118
PMP Essentials 21-Jan-2015 Compiled by Rakesh P This document contains essentials only, for detailed study you may refer PMBOK 5 th Ver. Please check the latest version for updated PPT

PMP.Essentials.150121

Embed Size (px)

Citation preview

Page 1: PMP.Essentials.150121

PMP Essentials 21-Jan-2015

Compiled by Rakesh P

This document contains essentials only, for detailed study you may refer PMBOK 5th Ver.

Please check the latest version for updated PPT

Page 2: PMP.Essentials.150121

PMP

• Project Coordinator

• Project expeditor

• Project Lead • Project Manager • Resources from many countries • More than 100 people • Project Management Team • Projects last longer than one year • High Budget • Ethics based on Ideal situations

illusion PMP is all about the best practices….

vs

29-49

Page 3: PMP.Essentials.150121

Project Management Fundamentals

Stake holder

Enterprise Environmental Factors

(EEF)

Organizational Process Assets (OPA )

Project

Program

Portfolio

Project Life Cycle

Organizational Structure

Functional Matrix Projectized

Organizational Project Management (OPM)

Constraints

Stakeholders

Project Phases

Project Management Office (PMO)

Page 4: PMP.Essentials.150121

Process Groups - 5

Knowledge Areas- 10

Processes- 47

Stake holder

About 185 Inputs Tools &

techniques Outputs

Page 5: PMP.Essentials.150121

Knowledge Areas 1. Initiating

2. Planning

3. Executing

4. Monitoring & Controlling

5. Closing

1. Integration . . . . .

2.Scope . .

3.Time . .

4.Cost . .

5.Quality . . .

6.Human Resource . .

7.Communication . . .

8.Risk . .

9.Procurement . . . .

10.Stakeholder . . . .

13 % 24 % 30 % 25 % 8 %

The PMP exams does not test on the Code of ethics and professional

conduct explicitly although the standards are integrated into the test

For all 5 process groups-

Proficient - Above average

Moderate Proficient – Average

Below Proficient- Below average

PMP Results

PASS / FAIL

Page 6: PMP.Essentials.150121

PMP (Project Management Professional) Exams

• Multiple choice (4) questions

• No negative marking

• Calculators are built into the Computer Based Test Exam

200 questions 4 Hours

175 questions

25 questions randomly placed "pre test questions" are included, and do not

count towards the pass/fail determination

Page 7: PMP.Essentials.150121

www.pmi.org • PMP (Project Management Professional)

• Based on PMBOK 5th version PMBOK - (Project Management Body of Knowledge)

• www.pmi.org membership (Optional)

myPMIRegister/Login

PMI Membership $ 129 + $ 10 and get free PMBOK 5th Edition

also get free e-books & sample questions.

• Project Management experience : For Graduate - 4,500 hours For High School – 7,500 hours

• 35 Contact hours ( Mandatory)

• Apply online for exams for ‘Confirmation on eligibility’ - Membership is not mandatory for applying. - PMI will review your application for completeness. And response in 5 working days.

3 years , within last 8 years

5 years , within last 8 years

Page 8: PMP.Essentials.150121

PMP Examination Fees

Total 3 attempts in a year

Page 9: PMP.Essentials.150121

Rescheduling the exams

Page 10: PMP.Essentials.150121

Exams eligibility

Eligibility of exams – one year after getting audit confirmation

21-49

Page 11: PMP.Essentials.150121

Confirmation on Exams eligibility

After 5 to 7 working days , Confirmation on eligibility ( for one year)

Page 12: PMP.Essentials.150121

www.prometric.com/pmi

Look at the availability for slots, select test location and month

Page 13: PMP.Essentials.150121

View your PMP certificate details

Page 14: PMP.Essentials.150121

Formulate a Plan

1. On first round , which you can answer within one minute each

2. Have a break of 10 minutes

3. On second round- these questions will take you a little longer to answer, but you may improve the speed 4. Have a break of 10 minutes 5. On third round, you will now be left most difficult / lengthy questions & review.

45 Questions in 30 minutes

120 Questions in 2:40 hours

30 Questions in 1 hour

Page 15: PMP.Essentials.150121

Answer all questions

You do not get any credit for an unanswered question.

If you are completely stumped by a question there are only four possible alternates.

You have at least 25% chance of getting it right.

2

If you can eliminate at least two apparently incorrect answers you chances have

improved to 50-50.

Always answer a question even if time is running out

Page 17: PMP.Essentials.150121

PMI Standards Extensions

• Software Extension to the PMBOK® Guide Fifth Edition

• Construction Extension to the PMBOK® Guide Third Edition

• Government Extension to the PMBOK® Guide Third Edition

Practice Guides

• Implementing Organizational Project Management: A Practice Guide

• Navigating Complexity: A Practice Guide

• Managing Change in Organizations: A Practice Guide

www.pmi.org membership benefits, Library of PMI global standards

Foundational Standards

• A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Fifth Edition

• PMBOK Guide 5th Edition in various languages

Chinese, French, German, Hindi, Italian, Japanese, Korean, Portuguese, Russian,

and Spanish translations of the Fifth Edition are available for PMI members to download. Sections

of the Arabic translation are available for PMI members.

• The Standard for Program Management—Third Edition

• The Standard for Portfolio Management—Third Edition

• Organizational Project Management Maturity Model (OPM3®)—Third Edition

Practice Standards and Frameworks

• Practice Standard for Project Risk Management

• Practice Standard for Earned Value Management—Second Edition

• Practice Standard for Project Configuration Management

• Practice Standard for Work Breakdown Structures—Second Edition (Reaffirmed)

• Practice Standard for Scheduling—Second Edition

• Practice Standard for Project Estimating

• Project Manager Competency Development Framework—Second Edition

http://pmi.books24X7.com (PMP Exam Prep: Questions, Answers & Explanations by Christopher Scordo)

Page 18: PMP.Essentials.150121

Few Suggested course material-

Suggested Study material

PMP Exam Prep - 8th Edition - Rita Mulkahy (Study “Knowledge area wise”)

PMP Certifications DUMMIES- 2nd edition- Cynthia Snyder

(Revise “Project Process Group: wise)

www.edwel.com (Free complimentary course material and questions)

Page 20: PMP.Essentials.150121

Refer PMP handbook for details

http://www.pmi.org/Certification/~/media/PDF/Certifications/pdc_pmphandbook.as

hx

PMI Lexicon of Project Management – Common Vocabulary

Code of Ethics and Professional Conduct

http://www.pmi.org/PMBOK-Guide-and-Standards/~/media/Registered/PMI_Lexicon_Final.ashx

http://www.pmi.org/en/About-Us/Ethics/~/media/PDF/Ethics/ap_pmicodeofethics.ashx

http://www.pmi.org/en/Certification/Project-Management-Professional-PMP/~/media/PDF/Certifications/PMP%20Examination%20Content%20Outline_2010.ashx

Examination Content Outline

Page 21: PMP.Essentials.150121

Project Management Experience

The PMI does occasionally audit the information that is presented in applications

in order to ensure that all the requisites are in order. You want to make sure that

you are honest about the information that is being presented. If your application is

audited your approval will be delayed until the audit is completed. Up to 10% of

PMI applications are audited.

