Portable Wire Integrity Tester(PWIT)
Mistake Proofing Onboard Wire Installations for Aircrafts
Hello, I am Joe Sunio, and we are the portable wire integrity tester or PWIT team.
I’d like to introduce the other presenters on my team:Paul KillianD’Arcy StylianoJoe Sunio,Paul Kim
1
22
2
Background
A major component of Boeing’s business is modifying and upgrading aircraft.Significant quality issues arose at Boeing Support Systems (BSS) in San Antonio Texas during C-17 retrofit programs.– Damaged avionics and other equipments during post integration
and reapplication of power to the aircraft– Large schedule delays– Significant cost overruns– Dissatisfied customer
Our team was asked to help locate potential causes and provide possible solutions.Many possible causes and improvement opportunities were exploredbut eventually narrowed down to the wire integration and testing steps in the retrofitting process.
Our solution was the Portable Wire Integrity Tester (PWIT)
A major component of Boeing’s business is the modification and upgrading of aircraft. Much of this effort is performed at the Boeing Support Services Center (BSS) in San Antonio, Texas.
The center performs maintenance and modifications for the C-17, KC-10, KC-135, and C-130 AMP.
Maintaining good relations with our customer, the US Air Force, plays a major role in keeping BSS a viable revenue center. That is why this team was formed to address quality issues that have occurred, impacting the relationship with our customer.
The issues were:• Damage occurring to aircraft components during Power On testing• Unacceptable schedule and cost overruns from mis-wires and repairs caused by the damage.• And a dissatisfied customers due to late deliveries and cost overruns.Our team was asked to help locate potential causes and provide possible solutions.
3
3
Project Selection & Purpose
Criteria 1
Starting with Criteria 1: Project Selection and Purpose
3
44
4
Types of data types used to select the project, and why
STEP 1Define
Process
STEP 2EstablishMetrics STEP 3
DeterminePerformance
STEP 4StabilizeProcess
STEP 5Set
Goals
STEP 6Develop
ImprovementPlan
STEP 7Implement
Improvements
1A.a
Process
Based
Management
Section 1A.aTo resolve quality issues encountered at BSS, the team utilized a company standard process called Process Based Management or PBM. PBM is a 7 step continuous improvement model utilized by the C17 Program to manage data and processes. During this process, various tools are used and data analyzed in finding the best solution or solutions towards improvement.
55
5
Types of data types used to select the project, and why1A.a
Why? Why?
Why?Why?
Why?
Causes
Machine
Mis-wiring CausingUnnecessary Rework
Effect
PeopleMeasurement
Environment Method Material
Trend Analysis
Brainstorming
Value Stream Mapping
Trend Analysis data such as schedule, requirements, cost, and re-work numbers are evaluated to pinpoint business improvement opportunities. Data indicated we were not performing to our set schedules and so the costs of the program were rising.
The key tools we used were:Value Stream Mapping to identify and involve stakeholders as early as possible in determining areas for improvement.
Brainstorming sessions so that stakeholders can generate a large number of ideas from a diverse set of experts.
Earned Value Management System (EVMS) and trend data were analyzed to determine cost or schedule inefficiencies in the various functions of the process.
66
6
Reason why the project was selected1A.b
0
5
10
15
20
25
30
35
Step1
Step2
Step3
Step4
Step5
Step6
Step7
Step8
EstimatedActual
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7
Receive
Airplane
Equipment
Removal
Remove
Wires
Add Wires Equipment
Installation
OPS Checks Test Flight
Step 8
Delivery
WOW
Section 1A.bThe project was selected due to schedule delays, rework, and equipment failures, which contributed to delayed deliveries to the US Air Force and rising costs. The value-stream mapping process showed a need for improvement in the functional test steps of the process.
Further analysis showed significant opportunities for process and quality improvements if Boeing eliminated the process of manually verifying retrofit wiring installations.
77
7
Involvement of potential stakeholders in project selection1A.c
BoeingStakeholders
ExternalStakeholders
Section 1A.cInternal and external stakeholders gave us valuable information in achieving our end results. Potential stakeholders were identified and selected according to their functional mapping in the current value stream. The value stream map identified key processes like Aircraft Received, Aircraft Modified, Systems Functional Check, Aircraft Check Flight, and Aircraft Delivered. From these steps, stakeholders were identified and included Technicians, Pilots, Engineers, Quality Inspectors, and Customers.
Stakeholder feedback such as comments from technicians, relating to problems with the process, were the drivers for this project.
88
8
1B.a
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetition
ReduceRepetition
ReduceReworkReduceRework
Project
Organizational
QualityQuality
ScheduleSchedule
Cycle TimeCycle Time
CostCost
Affected organizational goals, performance measures, and strategies
Section 1B.a Our program goals are designed to meet our C-17 Long Term Strategy. After mapping the current state these goals can be used to help develop and align our objectives in the future vision map with those of the program.
Project Goals were determined through stakeholders identifying their needs and concerns. The long term strategies, aligned to the project goals are:- To Exceed commitments by delivering airplanes back to our customer on schedule and under budget.
- Achieve aggressive, sustainable improvements to safety, quality, schedule and cost by reducing the number of defects.
- Strengthen stakeholder relationships by delighting our customer with a great product.
- And to Relentlessly improve and integrate processes by becoming more efficient in the process of modifying aircraft.
