Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Public Hearing on the2035 Mobility Vision Plan (MVP)
Draft Cost-Feasible Plan
Steering Committee - January 28, 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Polk Transportation Planning OrganizationPolk Transportation Planning Organization
December 7, 2010December 7, 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
This agenda item will include a staff presentation, comments from the public and Board action.
Topics• How We Got to this Point
• Recent Changes to Draft Cost Feasible Plan
• Public Comments Received to Date
• Requested Action: Recommend Approval of Draft 2035 Mobility Vision Plan
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
TPO Actions in support of the 2035 MVP• June 2009 – Approved 2060 Transportation Vision
Plan
• June 2009 - Plan Branding & Schedule
• Oct. 2009 – Approved Vision Statement/GOPs
• June 2010 – Approved 2035 Needs Plan
• August 2010 – Approved Draft 2035 Cost Feasible Plan & established Public Comment period
• December 2010 – Adoption Hearing
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
2035 Mobility Vision
The 2035 MVP will provide a safe, efficient and sustainable multi-modal transportation system that meets the diverse mobility needs of Polk County residents, workers and visitors.
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Goals
– Goal 1: A Multimodal Transportation System
– Goal 2: A Sustainable Transportation System
– Goal 3: A Regional Transportation System
– Goal 4: Freight & Goods Movement
– Goal 5: Efficient & Interconnected Transportation System
– Goal 6: A Safe & Secure Transportation System
– Goal 7: Economic Development & Fiscal Considerations
– Goal 8: Mobility Vision Plan Content, Development & Priorities
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
How Were Needs Identified?• 2030 Plan (TRIP), and Studies & Plans
• 2060 Transportation Vision Plan
• Polk Transit Authority Plans
• Central Polk Parkway Study
• Florida High Speed Rail Project
• Local Government Comp. Plans
• Deficiencies Identified in Polk County Model
• Input from Steering Committee, Cities and County
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Cost Feasible Plan is:• Financially constrained version of the 2035
Needs Plan
• Based on available revenue (federal, state & local) through the year 2035.
• Contains the most important projects (priorities) indentified in the Needs Plan.
• The source for the TPO’s future priority projects.
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Prioritization of Projects
Transit• Ridership• Transit Potential• Regional Connectivity/Accessibility• PTA/2060 TVP• Planned Growth
Highway• Approved MVP Goals• Current Needs vs. Future Needs• Addresses Congestion• Provides a linkage to desired destination or
facilities• Community/Environmental Impacts
Bicycle/Pedestrian/Multi-Use Trail• Proximity to Schools, Parks, Transit Services• Transit Dependency• Links to other Facilities• Crashes• Regional Trail System• Connections to Conservation Areas
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Non-motorized Facilities
• Top 100 Projects identified for:– Bicycle Improvements – typically done as part
of road projects– Sidewalk Improvements – done as part of
road projects or stand-alone enhancements
• Top Multi-Use Trail Projects– Done as funding & opportunities arise
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Financial Resources
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
DRAFT
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Federal Cash Grants, $210
State Cash Grants, $79
Federal Discretionary Grants, $28
State Service Development
Grants, $7
Passenger Fares, $81
Proposed Local Tax, $914
Transit Funding Forecast(2015 - 2035, YOE $M) Total Funding = $1,320 M
DRAFT
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Transit NeedsEstimated Costs
(2016 – 2035)
Total Needs** $3,214 M
Cost Affordable Projects $1,004 M
Difference -$2,210 M
Highway Capacity Needs
Estimated Costs(2016 – 2035)
Total Needs* $5,663 M
Cost Affordable Projects $1,819 M
Difference -$3,844 M
*Estimates as of Sept. 2010; excludes SIS Funding** Assumes operating needs phased in over life of plan
Needs vs. Available Funding
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Funding Set-Aside for Other Projects• $80 M reserved for 2016 - 2035• For Congestion Management Projects, to be
determined:– Sidewalk Projects– Multi-Use Trail Projects– Intersection Improvements– Intelligent Transportation System Enhancements
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Cost Affordable Projects
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Recent Changes: Transit• Referendum Not Approved by Voters• Fed. Operating Assistance No Longer Available after
2010 Census shows Urbanized Area > 200,000 Population
• Maintaining Existing Service Depends on New Local Funding
• New Local Funding Source Assumed to be in place by 2014
• Effect is to Defer Implementation of Some Transit Improvements from 2011 to 2014
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Recent Changes: Central Polk Parkway• PD& E determined 6 Lane Need• Cost Feasible Projects include:
– 6-Lane Segment from I-4 to US 17/92– New Interchange with I-4
• Seeking Additional Funding through:– Toll Revenues– Next SIS Plan - TRIP– Federal Earmark(s) - Private Sources
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Other Recent Changes• North Ridge Trail (Project #312) is now a Committed
Project• Western Polk Connector (#207) now unfunded due to
unfunded Interchange with I-4• Holly Hill Rd (#321), FDC Grove Rd (#322) & Crevasse –
Lakeland Park Connector (#310) are now funded projects
• CR 580 (#357) added as Funded Safety Improvement• US 27 (#98) now a partially funded project.• Local Collector Roads now included as Needs
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Public Comments Received to Date & How the Plan Responds
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Public Workshops• August 24th – Lakeland Police
Department• August 31st – Winter Haven Public
Library• September 21st – NE Polk County
Sheriff’s Office Substation• October 7th – Poinciana Community
Center
Additional Opportunities• September 11th - Eagle Ridge Mall• September 25th - Lakeland Square
Mall• October 23rd – Lakeland Hispanic
Festival• October 30th - Water, Wings & Things
(Circle B Reserve)
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
2035 MVP Brochure• Maps and Descriptions of all of
the projects• Available in Spanish
Project Website - 2035MobilityVisionPlan.org
• MVP Documents• Online Survey
TV, Radio & Newspaper• 2035 MVP Video (PGTV and MVP
Website)• AM1430 & AM1250 Interview• Numerous articles, press releases
covered in local papers
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Other Recent Changes• Comments received on the Draft CF projects have
been compiled and applied to the final prioritization.
• Minor adjustments have been made based on these comments.– CR 580 (Cypress Parkway)– Western Polk Connector
• Most comments to remove a project:– Central Polk Parkway East (10); (5) E205– Prj# 266 Haines City – Davenport Eastern Rd (9); (4) End
the proposed road at Carl Boozer Rd.
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Action Requested
TPO Staff is recommending that the TPO Board approve the 2035 Mobility Vision Plan Draft Cost-Feasible Plan.
The TPO’s Citizens and Technical Advisory Committees have approved the 2035 MVP Draft Cost-Feasible Plan.
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
Public Hearing The Polk TPO holds all public hearings in
compliance with Titles VI and VIII of the Civil Rights Act. Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability, or family status.
Roll Call Vote is Required
Polk Transportation Planning Organization2035 Mobility Vision Plan
Nov./Dec. 2010
End Presentation