    PARAMETRIC

    COSTESTIMATING

    SPEAKER: OTTORINO MAGGIORE VAN BEEST - PMP

    SAN DONATO MIL.SE - APRIL 9, 2010

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING

    1

  • 7/29/2019 Parametric Cost Estimates

    2/28

    TABLE OF CONTENTS

    PARA... WHAT?

    PARA... WHEN?PARA... WHY?

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING

    2

  • 7/29/2019 Parametric Cost Estimates

    3/28

    PARA... WHAT?

    PMI PMBOK

    CHAPTER 7 - PROJECT COST MANAGEMENT

    PARA 7.1 - ESTIMATE COSTS

    SUB-PARA 7.1.2 - ESTIMATE COSTS: TOOLS AND TECHNIQUES

    POINT 7.1.2.3 - PARAMETRIC ESTIMATING (PAGE 172)

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING

    3

    PARAMETRIC ESTIMATING USES A STATISTICAL RELATIONSHIP BETWEEN HISTORICAL

    DATA AND OTHER VARIABLES (E.G. SQUARE FOOTAGE IN CONSTRUCTION) TO

    CALCULATE AN ESTIMATE FOR ACTIVITY PARAMETERS, SUCH AS COST, BUDGET AND

    DURATION.

    THIS TECHNIQUE CAN PRODUCE HIGHER LEVELS OF ACCURACY DEPENDING UPON THE

    SOPHISTICATION AND UNDERLYING DATA BUILT INTO THE MODEL. PARAMETRIC COST

    ESTIMATES CAN BE APPLIED TO A TOTAL PROJECT OR TO SEGMENTS OF A PROJECT, IN

    CONJUNCTION WITH OTHER ESTIMATING METHODS.

  • 7/29/2019 Parametric Cost Estimates

    4/28

    PARA... WHAT?

    PARAMETRIC COST ESTIMATING (PCE) = STATISTICAL OR STOCHASTIC COST ESTIMATE

    PARAMETER = THE COST DRIVER(S)

    COST ESTIMATING RELATIONSHIP (CER):

    COST-TO-COST: ANCILLARIES F(MAIN ITEM)...

    COST-TO-NO-COST: COST F(WEIGHT, MATERIAL, POWER, FLOW RATE, VOLUME,SURFACE, LENGHT, DWS. N, LINES OF CODE, ...)

    GENERAL FORM OF CER: Y = F (X)

    F: FUNCTIONAL RELATIONSHIP

    X: INDEPENDENT VARIABLE OR PARAMETER

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING

  • 7/29/2019 Parametric Cost Estimates

    5/28

    PARA... WHAT?

    TYPICAL CURVES USED FOR CERS:

    LINEAR

    SEGMENTED LINEAR

    POLYNOMIAL

    POWER LAW

    LOGARITHMIC

    EXPONENTIAL

    RATIONAL

    POWER SERIES

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 5

  • 7/29/2019 Parametric Cost Estimates

    6/28

    PARA... WHEN?

    TIME & PROJECT DETAILS

    ANALOGUS

    ESTIMATING

    AACEI - RP N 17R-97

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING

    FOR ENGINEERING & CONSTRUCTION PROJECTS

    6

  • 7/29/2019 Parametric Cost Estimates

    7/28

    PARA... WHY?

    CAN BE ACCURATE AS DEFINITIVE COST ESTIMATES

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 7

  • 7/29/2019 Parametric Cost Estimates

    8/28

    PARA... WHY?

    IF YOUR BOSS TELLS YOU: WE NEED THE PROJECT COST ESTIMATE BY TOMORROW

    YOU...

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 8

  • 7/29/2019 Parametric Cost Estimates

    9/28

    PARA... WHY?

    PARAMETRIC COST ESTIMATING - TOP BENEFITS:

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 9

    CONSIDERABLY REDUCING COST & TIME CYCLE FOR PROPOSAL PREPARATION,

    EVALUATION AND NEGOTIATION

    ABOVE BENEFITS CAN BE ACHIEVED WHILE MAINTAINING OR IMPROVING THE

    QUALITY OF THE ESTIMATES PRODUCED

    COST AND CICLE TIME SAVINGS UP TO 80%

  • 7/29/2019 Parametric Cost Estimates

    10/28

    PARA... WHY?

    PARAMETRIC COST ESTIMATING - MAIN ROADBLOCKS:

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 10

    CULTURAL RESISTANCE

    SIGNIFICANT INITIAL INVESTMENT

    LIMITED GUIDANCE HOW TO MANAGE PROPOSALS BASED ON PCE

  • 7/29/2019 Parametric Cost Estimates

    11/28

    PARA... WHY?

