Pipeline Coating Process

Embed Size (px)

Citation preview

  • 8/13/2019 Pipeline Coating Process

    1/34

  • 8/13/2019 Pipeline Coating Process

    2/34

    may not be achievable: in such case a technical query should be raised and agreed to.

    Reinforcement

    All reinforcement shall meet the minimum specified % cross sectional area (CSA)

    requirements .

    There are commonly two methods of reinforcement; rigid preformed cages

    (usually manufactured on site using Zublin machines) and wire mesh fabric.On occasions both methods are used simultaneously. (This usually occurs

    where high thickness concrete coatings are required).

    Zublin Machine

    Typical Zublin made Cage

    Where rigid preformed cage reinforcement is used, the cages are fitted tothe pipe prior to the concrete application process. Wire mesh fabric

    however, is wound into the concrete during the concrete application

    process. .

    Cage reinforcement shall normally be required to meet the requirements of

    BS 4482, BS4449 or ASTM A615/A615M using wire with typically

    diameters of 5 mm for longitudinal and 7-8 mm for circumferential.

    Welded wire fabric reinforcement shall normally be required to meet the

    requirements of ASTM A82 for zinc coated drawn wires, Typically one layer

    of wire is required for concrete thicknesses up to 55 mm above 55 mmconcrete thickness two layers minimum are required.

    Potable water

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    3/34

  • 8/13/2019 Pipeline Coating Process

    4/34

  • 8/13/2019 Pipeline Coating Process

    5/34

    Responsibilities:

    The Incoming Supervisor shall ensure that the incoming holiday detection, reinforcement

    installation, fitting of end rings and end plugs are performed correctly. He shall quarantine

    pipes that are in need of repair and supervise the repair operation. He is also responsible for

    ensuring that all tasks are conducted in the safest possible manner.

    The QC inspector/Auditor shall be responsible for the release or quarantining of the incoming

    pipe. He shall maintain checks in accordance with function described in an agreed inspection

    Test Plan (ITP)

    The tally man shall be responsible for maintain pipe traceability and recording the disposition

    of rejected and repair pipes.

    3.0 Mixing of Concrete

    Prior to concrete coating, the batch plant, cement hopper and water feed systems are

    calibrated to allow accurate percentages of constituent materials to be delivered to the mixer.

    Typical constituents of the concrete mix are cement, high-density iron ore, sand and water.

    The concrete mix design is dependent on the Specific Gravity of materials being used and is

    proportioned accordingly.

    Typical Batch Plant Calibration Tolerances

    Cement 2%

    Aggregates 3 %

    Water 2%

    Whole 3 %

    Sand/aggregates are typically transported from their respective stockpiles to the Mixing Plant

    hoppers using rubber tired front end loaders. From the feed hoppers the sand and aggregate

    are metered into the mixer at the mix design quantities. Cement is typically auger fed from

    the cement silo into a weigh hopper which weighs off the required amount to meet the mix

    design requirement.

    Note:where aggregates are stored in outside open areas the working face of the stockpiles

    should be regularly turned over to maintain even moisture mix in the material. It is

    inadvisable to take the material from the very bottom of stockpiles where moisture is likely to

    be exceptionally high,

    Typical Batch Plant feed System

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    6/34

    After weighing, the cement is added to the aggregate in the mixer. After a period of dry

    mixing, water is metered by volume into the mixer and the batch mixed for the prescribed

    mixing time. On completion of the mixing the concrete is conveyed to the short feed hopper.

    From the hopper the fresh mix is gravity fed onto a short belt which in turn progresses the

    mix to the concrete application head.

    Note:Regular samples of the fresh concrete mix shall be taken from the feed belt to enable

    moisture content and fresh analyses to be carried out. Also for mix control purposes fresh

    mix test cube specimens are prepared.

    Cube Making

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    7/34

    Cube Samples

    Responsibilities:

    The Batch Plant Supervisor shall be responsible for batch p lant calibration and operation. He

    is to ensure that the parameters set through batch plant calibration are maintained

    throughout production. conveying aggregates to and from the correct holding hoppers

    ensuring that the correct amount of water is added to the concrete mix to provide consistent

    moisture content of the mix. He shall also be responsible in ensuring that the task is

    conducted in the safest possible manner.

    The QC laboratory Technician shall be responsible for ensuring concrete mix calibrations are

    carried out correctly, taking samples of the concrete mix for analyzing and preparing samplesfor testing. He shall also be responsible for consistently reporting test results to the Batch

    Plant Supervisor, and for logging all test results.

    4.0 COATING PROCESS:

    From the impingement incoming rack or indexer, pipes are placed on the concrete coating

    line rotation buggy s using an overhead crane using a spreader bar and suitably protected

    hooks. On the rotating buggy s the pipes are transported past the impingement coating head

    where premixed concrete is applied at high velocity to the pipe using impingement rollers.

    The concrete plant operator selects the pipe rotation and forward travel speeds at a setting

    that allows for the concrete to be applied to the correct concrete coating thickness.

    Pipes with anodes fitted are coated as per a plain pipe with the exception that a shadow plate

    and plastic wrap covering the anode is utilized to prevent excessive concrete covering the

    anode. After processing the plastic wrap shall be removed and the outer surfaces of the

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    8/34

    Anodes shall be cleaned and be free of concrete coating materials.

    Diameter or thickness of the concrete coating is controlled by measurement using a girth or

    tree tape and is performed at the coating head and again verified at the weigh station.

    Note Where wire mesh fabric reinforcement is used, the wire fabric is fed from a spool

    tensioning arrangement then travels though guides and onto the rotating pipe as the pipe is

    being impinged.

    Welded Wire Fabric Feed

    5.0 CLEANING AND WEIGHING STATION

    Upon completion of the concrete coating, the pipe cutback areas are cleaned, the end plugs

    are removed and any debris in the pipe interior is also removed. The OD of the concrete is

    again measured: taking six equidistant measurements along the pipe.

