147
EGMG ENERGYMEASUREMENTS Los Vegas Area Operations . QA. NA EG&G ENERGY MEASUREMENTS, INC., P.O. BOX 1912. LAS VEGAS. NEVADA 89125 tn March 17, 1994 NV-94-199 A' Robert Nelson, Project Manager Department of Energy Yucca Mountain Site Characterization Project Office 101 Convention Center Drive Las Vegas, NV 89109 FEBRUARY 1- FEBRUARY 28, 1994, PROGRESS REPORT - EG&G/ENERGY MEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THE YUCCA MOUNTAIN SITE CHARACIERIZATION PROJECT Enclosed is a progress report on the EG&G Energy Measurements, Inc. (EG&G/EM) Remote Sensing Laboratory (RSL) support to the Yucca Mountain Site Characterization Project (YMP) for February 1, 1994, through February 28, 1994. The progress report for EG&G/EM RSL support to YMP includes the following sections: * Work Accomplished * Expenditures * Status of Deliverables If you have any questions, please contact Elaine Ezra at (702) 794-7449. 'James Midhael, Manager NV Program CEms Enclosures ENCLOSURE lb

Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

EGMG ENERGYMEASUREMENTSLos Vegas Area Operations . QA. NAEG&G ENERGY MEASUREMENTS, INC., P.O. BOX 1912. LAS VEGAS. NEVADA 89125

tn

March 17, 1994NV-94-199

A'

Robert Nelson, Project ManagerDepartment of EnergyYucca Mountain Site Characterization Project Office101 Convention Center DriveLas Vegas, NV 89109

FEBRUARY 1- FEBRUARY 28, 1994, PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACIERIZATION PROJECT

Enclosed is a progress report on the EG&G Energy Measurements, Inc. (EG&G/EM)Remote Sensing Laboratory (RSL) support to the Yucca Mountain Site CharacterizationProject (YMP) for February 1, 1994, through February 28, 1994.

The progress report for EG&G/EM RSL support to YMP includes the followingsections:

* Work Accomplished* Expenditures* Status of Deliverables

If you have any questions, please contact Elaine Ezra at (702) 794-7449.

'James Midhael, ManagerNV Program

CEms

Enclosures

ENCLOSURE lb

Page 2: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

A

EG&G Energy Measurements, Inc.YMP Spatial Analysis SectionATTN: C. Elaine Ezra - MSN-02.P0 Box 1912Las Vegas, NV 89125

Page 3: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Robert NelsonFEBRUARY I - FEBRUARY 28, 1994, PROGRESS REPORT - EG&G/ENERGYMEASUR ENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CELARACIERIZATION PROJECTMarch 17, 1994Page 2

cc: S. Rougen, DOE/NV EMD (w/o end)M. Blanchard, DOE/YMP (w/o end)W. Dixon, DOE/YW (w/o endl)M. Dockter, DOE/NV (w/o end)R. Dyer, DOE/YMP (w/o end)J. Lorenz, REECo/YMPC. Newbmiy, DOE/YMPM. Ryder, DOE/YMP (w/o end):A Sons, DOE/YMPD. Wllinams, DOE/YMP (w/o encl)W. Wilson, DOE/YM-

Page 4: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L23 SITE INVEST[GATIONS

WBS 1.239A SPECIAL STUDIES: TRACERS, FLUIDS AND MATERIALS

SA OE394A TRACERS, FLUIDS AND MATERLAIS

REPORT PERIOD: February 1, 1994- February 28, 1994

REPORT DATE: March 18, 1994 -

RESPONSIBLE INDIVIDUALi Jim Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

L The processing plan for transfer of the Tracers, Fluids and Materials Databasefiles was reviewed and approved on February L All database tables have beentransferred to the GENISES system and have been translated from the DOSoperating system to the UNIX operating system.

2. A meeting was held on February 8 in the EG&G/EM YMPSAS- office to discussthe TFM database. In attendance were Craig Matthews (SAIC), Gillian Hall(LANL/CAG) and Chris Breed (LANL/S&1).

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

L The FOC does not have the correct version of the software required to operatethe input applications for the database. They are currently acquiring the software,and estimate the system will not be operational until mid- to the end of March.

2. The S100K funding to support the TFM database has not yet been transferred toEG&G/EM.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The transfer of the database into GENISES Uill be completed and an acceptanceletter provided to YMPO by March 31.

2. Interviews for the TFM database position wil continue.

1

Page 5: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWark Accomplished

WBS L23 SITE INVESTIGATIONS

WBS L23.9.5 SPECIAL STUDIES: THREE-DIMENSIONAL SITE MODEL

SA 0E39SA 3-D MODEING AND VISUALIZATION

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INDIVIDUAL D. Brickey

SUtMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

L An interactive demonstration of the 3-D) modeling and visualization capabilitieswas provided at the Technical Program Review on February 14. Thedemonstration included the Dynamic Graphics (DGI) EarthVision version of theCalma-generated thermal-mechanical stratigraphy model, and EarthVision-basedsaturated/unsaturated zone model, and a WaveFront-based 3-D visualization ofthe USGS' demonstration model of the Topopah Spring member. Dave Brickeyparticipated in the panel discussion portion of the 3-D) modeling session.

2. David Jefferis continued work on exporting the USGS' demonstration model ofthe Topopah Spring Model to EarthVision. The entire faiult structure has nowbeen exported into EarthVision, and was demonstrated at the Technical ProgramReview. Structural surfaces for each horizon have been created.

3. Dave Brickey continued work on the development of FY94 task plans.

4. A purchase requisition for the SGI Indigdt using FY93 capital carryover funds wasinitiated.

5. The purchase of the Lynx GMS software for the YPSAS facility was completed.A purchase request for software maitenance was initiated.

6. Evaluation of the WaveFront software continues. WaveFront is Lymn GMS's 3-Dvisualizer. The USGS's demonstration model (December 1993) has beenimported by Jennifer Geddes into WaveFront, and was demonstrated at theTechnical Program Review.

2

Page 6: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

7. Various Lynx GMS procedures have been developed by Jennifer Geddes for thefollowing: produce structure contours from a volume component model; export avolume component model from Lynx GMS to Wavefront, and extend volumecomponents.

8. A Senior Scientist in support of 3D modeling and visualization position wasopened.

9. The following products were delivered:

* Three viewgraphs were produced from screen capture views of theEarthVision-based thermal-mechanical model for Mark Tynan (YMPO) -YMP-94-041.0t YMP-94-042.% and YMP-94-043.0.

* A TAR formatted quarter inch cartridge tape with the file 'elv.dat (20 footelevation contour data for the Yucca Mountain Site) in Lynx GMS formatwas provided to William Zelinski (SNL) - NR94012802.

MAJOR PROBLEMS AND CORRECTIVE ACTION: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

L Completion of the conversion of the USGS demonstration model (December1993) from Lynx GMS format to DGrs EarthVision format is anticipated for theend of April 1994. Refinement of the methodology will continue in order toautomate the process as much as possible.

2. A task plan defining EG&G/EM's tasks for FY94 will be completed.

3. EG&G/EM staff will attend the UNLV Computer Graphics Laboratory on March3, 1994.

3

Page 7: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMWork Aoomplished

WBS L2.5 REGULATORY

WBS L2S3.5S GEOGRAPHIC NODAL INFORMA11ON STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE53SL94 TECHNICAL DATABASE INPUT

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DAlE March 18, 1994

RESPONSIBLE INDIVIDUAIL J. Beckett

SUMMARY OF WORK ACCOMPUSHED DURING REPORT PERIOD:

1. Two of twenty candidate submittals to the Tecihical Database were completedand are under internal review, prior to traerring to the CRF and GENISESTDB.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Environmental Sciences Division candidate data will contine to be processed intoData Transfer Packages for transfer to the CRF and the TDB.

4

Page 8: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L2.S

WBS L2.9.3.6

SA OES36A

REGULATORY

*GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

GENISES TECHNICAL DATABASE.

REPORT PERIOD:

REPORT DATE:

Februaiy 1, 1994 - February 28, 1994

March 18, 1994

RESPONSIBLE INDIVIDUAL- J. Beckett.

SUMP4ARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. An all day meeting washeld on Februazy 3 to revise the administrativeprocedures for the YMP Technical Data Management System. la attendancewere Ardyth Simmons (YMPO), Steve Bodnar, Bob Lewis and Hilary Abhold(M&O), and Elain Ezra and Jim Beckett.

2. A meeting was held on February 16 to discuss technical database requirements forSandia National Laboratories (SNL). In attendance were Ardyth Simmons andClaudia Newbury (YMPO), Joe Schelling, Mick Jones, and Dick Thompson(SNL), and Elaine Ezra, Jim Beckett and Dave Brickey.

3. Elaine Ezra and Jim Beckett participated in the YMP Technical Database paneldiscussion at the YM Technical Program Review on February 16.

4. The following submittal to the GENISES Technical Database was received duringthis period:

GS930308312312.008

GS920608312312.009

USGS OFR-91-493, Water Levels in ContinuouslyMonitored Wells in the Yucca Mountain Area,Nevada, 1985-1988 was received on February 8.

USGS OFR 90-113, Water Levels in PeriodicallyMeasured Wells in the Yucca Mountain Area, Nevada,by James M. Gemmell.

5

Page 9: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

5. The following submittals to the Yucca Mountain Project Technical Database wereprocessed into the GENISES TDB during this period:

TM000000000001.037

GS910808312232.002

GS93073117410L003

Meteorological Monitoring Program Summary ReportDecember 1985 through December 1991 (YMP/93412-MMPSR) was completed on February 1.

USGS OFR 92-28 Borehole and Geohydrologic Datafor Test Hole USW UZ-6, Yucca Mountain area, NyeCounty, Nevada was completed on February 14.

1983-1988 Leveling Results, 1983-1988 QuadrilateralResults and Various Earlier Data, was completed onFebruary 17.

6. No submittals were rejected by the TDBA during this period.

7. The following tabular reports were provided from the GENISES TechnicalDatabase.

NR94020804

NR94021102

NR94022507

A listing of the TIDBrIS report was provided to Jim Agnew (M&O)on February 10.

A listing of collar coordinates (xyz) for boreholes N31, N32, N37,N53, N54, N55 and UZ14 and UZ16 was prepared for Bill ZelinshL(SNL) on February 15.

A listing of borehole, trench and pit activities for the periods ofprior to 1987, 1987 to present, and planned was compiled forClaudia Newbury (YMPO) on February 25. Included was anestimate of the number of miles of seismic survey lims which werelaid.

NR94012310 A listing of for each borehole of the following attributes wascompiled, including total depth, depth of static water table,geophysical log types, lithologic/stratigraphic information, and thetype of tests. The report was prepared in both digital and hardcopyand provided to YMPO for transmittal to the US. NuclearRegulatory Commission on February 25.

6

Page 10: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

L The GENISES IDB is understaffed; four new positions have been opened.Interviews with internal applicants have been completed. Outside applicantinterviews will be initiated in early March.

2. GS920108314213.001 contains data that is not identified in the submittal package.A letter was sent to USGS requesting identification of data be provided.

3. GS930208318523.001 contains data that is not identified in the submittal package.A letter was sent to USGS requesting identification of data be provided.

4. GS930908314214.006 contains data that is not identified in the submittal package.A letter was sent to USGS requesting identifcaton of data be provided.

5. GS930908314214.007 contains data that is not identified in the submittal pacIage.A letter was sent to USGS requesting identification of data be provided.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Interviews will continue for the four additional GENISES TDB stafL

2. Site and Engineering Properties Database (SEPDB) badldog processing will beinitiated.

7

Page 11: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L2.5 REGULIATORY

WBS L2.53.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536B4 GIS DATABASE, SITE ATLAS, ARCVIEW AND GISCATALOG

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INDIVIDUAL: S. Rohde

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. The 'baselinef area of the GIS database continues to be evaluated, reformattedand verified to facilitate production activities.

2. Work to transfer the 2foot contour data developed from a YMP orthophotomission to the USGS was initiated.

3. Two groups of arc interchange data transfers were completed and delivered.

4. TWo candidates for the Scientist It position were interviewed.

5. A Table of Contents and an Introduction was written for the Site AtlasSupplement.

6. Susan Rohde met with Tom Bjerstedt (YM O) and Ciuck Harrington (ANL)on February 4 regarding the NRC data request for boulder deposit sampling sites.They reviewed the data in an ArcView session and reviewed hardcopy editplotsproduced in ARC/INFO. Additional data entry was identified to incorporatefield calibration sites (in addition to the sampling sites).

7. Susan Rohde met with Chuck Harrington (LANL) on February 17 regarding theNRC data request for boulder deposit sampling sites. Harrington reviewed andverified data entry pertaining to the February 4 meeting. He verified theautomation effort by reviewing attribute tables and viewing plotted data (bothhardcopy and on-line). Harrington identified changes to the existing source mapswhich will impact delivery and require modifications to the automation effort.

8

Page 12: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

-

8. Elaine Ezra met with Kent Ostler and Danny Rakestraw (EG&G/ESD) onFebruary 23 to discuss a process for updating the YMP 1990 disturbance map.Elaine prepared a draft proposal for ESD's review.

9. No ArcMiew datasets were distributed during this report period; however,updates and dataset verification continues to occur.

MAOR PROBLEM AND CORRECTlE ACI7ON UNDERTAKEN:

1. The FY93 Site Atlas, orginally scheduled for completion on September 30, 1993,was not received from the GPO for second proofing as anticipated. A memo wasreceived on February 7 by the printer stating that additional funds were required tocreate the second proof, and that once those funds were identified delivery of thesecond proof set would not occur until March 7. A memo was written to approve andappropriate the additional funds. These events, will again, impact the final deliverydate of the published FY93 Site Atlas.

2. A transfer of 2-foot contour data has been requested by the USGS. In meeting thisrequest, it was discovered during data verification that original source files did notcontain the z-value. A new request for data is being generated so that this data willbe useable.

3. Delivery of the NRC data request for Boulder Deposit Sampling Sites has beendelayed several times due to changes and additions to source data provided by thecustomer. The automation effort has been completed and we will continue to workclosely with LANL.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD.

1. Verification of GIS data continues in support of the March quarterly update ofthe GIS Data Catalog.

2. Receipt of the second proofing set for the FY93 Site Atlas from the GPO.

3. Review and approval of the second proofing set for the FY93 Site Atlas.

4. Transmittal of Site Atlas proofs to the GPO for final printing.

S. Initiation of FY94 Site Atlas tasing will occur.

6. Standardization of content and procedure for the transmittal of ArcView datatransfers.

9

Page 13: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPW~ork Acnpshed

WBS 12.5 REGULATORY-

WBS 1.2.S.3.6 GEOGRAPH[C NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536C4 GIS, MAPPING AND ANALYSIS SUPPORT

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INIIVDUAL. J. Donovan

SU1MMARY OF WORK ACCOMPWISED DURING REPORT PERIOD:

1. GIS map products were generated to support project participants and are detailed inthe 'Delivemblesl statement.

2. Photo products include the following:

NR94012601 Two duraflex 30-x40 prints of EG&G 90C-208 were provided to JerryLorenz OUECo) on February 4.

NR94020301 Ihree 35mm color slides and 10 8'xl0' color viewgraphs of thefollowing fames were provided to Allison Inglett (SAIC) on February11:

5826 257488 447490 37490 75

NR94012810 One color infrared Landsat TM image of the upper Amargosa RiverBasin (EG Neg. No. 911701L - MRSD 91017.04) was prepared forDebbie Zesiger (USGS) on February 11.

NR94020702 One contact color print each of Perf 17491, frames 34-69 wereprepared for Chris Fridrich (USGS) on February 15.

10

Page 14: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

NR94020101 One 1:12,000 scale mylar prints of orthophoto sheets 2,3,4,8,9,10 and11 were prepared for Larry Anderson (BR) on February 25.

One 1:12,000 scale mylar print of orthophoto with contours for sheet 3was prepared for-Larry Anderson (BR) on February 25.

3. The following digital data transfers were prepared:

NR94012802

NR94010703

NR94021101

NR94020901

One 1/4' cartridge tape in TAR format with the 20 foot elevationcontour data for the Yucca Mountain Site in Lynx compatible formatwas provided to Bill Zelinsid (SNL) on February 4.

Digital files of the 1:250,000 scale USGS Digital Elevation Model(DEM) files for an area around 30 miles of YMP was provided toWindy Weiland (EDCON) on February 10.

One amini cartridge' tape of the GIS coverages provided to the NRCunder NR93111001 was prepared for YMO for transfer to IDyo

County on February 11.

One 1/4' cartridge tape of the following ArcIfo coverages in exportformat was prepared for Willim Davies (USGS) on February 28:vegetation, faults, alluvium/bedrock contacts, existing boreholes anddisturbance features.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIEPATED SIGNIFICANT EVENIS PLANNED DURING NEXT REPORTPERIOD:

1. Continued level-of-effort.

11

Page 15: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMWWork, AMcmplishcd

WBS 1.2.5 REGULATORY

WBS 1.2.53.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536F4 REMOTE SENSING

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INDIVIDUAL: C.E. Era

SUMMARY OF WORK ACCOMPLEISED DUlRING REPORT PERIOD:

1. A meeting was held on February 2 with Don Unglesbee (SAIC), Elaine Ezra, MikePelan and Rex Windom to discuss EG&GIEM photo support to the YMP FieldOperlbions. Don wil be the primary point-of-contact for field requests for photostporL

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNMICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

12

Page 16: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPW~ork£ Accomolshed

WIBS 1.2.3 REGULATORY

WBS 1.2.33.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536E4 COMPUTER SUPPORT

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSBLE INDIVIDUAL: T. Rademacher

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Young Minds provided a demonstatin of their CD ROM Writing system onFebruary 1 to the EG&G/EM Y Spatial Analysis Section (YMPSAS).

2. A meeting was held on February 4 with John Gandi and Mary Ann Jones (YMPO),Jim Low (M&O), Elaine Ezra, Jim Beckett, Chuck Logan and Joanna Wiggins todiscuss computer resources management plans and procedures.

3. A meeting was held on February 16 with Jeffrey Schwalm (Dynamic Graphics),Elaine Ezra, Dave Brickey and David Jefferis to discuss EarthVision licensing issues.

4. System support was provided for the 3-D modeling and ArcView displays for theYMP Program Technical Review at the Stardust Hotel during the week of February14.

5. The SPARCenter 1000 fileserver hardware was received and inventoried. Theinstallation plan is in preparation.

6. An ARC/INFO software license for the SGI platform was received.

7. Character Pro optical character recognition (OCR) software was received for theRicoh FS2 scanner.

8. A letter to Environmental Systems Research Institute (ESRJ) requesting a pre-releaseversion of ArcView 2 was compiled (Ezra to Wiesee, dated February 14).

13

Page 17: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

9. A purchase request for PC ARC/INFO software maintenance was initiated.

10. A purchase request for an optical disk drive for the RSL Production System wasinitiated.

11. A purchase request for two 2.1 GB SCSI disk drives for the RSL Production Systemwas initiated.

12. A purchase request for a 5 GB 8mm tape drive for the RSL Production System wasinitiated.

13. A purchase request for a PC CD ROM reader was initiated.

14. A purchase request for a multiport repeater was initiated.

MAJOR }PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The Technical Database SPARCenter 1000 flleserver installation plan will bereviewed and approved and installation will be initiated.

2. An upgrade of the INGRES RDBMS unlimited user license from the SPARCstation 2to SPARCenter 1000 wil be initiated.

14

Page 18: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWlork AccmRlished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536G4 CAPITAL EQUIPMENT

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INDIVIDUAL: E. Ezra

SUMMARY OF WORK ACCOMPLISHIED DURING REPORT PERIOD:

1. A purchase request for a SPARCStation 10 was initiated for the RSL ProductionSystem.

2. A purchase request for five SPARC Classic workstations was initiated.

3. A purchase request for a MacIntosh personal computer system was initiated.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNMICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

15

Page 19: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPWork Accomliished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY AND.EVALUATION SYSTEM (GENISES)

SA OE536D4 PROJECT MANAGEMENT

REPORT PERIOD: February 1, 1994 - February 28, 1994

REPORT DATE: March 18, 1994

RESPONSIBLE INDIVIDUAL: . Ezra -

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

Rqxrtingn~acting~Panning

1. EG&G/EM RSL January Progress report was compiled and submitted toYMPO.

2. January PACS input was compiled and submitted to Robert Spiro (M&O).

3. FY94 Work Auizaon Directive reisions were completed and provided toYMPO on February 7.

4. A letter requesting conversion of FY94 to capital equipment fundswas submitted to YMO (Michael to Nelson, dated February 15).

5. Input to the FY94 Information Resource Management Long Range Plan wasprepared and submitted to YMPO (Ezra to Gandi, dated February 28).

MeetingslConferncesfrrining:

1. Weekdy Technical Data Managers staff meetings were held with ArdythSimmons (YMPO), Steve Bodnar and Bob Lewis (M&O) and Elaine Ezra andrim Beckett.

2. Jim Beckett attended a dry run for the Technical Data Management Systempresentation at the YMP Technical Program Review on February 11.

2. Elaine Ezra, Jim Beckett, and Dave Brickey participated in pand sessions at

16

Page 20: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

the Technical Project Review during the week of February 14.

