Upload
bethany-hensley
View
213
Download
0
Embed Size (px)
Citation preview
Plans for HV R&D at LANL
Vacuumchamber
Supplycryostat
Josh Long, Indiana U.
Tests in progress
Control purity, contaminants, attempt T < 1.8 K
Near Future
Breakdown studies of test cell materials
2007
Large-volume HV studies at DR temperatures, high pressure
Previous results from prototype system
Maximum leakage currents under these conditions (95% C. L.) :SF (2.07 K): 733 pANormal State (3.98 K): 169 pA
Short-duration breakdown not affected by neutron radiation (106/s, ~MeV)
Small commercial HV feedthrough exceeded maximum rating in air (40 kV) by 25% when immersed in SF
Maximum potentials sustained:11.8 liters Normal State (4.38 K), 7.2 cm gap:
(96 ± 7) kV/cm
12.8 liters SF at 2.14 K, 7.8 cm gap:
(31 ± 3) kV/cm
Pressure effects common in literature, e.g.:
LHe breakdown at 2 K (at 100 m gap) : 500 kV/cm (25 torr), 800 kV/ cm (700 torr) [Suehiro, et al., 12th Intl. Conf. Conduction and Breakdown in Dielectric Liq., Rome, 1996, 320.]Possible further degradation below 1.9 K
Bubble formation (common breakdown culprit) observed when charging above 10 kV, likely coincident with noise
Better performance (wide T, P range) without pressurizing?
Reduced surface roughness (64 -inch to 16 -inch)
Expect ~2x improvement in breakdown [Gerhold, IEEE Trans. on Dielec. and Elec. Insul., 1 (1994) 432-439 ]
No observed improvement at 1.9 K or 4 K
Results uncertain due to excessive contamination (oil, air backstreaming from pump)
Attempt to improve purity of LHe and reduce surface contaminants
Principal concerns (from literature):
Hydrocarbons
LHe contaminated with oil “useless” as insulator [Gerhold, Cryogenics (October 1972) 370]
Conducting contaminants
Oxygen
Existing (“accidental”) observations
4 K breakdown strength unchanged after many hours pumping with oil pump
Small gap breakdown at 2 K and 4 K unchanged after backstreaming event
Unchanged after frozen contaminants left to evaporate and system replenished with LHe passed through 10 mm pore filter
Current tests in progress
Control purity and surface contaminants systematically
Complete solvent cleaning of interior
RF Plasma discharge cleaner (for Hydrocarbons)
Dry pumps only for all applications
No LN2 pre-cooling: attempt using cold, filtered He gas from LHe supply dewar(can filter LN2 if not practical)
LN2 trap on LHe bath pumping line
LHe (and gas) filter on transfer line outlet
Charcoal + low porosity materials, Quantum Technologies
RGA monitoring
Further reduced surface roughness
Electrodes polished to ~ 8 -inch finish
Current tests in progress
Attempt operation below 1.8K
Colder LHe transfers
New transfer line operates with HV system below lambda point
Heat load reductions (also important for eventual operation with DR):
Tie central volume lateral support posts to 77 K
Tie supply cryostat upper neck to 77 K shield
Remove all unnecessary (conducting) instrumentation from supply cryostat upper neck
Cover open viewport holes in 77 K shield with quartz windows
Tie actuator rods to 77 K shield
Previous heat load 2 W
1 W
0.5 W
0.1 W
0.1 W
0.02 W
Other
Video monitoring of gap
Improved level sensing
R&D questions (initial test)
Breakdown study of test cell materials
Assess if low breakdown strength
Modify system as little as possible to compare to established baseline (initial test)
Acrylic: breakdown strength = 200 kV/cm in air at 300 K
Note: G-10 standoffs = 400 kV/cm
Assess if high leakage current (especially across straight, smooth surface)
Use existing HV test system
Later phase: refine test cells to reflect final geometry, coatings (or as necessary to attain higher breakdown if problems)
Plan/ technical assumptions
~65% of field in maximum HV-Ground gap
Good uniformity
Single 14 x 9 x 2 cm piece (rounded edges)
Equidistant between standoffs (back view):
Breakdown study of test cell materials
(ignoring G10 standoffs [ ~ 5])
Possible phase II: add 5 more at different angular positions to match edge length of actual cell (120 cm)
electrode
standoff
Breakdown study of test cell materials
Complications:
Acrylic thermal expansion ~ .02 from 2-300 K (?)
Cell shrinks 2 mm relative to 14 cm G-10 standoffs
-> Spring-loaded base to attach to isolation plate (?)
Cell shrinks 0.5 mm relative to adjacent points on electrode
-> Issues for mounting in recesses:
electrode
cell
Task Est Cost Est Duration Start Finishdesign cell (LANL engineer) 592 1 10/12/2006 10/13/2006design mount/electrode mods (LANL engineer) 2960 5 10/16/2006 10/20/2006procure cell 500 15 10/20/2006 11/3/2006procure mounts/electrode mods 2000 15 10/20/2006 11/3/2006install electrodes and cells (LANL tech) 2240 5 11/6/2006 11/10/2006procure LHe 4500 5 11/6/2006 11/10/2006run tests (LANL tech) 4480 14 11/13/2006 11/27/2006contingency (20%) 3454
Initial test total and dates 20726 10/12/2006 11/27/2006
procure remaining cells 2500 15 12/1/2006 12/14/2006procure remaining mounts/electrode mods 4000 15 12/1/2006 12/14/2006install electrodes and cells 2240 5 12/18/2006 12/22/2006procure LHe 4500 5 1/8/2007 1/12/2007run tests 4480 14 1/15/2007 1/29/2007contingency (20%) 3544
Full test total and dates 21264 12/1/2006 1/29/2007
Acrylic test total and dates 41990 10/10/2006 1/21/2007
Breakdown study of test cell materials
R&D questions
HV tests in upper cryostat prototype
What happens to breakdown strength and leakage currents in large LHe volumes/electrode gaps at 500 mK?