    Taking Girth Measurements

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    9/34

    Note: The concrete ends shall be finished square to the pipe axis and the crown of the

    concrete shall be slightly rounded.

    When all redundant material has been removed from the coated pipe, the pipe is weighed

    using a calibrated weigh scale or load cell.

    Pipes that are out tolerances for thickness and or weight may be flash coated or scraped to

    enable correct tolerances to be achieved. This rectification process shall be carried out whilst

    the concrete is in a green state and only if agreed to by the client.

    At the cleaning station continuity (anode to pipe) and isolation (rebar to anode & pipe) and

    reinforcement position checks shall be performed on pipes in accordance with the agreed

    inspection frequency included in the Project inspection Test Plan (ITP)

    Reinforcement placement check

    Note : In the case where welded wire is used for reinforcement, the excess wire on the finish

    end of the pipe is trimmed back to just below the concrete surface to ensure no protrudingwire is on the concrete surface.

    Excess Wire Fabric

    When accepted the details of the pipe weight and girth measurements are entered into a pre

    programmed computer that determines the negative buoyancy (NB) of the pipe.

    A typical formula for NB calculation

    Weighing devices used to determine the weight of the concrete-coated joints shall be

    certified in writing to accuracy of 0.5%. The calibration of weighing equipment shall be

    Coating http://pipecoating.blogspot.com/

    34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    10/34

    checked by test weighing method previously approved by contractor unless other procedures

    have been agreed and confirmed in writing. Calibration of the weighing equipment shall be

    checked daily.

    The unsaturated (as applied) submerged weight per metre (N/m) for each pipe shall be

    calculated from the pipe weight in air immediately after coating.

    The submerged weight, W (N/linear metre), shall be calculated using the

    following formula:

    where:

    Mc = Mass of fresh concrete coated pipe including reinforcement kg

    Dc = Outer diameter concrete coated pipe m. Average of 6 girth measurements

    Ds = Outer diameter of steel pipe plus twice the anti-corrosion coating thickness, m

    P1 = Density of field joint filing materials (assume 1025 )

    I = Cutback of concrete coating from bevelled end, m

    L = Mill length of steel pipe, m

    Pw = Density of seawater (assume 1025 )

    SW = Submerged weight

    For anode and crack/buckle arrestor pipes, the specified maximum submerged weight may

    be exceeded. Variations in buoyancy shall be ignored and the submerged weight value shall

    be adjusted by using an increased weight in air. The Principal shall specify the allowable

    weight variations in the Scope of Work.

    The results shall be recorded and tabulated against pipe number and presented to the

    Principal at the completion of each day s production. The submerged weight of each coated

    pipe shall be within the acceptance tolerances stated by the Client in the Scope of Work.

    Responsibilities:

    The concrete plant supervisor is responsible for ensuring that all equipment and personnel

    are adequately organized to carry out concrete batching, placement of reinforcement,

    coating, repairing and checking all coating parameters. He is also responsible in ensuring

    that the task is conducted in the safest possible manner.

    The concrete plant operator is responsible for maintaining the correct mix design, travel and

    rotation speeds, placement of reinforcement, end rings and anode protection.

    The coating Tally man is responsible for recording the traceability of the coated pipes, the

    correct recording of pipe weights, pipe lengths, coating diameter, cutback lengths and

    submerged weight (NB) calculation. He will also keep an ongoing log of running (NB)

    averages.

    The QA inspector/Auditor is responsible for the correct calibration of the weigh scales (NB

    station), periodic checking of any repairs to anti corrosion coating, the concrete coatingparameters, including wash out checks of the reinforcement, overlaps for reinforcement and

    periodic isolation/continuity checks.

    6.0 CONCRETE CURING

    Submerged

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    11/34

    From the cleaning area acceptable coated pipes are lifted by overhead crane onto trucks

    having suitable cushioning and supports that protect the green concrete. The pipes are

    transported to the curing area where the freshly concrete coated pipes shall be laid out in

    single layers approximately 250 mm apart on suitable sand berms using either an overhead

    gantry or mobile crane.

    Pipes that are to be cured using the Fog Cure method shall be covered as soon as practical

    with a tarpaulin and fog water spray shall be introduced via water pipes fitted with fine

    misting nozzles under the covers to maintain a high humidity beneath the covers.

    The pipes shall remain in the cure bay until the concrete has achieved a minimum stacking

    strength of 14 Mpa (as determined by concrete cube strength testing). On completion of the

    curing process and prior to stacking the cutback end rings shall be removed and any

    concrete contamination shall be removed from the coating steel cutback and internal bore.

    Pipes selected for concrete coupon testing shall be clearly marked and placed on hold in an

    area suitable for coupon extraction work to be performed. Coupon holes shall be repaired in

    accordance with the approved Concrete Repair Procedure.

    Note:Test cube specimens taken from the fresh mix at the batch plant shall be placed in the

    curing bay and cured in a manner identical to the pipe.

    7.0 REPAIRS

    Repairs to the coatings shall be carried out in accordance with an approved Repair

    Procedure. Coated pipes that cannot be repaired shall be rejected, stripped and re coated.

    Unacceptable pipe shall be marked up with Red/White hazard tape and recorded on the NCR

    system.

    After the completion of acceptable repairs the pipe will then be placed in its allocated storage

    area. The stacking height for concrete coated pipes shall be in accordance with the approved

    handling procedure.

    Repairs on freshly applied concrete shall be carried out at the coating plant whenever

    appropriate or at the curing bay.

    Typical repair procedure

    Upon visual examination, concrete coatings that are damaged, are defective or do not meet

    with requirements shall be repaired. The circumstances of the damage or defects will dictate

    the appropriate method of repair.

    Repairs Criteria

    If the area is less than 0.8m in any 3 m length of pipe may be repaired by hand patching

    providing that such repairs are carried out within 4 hours of concrete application.

    If the area is more than 0.8m but less than 25% of total coating repairs shall be made usinggunite. The concrete remaining shall be undercut to provide a key lock.