99
9
Types of project impact on each goal/performance measure1B.b
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetitionReduce
Repetition
ReduceReworkReduceRework
ProjectGoals
QualityQuality
ScheduleSchedule
Cycle TimeCycle Time
CostCost
OrganizationalGoals
Impacts
Automation = defects are not passed to the next process and customer, lowers rework costs, and improves customer relations.
Automation = defects are not passed to the next process and customer, lowers rework costs, and improves customer relations.
On time delivery enables the customer to reliably schedule aircraft and technology insertion into the fleet.
On time delivery enables the customer to reliably schedule aircraft and technology insertion into the fleet.
Speed and accuracy of automation improves process efficiency.Speed and accuracy of automation improves process efficiency.
Downstream system test savings, eliminating unscheduled overtime.Downstream system test savings, eliminating unscheduled overtime.
Section 1B.bOur project had an impact on each of our goals.The 1st impacted priority is Quality, where Automation eliminates defects, improves cost metrics, customer relations, and overall improvement in quality.
The 2nd impact is Schedule, where keeping schedules ensures the timely delivery of aircraft minimizing the impact to our customers operations.
The 3rd impact is Cycle Time, where the speed and accuracy of automation improves process efficiency and reduces waste.
And the 4th impact is Cost, where there is a reduction in man-hours needed per installation & avoidance of component damage during functional test.
1010
10
Degree of impact on each goal/performance measure, and how this was determined
1B.c
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetitionReduce
Repetition
ReduceReworkReduceRework
PWITGoals
QualityQuality
ScheduleSchedule
Cycle TimeCycle Time
CostCost
OrganizationalGoals
Impacts
Automation = defects are not passed to the next process and customer, lowers rework costs, and improves customer relations.
Automation = defects are not passed to the next process and customer, lowers rework costs, and improves customer relations.
On time delivery enables the customer to reliably schedule aircraft and technology insertion into the fleet.
On time delivery enables the customer to reliably schedule aircraft and technology insertion into the fleet.
Speed and accuracy of automation improves process efficiency.Speed and accuracy of automation improves process efficiency.
Downstream system test savings, eliminating unscheduled overtime.Downstream system test savings, eliminating unscheduled overtime.
DegreeGoal
HIGHHIGH
HIGHHIGH
LOWLOW
MEDMED
DegreeMetrics
HIGHHIGH
MEDMED
MEDMED
HIGHHIGH
Section 1B.cThe degrees of impact on each goal, performance measure or strategy were determined through stakeholder estimates and feedbacks of downstream savings. Based on the degree of importance in meeting organizational and project goals, impacts were rated either high (exceeds requirements – greater than 10%), medium (meets requirements about 5%), or low (minimal impact, less than 3%).
In the case of eliminating scheduled overtime, the PWIT goal of reducing repetition has a medium impact, but the potential to reduce overall cost at the organizational level has a positively high impact on our goals (greater than a 10% reduction).
1111
11
Potential internal and external stakeholders, and explain how they were identified
1C.a
Technicians
Pilots
Engineering
Quality Inspectors
Customers
Value Stream Mapping
InternalStakeholders
ExternalStakeholders
Section 1C.aIn the course of value stream mapping the current process, potential stakeholders were also identified. Our identified internal stakeholders are technicians, engineers, quality inspectors, and the pilots. Our external stakeholder being the customer. These stakeholders were identified because they had a significant impact or were significantly impacted by our project goals
During our process review, process owners and subject matter experts defined the role of stakeholders.
Team meetings took place in locations such as Long Beach, California and San Antonio, Texas
1212
12
Types of potential impact on stakeholders, and explain how these were determined
1C.b
ExternalStakeholders
Customers
InternalStakeholders
Technicians Pilots EngineeringQuality
Inspectors
Type of Impact
Overtime, Length of time, Extra troubleshooting
Scrubbed missions,Delays in missions,
Overtime, travel, Over utilization of lab facilities
More work Mission Capability
Impact Determinant
Budget,Schedule
Budget,Schedule
Budget,Schedule
Number of write ups
Award fee delays, Waivers, Nasty phone calls
ValidationMetrics,Team meetings
Metrics,Reviews,Post flight
Metrics,Reviews
Metrics,Reviews
Metrics,Reviews
Brainstorming Value Stream Mapping
Section 1C.bThe types of potential impacts on stakeholders were determined by value stream mapping, project reviews, fishbone exercises, and brainstorming. The value stream map identified areas for potential improvement in the process.
For example, during brainstorming and process discussion meetings with technicians, the issues of overtime and rework were highlighted in the budget figures as well as how well the team was doing compared to baseline metrics. Instead of taking 5 days for a wire integration and completion, the technicians were working up to 3 weeks on a single plane. This had a significantly negative impact to delivery time.
In addition, failures discovered during the Power-On process led to multiple impacts to various stakeholders ranging from extended workdays for technicians due to re-work, to dissatisfied flight crews whose missions are cancelled due to the unavailability of aircraft. This negatively impacted the goal of reducing overtime.
1313
13
Degree of potential impact on stakeholders, and explain how this was determined
1C.c
Stakeholders Degree of Impact Impact Determinant
Technicians 80% reduction of overtime Comparing industry standards
Pilots 15% fewer errors founds Comparison to errors found in production
Engineering 80% reduction in unnecessary overtime
Comparing industry standards
Quality Inspectors 80% fewer errors found Comparing industry standards
Customers 25% more airplanes received on time Delivery schedules
Section 1C.cDuring each step identified in the Value Stream Map, team meetings were established and brainstorming was utilized to determine the severity of the impact to the stakeholder groups.
