Upload
emma-johnson
View
215
Download
2
Embed Size (px)
Citation preview
Per
form
ance
Rev
iew
Co
mm
issi
on
Per
form
ance
Rev
iew
Co
mm
issi
on
PRC reportPRC report
29th Session of the Provisional Council
Brussels, 9 May 2008
Jean-François VIVIER
Chairman PRC
EUROCONTROL
2
Performance Review Commission
PRR 2007: Review of ATM performance in 2007
Recommendation a.
The Provisional Council is invited to note the PRC’s Performance Review Report
(PRR 2007) and to submit it to the Permanent Commission
PRR 2007 contentsTrafficSafetyCapacity and DelaysFlight-efficiencyEnvironmentCost-effectiveness
An extensive consultation process ANSB (29 January 2008)Written consultation (06 February - 06 March)Consultation meeting, 60 participants (06 March)CMIC (04 March)PCC (8 May)
3
Performance Review Commission
PRR 2007 - Safety (High-risk runway incursions)
Recommendation b.
The Provisional Council is invited to note that the number of high-risk runway
incursion reports is rising, and to request the Director General to report on
achieved performance to the Provisional Council on a regular basis.
2007 saw a number of high risk runway incursions, as well as one accident with direct ATM contribution - a runway collision in Bucharest.
10%
9%
18%
9%
10%
0
20
40
60
2002 2003 2004 2005 2006P15 States
Cla
ssifi
ed e
vent
s
Severity B
Severity A
% : Proportion of Severity A+B
Data source: EUROCONTROL SRU
Reported high-risk runway incursions
4
Performance Review Commission
PRR 2007 - Safety (Safety Maturity)
Recommendation c.
The Provisional Council is invited to support the standardisation of safety
reporting at a high level of integrity and consistency across EUROCONTROL
States, by every available means, and to request non-compliant States to
implement ESARR 2 fully .
19
11
24
18
30
22
28
33
00
5
10
15
20
25
30
35
2002 2003 2004 2005 2006 2007 2008
ANSPs
Regulators
Target
Safety Maturity
The safety maturity of ANSPs and that of Regulators further improved in 2007. However, ANSPs and Regulators in a number of States will have to make major efforts to reach the 70% maturity line by the deadline, given their progress to date and their current situation.
Compliance with ESARR2 improved in 2007, but has reached a plateau.
5
Performance Review Commission
PRR 2007 - Safety (EUROCONTROL Confidentiality Policy)
Recommendation d.
The Provisional Council is invited to request the Director General to ensure the
prompt implementation of the decision taken in May 2007 where PC 27 “invited
the Director General to undertake a review of EUROCONTROL’s publication and
confidentiality policy, to ensure the appropriate balance between confidentiality
and transparency of safety information” .
EUROCONTROL publication and confidentiality policy in relation to safety data (EAM 2/GUI 2 of 12-11-1999) addresses “the sharing of safety information between ATM service providers, the reporting of safety information to ATM regulators and the provision of safety information to the public, including those provided to the PRC”.
As a result of this policy, the PRC only receives disidentified, high-level safety data, which does not allow the PRC to review safety performance contrary to the provisions of Article xx of the Revised Convention.
Upon a PRC recommendation, the Provisional Council (PC 27, May 2007) “requested the Director General to undertake a review of EUROCONTROL’s publication and confidentiality policy, to ensure the appropriate balance between confidentiality and transparency of safety information” upon recommendation from the PRC.
To the PRC’s knowledge, this decision has not been acted upon so far.
6
Performance Review Commission
PRR 2007 (Capacity & Delays)
Recommendation e.
The Provisional Council is invited to note that ATFM delays have been rising for
the third consecutive year and to request the full commitment of all stakeholders
to the planning and implementation of ATC capacity in line with traffic growth.
2.9
4.1
5.5
3.63.1
1.8
1.2 1.2 1.3 1.41.6
0
1
2
3
4
5
6
7
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
min
ute
s o
f A
TF
M d
elay
per
flig
ht
0
1 000
2 000
3 000
4 000
5 000
6 000
7 000
IFR
fligh
ts in S
um
mer ('000)
Capacity/Staffing ATC special event (equipment, strike) Weather Other
Target
Target: 1.0min/flight
Actual: 1.6min/flight
ATFM en-route delays Summer (May- October)
source : EUROCONTROL/CFMU
Traffic
7
Performance Review Commission
PRR 2007 (Flight-efficiency, Environmental impact)
Recommendation f.
The Provisional Council is invited to note that its flight-efficiency performance
target was not met in 2007 and to request the Director General to inform the
Provisional Council as to the extent and timing of expected performance
improvements arising from airspace programmes coordinated by the Agency in
relation to achieving the flight efficiency target.
48.7 km 48.2 km 48.9 km
0
20
40
60
2005 2006 2007 2008 2009 2010
rou
te e
xten
sio
n (
km/f
ligh
t)
Direct en route
TMA Interface
Agreed target
- 2 km per f light
Upon a PRC recommendation, the PC adopted in 2007 a target to “reduce the European average route extension per flight of 2 km per annum until 2010”.
The target was not met in 2007. Considerable effort will be needed to meet it in the future.
8
Performance Review Commission
PRC recommendations arising out of PRR 2007
The Provisional Council is invited:
a. to note the PRC’s Performance Review Report (PRR 2007) and to submit it to the Permanent Commission;
Safety
b. to note that the number of high-risk runway incursion reports is rising, and to request the Director General to report on
achieved performance to the Provisional Council on a regular basis;
c. to support the standardisation of safety reporting at a high level of integrity and consistency across EUROCONTROL
States, by every available means, and to request non-compliant States to implement ESARR 2 fully;
d. to request the Director General to ensure the prompt implementation of the decision taken in May 2007 where PC 27 “invited the Director General to undertake a review of EUROCONTROL’s publication and confidentiality policy, to ensure the appropriate balance between confidentiality and transparency of safety information”
Capacity/delays
e. to note that ATFM delays have been rising for the third consecutive year and to request the full commitment of all stakeholders to the planning and implementation of ATC capacity in line with traffic growth;
Flight-efficiency, Environmental impact
f. to note that its flight-efficiency performance target was not met in 2007 and to request the Director General to inform the Provisional Council as to the extent and timing of expected performance improvements arising from airspace programmes coordinated by the Agency in relation to achieving the flight efficiency target .