    PLM220Project Management - Logistics

    Date

    Training Center

    Instructors

    Education Website

    Participant HandbookCourse Version: 2005 Q2

    Course Duration: 5 Day(s)

    Material Number: 50074218

    An SAP course - use it to learn, reference it for work

  • 7/22/2019 PLM220 - Project Management..Logistics

    2/334

    Copyright

    Copyright 2005 SAP AG. All rights reserved.

    No part of th is publication may be reproduced or transmitted in any form or for any purpose without the

    express permission of SAP AG. The information contained herein may be changed without prior notice.

    Some software products marketed by SAP AG and its distributors contain proprietary software

    components of other software vendors.

    Trademarks

    Microsoft, WINDOWS, NT, EXCEL, Word, PowerPoint and SQL Server are

    registered trademarks of Microsoft Corporation.

    IBM, DB2, OS/2, DB2/6000, Parallel Sysplex, MVS/ESA, RS/6000, AIX, S/390,

    AS/400, OS/390, and OS/400 are registered trademarks of IBM Corporation.

    ORACLE is a registered trademark of ORACLE Corporation.

    INFORMIX-OnLine for SAP and INFORMIX Dynamic ServerTM are registered trademarks

    of Informix Software Incorporated.

    UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.

    Citrix, the Citrix logo, ICA, Program Neighborhood, MetaFrame, WinFrame,

    VideoFrame, MultiWin and other Citrix product names referenced herein are trademarks of

    Citrix Systems, Inc.

    HTML, DHTML, XML, XHTML are trademarks or registered trademarks of W3C, World Wide

    Web Consortium, Massachusetts Institute of Technology.

    JAVA is a registered trademark of Sun Microsystems, Inc.

    JAVASCRIPT is a registered trademark of Sun Microsystems, Inc., used under license for

    technology invented and implemented by Netscape.

    SAP, SAP Logo, R/2, RIVA, R/3, SAP ArchiveLink, SAP Business Workflow, WebFlow, SAP

    EarlyWatch, BAPI, SAPPHIRE, Management Cockpit, mySAP.com Logo and mySAP.com are

    trademarks or registered trademarks of SAP AG in Germany and in several other countries all

    over the world. All other products mentioned are trademarks or registered trademarks of theirrespective companies.

    Disclaimer

    THESE MATERIALS ARE PROVIDED BY SAP ON AN "AS IS" BASIS, AND SAP EXPRESSLY

    DISCLAIMS ANY AND ALL WARRANTIES, EXPRESS OR APPLIED, INCLUDING WITHOUT

    LIMITATION WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR

    PURPOSE, WITH RESPECT TO THESE MATERIALS AND THE SERVICE, INFORMATION, TEXT,

    GRAPHICS, LINKS, OR ANY OTHER MATERIALS AND PRODUCTS CONTAINED HEREIN. IN

    NO EVENT SHALL SAP BE LIABLE FOR ANY DIRECT, INDIRECT, SPECIAL, INCIDENTAL,

    CONSEQUENTIAL, OR PUNITIVE DAMAGES OF ANY KIND WHATSOEVER, INCLUDING

    WITHOUT LIMITATION LOST REVENUES OR LOST PROFITS, WHICH MAY RESULT FROM

    THE USE OF THESE MATERIALS OR INCLUDED SOFTWARE COMPONENTS.

  • 7/22/2019 PLM220 - Project Management..Logistics

    3/334

    About This Handbook

    This handbook is intended to complement the instructor-led presentation of this

    course, and serve as a source of reference. It is not suitable for self-study.

    Typographic Conventions

    American English is the standard used in this handbook. The following typographic

    conventions are also used.

    Type Style Description

    Example text Words or characters that appear on the screen. Theseinclude field names, screen titles, pushbuttons as well as

    menu names, paths, and options.

    Also used for cross-references to other documentation

    both internal (in this documentation) and external (in

    other locations, such as SAPNet).

    Example text Emphasized words or phrases in body text, titles of

    graphics, and tables

    EXAMPLE TEXT Names of elements in the system. These include report

    names, program names, transaction codes, table names,

    and individual key words of a programming language,when surrounded by body text, for example SELECT

    and INCLUDE.

    Example text Screen output. This includes file and directory names

    and their paths, messages, names of variables and

    parameters, and passages of the source text of a program.

    Example text Exact user entry. These are words and characters that

    you enter in the system exactly as they appear in the

    documentation.

    Variable user entry. Pointed brackets indicate that youreplace these words and characters with appropriate

    entries.

    2005 / Q2 2005 SAP AG. All rights reserved. iii

  • 7/22/2019 PLM220 - Project Management..Logistics

    4/334

    About This Handbook PLM220

    Icons in Body Text

    The following icons are used in this handbook.

    Icon Meaning

    For more information, tips, or background

    Note or further explanation of previous point

    Exception or caution

    Procedures

    Indicatesthat the item is displayed in the instructors

    presentation.

    iv 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    5/334

    Contents

    Course Overview .... ...... ...... ...... ....... ...... ...... ...... ....... ...... ...... ....... .... vii

    Course Goals................................................................................. vii

    Course Objectives ....... ....... ....... ....... ...... ....... ...... ....... ....... ...... ....... . vii

    Unit 1: Introduction .. ...... ...... ...... ....... ...... ...... ....... ...... ...... ...... ....... ..... 1

    Project Structures.......... ...... ....... ...... ....... ....... ...... ....... ....... ....... ....... 2

    Unit 2: Dates...................................................................................27

    Time Scheduling with WBS Elements.................................................... 28Scheduling of Activities and Networks................................................... 32

    Actual Dates .. . .. . . . . . . .. . .. . . . . . . .. . .. . . . . . . .. . .. . . . . . . .. . .. . . . . . . .. . .. . . . . . . .. . .. . . . . . . .. . .66

    Unit 3: Capacities....... ...... ...... ....... ...... ...... ...... ....... ...... ...... ....... ...... .81

    Capacities - Overview......................................................................83

    Available Capacity and Capacity Requirements . . .. . . . . . . . . . . . . .. . . . . . . . . . . . .. . .. . . . . .93

    Capacity Analysis..... ....... ....... ...... ....... ...... ....... ....... ....... ....... ....... . 107

    Capacity Leveling..... ....... ....... ...... ....... ...... ....... ....... ....... ....... ....... . 117

    Confirmations ...... ...... ....... ....... ....... ...... ....... ...... ....... ....... ...... ...... 135

    Unit 4: External Activities .................................................................161

    External Processing ....... ...... ....... ....... ...... ....... ...... ....... ....... ....... .... 162

    Workflows in the Project System ... ... .... ... ... .... ... ... .... ... ... ... .... ... ... .... ... 177

    Service ...................................................................................... 181

    Unit 5: Materials .............................................................................197

    Assigning Material Components to Activities . . . . . . .. . .. . .. . . . . . . . . .. . .. . . . . . . . . . .. . .. . 198

    Processes of Material Procurement..................................................... 226

    Requirements Grouping .................................................................. 253

    Assemblies, Availability Check and Delivery from Projects . . . . .. . . . . . . . . . .. . . . . . . . . . 258

    Unit 6: Progress Tracking .................................................................281

    Progress Tracking for Material Components .. ... .. .. .. .. .. .. ... .. .. .. .. .. .. .. ... ... .. . 282

    Unit 7: ProMan ...............................................................................305

    ProMan...................................................................................... 306

    2005 / Q2 2005 SAP AG. All rights reserved. v

  • 7/22/2019 PLM220 - Project Management..Logistics

    6/334

    Contents PLM220

    vi 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    7/334

    Course Overview

    Course PLM220, Project Management - Logistics, includes logistics planning

    and control of projects. The course includes scheduling of projects; planning and

    realization of internal and external services; control and monitoring of processes for

    procurement, and supply of materials. In this course, you will also become familiar

    with the Customizing settings required in the SAP Project System for aspects of

    logistics.