3. Todd Radermacher anded Solaris Network Administraion II training duringthe week of February 21.

Employee Actions:

1. An advertizement for a computer technia was placed in the local newspaperon February 13.

2. Interviews for the 3-D modeling Scientific Specialist were conducted. Anoffer will be extended.

3. Interviews for the TDB Technologist mH positions were conducted. An offerwill be extended. Additional interviews will be conducted during March.

Quality Assurance:

1. A meeting with YMP QAD staff was held at the EG&G/EM YMPSAS officeson February 23 to disss the GENISES Technical Database. In attendancewere Steve Dana, nim Blaylock, Tomr Higgins, Amy Arceo, Mary McDaniel,John Matras, and Robert Harpster (YMP QAD) and fim Beckett, Elaine Ezraand Joanna Wiggins.

2. On February 1, 1994, Joanna Wiggins met with Frank Kratzinger (YMP QA)to close the 4 CARs issued against EG&GIEM in October of 1992. A letterfrom YMPQAD to EG&G/EM is forthcoming.

ES&H:

1. A monthly safety insecton was conducted at the YMPSAS offices (Broderickto Brandt, dated February 2).

MAJOR PROBLEM AND CORRECTIVE ACTION UNDERTAKEN:

1. Space rewsources at the Bank of America building are inadequate for the additionalpositions EG&G/EM is hiring to support the YMP. EG&G/EM was pursuing thelease of additional space in the Bank of America building which is proximal to itsexisting offices. EG&G/EM has notified the Project of its immediate spacerequiremens bat the February 10 space meeting.

17

Page 21: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ANUICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Continued efforts to hire additional staff and identify additional space.

2. Dave Walrath will attend advanced ARC/INFO raining during the week of March 14.

18

Page 22: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YPWorkr Accon=1ished,

WBS 1.2.12.23 PARTICIPANT RECORDS MANAGEMENT

SA OEC23A4 RECORDS MANAGEMENT

REPORT PERIOD- February 1, 1994 - February 28, 1994

REPORT DATE March 18, 1994

RESPONSIBLE INDIVIDUAI: J. Wiggins

SUMMARY OF WORK ACCOMPLSEIED DURING REPORT PERIOD-

1. Dan Graser (OCRWM Hoeadquart) pvided a briefing on the License SupportSystem (iSS) to the EG&G/EM YMP Spatial Analysis Section on February 18.

2. Two Technical Database submittal packages were received from the EG&GIEMEnvironmental Sciences Division. The packages are under review and will besubmitted to the Central Records Facility (CRF).

3. YM QAD conducted a surveillance of DOE and the Technical Data ManagemeSystem. A component of the surveillance involved EG&G/EM's process formanaging the GENISES Technical Database and the data flow.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNMICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Fourteen completed GENISES TDB Record Packages will be scanned and processedinto the CRF.

19

Page 23: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPWr Accomplished

WBS 1.2.122.3

SA OE152A4

ADMNSTATIVE SUPPORT

PHOTO/GRAPHICS SUPPORT

REPORT PERIOD:

REPORT DATE:

'RESPONSIBLE ADIVDUAL:

February 1, 1994 - February 28, 1994

March 18, 1994

E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. On February 22, an aerial video and oblique photo mission was flown. The missionwas requested by Robert Clark (SAIC) and funded under WBS 1.2.15. The obliqueaerial photo frame list follows:

S5ESP PortalNRT-1 TrenchesGhost Dance Fault PavementsLM 300 at SD-12Ghost Dance Fault PavementsFran Ridge - Tufts and PavementsC Well ComplexRed Cone and Black ConeYucca Mountain - High AngleBusted Butte -Yucca Mountain - Mid AngleBusted ButteNTS Area 25 - Yucca Mountain Ofs

(FOC, MFR, SMF)

PE"F7646764676467646764676467646764676467646764676467646

FRAhM001-031032-042043-056057-065066-072073-083084-090091-092093-100101102-109110111-126

20

Page 24: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Expenditures from December 27, 1993 to January, 1994(Dollars in thousands)

-Januaryco£_Tak

Total CostsTo Date

$ 147.3

RemAig

$ 404.7WBS 1.2.3Site Investigations

$ 552.0 s 78.5

WBS 1.2.5Regulatory

WBS 1.2.12

WBS 1.2.15Support Services

TOrALS

$2,500.0

$ 50.0

$ 194.2

$ 0.0

$ 735.0 $1,765.0

$ *0.0 $ 50.0

S 6.

$3108.0 s 272.7 $ 882.3 $2,225.7

WBS 1.2.5Capital Equipment S 341.6 $ 109.5 $ 109.5 $ 232.1

21

Page 25: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

STATUS OF DEIVERABLES FOR EG&GIEM RSL SUPPORT TO YMPFebruary 1, 1994 through February 28, 1994

GIS MAP SUPPORT

Requested by/ No. ofDscNf~on OrganiziM Date Sentg Cp es

YM-94-003.0 Existing & Olson/RSN 2/4/94 Fun 2Proposed Trenches

YNT-94-004.0 Existing & Olson/RSN 2/4/94 Full 2Proposed Pits

YMP-94-0Q5.0 Existing Olson/RSN 2/4/94 Full 2Borehole

YMP-93-087.3 Test lnter- Deeer/Duke Eng 2/4/94 Ful 1ference Sheet #16 Svs

YMP-93-088.2 Test Inter- DeKiever/Duke Eng 2/4/94 Full 1ference Sheet #17 Svs

YMP-93-093.2 Test Inter- DeKlever/Duke Eng 2/4/94 Full 1ference Sheet 122 Srs

YNTP-93-094.2 Test Inter- DIever/Duke Eng 2/4/94 Full 1ference Sheet #23 Svs

YMP-92-252.0 Flood Prone DeKiever/Duke Eng 2/4194 Full 1Areas Svs

YMP-94-005.0 Existing DeKiever/Duke Eng 2/4/94 Full 1Areas Svs

YM -P94-003.0 Trenches Dle}ver/Duke Eng 2/4/94 Full 1SYS

YMP-94-038.0 Planned ESF Biggar/M&O 2t7/94 page 2Design Support Boreholes

YlWP-94-039.0 Planned Forty- Bigar/MJM&O 2/7/94 page 2mile Wash Recharge Study

22

Page 26: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-040.0 Planned VolcanicBoreholes

YMP-94-017.0 TortoiseObseradons Along Roads inthe Yucca Mountain Area

YMP-94-022.2 Surface-BasedTesting Activities with Geology

YMP-94-023.2 Surface-BasedTesting Activities with Geology

YMP-94-04.2 Surfae-BasedTesting Activities with Geology

YMP-94-0Q5.2 Surface-BasedTesting Activities with Geology

YMP-94-026.2 Surfce-BasedTesting Activities with Geology

YMP-94-027.2 Surfce-BasedTesting Activities with Geology

YMP-94-028.2 Surface-BasedTesting Activities with Geology

YMP-94-029.2 Surface-BasedTesting Activities with Geology

YMP-94-030.2 Surfce-BasedTesting Activities with Geology

YMP-94-006.0 ProposedBoreholes

YMP-94-006.0 ProposedBdreholes

BiggarIM&O

Annear/EG&GIEM

Biggar/M&O

Biggar/M&O

BiggarQM&O

BiggarlM&O

Biggar/M&O

BiggarlM&O

BiggarlM&O

Biggar/M&O

Biggar/M&O

Olson/RSN

DeKiever/Duke EngSvs

2/7194

218/94

219/94

219194

2J9/94

219/94

2/9194

219/94

2/9/94

219/94

2/9/94

219/94

2199

219194

Page 2

Page 1

Full 1

Full 1

Ful 1

Full 1

Full 1

Full 1

Full 1

Full 1

Pul 1

Full 2

Full 1

23

Page 27: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Y1P-93-151.0 YM SouthernGreat Basin Digital SeismicNetwork Planning Map, USGS1:250,000 scale, Las Vegas,Nevada Quadrangle

YM-93-152.0 YM SouthernGreat Basin Digital SeismicNetwork Planning Map, USGS1:250,000 scale, Caiente,Nevada Quadrangle

YMP-93-153.0 YM SouthernGreat Basin Digital SeismicNetwork Planning Map, USGS1:250,000 scale, Goldfield,Nevada Quadrangle

YIA-93-154.0 YMP SouthernGreat Basin Digital SeismicNetwork Planning Map, USGS1:250,000 scale, Death Valley,California Quadrangle

YMP-94-016.0 Springs Within100 Miles of the NTS

YMP-94-033.0 Saturated ZoneBoreholes and GroundwaterGeochemistry Monitoring Stations

YMP-94-016.0 Springs Within100 Miles of the NTS

YMP-94-033.0 Saturated ZoneBoreholes and GroundwaterGeochemistry Monitoring Stations

YP-94-018.0 Selected PlannedBoreholes

YMP-94-044.0 Boreholeswith Geologic Structure

von SeggernlUNR

von Seggern/UNR

von SeggernIUNR

von Seggern/UNR

ChiedsonlYMPO

SmiciensilUNLV

SmicienskiUNLV

BueschlUSGS

Weeks/SAIC

2/14/94

2/14/94

2/14194

2114/94

2/14/94

2114/94

2/14/94

2114/94

2114/94

2114/94

FullMylar

FullMylar

FUlMylar

FullMylar

FUlPage

FullPage

FullPage

FullPage

Full

Full

11 0

I1

11

4

10

24

Page 28: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-OO5.I Existing Linden/SAICBoreholes

YMP-93-255.1 Streamflow and Williams/iYMPOPrecipitation Station Locationsin the CAB Area

YMP-93-195.3 Figure 1, Planned Reynolds/M&OFY94 Boreholes, Assuming ModifiedESF Design

YMP-94-034.0 Selected Trenches Vaniman/LANLand NRG #2

2115194

2/16/94

2/23/94

2/23/94

Full 2

Full 3

-page 1

paage 1

YNDP-93-302.0 Digital LineGraph Data

Girdley/YNPO : 2/23/94 Full 1

YMP-93-301.0 Base Map

YMP-94-005.1 Existing Boreholes

YMP-93-270.0 Recent Progressat Yucca Mountain

YMP-91-031.1 Regional AreaMap

YMP-91-032.1 Site Map

YMP-91-185.1 Existing Boreholes(with Depth) and Highest Pointof Elevation

Girdley/YMPO

Girdlcy/YMPO

InglettISAIC

Binzer/SAIC

Binzr/SAIC

Binzer/SAIC

2/23/94

2/24/94

2/25/94

2t25/94

2/25/94

2/25/94

2125/94

Fu11 1

Full 1

Full 1

Full 5

Full 5

FURl 5

YMP-91-186.1 Proposed Boreholes Binu=/SAIC(with Depth) and Highest Pointof Elevation

Full 5

YMP-94-047.0 Selected DeepSeis=ic Shotholes

Agnew/M&O

YMP-93-183.2Y1MP-93-338.0YMP-94-001.0YMP-94-002.0

Mcinley/USGSMcKinley/USGSMcKinley/USGSMcXinley/USGS

/251194

2/28/942/281942/28/942/28/94

PaIge 3

PagePagePagepage

1111

25

Page 29: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-07.0YMP-94-008.0YMP-94-009.0YMP-94-010.0YMP-94-012.0-AYMP-94-013.0-BYMP-94-014.0YMP-94-015.0YMP-94-019.0YMP-94-019.1YMP-94-020.0-CYMP-94-020.0-DYMP-94-031.0

YMP-94-045.0 Small MammalPlots

McKinley/USGSMcKinley/USGSMcKinleyfUSGSMcKinley/USGSMc~lneyfUSGSMcKinleyfUSGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinleyIUSGSMcKinley!USGSMcKinley/USGSMcKinley/USGS

Gabbert/EG&G/EM

2/28/942/281942128/942128/942128/942/28/942128/942128/942128/942/28/942/281942128/942/28/94

2128/94

PagePagePagePagePagePagePagePagePagePagePagePagePage

Page

11

111

1111

1

TOTAL NEW MAPS -33

TOTAL MAPS 114

26

Page 30: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ENERGY MEASUREMENTSRSL YMP Suppout OfficeEG&G Energy Measurements, IncP.O. Box 1912 M/S: V.02Las Vegas, Nevada 89125Telephone: (702)794-7852

FAX: (702)794.7469 TRANSMIlTALDate Sent: A/y i jp

N Robert Nelson napHaWe 794-7920

ORUNWATM DOE/YMPO

ADORESS BOA, 101 Convention Center Drive,Las Vegas, NV 89109

3 . .FEO-, C LI . . --t . ---- -r* o

One page size copy of:

YMP-93-307.0YMP-93-306.0YMP-93-305.0YMP-93-030.6YMP-94-047.0YMP-94-045.0YMP-94-044.0YMP-94-040.0YMP-94-039.0YMP-94-038.0YMP-94-034.0YMP-94-033.0YMP-94-031.0YMP-94-030.0YMP-94-029.0YMP-94-028.0YMP-94-027.0

YMP-94-026.0YMP-94-025.0YMP-94-024.0YMP-94-023.0YMP-94-022.0YM4P-94-017.0YMP-94-016.0YMP-94-009.0YMP-94-006.0YMP-94-005.1YMP-94-005.0YMP-94-004.0YMP-94-003.0

.W

APPRO.ED VID3Y $ I*Y| 3///q

WHOIT: RPA U Mmt Cusw~w YaLDW. YUUOwr PPe ML CC"

Form Y300M (Mm S1

Page 31: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ENERGY MEASUREMENTS

RSL YMP Support OfficeEG&G Energy Measurements, Inc.P.O. Box 1912. MfS: VY02Las Vegas, Nevada 89125Telephone: (702)794-7852

FAX: (702)794-7469

..S 1.2.5.36

:TRAOING DESIGNATOlT -R940319I404M '

WORK REQUESTToday's Date, 3116/94

,.1 f 71-

TO BE COMPLETED BY THE REQUESTOR: YMP Participant (YIN) Y

NAME: Robert Nelson SIGNATURE:

ORGANIZATION: DOE/YMPO TEpHONE: 794-7920

ADDRESS: BOA, 101 Convention Center Drive, Las Vegas. NV 89109

PURPOSEOFPROOUCT: Monthly Progress Report

WU TFIE PRODUCT BE USED IN OtULITY-AFFECTNG WORK? NO DATENEEDED: 3/28/94 RELEASAME DATA (YAM Y

PRODUCT FORMAT HDc: X Nu f atCopie: 1asr Scs:Page ofei NAoIg: NA Os: NA FlFrm= NA media: Paper

WORK DESCRIPTION:

Provide one page size copy of each of the new map products generated duringthe month of February 1994.

. . ,~~~~~~~~~~~~~~~~~~~~

TOZ.E PLrTED: BYGENIS SE POELD.T-- - j .ob-'Ee . . - .ii .t.- I

jcoetEalimata(YA4): ?40 'I �'�W�'I� NO r&md�edDUwfYDS�: 31?8f94

.. X:: :'.:' e... ' p ,- -. -.. ,GI.:.SAnys AI. .:. : -.flne J i h a -..- :.

RECEIVED DY:__-_-_- .j ., ._ _

APPROVED' : . - " gr' m Y -

IHIlE: RPwd GLUE: Custow yLLOW: YUPSO CoyINSTRUCTNs PROvYEDON BaCK)

