PeopleSoft 9 UpgradeInterface Planning
November 2011Roger Lurie, PS 9 Integration Lead
Chris Deaton, Quality Assurance Coordinator
Agenda• Project overview
• Interfaces and impact
• Timeline
• Current status
• What Next
• Questions and concerns
Project Overview
• Strategic ABOR Approved Project• PeopleSoft Upgrade to Version 9.0• Split of CS and HCM databases• Interface retrofits• Discontinue PSREP• http://peoplesoft.asu.edu
Interfaces ~ 550• PSREP – 60 app id’s
• OGATE – 1 application
• OSYNC – 3 processes
• Direct connect SQL – 76 app id’s
• Integration Broker – 14 nodes
• DBlinks – 9 dblinks
• BPEL/SOA – 5 applications
• SQL Server Integration Services – 12 packages
• Flat Files loaded to PS through Production Support - 118
• Flat Files extracted from PS via Production Support - 265
• Departmental MyReports and Dashboard extracts - ?
• Nelnet
Technical Impact• Data structures
• URL’s for deep links
• Datafile location at CMS
• Security configuration
• Split database(s)
• Other?
Business Impact• Plan, plan, plan!
– Staff resources– Environments– Development freeze
• Impact analysis
• Thoroughly test and signoff on apps
Discontinue App ID’sPSREP•TUTRAC_APP•USI_VPSA_APPS•SCIQUEST_APP•BTS_APP•SRC_FEE_APP•USIREG_APP•TRVL_APP•ASU_BTS_FDM_APP •HPRONLINE_APP•ASUO_APP•CEM_APP•CLAS_FAR_APP•CLAS_GWL_APP•HYPERION_APP•AR_APP
Enterprise•ASU_OHPR_APP•ASU_BTS_FDM_APP•ASU_AZUN_APP•ASU_WPC_HR_APP•ASU_KEYSTONE_APP•ASU_RSRCHAT_APP•ASU_CBADMIN_APP•ASU_AZTRANS_APP•ASU_MYCOURSE_APP•ASU_STUDRUPAL_APP
Enterprise Data Store (EDS)• Person, Address, Phone, Email and
Affiliation• Active Plan, Sub-Plan and Enrollment• Current Employees• Updated hourly and available 24 x 7• Join to EPM tables to extend, via OCM
Milestone Timeline
Build EDS for pilot project October – November
Pilot EDS with app developers in UTO and departments December - January
Production enable EDS End of January
Identify requirements; Prepare WebApp9, DARS and any other environments necessary for dedicated PS 9 testing
November - January
Retrofits to external apps, replace PSREP with EDS February - March
Integration testing for PS 9 February - March
Build split environments, apply split related modifications April - May
Retrofits to external apps for split April - May
Integration testing for split April - June
Test split May - June
User Acceptance Testing/Systems Test June - July
User Acceptance Testing Round 2 July - August
Go Live with Split/PS 9 September
WebApp4Dev
PS 8.9 or 9.0
WebApp4QA
PS 8.9 or 9.0
WebApp4Production
PS 8.9 Only Until Go Live
WebApp9 Dev
PS 9.0 Only
WebApp9 QA
PS 9.0 Only
Key Dates• Identify additional UTO hosted environments – December 16
• Impact Analysis complete – January 20
• Submit request for new app id, or unlock app id – January 31
• Test apps and signoff in 9.0 – March 31
• Test apps and signoff for split – June 30
• Prepare for production – August 31
• Migrate code to production – weekend of September 22
• Disable PSREP – September 30
What Next?• Review applications and batch processes• Begin planning/impact analysis• Participate in EDS pilot• Request app id enablement in 9.0 environment
(CRM Quick Code of M62), or• Request new app id (CRM Quick Code of S02)
Q and A