Filling the PMP credential application

44-51

Page 22: PMP.Essentials.150121

Project Management Experience

Project Title

Role Designation Start End months Initiating (Hour)

Planning (Hour)

Executing (Hour)

M & C (Hours)

Closing (Hours)

Total (Hours)

Project Summary

Total

The PMI does occasionally audit the information that is presented in applications

in order to ensure that all the requisites are in order. You want to make sure that

you are honest about the information that is being presented. If your application is

audited your approval will be delayed until the audit is completed. Up to 10% of

PMI applications are audited.

Filling the PMP credential application

Page 23: PMP.Essentials.150121

Project Management Experience- overlapping

Jan, Feb, Mar, Apr – Project 1

May, Jun – Project 2

Jul, Aug, Sep, Oct, Nov- Project 3

Page 24: PMP.Essentials.150121

Project Management Experience

Sample Form

Sample form for filling online project details for PMP. Fill project wide details

Project Management Experiences: Application Development: OVERVIEW Started

Sep 2008

Through

Mar 2010

Project Role

Project Manager

Primary Industry

IT/Software

Application Development: ORGANIZATION DETAILS Job Title

Organization Name

Address Line 1

Address Line 2

Address Line 3

City State/Providence/Territory Zip/Postal Code

Country

Phone Number

Contact Name

Contact Relationship

Contact E-mail Contact Phone Number

Application Development: PROJECT DETAILS Initiating Domain

760.00 Planning Domain

1,500.00 Executing Domain

3,000.00 Controlling Domain

2000.00 Closing Domain

600.00

Project details

City

Contact Relationship

Contact Name

Organization Name

Address Line 1

Contact E-mail Contact Phone Number

Zip/Postal Code

Job Title

Phone Number

Country

√ √

350 to 550 character

Page 25: PMP.Essentials.150121

Project Management Experience

Application Development: PROJECT DETAILS Initiating Domain

760.00 Planning Domain

1,500.00 Executing Domain

3,000.00 Controlling Domain

2000.00 Closing Domain

600.00

Project details

Project details (350 to 550 character)

• A brief, one-sentence project objective Project deliverables

IN-

PL-

EX-

MC-

CL- • A brief, one-sentence project outcome

Important-

Overlapping hours

Number of working hours in a month - ?

Page 26: PMP.Essentials.150121

Project Management Experience- Example

A brief, one-sentence project objective including project name and client

Project deliverables summarized by following process areas:

IN-Helped in writing Project Charter, Identified project phases, Identified key

stakeholders, understood business case etc.

PL- Created Project Management plan and subsidiary plans, Requirement

gathering, WBS, developed schedule and budget, Identified major risks,

created Change Management Plan, Kickoff meeting etc.

EX- Acquired final team, Hold meetings, Assigned task to team, gathered

status data, Issue tracking, Quality Audit, implemented approved change

requests, etc.

MC- Weekly status reports, Testing, Forecasting, UAT, Performance reporting,

etc.

CL- Final acceptance, Financial and Procurement closure, documented lesson

Learned, etc.

* A brief, one-sentence project outcome (ROI)

Page 27: PMP.Essentials.150121

Relationships Among Portfolios, Programs, and Projects contd…

• Organizational strategies and priorities are linked • Have relationships between portfolios and programs Organizational planning impacts the projects by means of project prioritization based on risk, funding, and other considerations relevant to the organization’s strategic plan.

Program Management Group of related projects Obtain benefits and control not available from managing them individually

Portfolio Management To achieve Strategic business objectives Prioritize resource allocations

Page 28: PMP.Essentials.150121

What is Project Management? Balancing Project Constraints

Resource Quality Risk

Expended to…

Customer satisfaction

13-28

Page 29: PMP.Essentials.150121

A strategy execution framework utilizing

– project, program, and portfolio management

– as well as organizational enabling practices

to consistently and predictably deliver organizational strategy producing

– better performance,

– better results,

– and a sustainable competitive advantage.

Organizational Project Management (OPM)

Organizational Project Management

(OPM)

Portfolio Management

Program Management

Project Management examines an enterprise’s project management

process capabilities.

OPM

Organizational Project Management Maturity Model (OPM3®)

Page 30: PMP.Essentials.150121

Organization Structure

Functional Head 1

Head of Projects

Project Manager

Functional Head 2

Functional Head 3

Staff

Staff

Staff/ Expeditor / Coordinator

Staff

Staff

Staff

Project Manager

Functional

Weak Matrix

Balance Matrix

Strong Matrix Staff Staff

Project Manager

Staff

Staff

Projectized CEO Coordination

Page 31: PMP.Essentials.150121

Process

Process Groups: I P E M&C C

Knowledge Areas:

I Scoped Time Cost and Quality with my HR to Communicate Risks

on Procurement to our Stakeholders.

Communicating Quality is 3. 3 X 2 6

Cost of Procurement to HR and Stakeholders is 4 4X4 16

Integrating Risk and Scope is 6. 6X3 18

Time is more costly at 7. 7X1 7

Total 47

Processes:

Page 32: PMP.Essentials.150121

processes

Initiating Planning Executing M&C Closing

1 Integration 1 1

2 Scope

3 Time

4 Cost

5 Quality

6 HR

7 Communications

8 Risk

9 Procurement 1

10 Stakeholder 1

Mark 4 boundaries for 4 process, right down above one

2 initiating ( develop project charter, 2.Identify stakeholder)

2 Closing ( Close project or phase, 2. Close procurements)

Page 33: PMP.Essentials.150121

processes

Initiating Planning Executing M&C Closing

1 Integration 0+2

2 Scope 1+1

3 Time 1

4 Cost 1

5 Quality 1

6 HR

7 Communications 1

8 Risk 1

9 Procurement 1

10 Stakeholder 1

11 processes in Monitoring & controlling

No controls in HR

8 controls ( Knowledge area wise)

2 integration-1. Monitor and control project work 2- Perform integrated change Control

1 scope- 1. control scope, 2. validate scope

1.Monitor & Control Project Work 2.Perform Integrated Change Control

1.Validate Scope

Page 34: PMP.Essentials.150121

processes

Initiating Planning Executing M&C Closing

1 Integration 1

2 Scope 1+3

3 Time 1+5

4 Cost 1+2

5 Quality 1

6 HR 1

7 Communications 1

8 Risk 1+4

9 Procurement 1

10 Stakeholder 1

Total 24 processes in planning – 10 planning processes in each knowledge areas 14 in Scope, Time, Cost and Risk 3 Scope: 1.Collect Requirements, 2.Define Scope, 3.Create WBS, 5 Time: 1.Define Activities, 2.Sequence Activities, 3.Estimate Activity Resources, 4.Estimate Activity Duration's and 5.Develop Schedule. 2 Cost: 1.Estimate Costs and 2.Determine Budget. 4 Risk: 1.Identify Risks, 2.Perform Qualitative Risk Analysis, 3.Perform Quantitative) Risk Analysis, 4.Plan Risk Responses.)

