Points Heating Process

Contents1  Start-up ............................................................................................................................................ 2 1.1   Arrange Site Visit .................................................................................................................... 2 1.2  Site Visit .................................................................................................................................. 2 

2  Form A ............................................................................................................................................. 3 2.1  Document: ............................................................................................................................... 3 2.2  CAD ......................................................................................................................................... 3 

2.2.1  Site Layout Drawing ............................................................................................................ 3 2.2.2  Schematic ............................................................................................................................ 3 

2.3  Form A Checking .................................................................................................................... 4 2.4  Form A IDC ............................................................................................................................. 4 2.5  Form A CEM Review & Submission ....................................................................................... 4 

3  Form B ............................................................................................................................................. 5 3.1  Document ................................................................................................................................ 5 3.2  CAD ......................................................................................................................................... 5 

3.2.1  Site Layout Drawing ............................................................................................................ 5 3.2.2  Schematic ............................................................................................................................ 5 

3.3  Form B Checking .................................................................................................................... 6 3.4  Form B IDC ............................................................................................................................. 6 3.5  Form B CEM Review & Submission ....................................................................................... 6 

4   AFC .................................................................................................................................................. 7 4.1  Document ................................................................................................................................ 7 4.2  CAD ......................................................................................................................................... 7 

4.2.1  Site Layout Drawing ............................................................................................................ 7 4.2.2  Schematic ............................................................................................................................ 7 

4.3   AFC Checking ......................................................................................................................... 7 4.4   AFC IDC .................................................................................................................................. 8 4.5   AFC CEM Review & Submission ............................................................................................ 8 

Page 2: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 2/8

1  Start-up

  Identify scope of Points Heating.

  Read Client Remit/CRD/MFR which provides brief commentary on the site under consideration.

  Locate site on 5 mile plan and identify access points.

  Locate site on Google maps.

  Locate site on CAB ride video and try and determine location of existing assets.

  Discuss access arrangement with Site Planner (Andy Hazell).

  Use this time to visualize the site visit.

1.1   Arrange Site Visit

  Site visits to be arranged only after a finalized Permanent Way Footprint is available (Except

when doing Grip 2 works).

  Daytime surveys under Separated Zone conditions are preferred.

  Night Time surveys only to be done if Daytime surveys impossible.

  Ensure availability of personnel (i.e. yourself & Andy).

  Attendance of the NR Project Engineer is preferred. Try to ensure that the site visit is arranged to

his/her convenience.

  Arrange for Paperwork well in advance of site works (i.e. Task Brief & Safe System of Working

Document).

  Using information in Section 1 & points above amend site works table to ensure everything

required is picked up on site.

  Book a Pool Car in advance or use a hire car.

  Carry a camera, notepad, pens, safety paperwork, Multimeter, Clampmeter to site.

  Also carry A4 section print outs of the Permanent Way Site Layout drawings to easily mark-up on

site.

1.2  Site Visit

  Arrive and undertake the site visit as planned in sections1 & 1.1 above. 

  Ensure all measurements are taken and all relevant assets are marked up on site.

  Make notes and create a summary in word post the site visit as a record.

  Upload photographs to folder 48 and make sure it has a date and name to it.

Page 3: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 3/8

2  Form A

2.1  Document:

  Use a previous Form A as a template. 5110144 LNW North Folder 51 and any of the site

subfolders is a good place to start.

  Change headers, footers, titles to begin with and amend the Form A to suit the site.

  Amend every section in line with what was observed/ measured on site and the scope.

  The main focus of the Form A Is Approval in Principle: Is there enough power to supply the

renewed points, are there any space constraints, is the proposal feasible? At this stage your

document should be P01 (Preliminary).

2.2  CAD

2.2.1  Site Layout Drawing

  Obtain latest & finalized footprint (Horizontal Layout) in CAD/Microstation format from

the PWay Team (ask the PM for the details of the person to speak to).

  Liaise with Lucy to setup the drawing (CAD/Drawing folder), making sure that the drawing

covers the junction/renewals site and ask Lucy to print you a hard copy.

  Mark-up the existing assets on site as per what you noted on site, and mark-up new items

(i.e. DNO Supply Cubicles, Points Heating Control Cubicles, Points Heating Transformers

and associated text to describe these).

  Make sure that you also mark-up the trough route to show existing cable routes.  Mark-up any new cable trough routes.

  Give it to Lucy to CAD up and request her to print a copy once done.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments. At this stage your drawing should be

P01 (Preliminary).