    Cracks caused by excessive deflection in handling or storage, with the following criteria shall

    be repaired by chiseling the crack not less than 25mm and repair shall be made using the

    same basic material as the coating:-

    Cracks in excess of 5mm width and extend over 180 circumferential around the coated pipe.

    Cracks which are between 250mm 1000mm in length longitudinally along the coated with

    the addition that the ends of each crack shall be drilled with a hole of 10mm nominal

    diameter to prevent crack propagation. The bottom of these holes shall be 7 -10mm from the

    anti-corrosion coating.

    Cracks extending halfway through the concrete or penetrated to the cage

    Longitudinal surface cracks of any width and less than 250mm in length shall not be

    considered a defect but holes of 10mm nominal diameter shall be drilled at the crack tips to

    prevent crack propagation. The bottom of these holes shall be 7 -10mm from the

    anti-corrosion coating.

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    12/34

    Surface damage shall not be considered a defect if :-

    The total surface area of damage per pipe is less than 0.1 m, and

    Max depth does not exceed 20% of coating thicknesses, and

    The remaining concrete is sound.

    Damage at the ends of the concrete coating need not be repaired provided that the damaged

    area is less than one third of the circumference for a length less than 200 mm.

    Hand Repairs

    Damaged areas may be repaired by hand patching in its green concrete state. Patching

    shall be carried out by removing the defective area down to underneath the reinforcement

    and undercutting the sides to form a key. The cavity formed shall be filled with a mix similar

    to that used in the coating process with the addition of just sufficient water to allow hand

    application. Polythene wrap shall be used to seal the repair before curing. Maximum

    allowable time between concrete coating and repair of green pipe will be 4 hours.

    Core Holes

    Prior to filling cores holes, each site will be inspected for damage to the anti-corrosion

    coating. Damage to this coating will be brought to the attention of QC personnel and the

    Customer. Core holes shall be repaired using concrete with the same proportion of

    constituents as the original coating.

    Core holes may also be repaired using concrete repair material Mapegrout Fast-Set

    (manufactured by Mapei) or Certite or similar product. A slight increase in water content

    may be considered acceptable to aid cure for some of the materials. The material shall be

    trowelled in such that the surface level is continuous with the level of the existing coating

    around the repair.

    Gunite Repair Criteria

    Repair on cured concrete coating and large repair areas shall be rectified using the gunite

    method of repair. The size of the gunite repairs shall be demonstrated and witnessed for

    suitability as an addendum to the Pre qualification trials for concrete coating. The concrete

    mix design used for gunite repairs will be of the same constituent make up as that of theparent mix material apart from the use of extra water to assist with the application. Curing of

    the repairs will be carried out by wrap sealing of polyethylene membrane.

    Gunite Repairs

    GREEN CONCRETE

    Damaged or defective areas shall be prepared by undercutting and exposing the

    reinforcement throughout the damaged area and removing any loose concrete material. The

    area shall then be filled by Gunite application until the entire repair area is reinstated to the

    level of the parent material. The completed repair shall be dressed in a manner that allows a

    smooth transition to the parent material. Within 30 minutes of the repair completion the green

    concrete coated pipe shall be placed in the fog cure.

    CURED CONCRETE

    Shall be performed as that for green repairs with the addition of a water wetting application to

    the cured concrete coating interfaces prior to Guniting. The repair area shall have a curing

    membrane tightly affixed and shall stay in place for a minimum of 48 hours to allow sufficient

    cure.

    Testing

    Repair materials used for concrete repairs shall be tested for compressive strength as

    determined by 28 day cube strength results. The minimum strength to be achieved shall bethat of the strength specified for the parent coating. The frequency of testing shall be at

    start-up, middle and end of project.

    Responsibility

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    13/34

    The repair foreman shall be responsible for coating repairs and shall ensure the correct

    equipment and repair method is used for coating repair. He shall also be responsible in

    ensuring that the task is conducted in the safest possible manner.

    QC, Inspector/auditor shall be responsible for checking the preparation and the completed

    repair.

    All repairs are to be recorded and inspected for compliance to the repair method statements.

    8.0 PIPE MARKING AND IDENTIFICATIONThe identity of each pipe shall be established and entered into the pipe tracking system such

    that traceability is maintained. Accepted pipes will be released for transportation to the

    stockpiles or other processes.

    Typical Marking Requirements

    Pipe no

    Length

    WT

    Heat no.

    Date of coating

    Responsibilities

    Load out Tally man, shall ensure that the correct pipe markings are applied in accordance

    with the agreed marking system. He shall also be responsible in ensuring that the task is

    conducted in the safest possible manner.

    QC, Inspector/Auditor shall be responsible for inspecting that the correct colour banding and

    markings are applied.

    9.0 SACRIFICIAL ANODE INSTALLATION

    Anode are typically fitted to the corrosion coated pipe prior to caging and concrete coating,

    however in some circumstances anodes can be retro fi tted i.e. after concrete coating.

    Process Description

    The Coated line pipe shall be positioned on the support racks, over the

    anode lifting saddle. The pipe will be positioned until the longitudinal seam

    weld (if any) is located around either the 12 or 6 o'clock position or

    approximately 150mm of the weld seam. Once positioned the lifting saddle

    will raise the lower half shell of anode to the stationary pipe and hold it in

    position. The second half shell of anode shall be offered to the pipe and

    positioned over the first half shell, by means of crane jib. The two halvesshall be carefully aligned and drawn tightly together using webbing

    tensioners, chain come-along or similar.

    The centering of the anode along the pipe shall be in a manner that allows

    for casing segments to be fed onto the pipes.

    Fit Up

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    14/34

    Electrode Handling

    Fillet Welding

    Welding will be by metal arc process

    Fillet welding shall be carried out continuously around three edges of the

    overlapping straps of the anode halves. An insulating material shall be

    placed under the weld area to guard against heat damage to the anti

    corrosion coating.

    Thermit Weld

    Fillet Weld

    Welding consumables will be SMAW electrodes for carbon steel.