1.Collect Requirements, 2.Define Scope, 3.Create WBS,

1.Estimate Costs, 2.Determine Budget.

,

1.Identify Risks, 2.Perform Qualitative Risk

Analysis, 3.Perform Quantitative Risk Analysis,

4.Plan Risk Responses

1.Define Activities, 2.Sequence

Activities, 3.Estimate Activity

Resources, 4.Estimate Activity

Duration's and 5.Develop Schedule.

Page 35: PMP.Essentials.150121

processes

Initiating Planning Executing M&C Closing

1 Integration 1

2 Scope

3 Time

4 Cost

5 Quality 1

6 HR 3

7 Communications 1

8 Risk

9 Procurement 1

10 Stakeholder 1

8 processes in Executing:

3 HR –Acquire project team, 2.Develop project team, 3.Manage project team

5 integration, Quality, communication, procurement and stakeholders

(1.Direct & manage project work,

2.Perform QA,

3.Manage communications,

4. Conduct procurements

5. Manage stakeholder engagements,)

Page 36: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Economic Models for Project Selection (Under Benefit Measurement Methods/Comparative approach)

1. Present Value (PV)

2. Net Present Value (NPV)

3. Internal Rate of return (IRR)

4. Payback Period

5. Cost benefit analysis

Page 37: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Present Value ( PV)

Value today of future cash flows

Qu: What is the present value of $ 300,000 received three years from now, if

we expect the interest rate to be 10 percent? Should the answer be more or less

than $ 300,000:

Ans- Less.

300,000/(1+.0.1) ³

= 300,000/(1.1 * 1.1 * 1.1)

= 300,000/1.331

= $ 225,394

Note: PV is also used for Planned Value (Cost Management)

Page 38: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter Net Present Value(NPV)

Present value of the total benefits(income or revenue) minus the cost over many

time periods

How to Calculate NPV

If NPV is +ve the investment is a good choice

Project with the greatest NPV is typically selected

Qu: Two project to chose,

Project A will take 3 year to complete and has NPV of $45,000

Project B will take 6 years to complete and has NPV of $85,000

Ans: Project B, Higher the NPV,

Time Period Income/Revenue PV of Income @ 10% interest rate

Costs PV of cost @ 10% interest rate

0 0 0 200 200

1 50 45 100 91

2 100 83 0 0

3 300 225 0 0

353 291

NPV = 353-291 = $ 62

Page 39: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Internal Rate of Return (IRR) • Think of Bank account ( interest rate)

• If a company has more than one project in which to invest, select with highest

return

• The rate (“interest rate”) at which the project inflows(revenues) and project outflows (costs) are equal.

Higher the IRR number, the better

Qu. Project A with an IRR of 21 % and Project B with an IRR of 15 %. Which one is a better option Ans. Project A ( Higher return)

Page 40: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Payback Period

Length of time it takes to recover its investment in the

project before it starts accumulating profit

Select Lesser payback period project

Page 41: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Cost Benefit analysis

Compares the expected costs of the project to the potential benefits

Benefits are same as revenue. Revenue is not the same as profit.

It is expressed as a decimal or ratio.

Greater than means the benefits are greater than cost

The BCR is the ratio benefits to cost.

Example: Sale price (1500)/ Cost(1000) = 1.5 to 1

You get $1.5 of benefit for every $1.00 of cost. Greater than one

indicates the benefits are greater than costs.

20/34

Page 42: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 1.Develop Project CharterOutputs1.Project Charter

Project A Project B Which Project would you select?

Net present value Rs 95,000 Rs 75,000 A

IRR 13 per cent 17 per cent B

Payback period 16 months 21 months A

Benefit(Revenue) Cost Ratio

2.79 1.3 A

Examples

Select Higher value

Select Lower value

Page 43: PMP.Essentials.150121

Inte

grat

ion

Man

agem

en

t 3.Direct and Manage Project WorkOutputs

Work Performance Data (Basic raw data) The raw observations and measurements identified during activities being performed

to carry out the project work.

This includes # of change request, # of defects, Technical performance measure,

Actual cost, Actual Schedule

-------------------------------------------------------------------------------------------------

Work Performance Information (Foundation for project decisions) The performance data collected from various controlling processes, analyzed in

context and integrated based on relationships across areas

Implementation status of change requests , Forecasted estimates to complete, Status

of deliverables

Work Performance Report (Formal reports) The physical and electronic representation of work performance information compiled

in project documents. Intended to generate decisions, actions, or awareness

Status report, recommendations ,Memos, justifications

Work Performance Data

Page 44: PMP.Essentials.150121

Work performance data, Information, Reports

1. Validate Scope

2. Control Scope

3. Control Schedule

4. Control Cost

5. Control Quality

6. Control Communications

7. Control Stakeholder

Engagement

8. Control Risks*

9. Control Procurement**

Work performance

Data

# of change request,

# of defects, Technical

performance measure,

Actual cost, Actual

Schedule

Work performance Information Foundation for project decisions- • Implementation status of change

requests • Forecasted estimates to complete • Status of deliverables

Monitor & control

Project work

Work performance

Reports

Status report,

recommendations ,

Memos, justifications

Perform Integrated

Change Control

Direct & Manage

Project work

Control Risks*

Control procurements**

Page 45: PMP.Essentials.150121

Deliverables

Validate Scope

c

Accepted deliverables

deliverables Control Quality

Validated deliverables (verified deliverables)

Direct & Manage project

work

Close project or phase

Page 46: PMP.Essentials.150121

Sco

pe

Man

agem

ent Summary

Control Quality

Validate Scope

Direct and Manage Project work

Closing

Development

Close Project or Phase

Testing

Page 47: PMP.Essentials.150121

6.Control Scope Sc

op

e M

anag

emen

t

No Gold plating

• Gold plating a project (adding extras) is not allowed

• Any change to scope must be evaluated for its effect on time,

cost, risk, quality, resources, and customer satisfaction

• No changes to scope are allowed without an approved

change request

• Scope changes should not be approved if they relate to work

that does not fit within the project charter

• You need to continuously determine what is and is not

included in the project

Page 48: PMP.Essentials.150121

2.Collect Requirements T&T5.Group Decision-Making techniques Sc

op

e M

anag

emen

t

An assessment process having multiple alternatives with an expected outcome in the

form of future actions. These techniques can be used to generate, classify, and

prioritize product requirements.

