PCC Update

Presentation to TEPPCJune 2010

Dana CabbellPCC Chair

Page 2: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Today

● Base Case Coordination System (BCCS)

● WECC-071 System Performance Criteria Drafting Team

2

Page 3: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

BCCS In a Nutshell

● Software Tool to Improve Current Process of Base Case Data Collection, Error Checking and Compilation

● Web-accessible Centralized Database

● Facilitates Improved Data Management

● Supports Integration with the Westwide System Model

3

Page 4: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Progress To Date

● Request for Information Issued August 2009

● Vendor Interviews

● Request for Proposal Approved by SRWG March 2010 Approved by TSS April 2010 Approved by PCC June 2010

● Presented to WECC Finance and Audit Committee in April and May 2010

4

Page 5: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

RFP Considerations

● Include sufficient detail in the RFP

● The selected vendor must ensure compatibility across multiple power system analysis platforms

● Steady state and dynamic data

● Vendors will recommend preferred file management and maintenance methods

5

Page 6: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Next Steps

● RFP Board Approval in July 2010

● Issue RFP to Vendors Fall 2010

● Develop Paper on Proposed Framework for Base Case Development with the BCCS (Revised Data Preparation Manual)

● Develop a Quantitative Cost/Benefit Analysis

● Vendor Bid Review Fall/Winter 2010-11

6

Page 7: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

WECC-071 System Performance Criteria

● WECC Drafting Team formed March 2010 Review TPL-(001 thru 004)–WECC–1-CR- System Performance

Criteria Requirement WRS1.1 Reliability Subcommittee was assigned to be the drafting team

● Existing WRS1.1: The NERC Category C (N-2) initiating event on double circuit towers also applies to the N-2 contingency of two adjacent transmission circuits on separate towers in a common corridor

● Remove or modify WRS1.1 classifying the N-2 of two adjacent transmission circuits on separate towers as Category D

Page 8: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Comm

on Corridor

850'

500'

800'

1000'

500 kV Single Circuit # 1

500 kV Single Circuit # 2

Subtransmission Barrier

230 kV Double Circuit # 3 and # 4

Single Circuit Subtransmission Line

250'

Comm

on Corridor

Common Tower

Common Corridor Definition

Page 9: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

TEPPC Study Request Scenario

● Study request submitted in the 2010 TEPPC Study Program -- determine economic benefits if WECC requirement WRS1.1 is removed

● Requested TSS to use judgment on how ratings might increase with this hypothetical criteria change If path ratings limited by an N-2 adjacent circuit

contingency, what would the rating be if the adjacent circuit criteria were reclassified as Category D?

● Discussion: Path Rating study required to determine the actual

change in a path rating Concern with the accuracy of the results of requested

scenario

Page 10: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Questions?

10

Dana CabbellPCC [email protected](909) 274-1588

All information on PCC can be found on the WECC website at

http://www.wecc.biz/committees/StandingCommittees/PCC/default.aspx

Page 11: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Back Up Slide

Page 12: PCC Update Presentation to TEPPC June 2010 Dana Cabbell PCC Chair

Common Corridor Definition

● Common Corridor definition from WECC TPL criteria: Contiguous right-of-way or two parallel right-of-ways with

structure centerline separation less than the longest span length of the two transmission circuits at the point of separation or 500 feet, whichever is greater, between the transmission circuits. This separation requirement does not apply to the last five spans of the transmission circuits entering into a substation.

● Adjacent Transmission Circuits definition from WECC TPL criteria: Transmission circuits within a Common Corridor with no

other transmission circuits between them. Transmission Lines that cross but are otherwise on separate corridors are not Adjacent Transmission Circuits.