2.2.2  Schematic

  Use an existing Schematic from the 5110144 LNW North Folder 56.3 (Golborne for 1

DNO, 1PHCC, Lancaster for 2 DNOs,2 PHCCS, Bamfurlong/Acton Bridge for 1 DNO, 2

PHCCs, and Earlestown/Penrith for 3 DNOs,3PHCCs).

  Modify the schematic to reflect the site specific DNO & Distribution characteristics, PHCC

connections and the type of point ends that are connected (based on photographs and

site notes.

  Give it to Lucy to CAD up and request her to print a copy once done.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments and pdf. At this stage your drawing

should be P01 (Preliminary).

Page 4: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 4/8

2.3  Form A Checking

  Compile a pdf of the Form A, Site Layout, Schematic and print a copy for Andy Hill.

  Make any necessary changes and send link (or pdf) to nominated checker and copy Andy into

all email interactions.

  Receive comments from the checker.

  Discuss with Andy, the checker’s comments and proceed to make any agreed changes to the

Form A. At this stage your Form A should be at P02 (Draft for Form A IDC).

2.4  Form A IDC

  Post the checking process, print 2 copies of the finalised Form A for Andy to take to an IDC

meeting.

  Post the IDC, discuss any comments with Andy and make agreed changes to the Form A.

  Include the IDC comments within the Form A document pdf.  Liaise with PWay and OLE close to the Form A submission date to ensure that our E&P

drawings are updated with the latest versions of the PWay drawings (confirm it also contains

the latest OLE layout).

  Ask Lucy to update our drawings with the updated PWay (At this stage your Form A should

be A01: For Form A Submission).

2.5  Form A CEM Review & Submission

  Sign the signature sheets within the document and obtain signatures from the checker and

 Andy.

  Print a copy of the signature sheets only in colour and a black and white copy of the Form A

and request a meeting with the CEM (if in the same office) or send a copy of the deliverable

via email (Please speak to the CEM before you do so).

  Await review comments, if there are no comments obtain the signature of the CEM (Final

signatory) and scan in the pages with everyone’s signatures on.

  Use PDF writer to replace the unsigned pdf pages with the signed pages.

  Print 3 copies of the Form A document (Colour/double sided) and 3 copies of the Site Layout

and Schematic drawings.  Bind the document and fold the drawings.

  Hand over the Form A to the PM/document controller and they will ensure that it is submitted

to the client. At this stage your drawing should be P01 (Preliminary).

Page 5: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 5/8

3  Form B

  Receive DRN (Design Review Notice) from Network Rail Project Engineer (NR PE).

  Review comments with Andy Hill.

  Draft up responses to the DRN with Andy and submit to the NR PE.

  Receive response acceptance from NR PE and receive approved Form A.

3.1  Document

  Update your approved Form A in line with a previous Form B as a template. 5110144 LNW

North Folder 51 and any of the site subfolders is a good place to start. (Just add the additional

sections in the other Form Bs to the Form A and do not re-write the Form B).

  The main focus of the Form B Detailed Design: Undertake Cable Calculations (230V

(Amtech), 110V (Excel)), Finalize location of new, modified and removed assets (PHT, PHCC,

DNO, TCBs, new trough routes, strip heaters).  Model the site based on a previous template (5110144 LNW North Folder 51) on Amtech to

obtain the 230V cable results. Ensure that there are no errors.

  Undertake 110V cable calculations also based on a previous template (5110144 LNW North

Folder 51). Update the relevant sections of the spreadsheet taking data from the 230V

 Amtech cable calculations. Ensure that there are no errors here either.

  Update the document with any comments agreed with the NR PE from the DRN.

  At this stage your document should be P03 (Preliminary).

3.2  CAD

3.2.1  Site Layout Drawing

  Obtain latest & finalized footprint (Horizontal Layout) in CAD/Microstation format from

the PWay Team.

  Liaise with Lucy to update the drawing (CAD/Drawing folder), making sure that the

drawing covers the junction/renewals site and ask Lucy to print you a hard copy.

  Add detail to the Form B site layout drawing. Layout of heater strips, location of new

TCBs.

  Update the drawing with any comments agreed with the NR PE from the DRN.

  Give it to Lucy to CAD up and request her to print a copy once done.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments. At this stage your drawing should be

P03 (Preliminary).

3.2.2  Schematic

  Modify the schematic to add the cable lengths, cable type, MCBs for the 230V and the

110V cables from Amtech and 110V excel spreadsheets.

  Update the drawing with any comments agreed with the NR PE from the DRN.

Page 6: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 6/8

  Give it to Lucy to CAD up and request her to print a copy once done.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments and pdf. At this stage your drawing

should be P03 (Preliminary).

3.3  Form B Checking

  Compile a pdf of the Form B, Site Layout, and Schematic and print a copy for Andy Hill.

