Upload
phamtuong
View
219
Download
1
Embed Size (px)
Citation preview
Updated Resettlement Plan Final Report August 2014
Papua New Guinea: Bridge Replacement for
Improved Rural Access Sector Project-Magi
Highway
Prepared by Department of Works, Port Moresby for the Government of Papua New Guinea
and the Asian Development Bank.
This is an updated version of the draft originally posted in December 2014 available on http://www.adb.org/projects/documents/bridge-replacement-improved-rural-access-sector-project-magi-highway
This Updated Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
INDEPENDENT STATE OF PAPUA NEW GUINEA
DEPARTMENT OF WORKS
`L2783/2784 PNG: BRIDGE REPLACEMENT FOR
IMPROVED RURAL ACCESS SECTOR PROJECT (BRIRAP)
I. Resettlement Plan Update– Magi Highway
Department of Works
August, 2014
I: Resettlement Plan – Magi Highway
Resettlement Plan: Bridge Replacement for Improved Rural Access Project (BRIRAP)
Document Stage: Final Draft
Project Number: L2783/2784 - PNG
May, 2014
Exchange Rate: 1USD = 2.8268
1PGK = 0.3538
Papua New Guinea: Bridge Replacement for Improved Rural Access
Project (Magi Highway)
Prepared by Department of Works, Port Moresby, for the Asian Development Bank.
The Resettlement Plan is a document of the borrower. The views expressed herein do not
necessarily reflect those of ADB’s Board of Directors, Management, or staff, and are final
updates.
Table of Contents
Abbreviations and acronyms………………………………………………………………………………………. iv
Glossary of terms……………………………………………………………………………………………………….. v
Map 1: Project Coverage…………………………..…………………………………………………………. vi
A. Executive Summary………………………………………………………………………………………………….. 1
Table 1: Summary of Eligibility Criteria…………………………………………………..………………….. 2
B. Project Description………………………………………………………………………………………………….. 3
Table 2: Bridge Span and Estimated Cost new bridge replacement…………………………. 4
C. Scope of Land Acquisition and Resettlement………………………………………………………….... 4
i. Projects Potential Impacts………………………………………………………………………………………….. 4
ii. Scope of Land Acquisition…………………………………………………………………………………………... 4
Table 3: Scope of Land Acquisition………………………………………………………………………..... 5
iii. Effects of Assets Lost…………………………………………………………………………………………..……... 5
iv. Common property resources……………………………………………………………………………………... 5
D. Socio Economic Information & Profile…………………………………………………………………….. 6
i. Demographic features of affected peoples……………………………………………………………….. 6
ii. Impacts of Land & Assets Acquisition on affected peoples………………………………………… 7
iii. Projects Impacts on poor, Different Ethnic groups, and other vulnerable groups……….. 9
iv. Gender and Resettlement Impacts……………………………………………………………………………… 10
E. Information Disclosure, Consultation and Participation…………………………………………… 11
i. Project Stakeholders……………………………………………………………………………………………… 11
ii. Consultation & Participation Mechanisms…………………………………………………………………… 11
iii. Activities undertaken to disseminate Project & Resettlement Information………………… 11
Table 4: Key Dissemination and Resettlement Activities ………………………………………… 12
iv. Results of Consultations with affected people…………………………………………………………… 12
v. Disclosure of the draft resettlement plan…………………………………………………………………… 13
vi. Planned information disclosure measures during project implementation………………… 13
F. Grievance Redress Mechanism……………………………………………………………………………….. 14
G. Legal Framework…………………………………………………………………………………………………….. 15
i. National & Local Laws & ADB Policy requirements…………………………………………………….. 15
Table 5: Comparison of PNG Laws & ADB Policy & Gap –Filling Measures……………… 18
ii. Resettlement Policy Principles for the project…………………………………………………………… 18
iii. Principles and Methodologies for determining valuations and compensation rates….. 19
iv. Description of Land Acquisition…………………………………………………………………………………. 19
H. Entitlements, Assistance & Benefits………………………………………………………………………… 20
i. Displaced Persons Eligibility for Entitlements…………………………………………………………….. 20
Table 6: Entitlement Matrix……………………………………………………………………………………. 21
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