For example, the Quality Inspectors analyzed the number of quality write-ups and determined an extraordinary amount of anomalies due to wiring problems during the Power On Phase.
Another example based on industry standards showed technicians could be impacted by an 80% reduction in mandatory overtime.
14
14
Current Situation Analysis
Criteria 2
Now D’Arcy will take us through the second criteria: Current Situation Analysis
Thank you Joe.
14
1515
15
Methods and tools used to identify potential improvement opportunities
2A.a
CausesMachine
Mis-wiring CausingUnnecessary Rework
Effect
PeopleMeasurement
Environment Method MaterialValue Stream Mapping
0
5
10
15
20
25
30
35
Step1
Step2
Step3
Step4
Step5
Step6
Step7
Step8
EstimatedActual
Trend Analysis
WOW
Section 2A.aOnce again, the value stream map was used to identify potential improvement opportunities. It helped stakeholders and team members understand the overall process, steps, problems, and possible improvements.
Using the cause and effect tool, known as the fishbone, the team took individual processes with their undesired effects and brainstormed possible causes. This resulted in several opportunities for improvement.
Subject matter experts from respective processes were asked to attend brainstorming and fishbone sessions, validating many of our potential opportunities.
In addition, industry best practices were used as baseline criteria during our trend analysis sessions to further identify and refine our choices.
1616
16
Methods and tools used to identify potential improvement opportunities
2A.a
Value Stream Mapping
… the team then went back to the value stream map, to better refine improvement opportunities and the path to a future state value map.
1717
17
Analysis of data to identify root potential improvement opportunities
2A.b
Brainstorming
CausesMachine
Mis-wiring CausingUnnecessary Rework
Effect
PeopleMeasurement
Environment Method Material
Value Stream Mapping
0
5
10
15
20
25
30
35
Step1
Step2
Step3
Step4
Step5
Step6
Step7
Step8
EstimatedActualWOW
Section 2A.bComparing performance data from successful wire integrations with the current processes showed areas where significant increase in efficiency were possible.
- Process walkthroughs, value stream mapping, and brainstorming also identified the largest improvement steps, with the fishbone outlining specific improvement areas.- Subject matter experts, technicians, and other stakeholders were instrumental in analyzing and deciphering the collected data.- One of the improvement areas identified by the value stream map was the testing and verification process.- Trend analysis of both project management and process data, showed where project tasks were taking longer and costs were higher than expected. Errors in wire integration were causing substantial overtime for technicians and overall decline in the morale of the group.
We used the fishbone process to identify potential causes and ideas for improvement opportunities for specific steps in the wire integration and verification process. A major question was why the integration and verification efforts were taking so long and with so many errors? Some possible causes were:Inadequate training, insufficient tooling and equipment, not enough hours and resources, inefficient inspection process, poor design of connectors AND bad supplier parts…
Benchmarking with other aircraft modification programs within the company also indicated similar trends and challenges.
1818
18
2A.b Analysis of data to identify potential improvement opportunities
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetitionReduce
Repetition
ReduceReworkReduceRework
PWITGoals
QualityQuality
ScheduleSchedule
Cycle TimeCycle Time
CostCost
OrganizationalGoals
Potential Improvement Opportunities
Increase inspection / supervisionProvide more tools for visibilityTraining
Increase inspection / supervisionProvide more tools for visibilityTraining
Insufficient allocated timeInsufficient automationNot enough people – increasing personnel
Insufficient allocated timeInsufficient automationNot enough people – increasing personnel
Avoidable reworkUnscheduled overtimeAircraft equipment failures
Avoidable reworkUnscheduled overtimeAircraft equipment failures
Manual testingManual process for defect isolationManual process for inspection
Manual testingManual process for defect isolationManual process for inspection
Impact
YesUnknown
Yes
YesUnknown
Yes
NoYesNo
NoYesNo
YesUnknown
Yes
YesUnknown
Yes
YesYes
Unknown
YesYes
Unknown
Impact?
This chart shows the potential improvement opportunities from our data analysis, color coded to our Project and Organizational Goals.
On the right reflects stakeholders’ impact feasibility evaluations for each opportunity and its respective goals.
For example, increasing personnel, initially considered as a potential improvement to the schedule and delivery time, was determined unfeasible after further review. Our findings did not show additional resources providing significant improvement in execution and delivery time.
1919
19
How stakeholders were involved in identifying potential improvement opportunities
2A.c
Brainstorming
CausesMachine
Mis-wiring CausingUnnecessary Rework
Effect
PeopleMeasurement
Environment Method Material
InternalStakeholders
ExternalStakeholders
Section 2A.cAll stakeholder groups separately participated in cause and effect brainstorming sessions, using the same data analysis tools and information.
This allowed for groups to feel comfortable in identifying issues, potential causes and how they felt it could better be handled, and ultimately define for our team what was important for them.
For example, technicians gave input to specific challenges they faced and how processes and procedures could be improved.
It also allowed for different perspectives on the same data, validating what the team saw, and presenting ideas where we lacked insight.
Then all stakeholder groups met together and compared and analyzed their findings.