There are various methods of reaching a group decision, such as:

1. Unanimity. A decision that is reached whereby everyone agrees on a single

course of action. One way to reach unanimity is the Delphi technique, in which a

selected group of experts answers questionnaires and provides feedback regarding

the responses from each round of requirements gathering. The responses are only

available to the facilitator to maintain anonymity.

2. Majority. A decision that is reached with support obtained from more than 50 % of

the members of the group. Having a group size with an uneven number of

participants can ensure that a decision will be reached, rather than resulting in a tie.

3. Plurality. A decision that is reached whereby the largest block in a group decides,

even if a majority is not achieved. This method is generally used when the number of

options nominated is more than two.

4. Dictatorship. In this method, one individual makes the decision for the group.

Page 49: PMP.Essentials.150121

4. Estimate Activity ResourcesOutputs Ti

me

Man

agem

ent

.1 Activity resource requirements

.2 Resource breakdown structure

.3 Project documents updates

.2 Resource breakdown structure A hierarchical representation of resources by category and type Another way to display resource requirements is a resource histogram It is a bar chart showing the amount of time that a resource is scheduled to work over series of time period For example: skill set needed and the months they are needed

1 Activity resource requirements The types and quantities of resources required for each activity in a work package

Page 50: PMP.Essentials.150121

Tim

e M

anag

emen

t

PERT ( Program Evaluation and Review Technique)

1. Beta Distribution

Expected Value = (Optimistic+ 4 * Most Likely + Pessimistic)

____________________________________

6

2. Triangular Distribution

Expected Value = (Optimistic+ Most Likely + Pessimistic)

____________________________________

3

5. Estimate Activity DurationsT&T4. Three-point estimating

Page 51: PMP.Essentials.150121

Tim

e M

anag

emen

t

`

Standard Deviation = (Pessimistic-Optimistic)

6

if you have multiple task, square SD for each task, total it . Take a square

root of the total.

5. Estimate Activity DurationsT&T4. Three-point estimating 5. Estimate Activity DurationsT&T4. Three-point estimating

1 Sigma - + 68.26 %

2 Sigma - + 95.44 %

3 Sigma - + 99.73%

Page 52: PMP.Essentials.150121

Tim

e M

anag

emen

t Prediction

Page 53: PMP.Essentials.150121

Tim

e M

anag

emen

t 6.Develop ScheduleT&T2.Critical Path Method

The critical path is the longest duration path through a network diagram and

determines the shortest time to compete the project

Critical path

Path Duration

Start, 1,2,4,5,End 3+3+8+4 =18

Start, 1,,3,5, End 3+6+4=13

Activity 1

Activity 3

Activity 2

Activity 5

Activity 4

3

6

3 8

4

Shown with bold arrows is the longest duration path, hence Critical path,

18 weeks long

Page 54: PMP.Essentials.150121

Tim

e M

anag

emen

t 6. Develop ScheduleT&T2.Critical Path Method

1 3 3

Activity 1

1 0 3 4 6 9

Activity 3

9 Float =5

14

7 8 14

Activity 4

6 o 14 15 4 18

Activity 5

15 0 18

Start

4 3 6

Activity 2

4 0 7

Float formula:

Late finish-Early Finish = 14-9 =5

Late Start – Early Start = 9-4 =5

End

ES Duration EF

Activity Name

LS Total Float LF

Forward

Pass

Backward

Pass

ES-Early Start, LS-Late Start,

EF-Early Finish, LF-Late Finish

Calculate float Any mistake ?

Page 55: PMP.Essentials.150121

Change request, Approved change requests, Validated changes

PL

Plan Procurement Management

EX

Direct and Manage Project Work

Perform Quality Assurance

Manage Project team

Manage stakeholder engagement

Conduct procurements

MC

Validate scope

Control scope

Control schedule

Control cost

Control Quality

Control Communications

Control Risks

Control Procurements *

Control stakeholders Engagement

1.Direct & Manage Project Work

2.Control procurements*

Validated changes

Change Request

Perform Integrated

change control

Approved Change Requests

Control Quality

Monitor & control project work**

Page 56: PMP.Essentials.150121

Tim

e M

anag

emen

t

Applying leads and lags

Lead: allowing successor activity to be scheduled earlier

3.Sequence ActivitiesT&T 3. Leads and Lags

Plastering Painting

FS+2 d

Lag: gap is inserted waiting time between activities,.

Activity B

Activity A

SS-5d

Page 57: PMP.Essentials.150121

Co

st M

anag

eme

nt

2.Estimate CostsT&T

12-54

Standard project estimating accuracy ranges

Type Range Use

Rough Order of magnitude (ROM)

-25% to +75% In concept phase. Top down, Little information

Budgetary -10% to +25% In the planning phase Decomposed from top down Some information

Definitive -5% to +10% In production Bottom-Up Detailed information

Page 58: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T

Cost of Quality

benefits of meeting quality requirements

Failure costs are also known as cost of poor quality

Cost of Conformance Money spent during the project to avoid failures

1. Prevention Cost – Training, Document processes 2. Appraisal Cost – Testing, Inspections

Cost of Nonconformance (Cost of Poor Quality) Money spent during and after the project because of failure

1. Internal Failure Cost – Rework, Scrap 2. External Failure Cost- Warranty, Lost Business, Liability

Page 59: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T

Cost of Quality

benefits of meeting quality requirements

Failure costs are also known as cost of poor quality

Cost of Conformance Money spent during the project to avoid failures

1. Prevention Cost – Training, Document processes 2. Appraisal Cost – Testing, Inspections

Cost of Nonconformance (Cost of Poor Quality) Money spent during and after the project because of failure

1. Internal Failure Cost – Rework, Scrap 2. External Failure Cost- Warranty, Lost Business, Liability

Page 60: PMP.Essentials.150121

Co

st M

anag

eme

nt

4.Control CostT&T1. Earned Value management

Actual Cost (AC)

Management Reserves

(BAC) Budget at Completed

Estimate at Completion (EAC)

• Project Cost

As on date Planned Completion Date

Revised Completion Date

• Cost Baseline

Cu

mu

lati

ve c

ost

Time

Planned value (PV)

Earned value (EV)

Forecast

Forecast

Forecast

Page 61: PMP.Essentials.150121

Example of Earned value

1. Based on % of work done as on today

PV (Planned value )= $ 10,000

If Work done = 50%

What is the value of work done = 10,000X50%= $ 5,000 Earned value

2. Based on aggregation of work package as on today

PV (Planned value)= $ 10,000 (Work package 1,3,4,6,7,8)

( 2000+1000+2000+1000+2000+2000)

If Work done = work package 1,3,4

What is the value of work done = 2,000+1,000+2,000

= $ 5,000 Earned value

Co

st M

anag

eme

nt

4.Control CostsT&T1. Earned Value Management ( EVM)

Page 62: PMP.Essentials.150121

Integrates scope, time and cost measures

PV – Planned Value (as on date), BAC- Budget at Completion (Total project cost)

AC – Actual Cost (as on date)

EV – Earned Value (value of planned work done as on a date)

• Schedule Variance SV=EV-PV

NEGATIVE is behind schedule, POSITIVE is ahead of schedule.