ii
Table 7: Entitlements to Entitled Persons……………………………………………………………….… 22
ii. Assistance to Vulnerable Groups……………………………………………………………………………….. 22
iii. Opportunities for affected persons to derive appropriate development benefits……… 22
I. Relocation of physical Structures……………………………………………………………………………. 23
i. Options for relocating physical structures………………………………………………………………… 23
ii. Consideration of Alternative relocation sites……………………………………………………………. 23
iii. Time Table for site preparation and transfer……………………………………………………………. 23
iv. Legal requirements to regularise tenure and transfer title……………………………………….. 23
v. Measures to assist displaced persons……………………………………………………………………….. 24
J. Income Restoration and Rehabilitation……………………………………………………………………. 24
i. Possible Livelihood Risks…………………………………………………………………………………………….. 24
ii. Income Restoration Program……………………………………………………………………………………… 25
iii. Special Measures to support vulnerable groups…………………………………………………………. 25
iv. Specific gender considerations…………………………………………………………………………………… 25
v. Suggested Training Programs………….………………………………………………………………………….. 26
K. Resettlement Budget & Financing Plan…………………………………………………………………… 26
i. Itemised budget for Resettlement activities………………………………………………………………. 26
Table 8: Resettlement Budget……………………………………………………………………………….. 27
Table 9: Resettlement Support Services Budget………………………………………………….. 27
ii. Flow of funds……………………………………………………………………………………………………………… 27
iii. Justification for calculating compensation rates and other cost estimates………………… 28
iv. Sources of Financing………………………………………………………………………………………………….. 28
L. Institutional Arrangements…………………………………………………………………………………….. 28
i. Responsibilities and mechanisms for carrying out Resettlement Plan………………………… 28
ii. Institutional capacity building program……………………………………………………………………… 29
iii. Role of Civil Society Groups………………………………………………………………………………………. 30
iv. Involvement of Women’s groups in Resettlement Planning and Management…………. 30
M. Implementation Schedule…………………………………………………………………………………….. 30
Table 10: Implementation Schedule (1) …………………………………………………………………. 31
Table 11: Implementation Schedule Update (2) ……………………………………………….. 32
N. Monitoring & Reporting………………………………………………………………………………………… 33
Table 12: Monitoring and Evaluation Indicators……………………………………………………….. 34
Tables
Table 1: Summary of Eligibility and Entitlements Criteria Matrix for DPs………………… 2
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
iii
Table 2: Bridge span and estimated cost of new bridge replacement…………………….. 4
Table 3: Scope of Land Acquisition…………………………………………………………………………. 5
Table 4: Key Dissemination and Resettlement Activities…………………………………… 12
Table 5: Comparison of GoPNG Laws & ADB –Policy & Gap – Filling Measures….. 18
Table 6: Entitlement Matrix……………………………………………………………………………….. 22
Table 7: Entitlements to Entitled Persons………………………………………………………….. 22
Table 8: Resettlement Budget……………………………………………………………………………. 27
Table 9: Resettlement Support Services Budget………………………………………………… 27
Table 10: Implementation Schedule 1..……………………………………………………………….. 31
Table 11: Implementation Schedule 2…………..…………………………………………………….. 32
Table 12: Draft Monitoring and Evaluation Indicators………………………………………….. 34
Appendices
Appendix I: Socio-Economic Survey………………………………………………………………………… 43
Appendix II: Public Information Bulletin…………………………………………………………………… 44
Appendix III: Land Acquisition Cadastral Survey Plan: Dogona Bridge……………………….. 45
Appendix IV: Land Acquisition Cadastral Survey Plan: Kokebagu River Bridge…………… 46
Appendix V: Land Acquisition Cadastral Survey Plan: Sivitatana Bridge…...………………. 47
Appendix VI: Land Investigation Report and Land Valuation: Dogona..……………………... 48
Appendix VII: Land Investigation Report and Land Valuation: Kokebagu River…………… 49
Appendix VIII: Land Investigation Report and Land Valuation: Sivitatana……..…………….. 50
Appendix IX: Improvement and Crop Valuation: Dogona………………………………………. 51
Appendix X: Improvement and Crop Valuation: Kokebagu River………………………….. 55