2020
20
Methods and tools used to identify the final improvement opportunities
2B.a
Causes
Machine
Mis-wiring CausingUnnecessary Rework
Effect
PeopleMeasurement
Environment Method Material
Why? Why?
Why?Why?
Why?
Improvement Opportunities
Section 2B.aProven industry methods and tools, such as the “5 Whys” and the “Fishbone (Cause and Effect Diagram),” were utilized during our stakeholder brainstorming sessions to identify final improvement opportunities from our organizational goals of cycle time, quality, cost, & schedule.
Each potential improvement went through the “5 Whys” to help clarify and bring structure to our Fishbone Diagrams. Both tools provided ways to better visualize and conceptualize the problems the team were facing.
This led to a clear organization of the opportunities for further analysis.
2121
21
Analysis of data to select the final improvement opportunities2B.b
It looks like the wire integration
effort is holding us up.
Do they need more training,
equipment, people?
I bet the internal
stakeholders would know.
Section 2B.bDuring our initial data analysis sessions with each group, a common theme started to emerge from our potential improvements list.
2222
22
Analysis of data to select the final improvement opportunities2B.b
Improvement Opportunities
Accurate and Quick Troubleshooting
Improve Manual Inspection Process
Reduce Aircraft Equipment Damage
Automation
Better Testing Equipment
Technicians Pilots EngineeringQuality
InspectorsCustomers
After paring down the list, using industry proven tools, relevant stakeholders were identified to help take our highest potential improvement opportunities and walk us through the steps in the integration process.
This training gave members in the team an understanding of how data simulation related to their current process and goals.
After the team experienced the issues first hand, we took a further defined list and asked the team to rank potential impacts to project and organizational goals.
For example, the following potential improvement opportunities were dropped from the list: training, redesigning of the connectors, and redesigning of the wire installation process.
The technicians at work were already highly trained and scenario modeling indicated additional training would not reduce human factors based issues.
Each connectors were mil-standard and could not be redesigned easily and cost effectively. A new design would also introduce possible quality problems from the supplier.
Finally, due to the nature of the wire integration effort as a modification to an existing aircraft, the current manual installation of the wires were necessary and the most efficient method.
2323
23
Identify the improvement opportunities, and explain validation of the final improvement opportunities
2B.c
Organizational Goals
Quality(Reduce Rework)
Quality(Reduce Rework)
Schedule(On-time Delivery)
Schedule(On-time Delivery)
Cycle Time(Reduce Waste)
Cycle Time(Reduce Waste)
Cost(Reduce Repetition)
Cost(Reduce Repetition)
Final List ofImprovementOpportunities
Accurate and Quick Troubleshooting
Improve Manual Inspection Process
Reduce Aircraft Equipment Damage
Automation
Better Testing Equipment
High Impact Medium Impact Low or No Impact
Section 2B.cThis chart shows the results of a Process Selection Matrix where our Processes are located in the far left column and our Key Objectives are located in the top row. Each cross point in the matrix is color coded to show the degree of impact the team determined each opportunity had on the organizational goals.
2424
24
Identify the improvement opportunities, and explain validation of the final improvement opportunities
2B.c
Organizational Goals
Quality(Reduce Rework)
Quality(Reduce Rework)
Schedule(On-time Delivery)
Schedule(On-time Delivery)
Cycle Time(Reduce Waste)
Cycle Time(Reduce Waste)
Cost(Reduce Repetition)
Cost(Reduce Repetition)
Final List ofImprovementOpportunities
Accurate and Quick Troubleshooting
Improve Manual Inspection Process
Reduce Aircraft Equipment Damage
Automation
Better Testing Equipment
1 5 3 1
5 5 3 5
5 1 3 5
3 5 1 3
5 3 3 3
10
18
14
12
14
Total
Assigning values to the original assessments, we involved our stakeholders to validate the chart above. This is illustrated below with data being run through each stakeholder, from the engineer, to the technician, to the quality inspector, validating the team’s results with the results from the stakeholders.
Through consensus, the ratings held up and it was quickly and easily seen that the steps and improvement opportunities to focus on were Automation,Reducing Damage to the Aircraft and Equipment During installation, and Providing Quick & Accurate Troubleshooting Capabilities.
25
25
Solution Development
Criteria 3
Now Paul will take us through section 3, “Solution Development”
Thank you D’Arcy
2626
26
Methods and tools used in development of potential solutions3A.a
Why? Why?
Why?Why?
Why?
0
5
10
15
20
25
30
35
POS1
POS2
POS3
POS4
POS5
POS6
POS7
POS8
EstimatedActual
Trend Analysis
Brainstorming
Value Stream Mapping
Section 3A.aBecause of Boeing’s Lean Plus Initiative, we used the following methods and tools to develop potential solutions: Value Stream Mapping, Trend Analysis, Brainstorming, and the 5 Whys.
We conducted brainstorming sessions using the process flow diagram and trend analysis, which in turn addressed our 5 why analysis.
Our main tool however, was the value stream mapping process which allowed the team to assess the impact of potential solutions on our project goals: Quality, Schedule, Cycle Time, and Cost.
2727
27
Analysis of data used in development of potential solutions3A.b
List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Connectors
Re-engineer Inspection Process
Better Tools
Training
Increase Technicians
Section 3A.bTo develop potential solutions the project team analyzed the information from our value stream map and consulted subject matter experts to create a list of potential solutions. In this brainstorming process the team gained insight as to possible solutions & improvement actions.