• Cost Variance CV=EV-AC

NEGATIVE is over budget, POSITIVE is under budget.

“Greater EV is better for project”

• Schedule Performance Index SPI = EV/PV

> 1 ahead of schedule

We are (only) progressing at ……… % of the rate originally planned.

• Cost Performance Index CPI =EV/AC

> 1 under budget

We are getting ………cents worth of work out of every $1 spent.

Co

st M

anag

eme

nt

4.Control CostsT&T1. Earned Value Management ( EVM)

Page 63: PMP.Essentials.150121

Example:

• As on Today PV=10,000

EV=10,000X50%= 5,000 (50% of planned work done)

AC=15,000

• CV=EV-AC=5,000-15,000 = (-) 10,000, more than budgeted

• SV=EV-PV=5,000-10,000= (-) 5,000, behind schedule

• CPI=EV/AC=5,000/15,000=.33 We are only getting 33 cents out of every dollar we put in the project

• SPI=EV/PV=5,000/10,000=.5 We are only progressing at 50 % of the rate planned

Co

st M

anag

eme

nt

4. Control CostsT&T1. Earned Value Management ( EVM)

Page 64: PMP.Essentials.150121

C

ost

Man

agem

en

t 4.Control CostsT&T1.Earned Value Management ( EVM)

Ans next…

34-54

If actual cost = 400, earned value = 350, planed value = 325, what is the cost variance A.350 B. -75 C. 400 D. -50

Page 65: PMP.Essentials.150121

C

ost

Man

agem

en

t 4.Control CostsT&T1. Earned Value Management ( EVM)

D = -50

If actual cost = 400, earned value = 350, planed value = 325, what is the cost variance A.350 B. -75 C. 400 D. -50

CV = EV-AC = 350-400 = -50

Page 66: PMP.Essentials.150121

Co

st M

anag

eme

nt

4.Control CostT&T2.Forecasting

Actual Cost (AC)

Management Reserves

(BAC) Budget at Completed

Estimate at Completion (EAC)

• Project Cost

As on date Planned Completion Date

Revised Completion Date

• Cost Baseline

Cu

mu

lati

ve c

ost

Time

Planned value (PV)

Earned value (EV)

Forecast

Forecast

Forecast

Page 67: PMP.Essentials.150121

Estimate at Completion (EAC),

may differ from Budget at Completion (BAC)

1. PM develops forecasted EAC, if BAC is no longer viable.

EAC=AC+ bottom-up ETC(Estimate to complete)

( most common bottom up simulation)

2. If problem will not occur in future

EAC = AC+BAC-EV

3. If expected to continue as earlier performance as per same CPI ( Cost)

EAC=BAC/CPI

4. If expected to perform at efficiency rate considers both CPI and SPI

EAC=AC+[(BAC-EV)/(cumulative CPI x Cumulative SPI)]

Stop work , if there is no budget or time included for this

Note : Estimate to Complete , ETC = EAC-AC

Co

st M

anag

eme

nt

4.Control CostT&T2.Forecasting

Page 68: PMP.Essentials.150121

• PV=3000

• EV=2500

• AC=2800

• CV=-300 we are over budget by $300

• CPI=.893

• SV=-500 we are behind schedule

• SPI=.833

• BAC=4000

• EAC=BAC/CPI = 4000/.893=4479, We currently estimate that the total

project will cost $ 4479

• ETC= EAC-AC = 4479-2800=1679, We need to spend $1679 to finish the

project

Co

st M

anag

eme

nt

4.Control CostT&T2.Forecasting

38-54

Page 69: PMP.Essentials.150121

Co

st M

anag

eme

nt

4. Control CostT&T 2. Forecasting

Progress Reporting of WBS Components

Rule When begins When completed

50/50 Rule 50% 100%

20/80 Rule 20% 100%

0/100 Rule 0% 100%

The status of any activity is considered as follows , when begins

and completed and the forecast will very based on following options:

PMBOK

221

Page 70: PMP.Essentials.150121

Co

st M

anag

eme

nt

4. Control CostT&T3.To-Complete Performance Index (TCPI)

A measure of cost performance that must be achieved when the remaining

resources in order to meet a specified management goal, expressed as the rate of

the cost to finish the outstanding work to the budget available

TCPI = work remaining ( BAC-EV)

fund remaining (BAC-AC)

To achieve BAC or new EAC get $.... Worth of value for every dollar

you spend

Note, EAC = BAC/CPI,(if work continues at same cost efficiency)

If TCPI is greater than 1 Harder to complete

The efficiency that must be maintained in order to complete on plan (BAC) BAC-EV BAC-AC

The efficiency that must be maintained in order to complete the current ETC BAC-EV EAC-AC

Page 71: PMP.Essentials.150121

Co

st M

anag

eme

nt

4.Control Cost T&T4.Performence Reviews

VAC= 4000-4479

= - 479,

We currently expect to be $ 479 over budget when the project is completed

Variance analysis.

Indicator of weather project is over or under the Budge at Completion ( BAC)

Variance At Completion

VAC = BAC – EAC

Budget at Completion-Estimate at Completion

+ve project is under budget

-ve project is over budget

=0 project is on budget

example

Page 72: PMP.Essentials.150121

COST

COST

COST

COST

Name Formula

Cost variance CV = EV - AC

Schedule variance SV = EV - PV

Cost performance Index CPI = EV / AC

Schedule performance index SPI = EV / PV

Name Formula

Estimate at completion - 1 EAC = AC + New ETC

Estimate at completion - 2 EAC = AC + BAC-EV

Estimate at completion - 3 EAC = BAC / CPI

Estimate at completion - 4 EAC = AC + ( BAC-EV) / CPIC X SPIC

To-Complete-Performance Index

TCPI= BAC-EV or BAC-EV BAC-AC EAC-AC

Estimate To Complete ETC = EAC- AC

Variance At Completion VAC = BAC-EAC

Type Range Use

Rough Order of magnitude (ROM)

-25% to +75%

In concept phase. Top down, Little information

Budgetary -10% to +25%

In the planning phase Decomposed from top down Some information

Definitive -5% to +10%

In production Bottom-Up Detailed information

COST OF QUALITY of Conformance Money spent during the project to avoid failures

1. Prevention Cost – Training, Document processes 2. Appraisal Cost – Testing, Inspections

Cost of Nonconformance (Cost of Poor Quality) Money spent during and after the project because of failure

1. Internal Failure Cost – Rework, Scrap 2. External Failure Cost- Warranty, Lost Business, Liability

Page 73: PMP.Essentials.150121

Qu

alit

y Quality Theorists

is defined as the degree to which the project fulfills requirements

required specs poor quality

(not as per specs)

refers to a general category or classification for a deliverable or

resource that indicates common function, but varying technical specifications

Grade, directly relates to reduced or additional functionality, influenced by cost.

