22
Parker Hill Branch Improvements City of Boston Martin J. Walsh, Mayor Boston Public Library and Public Facility Department May 17, 2017

Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Parker Hill Branch Improvements

City of BostonMartin J. Walsh, Mayor

Boston Public Library and Public Facility DepartmentMay 17, 2017

Page 2: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Meeting Agenda:-Introductions- Project Overview- Schedule- Questions

Page 3: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Project Team:Public Facilities Department: Director, Tricia Lyons

Brian McLaughlin, Tom Leahy, James SessumBoston Public Library: President, David Leonard

Eamon Shelton, Michael Colford, Alison FordArchitect: Bargmann Hendrie + Archetype, Inc.

Page 4: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie
Page 5: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

1931 Building constructed.

1989 Mission Hill Triangle Historic District added to National RegisterMHC review required.

2003 Petition to Boston Landmarks Commission for listing as an individual landmark accepted. Petition still ‘Pending’.BLC review required.

2005 Accessibility upgrades (exterior ramp, interior elevator) interior and exteriorrepairs.

Page 6: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Interior View

Page 7: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Water damage at building interior.

Page 8: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Water damage at main reading room.

Page 9: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Water damage at east wall

Page 10: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Damaged plaster at wall around window in

Auditorium.

Page 11: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Exterior Masonry - open joints and cracks instone.

Page 12: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Detail of open mortar joints at granite.

Page 13: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Patched treads and open joints at frontsteps.

Stone veneer not secured at sidewall.

Page 14: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Original steel windows remain.

Page 15: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Steel at windows is rusted throughout.

Page 16: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Investigations and water testing.

Page 17: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Test 3

Page 18: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Project Overview- Window Replacement- Interior Painting- Plaster Repair- Masonry Repairs- Stair Repair- Waterproofing

Page 19: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

1 1/4" 1/2"

CAULK

1 3/4"

LIMESTONE

SURROUND

STEEL FRAME

LEAD

CAMING

INTERIOR

EXTERIOR

1 1

/2"

.

(ORIGINALLY) OPERABLE HOPPER WINDOW IN MASONRY OPENING

(ORIGINALLY)

OPERABLE*

CASEMENT WINDOW,

FRAME AND SASH

* ONLY ONE WINDOW IS CURRENTLY OPERABLE

..

(ORIGINALLY) OPERABLE HOPPER WINDOW AT BASEMENT

LIMESTONE

SURROUND

STEEL FRAME

LEADCAMING

INTERIOR

EXTERIOR

1 1

/2"

EXISTING STEEL

CASEMENT WINDOW

EXISTING STEEL

HOPPER WINDOW7 1/2"

5"

EXISTING STEELHOPPER WINDOW

HOPPER WINDOWS ARE

SET IN BACKWARDS

RELATIVE TO CASEMENT

WINDOWS AT BOTTOMROWS

INTERIOREXTERIOR

D:\

Revi

t L

ocal\3

26

1_

Park

er

Hill

_R

20

15

_2

_ry

ou

ng.r

vt

EXISTING STEEL WINDOWS

PLAN DETAIL @ OPERABLE CASEMENT WINDOW

FULL SCALE

PLAN DETAIL @ OPERABLE HOPPER WINDOW

FULL SCALE

SECTION THROUGH EXISTING STEEL WINDOWS

1 1/2" = 1'-0"

ELEVATION OF EXISTING STEEL WINDOWS

3/8" = 1'-0"

DECEMBER 07, 2016

Page 20: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie
Page 21: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Schedule:

- Bid Release: May 2017- Bid Award: June 2017- Close branch/pack up collection: July 2017- Start construction July 2017- Complete construction May 2018- BPL move in May – June 2018- Open to the public – June 2018

Page 22: Parker Hill Branch Improvements City of Boston...May 17, 2017  · Boston Public Library: President, David Leonard Eamon Shelton, Michael Colford, Alison Ford Architect: Bargmann Hendrie

Questions?