    Target Audience

    This course is intended for the following audiences:

    Project managers and engineers Project teams

    Consultants

    Course Prerequisites

    Required Knowledge

    Basic knowledge of project management from a logistics perspective

    PLM210 or PLM200

    Course Goals

    This course will prepare you to:

    Plan and control projects from a logistics perspective

    Make the necessary settings in Customizing

    Course Objectives

    After completing this course, you will be able to:

    Schedule projects

    Plan and execute internal services

    Trigger and edit procurement processes

    Procure and deliver materials for the project

    2005 / Q2 2005 SAP AG. All rights reserved. vii

  • 7/22/2019 PLM220 - Project Management..Logistics

    8/334

    Course Overview PLM220

    SAP Software Component Information

    The information in this course pertains to the following SAP Software Components

    and releases:

    viii 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    9/334

    Unit 1IntroductionUnit Overview

    This chapter provides an overview of the business scenario used as an example to

    discuss the logistical aspects of project management in this course. You create a

    suitable project structure for this scenario and also clarify the various functions and

    processing options for work breakdown structures and networks.

    Unit Objectives

    After completing this unit, you will be able to:

    Create project structures consisting of WBS elements and activities in the Project

    Builder

    Unit Contents

    Lesson: Project Structures ... ... .... ... .... ... ... .... ... ... ... .... ... ... .... ... ... ... 2

    Exercise 1: Structures ..........................................................13

    2005 / Q2 2005 SAP AG. All rights reserved. 1

  • 7/22/2019 PLM220 - Project Management..Logistics

    10/334

    Unit 1: Introduction PLM220

    Lesson: Project Structures

    Lesson OverviewIn this lesson, you will learn about the various options for editing project structures

    You will create a project for producing a turbine using the Project Builder. You will

    also be introduced to Claim Management.

    Lesson Objectives

    After completing this lesson, you will be able to:

    Create project structures consisting of WBS elements and activities in the Project

    Builder

    Business Example

    Your company produces turbines. It has become evident that these turbines are

    too complex to produce using production orders. As an alternative, you use WBS

    elements and activities in the Project System.

    Work Breakdown Structures and Networks

    Figure 1: Sample Turbine Project

    2 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    11/334

    PLM220 Lesson: Project Structures

    The slide shows the project that is used as an example in the course. No logistics

    aspects other than dates are treated at WBS element level. The logistics aspects of the

    project - internal and external services and material requirements for example - are

    planned and executed using activities.

    The icons in the slides correspond to those used in the SAP system for project

    definition, WBS elements, network headers, activities and relationships. You will find

    them in all transactions in the project system.

    Figure2: Work Breakdown Structure: Functions

    The work breakdown structure (WBS) forms the basis for all other planning steps in

    the project. The emphasis is on planning, analysis, description, control and monitoring

    of costs, basic dates and budget.

    Costs, dates and payments are frequently planned using activities that are assigned

    to WBS elements.

    2005 / Q2 2005 SAP AG. All rights reserved. 3

  • 7/22/2019 PLM220 - Project Management..Logistics

    12/334

    Unit 1: Introduction PLM220

    Figure 3: Work Breakdown Structure: Maintenance Options

    You can use the Project Builder to create and change WBS elements.

    You can use the detail screens or the WBS element overview list for this purpose.

    You can use the hierarchy graphic to change WBS elements (by double-clicking on

    a WBS element in the graphic). You can also create new WBS elements and insert

    these into the hierarchy (connect mode).

    In addition to manual maintenance or maintenance via the hierarchy graphic (1, 2), youcan also use existing project structures or standard projects as templates to copy from.

    When you create a new WBS, you can use an existing WBS, a section of the project

    hierarchy or a standard WBS as a template to copy from. You can also incorporate

    WBS elements from other projects or from a standard WBS in an existing work

    breakdown structure (3, 4).

    4 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    13/334

    PLM220 Lesson: Project Structures

    Figure 4: Project Builder

    The Project Builder is a feature in the Project System that is particularly intuitive

    and easy to use.

    In the Project Builder, you can create or edit WBS structures or networks individually

    or in an integrated manner. To maintain WBS structures and networks, you can

    navigate quickly and efficiently in the Project Builder, between the various views

    (detail and overviews), graphics, and the project planning board. This unit and the

    subsequent units of the course will familiarize you with the functionality of the Project

    Builder.

    The Project Builder consists of a processing screen divided into three parts

    - the structure overview at the top left, the work list at the bottom left and a

    display/processing area to the right.

    2005 / Q2 2005 SAP AG. All rights reserved. 5

  • 7/22/2019 PLM220 - Project Management..Logistics

    14/334

    Unit 1: Introduction PLM220

    Figure 5: Activities and Networks: Functions

    You use the activities in the network to plan the labor, capacities, materials, and

    services that you require to carry out the various tasks in your project.

    The unit on capacities discusses internally-processed activities in detail.

    The unit on external activities deals with externally-processed activities and service

    activities.

    The unit on materials explains how material components are assigned, procured and

    consumed in the network.

    6 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    15/334

    PLM220 Lesson: Project Structures

    Figure 6: Activities: Maintenance Options

    In addition to maintaining data manually or via the network graphic (1, 2), you can

    use existing operative structures or standard structures as templates.

    When you create activities, you can use a standard network or an existing network as a

    template (3). You can also incorporate standard networks into an existing network (4).

    You can use the Project Builder or the project planning board to copy a standard

    project or operative project (including all activities) to a new project structure (5).

    2005 / Q2 2005 SAP AG. All rights reserved. 7

  • 7/22/2019 PLM220 - Project Management..Logistics

    16/334

    Unit 1: Introduction PLM220

    Figure 7: Network Graphic

    The network graphic provides all of the functions needed to process a network (the

    functions for inserting activities or relationships, for example).

    You can call up the network graphic from various transactions in the Project

    System, for example in network maintenance, scheduling and in the Structure/Dates

    Information System.

    The cycle analysis is a function that you can only perform in the network graphic. A

    cycle is a closed sequence of relationships and activities ("closed" means that when

    you start out from one activity, you end up back at the same activity by means ofrelationships). If the activity-relationship-activity path is cyclical, you will not be able

    to schedule the network. Cycle analysis is a tool that enables you to detect cyclical

    relationships and correct them.

    8 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    17/334

    PLM220 Lesson: Project Structures

    Figure 8: Project Planning Board

    The project planning board is particularly suitable for planning a project. It provides

    you with an instant overview of your project deadlines, enabling you to check your

    project for capacity bottlenecks. Additional options are also available for enhancing

    your project structure. In the following units, you will use both the Project Builder

    and the project planning board to edit your project.

    2005 / Q2 2005 SAP AG. All rights reserved. 9

  • 7/22/2019 PLM220 - Project Management..Logistics

    18/334

    Unit 1: Introduction PLM220

    Claim Management

    Figure 9: Claim

    Deviations from the project plan often occur as a result of delivery problems, price

    fluctuations, unforeseeable capacity bottlenecks and so on. In this case, clarifying

    responsibilities is extremely important for the contractual partners involved. Claim

    Management ensures that claims resulting from deviations are prepared vis--visthe contractual partner and submitted at a suitable point in time. Conversely, it also

    provides defence against claims from the contractual partner. The Project System

    supports claim management with the "Claim" message type, which can be used to

    document deviations from your project plan, appoint persons responsible for the

    deviation and initiate follow-up activities.

    You can enter claims directly in the SAP system or create and display them from the

    Internet (for example: a customer creates a claim over the Internet).

    10 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    19/334

    PLM220 Lesson: Project Structures

    You can include the following data in a claim:

    Descriptions - the cause of the deviation for example

    Actions and tasks to be initiated because of the deviation Persons responsible and partners by means of a link to the Partner Management

    function

    Costs incurred as a result of the deviation (cost planning using unit costing)

    Assigned WBS elements, SD and MM document items

    Assigned document info records (links to the Document Management System)

    2005 / Q2 2005 SAP AG. All rights reserved. 11

  • 7/22/2019 PLM220 - Project Management..Logistics

    20/334

    Unit 1: Introduction PLM220

    12 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    21/334

    PLM220 Lesson: Project Structures

    Exercise 1: Structures

    Exercise ObjectivesAfter completing this exercise, you will be able to:

    Create a work breakdown structure with assigned operations

    Use the project builder and the project planning board

    Business Example

    You create a separate project for project manufacturing of a turbine system. In doing

    so, you make use of standard structures as copy templates and various functions for

    further processing.

    Task:

    1. You will use the standard structure as a template to create the project. Call

    up the Project Builder.