I I I~~~~~~~~~~i

PNC RSL COPY

FormY3S20(Feb OM

Page 32: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

EIVERGYMEASREMVETS WBS: / 2. 53 (aTracking Number: IJ4ito~3i An

CUSTOMER EVALUATION

PRODUCT DELIVERED: DIGITAL DATA TRANSFER DATA REPORT OTHER

MAP PRODUCT ' PHOTO PRODUCT

~~~~~~~~~~~~~~~~~~~~.. -., .. ... :. . .I

5.:.CELL~rrr 4- GOOD 3 - RSATIFACTORY 2 - MARGINAL I - UNSAISFACTORY

PLEASE CIRCLE THE NUMBER WHICH CORRESPONDS TO YOUR RATING OF EACH ITEM, USING THE ABOVE SCALEAS REFERENCE.

1. THE PROCESS FOR REQUESTING THE PRODUCT 5 4 3 2 1WAS:

2. INTERACTIONS WITH THE STAFF WERE: 5 4 3 2 1

3. INTEGRATION OF ALL REQUESTED INFORMATION 5 4 3 2 1INTO THE PRODUCT WAS:

4. TIMELINESS OF THE PRODUCT WAS: 5 4 3 2 1

5. THE OVERALL QUALITY OF THE PRODUCT WAS: 5 4 3 2 1

8. AN OVERALL RATING OF THE SUPPORT PROVIDED: 5 4 3 2 1

WE ARE ALSO INTERESTED IN THE USEFULNESS OF OUR PRODUCTS. THE SIGNIFICANCE OF THE PRODUCT FORITS INTENDED USE WAS: (Please circle the appropriate number)

5 = CRITICAL 4 - IMPORTANT 3 - USEFUL 2 - LIMITED 1 - INSIGNIFICANT

BRIEFLY EXPLAIN HOW THE PRODUCT WAS USED.

IF YOU RATED ANY OF THE ABOVE ITEMS 1 OR 2. PLEASE EXPLAIN HOW THE PRODUCTS OR SERVICESPROVIDED COULD BE IMPROVED.

COMMENTS:

NAME: DATE: ORG:(Optional - for follow-up If necessary)

FOLD IN HALF AND STAPLE - ADDRESS IS ON BACK OF THIS FORMor FAX - (702)794-7469

Page 33: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

. 1

Los AlamosNATIONAL LABORATORYEarth and Environmental Sciences DivisionEES-13-#ucisar Waste Management R&D

N

WBS 12.9.1 -

QA N/A U;

U:November 16, 1993

TWS-EES-13-11-93-024

Mr. J. Russell Dyer, Acting Project ManagerYucca Mountain Site Characterization Project OfficeUS Department of EnergyP.O. Box 98608Las Vegas, NV 89193-8608

Dear Mr. Dyer.

Highlights of the Los Alamos Monthly Activity Report-October 1993

Attached are the highlights of the Los Alamos Monthly Activity Report for October 1993. Thisinternal document describes our technical work; however, the report has not received formaltechnical or policy review by Los Alamos or the Yucca Mountain Site Characterization Project. Datapresented in this document constitute predecisional information, should not be referenced, and arenot intended for release from the US. Department of Energy as referenceable information.

I

If you have changes to our distribution list, please call Susan Klein at (505) 667-0916.

Sincerely,

JuliX A anpa

LI

SH1Kelm

Attachment: a/s

Cy wlatt:MV. B. Blanchard, DOE/YMP, Las Vegas, NVW. L. Clarke, LLNL, Livermore, CAW. R. Dixon, DOE/YMP, Las Vegas, NVN. Z. Elkins, EES-13/LV, MS J900/527L. D. Foust, M&OfIRW, Las Vegas, NVL. R. Hayes, USGS, Denver, COV. F. Iorii, DOE/YMP, Las Vegas, NVS. H. Klein, EES-13, MS J521

M. Martin, M&O/TRW, Las Vegas, NVA. R. Pratt, EES-13, MS J521L. Shephard, SNL, Albuquerque, NMW. Simecka, DOE/YMP, Las Vegas, NVM. Voegele, SAIC, Las Vegas, NVRPC File (2), MS M321TWS-EES-13 File. MS J521

An Equal Opportunity Employer/Operated by the University of California

ENICLOSURE 71

Page 34: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Highlights from Los Alamos for October 1993

The following Los Alamos milestones were completed:

3342, "Progress Report on Analyses of Core, Cuttings, and ESF samples forAlteration History"

3365, "Field Guide to Fracture-lining Minerals"

3329, "Measured Solubilities and Speciations from Oversaturation Experiments ofNeptunium, Plutonium, and Americium in UE-25 Groundwater"

3381, "Natural Alteration in the Cooling Topopah Spring Tuff, Yucca Mountain,Nevada as an Analog to a Waste-Repository Hydrothermal Regime"

4012, "Diagenetic Alteration of Tuffs in Yucca Wash and Northern Crater Flat"

The following Los Alamos report was published:

"Geologic Evaluation of Six Nonwelded Tuff Sites in the Vicinity of Yucca

Mountain, Nevada for a Surface-Based Test Facility for the Yucca Mountain Project"

by D. Broxton, S. Chipera, F. Byers Jr., and C. Rautman (LA-12542-MS, 83 pp.).

Los Alamos hosted the DOE/NRC Technical Exchange on Radionuclide Migration, October

13-15. Los Alamos principal investigator Ines Triay presented results of a thorough study of

Np sorption onto Yucca Mountain tuffs as a function of temperature, groundwater

chemistry, and radionuclide concentration. This sorption data will be used in the next

Performance Assessment cycle. Robert Rundberg of the International Programs project

presented supplementary information, concentrating on the mechanistic aspects of Np

sorption onto oxide minerals. Results of solubility experiments on Pu, Am, and Np in J-13

and UE-25p #1 water were presented by Lawrence Berkeley Laboratory staff. C. Drew Tait

discussed results of Pu speciation in carbonate systems. He also presented data on the study

of Np speciation, using NMR and uranium carbonate, which validated the Nuclear Energy

Agency database. Pamela Rogers presented AFM studies of the surface of iron oxides; the

intent of this work is to elucidate surface reactions of radionuclides with tuff. A Los Alamos

site visit was conducted on October 15 and included presentations at the Photoacoustic

Spectroscopy laboratory, Transport laboratory, Atomic Force Microscopy laboratory, Mass

Specrometer laboratory, and Caisson facility.

Predecisionl informaton-preliminry data--do not reference II

Page 35: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Los Alamos Monthly Highlights for October 1993

WBS 1.2.3.1.2 Test Management and Integration. Staff represented the Test Coordination

Office at weekly surface-based testing meetings and participated in review of proposed

Revision 4 of AP-5.21Q, Field Work Activation. Staff provided field coordination and PI

support for three ESF'north-portal starter tunnel tests: Geologic Mapping, Constrqction

Monitoring, and Perched Water (a contingency test in the starter tunnel). Staff began

planning Los Alamos sample collection activities in the SRG-5 borehole in support of WBS

1.233.1.2.2.

WBS 1.2.3.2.1.1.1 Transport Pathways. In XRD studies, new chabazite and clinoptilolite

samples from Western Idaho and Eastern Washington were characterized as new references

to improve the quantitative analysis of zeolites from Yucca Mountain. XRD studies of UZ-16

were extended into the Topopah Spring Member, and sample preparation on deeper

samples resumed. XRD analysis of the basal vitrophyre of the Topopah Spring Member was

emphasized this month; these data will be compared with the alteration associated with the

upper vitrophyre of the Topopah Spring Member, analyzed earlier this summer. Alteration

associated with the vitrophyres provides information on both early high-temperature

processes at Yucca Mountain (analogous to some potential repository-induced thermal

alteration) and later lower-temperature water-rock interaction with transport through the

unsaturated zone.

G. Guthrie and D. Bish presented a short course for the Mineralogical Society of America

titled 'Health Effects of Mineral Dusts," 22-24 October in association with the Geological

Society of America meeting in Boston, MA. G. Guthrie also moderated a symposium titled

"Geochemical Aspects of Minerals in Physiological Fluids." The short course and the

symposium appear to be ushering in a new interest within the Mineralogical Society of

America in environmental mineralogy, as evidenced by discussions at the Mineralogical

Society of America business meeting. W. Carey, B. Carlos, and R. Raymond also attended

the Geological Society of America meeting.

Laboratory experiments suggest that silica dissolution, migration, and deposition is likely

to occur along the waste-imposed thermal gradient. Late-stage cooling fractures in the

devitrified Topopah Spring Member indicate the consequences of fracture-related silica

leaching. Backscattered-electron images of a quartz-filled fracture in the Topopah Spring

Member (drill core USW G-4, 984 ft depth) show significantly increased porosity within

2 mm of the fracture. This porosity is readily seen in SEM images. The nature of the silica

dissolution that is involved in the development of this pore space is revealed in XRD

Predecisional informatiopreliminary dat-do not reference 2

Page 36: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Los Alamos Monthly Highlights for October 1993

studies that show extensive loss of cristobalite (but not of feldspars and quartz) adjacent to

the fracture. The loss of cristobalite and development of porosity are also evident in high-

magnification SEM images of a cristobalite-rich horizon of the Topopah Spring Member in

drill core USW G-2, 1505 ft depth. The anhedral cristobalite grains that are prominent in

unaltered portions of the tuff are almost entirely absent in the altered portions, leaving large

amounts of pore space.

A paper titled "Paleogeothermal and Paleohydrologic Conditions in Silicic Tuff from

Yucca Mountain, Nevada" (D. Bish and J. Aronson; Clays and Clay Min. 41, pp. 148-161) was

distributed. This report describes the termination of significant hydrothermal activity

beneath Yucca Mountain 11 million years ago.

A report titled 'Geologic Evaluation of Six Nonwelded Tuff Sites in the Vicinity of Yucca

Mountain, Nevada for a Surface-Based Test Facility for the Yucca Mountain Project" was

published (D. Broxton, S. Chipera, F. Byers, Jr., and C. Rautman; LA-12542-MS, 83 pp.). This

report examines the lithologic, chemical, mineralogic, and hydrologic properties of five

possible sites for surface-based test facilities in both vitric and zeolitic nonwelded tuffs.

Surface-based facilities can be used to supplement the information to be obtained from ESF

tests beneath the actual repository block; surface sites may become particularly important if

ESF workings do not allow access to portions of the Calico Hills Formation. The report

recommends sites at Busted Butte (vitric nonwelded) and at Prow Pass (zeolitic

nonwelded).

WBS 12.3.2.1.2 Stability of Minerals and Classes. Staff continued to write the study plan

for this activity. A discussion of reaction kinetics, particularly for cristobalite, was

included, incorporating recent experimental results. Staff also included recent results that

suggest that both analcime and clinoptilolite undergo congruent dissolution at rates much

slower than rates obtained from simple batch experiments. The dissolution rates of analcime

and clinoptilolite also appear to decrease as the silica concentration increases.

WBS 1Z3A..1±3 Sorption Models. Staff participated in the DOE/NRC Technical Exchange

Meeting, giving two oral presentations and hosting a tour of the AFM facility. Staff

prepared an abstract for the national MRS meeting in December, and they are writing a

paper to be included in the proceedings from that meeting.

Predecisioanl infomtation-pirlinuiary data-do not reference 3

Page 37: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Los Alamos Monthly Highlights for October 1993

WBS 1.2.3.4.1.3 Speciation/Solubility.

Speciation. Task members participated in the NRC Technical Exchange held in Los Alamos

on 13-15 October. A presentation was made by C. Drew Tait titled "Actinide Carbonate

Speciation Studies by PAS and NMR Spectroscopies." Tours of the laboratory areas

(including the PAS spectrometer) in the CMR building were conducted for meeting

attendees. A large-scale reprocessing/purification effort to generate a new stock of Np-237

solution is presently underway, with a pilot trial completed this month. This effort is

anticipated to be the focus of activities during November. PAS studies continued on the

Pu(lV)-carbonate system, with quantitative measurements on the 485.5 nm peak as a

function of pH and on the speciation of the system at pH=8.5 and low (bi)carbonate

concentrations. Control experiments were conducted in the temperature-dependent

absorption study of the Np(02)+-carbonate system.

Solubility. Staff from Lawrence Berkeley Laboratory made a presentation titled "Recent

Solubility Results" at the NRC Technical Exchange on 13-15 October.

WBS 12.3.4.1.5.1 Retardation Sensitivity Analysis.

Integrated Transport. Staff prepared a draft of a final report on the FY93 site-scale flow and

transport simulation. It is anticipated that three species of Np, Cs, and Sr will be modeled.

A video showing modeling results for FY93 was completed and shown at the DOE-NRC

exchange on 13-15 October. Staff met With W. Glassley of LLNL to discuss the EQ3/6

interface for FEHM.

Code optimization. The memory-managed version of FEHM has been put under

configuration management. The system is marketed by INTERSOLV.

WBS 116 Exploratory Studies Facility. Staff completed three test planning and job

packages: Geologic Mapping, Construction Monitoring, and Perched Water for the north-

ramp starter tunnel. Staff began planning for the LLNL large block test; site selection at Fran

Ridge for this test was underway.

Predecisionol information-prelimwiwy data-do not reference 4

Page 38: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Los Alamos Monthly Highlights for October 1993

WBS 1.2.6.8.4 IDS. The IDS design and development work continued on schedule;. the

M&O is responsible for design and development of IDS for various PI's. This month the

M&O completed an engineering plan for IDS, which was reviewed by Los Alamos, signed

by the ED&D, and released by the M&O.

Staff visited WIPP at Carlsbad, New Mexico, to become familiar with the data management

system used at there. They met with staff from the U.S. Bureau of Mines, Denver Branch, to

discuss IDS concepts developed by this branch for the mining industry.

Predecisional infonnanion-preliminary data-do not reference 5

Page 39: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Los AlamosNATIONAL LABORATORYEarth and Enviromnental Sciences DvisionEES-13-Nudear Waste Management R&D

WBS 1.2.9.1QA N/A

December 15, 1993

TWS-EES-13-12-93-027

Mr. Robert M. Nelson, Acting Project ManagerYucca Mountain Site Characterization Project OfficeUS Department of EnergyP.O. Box 98608Las Vegas, NV 89193-8608

Dear Mr. Nelson:

Highlights of the Los Alamos Monthly Activity Report-November 1993

Attached are the highlights of the Los Alamos Monthly Activity Report for November 1993. Thisinternal document describes our technical work, however, the report has not received formaltechnical or policy review by Los Alamos or the Yucca Mountain Site Characterization Project. Datapresented in this document constitute predecisional information, should not be referenced, and arenot intended for release from the US. Department of Energy as referenceable information.

If you have changes to our distribution list, please call Susan lein at (505) 667-0916.

I-Ea

Sincerely,

61Ž-I '-

0A4At%

a Q o o o o C,)M Icj

ZN

o-N.;

bcQ

lt�;IQ-\

I-- Q)

kySHE/elm

Attachment: a/a

Cy W/att:M. B. Blanchard, DOE/M, Las Vegas, NVW. L. Clarke, LLNL, Livermore, CAW. R. Dixon, DOE/YMP, Las Vegas, NVJ. R. Dyer, DOE/YMP, Las Vegas, NVN. Z. Elkins, EES-13/LV, MS J900/527L. D. Foust, M&OiTRW, Las Vegas, NVL. R Hayes, USGS, Denver, COV. F. Iorii, DOE/YMP, Las Vegas, NVS. H. Klein, EES-13, MS J521

M. Martin, M&O/TRW, Las Vegas, NVA. R. Pratt, EES-13, MS J521L. Shephard, SNL, Albuquerque, NMW. Simecka, DOEJYMP, Las Vegas, NVJ. Mercer-Smith, EES-13, MS J521M. Voegele, SAIC, Las Vegas, NVRPC File (2), MS M321TWS-EES-13 File, MS J521

C'

shv,

An Equal Opportunity Employer/Operated by the University of CaliforniaENCLOSURE 1'2-

Page 40: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Highlights from Los Alamos for November 1993

WBS 123.1.1 Site Management. Los Alamos named Dr. J. Mercer-Smith as Project Leader forSite and Regulatory Investigation and Dr. C. Duffy as technical coordinator for geochemistry.

Staff met with A. Simmons and S. Nelson on 10 November to review milestones completed forFY93 and milestones planned for FY94 for the geochemistry, mineralogy/petrology, andretardation sensitivity analysis tasks.

WBS 1.2.3.1.2/.3 Test Management and Integration. Staff represented the Test CoordinationOffice at weekly surface-based testing meetings and M&O workscope coordination meetings.Staff provided multi-shift field coordination and PI support for ESF North Ramp starter tunneltests. Planning on the Phase 3 ESF tests was initiated including the M&O test-to-test, test-to-construction, and waste isolation evaluations.

The construction of the ESF starter tunnel alcove to support testing is nearing completion. Theactivity is fully supported by geologic mapping, consolidated sampling, hydrochemistry, andconstruction monitoring test activities; no perched water has been identified in the ESF.

WBS 1Z3.21.1.1 Transport Pathways. Quantitative-mineralogy data collection was completedfor all intervals of drill core UE-25 UZ-16, and the data are presently being prepared forquantitative analysis. Samnple spacing is closer in this core than in previous core studies,providing greater confidence in mineral-abundance trends important for sorption, waterevolution, and thermal loading evaluation. Particularly important are the distributions of thesilica polymorphs (quart, cristobalite, and tridymite); variability in the stabilities of thesepolymorphs is an important factor in silica dissolution/precipitation under thermal loading.

WBS 1±3±5 Volcanism. B. Crowe gave a presentation titled "Probability and MagmaticEffects" to the National Academy of Sciences on 9 November.

Following a systematic review of field relationships at the Lathrop Wells volcanic center, staffreached a strong consensus that Lathrop Wells was formed in four major eruptive episodes,separated by significant time breaks of thousands to tens of thousands of years. This polycyliceruptive behavior will be factored into volcanic risk assessment.

WBS 1±.3.3.1.3.1 Reactive Tracer Testing. Transport experiments were conducted on each ofthe C-Wells fracture specimens for Task 1.23.4.1.4. These fractures were not as well mated asthe Bandelier tuff fracture run previously, and the dispersive characteristics are somewhatdifferent. Nonetheless, systematic differences in the dissolved iodide and microsphere tracerbreakthrough curves are evidence of matrix diffusion effects in the Yucca Mountain fractures.

WBS 1.3.4.1.2.1 Batch Sorption. Staff continued to perform batch sorption experiments tostudy the influence of organic coatings on Np sorption onto tuff. Our results indicate thatdihydroxyphenylalanine (dopa) does not have a significant influence on Np sorption onto oxideminerals, which suggests that dopa does not have a strong affinity for Np and does notinfluence its sorption behavior significantly.

Staff submitted a summary of the sorption data to be used in the Total System PerformanceAssessment calculations for 1993 to the performance assessment group of SNL.

Predecisiora infonnadon-preliminary data-do not referenwe l

Page 41: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

November 1993 Highlights from Los Alamos

WBS 12.3.4.1Z3 Sorption Models. Staff prepared a presentation for the Materials ResearchSociety fall meeting in December. They received a sample of maghemite separated from YuccaMountain tuff and are developing methods to mount the sample for AFM experiments.

WBS 1.2.3.4.1.3 SpeciationlSolubility. Speciation. Despite a large number of publications, thecurrent knowledge of the solubility and hydrolysis constants for Np(V) is unsatisfactory, andthis problem must be resolved before solubility and sorption data can be modeled. A properunderstanding of NpO2+ hydrolysis reactions is also a prerequisite for understanding NpO2+carbonate complexation reactions, which will be the key thrust area for this task in FY94. Thismonth they began to review the data in the literature to determine the trends and the conditionsunder which they can examine the hydrolysis.

The temperature dependent UV-VIS-NIR absorption study on Np(V)-carbonate complexescontinued this month, concentrating on the 'NpO2(C0 3)-" and 'NpO2(C03)2 3 - equillibrium.

Solubility. Staff continued the Np, Pu, and Am solubility experiments in 0.1 M NaCl04.

WBS 123.4.1.4.112 Transport. The study plan for Diffusion (WBS 1.2.3.4.1A.2) was approvedby YMPO.

Staff collected eight water samples from Well J-13 and distributed them to five investigators;they will use light scattering techniques to determine the particle concentration in each sample.

Staff began studies to assess the transport behavior of radionuclides in fractures. Six fracturessamples for these experiments are expected from the SMF in January 1994.

Using fracture samples from the ESF, staff performed batch sorption experiments to determinewhether the retardation of radionuclides by the minerals in the fractures is different from theretardation provided by the tuff matrix. They obtained sorption coefficients for two initial Npconcentrations

Preliminary XRD measurements on the ESP samples indicated that the sample from the fracturecenter is mainly quartz and the sample from the material closer to the fracture walls is mainlycalcite. Our Np retardation results for these samples are in good agreement with batch sorptioncoefficients obtained for pure minerals and tuff. Previous results (reported in earlier LosAlamos Monthly Activity Reports) indicate that Np sorption coefficients for quartz range from 0to 0.5 ml/g in J-13 water in the Np concentration range from 3 x 10-5 to 7 x 10-7 M. Np sorptioncoefficients for synthetic calcite range from 1 to 50 ml/g in J-13 water in the Np concentrationrange from 3 x 10-5 to 7 x 10-7 M. The Np sorption coefficients for non-zeolitic tuff range from 0to 2 m/g in J-13 in the same Np concentration range. This result is important because it appearsto indicate that batch sorption coefficients obtained with the mineral phases that predominate inthe fractures could be used to predict the transport of radionuclides in fractured tuff.

WBS 1.26 Exploratory Studies Facility. Staff supported field activities at the Fran Ridge sitefor the LLNL large-block test. Site preparation activities are underway and test constructionactivities are in the final planning stage.

Predecsionl ifomain-preliminary data-do not referene2 2

Page 42: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

t:

November 1993 Highlights from Los Alamos

WBS 12.6.8.4 IDS. Staff provided darification of design requirements and continuedintegration and review of data-flow requirements controlled by test planning records andYMPO procedures. Staff reviewed field record submissions and facilitated data transfers to theconstruction and test organizations.

WBS 1±9.2.2 Project Control. The annual financial audit of Los Alamos was conducted byKPMG Peat Marwick. No identifiable concerns were noted.

Representatives of the Inspector General's office returned to Los Alamos to discuss issuesbrought up at their August 1993 Los Alamos visit. These issues were resolved by the TPO.

WBS 1.2.11.2/.31.5 Quality Assurance. Our major focus continues on revising documents tosatisfy the new Quality Assurance Requirements and Description (QARD). Of the forty-eightaffected documents, two are still in revision. All oter documents are in final preparation. Twodetailed technical procedures were issued.

Publications and MilestonesApproved by YMPO

Milestone 3252, 'Simulation Modeling of the Probability of Magmatic Disruption of thePotential Yucca Mountain Site'

M. Hawley and P. Rogers, 'Surface Reactions of Goethite Observed by AFM"(abstract for Minerals Research Society meeting)

Completed and forwarded to YMPO:Milestone 3348, "Colloid-facilitated Radionuclide Transport"Milestone 3357, "Caisson Experiments to test Flow and Transport Models"David Clark, 'Molecular Models for Actinide Speciation"Steven Bolivar, "Los Alamos 1992 Quality Assurance Status Report"Paul Reimus, "Transport of Synthetic Coloids and a Nonsorbing Solute Through aSaturated Natural Fracture"

Received by the TPO:Milestone 3351, "C-13 and 0-17 NMR Binding Constant Studies of Uranyl Carbonate

Complexes in Near-neutral Aqueous solutions"Milestone 3350, "Pu Carbonate Speciatiion Changes as Measured in Dilute Solutions"

Predecisional fomation-preliminary data-do not referenc 3

Page 43: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

November 1993 Highlights from Los Alamos

MONTHLY COSTUFTE REPORT

"Ij ~~~~~~~~~~~~~~~~~~~Fiscal Year|_________________________________________________________ 11994

WBS' |Actual Participant Subcon Purchase Subcon Accrued Approved Approved CumulativeElement

Costs Hours Hours Commitme Commitme Costs* Budget Funds Costs________ nts nts

1.2.1 0.0 0.0 0.0 0.0 40.0 10.0 0.0

1.2.3 751.5 4,671.0 1,677.9 319.8 9,274.0 2,308.0 1,165.

1.2.5 42.8 360.2 4.2 4.5 725.0 181.3 74.8

1.2.6 197.9 1,001.7 1,117.7 77.4 2,150.0 537.5 318.1

1.2.9 83.0 405.8 453.4 34.7 1,220.0 250.0 130.8

11211 58.9 313.1 257.9 49.1 1,200.0 300.0 91.4

1.2.12 68.7 0.0 851.4 48.4 500.0 125.0 68.9

1.113 1.4 15.2 0.0 0.0 100.0 25.0 5.4

1.2.15 45.7 229.5 196.9 18.0 538.0 134.5 79.9

Totals 1,249.9 6,996.6 4,559.4 551.9 0.0 15,747.0 3,871.3 1,934.

Predczsional informadon-prenuinary dEta-do not referncew 4

Page 44: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

November 1993 Highlights from Los Alamos

Variance Analysis ReportStatus through November 30,1993

PARTICIPANT: LANL PEM: WBS: 1.2.3A.13.1

WsS TITLE: Dissolved Species Concentration Umits

P&S ACCOUNT: 0A34131

FY 1994 Cumulative to Date > FY 1994 at Completion

BCWS BCWl ACWQ SV I SV% I SPI I CV I CV% I CP1 I BAC I EAC I VAC I VA lEACI P1161 161 50 0 0.0 100. )111 168.9 322.0 1068 1017151 4.8 322 93.8

Analysis

Cumulative Cost Varlance:

The variance shown in this account is due to an LBL contract invoice which was not costed in November. The ETChas been adjusted to reflect the pending costing of this invoice, which is anticipated shortly.

Cumulative Schedole Variance:

(Not reportable)

Variance At Complete:

(Not reportable)

Prededszonal infomation-preiminary data-do not referene 5

Page 45: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

November 1993 Highlights from Los Alamos

PARTICIPANT: LANL PEM: WBS: l2.3.4.145.1

WBS TITLE: Retardation Sensitivity Analysis

P&S ACCOUNT: OA34151

W.umulauv 10 oac > FY 1994 at Completion >

BCWS| BCWP| ACWP SV I SV% I SPI I CV I CV% I CPI BACI EAC I VAC I VAC9/ IBAC I TCP121 1 96 1 153 1 -25 1 -20.71 79.3 1 -57 1 -59.41 62.7 1 457 587 1 -130 1 -28.41 729 1 83.2

Analysis

Cumulative Cost Variance:

(Not reportable)

Cumulative Schedule Variance:

(Not reportable)

Variance at Complete:

The VAC shown by Los Alamos in this P&S account is attributed to an ernor in the ETCs for one of the componentsumnary accounts (OA341SILBO - Perform Integ. Trans Calc/Geochem/Phys Mod), which has been corrected, andto a work station error in another component summary account (OA341SlLC7 - Capital Equipment Update SunWorkstation N/Wrk), which mistakenly omitted BCWS and BCWP values for an account that is already completedand closed. Los Alamos will work with the PACS M&O to rectify the latter problem.

P&S ACCOUNT MANAGER DATE TPO DATE

Predecisional onnadon-pretlinary data-do not reference 6

Page 46: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Participant LANL Yucca Mtn. Site Cher. Project-Plennsing Control System 01-Nov-93 to 30-Nov-93PACS Participant Work Station (PPVS) Page - 1

Prepared - 12/14/93:15:53:14 UBS Status Sheet (W1S02) Inc. Dollars In Thousands

UBS No. - 1.2 UDS Manager

Wes Title - YUCCA MOUNTAIN PROJECT

Parent UBS No. Parent UBS Manager -

Parent USS Title

Statement of Work

See the current UBS Dictionary

Cost/Schedute PerformanceCurrent Period n1994 Cuiulative to Date FY1994 at Completion

id Description BCVS BCWP ACWP SV CV 8CWS BCWP ACWP SV CV BAC EAC VAC-1.2.1 SYSTEMS ENINEERING 6 6 0 0 6 6 6 0 0 6 40 34 61.2.3 SITE INWVESTIGATIONS 646 587 884 -59 .297 1264 1205 1312 -59 -107 9274 9491 -2171.2.5 REGULATORY 51 51 15 0 36 8S 85 46 0 39 725 686 391.2.6 EXPLORATORY STUDIES FACILI 143 143 152 0 -9 282 282 274 0 8 2150 2142 81.2.9 PROJECT MANAGEMENT 93 93 84 0 9 184 184 132 0 52 1220 1197 231.2.11 CUALITY ASSURANCE 104 104 108 0 -4 188 188 139 0 49 1200 1151 491.2.12 INFORMATION MANAGEMENT 34 34 69 0 -35 67 67 70 0 -3 500 503 -31.2.13 ENVIRONMENTV1 SAFETY, & EA 8 8 1 0 7 16 16 5 0 11 100 89 * 111.2.15 SUPPORT SERVICES 51 51 46 0 5 84 84 tO 0 4 538 534 4Total 1136 1077 1359 -59 .282 2176 2117 20M8 -59 59 15747 15827 -80

Resource Distributions by Element of CostFiacal Year 1994Budgeted Cost of Work Scheduled

Oct Nov Dee Jan Feb Mar Apr May Jun Jut Aug Sep TotalLBRHRS 6994 7413 7298 7462 7556 7569 7729 7837 7h56 7762 7752 7830 90958LABOR 502 527 518 532 556 577 599 623 605 600 572 585 6796SUBS 203 243 27 298 313 321 346 346 356 354 343 374 -3774TRAWVL 13 19 25 31 37 U 50 54 55 53 30 20 431PM1E 0 0 0 0 0 0 0 0 0 0 0 0 0OTHER 322 347 339 363 386 414 428 454 438 426 402 404 4723CAPITAL 0 0 0 23 0 0 0 0 0 0 0 0 23

Total 0CIS 1040 1136 1159 1247 1292 1356 1423 1477 1454 1433 1347 1383 15747

Page 47: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Participant LAML Yucca Ntn. Site Char. ProJect-Planning & Control System 01i-ov-93 to 30-Nov-93PACS PartfcIpant Work Station (PPWS) Page - 2

Prepared - 12/14/93:15:53:14 WuS Status Shest (1BS02) Ine. Dollars In thousands

Was No. - 1.2 -YUCCA M U TAIM PROJECT

Resource Distributions by Element of CoatFiscal Year 1994Actual Cost of Work Performed

Oct Nov DeC Jon Feb Mar Apr MAy Jun Jul Aug Sep TotalLBRHRS 6360 7034 0 0 0 0 0 0 0 0 0 0 13394LABOR 492 524 0 0 0 0 0 0 0 0 0 0 1016SUBS -65 331 0 0 0 0 0 0 0 0 0 0 266TRAVEL 18 46 0 0 0 0 0 0 0 0 0 0 64PM&E 0 0 0 0 0 0 0 0 0 0 0 0 0OTHER 254 370 0 0 0 0 0 0 0 0 0 0 624CAPITAL 0 88 0 0 0 0 0 0 0 0 0 0 88

Total ACWP 699 1359 0 0 0 0 0 0 0 0 0 0 2058

Resource DistributionsFiscal Year 1994 Oct Nov Dee Jan Feb Mar Apr may Jun Jul Aug Sep Total

BCUS 1040 1136 1159 1247 1292 1356 1423 1477 1454 1433 1347 1383 15747BCUP 1040 1077 0 0 0 0 0 0 0 0 0 0 2117ACUP 699 1359 0 0 0 0 0 0 0 0 0 0 2058ETC 0 0 1078 1233 1298 1378 1434 1496 1489 1471 1379 1513 13769

Fiscal Year Distribution AtPrior FY1994 FY1995 FY1996 FY1997 FY1998 FY1999 FYZOO2 FY2C01 FY2002 FY2003 Future Couplete

BCUS 14806 15747 37934 30943 26879 22465 16003 11087 9150 0 0 0 18S014BCWP 14644 2117 0 0 0 0 0 0 0 0 0 0ACWP 14238 2058 0 0 0 0 0 0 0 0 0 0ETC 0 13769 34173 32355 28130 22258 16859 11795 9600 0 0 0 185235

Page 48: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

WBS: 1.2.9.1QA: N/A

Los AlamosNATIONAL LABORATORYEnd and Bcez DIYW=

20l632 t

EES.3-Nudear Wate Management R&DMail Stop J521 Les Alms, NM S74Phone (506) 667 Fao (30) 667.194

March 11, 1994

LA-EES-13-03-94-003

Mr. Robert M. Nelson, Acting Project ManagerYucca Mountain Site Characterization Project OfficeUS Department of EnergyP.O. Box 98608Las Vegas, NV 89193-8608

Dear Mr. Nelson:

Los Alamos Monthly Activity Repart-December 1994

I- 0 6/1 �, CIO N

Attached is the Ls Alamos Monthly Activity Report for December 1994. This internal documentdescribes our technical work; however, the report has not received focnal technical or policy reviewby Los Alamos or the Yucca Mountain Site Characterization Project. Data presented in thisdocument constitute predecisional information, should not be referenced, and are not intended forrelease from the U.S. Department of Energy as referenceable information.

If you have changes to our distribution list, please call Susan Klein at (505) 667-0916.

0-41

Wth

a

Sincerely,

J ie . Canepa

4~

SHI~elm

Attachment- els

Cy w/attM.B. Blanchard, DOF.YMP, Las Vegas, NVW.L Clarke, LLNL, Livermore, CAW.R. Dixon, DOEWYMP, Las Vegas, NVJ.R Dyer, DOSYMP, Les Vegas, NVN.Z. Elkinr, EES-18tV, MS J90C527LD. Foust, M&OQIRW, Las Vegas, NVLR. Hayes, USGS, Denver, COV.F. Iorui, DOEIYMP, Las Vegas, NVS.H Klein, EES-13, MS J521

M.M. Martin, M&O/rRW, Las Vegas, NVA.R. Pratt, EES-13, MS J521LE. Shephard, SNL, Albuquerque, NM

, W.B. Simea, DOF/YMP, Las Vegas, NVJ.A. Mercer-Smith, EES-13, MS J521M.D. Voegele, SAIC, Las Vegas, NVRPC File (2), MS M321LA-EES-13 File, MS J521

An Equal OPportdty E'vloyerm erated by the Univmity of caifoma ENCLOSURE le

Page 49: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

mm

-mm

-mm

* mm

mu

*

a- - - .

-ft M..t m - Vmm1&Wfw ~ sw ~fX

IfE - -*S - .9m

: b - mau m in ,wa m a H

Yuc MountinSite aProjeSaft Site Locaion hd

Ama no

Page 50: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

lififf

YUCCA MOURTANSITE CHAIACTRIZATION ?IOICT

ISfnXG IOWIOLIS

In!~~~~~~~~~I

' 't' . BBC otuoluot lum

Ak,1'~~~~~~~~~~~~~~~~~~~~~it 'd ... .'t'' x .,bigliatS hA am ti

.~~~~~~~~~~~~~~~~~~~~ us ad how ki ImwuZkr * Af \I - Bbd.CiihupedkiwuO.C-Su

,.VW~~~~~~~~~~~~~~~A

'1> 'I4 i N /1u 'Sr_" W '_

b\I

Page 51: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

156O000I1

[ UZ N > | BZN U0Z// NU

/ UZ.N3.fl IazulO, /< UZN U/ ~ ~~~~ UZZN% 9, u4~

S t U Z~~~~~~~s "<lG Q~~UZ #

§ mzR{TsuilN SZN *IJ UN .1

MN~~~~~~~~~~~~~Nl

§ X BZ-NUW ll *>8 1uz- U4r*?KLJ ZSul

' ! 19 .2t >~~~~~~~~~~~~~~~~~~~.

NR14

Ir UZDN32

9 le N61 \ j~~~61

'I t>.

/~~~~~~~~~~~~~~~

rM 4 M 0A'S O I TRS ^ w~OUI ~ ~~~~~~~~~c

9U-N61

-.5 .5 TCeCA MUNiTI SIRMI~~~lS .5 lu~~HSTING IOUObIES

[JLO0IITU.S ANOW W4WUU

Page 52: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

E556000ft E56000oft E5140001t 1U68000ft

Page 53: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ThermsUMeechaninal MndIG Ghost Dance FaultView of Ghost Dance fault &Repository Limits

450o

4000i

4-a 35((

4 -,

C: ). _ 1

>Z

3000

Base ofRepository

14 PTH

60 CNIII5 8H1.24' CFmn

2 CFAW91 TW

EG&G YMP-94-007.0

Page 54: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ThermnI/MechanircI 3-Dl Mnrla* * 'a' ' ' ' " l''MM1 *-l FEMSl e give

Outline of Repository Limits projectedonto the Topographic Surface

.'.""~. ~ m.

