Parking Administration Systems (P.A.S.) Old Dominion University CS 410 Blue Team. Ken Dixon, Michael Hall, Kyle Jackson, Josh Lafountain, Michael Leming, James Morris. Organizational Chart. 2. Introduction. 3. CS410 BLUE TEAM. 5. 6. Contents. Problem Statement Problem Characteristics - PowerPoint PPT Presentation
Citation preview
1
Parking Administration Systems
(P.A.S.)
Old Dominion University
CS 410 Blue Team Ken Dixon, Michael Hall, Kyle Jackson, Josh Lafountain, Michael Leming, James Morris
2November 15, 2006 CS410 BLUE TEAM 2
Organizational Chart
Janet Brunelle(Product Manager)
Kenneth Dixon(Project Manager)
Josh Lafountain(Documentation/Risk Manager)
Michael Leming(Software Manager)
James Morris(Webmaster)
Kyle Jackson(Hardware Manager)
Michael Hall(Marketing Manager)
James LongParking Services Expert
Michael L. NelsonWeb Professional
Gene Hill PriceHardware
Professional
7November 15, 2006 CS410 BLUE TEAM 7
ContentsProblem StatementProblem CharacteristicsCustomerOur SolutionSolution CharacteristicsHow it worksMobile Parking Attendant SystemTag RenewalSoftware BreakdownDatabase TablesWhat’s in the BoxWhat’s Not in the BoxSample System for ODU(3 garages)Return on Investment Market AnalysisManagement PlanDevelopment PlanEvaluation PlanMarketing PlanMarket StatusCompetition MatrixSchedule Overview
Phase 0: Conception Organization ChartPhase 0: ConceptionMilestones and DeliverablesCustomer Return on Investment(ODU – 3 garages)PAS Return on InvestmentProject BudgetFunding PlanRisks/Impact MatrixRisk MitigationsConclusionReferencesQuestionsAppendix
8November 15, 2006 CS410 BLUE TEAM 8
Problem Statement
Business and university parking services currently lack an efficient online system for decal management as well as lot volume indication and prediction.
9November 15, 2006
Problem Characteristics
CS410 BLUE TEAM
No RFID to monitor traffic flowNo device indicating low capacity lots
availableNo automatic online decal renewal
systemLots expanding upward instead of
outward within the near futureLong waiting line for decal purchasesInefficient detection of parking violators
10November 15, 2006 CS410 BLUE TEAM 10
Customer
Any business or university with a decal controlled parking system.
11November 15, 2006 CS410 BLUE TEAM 11
Our Solution
P.A.S. – A hardware/software system that facilitates decal management and lot volume indication.
12November 15, 2006 CS410 BLUE TEAM 12
Solution Characteristics
PAS will…• Record historical data and interpret patterns• Allow dynamic lot control• Provide real-time lot occupancy• Allow web-based renewals and volume checking• Incorporate administrative functionality• Display alternate lot volumes• Send e-mail reminders for expiring passes
13November 15, 2006
PAS will not…
• Facilitate automatic ticketing
• Indicate where empty spaces are available
• Provide remote space reservation
• Show routes to alternate parking facilities
Solution Characteristics
CS410 BLUE TEAM
14November 15, 2006 CS410 BLUE TEAM 14
RFID Scanner/Reader
How it works
Vehicle Counter With Pressure Hose Sensor
15November 15, 2006 CS410 BLUE TEAM 15
RFID Chip
Parking Pass w/ RFID Chip
Vehicle Counter With Pressure Hose Sensor
RFID Scanner/Reader
(Remote) Computer System
Customizable Communication Board
Server
Database
Internet
Customizable Software
Students/Facility
Firewall
Firewall
HR Faculty/Student
Database
Major Functional Component Diagram
17November 15, 2006 CS410 BLUE TEAM 17
Mobile Parking Attendant System
Garage Computer System
WirelessRFID scanner
19November 15, 2006