Schedule, market condition etc

Symmetrical item, good grade

Low quality is always a problem; low grade may not be

Quality

Grade

Page 74: PMP.Essentials.150121

Qu

alit

y Quality

• Precision and Accuracy are not equivalent.

• Precision is consistency that the value of repeated

measurements are clustered and have little scatter.

(An assessment of exactness)

• Accuracy is correctness that the measured value is very

close to the true value.

(An assessment of correctness)

• Precise measurement are not necessarily accurate.

Precision Accuracy

Page 75: PMP.Essentials.150121

Qu

alit

y Quality Theorists -2. Proprietary Approach

Deming He developed 14 points to total quality management and advocated the Plan-Do-Check-Act (PDCA) cycle’ as the basis for quality improvement . 85% of cost of quality is management responsibility.

Juran He developed the 80/20 principle, advocated top management involvement and defined quality as ‘fitness for use” Defined by customer

Crossby Do the right the first time. The cost of non conformance is high. He popularized the concept of the cost of poor quality and advocated prevention over inspection and ‘zero defects’. He believed that quality is conformance to requirements

Kaizen Continuous improvement Sustained gradual small improvements

Taguchi Loss Function. Taguchi suggests that there is increasing loss, for the producer, the customer, and society, associated with increasing variability, or deviation from a target value that reflects the "ideal state." This relationship to variability can be expressed as a loss function

Page 76: PMP.Essentials.150121

Qu

alit

y

3. Seven Basic Quality Tools

1.Plan Quality ManagementT&T

1. Cause & Effect Diagram

2. Flowcharts

3. Check sheets

4.Pareto Diagrams

5. Histograms

6. Control charts

7. Scatter Diagrams

Page 77: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

The causes are found by looking at the problem statement and asking “why” until the

actionable root cause has been identified

1. Cause & Effect Diagram- Fishbone or Ishikawa diagram

Page 78: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

SIPOC Model

(Supplier-Input-Process-Output-Customer)

How a process or system flows from beginning to end

Determine the cost of quality

2. Flow charts

Page 79: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

They are especially useful for gathering attributes data while

performing inspections to identify defects.

A checksheet or tally sheet is a type of checklist that can be used to keep

track of data such as quality problems uncovered during inspections. This

data collected can in turn be translated into other format such as a Pareto

diagram .

3. Check sheet

Defect Frequency

Too long 8

Too narrow 4

Too wide 6

Too Short 2

Page 80: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

80/20 principle ( 80% of problems due to 20% root cause)

Help focus attention on the most critical issues

Prioritize potential ‘causes” of the problems

Arrange data from most frequent to least frequent

4. Pareto Diagram

Page 81: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

Pareto Diagram- calculation

Page 82: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

A Histogram is a variation of a bar chart in which data values are grouped together

and put into different classes. This grouping allows you see how frequently data in

each class occur in the data set. Higher bars represent more data values in a class.

Lower bars represent fewer data values in a class.

5. Histogram

Page 83: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

It is used to determine whether or not a process is stable or has predictable

performance.

Upper and lower specification limits are based on requirements of the agreement.

6. Control Chart

Inspection number

Nu

mb

er

of

Def

ects

Average

Page 84: PMP.Essentials.150121

Qu

alit

y

Rule of Seven (heuristic)- Process is out of control, if there are either at least 7

data points are in a row above or below the average, or 7 consecutive data points

with an upward or downward trend

This type of situation needs investigation and a cause should be found.

1.Plan Quality ManagementT&T3. Seven basic quality tools

6. Control Chart

Page 85: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

There are two types of control charts;

Variable Charts- which are used with continuous data , 1,2,3,4,9, etc

Attributes charts, for use of discrete data. Have only two values-Pass/fail,

present/absent Attribute data, Yes/No

6. Control Chart

Page 86: PMP.Essentials.150121

Qu

alit

y 1.Plan Quality ManagementT&T3. Seven basic quality tools

relationship between two variables

•Scatter diagrams, plot ordered pairs (X, Y) and are sometimes

called correlation charts because they seek to explain a

change in the dependent variable, Y, in relationship to a change

observed in the corresponding independent variable, X.

7. Scatter Diagram

Page 87: PMP.Essentials.150121

Qu

alit

y 2.Perform Quality Assurance-T&T

1. Affinity diagrams.

2. Process decision program charts (PDPC).

3. Interrelationship digraphs.

4. Tree diagrams. Also known as systematic diagrams

5. Prioritization matrices

6. Activity network diagrams

7. Matrix diagrams

1. Quality Management and Control Tools (7)

.1 Quality management and control tools

.2 Quality audits

.3 Process analysis.

Page 88: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

Used to consolidate a large amount of information into groupings of ideas

that have a natural 'affinity',

similar to mind-mapping techniques in that they are used to generate ideas that

can be linked to form organized patterns of thought about a problem.

Mind mapping technique used to consolidate ideas created through individual

brainstorming sessions into a single map to reflect commonality and differences

in understanding and to generate new ideas.

Flip chart may be used

Cards may be used

1.1. Affinity Diagram

Page 89: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

Used to understand a goal in relation to the steps for getting to the goal. The

PDPC is useful as a method for contingency planning because it aids teams in

anticipating intermediate steps that could derail achievement of the goal..

1.2. Process decision program charts (PDPC).

Page 90: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

An adaptation of relationship diagrams.

It provide a process for creative problem solving in moderately complex scenarios that

possess intertwined logical relationships for up to 50 relevant items.

It may be developed from data generated in other tools such as the affinity diagram, the tree

diagram, or the fishbone diagram.

a. Develop the problem statement.

. Write this statement at the top of a white board or flip chart.

b. Develop issues related to the problem.

These issues may be the result of a previous activity such as an affinity diagram

or a brainstorming session, or the team may need to develop them now.

c. Arrange the issues in a circle.