    2. Create project T-100## using the standard project T-20001 as a template. ##

    is a placeholder for your group number (if you are in group 3, then replace

    ## with 03).

    Enter the following data in the dialog box that appears:

    Field Name ValueProject def. T-100##

    Start Today

    Finish Two years from today

    Project profile 2001 Turbine model group

    1

    Template Std proj. def. T-20001

    3. Enter a name for your project, and the person responsible. Maintain the data at

    project definition level.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 13

  • 7/22/2019 PLM220 - Project Management..Logistics

    22/334

    Unit 1: Introduction PLM220

    Field Name Value

    Text Group ##, turbine A

    Responsible person ##

    4. Create two further WBS elements to record the details of thePlanning of systems

    and instrumentation WBS element.

    Assign the new WBS element the description Planning of systems.

    Use the same procedure to create the second WBS element. Call itPlanning of

    instrumentation.

    5. Display your expanded structure in the hierarchy graphic.

    Expand the display to show the entire project.

    Set thePlanning elementindicator for the new WBS elements.

    6. As a result of detailing the project structure, activity 2000Planning of systems

    and instrumentationis now assigned incorrectly.

    Rename it asPlanning of Systemsand assign it to the appropriate WBS element.

    7. To plan your turbine instrumentation, create an activity for thePlanning of

    instrumentationWBS element.

    The detail screen of the new activity is displayed. Enter the following data in

    the detail screen:

    Field Name ValuesText Planning of instrumenta-

    tion

    Work center 2000

    Work 35 hours

    Normal duration 5 days

    8. Take a look at your extended network in the network graphic.

    Save the project. The temporary network number is then replaced.

    9. Now call up the project planning board for an integrated view of your projectdeadlines. Use the1001 Elevators/Turbinesproject planning board and carry

    out time scheduling.

    Continued on next page

    14 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    23/334

    PLM220 Lesson: Project Structures

    10. Plan the material costs for your turbine. You are still unsure as to which

    components you will procure in the future but you can already plan material

    costs for the activities. Plan thePreliminary ordersactivities andMaterial

    procurement plant components.

    Enter the following data:

    Activity Material Planning

    3000 Preliminary orders EUR 100000

    3100 Material procurement System parts EUR 65,000

    Save your data.

    2005 / Q2 2005 SAP AG. All rights reserved. 15

  • 7/22/2019 PLM220 - Project Management..Logistics

    24/334

    Unit 1: Introduction PLM220

    Solution 1: Structures

    Task:

    1. You will use the standard structure as a template to create the project. Call

    up the Project Builder.

    a) SAP Menu! Logistics!Project System!Project! Project Builder

    (Double-click to select Project Builder)

    2. Create project T-100## using the standard project T-20001 as a template. ##

    is a placeholder for your group number (if you are in group 3, then replace

    ## with 03).

    Enter the following data in the dialog box that appears:

    Field Name Value

    Project def. T-100##

    Start Today

    Continued on next page

    16 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    25/334

    PLM220 Lesson: Project Structures

    Field Name Value

    Finish Two years from today

    Project profile 2001 Turbine model group1

    Template Std proj. def. T-20001

    a) Create project T-100## using the standard project T-20001 as a template.

    ## is a placeholder for your group number (if you are in group 3, then

    replace ## with 03).

    Click the iconCreate! Copy project.

    Enter the data indicated in the dialog box that appears.

    Confirm your entries by clicking the "Create project"pushbutton.

    Hint: The tree structure at the left of the screen now displays

    various objects that have been copied from the standard project:

    Project definition (first line)

    WBS elements

    Activities

    Network header

    Milestone (last line)

    The activities are grouped together in a network with a provisionalnumber (%00000000001). This number will be replaced when

    you save the activities.

    3. Enter a name for your project, and the person responsible. Maintain the data at

    project definition level.

    Field Name Value

    Text Group ##, turbine A

    Responsible person ##

    a) Select the project definition in the structure tree.

    Enter the data indicated in the detail screen that appears.

    Confirm your entries by clicking the Enterpushbutton.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 17

  • 7/22/2019 PLM220 - Project Management..Logistics

    26/334

    Unit 1: Introduction PLM220

    4. Create two further WBS elements to record the details of thePlanning of systems

    and instrumentation WBS element.

    Assign the new WBS element the description Planning of systems.Use the same procedure to create the second WBS element. Call itPlanning of

    instrumentation.

    a) Position the cursor in the templates area (bottom left) and expand

    Individual objects if necessary.

    Drag and drop a WBS element from the templates area to the Planning of

    systems and instrumentationWBS element in the tree structure.

    Assign the new WBS element the descriptionPlanning of systems.

    Enter the appropriate description in the "Text"field.

    Confirm your entries by clicking the Enterpushbutton.

    The new WBS element is now displayed in the tree structure.

    Use the same procedure to create the second WBS element. Call it

    Planning of instrumentation.

    Confirm your entries by clicking the Enterpushbutton.

    5. Display your expanded structure in the hierarchy graphic.

    Expand the display to show the entire project.

    Set thePlanning elementindicator for the new WBS elements.

    a) Click theHierarchy graphicspushbutton in the Project Builder.ChooseView! Completed view.

    Set thePlanning elementindicator for the new WBS elements.

    Double-click the appropriate indicator.

    Exit the hierarchy graphic using the Backpushbutton.

    6. As a result of detailing the project structure, activity 2000Planning of systems

    and instrumentationis now assigned incorrectly.

    Continued on next page

    18 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    27/334

    PLM220 Lesson: Project Structures

    Rename it asPlanning of Systemsand assign it to the appropriate WBS element.

    a) Position the cursor on the activity in the tree structure. Drag and drop the

    activity to thePlanning of SystemsWBS element.Change the description of the activity.

    Enter the new description Planning of systemsin the Textfield.

    Confirm your entries by clicking the Enterpushbutton.

    7. To plan your turbine instrumentation, create an activity for thePlanning of

    instrumentationWBS element.

    The detail screen of the new activity is displayed. Enter the following data in

    the detail screen:

    Field Name Values

    Text Planning of instrumenta-

    tion

    Work center 2000

    Work 35 hours

    Normal duration 5 days

    a) Expand the "Activity" icon in thetemplatesarea.

    Drag and drop the Activity (internal)entry from the templates area to the

    Planning of instrumentationWBS element in the tree structure.

    Enter the following data in the detail screen.

    Confirm your entries by clicking the Enterpushbutton.

    8. Take a look at your extended network in the network graphic.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 19

  • 7/22/2019 PLM220 - Project Management..Logistics

    28/334

    Unit 1: Introduction PLM220

    Save the project. The temporary network number is then replaced.

    a) Position your cursor on the network headerTurbinein the tree structure.

    ChooseNetwork Graphic.

    To call up an overview of the entire network, click the Complete view

    pushbutton.

    If you can no longer identify details in the activity display, change it using

    theActivitiesicon and choose thesmalldisplay format.

    Exit the network graphic using the Backpushbutton.

    Save the project. The temporary network number is then replaced.

    ChooseSave.

    9. Now call up the project planning board for an integrated view of your project

    deadlines. Use the1001 Elevators/Turbinesproject planning board and carry

    out time scheduling.

    a) SAP Menu!Logistics!Project System!Project!Project Planning

    Board! Change Project(Double-click to select transaction)

    Enter the project and project planning board and click theEntericon.

    Adapt the dates view of the planning board.

    ChooseAdapt graphic area.

    Carry out time scheduling for your project.

    Choose theSelect allicon and then clickSchedule.

    10. Plan the material costs for your turbine. You are still unsure as to which

    components you will procure in the future but you can already plan material

    costs for the activities. Plan the Preliminary ordersactivities and Material

    procurement plant components.

    Enter the following data:

    Activity Material Planning

    3000 Preliminary orders EUR 100000

    3100 Material procurement System parts EUR 65,000

    Continued on next page

    20 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    29/334

    PLM220 Lesson: Project Structures

    Save your data.

    a) Double-click the relevant activities in the table area of the planning board.

    Choose theAssignmentstab in the detail screen of the activity.

    Enter data as required.

    Confirm your entries by clicking theBackicon.

    ChooseSave.