Tag Renewal
Students/ Faculty
Server
Web Site
Credit CardCompany
Main Database
Tag Expiration Datesalary typeclassaddressnameUINTID Tag Expiration Datesalary typeclassaddressnameUINTID
Updated
durationaccess costtype durationaccess costtype
CS410 BLUE TEAM
21November 15, 2006
Database Tables
Tag ID UIN name address class salary Tag Expiration Date type
Tag ID Lisence make model year
type access duration cost
Student/Faculty Database
Vehicle Table
Access
CS410 BLUE TEAM
22November 15, 2006 CS410 BLUE TEAM 22
What’s in the Box
• Customizable Software• Server Computer• RFID Handheld Scanners• Lot Computers• RFID Readers/Antennas• Testing RFID tags• Display Boards• Training and Support
24November 15, 2006 CS410 BLUE TEAM 24
Sample System for ODU(3 garages)
Component Cost ($) Quantity Total ($)Customizable Software 3000.00 x 1 3000.00Database Software 0.00 x 1 0.00Server Computer 1850.00 x 1 1850.00RFID Handheld Scanner 1500.00 x 5 7500.00Lot Computer 750.00 x 3 2250.00RFID Reader 1600.00 x 6 9600.00RFID Antenna 170.00 x 12 2400.00Decals with RFID Tags 0.50 x 22000 11000.00Display Board 640.00 x 3 1920.00Car Counter 310.00 x 12 3720.00
43240.00
25November 15, 2006 CS410 BLUE TEAM 25
Return on Investment (Customer)
Convenience for the users:• No waiting in line• Reduces lot congestion• Identifies the location of least congested lots.
Over time, the cost to produce parking passes is reduced due to the renewal system.
• 4,254 decals would be distributed to incoming freshmen each year. Compared to 22,000 decals currently issued each year.
Helps increase the number of tickets issued to parking
violators, which will increase the amount fines collected.
27November 15, 2006 CS410 BLUE TEAM 27
Return on Investment (P.A.S.)
In order for P.A.S. to break even, ~305 sales of the system will have to be made.
29November 15, 2006 CS410 BLUE TEAM 29
Market Analysis
There are a total of 4216 degree-granting colleges in the United States.
2533: 4-year colleges1683: 2-year colleges
- National Center for Education Statistics
30November 15, 2006 30
Management PlanManagement Plan
D eve lop m en t P lan E va lu a tion P lan
M arke tin g P lan S ch ed u lin g P lan
F in an c ia l P lan O rg an iza tion a l P lan
R isk M an ag em en t P lan
M an ag em en t P lan
CS410 BLUE TEAM
31November 15, 2006 31
Development PlanDevelopment Plan
Client/server softwareClient/server software GUI ScreensGUI Screens RFID technologyRFID technology Based on future researchBased on future research Input and Output driversInput and Output drivers
CS410 BLUE TEAM
32November 15, 2006 32
Evaluation PlanEvaluation Plan
Frequency of Evaluation: 1. Every 3 months2. as often as necessary
Each phase will be evaluated based on the evaluation checklist for that phase. Technical
Factor
Marketing Factor
Financial Factor
Evaluation Checklist(Phase 0, 1, 2 or 3)
Personnel Factor
Administrative Factor
Phase 0 Phase 1 Phase 2 Phase 3
CS410 BLUE TEAM
33November 15, 2006 CS 410 BLUE TEAM 33
Marketing PlanMarketing Plan
• Old Dominion University beta testing siteOld Dominion University beta testing site
• Target Market: Universities/Colleges with Target Market: Universities/Colleges with a reoccurring commuter/residential a reoccurring commuter/residential population population
34November 15, 2006 CS410 BLUE TEAM 34
Market Status
The National Center for Education Statistics’ data shows 120 colleges (2-year and 4-year) have more than 23,000 enrolled students.
Of these 120 colleges, only 10 were found currently using technological parking solutions.
