PARAMETERS, STRENGTH &

ISSUES FOR LOW PERFORMING STATE

BIHAR

AS ON 01.01.2012

Page 2: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Requirement of school infrastructure• As per RTE act 2009 norms for school building are as under

which are to be completed by 31.03.2013.

All – weather building consisting of-

• At least one class-room for every teacher;

• An office-cum-store-cum-HM room;

• Barrier-free-access;

• Separate toilets for boys and girls;

• Safe and adequate drinking water facility to all children;

• A kitchen where mid-day meal is cooked in the school;

• Playground;

• Arrangements for securing the school building by boundary wall or green fencing;

• There shall be a library in each school providing newspapers, magazines and books on all subjects, including story-books.

Page 3: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Parameters

Page 4: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Comparison of completion rate (%age)

Components

Overall completion

ratePS UPS ACR DWS Toilets

National level 74% 77 % 87 % 70 % 94 % 71 %

Bihar State 55.26 73.37 94.49 48.85 90.53 68.25

Components State level district level block level

Bihar State 100.00 55.11

Supervision Structure (%age available)

Note: - At State level only 3 technical personals are available who are, not sufficient for providing resource support and monitoring 37 districts and more than 550 blocks. No organized technical personals are posted at block level. The vacancies of technical personals as per approved strength is 171.

Page 5: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Components Third partySchool layout/ school campus

plan

Environmental assessment

Bihar In Position In progress In progress

Components SCR%age of schools with SCR>35

PS UPS

Bihar 83 72 % 78 %

Status of Student Classrooms Ratio

Status of Third Party, Campus Plan, Environmental assessment.

Page 6: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

ComponentsACR

Boys toilets

Girls toilets

DW faciliti

esRamps

Boundary Wall

Bihar State 133660 22164 42501 5529 35756 37665

Total components

277275

Gaps as per DISE 2010-11

Note: - The Gap for boys toilets, drinking water facilities include schools without these facilities in rural areas as well.

Total components gaps: - 277275. These components do not include PS, UPS, HM Rooms, electrification CFE, Bala elements etc.

Page 7: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

ComponentsOverall spillover

componentsGaps of all

componentsTotal

Bihar 96627 277275 373902

Spillover Components

Spillover components IP & Not Started as on 30.09.11

Components PS UPS ACR DWS Toilets Others Total

Bihar 4651 11 74451 942 16572 - 96627

Total components yet to be completed.

Note: - Bihar State completed 145680 components ending 31.03.11.

Page 8: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

States

Allocation AWP&B 2011-12 as on 30.09.11

Expenditure against

allocation upto 30.09.11

%age expenditure

(as on 30.09.11

(NLCE= 21% )

Bihar 395686.42 7362.87 1.86

Financial Progress of AWP&B 2011-12

StatesAllocation as on

30.09.11

Expenditure against

allocation upto 30.09.11

%age expenditure

(as on 30.09.11 (NLCE= 74% )

Bihar 1069495.06 513506.30 48.01

Cumulative financial Progress of as on 30.09.11

Note: - The expenditure of Kerala (96%), Assam (48%),Gujarat (47%), MP (62%), Orissa, Punjab, Tripura, UP above 40%.

Page 9: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

StatesExcess rooms

available

Target reconciled or not

Allocation reconciled or not

Bihar 39634

There is difference in ACR, DWS and toilets (DWS component was reconciled upto 31.03.11)

The State has not added the allocation of 2011-12. Hence showing huge difference.Allocation as per PAB= 10695 croresState allocation = 6606 crores

Excess rooms available and reconciliation of targets

Page 10: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Strength &

issues

Page 11: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

• Third party evaluation in place.• Vertical expansion particularly for existing classrooms

under taken.• Provision for earth quake resistant measures taken duly

approved by competent authority (Dr. A. S. Arya).• Architect available at State level.• Community manual in local language available.

Strength

Page 12: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Comparison of Achievement of Bihar for 2010-11 and during Current year

(01.04.2011 to 30.09.11)

Components Achievements during 2010-11

(completed)

Achievements during 01.04.11 to

30.09.11 (completed)

Primary School 2233 607

Upper Primary schools 8 4

Additional classrooms 12206 18927

Drinking water facilities 5564 1686

Toilet facilities 6127 9948

Page 13: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

• The fundamental requirement of planning of school campus plan is missing. It has been left to Junior most functionaries with the result of haphazard growth of school campus

• The incremental planning should have been planned as shown.

Issues

Page 14: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

Planning for future, now

Spaces are accessible to all children

Planning holistically, with space for future expansion

Page 15: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

• The completion rate is only 55% which is far below than the National average of 74%.

• More than 96627 spillover components (not including HM rooms, electrification, CFE and Bala element etc.) including large number of new PS, additional classrooms, are in progress or not started so far as on 30.09.11.

• Huge ACR gaps of 1.33 lakhs still exists against total of 3.08 lakhs ACR gaps in the country.

• State has large gaps in toilets for boys and girls, ramps, boundary wall/green fencing etc.

• The capacity building in 2010-11 for completion of ACR was very low. State completed only 12206 ACR.

• State has to coordinate effectively with sanitation mission in the State for completion of above mentioned gaps in rural areas.

Page 16: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

• The supervision structure at State level is weak and need to be strengthen for supervision monitoring and technical support.

• Organized supervision structure at block level do not exists.• State has 6 districts which fall under earth quake zone V and 23

districts in Zone IV.• The systemic requirements of maintenance of expenditure

register, cashbook, daily cement register, site order book are not being updated and transparency is being completely ignored which is injurious for the quality control and financial management.

• Most of the ramps are not being constructed as per codal requirement. The required slopes of 1:12 is not being maintained. The railing is also not being provided.

• Plinth protection is not being provided in most of the schools.• No SMC constituted at school level under RTE compliance.• Technical resource support and field monitoring by State level

team is lacking.• Inconsistency in reporting of cumulative progress reports and

AWP&B reports.

Page 17: PARAMETERS, STRENGTH & ISSUES FOR LOW PERFORMING STATE BIHAR AS ON 01.01.2012

• Civil works of AWP&B 2011-12 not started till 30.09.11.

• Need for reconciliation of physical and financial targets.

• SCR is 83 against average SCR of 31 and is highest in the country.

• Distribution of classrooms to be done judiciously to avoid excess classrooms in certain schools.

• 39,634 excess rooms available in various schools although there is huge short fall in ACR gaps.

• The State has completed up till 31.03.11 only 1,45,680 components against a Gaps of 3,73,902 components which exists as on date

• A question to ponder: How the State is planning to complete gaps of spillover and yet to plan of 3,73,902 component.