    Electrodes shall be baked for 2 hours at 325oC and held at 150

    oC in a

    suitable holding oven prior to use. Alternatively, follow manufactures

    instructions. The Welder shall keep electrodes in an approved quiver during

    use and return unused electrodes to the holding oven when not working.

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    15/34

    Pipe Preparation:

    Areas of anti corrosion (TLPE) coating are be removed within each gap

    between half shells, each area of removal shall be as small as practical to

    accommodate the Thermit Graphite Mould

    The removal of coating shall be achieved by using a heated knife and / or a

    bolster type chisel cutting around the heated area that is to be stripped,following the removal of the coating the steel substrate shall be power

    ground to achieve a bright, clean roughened surface or St 3.

    Connecting of Bonding Leads (Electrical Connection):

    Each anode is normally manufactured complete with bonding leads; the

    bonding leads may be cut to size using a cable cutter or hacksaw to

    remove. The cable should be looped (pig tailed) so as not to be taut after

    welding.

    The end 25mm of PVC/PE sheathing is stripped back to expose clean

    copper cable. The cable may be cleaned with a wire brush if required.

    Cad welding process as follows:

    Clean the conductors and position them in the well dry mould;

    Place the metal retaining disc in the bottom of the crucible graphite mould;

    Pour the welding metal powder into the graphite crucible, spread starting

    powder onto the graphite mould edge;

    Open the mould lid and ignite the welding powder using a flint gun by firing

    the spark onto the starting powder;

    The exothermic welding process takes place inside the graphite mould; and

    finally the exothermic connection is finished.

    Clean the mould using scraper and brush and proceed to the next

    connection cable(s) ready for connection.

    After welding, each completed weld shall be tested for electrical continuity

    and mechanical bonding strength (1 blow with a 1 Kg Hammer)

    Electrical Continuity using Ohm meter

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    16/34

    Anti corrosion Coating:

    Subsequent to the satisfactory completion of anode installation, the

    anti-corrosion coating shall be reinstated as follows:

    The exposed areas of steel substrate around the Cad weld and anode

    straps shall be wire brushed to a clean finish. All bare steel shall then be

    coated using SOLVENTLESS2 PACK EPOXY or other approved repair

    material.

    Anode Completion:

    After final inspection, the Anode completion procedure will be carried out,

    consisting of the infilling of the gaps between anode halves with either a

    gunite concrete or hot poured marine mastic method.

    The reinforcement used during concrete coating shall be trimmed back from

    the edges of anode allowing a 25- 50mm gap. Electrical continuity test

    shall be carried out to ensure that the reinforcement is electrically isolated

    from the anode/pipe.

    The gaps between the anode and the parent concrete weight coating

    shall in filled with either a concrete mix similar to that of the parent coating

    material (by hand or gunite method) Or by other approved in fill methods

    (for example moulded hot bitumen) On completion a continuity check

    between Anode and the steel pipe shall be performed prior to moving the

    pipe to storage.

    Inspection control:

    Pre-qualification

    The anode installation procedure and inspection shall be pre-qualified prior

    to the start of production.

    The pre-qualification will be limited to anode closure (strap) and Cad welds.

    Weld / Welder Qualification

    Typically each welder shall perform one fillet weld on a test coupon

    sometimes supplied by client. The test coupon shall be macro sectioned

    and tested for hardness.

    All required tests shall be carried out and reported by credited 3

    rd

    PartyInspection Laboratory.

    Thermit Weld Qualification

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    17/34

    The test welds and coupons shall be sectioned and tested for copper penetration by a third

    party inspection house

    Hardness shall not exceed 248 Hv10 when taken at 2mm intervals extending to 10mm either

    side of the extreme edges of the weld.

    No cracks or penetration of alloying elements along grain boundaries by more than 0.5mm or

    any non-metallic inclusions will be detected at 200X magnification.

    10.0 OFFLINE TESTING

    Specific Density

    Sieve Analysis

    Moisture Content

    Deleterious Substances

    Fresh Analysis

    Water Absorption

    Compressive Strength Cubes

    Compressive Strength Cores

    Impact Test

    Shear Test

    ---------------------------------------------------------------------------------------------------------------------------

    -------

    SPECIFIC GRAVITY - BS 812: part 2 1985

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    Determination of the Specific Gravity (SG) of Aggregate/Iron Ore

    Equipment

    Pycnometer

    Electronic balanceGas ring or oven

    Procedure

    Obtain a sample weighing approximately 2000 grams.Thoroughly wash the sample to

    Typically each production welding operative will be qualified by

    demonstrating their capability to perform a series of Thermit welds on a

    coupon sample. Each weld shall be mechanically tested by a single blow

    from a 1kg hammer, aimed at 90 degrees to the sample surface - no lifting

    or fracturing shall result. Electrical continuity test shall be carried out

    between pipe and anode

    The macro sectioned and hardness and penetration tests reports will be

    identified by coupon unique numbers. Test results should meet the

    following:

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    18/34

    remove all material finer than No. 200 Sieve (75micron).Dry the retained sample over the gas

    ring (or oven) and then allow it to cool to room (ambient) temperature.

    Place 500 g of dry aggregate (Weight, A) into the Pycnometer and fill it with water. Whilst

    filling rotate the Pycnometer to eliminate all traces of trapped air within the sample material

    and allow settling. After settling, top up the Pycnometer with water again to remove any froth

    from the surface so that the water level in the hole at the to of the cone is flat and level. Dry

    the exterior of the Pycnometer and weigh (Weight, C).

    Empty all the contents of the Pycnometer into a tray, making sure that the aggregate is

    completely emptied. Refill the Pycnometer to the original level with water (only), dry the

    exterior and weigh (Weight, B).

    The difference in water temperature between the first and second weighing shall not exceed

    2C.

    Carry out the test twice.