Have standard parking decal
solutions (No RFID)
92%
Have technological
solutions8%
- National Center for Education Statistics
- Transcore Systems
35November 15, 2006 CS410 BLUE TEAM 35
Competition Matrix
Color-code Key:Green Blocks – Our systemGrey Blocks – Other systems
36November 15, 2006 36
Schedule OverviewSchedule Overview
* The entire detailed schedule can be found in Appendix D
ID Task Name Duration Start Finish
1 Phase 0 - P.A.S. Conception 81 days Mon 8/28/06 Thu 12/7/06
14 Phase 1 - Proof of Concept 87 days Mon 1/8/07 Fri 4/27/07
25 Phase 2 - Critical Design 525 days Sat 4/28/07 Tue 12/30/08
36 Phase 3 - Production Out Years 335 days Wed 12/31/08 Mon 1/25/10
2006 2007 2008 2009 2010 2011
CS410 BLUE TEAM
37November 15, 2006 37
Phase 0: Conception Phase 0: Conception Organization ChartOrganization Chart
Kenneth Dixon
Project Manager
James MorrisWebmaster
Josh LafountainDocumentation/Risk Manager
Kyle JacksonHardware Manager
Michael HallMarketing Manager
Michael LemingSoftware Manager
Risk Identification
Website Development
Resource Identification
Technical Research
SBIR
Market Research
WBS
User Interface
Competition Research
Budget Estimation
Michael LongParking Services Director,
ODU
Janet BrunelleProduct Manager
Legend
Team Member
Task
Executive
Expert
CS410 BLUE TEAM
38November 15, 2006 38
Phase 0: ConceptionPhase 0: Conception Milestones and Deliverables Milestones and Deliverables
* The entire detailed schedule can be found in Appendix G
ID Task Name Duration Start Finish
1 Phase 0 - P.A.S. Conception 81 days Mon 8/28/06 Thu 12/7/06
2 Develop Project Team 3 days Mon 8/28/06 Wed 8/30/06
3 Define Project 8 days Thu 8/31/06 Fri 9/8/06
4 Planning 40 days Sat 9/9/06 Sat 10/28/06
5 Initial Research 12 days Mon 8/28/06 Sat 9/9/06
6 Feasibility Presentation 1 day Mon 10/30/06 Mon 10/30/06
7 Plan Phases 17 days Tue 10/31/06 Sat 11/18/06
8 Documentation 11 days Mon 8/28/06 Fri 9/8/06
9 Milestone Presentation 1 day Tue 10/31/06 Tue 10/31/06
10 Final Presentation 17 days Wed 11/1/06 Mon 11/20/06
11 Preliminary Website 15 days Mon 10/30/06 Wed 11/15/06
12 Team Website 15 days Thu 11/16/06 Thu 12/7/06
13 SBIR 1 day Tue 11/21/06 Tue 11/21/06
August SeptemberOctober November December January
CS410 BLUE TEAM
39November 15, 2006 39
Phase 1: Proof of Conception Phase 1: Proof of Conception Organization ChartOrganization Chart
Kenneth Dixon
Project Manager
James MorrisJunior Database
Programmer
Josh LafountainJunior Programmer
1
Kyle JacksonJunior GUI Developer
Michael HallJunior Network
Engineer
Michael LemingJunior Programmer
2
Prototype Testing (Database)
Documentation (Database
Information)
Prototype Software (Database)
Prototype Testing (Networking)
Documentation (Networking)
Prototype Development
(Security)
Prototype Software Interfaces
Prototype Testing (Software Interfaces)
Setup Wizard GUI
Prototype Testing (GUIs)
Input GUI Screens
Prototype Software Interfaces (GUI)
Documentation (User Manual)
Documentation (Evaluation Manuals)
Software Expert
Database Expert
Network Expert
Legend
Team Member
Task
Executive
Expert
CS410 BLUE TEAM
40November 15, 2006 40
Phase 1:Proof of ConceptionPhase 1:Proof of ConceptionMilestones and DeliverablesMilestones and Deliverables
* The entire detailed schedule can be found in Appendix D
ID Task Name Duration Start Finish
14 Phase 1 - Proof of Concept 87 days Mon 1/8/07 Fri 4/27/07
15 Reassemble Project Team 3 days Mon 1/8/07 Wed 1/10/07
16 Planning 13 days Thu 1/11/07 Sat 1/27/07
17 Requirements 15 days Mon 1/29/07 Wed 2/14/07
18 Set Up 3 days Thu 2/15/07 Sat 2/17/07
19 Design 13 days Mon 2/19/07 Mon 3/12/07
20 Development 18 days Tue 3/13/07 Mon 4/2/07
21 Testing 14 days Tue 4/3/07 Wed 4/18/07