Appendix XI: Improvement and Crop Valuation: Sivitatana…………………………………... 59
Appendix XII: Contract of Sale between State & Landowners: Dogona.......................... 62
Appendix XIII: Contract of Sale between DPs and State: Brown River…………………………. 72
Appendix XIV: Contract of Sale between DPS and State: Sivitatana…………..……………….. 87
Appendix XV: List of APs on all Bridge sites…………………………………………………………………. 97
Appendix XVI: Photographs of DPs……………………………………………………………………………….. 102
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
iv
Abbreviations & Acronyms
ADB Asian Development Bank
APs Affected Persons
DLO District Lands Officer
DOL Department of Lands and Physical Planning
DOW Department of Works
DMS Detailed Measurement Survey
EA Executing Agency
EIA Environment Impact Assessment
GAD Gender Awareness Development
GAP Gender Action Plan
GoPNG Government of Papua New Guinea
Ha Hectares
HH Household
HIV/AIDS Human Immunodeficiency Virus/Acquired Immunodeficiency of Syndrome
IA Implementing Agency
IOL Inventory of Loss
LLG Local Level Government
MOA Memorandum of Agreement
OPA Office of Provincial Administration
PIU Project Implementation Unit
PLO Provincial Lands Officer
PPTA Project Preparatory Technical Assistance
IEE Initial Environment Examination
IPSA Initial Poverty and Social Assessment
JICA Japanese International Cooperation Agency
LNQ Liquefied Natural Gas
MTDP Medium Term Development Plan
NGO Non-Government Organisation
PNG Papua New Guinea
PSA Poverty and Social Assessment
RC Replacement Cost
RF Resettlement Framework
ROW Right Of Way
RP Resettlement Plan
SD&G Social Development & Gender
SES Social Economic study
SPRSS Summary Poverty Reduction and Social Research
SPS Safeguard Policy Statement (ADB)
STI Sexually Transmitted Disease
BRIRAP Bridge Replacement for Improved Rural Access Project
TOR Terms of Reference
WB World Bank
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
v
GLOSSARY OF TERMS
Meaningful consultation A process that (i) begins early in the PPTA and is carried out on an
ongoing basis throughout the project cycle. (ii). Provides timely
disclosure of relevant and adequate information that is
understandable and readily accessible to affected people. (iii). Is
undertaken in an atmosphere free of intimidation or coercion;
(iv).is gender inclusive and responsive, and tailored to the needs
of disadvantaged and vulnerable groups; and (v) enables the
incorporation of all relevant views of affected people and other
stakeholders into decision making, such as project design,
mitigation measures, and implementation measures.
Affected Persons
(APs)
Persons who are impacted by the project; either be relocation of
Households, economic losses including; Markets, trade stores,
and crops and also those who; live close to the project such as
neighbouring clans, public health and education workers, people
of the same electorate, province or people from other provinces
who regularly use the bridge.
Displaced Persons (DPs) In the context of involuntary resettlement, displaced persons are
those who are physically displaced (relocation, loss of residential
assets, access to assets, income sources, or means of livelihoods)
as a result of (i) involuntary acquisition of land, or (ii) involuntary
restrictions on land use or on access to legally designated parks
and protected areas.
Physical Displacement Relocation, loss of residential land, or loss of shelter as a result of
(i) involuntary acquisition of land, (ii) involuntary restrictions on
land use or on access to legally designated parks and protected
areas.
Economic Displacement Loss of Land, assets, access to assets, income sources, or means of
livelihoods as a result of (i) involuntary acquisition of land, or (ii)
involuntary restrictions on land use, or on access to legally
designated parks and protected areas.
Gender Mainstreaming The process of ensuring that gender concerns and women’s needs
and perspectives are explicitly considered in projects and
programs, and that women participate in the decision making
processes associated with development-based activities.