    2005 / Q2 2005 SAP AG. All rights reserved. 21

  • 7/22/2019 PLM220 - Project Management..Logistics

    30/334

    Unit 1: Introduction PLM220

    Lesson Summary

    You should now be able to:

    Create project structures consisting of WBS elements and activities in the Project

    Builder

    22 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    31/334

    PLM220 Unit Summary

    Unit Summary

    You should now be able to:

    Create project structures consisting of WBS elements and activities in theProject Builder

    2005 / Q2 2005 SAP AG. All rights reserved. 23

  • 7/22/2019 PLM220 - Project Management..Logistics

    32/334

    Unit Summary PLM220

    24 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    33/334

    PLM220 Test Your Knowledge

    Test Your Knowledge

    1. You can maintain the following objects in the Project Builder:Choose the correct answer(s).

    ! A Work Breakdown Structure

    ! B Internal Order

    ! C Maintenance Order

    ! D Network

    ! E Milestone

    ! F Project definition

    2005 / Q2 2005 SAP AG. All rights reserved. 25

  • 7/22/2019 PLM220 - Project Management..Logistics

    34/334

    Test Your Knowledge PLM220

    Answers

    1. You can maintain the following objects in the Project Builder:

    Answer: A, D, E, F

    The Project Builder is used for maintenance of structures in the project system.

    Order categories other than networks cannot be edited in the Project Builder.

    26 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    35/334

    Unit 2DatesUnit Overview

    In this unit you learn about functions for manual and automatic planning of dates

    in work breakdown structures and networks. In doing so, the various Customizing

    settings and influential factors for scheduling are also dealt with in detail. At the

    end of this unit, creation of actual dates, the necessary prerequisites for this and theinfluence on scheduling of actual dates are discussed.

    Unit Objectives

    After completing this unit, you will be able to:

    Schedule dates for WBS elements using the project planning board

    Perform scheduling with the aid of the project planning board

    Set the relevant tables in Customizing

    Enter actual dates for WBS elements and activities

    Unit Contents

    Lesson: Time Scheduling with WBS Elements .................................. 28

    Lesson: Scheduling of Activities and Networks.................................. 32

    Exercise 2: Scheduling ...... .... ... ... ... .... ... .... ... ... .... ... ... ... .... ... .53

    Lesson: Actual Dates................................................................66

    Exercise 3: Actual Dates from Confirmations................................ 71

    2005 / Q2 2005 SAP AG. All rights reserved. 27

  • 7/22/2019 PLM220 - Project Management..Logistics

    36/334

    Unit 2: Dates PLM220

    Lesson: Time Scheduling with WBS Elements

    Lesson OverviewThis lesson focuses on time scheduling with WBS elements You will learn about

    various functions that support you in time scheduling for work breakdown plans.

    Lesson Objectives

    After completing this lesson, you will be able to:

    Schedule dates for WBS elements using the project planning board

    Business Example

    Start by familiarizing yourself with the options for planning dates only for WBSelements. Take a look at how to use planning methods to simplify time scheduling.

    Functions of Time Scheduling with WBS Elements

    Figure 10: Time Scheduling Functions

    28 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    37/334

    PLM220 Lesson: Time Scheduling with WBS Elements

    The following functions are available to you:

    Sets of dates: Basic and forecast dates can be used as planned dates. Actual dates

    are also shown here. Check dates: You can check consistency of the dates within the project structure

    with or without taking activities into account.

    Inherit: Dates within the WBS can be inherited.

    Extrapolate: You can use the extrapolate function to calculate the dates for

    higher-level WBS elements.

    Shift: You can shift all of the planned dates for the WBS elements or just the

    dates in subhierarchies.

    Planning different calendars: You can use a different factory calendar for each

    activity or WBS element.

    Scheduling: The scheduling function calculates the dates for activities and

    networks.

    Planning form: You can use the planning form to extrapolate dates automatically

    - for example, when you save your data.

    Figure 11: Project Dates

    2005 / Q2 2005 SAP AG. All rights reserved. 29

  • 7/22/2019 PLM220 - Project Management..Logistics

    38/334

    Unit 2: Dates PLM220

    Basic Date Planning with WBS Elements

    Figure 12: Basic Dates WBS

    In projects without networks, dates can be planned manually for the WBS elements

    (basic dates).

    You can use the project planning board to plan basic dates for the WBS elements

    simply by dragging your mouse. You can plan these dates in the form of a table in

    Structure Planning.

    Basic dates can be extrapolated from lower to higher-level WBS elements or,conversely, inherited from higher to lower-level WBS elements. You can check the

    consistency of your scheduling data within the WBS structure.

    In the execution phase, you can enter actual dates by dragging your mouse. In the

    project planning board or the information system, you can compare the actual dates

    with the planned basic dates.

    30 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    39/334

    PLM220 Lesson: Time Scheduling with WBS Elements

    Lesson Summary

    You should now be able to:

    Schedule dates for WBS elements using the project planning board

    2005 / Q2 2005 SAP AG. All rights reserved. 31

  • 7/22/2019 PLM220 - Project Management..Logistics

    40/334

    Unit 2: Dates PLM220

    Lesson: Scheduling of Activities and Networks

    Lesson OverviewIn this lesson you will become familiar with various aspects of network scheduling.

    The lesson also deals with dates for objects assigned to network activities such as

    milestones and material components as well as date exchange with WBS elements.

    Lesson Objectives

    After completing this lesson, you will be able to:

    Perform scheduling with the aid of the project planning board

    Set the relevant tables in Customizing

    Business Example

    You have already created a project structure to produce a turbine. The project manager

    now wants to know whether the project can be completed on time. Schedule your

    project to find out the answer.

    Introduction

    Figure 13: Dates In Network Plan

    32 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    41/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 14: Scheduling

    Each time a network is scheduled, the system carries out forward and backward

    scheduling; determines floats and capacity requirements (if activated).

    Forward scheduling determines the earliest dates.

    Backward scheduling determines the latest dates.

    Floats occur if the earliest dates are different from the latest dates.

    The scheduling results:

    Scheduled start and finish for the network header

    Earliest start and finish dates (earliest dates) and latest start and finish dates

    (latest dates) for the activities

    Earliestand latest dates for the relationships

    Reduction levels used to schedule the network

    Float times (total and free float) for the activities

    Capacityrequirements for activities

    2005 / Q2 2005 SAP AG. All rights reserved. 33

  • 7/22/2019 PLM220 - Project Management..Logistics

    42/334

    Unit 2: Dates PLM220

    Figure 15: WBS / Overall Network Scheduling

    You can schedule networks individually (network scheduling). You can schedule all

    networks linked by relationships together (scheduling of overall network). You can

    also trigger network scheduling from WBS elements (WBS scheduling).

    The activity data, relationships between the activities and date restrictions form the

    basis for determining dates automatically (scheduling).

    As of Release 4.6A you can schedule maintenance orders from the Project System.

    In theProject Schedulingand Overall Network Schedulingtransactions, you can

    specify whether networks are scheduled together with maintenance orders that have

    been assigned as subnetworks.

    You can display an overview of the maintenance orders assigned to a project in the

    project planning board.

    34 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    43/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Scheduling Scenarios

    Figure 16: Bottom-Up Scenario

    In projects with assigned networks, you can use scheduling to derive the dates of the

    activities and WBS elements automatically.

    Using the project planning board, you can select WBS elements and schedule the

    activities assigned to them. The scheduling parameters determine how the activities

    are scheduled.

    Networks are always scheduled forwards and backwards. The scheduling type

    determines the original direction in which scheduling is carried out. The system

    determines the earliest dates of the activities by means of forward scheduling and

    the latest dates by backward scheduling.

    The differences between the earliest and latest dates of an activity are referred to as

    floats. If these are less than or equal to zero, the activity is termed critical.

    The dates of the assigned activities are summarized to give the scheduled dates of the

    WBS elements (thin time bars in the project planning board).

    The dates scheduled in the WBS structure can be copied to the basic dates of the WBS

    elements for the purpose of extrapolating them up the project hierarchy.

    2005 / Q2 2005 SAP AG. All rights reserved. 35

  • 7/22/2019 PLM220 - Project Management..Logistics

    44/334

    Unit 2: Dates PLM220

    Figure 17: Top-Down Scenario

    In work breakdown structures with assigned networks, you can plan basic dates for

    the WBS elements in order to specify that a certain part of the project has to be

    completed within a fixed time period.