22 Implementation 3 days Thu 4/19/07 Sat 4/21/07
23 Documentation 83 days Mon 1/8/07 Mon 4/23/07
24 SBIR Phase 2 5 days Mon 4/23/07 Fri 4/27/07
January February March April May
CS410 BLUE TEAM
41November 15, 2006 41
Phase 2: Critical DesignPhase 2: Critical DesignOrganization ChartOrganization Chart
Kenneth DixonProject Manager
Kyle JacksonSoftware Specialist
Kenneth DixonSoftware Specialist
Michael LemingSoftware Specialist
James MorrisDatabase Specialist
Josh LafountainDocumentation
Specialist
Legend
Team Member
Task
Executive
Hired Staff
Michael HallNetwork Specialist
Staffing (Hiring/Training)
Input/Output GUI Screens
Setup Wizard GUI
Prototype Testing (Input/Output GUIs)
Software Developer 3
Software Developer 4
Software Developer 1
Software Developer 2
Software Developer 3
Software Developer 1
Software Developer 4
Documentation (Beta Testing Results and
Update)
Prototype Software Interfaces
Prototype Testing
Software Developer 3
Software Developer 4
Software Developer 1
Software (Database)
Prototype Testing (Database)
Software Developer 2
Software Developer 5
Software Developer 6
Software Developer 2
Software Developer 3
Software Developer 4
Software Developer 5
Network Engineer 1
Software Developer 1
Prototype Testing(Networking)
Documentation(Contractual)
Prototype NetworkInterfaces/Security
Network Engineer 1
Network Engineer 1
CS410 BLUE TEAM
42November 15, 2006 42
Phase 2: Critical Design Milestones Phase 2: Critical Design Milestones and Deliverablesand Deliverables
* The entire detailed schedule can be found in Appendix D
ID Task Name Duration Start Finish
25 Phase 2 - Critical Design 525 days Sat 4/28/07 Tue 12/30/08
26 Develop Project Team 21 days Sat 4/28/07 Tue 5/22/07
27 Planning 23 days Wed 5/23/07 Mon 6/18/07
28 Requirements 11 days Tue 6/19/07 Sat 6/30/07
29 Setup 22 days Mon 7/2/07 Thu 7/26/07
30 Design 113 days Fri 7/27/07 Wed 12/5/07
31 Development 21 days Thu 12/6/07 Sat 12/29/07
32 Testing 24 days Mon 12/31/07 Sat 1/26/08
33 User Documentation 50 days Sat 4/28/07 Mon 6/25/07
34 Implementation 289 days Mon 1/28/08 Mon 12/29/08
35 Prototype Developed 1 day Tue 12/30/08 Tue 12/30/08
April May June July August SeptemberOctober November December January February March
CS410 BLUE TEAM
43November 15, 2006 43
Phase 3: Production Phase 3: Production Organization ChartOrganization Chart
Kenneth DixonProject Manager
Michael HallMarketing Director
Kenneth DixonHR Director
Michael LemingProduction Director
James MorrisProduction Director
Josh LafountainHR Director
Legend
Team Member
Task
Executive
Expert
Kyle JacksonSupplies Director
Staffing(Hiring/Training)
Marketing(Customer Feedback/
Advertising)
Marketing Specialist
Production Preparations
Production Manager
Contracting
CS410 BLUE TEAM
44November 15, 2006 44
Phase 3: Production Phase 3: Production Milestones and DeliverablesMilestones and Deliverables
* The entire detailed schedule can be found in Appendix D
ID Task Name Duration Start Finish
36 Phase 3 - Production Out Years335 days Wed 12/31/08 Mon 1/25/10
37 Develop Project Team 4 days Wed 12/31/08 Sat 1/3/09
38 Hire Staff Personell 5 days Mon 1/5/09 Fri 1/9/09
39 Prepare Production 326 days Sat 1/10/09 Mon 1/25/10
40 Marketing 326 days Wed 12/31/08 Thu 1/14/10
41 Create P.A.S. Website 90 days Wed 12/31/08 Tue 4/14/09
December January February March April May June July August SeptemberOctober NovemberDecember January February
CS410 BLUE TEAM
CS 410 BLUE TEAM 45November 15, 2006 45
Phase 1: BudgetPhase 1: BudgetPhase 1: Staffing Costs