Write the issues on the white board or flip chart.

d. Identify cause-and-effect relationships.

e. Draw arrows to indicate directions of influence.

f.Tally influence arrows. For each issue, clearly record the number of arrows

going in and going out.

A B

1.3. Inter relationship diagram

C

Page 91: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

Also known as systematic diagrams and may be used to represent

decomposition hierarchies such as the WBS, RBS (risk breakdown structure),

and OBS (organizational breakdown structure). In project management, tree

diagrams are useful in visualizing the parent-to-child relationships

in any decomposition hierarchy that uses a systematic set of rules that define a

nesting relationship.

Tree diagrams can be depicted horizontally (such as a risk breakdown structure) or

vertically (such as a team hierarchy or OBS). Because tree diagrams permit the

creation of nested branches that terminate into a single decision point, they are

useful as decision trees for establishing an expected value for a limited

number of dependent relationships that have been diagramed systematically..

1.4. Tree diagrams

Page 92: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

Identify the key issues and the suitable alternatives to be prioritized as a set of

decisions for implementation. Criteria are prioritized and weighted before being

applied to all available alternatives to obtain a mathematical score that ranks the

options.

1.5. Prioritization matrices

Page 93: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

Previously known as arrow diagrams. They include both the AOA (Activity

on Arrow) and, most commonly used, AON (Activity on Node) formats of a

network diagram. Activity network diagrams are used with project

scheduling methodologies such as program evaluation and review

technique (PERT), critical path method (CPM), and precedence

diagramming method (PDM).

1.6. Activity network diagrams

Page 94: PMP.Essentials.150121

Qu

alit

y 2. Perform Quality AssuranceT&T1. Quality Management and Control Tools (7)

A quality management and control tool used to perform data analysis within the

organizational structure created in the matrix.

The matrix diagram seeks to show the strength of relationships between

factors, causes, and objectives that exist between the rows and columns that

form the matrix.

It display relationship among two different groups of ideas or tasks

a b c d e f g h

1

2

3

4

5

6

7

8

1.7. Matrix diagrams

Page 95: PMP.Essentials.150121

Qu

alit

y 1,2,3 & 6 Sigma

Accuracy of estimates

TIME MANAGEMENT 1 Sigma 68.26% 2 Sigma 95.44 % 3 Sigma 99.73 %

Page 96: PMP.Essentials.150121

Pro

ject

Hu

man

Res

ou

rce

Man

agem

ent

1.Plan HR Management Outputs 1. HR management plan

Human Resource Management Plan Roles & Responsibilities,

Project Organization Charts,

Staffing Management Plan When ? the resource will be brought into the

project

Staff acquisition.

Resource Calendars

Staff Release Plan

Recognitions and Rewards

Training Needs

Compliance

Safety

Resource Histogram

.1 Human Resource management plan

Nu

mb

er

of P

eo

ple

Technical writers

Junior Programmers

Business Analyst

Senior Programmer

Project Manager

Page 97: PMP.Essentials.150121

Pro

ject

Hu

man

Res

ou

rce

Man

agem

ent

3.Develop Project TeamT&T6.Recognition & Rewards

6. Recognition & Rewards

Theories of motivation (Summary)

Sr By Theories

1 Maslow Hierarchy of needs Physiological, Safety, Belongingness & love, Esteem, Self Actualization PSBES

2 Herzberg Hygiene Theory Hygiene and Motivators HM

3 David McClelland

Achievement Theory Achievement, Affiliation, Power AAP

4 Victor Vroom Expectancy Theory Expectation of positive thing

Praise and Carrots PC

HMV

Page 98: PMP.Essentials.150121

Pro

ject

Hu

man

Res

ou

rce

Man

agem

ent

3.Develop Project TeamT&T6.Recognition & rewards

Leadership Theories (Summary)

Sr By Theories

1 Douglas McGregor

Theory X and Theory Y X- Needs Supervision Y- Committed

2 William Ouchi Theory Z When jobs were offered for life

3 Contingency Theory Y and Hygiene

4 Tannenbaum & Schmidt Continuum

Management Theory

Level of authority vs Freedom based on maturity

5 Paul Hersey and Ken Blanchard)

Situational Leadership Theory

Depends upon situations: Directing, Coaching, Supporting, Delegating

MOTH CMS

Page 99: PMP.Essentials.150121

Pro

ject

Hu

man

Res

ou

rce

Man

agem

ent

3.Develop Project TeamT&T6.Recognition & Rewards

1. Reward Power- PM can exhibit by offering perks etc

2. Expert power – Technical Power- Has to be earned

3. Legitimate power – Formal-Position because of position

4. Referent -respect by subordinates

Personality

Affiliation

5. Punishment Power – Coercive or penalty- afraid [Last]

Power of Leaders

Halo Effect

Page 100: PMP.Essentials.150121

Control Stakeholder Engagement

Manage

stakeholder

Engagement

Issue log

Change log, Issue log

Manage Project Team

Control communications

Change log

Perform Integrated

Change Control

Page 101: PMP.Essentials.150121

Pro

ject

Hu

man

Res

ou

rce

Man

agem

ent

4.Manage Project TeamT&T3.Conflict Management

Six Conflict Resolution techniques

Problem Solving/Confronting (Best approach)

Compromise/Reconcile. Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. (Second best approach) -------------------------------------------------------------------------------------------------------------------------- Withdraw/Avoid. postponing the issue to be better prepared or to be resolved by others. -------------------------------------------------------------------------------------------------------------------------

Smooth/Accommodate. Emphasizing areas of agreement rather than areas of difference; conceding one’s position to the needs of others to maintain harmony and relationships.

Collaborate. Incorporating multiple viewpoints; requires a cooperative attitude typically leads to consensus and commitment. ----------------------------------------------------------------------------------------------------------------------

Force/Direct. Pushing one’s viewpoint at the expense of others; offering only win-lose solutions, usually enforced through a power position to resolve an emergency. (worst approach)

PC

SC

Page 102: PMP.Essentials.150121

Co

mm

un

icat

ion

s 1.Plan Communications ManagementT&T3. Communication Models

• Encode- Prepare to speak/convey the message

• Transmit Message.

• Decode- Understand the message

• Acknowledge.

• Feedback/Response.

