIN

SCOTT

CARVER

WASHINGTONRAMSEY

LegendHighways Analyzed

County Boundary

Page 6: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Analysis of forecast data

Illustrative Analysis

Macro-level analysis

Inaccuracy = Forecast Traffic Actual Traffic

Inaccuracy estimated by different categories to better understand the data

Page 7: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

15,000

30,000

45,000

60,000

75,000

90,000

105,000

0 15,000 30,000 45,000 60,000 75,000 90,000 105,000

Forecast Traffic

Act

ual

Tra

ffic

TargetData

Page 8: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

FEIS

New

U.S

. Hw

y 10

SPA

RS

49

SPA

RS

73

TA-M

329

SPA

RS

65

TA-M

302

Average Inaccuracy Critical Link Inaccuracy

Anoka County

Overestim

ationU

nderestim

ation

Page 9: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

SPA

R-2

24

SPA

R-2

46

TA-M

300

TA-M

298

FEIS

TH

3

SPA

R-2

15

SPA

RS

17

TA-M

245

SPA

RS

75

TA-M

240

SPA

RS

18

TA-M

311

TA-M

308

SPA

RS

3

SPA

RS

16

SPA

RS

32

SPA

RS

75A

Average Inaccuracy Critical Link Inaccuracy

Dakota County

Overestim

ationU

nderestim

ation

Page 10: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Hennepin County

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

TAU

307

5TA

-M23

8TA

-M25

3SP

AR

-202

DEI

S T

H 6

10/T

H 2

52TA

-M29

2SP

AR

S 69

TA-M

309

SPA

R-2

02A

TA-M

307

SPA

RS

15TA

-M35

8SP

AR

S 72

TA-M

346

TA-M

253

Dis

t Add

nFE

IS U

S-12

/I-39

4TA

-M34

3TA

-M33

7FE

IS T

H 7

7/I-4

94TA

-M34

5SP

AR

S 61

SPA

RS

78

Average Inaccuracy Critical Link Inaccuracy

Overestim

ationU

nderestim

ation

Page 11: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Ramsey County

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0TA

U 3

077

TAU

306

5

SPA

R-2

27

FEIS

I35E

TA-M

289A

SPA

RS

37

TA-M

301

TAU

307

0

TAS3

084-

14

SPA

R-2

20

TAU

307

8

SPA

RS

33

TAS

3065

A-1

4

TAS

3081

A-1

4

TAU

306

9

TA-M

336

TA-M

304

TAU

307

4

SPA

R-2

10

TAU

307

3A

SPA

R-2

08

TAS3

081B

-14

TAU

306

6

TAU

307

6

TAU

306

1A

TAS

3080

TA-M

255A

TA-M

296A

SPA

RS

45

TAS3

085-

14

TAU

307

3

TAS

3074

B

TA-M

299

TAS

3081

TA-M

286

TAS

3074

C-1

4

SPA

RS

53

TAS3

082-

14

SPA

R-2

08A

TAS

3066

A-1

4

TA-M

242

SPA

RS

4

TAU

307

4A

Average Inaccuracy Critical Link Inaccuracy

Overestim

ationU

nderestim

ation

Page 12: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

TA-M

326

TA-M

207A

TAU

345

1B

TAU

345

1A

SPA

RS

2

SPA

RS

60

SPA

RS

19

SPA

RS

77

SPA

RS

2A

Average Inaccuracy Critical Link Inaccuracy

Washington County

Overestim

ationU

nderestim

ation

Page 13: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

TA-M

335

PSU

3203

A

PSU

3203

B

TAU

3204

A

SPA

RS

48

TAU

320

5

TA-M

372B

Average Inaccuracy Critical Link Inaccuracy

Carver & Scott County

Overestim

ationU

nderestim

ation

Page 14: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

StatisticsInaccuracy Ratio

= Forecast TrafficActual Traffic

Overestimation (Inaccuracy ratio>1.0)

Underestimation (Inaccuracy ratio<1.0)

Exact(Inaccuracy ratio=1.0)

Average Inaccuracy

Critical Link Inaccuracy

48% 48% 4% (within +/-0.5%)

27% 65% 8% (within +/-5.0%)

Note - The above statistics are based on data from the 108 project reports in the database

Page 15: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

StatisticsProject Type Frequency Average

InaccuracyMaximum Inaccuracy

Minimum Inaccuracy

Existing Roadways

New Roadways

77% 1.20 8.94 0.01

23% 0.95 5.00 0.16

Note - The above statistics are based on data from the 108 project reports in the databaseRoadways classified as existing or new facility based on the status at the time of report preparation

Page 16: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

Free

way

Divide

d Arte

rial

Undivi

ded A

rteria

l

Expr

essw

ay

Collec

tor

1.29

1.141.24

1.19

0.95

Highway Functional Classification

Average Inaccuracy

Overestim

ationU

nderestimation

Page 17: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

0-5,

000

5,00

0-10

,000

10,0

00-2

0,00

0

20,0

00-3

0,00

0

30,0

00-4

0,00

0

40,0

00-5

0,00

0

50,0

00-6

0,00

0

60,0

00-7

0,00

0

70,0

00-8

0,00

0

80,0

00-9

0,00

0

90,0

00-1

00,0

00

>10

0,00

0

0.61

0.740.740.760.80

0.730.790.81

0.981.05

1.08

1.47

Count Range

Overestim

ationU

nderestimation

Average Inaccuracy

Page 18: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0%

5%

10%

15%

20%

25%

0-0.

