Pipeline Project News Andrew Emhof Facilities Engineer, Interstate Marketing National Fuel Gas Supply Corp. Empire Pipeline, Inc. Appalachian Pipeliners Association Speaker Dinner May 16, 2017

Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Embed Size (px)

Citation preview

Page 1: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Pipeline Project News

Andrew EmhofFacilities Engineer, Interstate Marketing

National Fuel Gas Supply Corp.

Empire Pipeline, Inc.

Appalachian Pipeliners Association Speaker Dinner

May 16, 2017

Page 2: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

National Fuel Gas Company

• 1.8 Tcfe Proved Reserves (1)

• 785,000 net acres in Marcellus Shale

• 3 million Bbls/year of crude oil

production in California

• $1.3+ billion midstream investments

since 2010

• Coordinated infrastructure build-out

in Appalachia with NFG Upstream

• 740,000 Utility customer accounts

Upstream

Midstream

Downstream

(1) Total proved reserves are as of September 30, 2016.2

Page 3: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Planned Expansion ProjectsMeeting the Demands of an Evolving Market

Page 4: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Planned Expansion Projects

Northern Access

• Capacity:

• 497,000 Dth/d on NFGSC

• 350,000 Dth/d on Empire

• Market:

• Seneca Resources

• Transportation Path: Seneca’s Clermont production area to TGP 200 Line and Chippawa (TCPL)

• Facilities:

• 99.0 Miles of 16” and 24” pipeline

• New 22,214 HP Pendleton CS

• Enhanced 5,350 HP Porterville CS

• Dehydration facility

• Various M&R facilities

• Project in-service not expected before 2019 due to regulatory delays

Delivery Point

Northern

Access

Chippawa

(TCPL)

Clermont

TGP 200

Line

4

Page 5: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Northern Access: Project Milestones

• Summer 2014: Open season held

• Capacity subscribed by foundation shipper

• Summer 2014-Winter 2015: Conducted environmental and engineering studies

• July 24, 2014: Began FERC Pre-filing process

• March 17, 2015: Submitted initial FERC 7(b)/7(c) applications

• Summer 2015-Winter 2016: Conduct right-of-way negotiations

• November 2, 2015: Submitted amended FERC 7(b)/7(c) applications

• Relocated Pendleton Compressor Station

• February 2016: Submitted NYS DEC 401 Water Quality Certification application

• July 27, 2016: Received favorable FERC Environmental Assessment

• February 3, 2017: FERC 7(c) certificate received

• April 7, 2017: NYS Water Quality Certificate and air permits denied by DEC

• April 21, 2017: Filed petition with US Court of Appeals for the 2nd Circuit

• Anticipate at least a 12-month review before decision ruled

5

Page 6: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Northern Access: Modernized Gas Storage Engine

6

Page 7: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Planned Expansion Projects

Line D Expansion

• Capacity: 77,500 Dth/d

• Market:

• Increased On-System Demand

• Transportation Path: Lamont (TGP 300 Line) to Erie, PA region

• Facilities:

• 4,140 HP of compression at new Keelor CS

• Lamont M&R Upgrades and station modifications

• Satisfied FERC Prior Notice Blanket Requirements in February 2016

• Targeted in-service: Fall 2017

Delivery Point

Line D

ExpansionErie

North East

Lamont

Warren

7

Page 8: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Line D Expansion: Project Milestones

• Fall 2014: Open season held

• 77,500 Dth/d of capacity subscribed

• December 21, 2015: Applied for FERC Prior Notice Blanket Certificate

• February 26, 2016: Received FERC approval

• Summer 2016-Winter 2017: Commence initial construction activities

• Keelor CS site development

• Complete pipeline MAOP remediation work

• Install upgrades at Bowen CS

• Increase meter capacity at Lamont

• April 17, 2017: PADEP Air Permit granted

• Fall 2016-Summer 2017: Construction of mechanical facilities

• Installation of new compressors at Keelor CS

• Commission new facilities

• Fall 2017: Projected in-service date

8

Page 9: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Line D Expansion: Keelor CS Site as of May 2017

9

Page 10: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Planned Expansion Projects

Mainline Extension to Pennsylvania Chemicals Project

• Capacity: 133,000 Dth/d

• Market:

• New ethylene cracker facility being built by Shell Chemical Appalachia

• Other delivery locations as available

• Transportation Path: Holbrook (TETCO) and New MAPP to Potter Township, PA region

• Facilities:

• 4-mile extension from Line N

• Other minor Line N enhancements

• Open Season closed May 4, 2017

• Foundation Shipper signed

• Targeted in-service: July 2019

10

Page 11: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Planned Expansion Projects

Empire North Project

• Capacity: 300,000 Dth/d (scalable)

• Market:

• Negotiating with key subscribers

• Transportation Path: Jackson and Corning (Millennium) to Hopewell (TGP 200 Line) and Chippawa (TCPL)

• Facilities:

• 3 compressor stations

• Other M&R facilities

• No new pipeline construction required

• Open Season closed Fall 2015

• Foundation shipper agreement in place for substantial portion of expansion capacity

• Targeted in-service: As early as November 2019

11

Page 12: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Potential Future Expansion ProjectsBroadening Our Reach

Page 13: Pipeline Project News - National Fuel Gas · PDF fileLine D Expansion: Project Milestones • Fall 2014: Open season held • 77,500 Dth/d of capacity subscribed • December 21, 2015:

Potential Future Expansions

Line N Expansion

• Replacement of remaining older-vintage pipeline, increasing System Maximum Operating Pressure

• Expand or develop new interconnections with other pipelines (Columbia, DTI, NEXUS, Rover, TETCO, TGP)

• Develop market-area delivery points

Production-related expansions

• Replacement/expansion of existing pipelines in Marcellus/Utica Shale fairway

• Development of new facilities for delivery to TGP, Transco, DTI, or Canada

13