    Evaluation

    Calculate the Specific Gravity of the aggregate as follows:

    Specific Gravity (SG) = Weight A / ((Weight A + Weight B) Weight C))

    Report

    Record Specific Gravity

    ---------------------------------------------------------------------------------------------------------------------------

    --

    SIEVE ANALYSIS (GRADATION) OF AGGREGATES - ASTM C 33

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    19/34

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    To establish a Sieve Analysis (Gradation) of aggregates using interlocking, circular sieves of

    standard aperture sizes

    .

    Equipment

    Nest of certified sieves

    Sieve shaker

    Calibrated weigh scale

    Oven or gas ring

    Sampling box

    Oven trays

    Plastic bucket

    Sampling scoop

    Procedure

    A representative sample of material to be analyzed shall be taken in a proper sapling

    method. The sample shall be at least 1500 grams.

    The sample shall be weighed and the weight recorded. After weighing the sample shall be

    oven or gas ring dried making sure that none of the sample is spilt from the heating tray.

    After drying the sample shall be passed through a set of known mesh size sieves, making

    sure that all the sample is removed from the heating tray. The sieves shall be interlocked in

    order of aperture size, starting with the larges mesh size at the top.

    The interlocking sieves (including bottom pan) shall be agitated sufficiently (normally with the

    aid of mechanical vibrator/shaker) for a period of time (usually 4 minutes minimum), to

    ensure that the material has completely passed through the respective grade sizes.

    The aggregate which is retained in each of the sieves and the bottom pan are then

    individually accurately weighed and the weights recorded.

    Calculations

    After the mass of aggregate retained on each sieve and in the receiver has been determined,

    calculations are then carried out. Note that mass retained and mass passing on each sieve

    are recorded and percentage passing is eventually calculated from the obtained results.

    Visual representation of the particle size distribution is carried out be means of gradation

    graph showing the sieve aperture size against the percentage passing that particular sieve

    size.

    Due to the relative values of the aperture size, it is convenient to plot them to a logarithmic

    scale.On completion of plotting, the points of the plot are joined together with straight lines resulting

    in a graph that is termed the gradation curve.

    Evaluation of results

    The obtained grading curve should be within the envelope limits drawn by the applicator and

    approved by the client and/or limits extracted from the ASTM C33 Standard.

    Report

    The type of aggregate

    Results and percentages calculate

    Sieve Analysis

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    20/34

    ---------------------------------------------------------------------------------------------------------------------

    MOISTURE CONTENT OF AGGREGATES

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    Determination of the mass of water in an aggregate, expressed as a percentage of the mass

    of the oven-dry, sample material.

    Equipment The moisture content can be determined by any one of two methods.

    An oven or gas ring

    A calibrated weigh scale

    Oven pan

    Speedy moisture content tester (alternative method)

    Procedure & Calculation (oven/gas ring dried method)

    The sample is weighed, and then, after being oven- dried, it is re-weighed. Weigh the

    masses before and after drying W1 and W2, respectively, then:Moisture content, % = (W1 W2) / W2 x 100

    Use of Speedymoisture content tester (use only in case of accelerated test)

    This is a proprietary device whose action is based on the very rapid absorption of water by

    calcium carbide. Standardized quantities of aggregate and calcium carbide are mixed by a

    standard procedure in a hand-held, sealed pressure vessel. Acetylene gas is formed by the

    action of the moisture on the calcium carbide, and the pressure of the gas is related to the

    quantity of moisture. The vessel is fitted with a pressure gauge calibrated to give a direct

    reading of the moisture content.

    Note :This test is unsuitable for larger sizes of coarse aggregate.

    Report

    Moisture Content in %

    Moisture Content

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    21/34

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    22/34

    -----------------------------------------------------------------------------------------------------------------------

    DELETERIOUS SUBSTANCE IN AGGREGATES - ASTM C40-92

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    To determine the organic impurities, including silt and clay in the aggregates

    Apparatus

    Glass bottle, 500ml

    Sodium hydroxide solution, 3% NaOH

    Reference color standards

    Procedure (extract from ASTM C40-92)

    Preparation of solution :

    Dissolve reagent grade potassium dichromate (K2Cr207) in concentrated sulfuric acid (SG

    1.84) at the rate of 0.250 g/ml of acid. The solution must be freshly made for the color

    comparison by gently heating, if necessary, to effect solution

    .

    Fill a glass bottle to the 130ml level with sample of aggregate to be tested.and add the 3%

    NaOH solution into the bottle until the volume of the aggregate and liquid after shaking is

    about 200ml.

    Cork the bottle, shake it vigorously and allow it to stand for 24 hours.afterward fill a fresh

    glass bottle to the 75ml level with reference standard color solution prepared not more than 2

    hours earlier per the preparation procedure described in Sub-clause B.3.1

    Compare the color of the supernatant liquid of the test sample with that of the reference color

    solution.

    Record the color comparison result to that of the reference standard, e.g. lighter, darker or

    same color.

    Evaluation

    If the color of the supernatant liquid is darker than that of the referenced standard, the

    aggregate tested is considered to contain possible traces of injurious organic compounds. As

    such perform further tests.

    Report

    Record

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    23/34

    Deleterious Substances

    --------------------------------------------------------------------------------------------------------------------------

    FRESH ANALYSIS

    Note:This practice may be modified by the requirements of the customer s specification,

    see relevant Project Inspection Test Plan (ITP)

    Scope

    To verify W/C ratio, cement and aggregate content of the concrete mix. This procedure

    applies to fresh concrete coating drawn from the batching mixer or feed conveyor to the

    application head.

    Equipment

    Set of test sieves

    Mechanical sieve shaker

    Calibrated Electronic balance to an accuracy of 1.0g

    Gas ring (to accelerate drying)

    BucketGunny sacks

    Procedure

    Prior to carrying out a mix analysis, it is necessary to carry out a gradation on a

    representative sample of each aggregate used in the concrete. It is also necessary to know

    the nominal mix design in percentage terms.

    Obtain a representative sample of at least 2kg of freshly mixed concrete from the feed belt,

    place in a suitable bucket , cover the bucket with a damp gunny sack and immediately

    transfer the sample to the laboratory. This test shall be carried out without any delays.