For example, our Human Factors Experts helped us to develop ideas on how to better train technicians and our process expert gave us guidance on how to better engineer the inspection process.
2828
28
Analysis of data used in development of potential solutions3A.b
CausesMachine
Mis-wiring CausingUnnecessary Rework
EffectPeopleMeasurement
Environment Method Material
Re-engineer Verification Method
Re-engineer Connectors
Re-engineer Inspection Process
Better Tools
Training
Increase Technicians
List ofPotential Solutions
Value Stream Mapping
The fish bone diagram helped to evaluate the list of potential solutions to see if they would effect the improvement opportunities that were identified during the early stages of this project.
The solutions were then inserted into the value stream map to see if they would beneficially affect the process.
Using the metrics from section 1Bc, different solutions were rated and subsequently compared against one another and the current processes.
2929
29
Analysis of data used in development of potential solutions3A.b
Re-engineer Verification Method
Re-engineer Connectors
Re-engineer Inspection Process
Better Tools
Training
Increase Technicians
List ofPotential Solutions
For example, increasing the number of technicians was determined to be non value added since the area was not large enough to accommodate extra technicians and the nature of the wiring did not allow for additional parallel efforts.
3030
30
Indicate criteria used to select final solution3A.c
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetitionReduce
Repetition
ReduceReworkReduceRework
PWITGoals
QualityQuality
ScheduleSchedule
Cycle TimeCycle Time
CostCost
OrganizationalGoals
Organizational Criteria for Final Solution
Reduction of human factors and decrease defects in manufacturingReduction of human factors and decrease defects in manufacturing
Time to implementTimely delivery = Award FeesTime to implementTimely delivery = Award Fees
Reducing human factors and increasing automationReducing human factors and increasing automation
Return On InvestmentReturn On Investment
Project Criteria for Final Solution
Lower rework from mis-wiringLower repairs caused by mis-wiringLower rework from mis-wiringLower repairs caused by mis-wiring
Lower unscheduled re-fitting of wiresLower repairs
Lower unscheduled re-fitting of wiresLower repairs
Lower setup and tear down timeLower manual testingLower troubleshooting time
Lower setup and tear down timeLower manual testingLower troubleshooting time
Minimize component wasteReduce troubleshooting overtimeReduce repeated repair work
Minimize component wasteReduce troubleshooting overtimeReduce repeated repair work
Section 3A.cThe criteria used to select our final solutions were a combination of Boeing’s organizational goals (from Section 1B.a) and our projects goals:
Applying lean techniques to Reduce Rework, Reduce Waste, Reduce Repetition, and subsequently deliver on time.
This process ensured that both the organizational and project goals were being met.
3131
31
Methods and tools used to select the final solution3B.a
Copyright © 2005 Boeing. All rights reserved.
BOEING PROPRIETARY-DISTRIBUTION LIMITED TO BOEING PERSONNEL ONLY 9/18/20081
IDS Support Systems – San Antonio
BOEING PROPRIETARY
C-17 Modification Process Stations
CELL 1or
POS 1
CELL 2or
POS 2
CELL 3or
POS 3
CELL 4or
POS 4
CELL 5or
POS 5
CELL 6or
POS 6
CELL 7or
POS 7
– POST FLT
– PRE-OPS / HSC
– SHAKE
– ENG PRESERV
– POWER OFF
– DEPAINT – REMOVALS
– FEEDER LINE REMOVALS
– MOD DEPANEL
– MA INT SET-UP
– LRU REMOVALS
– DELETIONS
– FEEDER LINES REWORK
– MOD REWORK
– INSTALLATIONS
– FEEDER LINE INSTALLATIONS
– POWER ON
– OPS CHECKS – PAINT
CELL 8or
POS 8
– PRE-FLT
– DELIVERY
– FUEL ON
– ENG. RUN
– FCF
Process Map
ProcessWalk-through
Brainstorming
Value Stream Mapping
Section 3B.aThe Lean Plus processes in which the team used to validate the final solutions were:
Brainstorming – This technique was helpful to discuss viability of potential solutions, and give stakeholders an opportunity for direct input, and their impact on our current processes and goals. This process was also helpful in minimizing stakeholder resistance and allowed continuous open communication.
Value Stream Map – This tool was used for overall process flow validation and the ability to satisfy our project goals.
Process Walk Through - Stakeholders participated in a walk through of the new process to validate our solution capabilities.
Benchmarking – This was used to further compare the improvement opportunities against what other companies were doing, and also helped to compare best practices. The project team found in the automotive industry that they had experienced great successes checking automotive wiring quickly using an automated tool set.
3232
32
Analysis of data to select the final solution3B.b
List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Connectors
Re-engineer Inspection Process
Better Tools
Training
Increase Technicians
Final List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Inspection Process
Better Tools
Stakeholders
Value Stream Mapping
Section 3B.bIn the final analysis the project team took the list of potential solutions and eliminated those solutions that were determined by the stakeholders to be non productive. We then compared the data obtained from benchmarking and ratings to the metrics of our goals. This narrowed the list to the following “best solutions”:
Reengineering the inspection process
Using Better tools
And Reengineering the verification method
3333
33
List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Connectors
Re-engineer Inspection Process
Better Tools
Training
Increase Technicians
Involvement of stakeholders in selection of the final solution3B.c
InternalStakeholders
ExternalStakeholders
Final List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Inspection Process
Better Tools
Section 3B.cStakeholder involvement in the final solution process was based on their expertise in their respective field. During this time the project team worked together with the stakeholders to rate project goals and ultimately the final list of potential solutions.