~~~~~~~~oo ~ ~ ~ ~ ~ ~ ~ ~ ~ I ~

EG&G YMP-94-ao.0

Page 55: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

l533840!tIS4m0cm

Iss66eftIssoccea

IS4VO"7EsMOMn

;a -a -J- -a =

Ili 3fw 11 22WIr

TORTOISE OBSERVATIONS

0

A

Marked ICtloose

Unmiaked lortoise

1mills

Contour Interval 200 Feet

ff0. E646 fl(P-94-009.0

Page 56: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Natural BarriersOutside Inside

0 M Unsaturated Zone

E 10 Saturated ZonesotAN

Natural Barriers In:Unsaturated ZoneSaturated Zone

Conceptual ControlledArea Boundary

Repository Umits

6..........

..6........

.... s.......

0%4e

Page 57: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

SECTION A

- 95u.eE .

C

I.a* 96:

e 151

E

950 c

ag

750

700O

\550

0 2800 ^

£ *n2S (c nSo-:

YMP-94-01. O-A

% 2!3:6- n cE7n: Distance (meters)i 5vn.-:

Page 58: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

.I."J U, tag. ! (BSiouS) *uousc a*Ol;K i ) .flt '

--- --- --- -t- --e

: GVE99;) -BStCt. I

009

Oct.

00605:

oa

ons

/005. *t

03

v

a0

3iI0a,

(44noS) 19 8 N011O3S (4PoN) 6

Page 59: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

N2 0 2 1 Ecological Study Plot Nkirber/Averoget 2 MI LES 2 NUzber of Vehicle Posses per Day

2 a 2

K ILIOME TERtS Attst t"04 e

Page 60: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

fT

TECHNICAL DATA BASE INPUT TO 3-D MODELING

THERMAUMECHANICAL 3-D MODEL(View Looking to the Southeast)

TECHNICAL DATA BASE

MARKERS

Wdlljd | arkerjNam T TVD

H-5 TOPO 4sSQ.*, ............. ................ .... .......

H-5 TCw 4440.9......... ..........................

H-5 P n 4251.0........ ....................

H-S TSw2 3268.9..... ........... ...... ............. ............. ...

H-6 M7w3 3196.0

H-S CHnO 2971.0

TCwPTnTSwITSw2TSw3CHn1CHn2

CHh3PPwCFnh

CFMnlCA

CFMn3CRw

WJlID Nomling EasUng Eleveaton

G-4 7660=7.1 56301.6 4166.9.............. . ............... ............................ .. ...

H-t 770254 3 5623".0 4274.4

H-3 75654 .1 55451.7 466.4~~~~~~~~~..... ....... ............... .................... .... ...........

H-4 761643.6 5 1.1 4096.5

H-5 766634.3 56909.7 4850.8

H-6 76329W.9 5S4074.9 4270.6

NRG-6 766725.4 564167.0 4092.0

EGAG YWP-O15k

Page 61: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

MMEP LOG FM THE UNORMEN BOW RAGE FAULTlHENoH 14D, INBER (OWM WALL, NORMI SCH

S WOWvd686 aa" I

mom Amme~~~~~~~~~YMP44419.0

Page 62: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

E w

{ _ *1 . .,: :,.:'-

;; ii. 4, , -;.* J* ff ... .. ;. . 19

11 i@ ,w ; ---- --- --- -i * -- -- --- --- --- -

.I II:;~~~~~~~~~~~~II

. .. .: .: -:, II: ,^ 7. _ :I ' ' ':E " ""U l

Il@ie;;;;,;4,;.Il.l:, ,.llli".#:

Il'l:Cl:II@'U'I:l

-.I/

X, �i,;; �fl

TRENCH LOG FROU TtE NORTHRN BON RIDGE FAULTlRENCH 14D, WNER (OUTI WMLL NORTH BACH

Ihim Yak IS mlqda Is

_ _ _~ML Am M 1YMP44419.1

Page 63: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

C (Northwest) C (Cost)

3- r SECTION C 1 ';)

6 0- -20 BLC 6; !C 0: Z2C 2

' 65 .

9'.-. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ YP9C-20. -

ma:

0 200 4t 6: 2jt 4= ~ ~ ~ MP-4-20 0-

Page 64: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

_ .C..AI.. InD (Northwest) auiciiUri u D (Eas')

ae. Z f-BE'c - Se/-d ,-5

w X -~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~a

752 -5-

6- I AC

_- 2:: 'CC e:c e:; *:: 2:: C2 e:: s:: 2::: 22: 2': se:: 28:2 !C

i" ' _-' nf':: Distance (mneters) 'iv'-t2s ,> sn7o::

YMP-94-021 .0-D

Page 65: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Isiodditf

YUCCA MOUNTAIN SITECHIARACTERIZATION PROJECT

GEOPHYSICAL DATAScale M:1UON

.... . me. .... a.......me S ee - - , ee. .,SeS

N

* zstiad g Ioue~ .1* Lhe I tleletew hlat* UAe I lefue hiul

ROAD IHIOWUS/ ligit WIt laul Class 3, lui Sulace

Uaifproled ba. Clas 4 Gravel SubceTrail. Cla S. lou Wkel Dfie ot OlinCEOIOGIC SIIUIE

.' ' Cao ti, lilDt9 t

A Le ua tc li mit

V taitial ttpsiloJ 0ollutW opiha 38 laip

* n1 ib. ftts.0

hpil~~lk -4 Eumbliem al

b~~iW~~iX"X~~t"I

q - i~~~~~i -~ I i

_ , ,_N

A~ ~ ,,l,' i. __.

Page 66: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ENERGY MEASUREMENTSRSL YMP Support OfficeEG&G Energy Measurements, Inc.P.O. Box 1912. M/S: V-02Las Vegas, Nevada 89125Telephone: (702)794-7852

FAX: (702)794-7469

. . :. '-::':'2..29(, .:'-'~~~~~~~ ~~:" :: ..N" . .....~~O N. Q NA-' ,C

WORK REQUESTToday's Date: 22 41 e75~

TO BE COMPLETED BY THE REOUESTOR:

NAME: Robert Nelson

YMP Participant (Y/N) YL

SIGNATURE:

ORGANIZATION: DOE/YMPO TELEPHONE: 794-7920

BOA. 101 Convention Center Drive, Las Vegas, NV 89109ADDRESS:

PURPOSE OF PRODUCT: _Monthly Progress Report

WLL THE PRODMCT USED IN OUALITY-AFFECTNG WORK? NO DATE NEEDED: 2/28/94 RELEASABLE DATA (YN y

PRODUCT FORMAT Harcopy. X Number of Copies: 1Digital: NA OS: NA

MapSizeorscale: Page oe NAFieFonma: NA Media: PaD

WORK DESCRIPTION:

Provide one page size copy of each of the new map products generated during

the month of January 1994

WHITE: RJed LI BLE: Cunonw YELLOW: YIPSOCopy P1MK RSLCcpy

(INSTRCTONS POViDE ON BACK)Fowm Y3002 (Fab 93)

Page 67: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

'ENERGY MEASUREMENTSRSL YMP Suppot OfficeEG&G Energy Measurements, Inc.P.O. Box 1 912 M/WS: V-02 oK4Q$4tAV./ '9 I JO2Las Vegas, Nevad-a 89125 __ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _

Telephone: (702)794.7852 1,

FAX: (02)794-7469 TRANSMITTAL Data S .Dale Sent|: -2 }¢(;/

NAME: Ponhpr't NIbPsin TELEPHONE: 794-70?i0

ORGANIATON: DOnF/Y0P

ADOMSS BOA., 101 Conventioti Center Drive. Las Veqas, INV 89109

One page size copy ot:

YMP-93-183.2YMP-93-338.0YMP-94-001.0YMP-94-002.0YMp-94-007.0YMP-94-008.0YMP-94-009.0YMP-94-010.0YMP-94-012.0-AYMP-94-013.0-BYMP-94-014.0YMP-94-015.0YMP-94-019.0YMP-94-019.1YMP-94-020.0-CYMP-94-021.0-DYMP-94-031.0

APPRO ED BY: - i f O- -

WHITE: RBcLU SIJ: Claws YEUOWf: YMPBOCqw PINKC R3L Copy

'V

Form Y30O1 fMat gm

Page 68: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

* ORIEN SCALE GRD TCKDSPL ~ * RSH*IETUM e

Page 69: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

_ ORIT SCALE DSP RSRE U N gg u s '

isI

I

I E

Page 70: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

cEGg ENERGYMEASUREMENTSLas Vegas Area OperationsEGSG ENERGY MEASUREMENTS. INC. PRO BQX 1912 LAS VEGAS NEVADA 89125

'Nl~

0,(JNWBS 1.2.5.3

QA. NA

I" 'I'

February 28, 1994NV-94-140

t!oLnLo\Dw-Pl-Robert Nelson, Project Manager

Department of EnergyYucca Mountain Site Characterization Project Office101 Convention Center DriveLas Vegas, NV 89109

JANUARY 1 - JANUARY 31, 1994, PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACTERIZATION PROJECT

Enclosed is a progress report on the EG&G Energy Measurements, Inc. (EG&G/EM)Remote Sensing Laboratory (RSL) support to the Yucca Mountain Site CharacterizationProject (YMP) for January 1, 1994, through January 31, 1994.

The progress report for EG&G/EM RSL support to YMP includes the following sections:

* Work Accomplished* Expenditures* Status of Deliverables

If you have any questions, please contact Elaine Ezra at 794-7449.

K '

J/5

ManagerNV Program

CE:ns

4-40

Enclosures

dt-1-I,--

I

C mcInsu 4 - 5/9$

Page 71: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Robert NelsonJANUARY 1 - JANUARY 31, 1994, PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACTERIZATION PROJECTFebruary 28, 1994Page 2

cc: S. Ronshaugen, DOE/NV EMD (w/o end)M. Blanchard, DOE/YMP (w/o encl)W. Dixon, DOE/YMP (w/o encl)M. Dockter, DOE/NV (w/o encl)R. Dyer, DOE/YMP (w/o encl)J. Lorenz, REECo/YMPC. Newbury, DOE/YMPM. Ryder, DOE/YMP (w/o encl)A. Simmons, DOE/YMPD. Williams, DOE/YMP (w/o encl)W. Wilson, DOE/YMP

Page 72: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.3

WBS L2.3.9A

SA 0E394A

SITE INVESTIGATIONS

SPECIAL STUDIES: TRACERS, FLUIDS AND MATERIALS

TRACERS, FLUIDS AND MATERIALS

REPORT PERIOD:

REPORT DATE:

Januaiy 1, 1994 - January 31, 1994

February 28, 1994

RESPONSIBLE INDIVIDUAL: Jim Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. LANL completed installation and testing of the PC-based TFM application on anEG&G/EM PC

2. A meeting was held on January 24, 1994, to plan the integration of the FOC TFMdata input application and the GENISES database. In attendance were ClaudiaNewbury (DOE YMPO), John Gauthier (M&O/WCFS), Chris Breeds (LANL),and Chris Berlien and Jim Beckett.

3. A meeting was held on January 27, 1994, to plan the integration of the TIDBITSdatabase and the TFM database. In attendance were Claudia Newbury (YMPO),John Gauthier (M&O/WCFS), Elaine Ezra, Chris Berlien and Jim Beckett. Auser requirements study was recommended and will be initiated by February 28,1994.