    PARAMETRIC COST ESTIMATING - OBJECTIVES:

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 11

    PRODUCTION OF MORE RELIABLE ESTIMATES

    SHORTER TIME REQUIRED

    BETTER DATA UNDERSTANDING

    EASIER TO COMPUTE CONCEPTUAL DESIGNS

    NO OTHER MEANS TO ESTIMATE EARLY COSTING

    BILL OF MATERIAL IS NOT REQUIRED

    MUCH EASIER TO HANDLE SCOPE, TECHNICAL AND PERFORMANCE CHANGES

    BETTER RISK MODELLING AND UNDERSTANDING

  • 7/29/2019 Parametric Cost Estimates

    12/28

    PARA... WHY?

    PARAMETRIC COST ESTIMATING - USE OF OUTPUTS:

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 12

    PROPOSAL PRICING

    ROUGH ESTIMATES

    ECONOMIC STUDIES

    ACTIVE PROJECT MANAGEMENT - SUPPORTS EARNED VALUE

    RISK ANALYSIS

  • 7/29/2019 Parametric Cost Estimates

    13/28

    PARA... OWNER-CONTRACTOR...?

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 13

    OWNER CONTRACTOR

    screening or

    feasibility

    stochastic or

    judgement

    concept study or

    feasibility

    primarly

    stochastic

    budget,

    authorization, or

    control

    mixed, but

    primarly

    stochastic

    control or / bid /

    tender

    primarly

    deterministic

    check estimate

    or bid / tenderdeterministic

    POSSIBLE

    COMMON

    UNDERSTANDING

    &

    INVESTMENTS

  • 7/29/2019 Parametric Cost Estimates

    14/28

    PARA... FORMULA?

    EXAMPLES: COST CAPACITY FORMULA

    INDUSTRIAL PLANTS

    C2 = C1 (Q2/Q1)K

    LOG C2 = LOG C1 - K LOG Q1 + K LOG Q2

    Y = A + K X

    0.2 K

    AVERAGE = 0.6

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 14

    LOG C

    LOG Q

    COMMERCIAL JET AIRPLANES

    LOG C = F (LOG MAX TAKE-OFF WEIGHT) K = 0.85

    LOG C = F (LOG NUMBER OF SEATS) K = 1.10

    LOG C = F (LOG LENGHT) K = 1.90

  • 7/29/2019 Parametric Cost Estimates

    15/28

    PARA... FORMULA?

    EXAMPLES: PLANT EQUIPMENT

    SHELL & TUBE HEAT EXCHANGER BEU TYPE - CARBON STEEL

    CHE = EXP [A + B LN (W)]

    4400

  • 7/29/2019 Parametric Cost Estimates

    16/28

    PARA... FORMULA?

    ENTIRE PLANT

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 16

    CE1 CE2 CE3 CE4 CE5 CE.. CEN

    CET1 CET2 CET3 CET4 CET5 CET... CETN

    BASE COST =

    I CETI

    TOTAL COST = BASE COST + ESCALATION + CONTINGENCY

  • 7/29/2019 Parametric Cost Estimates

    17/28

    PARA... FORMULA?

    EXAMPLE: OFFSHORE PLATFORM DECOMMISSIONING

    PLUG AND ABANDONMENT

    C1 = K0 + K1 CT + K2 JOB + K3 NW + K4 RIG + K5 WB + K6 SEASON + K7 WOW

    CT = CONTRACT TYPE (=0 X RATE CONTRACT; = 1 TURNKEY CONTRACT)JOB = JOB SPECIFICATION (=0 TEMPORARY PLUG & ABANDON; =1 PERMANENT P&A)NW = NUMBER OF WELLSRIG = RIG DEPLOYMENT (=0 RIGLESS OPERAT.; =1 RIG OPERATION)WB = WORKBOAT DEPLOYMENT(=0 WORKBOAT NOT EMPLOYED; =1 WORKBOAT EMPLOYED)SEASON = SEASON WHEN THE WORK BEGANWOW = WAITING ON WEATHER (=NO WEATHER INTERRUPTION; =1 WEATHER INTERRUPTION)

    STRUCTURE REMOVAL

    C2 = H0 + H1 ST + H2 WD + H3 CF + H4 MW + H5 TW + H6 REEF + H7 TOW

    ST = STRUCTURE TYPE (=0 CAISSON; =1 OTHERWISE)WD = WATER DEPHTCF = COMPLEXITY FACTOR = NC (NUMBER OF CONDUCTORS) + NPL (PIPELINE ATTACHMENTS) + NP (PILES) + NSP (SKIRT PILES ASSOCIATED WITH THESTRUCTURE)MW = MAXIMUM COMPONENT WEIGHTTW = TOTAL STRUCTURE WEIGHT (DECK + JACKET + EQUIPMENT + PILING AND CONDUCTORS)REEF = STRUCTURE DISPOSITION (=0 ON-SHORE REMOVAL; =1 ARTIFICIAL REEF DONATION)TOW = REEF REMOVAL METHOD (=0 TOPPLED-IN-PLACE OR PARTIALLY REMOVED; =1 TOWED TO SITE)

    SITE CLEARANCE AND VERIFICATION

    C3 = W0 + W1 AGE + H2 WD + H3 ND + H4 N

    AGE = AGE YEARS UPON REMOVALWD = WATER DEPHTND = NUMBER OF DAYSN = NUMBER OF ITEMS COLLECTED

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 17

    STUDY BY MARK J. KAISER

  • 7/29/2019 Parametric Cost Estimates

    18/28

    PARA... POWER FORMULA?