    You can use the Top-Down scheduling scenario or suitable scheduling parameters

    to stipulate that activities be scheduled within these time constraints: deselect the

    Network determines schedulingand Adjust basic datesindicators.

    36 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    45/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 18: Scheduling Scenarios

    As of Release 4.6, you have the option of using predefined scheduling scenarios. The

    standard scheduling options are of course still available. Depending on the transaction

    from which you trigger the scheduling, you use either the Parameters for WBS

    scheduling table or Scheduling parameters for the network type.

    Caution: The scheduling result depends on the transaction from which you

    start the scheduling.

    2005 / Q2 2005 SAP AG. All rights reserved. 37

  • 7/22/2019 PLM220 - Project Management..Logistics

    46/334

    Unit 2: Dates PLM220

    Customizing in Time Scheduling

    Figure 19: Customizing for Scheduling 1

    Scheduling types are used both for network scheduling and for WBS scheduling. The

    indicators have the following meanings: Forward: Forward scheduling is carried out

    first, followed by backward scheduling. Backward: Backward scheduling is carried

    out first, followed by forward scheduling. Cap.requirements only: No scheduling is

    carried out at all. Instead, the start and finish dates of the network header are copiedto each activity. Todays date: Backward scheduling is carried out first, followed by

    forward scheduling starting from todays date. Basic dates with times: This indicator

    is notrelevant for networks.

    Scheduling parameters are created for specific plants and network types. The

    scheduling parameters determine scheduling, for example, in the transactions network

    maintenance (CN22) and scheduling of the overall network (CN24). The indicators

    have the following meanings: Adjust basic dates: Determines that the scheduled dates

    are copied to the basic dates of the network header after a scheduling run. The settings

    for secondary requirements do not have any impact in the network. Scheduling type:

    Determines the type of scheduling - for example, forward first, then backward. Start

    in the past: Determines how long ago (in days) the start date can be. If it is more than

    the specified number of days, scheduling is carried out for todays date. Automatic

    scheduling: Scheduling is carried out on saving. Log automatic: If a log is generated,

    it is displayed automatically. Break spec. scheduling: The exact time at which a break

    is scheduled (in the work center) is taken into account. Shift order: Determines how

    38 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    47/334

    PLM220 Lesson: Scheduling of Activities and Networks

    the system deals with partially-confirmed activities during scheduling (see below).

    Latest material dates: The requirements dates for a material are determined based on

    the earliest or latest date. Reduction type: Either all activities or only those along

    the critical path are reduced. Maximum reduction level: A reduction strategy canhave up to six levels. The highest level of reduction is specified here. Rescheduling:

    Determines how the system deals with work allocated in workforce planning after

    another scheduling run has been carried out.

    Figure 20: Customizing for Scheduling 2

    The profile for WBS scheduling is used for scheduling in the project planning board

    transaction CJ2B or in the project scheduling transaction (CJ29).

    The indicators have the following meanings: Scheduling type: Determines the type of

    scheduling, for example, forward first, then backward. Start in the past: Determineshow long ago (in days) the start date can be. If it is more than the specified number of

    days, scheduling is carried out for todays date. Scheduling form: Specifies which

    object - network header or WBS element - is used as a basis for scheduling. Adjust

    basic dates: Determines that the scheduled dates are copied to the basic dates of

    the WBS elements after a scheduling run. Log automatic: If a log is generated,

    it is displayed automatically. Shift order: Determines how the system deals with

    partially-confirmed activities during scheduling (see below). Schedule when saving:

    Scheduling is carried out on saving. Latest material dates: The requirements dates

    for a material are determined based on the earliest or latest date. Maximum reduction

    level: A reduction strategy can have up to six levels. The highest level of reduction is

    specified here. Reduction type: Either all activities or only those along the critical

    path are reduced.

    The WBS scheduling profile is stored in the project definition control data. It can

    be copied as a default value from the project profile. One (or neither) of the two

    scheduling scenarios is displayed by default in the project profile.

    2005 / Q2 2005 SAP AG. All rights reserved. 39

  • 7/22/2019 PLM220 - Project Management..Logistics

    48/334

    Unit 2: Dates PLM220

    Other Influencing Factors in Scheduling

    Figure 21: Scheduling: Duration

    When scheduling internally-processed activities and general costs activities, the

    system uses the normal duration you maintained in the activity. The duration can be

    calculated from the work planned, provided you have stored a formula for calculating

    the duration from internal processing in the work center.

    When scheduling externally-processed activities, the system uses the number ofplanned delivery days you maintained for an external activity. You can, however, also

    use the normal duration from the internal processing screen of the external activity if

    you activate this explicitly in the control key of the external activity.

    Scheduling interprets the time interval for relationships as the minimum time interval.

    When calculating the dates, scheduling can increase the time interval but not reduce it.

    You can maintain a work center in internally and externally processed activities and in

    relationships. The following information is stored for scheduling in the work center:

    Formulas for calculating the duration of activities.

    A factory calendar and the operating time for each workday.

    40 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    49/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 22: Control Key

    The control keys for activities are set in Customizing using transaction OPSU. The

    control key indicators function as follows: Schedule: Activities and activity elements

    are scheduled. For activity elements, the dates for the activity are determined. Det.

    cap. req.: Capacity requirements are determined for activities and activity elements.

    The capacity requirements are determined using the scheduling results. Therefore,

    only set this indicator if you also set the scheduling indicator. Costs act.: This

    indicator specifies that you use the control key for general costs activities. Costing:

    This indicator determines that activities and activity elements are taken into account in

    costing.Print time ticket: This determines whether time tickets can be printed. Time

    tickets are only printed if thePrint indicator is also selected. For information on

    further relationships, see the online help. Confirmation: Determines whether activities

    and activity elements can be confirmed. External proc.: Determines whether activitiesand activity elements are processed internally or externally. Service: Determines

    whether services can be planned for activities and activity elements. Only set this

    indicator if you select the External proc. indicator to allow external processing.

    Print conf.: This determines whether completion confirmation slips can be printed.

    Completion confirmation slips are only printed if thePrintindicator is also selected.

    For information on further relationships, see the online help. Print: Determines

    whether work papers such as time tickets, completion confirmation slips can be

    printed. For information on other relationships, see the online help. Sch.ext.proc.:

    Determines whether activities are to be scheduled in line with the Planned delivery

    time orNormal duration.

    2005 / Q2 2005 SAP AG. All rights reserved. 41

  • 7/22/2019 PLM220 - Project Management..Logistics

    50/334

    Unit 2: Dates PLM220

    Figure 23: Relationships

    Relationships determine the chronological sequence of the individual activities in a

    network (or standard network). You can enter additional data (such as a time interval

    or reference to a particular factory calendar) in the detail screen for each relationship.

    The network graphic enables you to represent relationships in a time-dependent

    manner todisplay the logical sequence. All relationships in the network graphic are

    displayed as FS relationships by default.

    42 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    51/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Scheduling Example

    Figure 24: Example of Scheduling

    A network is always scheduled forwards and backwards. The scheduling type

    specifies whether forward scheduling or backward scheduling is carried out first.

    Forward scheduling calculates the earliest start and finish dates for the activities.

    All activities that do not have predecessors are start activities. The scheduling start

    start date is the start date in the network header or the start date determined from

    backward scheduling.Backward scheduling calculates the latest start and finish dates for all the activities.

    Target activities are network activities that do not have successors. The scheduling

    start date is the finish date in the network header or the finish date determined from

    forward scheduling.

    In the example above, the start dates are set to the beginning of the day (00:00) and the

    finish dates to the end of the day (24:00). If work centers are entered for the activities,

    the start and finish dates are within the operating time of the work centers affected.

    2005 / Q2 2005 SAP AG. All rights reserved. 43

  • 7/22/2019 PLM220 - Project Management..Logistics

    52/334

    Unit 2: Dates PLM220

    Figure 25: Total Float, Free Float

    Legend:

    ES= Earliest Start EF= Earliest Finish

    LS= Latest Start LF= Latest Finish

    TF= Total Float FF= FreeFloat

    Floats supply information on the time reserves available for individual activities. Youcan use the floats calculated in scheduling, for example in capacity leveling, to shift

    activities between the earliest and latest dates or to extend their duration.

    A total float is the difference between the latest start and earliest start (LS - ES) or

    between latest finish and earliest finish (LF - EF).