4. The following tabular reports were provided from the Technical Database.

NR94010302- January TIDBITS report providing current data in TIDBITSdatabase.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

1. The point of data input for the TFM daily usage is the FOC. However, the FOCdoes not have the correct release of the software to run the LANL application.The FOC estimates a delay of 30 to 45 days for acquisition and testing of thesoftware.

2. The S100K funding to support the TFM database has not yet been transferred toEG&G/EM.

1

Page 73: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The TFM FOC application will be loaded and tested by February 28, 1994.

2. The TFM data will be loaded into GENISES and verified by February 28, 1994.At that time, report and query capability will be provided to YMPO.

3. Gillian Hall (LANL) will provide training on the installation and operation of thePC-based application for TEM data input.

4. Interviews for the TFM database position will be initiated.

2

Page 74: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 123 SITE INVESTIGATIONS

WBS 12.3.9.5 SPECIAL STUDIES: THREE-DIMENSIONAL SITE MODEL

SA OE395A 3-D MODELING AND VISUALIZATION

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: D. Brickey

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. The contract extension for the Lynx consultant, Jennifer Geddes, was initiated.Jennifer arrived January 4 and is scheduled to provide Lynx support throughJuly 4, 1994.

2. A meeting was held on January 5, 1994, with Mark Tynan (YMOM), JohnGauthier, Rob Clayton (M&O/WCOES), Dave Brickey, David Jefferis, and JenniferGeddes to discuss preparations for the Technical Program Review during theWeek of February 14, 1994. EG&G will provide support to Mark Tmnan for thismeeting in the form of panelists, displays, and interactive computer sessions.

3. Dave Brickey, David Jefferis, and Jennifer Geddes are working to explicitly defineEG&G's tasks for FY94 for submittal to YMPO.

4. Dave Brickey attended a Geostatistics short course at the Mackay School ofMines during the week of January 17, 1994.

5. Completed development of methodology to export cross-sections from Lynx GMSto ARC/INFO for final product development.

6. Work continues on exporting a volume component Lynx GMS model toEarthVision. To date, the -basic fault structure has been exported.

7. The process to hire a Senior Scientist in support of 3D modeling and visualizationhas been initiated.

3

Page 75: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

8. The following products were produced:

* Two views of the Thermal/Mechanical (formerly Calma) model wereproduced for John Gauthier's (M&O/WCFS) Quarterly Report - YMP-93-007 and YMP-93-008.

* 3D model of Saturated/Unsaturated Zones, base of proposed repository,and limits of the Natural -Barriers with the 3-D model was produced withhardcopy perspective view output of the model for James Replogle(YMPO) - YMP-94-010.0.

* Four cross-sections were produced for Rick Nolting (M&O) of theThermal/Mechanical (formerly Calma) model - YMP-94-012.0, YMP-94-013.0, YMP-94-020.0, and YMP-94-021.0.

* One view of the of the Thermal/Mechanical (formerly Calma) model wasproduced for Elaine Ezra (EG&G/EM) - YMP-94-015.

* TWO viewgraphs (3400 feet and 3700 feet elevation of the USGS YMP.R0rev. December, 1993) were prepared for Mark ¶nan (YMPO) -NR94012811.

MAJOR PROBLEMS AND CORRECTIVE ACTION: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The FY93 capital equipment funds will be released. Purchase requisition for anSGI Indigo? will be resubmitted.

2. Lynx GMS- software license will arrive.

3. Technical Program Review preparations will be completed and executed.

4. Development of conversion methodology from Lynx GMS to DGrs EarthVisionwill continue.

5. Submit a plan defining EG&G's tasks for FY94 for submittal to YMPO.

4

Page 76: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EW&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5 REGULATORY

WBS L2.53.5 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE535L94 TECHNICAL DATABASE INPUT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: J. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. EG&G/EM Environmental Sciences initiated the transfer of candidate datapackages to the Participant Data Archive (PDA) and the Local Records Center(LRC).

2. A schedule of data transfer packages to the YMP Technical Database (TDB) wasprovided to the YMP Data Manager for approval.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Corrective action will be completed on the Environmental Sciences PDAcandidate data. These data will be processed into Data Transfer Packages thensent to the CRI and the TDB.

5

Page 77: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536A GENISES TECHNICAL DATABASE -

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: J. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Jim Beckett met with Joe Schelling (SNL) on January 7, 1994, to discuss providinga copy of the technical database to Sandia.

2. Jim Beckett provided a presentation and tour on January 20, 1994, to classmembers of a DOE sponsored training course titled "Introduction to GIS." Inattendance were RJ. Niggemyer, L Garcia, D. Workman, G. Van Cott, R.C.Raedeker, M. Wagner and Y. Zhao of SAIC

3. Restructure of GENISES database keys to associate the Parameter Dictionaryparameter and attribute numbers continues.

4. There were no submittals to the GENISES Technical Database received duringthis period.

5. The following submittals to the Yucca Mountain Project Technical Database wereprocessed into the GENISES TDB.

GS920483117412.014 - USGS OFR 92-367 Seismicity and FocalMechanisms for the Southern Great Basin of Nevada and California in1990.

GS920483117412.022 - USGS OFR 92-340 Seismicity and FocalMechanisms for the Southern Great Basin of Nevada and California in1991.

6

Page 78: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

GS9204831i7412.032 - USGS OFR 92-572 Seismicity and FocalMechanisms for the Southern Great Basin of Nevada and California from1987 through 1989.

1A000000000051.001 - Long-term Thermal Stability of Clinoptilolite: TheDevelopment of a B Phase.

6. The following submittals were rejected by the TDBA:

GS930731174101.001 - YMP Level Data 11/1990 - 7/1991. The hardcopytext provide was of poor quality and could not be interpreted.

GS93073il74101.002 - GPS Data for Quadrilateral Surveys 11/1990 -7/1991. The hardcopy text provide was of poor quality and could not beinterpreted.

7. The following tabular reports were provided from the Technical Database.

NR94010302

NR93122003

NR93122004

NR93122001

NR94011406

NR94011903

NR94012501

A copy of the TIDBITS database report was prepared for JohnGauthier (WCFS) on January 3.

One copy each of two INGRES reports on hydrologic boreholes wasprepared for Amy Smiceinski (UNLV HRC) on January 4.

One INGRES report of existing boreholes with designator, PI, totaldepth and activity type was prepared for Amy Smiceinski (UNLVHRC) on January 4.

A digital file in ASCII format of existing and planned activities withactivity id, and position was prepared for Gillian Hall ( LANL) onJanuary 4.

A tabular report of existing boreholes with id, elevation, andposition was provided to Kathleen Scott (RSN) on January 19.

A tabular report of near- and far-field radiological monitoring siteswith id, and coordinate locations was provided to Kevin Shenk(SAIC) on January 30.

A digital file listing the planned and existing borehole data withactivity id, elevation and position was provided to Steve Nelson(WCFS) on January 30.

7

Page 79: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

NR94012608 A Report on distances between selected boreholes was prepared forAllison Inglett (SAIC) on January 27.

NR94012703 A tabular data report on selected boreholes with id, type, andlocation was prepared for Chris Breed (LANL) on January 27.

MAJOR PROBLEMS AND CORRECTMvE ACTION UNDERTAKEN:

1. The GENISES TDB is understaffed; four new positions have been opened.

2. LA00000000019.002 data submittal package contains sample locationinformation. However, the data provided is insufficient to be captured inGENISES. A letter was sent to Los Alamos National Laboratory requestingcoordinate data be provided.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Interviews for four additional GENISES TDB staff will be initiated.

2. Support to the YMP Technical Program Review will be provided.

8

Page 80: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Acconmplished

WBS L2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536B4 GIS DATABASE, SITE ATLAS, ARCVIEW AND GISCATALOG

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIIDUAL: S. Rohde

SUMMARY OF WORK ACCOMPIUSHED DURING REPORT PERIOD:

1. The GENISES Geographic Information System (GIS) Data CatalogQuarterly update was completed and 165 copies were provided to the YMPOffice. This update included a reformatting of the Catalog to mirror thestructure of the Parameter Dictionary and included a 40% increase incontent.

2. The FY93 Site Atlas map separates and text page proofs were receivedfrom the Government Printing Office (GPO). The proofs were reviewedand corrected. The corrected proof set was submitted back to the GPO.

3. The 'baseline" area of the GIS database is being evaluated, reformattedand verified to facilitate map production activities and for inclusion to theYMP GIS Catalog.

4. Susan Rohde met with Joseph Chirieleson (YMPO) on January 5, 1994, todiscuss data availability and needs for a water quality sampling programbeing developed for the Groundwater Monitoring Environmental FieldActivity Plan.

5. Susan Rohde met with Tom Bjerstedt (YMPO) and Chuck Harrington(LANL) on January 12, 1994, to discuss the submittal of boulder depositsampling sites. A U.S. Nuclear Regulatory Commission data request andresulting products were identified. Data entry was initiated and completed.Field maps and table were provided to Tom Bjerstedt. Data verification ispending.

9

Page 81: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

6. Susan Rohde met with Joseph Chirieleson (YMPO) and invited attendeeson January 20, 1994, to discuss the development of the water qualitysampling program, as mentioned above. Susan gave a brief overview ofavailable data, existing products and how to retrieve data from the GIS toaid in the program. Participants included: Ken Johannesson, Kathy Lao,Klaus Stetzenbach (University Nevada Las Vegas Harry Reid Center);Greg Fasano and Don Powers (SAIC); and Robert Craig and Pat Tucci(USGS).

7. No ArcView datasets were distributed during this report period.

MAJOR PROBLEMS AND CORRECTIVE ACLION UNDERTAKEN:

1. The FY93 Site Atlas, originally scheduled for completion on September 30, 1993,was received from the GPO, in proof form. The proofing set contained significanterrors; multiple corrections were identified, initiated, and completed. Because ofthe number and nature of errors, a second proofing set has been requested of theGPO before final printing is initiated. These events will again impact the finaldelivery date of the published FY93 Site Atlas.

ANTICIPATED SIGNIFICANT EVENTS PIANNED DURING NEXT REPORTPERIOD:

1. Verification of GIS spatial data will continue in support of the Marchquarterly update of the GIS Data Catalog.

2. The second proofing set for the FY93 Site Atlas will be received from theGPO, reviewed and transmitted to the GPO for final printing.

3. A job posting for an analyst to support this task element will be developed.

4. The FY94 Site Atlas tasking will be initiated.

5. Staff will participate in the YMP Technical Review, including providing aninteractive Arcview demonstration at the Technical Data Managementsession.

6. Data entry for the boulder deposit sampling sites will be verified, and aTechnical Database data submittal will be initiated.

7. ArcView dataset transfer standards and procedures will be initiated.

8 ' Six ArcView data requests for Project participants will be completed.

10

Page 82: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YeWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA 0E536C4 GIS, MAPPING AND ANALYSIS SUPPORT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: J. Donovan

SUEMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. GIS map products were generated to support project participants and are detailed inthe wDeliverablesw statement.

2. Photo products include the following:

NR93062905 Two 8"x10" color prints of two slides were prepared for Jerry Lorenz(REECo) on January 4.

NR93081701 One 30"x30" color duraflex print of EG&G Negatives #93A010L,93D1011, 93E171L, 92G361L and 92g-362L were prepared for JerryLorenz (REECo) on January 4.

NR93122902 One 36"x36" duraflex print of EG&G Negative #7488-127 wasprepared for Allison Inglett (SAIC) on January 5.

NR93122901 Three 8"MMO" color prints of EG&G Negative #89I-1400L was preparedfor Diane Gunter (SAIC) on January 5.

NR93121504 One mylar contour overlay and one paper orthophoto print of each of1:6,000 scale sheets (4, 5, 6, 11, 12) were provided to RobertDickerson (SAIC) on January 10.

NR94010403 One 16" x 20" color print of EG&G Negative #6677-21 was preparedfor Allison Inglett (SAIC) on January 11.

11

Page 83: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

NR94011104

NR93122002

One 16' x 20' color pint of EG&G Negative #7249-2 was preparedfor Allison Inglett (SAIC) on January 12.

One duraflex prints of the 1:100,000 scale Yucca Mountain color ratiocomposite satellite image map was prepared for Eric Smistad (YMPO)on January 13.

NR94011301 Two 40" x 30' color duraflex prints of EG&G negative 90C-208 wasprepared for Jerry Lorenz (REECo) on January 21.

NR94012607 One copy each of the following proof books were provided to ArdythSimmons (YMPO) for the NRC on January 26: Perf #'s 7488 (2volumes), 7489 (2 volumes), 7490 (2 volumes), 7491 (2 volumes) and7528.

3. The following digital data transfers were prepared:

NR93091603

NR94010704

NR93121606

NR93111801

NR94011002

NR93111001

NR93121701

One 1/4" cartridge tape of the following Arc/Info coverages in exportformat was prepared for William Davies (USGS) on January 3: 10 foothypsography, orthophoto index, roads, proposed repository outlineboundary, and conceptual controlled area boundary.

One Arc/Info export file with survey reference points was prepared forCorinne Tylor (SNL) on January 7.

One 8mm TAR tape containing hydrology, roads, hypsography andtransmission lines in .dxf file format was prepared for Frank Ennis(RSN) on January 7.

One 8mm tape containing the following coverages in Arc/Info exportfile format was provided to Hal Rager (DRI) on January 11: surfacedisturbance features, existing and planned boreholes/pits/trenches,geofeatures, 10 foot hypsography, and roads.

One 8mm tape containing the Scott and Bonk Faults Arc/Info coveragein .dxf file format was provided to Don Trujillo (MK) on January 20.

A copy of the Arc/Info coverages previously provided to the NRC wereprepared for Ardyth Simmons (YMPO) to be delivered to Nye Countyon January 21.

Two foot elevation contours from sheets # 53, 54, 60, 61, 67, and 68were transferred to .dxf file format and provided to Ken Kreeger(REECo) on January 24.

12

Page 84: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

NR93121606 One 8mm TAR tape containing 20 foot elevation contour data in .dxffile format was provided to Frank Ennis (RSN) on January 24.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Continued level-of-effort.

13

Page 85: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536F4 REMOTE SENSING

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD: None.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

14

Page 86: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA 0E536E4 COMPUTER SUPPORT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: T. Radermacher

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. APUNIX OpenRead Plus OCR software was received and installed.

2. Easi-Pace software was installed for Image Processing.

3. Received and installed tape drive hardware/software for data transmittal to the stateand effected counties.

4. Added two GRID and one COGO floating licenses to the YMPSAS computer system.

5. New Novell software was purchased for the Environmental Sciences Departmentwhich will allow interaction with the YMPSAS computer network.

6. Two 1.3 gigabyte disk drives and a 1 gigabyte optical disk were purchased to providecomplete mirroring capability for the YMPSAS data.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The Technical Database SparcCenter 1000 fileserver is expected to be delivered. Asystem configuration plan and installation plan is under development.

15

Page 87: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA 0E536G4 CAPITAL EQUIPMENT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. $179K of FY93 funds were converted to operating dollars.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

ANTICIPATED SIGNIICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Purchase requests for the FY93 capital equipment will be initiated.

2. A letter reauesting conversion of FY94 operating funds to capital funds will beIIdrafted.

16

Page 88: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536D4 PROJECT MANAGEMENT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

Reporting/Tracking/Planning

1. EG&G/EM RSL December Progress report was compiled and submitted toYMPO.

2. December PACS input was compiled and submitted to Robert Spiro (M&O).

Meetings/Conferences/Training:

1. Weekly Technical Data Managers staff meetings were held with ArdythSimmons (YMPO), Steve Bodnar and Bob Lewis (M&O) and Elaine Ezra andJim Beckett.

2. Todd Radermacher attended the Solaris System's Administrator's II training inMilpitas, CA during the week of January 10.

3. Helen Simmer and Jeff Donovan attended YMP Orientation on January 11.

4. Elaine Ezra and Jim Beckett attended a Technical Project Review dry run onJanuary 14 for the Technical Data Management System portion of the session.

5. Dave Brickey attended a Geostatistics short course in Reno, NV during theweek of January 18.

6. Joanna Wiggins attended the Records Management Conference in Vienna, VAduring the week of January 18.

17

Page 89: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

7. Chris Berlien attended INGRBS 4GL training in Alameda, CA during theweek of January 24.

Employee Actions:

1. Four additional job postings were opened including: a 3-D modeling SeniorScientist, a QA Administrator, a GIS Scientist II and a Chief Clerk for theProduct Status Tracking System.

Quality Assurance:

1. YMPSAS drafted its first monthly report showing statistics gathered from anewly developed Customer Evaluation Form. This form was designed tofacilitate quality improvement of our products. Quarterly, we will trend thedata as a further means to improve our processes.

2. Our YMP GENISES Technical Database QA implementing procedure, YLP-Sm. lQ-EGG was officially placed on controlled distribution on January 28,1994. On January 31, 1994, all YMPSAS staff was trained to the procedure.

3. On February 01, 1994, Joanna Wiggins met with Frank Kratzinger (YMP QA)to close the 4 CARs issued against EG&G/EM in October of 1992. A letterfrom YMPQAD to EG&G/EM is forthcoming.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Elaine Ezra and rim Beckett will attend an off-site all day meeting to discussTechnical Data Management System procedures.

2. GENISES staff will support the YMP Technical Program Review during the week ofFebruary 14.

3. Todd Radermacher will attend Solaris Network Administration II training during theweek of February 21.

4. Interviews with Technologist m database applicants will be initiated.

18

Page 90: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&GIEM RSL SUPPORT TO YMPIWork Accomplished

WBS 1.2.12.2.3 PARTICIPANT RECORDS MANAGEMENT

SA OEC23A4 RECORDS MANAGEMENT

REPORT PERIOD: January 1, 1994 - January 31, 1994

REPORT DATE: February 28, 1994

RESPONSIBLE INDIVIDUAL: J. Wiggins

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. 14 QA record packages have been submitted into the YMP Central Records Facility(CRF). Accession numbers from the CRF have been received, confirming CRFacceptance.

2. Joanna Wiggins attended the YMP Records Council meeting at TRW, Vienna,Virginia, January 18-21, 1994, to provide input to a new supplemental DOE Order,1324.5. This Order will impact our YMP records management.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

1. The OCRWM RIDs and Records Management (supplemental DOE Orders 1324.2 and1324.5) Orders are near approval, which will mean implementing a new RIDs andRecords Management program for the EG&G/EM YMP program. To ensurecompliance with this Order, an additional Clerk A will be hired to assist JoannaWiggins with Records Management.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

19

Page 91: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Expenditures from December 27, 1993 to January, 1994(Dollars in thousands)

Task BudgetJanuary

SQ7L

$ 78.5

Total CostsTo Date

$ 147.3

Remaining

$ 404.7WBS 1.2.3Site Investigations

$ 552.0

WBS 1.2.5Regulatory

WBS 1.2.12

WBS 1.2.15Support Services

TOTALS

$2,500.0

$ 50.0

$ 194.2

$ 0.0

$ 735.0 $1,765.0

$ 0.0 $ 50.0

$3108.0 $ 272.7 $ 882.3 $2,225.7

WBS 1.2.5Capital Equipment $ 341.6 $ 109.5 $ 109.5 $ 232.1

20

Page 92: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-!and Pr

YMP-4and Pr

YMP-SBorehc

YMP-SBorehc

YMPC5Area I

YMP-SMecha

YMP-SMecha

YMP-SArea I

YMP4Extent

YMP-SObserv

YMP-5Drifts

YMP-SBorehc

STATUS OF DELIVERABLES FOR EG&GIEM RSL SUPPORT TO YMPJanuary 1, 1994 through January 31, 1994

GIS MAP SUPPORT

Requested by/lEston Organization Date Sent si

93-014.0 YMP Existing Olson/RSN 1/3194 Fulloposed Trenches

)3-017.0 YMP Existing Olson/RSN 1/3/94 Fulloposed Test Pits

93-190.2 YMP Existing Olson/RSN 1/3/94 Full)les

)3-191.1 YMP Proposed Olson/RSN 1/3/94 Fulliles

93-295.1 YMP Regional IngletttSAIC 1/3/94 Pagelap

W4-08.0 Thermal/ Gauthier/M&O 1/6/94 Pagenical 3-D Model

)4-007.0 Thermal! Gauthier/M&O 1/6/94 Pagenical Model

93-295.0 YMP Regional InglettlSAIC 1/11/94 Page4ap

93-331.0 YMP Lateral Melander/SAIC 1/12/94 Pageof Natural Barriers

94-009.0 Tortoise Rautenstrauch/ 1/12/94 Pageations EG&G/EM

94-010.0 3D Repository Replogle/YMPO 1/13/94 PageVugraph

93-338.0 Existing HinojosalQATSS 1/14/94 Fullles

21

No. ofCopies

2

2

2

2

1

5

5

I

12

1

61

S

Page 93: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-304.0 ApprovedRoads

YMP-93-012.4YMP-93-029.7YMP-93-045.1YMP-93-72.2YMP-93-073.2YMP-93-074.2YMP-93-075.2YMP-93-076.2YMP-93-077.2YMP-93-078.2YMP-93-079.2YMP-93-080.2YMP-93-081.2YMP-93-082.2YMP-93-083.2YMP-93-084.2YMP-93-085.2YMP-93-086.2YMP-93-087.3YMP-93-088.2YMP-93-089.2YMP-93-090.2YMP-93-091.2YMP-93-092.2YMP-93-093.2YMP-93-094.2YMP-93-095.2YMP-93-096.2YMP-93-097.2YMP-93-098.2YMP-93-099.2YMP-93-100.2YMP-93-101 .2YMP-93-174.0YM-93-175.0YMP-93-195.3YNP-93-202.1YM-93-203.2YMP-93-256.1YMP-93-260.1