    Weigh a 500g sample into a tray and determine the moisture content of the sample.

    Weigh a further 1,000g into a 150 micron sieve. Wash this sample carefully under a gentle

    flow of clean water until the water draining from the sieve is clean and clear. Be very careful

    to ensure that no material spills over the side of the sieve.

    When washing is complete, transfer the cleaned sample onto a tray, using a further quantity

    of clean water to wash all traces of material out of the sieve and into the tray. Carefully drain

    off excess water, making sure that no material is lost in the process.

    Place the tray over a burner and dry it thoroughly. Ensure that the rate of drying is gentle

    enough to prevent material being ejected from the tray as the water vaporises, or alternately

    cover the tray with an identical tray to trap any ejected material.

    Once the sample is completely dry, remove from the heat and allow it to cool before

    transferring to the sieve stack.

    When the sample has been placed into the sieve stack close the sieve stack securely and

    operate the shaker for five minutes. Remove the stack from the shaker. Carefully separate

    the nested sieves and weigh and record the amount of material retained on each sieve,

    ignoring the contents (if any) in the sieve pan.

    Input the weights into the pre formatted calculation spreadsheet, or alternatively write by

    hand on a blank fresh mix analysis form. For manual calculation, the procedure is as follows:

    Record the weight on each sieve in turn

    Determine the cumulative weight retained on each sieve by adding the weights of all

    previous sieves in the stackDetermine the dry weight of the 1,000g sample used for each sieve

    Calculate the cumulative weight retained as a percentage of the sample dry weight

    For each sieve, calculate the percentage of the dry weight passing that sieve by subtracting

    the value from the previous step from 100%

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    24/34

    The preformatted spreadsheet automatically calculates the mix ratios. To do this manually,

    the following procedure is used:

    Determine the weight of fines ( < 150 micron) particles of each aggregate in the mix sample

    by multiplying the percentage of that aggregate passing the 150 micron sieve (from the

    aggregate gradation) by the percentage of that aggregate in the mix by the dry weight of the

    fresh mix sample.

    Example: If 15% of the sand passes the 150 micron sieve in the sand gradation, and the mix

    design incorporates 20% sand, and the fresh mix sample weighs 1,000g with a moisture

    content of 6%, then the weight of sand fines in the sample is:-

    15% x 20% x (1,000 x 94%), or 0.15 x 0.2 x 1000 x 0.94 = 28.2g

    Repeat this step for each aggregate, and total the weights determined in this way. This

    gives the total weight of fines in the fresh mix sample.

    From the fresh mix gradation, calculate the total weight passing the 150 micron sieve by

    subtracting the cumulative weight retained on that sieve from the dry weight of the sample.

    This is the apparent weight of cement in the sample.

    Note, this weight will include fine particles of aggregate. Subtract from it the total fines

    weight calculated previously. The result is the corrected weight of cement.

    Subtract the corrected weight of cement from the dry weight of the mix sample. The result

    is the corrected weight of aggregate.

    Determine the weight of water in the sample by multiplying the sample wet weight by the

    moisture content.

    The water to cement ratio is given by dividing the weight of water by the corrected weight

    of cement.

    The aggregate to cement ratio is given by dividing the corrected weight of aggregate by the

    corrected weight of cement.

    Report

    Record

    Fresh Analysis

    Fresh Analysis

    -----------------------------------------------------------------------------------------------------------------------

    CONCRETE DENSITY

    Note:This practice may be modified by the requirements of the customer s specification, seerelevant Project Inspection Test Plan (ITP)

    Scope

    To determine concrete density on removed samples (coupons or cores) removed from a

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    25/34

    concrete coating.

    Equipment

    Balance sensitive to 1.0g

    Container suitable for transporting coupons to lab/cure bay

    Core drilling equipment (core sampling)

    Hand tools to assist in removal of samples

    Wire cutters (coupon sampling)

    Test specimen

    Draw specimen (coupon) at production line taken immediately after coating or from a cure

    pipe (core) dependant on the agreed method of sampling.

    Procedure (coupon method)

    Brush the sample with a fine bristle brush to remove all loose particles from the sample

    surface.

    Weigh sample and record as Weight A.

    Transfer the sample to pipe curing bay with the pipe and allow the sample to cure for the

    same period of time as of the coated pipe (a minimum of four (4) days). Sample may also be

    oven dried to the constant weight.

    Procedure (coupon and core)

    After cure immerse sample in seawater filled tank at room temperature for not less than 24

    hours. Draw sample from tank, let it surface dry or remove excess surface moisture, weigh

    and record as Weight B.

    Suspend the sample from a wire and weigh it in water and record as Weight C (this is to

    check bulk density of concrete).

    With the weights determined in accordance with the above procedures, calculate the

    following:

    a) Water absorption after Immersion, % = (B A) / A x 100

    b) Density (Air- dry), Kg/m3 = A / (A C)

    c) Density (Saturated), Kg/m3 = B / (B C)

    Report

    Record

    Sample ID

    Concrete coating date

    Sample type

    Calculation and results

    Density

    Density Test

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    26/34

    ------------------------------------------------------------------------------------------------------------------------

    COMPRESSIVE STRENGTH OF CUBES

    Note:This practice may be modified by the requirements of the customer s specification,

    see relevant Project Inspection Test Plan (ITP)

    Scope

    Preparation and testing samples of concrete for compressive strength properties using the

    cube mold method of sampling.

    Equipment

    100mm Cube Molds

    Trowel

    Bucket or Container

    Vibrating hammer complete with square face (50mm x 50mm) tamping foot

    Calibrated Compression Testing Machine.

    Procedure

    Draw concrete samples of the production working mix from the conveyor during transfer of

    concrete from the mixer to the application head. Ensure that only freshly mixed concrete is

    used for the sampling.

    Place sample material in a bucket and over the bucket with a moist gunnysack to prevent

    premature dehydration of the sample.