Country Safeguard
Systems.
This is the legal and institutional framework of Papua New
Guinea, and it consists of its national, sub national, or sectoral
implementing institutions and relevant laws, regulations, rules
and procedures that pertain to the policy areas of social safe
guards.
Significant Impact The loss of 10% or more of productive assets, (income
generation),or physical displacement and or both.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
vi
MAP 1: PROJECT LOCATION
1
A. EXECUTIVE SUMMARY
1. The project aims to replace temporary timber and bailey bridges and other badly
deteriorating bridges on the National Highways in PNG with permanent bridges. The old
bailey bridges will be used on Provincial and District roads to provide access to rural areas.
The Project cover 27 replacement bridges on five priority National Highways and 22 reusable
bridges on provincial, district and local roads connecting rural communities within the
corridor of influence of these five priority national highways.
2. This contract package along the Magi highway in the Central Province involves the
replacement of three single lane steel plate girder bridges more permanent two lane steel
plate girder bridges. The old bridges will be dismantled and transported to Kwikila DOW base
camp. The Central Provincial Government and DOW will decide on the relocation of the three
bridges within the district. According to Land investigations at all bridge sites there are more
than two land claimants without any dispute.
3. This sub-project requires land acquisition, which will not displace Households but will
affect other improvements. Compensation for loss of land, gardens, tree crops, and other
social and economic establishments need to be made prior to commencement of works is
critical to ensuring that the construction commences and completes without disruption.
4. The State will acquire 6.1863 hectares of land for the project, which will affect many
food crops and plants on the ROWs at the three bridge sites. Loss of assets will include one
grave yard and many food crops and economic plants and trees. Compensation will be paid
to the entitled persons at replacement cost for foregoing their assets. Total Costs of
displacement at replacement cost will amount to Three Hundred and Eleven Thousand,
Seven Hundred and Ninety Two Kina and Seventy Toea (K311,792.70). On that basis,
customary landowners have unanimously agreed to sell their land to the State and for
reasons being that they desperately need permanent bridges for safe access. and they have
sufficient land for sustaining livelihoods
5. The number of HHs and DPs identified and recorded in the initial RP (2011) was
substantially reduced from 48 HHs to 41 at an average occupation rate of 5 persons per HH
and DPs from 258 to 205. All these HHs are headed by males. Both males and females
contribute in household activities to feed every household member. The DPs originate from
within the Rigo Central district despite certain claims that the Sivitatana DPs migrated from
Inland Rigo while Kokebagu DPs originate from Saroa village. In terms of education and
health services, the DPs have the drive the to send school age children to school as most
primary schools are located within their respective villages but the completion rate is poor.
Due to poor water quality and food intake their health status is poor where many people die
out of dysentery related diseases before they reach the nearest hospital.
6. All DPs at this sub-project areas relay on subsistence farming. Cash income from
garden produce such as vegetables, yams, taro, Aibika, and cash crops like coconut, support
their livelihoods. All DPs are eligible and are entitled to receive displacement fees at
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
2
replacement costs. This is likely to have positive impact on all DPs including women and
children and other vulnerable groups in the short term.
7. The following table shows the criteria being applied to determine eligibility to receive
an entitlement:
Table 1: Summary of Eligibility and Entitlements Matrix Criteria for DPs
8. Both male and female DPs expressed full support for the construction as they want to
have safe access because Dogona is a traffic hazard while Kokebagu and Sivitatana
continuously gets over flooded during heavy rains and prevent access for over a week.
Immediate replacement would be more of greater benefit to DPs including Affected Persons
(APs) mainly those who ply the Magi Highway between Port Moresby, Rigo and Abau
electorates in the Central Province. An initial MOA has been signed by DPs giving their
consent to the State to proceed with project implementation. A total of six contracts of sales
between the state and DPs have been signed to give effect to land acquisition in lieu of cash
payment.