1

0.1-

0.25

0.25

-0.5

0

0.50

-0.7

5

0.75

-1.0

1.0-

1.25

1.25

-1.5

0

1.50

-2.0

0

2.00

-2.5

0

2.50

-3.0

0

3.00

-4.0

0

4.00

-5.0

0

5.00

-6.0

0

>6.

00

0.4%0.2%0.4%1.1%

1.9%

3.8%

10.5%

8.4%

18.0%

24.0%

21.9%

8.3%

1.1%0.1%

Estimated Inaccuracy

Frequency DistributionOverestimation - 44%Underestimation - 56%

Page 19: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

• No clear trend seen in the estimation of average inaccuracy by project

Trend of underestimation seen in the estimation of inaccuracy on critical links

• Higher functional classification roads and higher volume roadways seem more prone to underestimation

Summary

Page 20: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Quantitative Analysis

• To identify the factors influencing forecast inaccuracy

Only main roadways included

Other roadways in the project not included

Additional information collected for the main roadways used in the analysis

Page 21: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

• Ordinary Least Square Regression Model

I = f(N, H, F, V, D, T, S) where,

I = Inaccuracy ratio

N = Number of years between report year and forecast year

H = Highway type - radial or lateral

F = Functional classification

V = Project VKT or VMT

D = Segment direction

T = Decade of report preparation

S = Roadway status - existing or new

Page 22: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Southwest

Northwest

West

Northeast

Southeast

Middle-North

Middle-South

North

North

South

South

Middle East

Minneapolis

Saint Paul

Page 23: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Dependent Variable = Forecast Traffic/Actual TrafficVariable

Number of years

Project VMT

Radial highway type

Collector

Divided Arterial

Expressway

Undivided Arterial

East

Middle North

Middle South

North

Northeast

Northwest

South

Southeast

Southwest

West

Rept year between 1970-1980

Rept year between 1980-1990

Rept year after 1990

New Facilities

constant

Number of obs

R-squared

Adj R-squared

Root MSE

Coefficient Std. Error t P>|t|

-0.034 0.004 -9.560 0.000

0.000 0.000 -1.430 0.153

-0.108 0.033 -3.330 0.001

-0.112 0.226 -0.500 0.619

0.047 0.057 0.830 0.407

0.097 0.043 2.270 0.024

0.031 0.049 0.640 0.523

0.264 0.082 3.230 0.001

-0.036 0.073 -0.490 0.624

-0.348 0.105 -3.320 0.001

-0.113 0.072 -1.560 0.119

0.552 0.077 7.200 0.000

-0.193 0.087 -2.220 0.027

-0.056 0.071 -0.780 0.434

0.358 0.070 5.140 0.000

-0.162 0.079 -2.050 0.041

-0.154 0.083 -1.860 0.063

0.111 0.042 2.610 0.009

0.064 0.047 1.350 0.177

0.278 0.220 1.260 0.207

-0.125 0.039 -3.220 0.001

1.639 0.088 18.630 0.000

1275

0.251

0.238

0.503Positive & significant - Overestimation; Negative & significant - Underestimation

Page 24: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Qualitative Analysis• Conducted interviews with modelers in the

Twin Cities

Modeling experience varied among the interviewees

Seven interviews conducted in May - June 2008

Interviews conducted in-person, via email or over the phone

Page 25: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Goal was to obtain perspectives and useful insights on modeling in the Twin Cities

To understand the reasons for inaccuracy in traffic forecasts

Page 26: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Standard set of 5 questions asked of all the interviewees

1. Your understanding of possible sources of error in the Twin Cities models?

2. With the current expertise in modeling that we have, what could have be done differently with the model development in 1970s, 1980s?

Page 27: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

3. How does the Twin Cities model compare with other models that you have worked with or had an opportunity to look at?

4. How would you respond to criticisms against modeling?

5. Have there been instances of political compulsions influencing the model forecasting in the Twin Cities?

Page 28: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Inability of model to understand and predict societal changes

Labor force participation of women

Increases in mobility and auto ownership

Increasing influence of internet & technology

Stated reasons for inaccuracy

Page 29: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Model Inputs

Population - Employment inputs

Network inputs

Technical limitations inherent in previous models

Fewer people involved in modeling

Page 30: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Lack of a good understanding of trip distribution

Use of a fixed percentage of daily traffic for peak periods

Inability of the model to handle peak spreading

Page 31: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Over importance to home-based work (HBW) trips

Too much emphasis to assignments on principal arterials

Handling of special generators

ex. Mall of America

Page 32: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Political compulsions NOT too much of an issue in the Twin Cities

