Upload
shon-cook
View
217
Download
0
Embed Size (px)
Citation preview
PHASE 7 FACILITIES ENGINEERING
7.1.2 Types of Development Platform Options
There are two options which are technically and commercially viable
1. The Fixed jacket platform and the floating production storage and offloading (FPSO)
2. A long term and fixed on site platform is preferable (Jacket Platform)
7.2.1 Facilities Design Concept
The platform is planned for an unmanned facility to eliminate the need for personnel to be on rig
The platform should be designed to accommodate servicing barges or vessel in the future
The design is also aimed to withstand 25 years operating life with 30 years structural design life with
monsoon storm condition.
A remote well testing will be run on a monthly basis
Geological Data of Gelama Merah
1. Location 75 km from Labuan crude oil terminal (LCOT) and 15 to 20 km from Samarang Platform
Number of wells: 6 wells consist of 5 producers and 1 vertical water injection
2.The producer consists of 1 horizontal and 4 deviated wells
7.2.2 Top Structure
The Jacket Platform topside will be modularized integrated deck supporting the main production , a mezzanine deck and a helideck
The deck on top of the wellhead shall have sufficient space to accommodate wireline and coiled tubing services
7.2.3 Substructure
The Jacket shall be a 6-pile steel-insert structure utilizing 8 conductor slots and is to be designed
1.To withstand loading resulting from operations
2.To support facilities on the main production module on the top structure
3.To accommodate the risers, caisson and boat landing consideration the sea level depth
PHASE 7 FACILITIES ENGINEERING
7.3 Operation Facilities and Equipments
The selection of production facilities is based on four main decisional
1.Transport and hydrocarbon evacuation
2.Substructure options
3.Processing facilities
4.Wellhead location
7.3.1 Wellhead
Fluid flow from individual well will flow through the Xmas tree and routed to the production manifold
7.3.2 Production flowlines, Flow control and Manifold
Collect production from several individual wells and direct it to Samarang Platform Direct production from a selected well to a well test facility located at each manifold
site via a test header.
PHASE 7 FACILITIES ENGINEERING
7.3.4 Phase Separator
A three phase horizontal separator will be use at Central Processing Platform (CPP) Separator receives production from individual well via manifold
7.3.5 Water Injection
Water injection system consist of coarse filtration, fine filtration. Deaeration and water injection pumps
Sea water Lift Pump Hypochlorinator to prevent marine growth
7.3.6 Gad Handling
The produced solution gas will be use for
1. Future gas lift supply
2. Flaring
3. Onsite use for operated vessels and control systems
www.themegallery.com
Company Logo
PHASE 7 FACILITIES ENGINEERING
7.3.8 Electrical Power and Lighting
A closed cycle vaporized thermo generator (CCVT) or a micro-turbine with configuration of 2 units, 1 unit on standby basis
7.3.9 Drain System
Close drain, drain piping run throughout the platform and routed to vessels on lowest level of the platform
Open drain, drain line converge into headers, then flow into closed drain vessel
7.3.10 Flare System
Depressure gas from various pieces of equipment within the platform Safety mechanism for abnormal process operations that may create unwanted pressure surge
www.themegallery.com
Company Logo
PHASE 7 FACILITIES ENGINEERING
7.4.1 Safety Shutdown System
Safeguard the equipment and the overall facilities Perform specified functions to maintain a safe state of the process when
unacceptable or dangerous process condition are detected
7.4.4 Platform Data and Communication System
A digital microwave radio system and a marine VHF radio system will be installed
7.5.1 Pipeline Tie-Ins
The nearest CCP in Sabah offshore is located in Samarang-B Platform (SMP-B), approximately 15-20km from GM Platform location
Tie-in to current existing platform is preferable to Reduce cost for processing and deck load on GM Platform itself Reduce cost for leasing a FPSO vessel for the whole 20 years
www.themegallery.com
Company Logo
PHASE 7 FACILITIES ENGINEERING
www.themegallery.com
Company Logo
Figure 7.1 Tie-in from GMJT-A to SMP-B diagram
Scope of work for Tie-In
Fabbrication and installation of new riser and receiver/launcher
Structural strengthening required for platform upgrading
Associated piping, new vessel installation
Deck extension to accommodate riser
PHASE 7 FACILITIES ENGINEERING
7.6.4 Corrosion Monitoring
Corrosion monitoring is necessary to
1. Monitor the availability of the inhibition system to optimize inspection frequency
2. Monitor pigging debris for corrosion products
3. Cathodic protection and external anti corrosion coating shall be applied to
maintain the pipeline integrity
7.7 Abandonment
Decommissioning of Gelama Merah platform will take place when it is no longer
economical to continue production.
www.themegallery.com
Company Logo
PHASE 7 FACILITIES ENGINEERING