Employee Type Days Annual Salary Employee CostJunior Project Manager 87 $ 25,000 $ 8,365 Junior GUI Designer 1 82 $ 22,000 $ 6,938 Junior GUI Designer 2 82 $ 22,000 $ 6,938 Junior Programmer 82 $ 22,000 $ 6,938 Junior Database Engineer 82 $ 22,000 $ 6,938 Junior Networking Engineer 82 $ 22,000 $ 6,938 Database Consultant 13 $ 50,000 $ 2,500 Network Consultant 13 $ 50,000 $ 2,500 Software Consultant 13 $ 50,000 $ 2,500 Total Salary $ 50,558 Employee Overhead (40% of salary) $ 20,223 Total Personal Cost $ 70,781
Total Phase 1 Cost: $ 92,415Phase 1: Hard Resource Costs
Resource Units Cost per Unit Total CostDell Poweredge Server 1 $ 1,200 $ 1,200 Dell Thin-Client Desktop 1 $ 750 $ 750 Dell Precision Workstation 6 $ 1,500 $ 9,000 Microsoft Office 2003 Professional 6 $ 500 $ 3,000 RFID Handheld Wireless Scanner 1 $ 1,500 $ 1,500 RFID Scanner 2 $ 1,600 $ 3,200 RFID Antenna 4 $ 170 $ 680 Hydraulic Car Counter 4 $ 310 $ 1,240 LED Display Board 1 $ 640 $ 640 Various Wiring (2% of Cost) $ 424 Total Hard Resource Cost $ 21,634
CS 410 BLUE TEAM 46November 15, 2006
Phase 2: BudgetPhase 2
Employee Type Days Annual Salary Employee CostSoftware Developer 1 525 $ 40,000 $ 80,769 Software Developer 2 525 $ 40,000 $ 80,769 Software Developer 3 380 $ 40,000 $ 58,462 Software Developer 4 380 $ 40,000 $ 58,462 Software Developer 5 210 $ 40,000 $ 32,308 Software Developer 6 210 $ 40,000 $ 32,308 Network Engineer 120 $ 45,000 $ 20,769 Database Engineer 120 $ 45,000 $ 20,769 Project Manager 525 $ 60,000 $ 121,154 Total Salary $ 505,769 Employee Overhead (40% of salary) $ 202,308 Total Personal Cost $ 708,077
Phase 2Resource Units Cost per Unit Total CostDell Thin-Client Desktop 2 $ 750 $ 1,500 Dell Precision Workstation 6 $ 1,500 $ 9,000 Microsoft Office 2003 Professional 6 $ 500 $ 3,000 RFID Handheld Wireless Scanner 4 $ 1,500 $ 6,000 RFID Scanner 4 $ 1,600 $ 6,400 RFID Antenna 8 $ 170 $ 1,360 Hydraulic Car Counter 8 $ 310 $ 2,480 LED Display Board 2 $ 640 $ 1,280 Various Wiring (2% of Cost) $ 620 Total Hard Resource Cost $ 31,640
Total Phase 2 Cost: $ 739,717
CS 410 BLUE TEAM 47November 15, 2006
Phase 3: BudgetPhase 3
Employee Type Days Annual Salary Employee CostHR Manager 90 $ 24,000 $ 8,308 Production Manager 260 $ 35,000 $ 35,000 Production Worker 1 260 $ 22,000 $ 22,000 Production Worker 2 260 $ 22,000 $ 22,000 Production Worker 3 260 $ 22,000 $ 22,000 Software Developer 260 $ 40,000 $ 40,000 Customer Service 260 $ 24,000 $ 24,000 Technical Support 260 $ 35,000 $ 35,000 Market Specialist 120 $ 60,000 $ 27,692 Total Salary $ 236,000 Employee Overhead (40% of salary) $ 94,400 Total Personal Cost $ 330,400
Phase 3Resource Units Cost per Unit Total CostPackaging and Shipping Cost 3000 $ 200 $ 600,000 CD-ROM Disks 3000 $ 0.30 $ 900 Total Hard Resource Cost $ 600,900
Total Phase 3 Cost: $ 931,300
48November 15, 2006 48
Project BudgetProject Budget
Overall Project CostYear 1 240,770$ Year 2 265,000$ Employee Overhead (40% of salary) 202,308$ Total Personnel Cost 708,078$
Year 1 31,640$ Year 2 -$ Total Hard Resource Cost 31,640$
Personnel 505,770$ Hard Resources 31,640$ Total Budget 537,410$
Total PAS Phase 2 Budget
Phase 2Personnel Cost
Hard Resouce Cost
Employee Salaries 50,558$ Overhead 20,223$ Total Personnel Cost 70,781$
Total Hard Resouce Cost 21,634$
Personnel 70,781$ Hard Resources 21,634$ Total Budget 92,415$
Total PAS Phase 1 Budget
Phase 1Personnel Cost
Hard Resource Cost
Employee Salaries 236,000$ Employee Overhead (40% of salary) 94,400$ Total Personnel Cost 330,400$
Total Hard Resource Cost 600,900$
Personnel 330,400$ Hard Resources 600,900$ Total Budget 931,300$
Total PAS Phase 3 Budget
Phase 3Personnel Cost
Hard Resource Cost
1,561,125$
CS410 BLUE TEAM
49November 15, 2006 49
Funding PlanFunding Plan
• National Science FoundationNational Science Foundation– Division of Information & Intelligent SystemsDivision of Information & Intelligent Systems– Digital Society & TechnologiesDigital Society & Technologies– Deadline: April 26, 2007Deadline: April 26, 2007