    A free float is the difference between the earliest start of a successor activity and

    the earliest finish of the activity in question (ES successor - EF activity). Since the

    successors for the free float are within their earliest dates, the time reserve is fully

    available to the current activity.

    44 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    53/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 26: Example of Floats

    This slide describes how total floats and free floats are calculated.

    The total float of activity 40 can be calculated from the difference between the earliest

    and latest start of an activity:

    Day 6 (0:00) - Day 5 (0:00) = 1 day.

    The free float of activity 40 can be calculated from the difference between the earliest

    start of the successor (activity 50) and the earliest finish of the activity.

    Day 9 (0:00) - Day 7 (0:00) = 1 day.

    2005 / Q2 2005 SAP AG. All rights reserved. 45

  • 7/22/2019 PLM220 - Project Management..Logistics

    54/334

    Unit 2: Dates PLM220

    Time Constraints and Reductions

    Figure 27: Time Constraints

    You can maintain constraints for the start and finish of activities.

    Constraints can be relevant for both the earliest and the latest dates.

    You can maintain constraints for basic and forecast date sets.

    46 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    55/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 28: Reduction

    You can use reduction if the time period within which the activities are to be scheduled

    is not long enough to process all activities. This allows you to reduce the scheduled

    duration of internally-processed activities.

    Reduction only affects the activities for which a reduction strategy has been stored.

    At the most, the system reduces as far as the level of reduction strategy entered

    in the network header.

    During scheduling, the system determines one reduction level for each activity. For

    example: The system calculates the earliest dates and determines reduction level 2 for

    an activity. This reduction level is transferred to the latest dates.

    Important: Remember to be careful when using the reduction function as the system

    does not know whether the duration of an activity can be reduced. It does not carry

    out plausibility checks or check available capacities.

    You can use reduction strategies to control how an activitys lead time can be reduced

    in levels. You can enter a reduction strategy in each activity.

    You can define up to six reduction levels for each reduction strategy. You can enter by

    what percent you want to reduce for each reduction level.

    2005 / Q2 2005 SAP AG. All rights reserved. 47

  • 7/22/2019 PLM220 - Project Management..Logistics

    56/334

    Unit 2: Dates PLM220

    Scheduling of the Overall Network

    Figure 29: Scheduling of the Overall Network

    The confirmed delivery date of an item in the sales order corresponds to the finish

    date of the assigned network. If the end of a network is shifted because of scheduling

    problems, the confirmed delivery date in the sales order is changed automatically. You

    can, however, also fix a confirmed delivery date for the item on the Schedule lines

    tab page.

    As of Release 4.0, scheduling of the overall network for the sales order item can be

    started in the sales order itself.

    This function schedules both the network assigned to the sales order item and all other

    networks linked to this network via a relationship.

    This function updates all items in the sales order that refer to the overall network.

    48 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    57/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 30: Overall Network Scheduling with Selection Options

    As well as overall network scheduling (transaction CN24), which you can use to

    schedule several networks and subnetworks together, you also have at your disposal,

    from ECC 5.0 onwards, the new functionoverall network scheduling with selection

    options(transaction CN24N).

    You use this function along with suitable selection criteria to specify which networks

    and subnetworks are to be taken into account as part of overall network scheduling.

    You can display additional information on the selected activities and subnetworks on a

    monitor and jump to the next screen to processing or confirmation of activities.

    A prerequisite for the use of theOverall network scheduling with selection options

    function is that you have defined suitable levels beforehand in Customizing for the

    project system and have assigned network types and number intervals. Note that

    you can only schedule using two levels.

    By using a BAdI forOverall scheduling with selection options, you have other

    functions at your disposal such as control of data exchange between activities and

    assigned subnetworks.

    2005 / Q2 2005 SAP AG. All rights reserved. 49

  • 7/22/2019 PLM220 - Project Management..Logistics

    58/334

    Unit 2: Dates PLM220

    Figure 31: Subnetwork Monitor

    Dates of Assigned Objects

    Figure 32: Dates: Activity Elements

    Unlike activities, activity elements are not scheduled independently. The system

    calculates the dates for activity elements with reference to the start or finish dates of

    the activity. You maintain a time interval for the start and for the finish. The dates ofthe activity element must always lie entirely within the duration of the higher-level

    activity.

    50 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    59/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Figure 33: Requirements Date: Material

    The system calculates the requirements date for components with reference to the start

    or finish date of the activity. You can use the Scheduling parameters for network type

    or theParameters for WBS schedulingto control whether the earliest or latest start

    date is used as the requirements date. The transaction used to trigger the scheduling

    determines which of the two tables is used. If you schedule within the network or

    the overall network, theScheduling parameters for the network type apply. If you

    schedule within the project planning board or using structure planning, the Parameters

    for WBS schedulingapply.

    If the requirements date is before the finish date of the activity, you can store a

    corresponding time interval by using an offset to the finish date.

    You can also set a requirements date for a material manually.

    2005 / Q2 2005 SAP AG. All rights reserved. 51

  • 7/22/2019 PLM220 - Project Management..Logistics

    60/334

    Unit 2: Dates PLM220

    Figure 34: Dates: Milestone

    The slide describes milestones that are assigned to activities. The planned date is

    either entered manually or with reference to the activity. If the date refers to the

    activity dates, you must decide whether it is to refer to the earliest or latest dates

    and the start or the end of the activity. Additionally you enter a positive or negative

    offset for this reference point.

    You can also assign milestones to WBS elements. As of Release 4.6, the planned dates

    for a milestone can refer to the basic start or finish date of a WBS element.

    52 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    61/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Exercise 2: Scheduling

    Exercise ObjectivesAfter completing this exercise, you will be able to:

    Carry out time scheduling with predefined scenarios

    Use relationships and restrictions

    Business Example

    Using the project planning board, you calculate the dates and floats for carrying out

    the individual activities of your turbine project. At the same time, you also take into

    account the time-based dependencies of the individual activities and, if necessary,

    other conditions.

    Task 1:

    1. Call up the project planning board.

    2. Process your project T-100## in the project planning board. Use the1001

    Elevators/Turbinesplanning board profile.

    3. Optimize the project display to show all activities completely.

    4. Plan dates for your project using the predefined bottom-up scenario.

    First check the time scheduling settings.

    Set the scheduling scenario to Bottom-up scenario (pre-defined) if you have

    not already done so.

    Plan the dates for the entire project.

    Hint: The bottom-up scheduling scenario is set so that all activity

    dates are determined and then the earliest and latest dates for each

    are transferred to the assigned WBS elements. To finish, dates are

    extrapolated for upper-level WBS elements within the hierarchy.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 53

  • 7/22/2019 PLM220 - Project Management..Logistics

    62/334

    Unit 2: Dates PLM220

    5. Check the floats for your project. Display both the earliest and the latest dates.

    Hint: Scheduling always calculates the dates of activities forwards andbackwards. Each activity (and activity element) thus has two time bars.

    Different colors (usually blue and red) are used to distinguish between

    activities in the planning board that still have or no longer have time

    floats.

    6. Change the duration of activity 4000Production of running gear, bearing, valves

    and look at the effect this has on scheduling.

    Reduce the duration of the activity to 30 days.

    Hint: Although the system adjusts the time bars of activity 4000 in the

    graphic, the overall project dates are no longer up to date. You need to

    perform scheduling again. Note the changes to activities 3000 and 3100.

    How are activities 3000 and 3100 affected?

    7. Save your scheduling data.

    Task 2:

    1. Now take a look at the scheduling details. Once again, use the project planning

    board for this purpose. Call up your project.

    2. Create two further activities within activity 5010Planning of instrumentation.

    The activities will be linked to each other at a later stage.

    3. Input the details for the two new activities.

    Enter the following data in the detail screen for activity 5020:

    Field Name Values

    Text Detailed planning for

    instruments

    Work center 2000

    Work 10 hours

    Normal duration 3 days

    Continued on next page

    54 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    63/334

    PLM220 Lesson: Scheduling of Activities and Networks

    If the system asks you to enter a business area, choose business area 2000.

    Go to the detail screen for activity 5030. Enter the following data:

    Field Name Values

    Text Corrections for

    instruments

    Work center 2000

    Work 10 hours

    Normal duration 72 hours

    4. Schedule your project.

    How does scheduling affect the WBS elements in the project?