    Prepare the required amount of cubes required for each sampling period plus two extra

    cubes to used as spares. Make the test cubes as soon as practicable after sampling to avoid

    dehydration.

    Fill each test cube mold with concrete in three layers of 50mm. Compact each layer until

    refusal using a vibrating hammer equipped with a square faced tamping foot attachment.

    On completion of compacting the topmost layer of the sample the surface shall be prepared

    level with the top edges of the mold using a square edged trowel. Each sample shall be

    marked with it s ID and sample number. Also for day night operations the ID should include

    the letters D/S or N/S

    Curing of sample

    Immediately after the sample preparation, cover the molds with a moist gunny sack and

    place the cubes in the fog cure. Check closely that an uninterrupted moist condition exist

    throughout the curing period.

    After overnight curing, the mold screws are loosened, the mold dismantled and cube sample

    is carefully removed and placed in a water tank. The samples shall remain saturated until

    required for crushing.

    Note :ensure that before placing the samples in the water tank that a correct, legible ID

    exists on each sample

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    27/34

    Compression Testing

    The testing machine shall be capable of applying load manually or automatically at the

    specified rate uniformly without shock. It should be annually (or anytime when anomalies in

    the results are

    observed) be calibrated and certified by 3rd

    Party Certifying Agency for compliance.

    Prior to testing each sample shall be weighed (in saturated state), in kilograms.The

    dimensions of the samples shall be measurement in mm.

    Determine the density of each test cube either by obtained weight over cube measure or by

    water displacement method.

    After weights, measurements and densities have been determined the test cube shall be

    placed between the testing machine platens ensuring that all bearing surfaces of the testing

    machine platens and the sample are wiped free of any debris.

    Carefully center the cube on the lower platen, ascertaining that load will be applied to the two

    opposite cast faces of the cube in a correct and even manner.

    Without shock, apply and increase the load continuously at a nominal rate within the range of

    0.2 - 0.4N/mm per second until no greater load can be sustained.

    Record the maximum load applied to the cube.

    Calculation and expression of the results

    Calculate the cross-sectional area of the cube face f rom the checked nominal or measured

    dimensions.

    Calculate the compressive strength of each cube by dividing the maximum load by the cross-

    sectional area of cube.

    Express the results to the nearest 0.5N/mm2 or any otherwise agreed units.

    Report

    RecordConcrete Compressive Strength (Cube Sample)

    NOTE : The drawing and Test on drilled CORES is in accordance with BS1881Part 120.

    Cube: Core Compressive Strength Correlation (if required) is carried out by this standard

    Compressive Strength Cubes

    --------------------------------------------------------------------------------------------------------------------------

    COMPRESSIVE STRENGTH OF CORES - BS1881

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    Preparation and testing samples of concrete coating for compressive strength properties

    using the extracted core method of sampling.

    Equipment

    Core drill, support stand and correctly sized core bits

    Calibrated Compression Testing Machine.

    Facing saw

    External calipers

    Acetate film

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    28/34

    Capping compound

    Bucket, Container or plastic bags

    Water & Power source

    Procedure

    Pipes selected during production for core sampling shall be clearly marked CORE TEST

    and the pipe number and date coated shall be entered into the laboratory LOG

    After a curing period (minimum 48 hrs) the core test pipe shall be located in the designated

    area for core drilling. The core drilling equipment shall be checked for good working condition

    and properly connected to the power source. The core drill bit shall be of a size that will allow

    35 45 mm diameter cores to be removed. Core diameters shall remain constant throughout

    the project. Only suitably qualified/trained operators shall perform core drilling.

    The core drilling rig shall be firmly located on top of the pipe ( 90) and the core drilled in a

    downward direction. Whilst drilling, water shall be used to lubricate the drilling bit and the

    core rig shall be fitted with a positive stop system to ensure the core bit does not exceed the

    limitation of penetration (being 7 mm from the PE coating). Core samples shall NOT betaken from the end 300 mm of the concrete coating.

    On completion of drilling, the core drill, including core shall be carefully removed from the

    concrete coating. The core sample shall then be carefully removed from the drill bit. When

    removed, all cores from the test pipe shall have a band of electrical tape fastened around

    them on which the pipe number shall be marked using a ball point pen. The cores shall be

    placed in unique plastic bag for each test pipe. DO NOT MIX CORES FROM OTHER TEST

    PIPES. The bag containing the cores shall also be clearly marked with the test pipe number.

    When received at the laboratory the cores shall be removed from their respective bags and

    checked for condition and quantity. If more cores are required, advise the core man as soon

    as possible. All cores are to be trimmed and left to dry for 24 hours. When dry, the cores shall

    be capped (apart from cores that will be used for density and water absorption tests). These

    cores will be capped later. When capped, each core top cap shall be identified with the date

    coated and with the letters D (day) or N (night) and placed into the storage tank with the

    identification facing upward. The same procedure will apply to density and water absorption

    samples after tests are complete. Cores will be stored in a water tank maintained at 23

    2C.

    Crushing

    Specimens shall be removed from the curing tank and shall be in saturated condition when

    tested, ideally removed from the tank approximately 30 minutes prior to crushing.

    Select appropriate testing machine platens to suit anticipated compressive force. Clean

    platen surfaces and ensure absence of extraneous matter. The core-seating rig (if required),

    fabricated in accordance with BS 1881, is placed in the centre of the location circle and thecores inserted.

    Apply the load, without shock, at a nominal loading of 0.2 N/mm2/sec. - 0.4 N/mm2/sec. at a

    constant rate for cores. Observe the fast advance and ensure seat correctly on the

    apparatus. Operate the controls as failure is approached to maintain load rate(s) above as far

    as practicable. When failure occurs the maximum load applied shall be recorded.