Each stakeholder group independently rated solutions' impacts to the goals. These ratings were brought by the stakeholders to the brainstorming, value stream mapping, and evaluation meetings. This lead to the buy-in over the final solutions.
For example, the technicians served as subject matter experts for the viability of solutions which directly affected their existing process and the effect the final solution would have on them. Each stakeholder in the meeting could immediately see how the effected processes could positively impact other stakeholders.
34
34
Describe final solution, and explain solution validation3C.a
Final List ofPotential Solutions
Re-engineer Verification Method
Re-engineer Inspection Process
Better Tools
Loop-Back
Correct connections
Open connection
Mis-wire (“crossed wires”)
x
x
x
Modified Aircraft Cables
PWIT
Section 3C.aWe created a Portable Wire Integrity Tester or PWIT that automatically and quickly checked all of the wiring that was modified by the technicians. PWIT incorporated all 3 final solutions found in section 3B.
It enabled technicians to find wiring errors immediately, instead of finding them during functional tests.
We validated PWIT by creating a cost benefit analysis on the predicted final cost. This also included recurring cost, and comparing that to current process, producing a high ROI.
We presented our findings to the project manager and he gave us development funds for a prototype PWIT to use on a small scale pilot project.
We were successful during the pilot project and validated our ROI estimates.
34
3535
35
Tangible and intangible benefits expected to be realized
TANGIBLE
ROI – cost reductionReducing wiring errors
Tightening scheduleImproving quality
INTAGIBLE
Improved Morale of techniciansPilot & Customer Confidence
3C.b
Section 3C.bThe following benefits were anticipated from brainstorming sessions, stakeholder surveys, and analyzing cost and risk data.
The tangible benefits were:•A Return On Investment of 10 to 1•Reducing wiring errors by 50%•Tightening schedule and Improving quality
The expected intangible benefits were determined from brainstorming sessions with our stakeholders and were:•Improved morale of technicians•Increased Pilot and Customer Confidence
3636
36
Use of data to justify implementation of final solution
ROI from pilot project and modelingData from pilot project on schedule, improved quality, passed function testsData from benchmarking of automotive industry before they implemented this tester
3C.c
$10,000,000
$1,000,000
WOW!90% Savings!!!
Section 3C.cThe data that was used to justify implementation of PWIT came from our Quality & Cost Analysis.
The most surprising finding was the ROI from the pilot project and simulation exercises. A 90% reduction in current costs and 10% reduction in Cycle Time.
Other data used were:•Feedback reports from stakeholders
•Data from pilot project on schedule, improved quality, and passed functional tests
•Data from benchmarking of the automotive industry before and after they implemented this automated tester.
•And analysis showing that this project would meet all of our project and organizational goals of Quality, Schedule, Cycle Time, and Cost.
37
37
Project Implementation & Results
Criteria 4
Now Joe will take you through Criteria 4, “Project Implementation & Results”
Thank you Paul!
3838
38
Types of internal and external stakeholder involvement in implementation
4A.a
Surveys
Training
Metric Reviews
ScheduleReviews
Surveys
ScheduleReviews
InternalStakeholders
ExternalStakeholders
Brainstorming Brainstorming
Metric Reviews
Section 4A.aStakeholder involvement in implementation consisted of the following:•Linking back to 1CC, all stakeholders were impacted by this project in a degree equal to or greater than the anticipated impact.
•Brainstorming and surveys from all stakeholders brought to this process a number of ideas from diverse expertise.
•Technicians were trained in the use of PWIT and all stakeholders were shown the effects of the process change.
•Metric and Schedule reviews involving all stakeholders, Technicians, Pilots, Engineers, Quality Inspectors, & Customers were conducted.
•One great suggestion, from our brainstorming sessions, that was implemented was the portability of the wire integrity tester. Technicians and Quality Inspectors voiced concerns and provided expertise in making sure the tool could be used in the aircraft itself.
3939
39
How types of resistance were identified and addressed4A.b
Hard to use
Don’t AddMore Work
Cost is tooHigh
QualityVerification
Reliability ofPWIT
Easy to use
ReducedTotal Work
AffordableHigh ROI
IncreasedQuality
ReliabilityConfirmed
Identified Addressed
Section 4A.bWe identified resistance by speaking to stakeholders and showing them the proposed solution. Some of the concerns were:•Difficulty in using a new system,•Added workload,•Portability•And a reduction of Quality
For example, the difficulty of use and added workload concerns were brought forward by the technicians. These concerns were assuaged by gathering their inputs during the design and prototyping phases. We addressed each concern during project reviews attended by all stakeholders so that once the design was finished, it was clear that the system was easy to use and reduced their total workload.
4040
40
How stakeholder buy-in was ensured
Design and Project Reviews attended by all stakeholder groupsPrototyping gave technicians a tangible product to testPrototyping showed verifiabilityResults meet or exceeded expectations & requirements
4A.c
Loop-Back
Correct connections
Open connection
Mis-wire (“crossed wires”)
xx
x
Section 4A.cStakeholders were involved in all phases of the project, generating the concerns previously mentioned. Design and project reviews were held and all stakeholder groups, technicians, quality inspectors, pilots, engineers, and the customer, were represented at each of these reviews. Buy-in from all groups were needed to move forward to the next design phase of the project.
