Pilot DSM Projects
March , 20112nd Dec, 2013
Confidential Slide 2
Presentation Flow
Overview of R-Infra Mumbai Distribution Business
DSM Pilots
- Objectives
- Designing DSM Programs
- Promotion of DSM
- Various RInfra DSM Programs
Process & Response
Confidential Slide 3
Overview of R-Infra, Mumbai Distribution Business
Confidential Slide 4
NORTHZONE
CENTRALZONE
SOUTH CENTRAL
ZONE
BHAYANDAR
KANDIVLIOFFICE
MALAD
GOREGAON
JOGESHWARI
VILEPARLE
SANTACRUZ
KHAR
BANDRA
DINDOSHIOFFICE
KANDIVLI
MIRA ROAD
DAHISAR
BORIVALI
SOUTH ZONE
ANDHERI
SANTACRUZ
OFFICE
TO
DADA
R
MANKHURD
EAST ZONE
TILAK NAGAROFFICE
GHATKOPAR
CHEMBURGOVANDI
VIKHROLI
NORTHZONE
CENTRALZONE
SOUTH CENTRAL
ZONE
BHAYANDAR
KANDIVLIOFFICE
MALAD
GOREGAON
JOGESHWARI
VILEPARLE
SANTACRUZ
KHAR
BANDRA
DINDOSHIOFFICE
KANDIVLI
MIRA ROAD
DAHISAR
BORIVALI
SOUTH ZONE
ANDHERI
SANTACRUZ
OFFICE
TO
DADA
R
MANKHURD
EAST ZONE
TILAK NAGAROFFICE
GHATKOPAR
CHEMBURGOVANDI
VIKHROLI
Overview – R-Infra Mumbai Distribution Business
Distribution Area 400 Sq. km*
No. of Customers ~2.9 Million
Max. System Demand 1,697 MVA
Sale 7,448 MU’s
T&D Loss ~9 %
Reliability Index 99.98 %
Power Transformers 3,012 MVA
Substations 4,554 MVA
Figures till Aug 2013
* Inclusive of addition of 2 villages
Serving Mumbaikars since last 85 Years
Confidential Slide 5
RInfra Management Commitment
Confidential Slide 6
Earth Hr. Celebration
EE&EC-Offices and Quarters
APFC Installation
EE Technology pilots
SEMS, Light pipe etc
Solar PV plant
Biogas plant
Practice
2
I will, Mumbai will
Educate
Knowledge Forum
Energy Conservation Day/week
Celebration
Let’s Turn Around Campaign
EE&EC Awareness via
e-Newsletter, Bill etc
Urja Samvardhan Upkram
1
T 5 FTL program
Implement
EE Ceiling fan program
Capacitor Installation
APFC panel Installation
EE AC & Refrigerator
STLT Lamp Conversion
Energy Audit Scheme
CFL Distribution
3
RInfra Approach to DSM/EE/EC
Confidential Slide 7
DSM PILOTS
Confidential Slide 8
Objectives
Create awareness among the target (and other) customer base on the benefits of 5-star / EE appliances.
Remove barriers to purchase of 5-star appliances.
Monitor and evaluate the benefits of 5 star appliances.
Learning for future initiatives.
Confidential Slide
Identify the Target Consumer / Appliance
Estimate Potential Energy Savings
Evaluate Approaches ( Incentives to customers etc.)
Design of DSM Pilot Project
Establish an Implementation Plan
Develop a Monitoring Plan
Estimate the program Transaction costs
Identify and evaluate DSM Technologies / Measures
Confidential Slide
Mode of Promotions
10
Online : Website Electric Bills Emailer Customer Touch Points facebook
Confidential Slide 11
Website
Confidential Slide 12
Electricity Bills
Confidential Slide 13
Emailers
Confidential Slide
Customer Touch Points
14
Confidential Slide
Confidential Slide
DSM Pilot Projects at Rinfra
Report Energy Savings
Measurement & Verification of Energy Savings
Implement the Monitoring Plan
Name of the Pilot Target sector Target Quantity
Detailed Energy Audit Commercial & Industrial
50
5 star Ceiling Fan – Phase I Residential 5000
5 Star Split AC – Phase I Small Commercial 200
T5 Tube lights Residential & Commercial
100000
5 Star Ceiling Fan – Phase II Residential 20000
5 Star Refrigerator Residential 5000
5 Star Split AC – Phase II Commercial & Industrial
1500
Automation in Air conditioning Commercial 2500 TR
Confidential Slide 17
T5 FTL
2011-12
5* Split AC 2011-
12
5* Fan 2011-
12
CFL 2006-07 5* Refrigerator 2012-13STLT Lamp
Conversion 2008-09LT Capacitor 2010-11
R-Infra DSM Programs
12
3 4 5
67
Energy Audit 2008-
09
8
Confidential Slide 18
CFL Program
Program Details:
Launched in : FY 2006-07
Consumer type : All Category
Product offering : 15 W CFL
Discount : 62%
Investment : INR 118 Lac
Salient Features:
Tie-up with M/s Bajaj
Energy Saving CFL worth Rs. 165 at Rs. 63 under scheme;
Payment in installments
If first 9 installments, of Rs. 7 each, are paid in time, last 3
(Rs.19) waived off
Achievements : Consumers – 2.05 Lacs; CFLs sold – 6.17 Lacs
Savings till date – 38 MU
Confidential Slide 19
Capacitor Installation ProgramProgram Details:
Launched in : FY 2010-11
Consumer type : Commercial / Industrial
Product offering : All Poly propylene capacitor
Discount : 30% with extended product Investment :
Act as a facilitator. Negligible
Investment
Salient Features:
Tie-up with Shreem & Energe Capacitors
Extended warrantee of 5 Years
Cost Inclusive of Installation & Wiring
Achievements :
Capacitor Installed : 2178 kVAR
Savings : 2 MU / Annum
Confidential Slide 20
Salient Features:
Tie-up with OSRAM for T5 FTLs
Two years extended warrantee
Free of cost Installation
T5 FTL Program
Program Details:
Launched in : FY 2011-12
Product Offering : T5 Tube Light (31 w) Discount : 60%
Investment : 33 Lacs
The first Energy saving tube-light program in India with 60% price
discount
Achievements :
Units Sold – 4000 Nos.
