PARAMETERS AND ISSUES FOR LOW
PERFORMING STATES
AS ON
30.09.11
Requirement of school infrastructure
• As per RTE act 2009 norms for standard schools for school building are as under: and to be completed by 31.03.2013.
All – weather building consisting of-
• At least one class-room for every teacher;
• An office-cum-store-cum-HM room;
• Barrier-free-access;
• Separate toilets for boys and girls;
• Safe and adequate drinking water facility to all children;
• A kitchen where mid-day meal is cooked in the school;
• Playground;
• Arrangements for securing the school building by boundary wall or green fencing;
• There shall be a library in each school providing newspaper, magazines and books on all subjects, including story-books.
Parameters
States
Cumulative completion
rate(NLCCR =
74%)
Primary school
completion rate
(NLCCR = 76.81%)
Upper primary schools
completion rate
(NLCCR = 87%)
Additional classrooms completion
rate(NLCCR =
70%)
Orissa 70.65 73.04 106.59 68.48
Supervision Structure (%age available)
States State level district level block level
Orissa 44.44 81.8291.77
States Third partySchool layout/
school campus planEnvironmental
assessment
Orissa In Position In progress In progress
States SCR%age of schools with SCR>40
PS UPS
Orissa 26 19 % 31 %
Status of Student Classrooms Ratio
Status of Third Party, Campus Plan, Environmental assessment.
Gaps DISE 2009-10 as on 1.4.11
StatesACR DWS Toilet
for boysToilet
for Girls
Total
Orissa 4036 5797 45260 32965 88058
States
Overall spillovercompone
nts
Gaps all components
Total %age expenditur
e as(NLCE =
73%)
%age completion
(NLCE= 74% )
Orissa 21395 88058 109453 85.08 85.08
Spillover Components
Spillover components IP & Not Started as on 30.09.11
States Capacity building
ACR
PS UPS ACR DWS Toilets Others Total
Odisha 10786 1546 -1172
11678 1432 5567 21395
States
Allocation AWP&B 2011-12
as on 30.09.11
Expenditure against
allocation upto 30.09.11
%age expenditure (as
on 30.09.11
Orissa64134.41 26543.73 41.39
Financial Progress of AWP&B 2011-12
States
Allocation AWP&B 2011-12
as on 30.09.11
Expenditure against
allocation upto 30.09.11
%age expenditure (as
on 30.09.11
Orissa 313366.15 266611.98 85.08
Cumulative financial Progress of as on 30.09.11
StatesExcess rooms
availableTarget
reconciled or not
Allocation reconciled or not
Orissa 15311
The process of reconciling the
targets is almost
complete.
The process of reconciling the allocation is almost complete.
However State is surrendering Rs 37 crores approximately
Excess rooms available and reconciliation of targets
issues
Orissa• The completion rate is far below than the National average.
• More than 33000 spillover components including large number of new PS, UPS and additional classrooms, are in progress or not started so far as on 31.03.11. In addition to 13433 components have been added for AWP&B 2011-12 leaving besides furniture and library components.
• State has large gaps in toilets for boys and girls, ramps, boundary wall etc. although state has manageable ACR gaps out of which 7841 ACR have been approved by PAB for 2011-12.
• State has to coordinate with sanitation mission in the State for completion of above mentioned gaps in rural areas.
• The supervision structure at State level is weak and need to be strengthen for supervision and monitoring.
• State has 12ve Cyclone prone districts namely, Bhadrak, Cuttack, Dhenkanal, Ganjam, Jagatsinghpur, Jajpur, Kendyapara, Keonjhar, Khurda, Mayurbhanj, Nayagarh and Puri. State has to ensure disaster management and design the school infrastructure and make them cyclone resistant as per codal requirements.
• The systemic requirements of expenditure register, cashbook, daily cement register are not been updated and transparency is being completely ignored which is injurious for the quality control.
• Most of the ramps are not being constructed as per codal requirement. The required slopes of 1:12 is not being maintained. The railing is also not being provided.
• Although there is provision of plinth protection in the estimates but in variably the plinth protection not been provided on the ground with the result that is endangering the foundation of the building.
• MHRD guideline provide composite schools having classrooms, separate toilet for boys and girls, adequate drinking water facilities, Kitchen shed, child friendly elements, boundary wall/fencing. It has been observed that in newly constructed school building, these are not being secured with boundary wall/fencing.
• Flooring in the classrooms is not being laid as per IPS flooring i.e. of panels not more than 2 sqm.
• Schools/classrooms design need rethinking for better cross ventilation and light. Where ever quality bricks (kiln bricks) are available are construction is being done with course stone masonry the frame structure can be dispensed with masonry
structure to make it cost effective.
Thanks