    OPTIMIZATION STUDIES

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 18

    FROM CONCEPT

    TO ALTERNATIVE PROJECTS

  • 7/29/2019 Parametric Cost Estimates

    19/28

    PARA... FROM?

    PARAMETRIC COST ESTIMATING - BUILDING CERS:

    CERS ARE BUILT UPON STATISTICAL DATA ANALYSIS

    SIGNIFICANCE OF CERS IS QUANTIFIED BY SEVERAL PARAMETERS; MOST

    IMPORTANT:

    COEFFICIENT OF DETERMINATION R2 : REPRESENTS THE PORTION OF VARIATION

    IN THE INDEPENDENT VARIABLE THAT HAS BEEN EXPLAINED BY THE REGRESSION

    LINE

    0R21

    R2 ACCEPTABLE 0.70

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 19

  • 7/29/2019 Parametric Cost Estimates

    20/28

    PARA... WHY?

    PARAMETRIC COST ESTIMATING - ARE YOU SURE COST DRIVERS YOUR

    ORGANIZATION IS USING ARE CORRECT?

    AN EXAMPLE - STUDY ON SAUDI ARABIAN RESIDENTIAL VILLA

    COST = F (PARAMETER)

    COST DRIVER = PERIMETER TO FLOOR RATIO = WALL AREA (M2) / PLAN AREA (M2)

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 20

    TYPICAL:

    - GROSS FLOOR AREA 600 M2

    - EXTERIOR DIMENSION 15 X 20 M

    - N 2 FLOORS- STORY HEIGHT 3 M

    TYPICAL

    STUDY BY A.D. IBRAHIM, A.A. SHASH, S.A. ASSAF, O.A. JANNADI

  • 7/29/2019 Parametric Cost Estimates

    21/28

    PARA... CURVES?

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 21

    PARAMETRIC COST ESTIMATING - BUILDING CERS:

    CURVES USUALLY PROVIDE MORE CREDIBLE

    AND ACCURATE RELATIONSHIPS

    LINEAR RELATIONSHIPS ARE VERY RARE

    AND OF LIMITED VALIDITY

  • 7/29/2019 Parametric Cost Estimates

    22/28

    PARA... PROCESS!

    PARAMETRIC MODEL BUILDING PROCESS

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 22

    MODEL

    REQUIREMENTS

    DATA

    SUPPORT MODEL

    REQUIREMENTS?

    DATABASE

    DEVELOPMENT

    NO

    YES

    MODEL

    DEVELOPMENT

    CALIBRATION AND

    VALIDATION?

    NOT

    OK

    UPDATE REQUIRED?

    YES

    OKDOCUMENT

    RESULTS

  • 7/29/2019 Parametric Cost Estimates

    23/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 23

    DATABASE DEVELOPMENT - DATA NORMALIZATION

    NORMALIZATION = DATA CORRECTION FROM DISSIMILARITIES, SUCH AS:

    SOURCED FROM DIFFERENT ORGANIZATIONS

    CHANGES IN ORGANIZATION

    LEARNING / FORGETTING EFFECT

    CURRENCY FLUCTUATION

    ESCALATION

    UNUSUAL EVENTS

    ETC.

    MAIN LIMITATION: UNRECORDERED DATA / INFO UNAVAILABILITY

  • 7/29/2019 Parametric Cost Estimates

    24/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 24

  • 7/29/2019 Parametric Cost Estimates

    25/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 2

  • 7/29/2019 Parametric Cost Estimates

    26/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 26

    SOME IDEAS TO WORK ON

    OWNER - CONTRACTOR RELATIONSHIP: PCES BASED BIDS

    CONTRACT STRUCTURE

    CONTRACT SCOPE AND PRICE

    OWNER & CONTRACTOR COMMON INVESTMENTS

    SHARE INFO & DATA ESTABLISH COMMON TEAM

    DEVELOP REAL PARTNERSHIP

    ...

  • 7/29/2019 Parametric Cost Estimates

    27/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 2

    CONCLUSIONS

    REQUIRES MANAGEMENT SUPPORT

    NEEDS COMPANY CHAMPIONS

    REQUIRED CONSTANT SELLING

    CONSIDERABLE START-UP COST

    TEAM REQUIRES TRAINING

    REQUIRED CULTURE CHANGE

    IMPLEMENTATION IS A CHALLENGING EFFORT

    DATABASE DEV. AND DATA NORM. ARE THE MOST CHALLENGING EFFORTS

    EFFORT: 95% DATABASE DEV. & DATA NORM., 5% CALIBRATION

    REQUIRED PROJECT FULL UNDERSTANDING

  • 7/29/2019 Parametric Cost Estimates

    28/28

    PARA... START!

    WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 28