For example, prototyping and demonstration was essential for buy-in with the customer because after seeing the prototype in action, the customer committed funds for the full design. In addition, the demonstration was essential for the technicians because it showed their requirements & concerns were being tangibly addressed.
4141
41
Plan developed by team to implement solution4B.a
dddddd
System Validation
Execute Verification
IDENTIFYNEED FORCHANGE
AUTH.TO
DEVELOP
HIGHLEVELRQMT
INITIALCONCEPT
CONCEPTSELECT
PRELIMDEFIN.
DETAILDEFIN.
PRODUCE&
DELIVER
AUTH.TO
IMPLEM.PHASE 1 PHASE 2 PHASE 3 PHASE 4 PHASE 5 PHASE 6 PHASE 7 PHASE 8 PHASE 9
Project Level
Review
PPR SystemRequirement
Review
SystemDesignReview
ChangeControlBoard
PreliminaryDesignReview
CriticalDesignReview
Physical Configuration
Audit
Baseline top- level requirementsDefine candidate concepts Select concept
Authorize
Implement.Baseline complete
system requirements
Releasedrawings
Go / No -go decision
Project plan (IMP/IMS)
Promote to PLR
Requirements Validation1. Determine Verification
Methodfor each requirement
PHASE 10
OPSSUPPORT
Test Readiness
Review
2. Develop V&V Master Plan
Section 4B.aThe team reached a consensus with the customers & stakeholders when formulating a project plan. Per C-17 project management standards, several meetings took place to transform the project plan from major milestones down to the detailed task.
For each project review, there are entry and exit criteria that must be met before the official closure of the review. Each stakeholder group must agree that all criteria were met before moving to the next review.
4242
42
Procedure, system, or other changes made to implement the solution, and to sustain the results
4B.b
Value Stream Mapping
Loop-Back
Correct connections
Open connection
Mis-wire (“crossed wires”)x
x
x
Section 4B.bThe project team took into account the necessary changes to ensure and sustain accurate results.
New processes were generated, wasteful processes were removed, and existing processes were streamlined and made more efficient, integrating PWIT into the aircraft retrofit.
All stakeholders were trained to understand the new process flow for validating wiring changes, wire installations, and how each step may affect their daily tasks.
4343
43
Procedure, system, or other changes made to implement the solution, and to sustain the results
4B.b
Loop-Back
Correct connections
Open connection
Mis-wire (“crossed wires”)x
x
x
Technicians were trained in the use of PWIT.
Quality Inspectors were trained to understand and validate new reports generated from the PWIT System.
The confidence level for the team's ability to produce a defect free aircraft modification was high.
4444
44
Creating/Installing a system for measuring and sustaining results
4B.c
STEP 1Define
Process
STEP 2EstablishMetrics STEP 3
DeterminePerformance
STEP 4StabilizeProcess
STEP 5Set
Goals
STEP 6Develop
ImprovementPlan
STEP 7Implement
Improvements
Process
Based
Management
Section 4B.cThe over-arching system used has been our Process Based Management, to identify the area for improvement and drive this LEAN+ initiative.
The project team indentified several measurement systems that helped to validate their findings. In order to ensure that all organizational goals have been met, the project team used the following management tools: Mis-wire Logs, EVMS, and Trend Analysis.
Mis-wire logs were used to show time and process improvements, validating the capability of the system to catch mis-wirings quicker and more efficiently than the current process. The logs also provided data for the EVMS and Trend Analysis tools mentioned above.
EVMS was used to manage scope, schedule, and costs of a project.
Trend Analysis was used to track that data over time and validate results.
4545
45
Tangible and intangible results realized
Tangible:– 10 to 1 ROI exceeded.– Reducing wiring errors by 85%– Improving schedule 1 week.– Improving quality – no mis-
wired systems, no wiring defects, reduced re-work.
– Avoid damaging expensive aircraft equipment.
– Correction of previously untested, undected wiring problems.
– Ability to lower cost estimates on future bids of aircraft mods.
– Opportunity to competitively bid for other aircraft platforms, such as the P-8A, 787, C-130, etc..
Intangible– Improved Morale of Team– Pilot Confidence– Customer confidence
4C.a
Section 4C.aThe Tangible results realized were:
Cost savings exceeding our ROI projection of 10 to 1.Reduced wiring errors by 85%.Improved schedule performance by 1 week per aircraft.Improved quality - No mis-wired systems, no wiring defects, reduced re-work.and the other results shown on the slide
The Intangible results realized were:Improved Morale of entire Team.Increased Pilot Confidence in the quality of their airplane,
AndIncreased Customer confidence in Boeing’s workmanship.