Crawford/YMPO 1/14/94 Full 1

McKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcldnley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGS

1/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/141941/14/941/14/941/141941/14/94

PagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePage

22

Page 94: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-295. 1YMP-93-320.0YMP-93-321.0YMP-93-308.0YMP-93-309.0YMP-93-310.0YMP-93-31 1.0YMP-93-312.0YMP-93-313.0YMP-93-314.0YMP-93-315.0YMP-93-316.0YMP-93-317.0YMP-93-318.0YMP-93-319.0YMP-93-322.0YMP-93-323.0YMP-93-324.0YMP-93-004.2YMP-93-005.2YMP-93-132.2YMP-93-133.3YMP-93-284.0YMP-93-284.1YMP-93-300.0YMP-93-303.0YMP-93-308.1YMP-93-325.0YMP-93-326.0YMP-93-330.0YM-P93-331.0YMP-93-331.1YMP-93-332.0YMLP-93-332.1YMP-93-334.0YMIP-93-335.0YMP-93-336.0

McKiRney/USGSMcKinley! USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGS

1/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/941/14/94.1/14/941/14/941/14/94

1/19/94

1/19/94

PagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePage

PageVugraph

Fuli

YMP-94-015.0 TechnicalDatabase Input to 3-D Modeling

YMP-93-183.2 YMP Shaft SiteLocation Study

Ezra/YMPSO

Nolting/M&O

23

Page 95: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-0.0 YMP ExistingBoreholes

YMP-94-002.0 YMP PlannedBoreholes

YMP-94-O0.0 YMP ExistingBoreholes

YMP-93-191.1 ProposedBoreholes

YMP-93-300.0 YM Faults

YMP-94-019.0 Trench 14 Log

YMP-94-012.0 Section A

YMP-94-013.0 Section B

YMP-94-020.0 Section C

YMP-94-021.0 Section D

YMP-93-306.0 YMP Near-FieldRadiological Monitoring Sites

YMP-93-307.0 YMP Near-FieldRadiological Monitoring Sites

YMP-94-014.0 Vehicle Passes

YMP-93-278.1 Trenches

YMP-94-022.0 Surface BasedTesting Activities

YMP-94-023.0 Surface BasedTesting Activities

YMP-94-024.0 Surface BasedTesting Activities

Smiceinski/UNLV

Dlugosz/YMPO

Dlugosz/YMPO

ScottSAIC

Scott/SAIC

MengesIUSGS

Nolting/M&O

Nolting/M&O

Nolting/M&O

Nolting/M&O

Shenk/SAIC

ShenkISAIC

Sowed/EG&G/EM

Bjerstedt/YMPO

Biggar/M&O

Biggar/M&O

Biggar/M&O

1/19/94

1/19/94

1119/94

1120/94

1/20/94

1/21/94

1/21/94

1/21/94

1/21/94

1/21/94

1/24/94

1/24/94

1/24/94

1/24/94

1/24/94

1/24/94

1/24194

FullPage

PageVugraph

PageVugraph

Full

22

I1

11

1

Full

Page

FuU

Full

Full

FuUl

Full

1

2

1

1

1

1

1

Full 1

Page

Page

Full

4

1

1

Full 1

Full 1

24

Page 96: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-025.0 Surface BasedTesting Activities

YMP-94-026.0 Surface BasedTesting Activities

YMP-94-027.0 Surface BasedTesting Activities

YMP-94-028.0 Surface BasedTesting Activities

YMP-94-029.0 Surface BasedTesting Activities

YMP-94-030.0 Surface BasedTesting Activities

YMP-94-010.0 3-D RepositoryDrifts

YMP-94-019.1 Trench 14 Log

YMP-94-03 1.0 GeophysicalData

YMP-94-022.1 Surface-BasedTesting Activities with Geology

YP-94-023.1 Surface-BasedTesting Activities with Geology

YMP-94-024.1 Surface-BasedTesting Activities with Geology

YMP-94-025.1 Surface-BasedTesting Activities with Geology

YMP-94-026.1 Surfice-BasedTesting Activities with Geology

YMP-94-027.1 Surface-BasedTesting Activities with Geology

Biggar/M&O

Biggar/M&O

Biggar/M&O

Biggar/M&O

Biggar/M&O

BiggarlM&O

Replogle/YMPO

MengeslUSGS

Tynan/ PO

Biggar/M&O

Biggar/M&O

Biggar/M&O

Biggar/M&O

Biggar/M&O

Biggar/M&O

1/24/94

1/24/94

1/24/94

1/24/94

1/24/94

1/24/94

1/24/94

1/25/94

1/26/94

1/27/94

1/27/94

1127/94

1/27/94

1/27/94

1/27/94

Full

Full

Full

Ful

Ful

Full

Full

Page

Full

Ful

Ful

Full

Full

Full

Full

25

Page 97: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-94-028. 1 Surface-BasedTesting Activities with Geology

.YMP-94-029.1 Surface-BasedTesting Activities with Geology

YMP-94-030. 1 Surface-BasedTesting Activities with Geology

BiggarlM&O

Biggar/M&O

BiggarIM&O

1127194 Full 1

1/27/94

1/27/94

Full 1

FuU 1

TOTAL NEW MAPS 39

TOTAL MAPS 1A77

26

Page 98: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

n EGcG ENERGYMEASUREMENTSLas Vegas Area Operatlons WBS 1.2.5.3EG&G ENERGY Vf#SY.EMEYyS INC. P.O BOX 1912. LAS VEGAS. NEVADA 89125 ; Q NA

January 18, 1994NV-94-045

Mr. Robert Nelson, Project Manager U'

Department of Energy 0Yucca Mountain Site Characterization Project Office101 Convention Center DriveLas Vegas, NV 89109

NOVEMBER 1- DECEMBER 31, 1993, PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS, INC. REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACTERIZATION PROJECT

Enclosed is a progress report on the EG&G Energy Measurements (EG&G/EM)Remote Sensing Laboratory (RSL) support to the Yucca Mountain Site CharacterizationProject (YMP) for November 1, 1993, through December 31, 1993.

The progress report for EG&G/EM RSL support to YMP includes the followingsections:

* Work Accomplished* Expenditures* Status of Deliverables

If you have any questions, please contact Elaine Ezra at (702) 794-7449.

JAb Michael, Manager CNV Program

CE:Dns 0

Enclosures

Page 99: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Robert NelsonNOVEMBER 1- DECEMBER 31, 1993, PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS, INC REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SiTE CHARACIERIZATION PROJECTJanuary 18, 1993Page 2

cc: S. Ronshaugen, DOE/NV EMD (w/o end)vM. Blanchard, DOE/YMP (w/o end)W. Dixon, DOE/YMP (w/o end)M. Dockter, DOE/NV (w/o end)R. Dyer, DOE/YMP (w/o end)J. -- Lorenz, REECo/YMPC. Newbury, DOE/YMPA. Robison, DOE/YMP (w/o end)AL Ryder, DOE/YMP (w/o end)A. Simmons, DOE/YMPD. Williams, DOE/YMP (w/o end)W; Wilson, DOE/YMP

Page 100: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L23 SITE INVESTIGATIONS

WBS L23.9A SPECIAL STUDIES: TRACERS, FLUIDS AND MATERIALS

SA OE394A TRACERS, FLUIDS AND MATERIALS

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAL: J. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Jim Beckett and Chris Berlien attended a TFM meeting held on December 17.Also attending the meeting were: Claudia Newbury (YMPO), Chris Breeds, JimHall, Gillian Hall, Hemi Kalia (LANL), and James Arnold (REECo). Themeeting was held to provide a detailed description of the current applicationsoftware developed to support the TFM database. A recommendation was madeby EG&G/EM to focus all of LANL's software application development efforts into the user interface for daily data input. The recommendation was approved bythe DOE. Tasking discussed during the meeting included the following:

* LANL will complete all bacldog data entry prior to transition of thedatabase to EG&G/EM.

* LANL will complete the installation of the PC-based application andtraining of the data entry personnel prior to the transition.

* EG&G/EM will provided a copy of the GENISES database keys for theTFM database design personnel.

The TFM database is currently scheduled to transition from LANL toEG&G/EM by February 1, 1994.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: A job requisitionhas been opened to staff this activity. It is expected that this position can be filled bymid-March. Existing YMPSAS staff will continue to maintain the effort until dedicatedsupport is hired.

1

Page 101: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

The TMF database is currently in the development states of its life-ccle and resides ona PC platform. A significant effort will be required to develop the system to satisfyfuture DOE requirements. EG&G/EM action cannot be initiated until the currentdesign structure is provided by 1ANL

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. A copy of the PC-based application software, TFM data dictionary and test fileswill be provided by LANL to EG&G/EMP

2. Training will be provided to LANL to EG&G/EM personnel on the applicationsoftware.

2

Page 102: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 123 SITE 1NVESTIGATIONS

WBS L23.9.S SPECIAL STUDIES: THREE-DIMENSIONAL SITE MODEL

SA OE395A 3-D MODELING AND VISUALIZATION

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAL D. Brickey

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. A meeting was held on November 4 with Mark tian (YMPO), John Gauthier(M&O), Dave Brickey, Dave Jefferis, Elaine Ezra (EG&G/EM) and JenniferGeddes (Lynx) to discuss FY94 tasking.

2. Ken Brisebois (Lynx Geosystems) visited the YMPSAS on November 11. Hedemonstrated the new Motif interface with the Lynx GMS software and its newfeatures. Lynx is working on an interface with ISITIS (geostatistical software) toextend the geostatistical capabilities of Lynx

3. A meeting was held on November 18 with Mark Iynan (YMPO), John Gauthier,Ron Smith and Bob Elayer (M&O) and Dave Brickey to discuss the North RampDesign 3-D modeling requirements. Elayer was directed to work with SNL (DaveKessel) for assistance with the North Ramp modeL

4. A meeting was held on November 23 wath Mark Tynan and Tim Sullivan(YMO), Bob Elayer and John Gauthier (M&O), Bill Zelinski (SNL) and DaveBriekey to discuss 3-D modeling efforts. Sullivan directed Elayer to use SNL 2-Dcross-sections for North Ramp tunnel design work.

5. Bill 7Zilinski has recently been hired to work on SNLs 3-D modeling tasking. Hevisited YMPSAS on November 23 to meet the 3-D modeling/visualization andGENISES staff and to request data from the Technical Database.

6. A Dynamic Graphics (DGI) briefing was provided by Paul White (DGI) onDecember 8 at the YMPSAS facility. EarthVision 2.0, due for release inFebruary 1994, was demonstrated. This included the demonstration of the new 2-D kriging and map production from the 3-D model. John Gauthier and RobClayton (M&O) and Dave Brickey and Dave Jefferis attended.

3

Page 103: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

7. Dave Jefferis attended a meeting on Geophysics in Support of ESF DesignWorkshop on December 13. Jefferis provided a status report on the conversion ofthe SNL Calma thermal mechanical model to EarthVision.

& A meeting was held on December 14 to discuss products for the February YMPTechnical Program review. Attending the meeting were John Gauthier (M&O),Elaine Ezra, Dave Brickey and Dave Jefferis.

9. A meeting was held on December 17 with John Gauthier and Rob Clayton(M&O) and Dave Brickey and Dave Jefferis to discuss FY94 tasking for the 3-Dmodeling effort.

10. The USGS 'Demonstration lithologic Moder of the Topopah Spring Memberwas provided to YMPSAS on December 6. Included were the 3-D model, aworking borehole database including vertical sections (ie. virtual boreholes)primary (Scott and Bonk) and secondary (SAIC developed) cross-sections, andiospach maps. The new model was loaded on the YMPSAS system. The previousversion of the model was archived.

11. Directional surveys for the boreholes used to create the Calma model wereprocessed into the EarthVision directed well database.

12. The Lynx Geosystems professional services support contract extension wascompleted. Jennifer Geddes will be working to support the Lynx modeling effortfor the period January through June. Her tasking includes:

* Provide Lynx training to EG&G/EM and M&O staff as needed. Trainingwill include the motif interface and other new features of the new GMSrelease, and Engineering model and modeling concepts.

* Develop standard training sets and materials for future in-house training ofnew Lynx users (especially as related to the new motif interface).

* Develop standard products and procedures for preparing the standardproducts from Lynx GMS. Assist EG&G in developing the DXF exporttool for the capability of product enhancement in ARC/INFO.

* Assist in developing system interoperability between Lynx and other datavisualization softwares (DGrs EarthVision, SGrs IRIS Explorer, ESRIrsARC/INFO, and others as required). Assist in the development of

- measures of differences between models where the conversion is anapproximation.

4

Page 104: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

* Assist EG&G/EM Environmental Sciences staff in developinggeostatistical-based analysis of environmental data.

* Support the development of technical exhibit and demonstration routinesfor Lynx system capabilities. Completion of this task by March 30, 1994, isrequired.

* Provide as needed support to EG&G/EM in developing 3-D data models.

* Weekly status reports discussing progress on assigned tasking, identificationof problem areas and recommendations for process improvement.

13. One Lynx Geosystems software license was ordered for the YMPSAS.

14. An IndigoJ was installed at the YMPSAS facility, on loan from the Nellis RemoteSensing Laboratory until the FY93 capital equipment items can be purchased.

15. An Indigcf was installed at the YMPSAS facility, on loan from the M&O/WCFS.

16. One Network Controller License for-Dynamic Graphics software was ordered andreceived.

17. A conceptual plan was develop to export a Lynx GMS, volume componentdeveloped, model to Dors EarthVision.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

1. Three scientists are working full time on the 3-D modeling activities. It wasexpected that the SGI workstation identified for FY93 capital equipmentacquisition would have been available several months ago. I the FY93 capitalfunds are not available in the January FIN plan to purchase the workstation, itmay not be possible to progress on the 3-D data model development and standardproduct generation in a timely manner.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Product development in support of YMP Technical Program Review.

2. Produce cross-sections from the USGS Lynx model

3. A Senior Scientist position will be initiated.

4. A conversion method for porting a Lynx GMS, volume component developed,model to DGrs EarthVision will be initiated.

S

Page 105: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.25 REGULATORY

WBS 12.53.5 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OES35L94 TECHNICAL DATABASE INPUT

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUALU J. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD: None

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: EG&G/EMcurrently has 20 data submittals to the Participant Data Archive (FDA) which do notcomply with DOE submittal schedule requirements. DOE data submittal requirementsare currently under review by EG&G/EM Environmental Sciences to ensure compliance.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. A schedule for data submittal will be provided to the YMP Data manager.

6

Page 106: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5 REGULATORY

WBS L2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA 0E536A GENISES TECHNICAL DATABASE

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDVIYDUAL: I. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Jim Beckett met with C. Marie Steel (SNL) on November 17 to discuss TDB datasubmittals.

2. Jim Beckett gave an impromptu presentation to the DOE Standards WorkingGroup on December 2 on the incorporation of spatial data transfer standards intothe YMP GENISES Technical Database design. The working group membersand their affiliations are shown as Attachment A.

3. Jim Beckett met with Peter Chamberlin (Inyo County Planning Director) andBrad Mettam (Inyo County Project Coordinator) on December 7 to discusstechnical data availability, GENISES database structure and systems technology.

4. Jim Beckett and Chris Berlien attended the Technical Data Managers WorkingGroup meeting on December 8.

5. Jim Beckett and Chris Berlien met with Gail Heitland (SAIC) and Pat McKinleyon December 9 to discuss implementation of the Parameter Dictionary.

6. Elaine Ezra, Jim Beckett and Chris Berlien met with Steve Bodnar (M&O) onDecember 16 to discuss linking attributed to parameters. Associated efficienciesrelated to participants submitting and retrieving technical data and the building ofthe database were discussed.

7. With the release of the Parameter Dictionary, modifications to the GENISESdatabase have been initiated. A digital copy of the Parameter Dictionary wasprovided by Carol Johnson which was processed into GENISES.

7

Page 107: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

8. Test Interference Evaluation reports prepared during the period November 1through December 31, 1993, were entered into the prototype TIDBITS database.

9. Job postings for four new Technical Database staff were opened.

10. A document scanner with Optical Character Recognition (OCR) software hasbeen initiated and scanning of hardcopy TDB submittals has been initiated.

11. Recommendations for an improved process for assigning borehole designationsand their locations were drafted and provided to Ardyth Simmons (YMPO).

12 The following submittals to the GENISES Technical Database were received.

* USGS OFR 682-C - Principal Facts for About 16,000 Gravity Stations inthe Nevada Test Site and Vicinity (GS920508314212.005)

* USGS OFR 92-28 - Borehole and Geobydrologic Data for Test Hole USWUZ-6, Yucca Mountain Area, Nye County, Nevada (GS910808312232.002)

* USGS OFR 91-572 - Seismicity and Focal Mechanism for the SouthernGreat Basin of Nevada and California 1987 through 1989(GS920983117412.032)

* USGS OFR 92-340 - Seismicity and Focal Mechanisms for the SouthernGreat Basin of Nevada and California in 1991 (GS920783117412.022)

* USGS OFR 92-367 - Seismicity and Focal Mechanisms for the SouthernGreat Basin of Nevada and California in 1990 (GS9200483117412.014)

* USGS OFR 92-343 - Gravity and Magnetic Data for Fortymile Wash,Nevada Test Site, Nevada (GS920508314212.004)

13. The following submittals to the GENISES Technical Database were processedinto the GENISES TDB.

* SAND8O-1453 - Rock Mechanics Properties of Volcanic Tuffs from theNevada Test Site (SNSAND80145300.000) on November 29, 1993.

* LAO00000000017.002 - Dehydration and Rehydration of a Tuff Vitrophyrewas completed on December 20, 1993.

* IA000000000034.002 - Diffusion of Sorbing and Non-sorbing Radionuclideswas completed on December 27, 1993.

8

Page 108: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

14. No backlogged submittals to the SEPDB were processed administratively into theGENISES Technical Database.

15. The following tabular reports were processed from the Technical Database.

* A tabular-report listing the distance and azimuth of the following boreholesfrom the centerline of the baseline ramp design was prepared for RonNance (SAIC) on December 1: NRG-1, 2, 2, 2b, 3, 4, 5, 7, 7a and SD-9.

* rTWo tabular reports showing all boreholes used in hydrologic studies wereprepared for Greg Fasano (SAIC) on December 17:

Existing boreholes with the following attrbutes: Activity identifier,WBS number, SCP reference nlmber(s), study plan number(s),purpose, location, status, land ownership, data source and Site Atlasmumber.

Planned boreholes with the following attributes: activity identifier,location and status.

* A digital file listing the core recovery percentages for all availableboreholes was provided to William Zelinsky (SNL) on December 27.

* Two reports listing the names and locations of the planned boreholes andthe existing boreholes that fall within the proposed repository block andwithin 80 feet either side of the ramps were prepared for Claudia Newbury(YMPO) on December 28.

* A report listing all of the information entered into the TIDBITS databaseto date was provided to John Gauthier (M&O/WCFS) on December 29.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: The GENISESTDB is understaffed; four new positions have been opened.

ANTICIPATED SIGNIFICANT EVENTS PIANNED DURING NEXT REPORTPERIOD:

1. Interviews for four additional GENISES TDB staff will be initiated.

2. Site and Engineering Properties Database bacldog processing will be initiated.

3. Support to the YMP Technical Program Review.

9

Page 109: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 125 REGULATORY

WBS 12.53.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536B4 GIS DATABASE, SITE ATLAS, ARCVIEW AND GISCATALOG

REPORT PERIOD: November 1 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDlVIDUAIA S. Rohde

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Norma Biggar (M&O) met with laine Ezra, Jim Beckett and Chris Berlien onNovember 9 to discuss the YMP planned activities database and the M&OActivities Catalog and Planned Borehole Catalog.

2. The thermal-mechanical stratigraphy model developed by Sandia NationalLaboratories (SNL) was transferred to the Dynamic Graphics Earthvision systemoperated by EG&G/EM for the YMPO. The model transfer was verified forcompleteness and accuracy. Standard products that can be made available toparticipants were identified in a letter report prepared for the YMPO (YMSO-93-255).

3. The FY93 Site Atlas map separates and text pages were submitted to theGovernment Printing Office for publication.

4. The FY93 Site Atlas companion data sheets were completed and verified.

5. No ArcView datasets were distributed during this report period.

6. Sue Rohde has assumed the role as acting task leader for this task element. Suewill be responsible for directing the development of the YMP GIS database andstandard products.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: The FY93 SiteAtlas, originally scheduled for completion on September 30, 1993, was submitted to theGovernment Printing Office.

10

Page 110: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The GIS Catalog Quarterly update will be provided to YMPO.