System should be dis-mountable within ~ 1 week to run w/o DR if necessary
Couple existing HV test system to DR via dedicated insert in upper cryostat prototype
Plan/ technical assumptions
No interference with injection/relaxation insert (though separate experiments will have to run in series)
Heat loads in existing test system can be controlled
How much improvement can be attained with pressurized LHe (~1 atm) at these temperatures?
Incorporate best candidate materials for electrodes and cell prototypes
Address remaining questions about purity by condensing LHe from filtered gas (if time)
Pump and flush HV volume
Backfill with P > 1atm He gas
Pre-cool with LN2 through coiled line
Flush coiled line
Pre-cool to 4.2 K with cold He/ LHe through coiled line
Evacuate and seal coiled line
Open LHe valve to fill HV volume from LHe supply
Close LHe valve
OPTION: Pressurize LHe volume with He gas to P ~ 1.4 atm
Push down plastic heat stopper
Engage thermal link(s) to DR
Cool to 1.5 K (0.5 K)
Design from D. Haase, 8/06
Design from D. Haase, 8/06
Significant design work remaining
Operation contingent on reducing heat loads in HV volume
DR ~ 50 mW @ 300 mK (?)
Current HV system heat load: 2W
Target: < 1 W
Additional coiled pre-cooling line around copper shield possible (10 K?)
Heat load through SI: ~ 0.5 W
~20” Revised Spool
Modified Adapter
Proposed location for HV 1K frig
Location for future purifier
Procurement begun for adaptor parts
Task Est Cost Est Duration Start Finishdesign insert (LANL engineer) 8880 21 10/9/2006 10/30/2006procure pre-cool lines (HV tank, shield) 500 7 10/31/2006 11/6/2006procure pre-cool lines (DR volume) 500 7 10/31/2006 11/6/2006procure LHe valve, f ilter 2000 30 10/31/2006 11/30/2006procure safety valve, line 2000 30 10/31/2006 11/30/2006procure thermal sw itch(es) 5000 30 10/31/2006 11/30/2006procure LHe volume 5000 50 10/31/2006 12/19/2006procure heat exchanger(s) 5000 50 10/31/2006 12/19/2006
install LHe volume, valve, f ilter (LANL tech) 6720 21 1/8/2007 1/28/2007install heat exchangers, sw itches (LANL tech) 6720 21 1/29/2007 2/17/2007Modify copper shield (pre-cool line, LANL tech) 2240 7 2/18/2007 2/24/2007Install HV volume pre-cool line (LANL tech) 2240 7 2/25/2007 3/2/2007
contingency (50%) 23400
assembly total and dates 70200 10/9/2006 3/2/2007
Initial test (debug, low -T data):procure LHe 6000 5 3/5/2007 3/9/2007run tests (LANL tech) 13440 40 3/3/2007 4/15/2007
operations contingency (50%) 9720
initial operation total and dates 29160 3/5/2007 4/15/2007total 99360
HV tests with DR (guesses; independent of cell tests)
Subsequent tests (pressurization, new electrodes, etc: 3-4 weeks each with dedicated use of DR ~ 2x as long to assemble (Summer 2007) if no work in parallel with cell tests ?
R&D questions
Other HV issues
Possible in principle via Kerr effect (accuracy? Effect of acrylic?)
Either can be incorporated whether or not system coupled to DR
Plan/ technical assumptions
Can we assess field uniformity in test system?
Will need additional windows for scanning large regions of gap or scanning behind HV electrode (Kerr)
Can we bring 350 kV directly into system?
Figure: Karamath, Lepton Moments conference (2006)
Can already bring 50 kV into present LANL test system at 1.9 K
(1.5 < gap < 8) cm
Electrical breakdown in a full cell
an extensive literature deriving from interest in insulating high power superconducting apparatus
suggested possibilities 1) impurities 2) motion of individual electrons – localized or delocalized 3) field emission
field emission from the cathode is the most likely possibility based on what is known about helium
highly localized dissipation of energy by electrons creates hot spotliquid vaporizes, creates macroscopic bubble; avalanche and breakdown
ensues
FROM G. SEIDEL, LANL, 9/27/06 (NOT PRESENTED)
stainless canaluminumplate
wire sealflange
G-10standoff
HV plungercontrol rod
Indium seal
ceramicstandoff
HV electrodeground electrode
groundcontrol rod
Vacuum-LHeHV feedthrough
bearingsbellows
0.53 m
quartz window
High voltage system prototype at LANL
Vacuumchamber
Supplycryostat
HVfeedthrough
Actuator
Test proposed amplification method
Measure breakdown properties of large volumes of LHe
Existing data: 150 kV/cm at 4 K, 1cm gap
LHe bath pumping line