  Make any necessary changes and send link to nominated checker (or pdf) and copy Andy into

all email interactions.

  Receive comments from the checker.

  Discuss with Andy, the checker’s comments and proceed to make any agreed changes to the

Form B. At this stage your drawing should be P04 ( Draft for IDC).

3.4  Form B IDC

  Post the checking process, print 2 copies of the finalised Form B for Andy to take to an IDC

meeting.

  Post the IDC, discuss any comments with Andy and make agreed changes to the Form B.

  Include the IDC comments within the Form B document pdf.

  Liaise with PWay and OLE close to the Form B submission date to ensure that our E&P

drawings are updated with the latest versions of the PWay drawings (confirm it also contains

the latest OLE layout).

  Ask Lucy to update our drawings with the updated PWay At this stage your drawing should be

B01 (for Form B Submission).

3.5  Form B CEM Review & Submission

  Sign the signature sheets within the document and obtain signatures from the checker and

 Andy.

  Print a copy of the signature sheets only in colour and a black and white copy of the Form B

and request a meeting with the CEM (if in the same office) or send a copy of the deliverable

via email (please speak to the CEM before you do so).

  Await review comments, if there are no comments obtain the signature of the CEM (final

signatory) and scan in the pages with everyone’s signatures on. 

  Use PDF writer to replace the unsigned pdf pages with the signed pages.

  Print 3 copies of the Form B document (Colour/double sided) and 3 copies of the Site Layout

and Schematic drawings.

  Bind the document and fold the drawings.

  A CD with the document and drawings may be to be produced, plus a duplicate to keep on

file.

  Hand over the Form B to the PM/document controller and they will ensure that it is submitted

to the client.

Page 7: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 7/8

4   AFC

  Receive DRN (Design Review Notice) from Network Rail Project Engineer (NR PE).

  Review comments with Andy Hill.

  Draft up responses to the DRN with Andy and submit to the NR PE.

  Receive response acceptance from NR PE and receive approved Form B.

4.1  Document

  No additions, just incorporation of NR PE comments.

  Update the document with any comments agreed with the NR PE from the DRN.

  At this stage your document should be C01 (Approved For Construction).

4.2  CAD

4.2.1  Site Layout Drawing

  Obtain latest & finalized footprint (Horizontal Layout) in CAD/Microstation format from

the PWay Team.

  Liaise with Lucy to update the drawing (CAD/Drawing folder), making sure that the

drawing covers the junction/renewals site and ask Lucy to print you a hard copy.

  Update the drawing with any comments agreed with the NR PE from the DRN.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments. At this stage your drawing should be

C01 (Approved for Construction).

4.2.2  Schematic

  Update the drawing with any comments agreed with the NR PE from the DRN.

  Give it to Lucy to CAD up and request her to print a copy once done.

  Check the CADed up version against your mark-up and identify any discrepancies.

  Give it back to Lucy to make any final amendments and pdf. At this stage your drawing

should be P03 (Preliminary).

4.3   AFC Checking  No additional checking required, Andy can check the AFC against NR PE Comments.

Page 8: Points Heating Process

8/12/2019 Points Heating Process

http://slidepdf.com/reader/full/points-heating-process 8/8

4.4   AFC IDC

May not be required, however, if required do as follows:

  Post the checking process, print 2 copies of the finalised AFC for Andy to take to an IDC

meeting.

  Post the IDC, discuss any comments with Andy and make agreed changes to the AFC.

  Include the IDC comments within the AFC document pdf.

  Liaise with PWay and OLE close to the AFC submission date to ensure that our E&P

drawings are updated with the latest versions of the PWay drawings (confirm it also contains

the latest OLE layout).

  Ask Lucy to update our drawings with the updated PWay, at this stage your drawing should

be B01 ( For AFC Submission).

4.5   AFC CEM Review & Submission

  Sign the signature sheets within the document and obtain signatures from the checker and

 Andy.

  Print a copy of the signature sheets only in colour and a black and white copy of the AFC and

request a meeting with the CEM (if in the same office) or send a copy of the deliverable via

email (please speak to the CEM before you do so).

  Await review comments, if there are no comments obtain the signature of the CEM (final

signatory) and scan in the pages with everyone’s signatures on. 

  Use PDF writer to replace the unsigned pdf pages with the signed pages.

  Print 3 copies of the AFC document (Colour/double sided) and 3 copies of the Site Layout

and Schematic drawings.

  Bind the document and fold the drawings.

  The CEM will need to stamp the document and drawings prior to AFC submission.

  Hand over the AFC to the PM/document controller and they will ensure that it is submitted to

the client.