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    29/34

    Report

    Record

    The specimen ID

    Pipe number

    Compressive strength to the nearest 0.5 MPa

    Core Samples

    Core crushing

    ---------------------------------------------------------------------------------------------------------------------------

    WATER ABSORPTION

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    Determination of water absorption on sample removed from concrete coating (coupon or core)

    Determination of water absorption using a fully coated concrete pipe (full-scale method)

    Equipment

    TestSample

    Calibrated Balance

    Container suitable for immersing sample

    Fresh concrete sample (at least 500 grams)

    Full Scale

    Calibrated weighbridge or load cell

    Suitable water tank

    Crane

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    30/34

    Procedure (Sample testing)

    Brush the removed sample (coupon or core) with a fine bristle brush to remove all loose

    particles

    from the sample surface.Weigh dry sample and record as Weight A.

    Transfer the sample (coupon) to pipe curing bay with the pipe and allow curing for the

    same period of time as the coated pipe.

    Immerse sample in seawater tank at room temperature for not less than 24 hours. Remove

    the sample from the tank, let it surface dry or remove excess surface moisture before

    weighing and record as Weight B.

    Suspend the sample from a wire and weigh it in water and record as Weight C (this is to check

    bulk density of concrete).

    Calculate the water absorption of the sample as follows:

    a) Absorption after Immersion, % = (B A) / A x 100

    Calculate the bulk density as follows:

    b) Bulk Density (Air- dry), Kg/m3 = A / (A C) IF REQUIREDc) Bulk Density (Saturated), Kg/m3= B / (B C) .. IF REQUIRED

    Procedure (Full scale method)

    Weigh a fully concrete coated pipe that has been cured record as weight A.

    Place the pipe in a water tank filled with seawater at room temperature, if fresh water is used

    a

    calculation between sea and fresh water shall be used in the calculation process.

    Allow the concrete to fully saturate, normally 24 hrs

    After 24 hrs remove the pipe from the water tank and allow all free water to drain off. Weigh

    the

    pipe and record as weight B

    Calculate the water absorption of the concrete coated pipe as follows;

    Absorption after Immersion, % = (B A) / A x 100

    Report

    Record

    Sample(coupon)

    Full scale water immersion

    Water Absorption sample

    Water Absorption test

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    31/34

    -------------------------------------------------------------------------------------------------------------------------

    IMPACT TESTING OF CONCRETE

    Note:This practice may be modified by the requirements of the customer s specification, see

    relevant Project Inspection Test Plan (ITP)

    Scope

    This procedure applies to concrete coated pipe subjected to repeated Impact simulating the

    pipe movement during transportation and handling at lay barge during installation. It is

    carried out to determine concrete integrity when subjected to high impact energy.

    Equipment

    Impact testing rig

    Test Pipe with concrete coating

    Timer

    Tape measure

    Striker edge: 10mm radius

    Hammer Weight 2,680 Kg and/or 1,840 Kg

    Camera

    Procedure

    The test shall be carried out 90 to pipe axis at one location.

    The test shall be supported with a minimum of 2M concrete sections on either side of the

    section under test. Impact blows (5 times) shall be directed on the same location. Hammer

    should have a vertical drop of 660mm giving a velocity of impact of 3.60 m/second (7 Knots).

    After each impact a photograph of the impact area shall be taken together with a sketch of

    spalled areas including dimensions of cracks (length and width).

    Acceptance criteria:- Typically

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    32/34

    The anti- corrosion coating shall not be visible after impact (5 blows).

    Spalling has not occurred further than 300mm from the impact location.

    Report

    Record

    Impact Testing of Concrete

    Impact Test Rig Drawing

    ---------------------------------------------------------------------------------------------------------------------------

    SHEAR TEST OF CONCRETE

    Note:This practice may be modified by the requirements of the customer s specification,

    see relevant Project Inspection Test Plan (ITP)

    Scope

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    33/34

    To evaluate the inter facial shear strength between the anti-corrosion and concrete coating

    applied to a pipe.

    Equipment (typical)

    200MT Hydraulic Jack complete with pressure gauge

    Supporting fixtures (design to suit testing set-up)

    Measuring gauge for displacement of upper platen

    Calibrated dial gauge

    Procedure

    A pre prepared coated section of pipe shall be selected having concrete pipe sections of

    minimum of 500mm test length. The preferred maturity of the coating is a minimum 7-days

    after coating.

    Oxy cut from a cured concrete coated pipe approximately 900mm concrete coated test pipe.

    Cut only one test piece from each individual coated pipe. Alternatively, pipe can be coated

    partly at a section length of 0.50 to 0.90 meter located at one end of pipe (proximity to

    cutback). This is depending on what fixture is available from the time of carrying out test.

    After having cut the test piece, prepare the cross-sectional surface of the concrete at one end

    so that it is near perpendicular to the axis along the piece length.

    Carefully center the test piece on the lower platen of the Hydraulic Jack (Compression

    machine) unit with the concrete section supported by the appropriate supporting fixtures.

    Then slowly lower the top platen to just touching the steel pipe end. Without shock, apply and

    increase the load continuously at a nominal rate within the range of 0.2N/mm2 per second

    until no greater load can be sustained.

    Record the maximum load applied and calculate the surface area (SA) of the anti- corrosion

    coating surface as follows:

    Surface area, mm2 = 3.1416 x d x L

    Where,

    d = Pipe OD + anti-corrosion coating thickness

    L = Length of concrete coating

    Minimum required load (Kg-f) = 0.17N/mm2 x SA / 9.81

    Report

    Record

    Shear Testing results

    Shear Bond Test

    Coating http://pipecoating.blogspot.com/

    f 34 12/12/2013 5:28 PM

  • 8/13/2019 Pipeline Coating Process

    34/34

    Subscribe to: Posts (Atom)

    Posted by OZZIE GRIFFIN at 4:08 AM 4 comments:

    Labels: Pipecoating Part 3

    IF YOU ARE A LOTTERY PLAYER VISIT MY URL SIXFROMSIX. COM

    IT"S A WINNER

    Home

    Pages

    Awesome Inc. template. Powered by Blogger.

    Coating http://pipecoating.blogspot.com/