2. Job postings for an additional analyst to support this task element will beinitiated.

3. Review and approval of Site Atlas map portfolio proofs.

4. Transmittal of Site Atlas proofs to the Government Printing Office.

11

Page 111: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L2.5 REGULATORY

WBS L25.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA 0E536C4 GIS, MAPPING AND ANALYSIS SUPPORT

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAIA J. Donovan

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. GIS map products were generated to support project participants and are detailedin the "Deliverables" statement

2. Photo products include the following:

* One blackline copy each of sheets 2-30 of the 1:6,000 scale 10 footelevation contours was prepared for Art Braun on November 2.

* Two 24" x 24" duraflex prints of EG&G 7488-127 were prepared for CarmaHernandez (SAIC) on November 3.

* One display print, 10 pagesize prints and one contact negative of EG&G93K-629L was prepared for Jerry Lorenz (YM/REECo) on November 22.

* One 8" x 10" color print and one color viewgraph of Perf #7488, frames130 and 198 were prepared for Carma Hernandez (SAIC) on November24.

* Two 8" x 10" color prints and one color viewgraph of Perf #7528, frames21, 32, 40, 62 and 65 were prepared for Carma Hernandez (SAIC) onNovember 24.

* Two 2"x2V4 B&W duraflex prints of EG&G Negative 86A 002L wereprepared for Allison Inglett (SAIC) on December 8.

12

Page 112: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

* One pagesize color print of EG&G Negative 911-061L was provided toEric Smistad (YMPO) on December 10.

* Six 24" x 30U duraflex prints of a USGS negative was provided to AllisonInglett (SAIC) on December 13.

* One contact print each of Perf #7488, frames 214, 215 and 216 wereprovided to Mark Tynan (YMPO) on December 13.

* One 8"x10" color print of each of the following frames was provided to DonUnglesbee (SAIC/FOC) on December 17:

Perf #7528, frames 62, 65, 66, 21, 32, 33, and 40.

* Four foam core mounted 24" xc 30" color duraflex prints of the followingJohnson Control photos were provided to Allison Inglett (SAIC) onDecember 20: YM-5662, YM-5666 and YM-5681.

3. The following digital data transfers were prepared:

* One 8mm tape containing the following ARC/INFO coverages convertedto .DXF formatted files were provided to Frank Ennis (RSN) onNovember 22:

Hydrology, roads, railroads, topography and transmission lines forBig Dune, Crater Flat, East of Beatty Mountain, Topopah Springand Topopah Spring, NW 7.5" quadrangles.

* A digital transfer of 10-foot elevation contours in TAR file format wasprovided to Tracy Felger (SAIC) on November 29.

* The following ARC/INFO export files were provided to Jim Nelson(SAIC) on December 14:

Alluvuni/bedrock contact; geologic structure from Scott and Bonk,Primary structure points; Secondaxy structure points; Busted Butte7.5' hypsography, and Topopah Springs NW 7.5' hypsography.

* A digital version of the 20-foot elevation contour data for the YuccaMountain site in Lynx format was provided to Robert Elayer (M&O/MK)on December 17.

* A digital version of the 20-foot elevation contour data for the YuccaMountain site in Lynx format was provided to Jim Nelson (SAIC) onDecember 20.

* TIo digital files containing the 1:250,000 scale digital elevation model

13

Page 113: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

(DEM) data in EarthVision 2-D grid format and ASCII format for an areacovering 36'41' to 37N Latitude and -116'20' to -116' 37 Longitude wereprovided to Sierra Boyd (LLNL) on December 20.

* The following ARC/INFO coverages were provided to Charles Schlinger(SAIC) in digital format, with documentation on December 23:

NTS boundary; Nellis Air Force Range boundary; geographicreference points in the YM area; conceptual controlled areaboundary, conceptual perimeter drift boundary; Nevada townshipand range grid system; Death Valley National Monument boundary;Toiyabe National Forest boundary state and county boundaries forNV, CA, OR, WA, ID, western Montana, UT, NM and AZ;locations of active mines in NV; proposed ramp configuration;proposed surface facilities for ESF; roads; faults; geologic features;streams; springs in NV; elevation contours; locations of recordedelevations; reclamation sites; predator study locations; ecologicalstudy plot locations; lagomorph study plot locations; magneticmonitoring sites; spring flow monitoring sites; springs and wells inNV,; stream flow monitoring sites; temperature and precipitationmonitoring sites; southern Great Basin Seismic Monitoring Networklocations; existing boreholes; existing trenches; existing pits; existingpavements; planned boreholes; planned pits and planned trenches.

* The following ARC/INFO coverages were provided in export format indecimal degree to William Davies (USGS) on December 27:

10 foot elevation contours; 1:6,000 scale orthophoto index; 1:24,000scale roads; proposed repository outline; and conceptual controlledarea boundary.

* The following ARC/INFO coverages were provided in export format indecimal degrees to David vo, Seggern (UNR) on December 27:

Southern Great Basin Seismic Monitoring System locations, NTSboundary, Nellis Air Forte Test Range boundary, Death ValleyNational Monument boundary, Nevada State boundary, primary,secondary, county, improved and other roads for Nye County.

* The following ARC/INFO coverages were provided in ASCII format toFrank Ennis (RSN) on December 27:

Hypsography, roads, railroads, hydrology and tansmision lines forthe USGS 7.5 topographic quadrangles: Beatty Mountain, CararraCanyon and Ashton.

* The following ARC/INFO coverages were provided in ASCII format toFrank Ennis (RSN) on December 27:

14

Page 114: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Hypsography for the USGS 7.5" topographic quadrangles: TopopahSpring, Topopah Sprng NW, East of Beatty Mountain, Crater Flatand Big Dune.

4. The following Calma model products were generated:

* Cross-sections were prepared using the Calma model in EarthVision forMark tynan (YMPO).

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Continued level-of-effort.

2. Interviews for a GIS analyst will be initiated.

15

Page 115: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplishred

WBS 1.2.5 REGULATORY

WBS 12.53.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSrEM (GENISES)

SA OES36F4 REMOTE SENSING

REPORT PERIOD- November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUALs C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD: None.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

16

Page 116: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 12.53.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536E4 COMPUTER SUPPORT

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAI: T. Radermacher

SUMMARY OF WORK ACCOMPIJSHED DURING REPORT PERIOD:

1. On December 21, a meeting was held to discuss an NRC request for on-lineaccess to the Automated Technical Data Tracking system and the GENISESdatabase. Attending the meeting were John Gandi, Mary Ann Jones, ArdythSimmons (YMPO), Jan Statler (SAIC), Harry Leake, Steve Bodnar and BobLewis (M&O), and Elaine Ezra and Todd Radermacher.

2. ArcView was installed on the RSL YMP system.

3. The Rastergraphics colorstation plotter was installed with Zeh Graphics plottingsoftware -for network use.

4. A Ricoh FS2 scanner with APUNIX OpenScan software was installed on theYMPSAS system.

5. Arc/Info COGO was installed on the YMPSAS system.

6. The YMPSAS Risk Assessment was drafted.

7. A technician position was opened. -

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. The SparcCenter 1000 fileserver for YMPSAS is expected to be delivered.

2. Interviews for the technician position will be initiated.

17

Page 117: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L2.5 REGULATORY

WBS L2.53.6 GEOGRAPHIC NODAL INFORMAT[ON STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536G4 CAPITAL EQUIPMENT

REPORT PERIOD: November 1, 1993 -December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUALA E. Ezra

SUAMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD: None.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN:

1. The pending approved FY93 capital equipment items are as follows:

SparclO Workstation $ 33K5 X-terminals $ 31KImage Processing system $ 64KImaging System $ 15KRouter $ 3

$173K

FY93 operating funds have not yet been transferred to capital funds under the FIN planConsequently, the above capital equipment items have not yet been purchased, which iscausing an increasingly difficult resource scheduling problem.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Wayne Kozai has stated that the FY93 capital funds will be available under theJanuary FIN plan.

18

Page 118: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 2.S REGULATORY

WBS 12S.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536D4 PROJECT MANAGEMENT

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAL E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Reporting/Tracking/Planning

* EG&G/EM RSL October Progress report was compiled and submitted toDOE/YMPO.

* October and November PACS input was compiled and submitted to RobertSpiro (M&O).

2. Meetings/Conferences/Training:

Weekly Technical Data Managers staff meetings were held with Ardyth Simmons(YMPO), Steve Bodnar and Bob Lewis (M&O) and Elaine Ezra and Jim Beckett.

Jon Pickus and Dave Jefferis attended the YMP Orientation on November 9.

YMPSAS staff attended the COMDEX 94 conference during the week ofNovember 15.

Dave Jefferis attended Hazards Communication Training on November 12.

Todd Radermacher attended Solaris System Administration training during theweek of November 29.

Jon Pickus and Sue Rohde attended the Nevada State GIS Conference onDecember 6-8.

19

Page 119: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

3. Employee Actions:

Jeff Donovan began his position as the new task leader for the YMP GIS MapProduction group on December 13.

Six job postings were opened including: four technical database staffi, onecomputer technician and one 3-D modeling Scientific Specialist. Four additionaljob postings will be prepared.

4. Quality Assurance:

The line Procedure for the processing of technical data to and from theGENISES TDB was submitted to YM Plans and Procedures Department (PPD)on October 28, 1993. On November 29, the line procedure was sent out by PPDfor technical review.

Letters requesting extensions to the response for corrective action requests YM-93-005 through YM-93-008 and completion due date for Technical DirectiveEGG-93-004 were submitted to YMP QAD. Both actions are dependent uponapproval of the EG&G/EM Line Procedure for Technical Database.

A DOE surveillance (YMP-SR-94-008) was conducted on November 29 to verifyEG&G/EM's implementation of the Technical Directive.

5. Safety.

An unannounced DOE safety inspection was conducted on December 16 at theYMPSAS facility.

MAJOR PROBLEMS AND CORRECIVE7 ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Todd Radermacher will attend Solaris training during the week of January 10.

2. Dave Brickey will attend a geostatistics training course during the week of January18.

20

Page 120: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS L2.1223 PARTICIPANT RECORDS MANAGEMENT

SA OEC23A4 RECORDS MANAGEMENT

REPORT PERIOD: November 1, 1993 - December 31, 1993

REPORT DATE: January 14, 1994

RESPONSIBLE INDIVIDUAL: J. Wiggins

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Fourteen QA data record packages were transmitted to the LRC.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Joanna Wiggins will attend a Records Management Council meeting in Vienna,Virginia, during the week of January 18.

21

Page 121: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Task

WBS 1.23Site Investigat

WBS 12.5Regulatory

WBS 12.12

WBS 12.15Support Servil

TOTALS

Expenditures from November 1, 1993 to November 28, 1993(Dollars in thousands)

November Total CostsBudget Cost To Date R

S 630.0 $ 17.8 $ 49.8ions

$2,500.0 S 153.2 $ 407.9

$ 100.0 $ 0.0 $ 0.0

$ 12.0 L0. $ Oces

$3242.0 S 171.0 $ 457.7

Remaining

S 580.2

$2,092.1

$ 100.0

$ 12.0

$2,7843

22

Page 122: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

Expenditures from November 29, 1993 to-December 26, 1993(Dollars in thousands)

December Total CostsTask Budget Cost To Date Remaining

WBS 1.23 S 630.0 $ 19.0 $ 68.8 $ 561.2Site Investigations

WBS 1.2.5 $2,500.0 S 132.9 $ 540.8 $1,959.2Regulatozy -

WBS 12.12 $ 100.0 $ 0.0 $ 0.0 $ 100.0

WBS 12.15 S 12. $ 0.0 0. 12.Support Services

TOTALS $3242.0 $ 151.9 $ 609.6 $2,632.4

23

Page 123: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

STATUS OF DELIVERABLES FOR EG&G/EM RSL SUPPORT TO YMPNovember 1, 1993 through December 31, 1993

GIS MAP SUPPORT

Requested by/Organization

No. ofSize CopiesDescwgtion Date Sent

YMP-93-012.4 BoreholeSummary

YMP-93-205.1 ExistingBoreholes

YMP-93-284.1 CollectionGauge Locations Map

YMP-93-205.1 ExistingBoreholes

YMP-93-160.1 Trench 14D -Bow Bridge Fault

YMP-93-300.0 YM Faults

YMP-93-300.0 YM Faults

YMP-93-204.1 LateralExtent of Natural Barrierson Q-List

YMP-89-031.2 ExpandedView of Proposed Activities

YMP-93-129.0 ExistingBoreholes (with Depth)and Exploratoiy StudiesFacility

YMP-93-300.0 YM Faults

YMP-93-172.0 Existing& Planned Boreholes withGeologic Structure

Weeks/YMQAD

Zelinsld/SNL

Ambose/Hydrologic

Linden/SAIC

Menges, USGS

Bullock, RSN

Bullock/RSN

Brandstetter/M&O

Green/EG&G/EM

Green/EG&G/EM

Bullock/RSN

Asgarian/M&O

11/2/93

11/2/93

11/2/93

11/3/93

11/3/93

11/4/93

11/4/93

11/5/93

11/5/93

11/5/93

11/9/93

11/9/93

PageVugraph

Full

Full

21

3

1

Full 1

FUll 1

Full 8

Full 8

Page

FullVugraph

FullVugraph

Full

Page

1

11

11

4

1

24

Page 124: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-172.0 Existing& Planned Boreholes withGeologic Structure

YMP-93-295.1 RegionalArea Map

YMP-93-244.0 Existingand Planned Boreholes,Preliminary

YMP-93-1902 ExistingBoreholes

YMP-93-191.0 ProposedBoreholes

YMP-93-194.0 AlluviumContacts

Asgarian/M&O

Inglett/SAIC

Iglett/SAIC

Sinks/USGS

Sinks/USGS

-Wetzel/TRW

11/10/93

11/10/93

11/10/93

11/10/93

11/10/93

11/10/93

Page 1

Page

Page

1

1

1Full

Full

Page

1

1

YMP-93-175.0Streams

Ephemeral Ritcey/M&O 11/12/93 Page 3

YMP-93-174.0 Springs

YMP-93-045.1 EcologicalStudy Plot Number/AverageNumber of Vehicle PassesPer Day

YMP-93-203.2 RepositoryBase Map Sheet B

YMP-93-202.1 RepositoryBase Map Sheet A

Ritcey/M&O

Sowell/EG&G/EM

Oliver/USGS

Oliver/USGS

11/12/93

11/12/93

11/12/93

11/12/93

Page 3

Page

Full

5

4

Full 4

YMP-93-255.0 YMP Stream-flow and PrecipitationStations

Sinks/USGS 11/16/93 Full 1

YMP-93-243.0 YMP PlantSuccession Study Plots

BlomquistEG&G/EM

11/16/93 Page 1

25

Page 125: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-055.1YNP-93-176.0YMP-93-176.1YMP-93-197.0YMP-93-203.1YMP-93-205.1YMP-93-264.0YMP-93-265.0YNP-93-266.0YMP-93-267.0YMP-93-277.1YMP-93-278.1YMP-93-279.0YMP-93-281.0YMP-93-285.0YMP-93-286.0YNP-93-287.0YNP-93-288.0YNP-93-288.1YNP-93-289.0YMP-93-290.0YMP-93-290.1YMP-93-292.0YNP-93-292.1YMP-93-294.0YMP-93-295.0

McKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGS

11/17/93* 11/17/9311/17/9311/17/93

*11/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/9311/17/93

PagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePage

YMP-93-309.0 ExistingBoreholes

YMP-93-310.0 ExistingTrenches

YMP-93-190.2 ExistingBoreholes

YMP-93-191.0 ProposedBoreholes

YMP-93-014.0 Existing &Proposed Trenches

YMP-93-017.0 Existing &Proposed Test Pits

Inglett/SAIC

Inglett/SAIC

Estes/USGS

Estes/USGS

Estes/USGS

Estes! USGSEstes/USGS

11/17/93

11/17/93

11/19/93

11/19/93

-11/19/93

11/19/93

Page 2

Page 3

Full 4

Full 4

Full 4

Full 4.

26

Page 126: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-043.2 Approvedand Unapproved Roads

YMP-93-165.1 Air Qualityand Meteorology MonitoringSites

YMP-93-308.0 RepositoryBase Map of Selected Area

YMP-93-293.0 EistingBoreholes (with Depth) andPotentially Useable Areas

YMP-93-296.0 PlannedBoreholes (with Depth) andPotentially Useable Areas

YMP-93-029.7 Figure 5.3Planned FY94 Trenches andTest Pits in RegionalInvestigations (ProposedLocations)

YMP-93-030.6 Figure 5.2Planned FY94 Trenches inthe Site Area (ProposedLocations)

YMP-93-195.3 Figure 5.1Planned FY94 Boreholes,Assuminig Modified ESEDesign

YMP-93-256.1 Figure 5.4FY94 Seismic ReflectionLine Locations andAssociated Shotholes

YMP-93-320.0 Cross-SectionIndex Map/Calna Model

Estes/USGS

Prowell/SAIC

Oliver/USGS

Bush/SAIC

Bush/SAIC

Reynolds/M&O

Reynolds/M&O

Reynolds/M&O

Reynolds/M&O

TVan/YMPO

11/19/93

11/19/93

11/19/93

11/22/93

11/22/93

11/22/93

11/22/93

11/22/93

11/22/93

11/23/93

Full 4

Page

Full

Full

10

4

.1

Full 1

Page

Page

Page

Page

Full

27

Page 127: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-321.0 Cross-SectionA-A' (VSCALE 150 ft/in;HSCALE 300 ft/in)

YMP-93-322.0 Cross-SectionC-C' (VSCAILE 150 ft/in;HSCALE 300 ft/in)

YMP-93-323.0 Cross-SectionB-B' (VSCALE 150 ft/in;HSCALE 300 ft/in)

YMP-93-311.0 TopographicProffic Study

YMP-93-312.0 YMP Topo-graphic Profle Study

YMP-93-319.0 GeologyBase Map, Sheet 7

YMP-93-318.0 GeologyBase Map, Sheet 6

YMP-93-317.0 GeologyBase Map, Sheet 5

YMP-93-316.0 GeologyBase Map, Sheet 4

YMP-93-315.0 GeologyBase Map, Sheet 3

YMP-93-314.0 GeologyBase Map, Sheet 2

YMP-93-313.0 GeologyBase Map, Sheet 1

YMP-93-324.0 YMP, 1:3,600Scale Base Map

YMP-93-260.1 YMPSelected Boreholes

Tynan/YNTO 11/23/93 Full 4

Tyan/YMPO

Mynan/YMPO

Peck/SAIC

Peck/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Felger/SAIC

Meyers/SAIC

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/23/93

11/29/93

11/29/93

Full 4

Full 4

Ful 1

Full 1

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

Page

28

Page 128: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-072.2 TestInterference Map Sheet 1

YMP-93-073.2 TestInterference Map Sheet 2

YMP-93-074.2 TestInterference Map Sheet 3

YMP-93-075.2 TestInterference Map Sheet 4

YMP-93-076.2 TestInterference Map Sheet S

YMP-93-077.2 TestInterference Map Sheet 6

YMP-93-078.2 Test :Interference Map Sheet 7

YMP-93-079.2 TestInterference Map Sheet 8

YMP-93-080.2 Test -Interference Map Sheet 9

YMP-93-081.2 TestInterference Map Sheet 10

YMP-93-082.2 TestInterference Map Sheet 11

YMP-93-083.2 TestInterference Map Sheet 12

YMP-93-084.2 TestInterference Map Sheet 13

YMP-93-085.2 TestInterference Map Sheet 14

YMP-93-086.2 TestInterference Map Sheet 15

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

PageFul

PageFull

PageFul

PageFul

PageFull

PageFull

PageFull

PageFuU

PageFll

PageFul

PageFul

PageFul

PageFull

PageFul

PageFul

II . 29

Page 129: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-0873 TestInterference Map Sheet 16

YMP-93-088.2 TestInterference Map Sheet 17

YMP-93-089.2 TestInterference Map Sheet 18

YM-93-0902 TestInterference Map Sheet 19

YMP-93-0912 TestInterference Map Sheet 20

YMP-93-922 Test -Interference Map Sheet 21

YMP-93-093.2 TestInterference Map Sheet 22

YMP-93-094;2 TestInterference Map Sheet 23

YMP-93-095.2 TestInterference Map Sheet 24

YMP-93-096.2 TestInterference Map Sheet 25

YMP-93-0972 TestInterference Map Sheet 26

YMP-93-098.2 TestInterference Map Sheet 27

YlP-93-099.2 TestInterference Map Sheet 28

YMP-93-100.2 Test -Interference Map Sheet 29

YMP-93-101.2 TestInterference Map Sheet 30

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

'Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

Springer/SAIC

11/30/93

11/30/93

11/30/93-

11/30/93

11/30/9311/30/ 93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

11/30/93

PageFul

PageFul

PageFull

PageFull

PageFul

PageFull

PageFul

PageFu-

PageFul

PageFull

PageFul

PageFul

PageFull

PageFull

PageFul

21

30

Page 130: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-008.2 Orthophotohdex

YMP-93-291.0 MRDS DataLocations in the Vicinityof Yucca Mountain

YMP-93-132.2 YMP ActivitiesReported Complete (Near Field)

YMP-93-133.3 YMP ActivitiesReported Complete (Far Field)