    5. Link activities 5010, 5020 and 5030 with relationships. Use FS relationships

    for this.

    6. Schedule your project.

    Note how the time bars for activities 5010, 5020 and 5030 change.

    7. The three activities are not yet integrated in the rest of the network. In the

    graphic, create an FS relationship between activity 1000 and activity 5010.

    8. Schedule your project.

    9. Using the table, create an FS relationship between activity 5030 and activity

    3100.10. Schedule your project.

    11. Check the floats in your project. Click the Dates tab on the detail screen for

    activity 5010Planning of instrumentation.

    What is the total float of the activity? _____________

    Display the total float directly in the diagram area. Configure the system in such

    a way that only those activities with a negative total float are highlighted as

    critical activities.

    12. Activity 5020Detailed planning for instruments is not to start before a certain

    date. Set a date constraint in the Datesdetail screen for the activity.

    Set a date constraint for the start date.

    As start date, enter the earliest start date plus one week in the future.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 55

  • 7/22/2019 PLM220 - Project Management..Logistics

    64/334

    Unit 2: Dates PLM220

    13. Schedule your project.

    What is the free float of activity 5010? _____________

    Why does activity 5010 have a free float?

    14. Save your scheduling data.

    56 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    65/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Solution 2: Scheduling

    Task 1:

    1. Call up the project planning board.

    a) SAP Menu!Logistics!Project System!Project!Project Planning

    Board! Change Project(Double-click to select transaction)

    2. Process your project T-100## in the project planning board. Use the1001

    Elevators/Turbinesplanning board profile.

    a) Enter your project in theProject def. field, selectW. activities, enter the

    corresponding planning board profile and select Open project.

    3. Optimize the project display to show all activities completely.

    a) Use theZoom in on graphic icon to choose a suitable zoom factor.

    Optimize the graphic display using the Adapt graphic area icon.

    4. Plan dates for your project using the predefined bottom-up scenario.

    First check the time scheduling settings.

    Set the scheduling scenario to Bottom-up scenario (pre-defined) if you have

    not already done so.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 57

  • 7/22/2019 PLM220 - Project Management..Logistics

    66/334

    Unit 2: Dates PLM220

    Plan the dates for the entire project.

    Hint: The bottom-up scheduling scenario is set so that all activitydates are determined and then the earliest and latest dates for each

    are transferred to the assigned WBS elements. To finish, dates are

    extrapolated for upper-level WBS elements within the hierarchy.

    a) First check the time scheduling settings.

    ChooseOptions.

    Set the scheduling scenario toBottom-up scenario (pre-defined).

    Confirm your entries by clicking the Copypushbutton.

    Plan the dates for the entire project.

    ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    5. Check the floats for your project. Display both the earliest and the latest dates.

    Hint: Scheduling always calculates the dates of activities forwards and

    backwards. Each activity (and activity element) thus has two time bars.

    Different colors (usually blue and red) are used to distinguish between

    activities in the planning board that still have or no longer have time

    floats.

    a) ChooseSet of Dates/View.

    Activate theLatest dateindicator and confirm your data entries by clicking

    Confirm.

    6. Change the duration of activity 4000Production of running gear, bearing, valves

    and look at the effect this has on scheduling.

    Reduce the duration of the activity to 30 days.

    Hint: Although the system adjusts the time bars of activity 4000 in the

    graphic, the overall project dates are no longer up to date. You need to

    perform scheduling again. Note the changes to activities 3000 and 3100.

    Continued on next page

    58 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    67/334

    PLM220 Lesson: Scheduling of Activities and Networks

    How are activities 3000 and 3100 affected?

    a) Double-click the line containing activity 4000 to call up the detail screen

    for the activity.Reduce the duration of the activity to 30 days. Enter this duration in the

    Normal durationfield on theInternaltab.

    Confirm your entries by clicking theBackicon.

    b) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    The extended duration of the activity affects the entire network.

    Previously, activity 3000 was critical (it had negative floats). After

    scheduling, it has positive floats. Activity 3100 behaves in a completely

    different way. In the network structure graphic, you can see that theactivities lie in two different, parallel paths. Before scheduling, the

    first path (with activity 3000) is the critical path in the network. After

    scheduling, the other path (with activity 3100) represents the critical path.

    7. Save your scheduling data.

    a) Choose Save.

    Do not save any user-specific settings.

    Task 2:

    1. Now take a look at the scheduling details. Once again, use the project planning

    board for this purpose. Call up your project.

    a) SAP Menu!Logistics!Project System!Project!Project Planning

    Board! Change Project(Double-click to select transaction)

    Enter your project in the Project definitionfield, selectWith activities, and

    click theOpen projecticon.

    As before, optimize the project display by clicking the Zoom in on graphic

    andAdapt graphic area icons.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 59

  • 7/22/2019 PLM220 - Project Management..Logistics

    68/334

    Unit 2: Dates PLM220

    2. Create two further activities within activity 5010Planning of instrumentation.

    The activities will be linked to each other at a later stage.

    a) Select activity 5010Planning of instrumentation.ChooseCreate.

    The templates area is shown on the left of the project planning board.

    Double-click theActivity (internal)object in the templates area.

    The system creates an internal processing activity with default values. The

    assignment to the WBS element is copied by the selected activity. The

    detailed settings for the activity will be carried out later.

    b) Create the second activity.

    Double-click theActivity (internal)object in the templates area once again.

    Hide the templates area.

    Click theOpen/close left-hand windowicon.

    3. Input the details for the two new activities.

    Enter the following data in the detail screen for activity 5020:

    Field Name Values

    Text Detailed planning for

    instruments

    Work center 2000

    Work 10 hours

    Normal duration 3 days

    If the system asks you to enter a business area, choose business area 2000.

    Go to the detail screen for activity 5030. Enter the following data:

    Continued on next page

    60 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    69/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Field Name Values

    Text Corrections for

    instruments

    Work center 2000

    Work 10 hours

    Normal duration 72 hours

    a) With theControlkey pressed, select the two activities.

    Call up the detail screen for the activities.

    Click theDetailed information for objecticon.

    Enter the following data in the detail screen for activity 5020.

    ChooseNext.

    If the system asks you to enter a business area, choose business area 2000.

    The detail screen for activity 5030 appears. Enter the data specified.

    Exit editing using theBackicon.

    4. Schedule your project.

    How does scheduling affect the WBS elements in the project?

    a) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    Bottom-up is still selected as the scheduling scenario. The activity dates

    are transferred to the higher-level WBS elements. In the example above,

    the date of the WBS element Planning of instrumentationis adjusted. Note

    the different durations (3 days or 72 hours) of the two new activities.

    5. Link activities 5010, 5020 and 5030 with relationships. Use FS relationships

    for this.

    a) With theControlkey pressed, select the activities.

    SelectConnect selected activities.

    The system creates FS relationships between the activities. The order of

    the relationships is determined by the order in which the activities aredisplayed in the planning board (from top to bottom).

    6. Schedule your project.

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 61

  • 7/22/2019 PLM220 - Project Management..Logistics

    70/334

    Unit 2: Dates PLM220

    Note how the time bars for activities 5010, 5020 and 5030 change.

    a) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    7. The three activities are not yet integrated in the rest of the network. In the

    graphic, create an FS relationship between activity 1000 and activity 5010.

    a) Activate the connect mode.

    Click theSwitch connect mode on/officon.

    The cursor is displayed as a pencil in the graphic area. Create the FS

    relationship.

    With the mouse button pressed, drag the cursor from the right half of

    activity 1000 to the left half of activity 5010, and release the mouse button.

    Deactivate the connect mode.

    Click theSwitch connect mode on/officon.

    8. Schedule your project.

    a) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    9. Using the table, create an FS relationship between activity 5030 and activity

    3100.

    a) Select activity 5030.

    Click theEdit relationships (tabular) icon.

    A list of the activity relationships appears.

    b) Create an FS relationship for activity 3100 Material procurement plant

    components.

    Choose theSuccessortab page.

    Select activity 3100 in theActivity selectionsection.

    Choose theCreate requirementicon.

    Confirm your data entries by clicking the Continueicon.