CS410 BLUE TEAM
50November 15, 2006 CS410 BLUE TEAM 50
Risks/Impact Matrix
Anticipated Risks:
1 - Customer Buy-in
2 - Hardware Failure
3 - Software Failure
4 - Cost
5 - Counterfeit
3
45
1
2
51November 15, 2006 CS410 BLUE TEAM 51
Risk Mitigations
Risk # Risk Description Mitigation Action
1 Consumers do not trust stability of new emerging businesses
Providing cheaper prices, Giving extra feature list, Delivering working system
2 Components and Software cost is extremely expensive
Undercutting competitors, Open source software, database and OS
3 Tags could be duplicated Research existing rfid solutions
4 Failure is always possible with hardware
Redundancy, Camera
5 Software is error-prone Testing, Backups
52November 15, 2006 CS410 BLUE TEAM 52
Conclusion
• Technological devices are readily available.• Customizable software can be tailored for each
individual college.• Historical data collected from the system will allow for a
more efficient lot management system.• Majority of colleges currently do not have a technological
lot management system.• Our clients customers will have a more positive
experience in finding available lots and purchasing/renewing their decals.
• Overall, our P.A.S. will allow for a more efficient online system for decal management and lot volume control.
53November 15, 2006 CS410 BLUE TEAM 53
References
• American Association of Community Colleges
• National Center for Education Statistics
• Parking Services, Old Dominion University– James Long: Director– Michael J. Frizzel: Assistant Director
• RFID Journal
• RFID Technology
• Transcore Inc.
56November 15, 2006 CS410 BLUE TEAM 56
A
RFID -- Radio Frequency IDentification RFID is implemented using a coil of fine metal wires forming an antenna connected to a chip with stored information.
Passive RFID chips are activated by power generated from the radio frequency being captured by coils and powering the chip for data transfer.
Active RFID chips exchange data in exactly the same way, but are battery powered providing the chip a constant flow of energy.
What is RFID
61November 15, 2006 CS410 BLUE TEAM 61
Software BreakdownInterface to displays
The software will need the ability to drive the various LED displays at the garages as well as any other displays such as main campus displays.
Interface to ReadersThe readers must be able to communicate to the thin clients and the thin clients must recognize the communication.
Interface to Main ServerThe thin clients and the handheld scanners will need the ability to communicate with the central server in order to vary passes as well as update historical data and garage capacity counts.
Database LookupsVarious methods for putting data into the database as well as retrieving the data and operating on it.
Web based administration interfaceAccessible interface for those who manage the parking to monitor and get reports about current, past, and projected data. Entering of new pass subscriptions or modifying previous ones. Changing the types and classes of parking structures.
Regular Internet InterfaceProvide the ability for remote users at home or via WAP (cellphone) users to remotely monitor the garages as well as emailing of citations and/or subscription renewals.
Real-Time capacity trackingInterfacing with the counters both pressurized and RFID readers to allow for computing the current number of cars in a specific parking structure as well as how many of those cars are decaled vs. non-decaled. Responsible for initiating changes to displays and internet interfaces as well as coordinating with the web based administration.