Estimated Savings – 0.15 MU
Confidential Slide 21
Salient Features:
Tie-up with LG for 5 star AC
Extended warrantee of 1 Year on machine & 4 years on
compressor
Free standard Installation
EE Air-conditioner Program
Program Details:
Launched in : FY 2011-12
Consumer type : small commercial
New technology : 5 star Split type AC
Discount : 40%
Investment : 3.7 Lacs
Achievements :
Units Sold – 51 Nos.
Estimated Savings – 0.19 MU
Confidential Slide 22
EE Air-conditioner Program
5 Star Split AC program Phase 2
Target quantity : 1500 Nos.
Target Saving : 3.87 MU
Target Timeline : June 2015
Program Partner : M/s Godrej
Smart End Use Management System ( SEMS)
Automation in Air conditioning
Target quantity : 2500 TR
Target Savings : 1.3 MU
Target Timeline : June 2015
Technology Provider : M/s Amplebit
MOU will be signed with 20+ Consumers.
Confidential Slide 23
EE Ceiling Fans program
Salient Features:
Tie-up with Havells for 5-star Ceiling Fans
Old fan disposal in environmentally safe way.
Program Details:
Launched in : FY 2011-12
Product offering : 5-star Fans (50 Watts)
Discount : 60%
Investment : 27 Lacs
The first Energy Saving Ceiling Fans Program in India with 60 % price
discount.
Achievements :
Phase I – 5000 Units , Savings- 0.21 MU pa
( Completed in Aug 12 )
Phase II: 10000+ Units till date
Confidential Slide 24
Refrigerator Program
5 Star Refrigerator Program
Target Quantity : 5000 Nos.
Target saving : 1.54 MU
Target Timeline : April 2015
Program Partner : M/s Godrej
Achieved : 2500+ Installations
Saving achieved :0 .71 MU
Confidential Slide 25
Street Light Lamp Conversion Project
Launched in : FY 2008-09
Consumer type : Street Light
Old Fixtures : HPMV ( 125 W )
Replaced with : HPSV lamps (70 W)
Replacement of : 36560 lamps
Saving Achieved : 16.98 MU ( Till Date )
Used Lamps were disposed through MPCB approved Vendor at cost
Street Light Conversion Program
Confidential Slide 26
Salient Features:
Completed : 50 Audits
Tie up with reputed Energy Auditing Firms.
Energy Audit Scheme
Program Details:
Launched in : 2008-09
Target Audience : Commercial / Industrial
Large consumers : 75:25 % basis
Achievements :
Estimated Savings Large Consumer: 5.13 MU
Estimated Savings Small consumer : 3.2 MU
Confidential Slide 27
Process & Response Evaluation
Confidential Slide 28
Evaluation Methodology
A survey carried out in the area where Test – pilot was conducted
The survey was carried out by reputed third party marketing agency
The questionnaire was carefully designed to understand the acceptance of offer, execution channel and product by the consumers
Confidential Slide 29
Major Findings
Likes by the consumers
Concept of Energy Saving
Extended Warrantee
Installation included
Ease of offer redemption process
Confidential Slide 30
Major Findings
Dislikes by the consumers
Expensive
The discounted price is more than available options.
Compares it with the existing inefficient appliance and feel that investment is unnecessary.
No visible change in bill post-retrofit
As the lighting load form a small part of entire energy consumption ,the reduction in bill can easily get masked by addition of appliances/ seasonal variations
Confidential Slide 31
Major Findings
Dislikes by the consumers
Not a high priority item
Not an energy guzzler. Hence low priority item for energy saving
Reluctance in giving away appliance in working condition
Wants to have product demo at home
Communication in local language preferred
Confidential Slide
Other Issues Programs not qualifying the DSM tests due to lower power
purchase cost Poor response from Manufacturers Lack of awareness in consumers on 5 star / EE appliances Consumers don’t notice adds on electricity bills Higher promotion cost due to lack of awareness. Due to consumer mix, the promotion cost increases for
commercial sector. Strike rate 3 to 4%
32
Major Findings
Confidential Slide
Other Issues Quality of products Consumer expects immediate response from vendor. Consumer not reachable to vendor. Vendor not much techno savvy Difficult to digest for consumer the fact of any utility funding
for energy efficiency and consumer benefits. Consumer not agree for M&V
33
Major Findings
Thank You!