    10. Schedule your project.

    a) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    Continued on next page

    62 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    71/334

    PLM220 Lesson: Scheduling of Activities and Networks

    11. Check the floats in your project. Click the Dates tab on the detail screen for

    activity 5010Planning of instrumentation.

    What is the total float of the activity? _____________Display the total float directly in the diagram area. Configure the system in such

    a way that only those activities with a negative total float are highlighted as

    critical activities.

    a) Double-click either the activity time bar or the activity number.

    Go to the Datestab page.

    Note the total float.

    Exit the detail screen by clicking theBackicon.

    b) Choose theOptionsicon.

    ChoosePlanning boardin the tree structure and then click theDiagram

    area tab.

    Select theShow total floatindicator.

    Enter the value 1- in the Critical fromfield (note the sign)

    Confirm your data entries by clickingCopy.

    12. Activity 5020Detailed planning for instruments is not to start before a certain

    date. Set a date constraint in the Datesdetail screen for the activity.

    Set a date constraint for the start date.

    As start date, enter the earliest start date plus one week in the future.a) Double-click either the activity time bar or the activity number.

    Select theDatestab page.

    Choose theCannot start beforevalue in the Startfield.

    As start date, enter the earliest start date plus one week in the future.

    Confirm your entries by clicking theBackicon.

    13. Schedule your project.

    What is the free float of activity 5010? _____________

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 63

  • 7/22/2019 PLM220 - Project Management..Logistics

    72/334

    Unit 2: Dates PLM220

    Why does activity 5010 have a free float?

    a) ChooseSelect allto select all objects.

    Start the scheduling procedure by clicking the appropriate icon.

    Note the free float in the detail screen of activity 5010.

    The free float is the difference between the earliest finish date for an

    activity and the earliest start date for the successor. The earliest start for

    the successor was only set to a later date by restricting the start date of the

    successor (5020, Cannot start before). Free floats also appear for parallel

    activities that have the same successor. In this case, the longer activity

    determines the earliest start date of the successor and the shorter activity

    has a free float.

    14. Save your scheduling data.

    a) ChooseSave.

    Do not save any user-specific settings.

    64 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    73/334

    PLM220 Lesson: Scheduling of Activities and Networks

    Lesson Summary

    You should now be able to:

    Perform scheduling with the aid of the project planning board

    Set the relevant tables in Customizing

    2005 / Q2 2005 SAP AG. All rights reserved. 65

  • 7/22/2019 PLM220 - Project Management..Logistics

    74/334

    Unit 2: Dates PLM220

    Lesson: Actual Dates

    Lesson OverviewThis unit deals with the various ways of entering actual dates for WBS elements and

    activities. At the same time, prerequisites for entering actual dates are discussed as

    well as the effect of actual dates on subsequent scheduling runs.

    Lesson Objectives

    After completing this lesson, you will be able to:

    Enter actual dates for WBS elements and activities

    Business Example

    You want to compare planned dates with the actual execution dates in the execution

    phase of your project in order to be able to monitor the date situation for your project.

    To do this, you enter the actual dates for your project.

    Entering Actual Dates

    Figure 35: Actual Dates

    To monitor the dates for a project, you compare the basic dates with the actual dates

    or forecast dates.

    66 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    75/334

    PLM220 Lesson: Actual Dates

    Actual dates can be set manually for WBS elements. If you are using network

    activities, actual dates are set by confirming activities. If activities are assigned to

    a WBS element, the actual dates of the activities are proposed to the WBS element

    as provisional dates that can be transferred to the actual dates of the WBS elementif necessary.

    Important: Actual dates are usually updated for an activity during activity

    confirmation. You can suppress this update if necessary. To do this, select the No

    date updateindicator during confirmation.

    Actual Dates of WBS Elements

    Figure 36: Actual WBS Dates

    Legend:

    AS = Actual start date AF= Actual finish date

    CNF= Finally confirmed REL= Released

    For WBS elements without assigned activities:

    You can always maintain the actual start if the WBS element has the status

    Released or Partially released.

    You can only maintain the actual finish if all lower-level WBS elements have

    an actual finish date.

    2005 / Q2 2005 SAP AG. All rights reserved. 67

  • 7/22/2019 PLM220 - Project Management..Logistics

    76/334

    Unit 2: Dates PLM220

    The following also applies to WBS elements to which activities are assigned:

    You can only maintain the actual start if the assigned activity has the status

    Partially released or Released. You can only maintain the actual finish date if all the lower-level WBS elements

    also have an actual finish date and all the activities for the WBS element have

    the status Finally confirmed.

    Actual Dates of Activities

    Figure 37: Actual Dates of Activities

    Actual dates are entered in networks using confirmation. This can be carried out using

    individual or collective confirmation, or the cross application time sheet.

    Once an activity has been finally confirmed, the start and finish of the earliest and

    latest dates match the actual start and actual finish dates.

    Partial confirmations affect the scheduling result for the earliest date in accordance

    with the Shift order indicator.

    The Shift order indicator is not set: The actual start date and forecast duration

    of the partial confirmation are taken into account when the earliest date is

    calculated. The Shift order indicator is set: The actual start date of the partial confirmation

    is not taken into account when the earliest date is calculated.

    68 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    77/334

    PLM220 Lesson: Actual Dates

    To call up an overview of your planned dates at a certain point in time (baseline), use

    either project versions or forecast dates.

    2005 / Q2 2005 SAP AG. All rights reserved. 69

  • 7/22/2019 PLM220 - Project Management..Logistics

    78/334

    Unit 2: Dates PLM220

    70 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    79/334

    PLM220 Lesson: Actual Dates

    Exercise 3: Actual Dates from Confirmations

    Exercise ObjectivesAfter completing this exercise, you will be able to:

    Describe the effects of actual dates on time scheduling

    Business Example

    You create partial confirmations for activities that are already being processed and

    calculate the resulting shifts in dates for your project.

    Task:

    1. So far, you have planned dates but not begun to enter actual dates. Actual dates,

    however, can also affect your planned dates. Take a look at how actual dates

    affect planned dates in the project planning board. To do this, start by opening

    your project in the project planning board and alter the display accordingly.

    2. Before you start to enter actual dates, transfer the dates planned previously (basic

    dates) to the set of dates for alternative time scheduling (forecast dates).

    Show the forecast dates, compare them with the basic dates, and then hide

    them again.

    Hint: Forecast dates can be determined via scheduling in the sameway as basic dates. These dates are simply alternative dates for time

    scheduling and are used in the course to freeze time scheduling at a

    certain point in time. This allows comparisons to be made with changed

    time scheduling (basic dates) at a later stage.

    3. Before you can enter actual data, you have to release activities or WBS elements.

    Release the WBS element T 100##.1Engineering and Design.

    The status is inherited to lower-level activities to allow you to continue entering

    actual activity data.

    4. Enter a partial confirmation for the activity 1000Engineering of

    drawing/calculation/design. Display both the actual dates and the basic dates inthe diagram area.

    Enter the following data in the confirmation dialog window:

    Continued on next page

    2005 / Q2 2005 SAP AG. All rights reserved. 71

  • 7/22/2019 PLM220 - Project Management..Logistics

    80/334

    Unit 2: Dates PLM220

    Field Name Values

    Compl. Deselect

    Final conf. Deselect

    Processing % 20 %

    Actual start Copy the earliest start

    date

    Actual finish Actual start plus 2

    working days

    Forecast duration 14 days

    5. Schedule your project.

    Note how the basic dates for activity 1000 change.6. You can use theShift orderindicator to prevent the actual dates from affecting

    scheduling. Activate this indicator and carry out the scheduling process again.

    Except for theShift orderindicator, the settings for the predefined profileIDES

    scheduling forwardcorrespond to the bottom-up scenario.

    Reschedule your project.

    Notice how the time bar of activity 1000 becomes shorter and the dates of all

    following activities are adjusted.

    7. Compare the basic dates with the forecast dates.

    Hide the forecast and actual dates again.

    8. Select the bottom-up scheduling scenario again.

    9. Save the changes to your time scheduling settings.

    72 2005 SAP AG. All rights reserved. 2005 / Q2

  • 7/22/2019 PLM220 - Project Management..Logistics

    81/334

    PLM220 Lesson: Actual Dates

    Solution 3: Actual Dates from Confirmations

    Task:

    1. So far, you have planned dates but not begun to enter actual dates. Actual date