YMP-93-0722 TestInterference Map Sheet 1

YM.-93-0732 TestInterference Map Sheet 2

YMP-93-074.2 TestInterference Map Sheet 3

YMP-93-075.2 TestInterference Map Sheet 4

YMP-93-076.2 TestInterference Map Sheet 5

YMP-93-077.2 TestInterference Map Sheet 6

YMP-93-078.2 TestInterference Map Sheet 7

YMP-93-0792 TestInterference Map Sheet 8

YMP-93-080.2 TestInterference Map Sheet 9

YMP-93-0812 TestInterference Map Sheet 10

Springer/SAIC

Mrotek/M&O

Rixford/M&O

Rixford/M&O

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGSOliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

11/30/93

12/1/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

Page

Full

1

1

Page

Page

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

31

Page 131: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-082.2 TestInterference Map Sheet 11

YMP-93-083.2 TestInterference Map Sheet 12

YMP-93-084.2 TestInterference Map Sheet 13

YMP-93-085.2 TestInterference Map Sheet 14

YMP-93-086.2 TestInterference Map Sheet 15

YMP-93-0873 TestInterference Map Sheet 16

YMP-93-088.2 TestInterference Map Sheet 17

YMP-93-089.2 TestInterference Map Sheet 18

YMP-93-090.2 TestInterference Map Sheet 19

YMP-93-091.2 TestInterference Map Sheet 20

YMP-93-092.2 TestInterference Map Sheet 21

YMP-93-093.2 TestInterference Map Sheet 22

YMP-93-094.2 TestInterference Map Sheet 23

YMP-93-095.2 TestInterference Map Sheet 24

YMP-93-096.2 TestInterference Map Sheet 25

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Olver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

Full

Full

Full

Full

Full

Full

Fu

Full

Full

Full

Full

Full

Full

Full

Full

32

Page 132: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-097.2 TestInterference Map Sheet 26

YMP-93-098.2 TestInterference Map Sheet 27

YMP-93-099.2 TestInterference Map Sheet 28

YMP-93-1002 TestInterference Map Sheet 29

YMP-93-1012 TestInterference Map Sheet 30

YMP-93-308.1 RepositoryBase Map of Selected Area

YMP-93-331.0 YMP LateralExtent of Natural Barriers

YMP-93-332.0 YMP NorthPortal

YMP-93-332.1 North Portal

YMP-93-303.0 ESF NorthPortal Test Interference

YMP-93-255.0 YMP Streamflowand Precipitation Stations

YP-93-072.2 TestInterference Map Sheet 1

YMP-93-073.2 TestInterference Map Sheet 2

YMP-93-0742 TestInterference Map Sheet 3

YMP-93-075.2 TestInterference Map Sheet 4

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Oliver/USGS

Replogle/YMPO

Replogle/YMPO

Replogle/YMPO

Gauthier/M&O

Dlugosz/DOE

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

12/2/93

12/2/93

12/2/93

12/2/93

12/2/93

12/3/93

12/6j93

12/6/93

12/6/93

12/7/93

12/7/93

12/8/93

12/8/93

12/8/93

12/8/93

Full

Full

Full

Full

Full

Full

Page

Page

Page

Page

Full

Full

Full

Full

Full

2

2

2

2

2

4

36

30

1

1

1

3

3

.3

3

33

Page 133: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-076.2 TestInterference Map Sheet 5

YMP-93-077.2 TestInterference Map Sheet 6

YNP-93-078.2 TestInterference Map Sheet 7

YMP-93-0792 TestInterference Map Sheet 8

YNP-93-080.2 Test :Interference Map Sheet 9

YMP-93-081.2 TestInterference Map Sheet 10

YMP-93-082.2 TestInterference Map Sheet 11

YMP-93-0832 TestInterference Map Sheet 12

YMP-93-084.2 TestInterference Map Sheet 13

YMP-93-085.2 TestInterference Map Sheet 14

YMP-93-086M2 TestInterference Map Sheet 15

YMP-93-0873 TestInterference Map Sheet 16

YMP-93-088.2 TestInterference Map Sheet 17

YNP-93-089.2 TestInterference Map Sheet 18

YNP-93-0.2 TestInterference Map Sheet 19

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

34

Page 134: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-091.2 Test ^Interference Map Sheet 20

YMP-93-092.2 Testinterference Map Sheet 21

YMP-93-093.2 TestInterference Map Sheet 22

YMP-93-094.2 TestInterference Map Sheet 23

YMP-93-095.2 TestInterference Map Sheet 24

YMP-93-096.2 TestInterference Map Sheet 25

YMP-93-097.2 Testinterference Map Sheet 26

YMP-93-098.2 TestInterference Map Sheet 27

YMP-93-099.2 TestInterference Map Sheet 28

YMP-93-1002 Testinterference Map Sheet 29

YMP-93-101.2 TestInterference Map Sheet 30

YMP-93-326.0 TortoiseLocations Along Roads in 1983

YMP-93-205.1 ExistingBoreholes

YM-93-004.2 YMP Partici-pants Tour Map

YMP-93-0.2 YMP Partici-pants Tour Map

Jacobs/SAIC

Jacobs/SAIC

Iacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Jacobs/SAIC

Annear/EG&G/EM

Weeks/SAIC

Inglett/SAIC

;I.g.ett/SAIIngett/SAIC

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/8/93

12/9/93

12/10/93

12/10/93

Full

Full

Full

Full

Fu

Full

Full

Full

Full

Full

Fbul

Page

Full

Page

Page

35

Page 135: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-325.0 YMP ESF Ramps Inglett/SAICwith TZ# 16, NRGA4, and Trench 14

12/13/93 Full 2

YMP-93-336.0 LocationMap for Site CharacterizationActivities

YMP-93-330.0 Topographyof YM Area A

YMP-93-335.0 Topographyof YM Area B

YMP-93-313.0

YUP-93-314.0

YMP-93-315.0

YMP-93-316.0

YMP-93-317.0

YMP-93-318.0

YMP-93-319.0

Contour Map

Contour Map

Contour Map

Contour Map

Contour Map

Contour Map

Contour Map

Nance/SAIC

Elayer/M&O

Elayer/M&O

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Braum/SAIC

Biggar/M&O

Matras/SAIC

Matras/SAIC

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/14/93

12/17/93

12/17/93

12/17/93

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

FullMylar

Full

Page 30

YMP-93-271.0 YMP Existing& Planned Boreholes withGeologic Structure :

YMP-92-288.0 YMP FieldPlanning Map

YMP-92-1463 YMP FieldPlanning Map

Full

Full

2

2

36

Page 136: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YMP-93-184.1 Existing &Planned Water Table Boreholes

YMP-93-334.0 Neutron AccessBorehole

YMP-93-160.1 Trench 14D -Bow Ridge Fault

YMP-93-161.0 Trench 14D -Bow Ridge Fault - TectonicFeatures

YMP-93-162.0 Trench 14D -Bow Ridge Fault - FaultDisplacements

YMP-93-163.0 Trench 14D -Bow Ridge Fault - SoilStratigraphic

YMP-93-164.0 Trench 14D -Bow Ridge Fault - MostRecent Event

YMP-93-259.0 PreliminaryTrench Log

Fasano/SAIC

Chornack/USGS

Menges/USGS

Menges/USGS

Menges/USGS

Menges/USGS

Menges/USGS

Menges/USGS

12/17/93

12/21/93

12/21/93

12/21/93

12/21/93

12/21/93

12/21/93

12/21/93

FullPage

11

Page

Page

5

1

1Page

Page 1

Page

Page

Page

1

1

1

TOTAL NEW MAPS j1

TOTAL MAPS 585

37

Page 137: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

DOE STANDARDS WORKNG GROUPPalace Station - Room 3010

December 2, 1993

Address/Organization Telephone. Fax E-Mail

Alton Cox

John Zehelean

Steve Hackman

Paul Richard

Kurt Fuchel

Walt Discena

Bill Lidinsky

DOE42 (301) 903-2956(301) 9034125 (Fax)

CDSI (301) 903-5780(301) 903-2024 (Fax)

HR43 (301) 903-6111(301) 903-6223 (Fax)

C=US/A=ATrMAIL/P=USDOE/O=HQ/S =HACKMANStevenHac @ hq.doe.gov/G=STEVEN

SWPA (918) 581-7482(918) 581-7530 (Fax)

BNL (516) 2824116(516) 282-7688 (Fax)Fuchel @ bnLgov

PNL ,

Fermilab

(509) 375-6985(509) 375-6703 (Fax)WV Discenza @ pnLgov

(708) 840-8067lidinsky @ hepmnet

Sarah Morris

Andy Johnson

W. Bill Sylvester

DOE Savannah River

Westinghouse Savannah River CO

Office of Field ManagementFM-1 HQ DOE

(803) 725-3846(803) 725-5833 (Fax)SHM @ SRS.GOV

(803) 644-6869(803) 644-6922 (Fax)AJJ @ SRS.GOV

(202) 586-6500(202) 586-7738 (Fax)

1 Attachment A

Page 138: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

DOE STANDARDS WORKING GROUPPalace Station - Room 3010

December 2, 1993

Ten Harris Office of Energy Efficiency &Renewable Energy EE-64Golden Field Office

(202) 586-7387(202) 586-8177 (Fax)

Bill McSpadden RSN (702) 794-5510(702) 794-5560 (Fax)

Janet Dixon

Mike Andrew

Roy Gibbs

Stanford Linear Accel Ctr.

Mason & Hanagar Pantex

Office of EnvironmentSafety & Health EH-31

(415) 926-3688(415) 926-3329 (Fax)

(806) 477-3554(806) 477-5636 (Fax)

(301) 903-4343(301) 903-2582 (Fax)

2

Page 139: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

rl EGJG ENERGY MEASUREMENTSSanta Barbara OperationsEG&G ENERGY MEASUREMENTS. INC., 101 CONIENTION CENTER DRIVE, LAS VEGAS, NEVADA 89109 TEL: (702)794-7463

WBS 1.2.13.4NQA

April 4, 1994LV94-RAG-024

Wendy Dixon, Director -Project and Operations Control Division aYucca Mountain Project Office -DOE Field Office, Nevada -P. O. Box 98518Las Vegas, NV 89193-8518

MARCH 1994 PROGRESS REPORT

Attached is the March 1994 progress report on biological studies and support activitiesconducted by EG&G/EM for the Yucca Mountain Site Characterization Project. Pleasecontact Tom O'Farrell (293-7762) or me (794-7474) if you have questions regarding thisreport.

W. Kent Ostler, ManagerEnvironmental Science Department

RG-vk

Attachment

cc: G. Ryder, DOE/YMPD. Sorensen, SAICP. Schilling, SAIC-

ENCLOSURE 7

Page 140: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YUCCA MOUNTAIN PROJECTBIOLOGICAL RESOURCES PROGRAM

MONTHLY PROGRESS REPORTMARCH 1994

Summary of Work Accomplished During Report Period

EG&G Energy Measurements (EG&G/EM) conducted work for the Biological ResourcesTask (WBS 1.2.13.4.11) for the Project Office.

ISSUES and CONCERNS

0 On March 17, EG&G/EM field biologists observed that the new above-ground 8-inchwaterline from H-Road to C-Well would potentially prevent tortoises from movingfrom the northern tip of Fran Ridge west into Midway Valley. This potential impact totortoises was not identified at the time of the preactivity survey. EG&GIEM met withthe Project Office and is preparing-a report to assess the impacts on tortoises and toprovide mitigation recommendations. Until mitigation actions are taken, biologists willcontinue to monitor the pipeline to ensure no tortoises are trapped on either side.

WORK PROGRESS

* EG&G/EM participated in the Nuclear Waste Technical Review Board meetings onMarch 21 and 22. These meetings were part of the TRB review of the YMPTerrestrial Ecosystems Program. EG&G/EM assisted with the field tour, presented anupdate on proposed changes in the Program, and participated in a roundtable discussionwith the Board concerning issues related to the Program.

* A draft was completed of the annual report of work accomplished in 1993 for the YMPBiological Resource Monitoring Program. The report is being submitted forDOEIYMP review.

* EG&G/EM scientists presented four oral presentations and one poster session at theannual meeting of the Desert Tortoise Council in Tucson, AZ. These presentationswere based on tortoise studies being conducted for YMP.

* EG&G/EM conducted two preactivity surveys to assess potential impacts on biologicalresources and two reclamation inventory. One biological resource survey report -andone reclamation stipulation report were submitted to Project Office.

* All other work was part of continuing studies. Radiomarked desert tortoises werelocated once each week. Side-blotched lizards were captured, marked, and released onnine plots to monitor the effects of site characterization activities. Topsoil stockpileswere checked to determine if re-application of a chemical stabilizing was needed.

Page 141: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YUCCA MOUNTAIN PROJECTBIOLOGICAL RESOURCES PROGRAM

MONTHLY PROGRESS REPORTFEBRUARY 1994

Summary of Work Accomplished During Report Period

EG&G Energy Measurements (EG&G/EM) conducted work for the BiologicalResources Task (WBS 1.2.13.4.11) for the Project Office.

ISSUES and CONCERNS

* None

WORK PROGRESS

* EG&G/EM conducted two preactivity surveys to assess potential impacts onbiological resources and one reclamation inventory. One biological resourcesurvey report was submitted to Project Office. One resurvey for tortoises wasconducted.

* Located radionarked desert tortoises once weekly. Continued preparingpresentations for the Desert Tortoise Council meetings in March.

* The NRG5 topsoil stockpile was seeded. Two reclamation demonstration plotswere established on the topsoil stockpile from the Concrete Batch Plant. Shrubswere transplanted to the Trench A2 reclamation site (575 plants) and to the 10GSF pit sites (100 plants).

* EG&G/EM met with the Project Office (W. Dixon) to discuss the TechnicalReview Board meetings scheduled for March.

* Preparation continued of the annual report of work accomplished in 1993 for theBiological Resource Monitoring Program.

* An EG&G/EM scientist presented a poster on reclamation studies beingconducted at Yucca Mountain at the annual meeting of the Society for RangeManagement in Colorado Springs, CO.

Page 142: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

n EGcG ENERGY MEASUREMENTS064 Santa Barbara Operations

EG&G ENERGY MEASUREMENTS, INC.. 101 CONVENTION CENTER DRIVE. LAS VEGAS, NEVADA 89109 TEL: (702)794-7463

WBS 1.2.13.4NQA

March 1, 1994LV94-RAG-020

Wendy Dixon, DirectorProject and Operations Control DivisionYucca Mountain Project OfficeDOE Field Office, NevadaP. O. Box 98518Las Vegas, NV 89193-8518

FEBRUARY 1994 PROGRESS REPORT

Attached is the February 1994 progress report on biological studies and support activitiesconducted by EG&G/EM for the Yucca Mountain Site Characterization Project Pleasecontact Tom O'Farrefl (293-7762) or me (794-7474) if you have questions regarding thisreport.

K strMng

W. Kent Ostler, ManagerEnvironmental Science Department

RG:vk

Attachment

cc. G. Ryder, DOE/YMPD. Sorensen, SAICP. Schiilin& SAIC

t.ClTlR

U 'IB1,7a"C''l A1~L1

ENCLOSURE 4

Page 143: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YUCCA MOUNTAIN PROJECTBIOLOGICAL RESOURCES PROGRAM

MONTHLY PROGRESS REPORTJANUARY 1994

Summary of Work Accomplished During Report Period

EG&G Energy Measurements (EG&G/EM) conducted work for the BiologicalResources Task (WBS 12.13.4.11) for the Project Office.

ISSUES and CONCERNS

* None

WORK PROGRESS

* EG&G/EM conducted three preactivity surveys to assess potential impacts onbiological resources. Two biological resource survey and reclamation inventoryreports were submitted to Project Office. One resurvey for tortoises wasconducted. One casual access survey was conducted EG&G/EM (A. Hughes)also met with DOE/YMP (G. Ryder), DRI (P. Buck), and SAIC (M. Griffin) todiscuss the status of surveys and activities that may occur during the next severalmonths.

* Continued locating desert tortoises once weekly. One tortoise was active andanother had moved to a new burrow.

* Eleven topsoil stockpiles associated with fault line terizaton studies inCrater Flats were stabilized by seeding, mulching, and covering them with netting.The reseeding of the disturbed area at the ESF Borrow Pit Topsoil Stockpile wascompleted. The seeding and water harvesting treatments being tested atreclamation site 5 were completed.

m EG&G/EM met with DOE (W. Dixon) to discuss the Technical Review Boardmeetings scheduled for March.

* Preparation continued of the annual report of work accomplished in 1993 for theBiological Resource Monitoring Program.

* Abstracts of presentations being prepared for the 1994 Desert Tortoise CouncilSymposium were approved by DOE

Page 144: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

n EGiG ENERGY MEASUREMENTS04)~ Santa Barbara Operations . A N

EG&G ENERGY MEASUREMENTS. INC.. 101 CONVENTION CENTER DRIVE. La VEAS, NEVADA 89109

-. bo .TEL: (702)794-7463

WBS 1.2.13.4NQA

February 2, 1994LV94-RAG-018

Wendy Dixon, DirectorProject and Operations Control DivisionYucca Mountain Project OfficeDOE Field Office, NevadaP. 0. Box 98518Las Vegas, NV 89193-8518

JANUARY 1994 PROGRESS REPORT

Attached is the January 1994 progress report on biological studies and support activitiesconducted by EG&G/EM for the Yucca Mountain Site Characterization Project Pleasecontact Tom O'Farrell (293-7762) or me (794-7474) if you have questions regarding thisreport.

W. Kn slr Manage

W. Kent Ostler, ManagerEnvironmental Science Department

RG:vk

Attachment

cc: G. Ryder, DOE/YMPD. Sorensen, SAICP. Schilling, SAIC

ACTI1n

A:(eC

'3 vnSUR 16~

Page 145: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

rn EGrG ENERGY MEASUREMENTSSanta Barbara OperationsEG&G ENERGY MEASUREMENTS, INC.. 101 CONVENTION CENTER DRIVE, LAS VEGAS, NEVADA 89109 JUEL: g02 )794-7463

2- so ? 30P ;-

WBS 12.13.4NQA

January 4, 1994LV94-RAG-018

Wendy Dixon, DirectorProject and Operations Control DivisionYucca Mountain Project OfficeDOE Field Office, NevadaP. 0. Box 98518Las Vegas, NV 89193-8518

DECEMBER 193 PROGRESS REPORT

Attached is the December 1993 progress report on biological studies and supportactivities conducted by EG&G/EM for the Yucca Mountain Site CharacterizationProject. Please contact Tom O'Farrell (293-7762) or me (794-7474) if you havequestions regarding this report.

UU-�U,e

W. Kent Ostler, ManagerEnvironmental Science Department

RG:vk

Attachment

cc: G. Ryder, DOE/YMPD. Sorensen, SAIC -P. Schilling SAIC

4•-

•-14 /1eC~AIw

tsiLOSURa '{

Page 146: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

YUCCA MOUNTAIN PROJECTBIOLOGICAL RESOURCES PROGRAM

MONTHLY PROGRESS REPORTDECEMBER 1993

Summary of Work Accomplished During Report Perio

EG&G Energy Measurements (EG&G/EM) conducted work for the BiologicalResources task (WBS 1.2.13.4.11) for the Project Office.

ISSUES and CONCERNS

* None

WORK PROGRESS

* EG&G/EM conducted one preactivity survey to assess potential impacts onbiological resources from the proposed extension of the North Portal Pad.Reclamation inventories were conducted at two sites. Three biological resourcesurvey and one reclamation inventory reports were submitted to Project Office.Two resurveys for tortoises were conducted. One casual access survey wasconducted.

* Continued locating desert tortoises once weekly. At the end of the December alltortoises had entered hibernation. Abstracts to be considered for presentation atthe 1994 Desert Tortoise Council Symposium were submitted to DOE for reviewand approval. Conducted raven population monitoring surveys.

* EG&G/EM met with DOE (W. Dixon) to discuss proposed changes in the SiteCharacterization Effects Studies for the Biological Resources MonitoringProgram. The changes were proposed after evaluating existing data and inputreceived during the Technical Review Board evaluation of the TerrestrialEcosystems Program in November.

* Preparation continued of the annual report of work accomplished in 1993 for theBiological Resource Monitoring Program.

* The annual report for the renewal of EG&G/EMs State of Nevada animalhandling permit was submitted. A new permit for 1994 is expected in January.

* The Topsoil Quality and Soil Amendment Study was implemented at ReclamationTrial Site #1 on the north end of Yucca Mountain. One hundred-sixty plots withcombinations of soil type (native vs. imported) and soil amendments (organicmatter, polyacrylamide gel and fertilizer) were established at the site.

Page 147: Part 2 of 2, Yucca Mountain Site Characterization Project Monthly … · 2012. 11. 18. · The transfer of the database into GENISES Uill be completed and an acceptance letter provided

EG&G Energy Measurements 2Monthly Progress ReportDecember 1993

Interim reclamation was completed at the ESF Topsoil Stockpile and NeutronBoreholes N-il, N-15, N-16, N-17, N-32, N-33, N-34, N-35, N-38, and N-53. Atthe topsoil stockpile, several seed mixes and straw tackifying methods wereapplied to test their effectiveness.

Topsoil samples were collected at the Borrow Pit Topsoil Stockpile and at theNRG-6 Topsoil Stockpile. These samples were sent to the Microbial BiomassService at Oregon State University for analysis of soil viability.