4646
46
How project results link to organizational goals, performance measures, and/or strategies
4C.b
On timeDeliveryOn timeDelivery
ReduceWaste
ReduceWaste
ReduceRepetitionReduce
Repetition
ReduceReworkReduceRework
PWITGoals
GoalsMet
C-17 Long Term Strategy
Execute Flawlessly
Create New Frontiers
Our Vision:People Working Together
to Provide the World’s First Choice for Airlift/ Mobility Solutions
Our Vision:People Working Together
to Provide the World’s First Choice for Airlift/ Mobility Solutions
Exceed commitmentsAchieve aggressive, sustainable improvements to safety, quality, schedule and costStrengthen stakeholder relationshipsRelentlessly improve and integrate processes
Integrated innovative technology to bridge the C-17 to the AJACSLeverage Network Centric technology for Agile Mobility SolutionsCreate Network-Centric Capability Integration
Capture additional C-17 business (C-17, BC-17, International) and bridge to the C-17BKeep PE/PI soldExpand strategic alliances and partnershipsKeep GSP sold
Value Creation
Value Creation
Boeing Leadership AttributesLives Boeing Values – Finds a Way – Inspires Others – Sets High Expectations – Charts the Course – Delivers Results
Grow the Business
• Customer• Work Force• Suppliers• Community• Shareholders
StakeholderRequirements& Expectations
TimeTime
Growth Growth ++
ProductivityProductivity
Loop-Back
Correct connections
Open connection
Mis-wire (“crossed wires”)
xx
x
Value Stream Mapping
Section 4C.bThe implementation of the PWIT met and exceeded our organizational goals:
• Quality - no wiring defects flowed to the Pilots or Customer. This built Pilot & Customer Confidence in the quality of our work.
• Schedule - able to deliver the aircraft on time to the Customer. This built customer confidence in our ability to execute on time, as promised.
• Cycle Time - able to reduce cycle time by 1 week. This reduced waste and subsequently cost.
• Cost – ROI was 15 to 1, more than the projected 10 to 1.
4747
47
Explain how results were shared with stakeholders4C.c
Section 4C.cCommunication between the stakeholders and the project team played a key role in the success of implementing a project plan. Crucial parameters for success were built into the EVMS and project plan. These parameters were then agreed by all involved.
At the Team Level, pre-deployment and post deployment results were reviewed, and all agreed that the Log reports, write ups, technician reports, and pilot observances verified the expected results.
Evaluation forms filled out by the customer signified adherence to the project implementation expectations, that we will provide a product at the contractual date without open items.
For the Pilots, documented problems observed in flight were compared with written test procedures, and for the past 10 aircraft mods we have seen zero write ups related to wiring problems, a significant improvement in quality and workmanship.
The Technicians have been able to automatically identify problems accurately, showing a dramatic reduction in troubleshooting time.
And for Engineering, the various inputs allowed them to design & produce better wiring modification assemblies.
48
48
Team Management & Project Presentation
Criteria 5
Now D’Arcy will take you through the final criteria: Team Management and Project Presentation
Thank you Joe
49
49
Explain how team members were selected, and how they were involved throughout the projectProject Manager – Vincent TruongBSS Manager - Scott Bass Program Manager – Joe SunioCost Account Manager – D’Arcy StylianoProduction Support & Tools Manager – Lou RighiTechnical Lead – Paul D. KillianR & P Specialist – Paul D. Kim
5A
Section 5ATeam members were selected based on their overall knowledge of the business and quality issues facing BSS, as well as their leadership roles in selecting, implementing, and leading the activities that lead to the ultimate improvement being experienced at BSS as a result of PWIT.
During Value Stream Mapping analysis, Scott Bass was not only identified as a stakeholder, but was a key component in obtaining authorization for funding and implementation of the project. Vincent Truong and Paul Killian understood the needs of BSS and other stakeholders, and implemented the solution to bring about a positive change in the process of modifying aircraft at BSS and took this PWIT project from infancy through design to implementation.
50
50
How the team was prepared to work together
IntroductionsTeam Building - The Five Dysfunctions of a Team, according to Patrick M. Lencioni– Absence of Trust– Fear of Conflict– Lack of Commitment– Avoidance of Accountability– Inattention to Results
Ground Rules– Task and Performance Metrics Defined & Reviewed Periodically– Strengths & Weaknesses / Risks
CollaborationExecution
5B
Section 5BFollowing the team's selection, a series of meetings & training sessions were held outlining 5 key dysfunctions of a team, our own assessment of the team, and how we were going to address our shortcomings. The 5 dysfunctions are:
* Absence of Trust,* Fear of Conflict,* Lack of Commitment,* Avoidance of Accountability, and* Inattention to Results.
To help understand how to address the 5 dysfunctions we all agreed upon the goals of the project. It was agreed that all conflicts, accountability, and results will be measured by those goals. It was also understood that conflict was welcomed. We wanted true dialogue based on the trust that everyone had the same goals and objectives in mind.
51
51
How the team managed performance to ensure effectiveness
MeetingsStatus ReportingMetricsProject Management ToolsCustomer Engagement
5C
Section 5CAs expected, initial meetings were long with numerous conflicts. Ground rules were set and again personal attacks were not tolerated. Because we had agreed that all conflict resolutions would revolve around our goals, it was easy to see the team's effectiveness and cohesion as meetings became shorter, tasks were executed, and morale of the team remained high.
EVMS, Trend Analysis and other project management tools also aided in accountability and focusing our attention on the results. The tools were used to manage performance and the data from the tools gave us confidence in our progress.
For example, in our weekly meetings, as we got familiar with the metrics involved, status reports were shortened to basic statistical numbers, however, the quality of the statuses were high because we could openly and knowledgeably ask questions about the “numbers”, trusting the other member of the team would answer truthfully.The reports were also easily understood by all, regardless of background, due to the extensive training.
52
52
Questions?
And that concludes our PWIT Briefing