Sender

Encode Transmit message Decode

Acknowledge

Feedback message

Encode Decode

Noise

Noise

Receiver Medium

Page 103: PMP.Essentials.150121

Co

mm

un

icat

ion

s 1.Plan Communications Management T&T3. Communication Models contd…

Non verbal- About 55 % of all communications

(based on physical mannerism – body language)

Para lingual (Vocal inflection) – 38 % Pitch and tone of voice

help to convey a message

Only 7% of message consists of the actual words that you use

Page 104: PMP.Essentials.150121

Knowledge Area Plans Additional Plan

Integration PROJECT MANAGEMENT

PLAN

Change management plan

Configuration Management

Plan

Scope Scope management plan Requirement management

plan

Scope baseline

(1. Project scope statement,

2. WBS, 3. WBS dictionary)

Time Schedule management plan Schedule baseline

Cost Cost management plan Cost baseline

Quality Quality management plan Process improvement plan

Human Resource HR management plan Staffing Management Plan

Communications Communication management

plan

Risk Risk management plan

Procurement Procurement management

plan

Stakeholder Stakeholder management plan

3.Control Communications InputProject Management Plan C

om

mu

nic

atio

ns

Page 105: PMP.Essentials.150121

3.Control Communications C

om

mu

nic

atio

ns

Project Documents (Other than Plan and baselines)

Change Log

Change Request

Project Charter

Resource Calenders

Work Performance data

Risk register

Project Statement of Work

Stakeholder register

Issue log

Project Schedule

Agreements etc.

Page 106: PMP.Essentials.150121

Ris

k 1.Plan Risk ManagementInputs

• Risk categories,

• Common definitions of concepts and terms,

• Risk statement formats,

• Standard templates,

• Roles and responsibilities,

• Authority levels for decision making, and

• Lessons learned.

5. OPA

Page 107: PMP.Essentials.150121

Ris

k 1.Plan Risk management

• Probability and Impact Matrix

A probability and impact matrix is a grid for mapping the probability

of each risk occurrence and its impact on project objectives if that risk occurs

Risk 6

Risk 9

Risk 1 Risk 4

Risk 3 Risk 7

Risk 2 Risk 5 Risk 11

Risk 8 Risk 10

Risk 12 P

rob

ab

ilit

y

High

Medium

Low

Low Medium High

Impact

Separate probability/impact matrix or chart for negative risks and positive risks

Page 108: PMP.Essentials.150121

Ris

k 3.Perform Qualitative Risk Analysis2.Probability and Impact Matrix

0.90 0.27 Risk 6

0.54 Risk 9

.81 Risk 1 Risk 4

0.60 0.18 Risk 3 Risk 7

0.36 Risk 2 Risk 5 Risk 11

0.54

0.30 0.09 (watch list)

0.18 Risk 8 Risk 10

0.27 Risk 12

0.30 0.60 0.90

Pro

bab

ilit

y

Impact

Page 109: PMP.Essentials.150121

Ris

k 3.Perform Qualitative Risk AnalysisOutputs

.1 Project documents updates

Watch list

Low priority risks

Determined to be of to low priority and low impact

Watch list

Page 110: PMP.Essentials.150121

Ris

k 2.Identify RisksT&T6.SWOT Analysis

S-Strength, W-Weakness

O-Opportunities T-Threats

S W

O T

Internal

External

Transform

Transform

Match

Page 111: PMP.Essentials.150121

Build or Upgrade

Build $ 100,000

Upgrade $ 50,000

Success (Opportunities)

Failure (Threats)

Success

(Opportunities)

Failure

(Threats)

$ 50,000

-$ 90,000

$ 60,000

- $ 50,000

65%

35%

80%

20%

Ris

k-

4.Perform Quantitative Risk AnalysisT&T 2. Quantitative risk analysis and modeling techniques

Decision Node Chance Node

Cost Revenue

EMV

=(0.65*50,000+0.35(-90000)

=32500-31500

=1000

EMV

=(0.8*60000+0.20(-50000)

=48000-10000

=38,000

Higher the value, Select

Page 112: PMP.Essentials.150121

Ris

k 5.Plan Risk ResponsesT&T

Avoid- Eliminate threat by eliminating cause

Mitigate – Reduce the probability

Transfer- Shift the impact to third party

Accept- Decides to acknowledge, but waits

1. Strategies for Negative Risk/Threats-

Exploit- To ensure it is realized, Counterpart of avoid risk

Enhance- Like mitigate, increase the probability

Share- Share with 3rd party

Accept- Same as threats

2.Strategies for Positive risks /Opportunities-

3. Contingent response strategies

Contingency plans or Fallback plans

Events that trigger the contingency response, such as missing intermediate

milestones

.1 Strategies for negative risks or threats

.2 Strategies for positive risks or opportunities

.3 Contingent response strategies

.4 Expert Judgment

ATM Avoid

Transfer

Mitigate

SEE

• Share

• Enhance

• Exploit

Avoid

Mitigate

Transfer

Accept

Exploit Enhance

Share

Accept

Page 113: PMP.Essentials.150121

Ris

k 5.Plan Risk ResponsesT&T

3. Contingent response strategies

Contingency plans or Fallback plans

.Events that trigger the contingency response, such as missing intermediate

milestones

Secondary Risk: A risk that arise as a direct result of implementing a risk

response. This is a new risk

Residual risk: A risk that remains after risk response have been

implemented

.1 Strategies for negative risks or threats

.2 Strategies for positive risks or opportunities

.3 Contingent response strategies

.4 Expert Judgment

Secondary Risk

Residual Risk

Page 114: PMP.Essentials.150121

Determine Budget

Estimate costs

Estimate activity

durations

Control Cost

Control Risks

Reserve Analysis

Page 115: PMP.Essentials.150121

Stak

eho

lde

r 1.Identify Stakeholders-T&T

1. Stakeholder Analysis –

(Power/Interest grid)

A to D are placement of Stakeholders

.1 Stakeholder analysis

.2 Expert judgment

.3 Meetings

Monitor

Page 116: PMP.Essentials.150121

Control Stakeholder Engagement

Manage

stakeholder

Engagement

Issue log

Change log, Issue log

Manage Project Team

Control communications

Change log

Perform Integrated

Change Control

Page 117: PMP.Essentials.150121

Code of ethics and professional conduct

Code of ethics and professional conduct http://www.pmi.org/en/About-Us/Ethics/~/media/PDF/Ethics/ap_pmicodeofethics.ashx

2. Respect

3. Fairness

4. Honesty

1. Responsibility

58-71

Page 118: PMP.Essentials.150121

- If you like this slide, please send your feedback, suggestions to

[email protected]

Rakesh P

PMP, MBA 25 years in IT

Poses Project Management experience in India, USA and Middle East

PMP and Agile Coach

PMP Trainer since 2006 and Agile Coach since 2010.

Trained candidates from TCS, Infosys, Wipro, HCL, Dell, GE, IBM, Oracle, PWC, mPhasis, ITC Infotech, HP, SAP, Atos, Accenture, Phillips, CG-coreEL, Manipal Hospitals, Caterpillar, United Nations, Healthedge Inc -USA, Convet Health-USA, California Water Department , Saudi Railways- Telecom, CTS, Synergy, Novo, Cowen, BAeHAL, Rambus, Bosch, ANZ, State Street, Cap Gemini, Temenos, Quintiles etc