Private consultants likely to face more pressure from clients

Public agencies more likely to face a “push” to use existing or expected trends

Page 33: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Comparison of demographic forecasts

Average Inaccuracy estimated using 1975 Metropolitan council forecasts

County

Anoka

Carver

Dakota

Hennepin

Ramsey

Scott

Washington

Total 7-county

1980 Population 1990 Population 2000 Population

1.08 1.01 0.93

1.02 1.19 1.04

1.17 1.19 1.19

1.10 1.08 1.06

1.12 1.17 1.22

1.02 1.04 0.89

1.11 1.27 1.22

1.11 1.12 1.10

Page 34: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

TBI Data 1949 1958 1970 1982 1990 2000 1990 - 1970

2000 - 1970

HBW Average Trip Length: MilesHBW Average Trip Time: Minutes

Trips Per Capita

Trips Per Household

Persons Per Household

Workers Per Household

Auto Occupancy: HBW

Auto Occupancy: OverallPercentage of Women in Labor Force*

na na 6.57 8.11 9.2 11.4 40% 74%

na na 19.8 na 21.2 25.6 7% 29%

1.78 2.45 2.72 3.37 3.9 4.2 43% 54%

na 7.52 8.88 9.08 10.12 10.3 14% 16%

na na 3.27 2.68 2.56 2.46 -22% -25%

na na 1.3 1.38 1.42 na 9% na

1.12 1.12 1.19 1.15 1.07 1.05 -10% -12%

1.55 1.57 1.5 1.3 1.29 1.35 -14% -10%

na na 48.8% 60.0% 67.8% 72.5% 39% 49%

*Source: 2005 Twin Cities Transportation System Performance Audit

TBI data

Page 35: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Network InputsNew facilities identified in the 1976 Regional Development Framework (RDF) and expected to be completed by 1990

Highways

I-35E

I-35E

I-94 (Minneapolis)

I-494

US 10

US 169/212

US 169 (W River Rd)

US 169/ State 101 (Shakopee Bypass)

Co Rd 18 (Hennepin)

Co Rd 62 (Hennepin)

Northtown Corridor

Northtown River Crossing

LaFayette Expressway (52)

I-335

From To Year Built

West Seventh Street I-94 1984-1991

I-35 State Highway 110 1981-1985

US 12 57th Ave N 1980-1982

State Highway 5 I-494 1982-1986

Ramsey Co Rd J State Highway 47 1990

I-494 State Highway 41 1994-1996

86th Ave N Northtown Corridor 1983

US 169 State Highway 13 1976-1980

5th Street S Minnetonka Blvd 1994

Co Rd 18 I-494 1985-1986

US 169 I-94 Not built yet

US 10 US 169 1998

I-494/State Highway 110 State Highway 55/52 1985-1994

I-94 I-35W Control Section eliminated in 1979

Page 36: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Forecasting is a complicated long-term process

It is difficult to anticipate changes and control for errors

Recommendations

Page 37: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Better record keeping and data archiving procedures extremely essential

Better understanding and incorporation of fundamental societal changes is important

Blindly following existing trends might not be the best approach

Page 38: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Lesser importance needs to be given to the use of absolute numbers in forecasts

Use of ranges

Acknowledgement of uncertainties

Non-modelers

Essential to understand the science, limitations and applicability of traffic forecasts

Page 39: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Questions?

Page 40: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

Dependent variable: Inaccuracy Ratio = Forecast Traffic/ Actual TrafficVariable

Number of yearsProject VKT

Radial Highway TypeCollector

Divided ArterialExpressway

Undivided ArterialEast

Middle-NorthMiddle-South

NorthNortheastNorthwest

SouthSoutheastSouthwest

Westcons

Number of obsR-squared

Adj R-squaredRoot MSE

Coefficient Std. Error t P>|t|-0.029 0.004 -8.100 0.0000.000 0.000 -1.550 0.121-0.059 0.039 -1.520 0.1280.027 0.282 0.100 0.9220.051 0.069 0.730 0.4630.128 0.052 2.460 0.0140.148 0.054 2.740 0.0060.181 0.098 1.850 0.065-0.059 0.087 -0.680 0.494-0.395 0.120 -3.280 0.001-0.127 0.080 -1.580 0.1150.492 0.092 5.360 0.000-0.184 0.098 -1.860 0.0620.034 0.077 0.450 0.6530.324 0.083 3.920 0.000-0.197 0.090 -2.190 0.029-0.333 0.086 -3.880 0.0001.552 0.095 16.400 0.000

13580.1610.1510.638

Positive & significant - Overestimation; Negative & significant - Underestimation

Page 41: Post-Construction Evaluation of Forecast Accuracy · forecast data 2, 984 of 5,158 roadway segments have actual traffic data (AADT) •The same information was collected from all

0

15,000

30,000

45,000

60,000

75,000

90,000

105,000

0 15,000 30,000 45,000 60,000 75,000 90,000 105,000

Forecast Data Target Data