9. The month of May is the cut-off date for any claims. DOW will commence
compensation payment in July 2014 based on the LIR and Valuation commissioned by DOW
as per Valuation. Compensation payments for both land acquisition and crop damage will be
paid to all identified DPs as there are no land disputes between DPs. The DPs expressed their
willingness to relocate upon receipt of compensation payments. ADB will be constantly
updated on the relocation progress.
Type of Impact Entitled Person (s) Entitlements
Permanent
Acquisition of Land
Legal Owner(s)
including customary
Landowners
Informal settlers on
land to be acquired.
Provision of similar size of land is not visible.
Will be paid compensation at replacement
costs for Land acquisition and damage to
households and crops.
Temporary Use of
Land
Legal or Customary
Land owners.
Contractor will pay rent on negotiated rates
between DPs & Contractor.
Loss of Crops and
Trees
All DPs irrespective of
Legal status.
All crops and trees deemed for damage will be
paid compensation based on market rates
Loss of Commercial
Structures
ALL DPs regardless of
Customary or migrant
settlers.
DPs will be provided compensation at
replacement costs without deductions for
depreciation or salvage materials or assistance
in finding an alternate site.
Loss of Livelihoods Any vulnerable HHs
identified by
additional social
assessment.
Vulnerable households will receive priority
employment for project construction &
maintenance work.
Unforeseen or
unintended impacts.
Concerned displaced
persons.
Will be determined as per the principles of
this RP & ADB’s Safeguard policies.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
3
B. PROJECT DESCRIPTION
10. The Project aims to replace aging and single lane bailey bridges and other badly
deteriorated bridges on the National Highways in Papua New Guinea (PNG) with double lane
permanent bridges. The old bailey bridges will be dismantled and re-deployed to Provincial
and District roads to provide access to rural areas. The Project will cover replacement of 27
bridges which include: 17 bailey bridges, two steel truss bridges, three steel plate girder
bridges, two log bridges and three cause-ways. Twenty two (22) of these bridges (17 bailey
bridges), 3 steel plate girder bridges and the two steel truss bridges) are reusable on the five
priority National Highways.
11. It is anticipated that improving access for rural communities will have positive impacts
on access to better social and economic services, and therefore better living standards.
Importantly this project will contribute to improved flow of traffic, less traffic congestion at
bridge sites, and a safer road transport service.
12. Expected overall outcome is improved and safer access to markets and social services
for rural population living along the selected road corridors and expected specific outputs
are: (i) Reduced bottlenecks on the National Highways, (ii). Safer journeys for both motorized
and non-motorized transport users on the roads, (iii). Improved capacity of the road agencies
especially Department of Works (DOW) and National Roads Authority (NRA) to manage
bridge assets but also to provide greater levels of accountability and transparency; and (iv)
maintenance of the bridges by beneficiary communities” (DOW 2011).
13. The project is aligned and consistent with the medium and long term national
development plans, goals and strategies. One of the targets of the National Governments
Strategic Development Plan 2010-2030 is that by 2030 eighty five percentages (85%) of rural
communities will have access to better and safer road transportation. This project will
contribute towards achieving that target. In addition, it should have positive impact on rural
industries such as Mining, Petroleum, Logging, Agro-forestry, Agriculture and other
downstream processing projects.
14. The Project is estimated to cost US$100 million and will be funded by an ADB loan of
US$90 million comprising a US$50 million ADF loan and US$40 million OCR loan, and
counterpart funding of US$10 million from the GoPNG.
15. The Magi Highway component of the project will cost US$12.9 million or K36.5 million
based on detailed engineering design (DED) and current exchange rates. Table 2 provides
details of the specifications of the three bridges and their estimated costs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
4
Table 2: Bridge span and estimated cost of new bridge replacement.
16. The existing Steel plate Girder Bridges (STBs) are small and deteriorating. These will
be dismantled, transported to and stored at DOW base Camp at Kwikila District Station. DOW
will make a decision in consultation with CPG whether or not to re-use them on provincial or
district roads in the Central Province.
17. This resettlement plan (RP) relates to the three bridges and the bridge site
communities that will be affected and have their land and garden crops displaced as a result
of the construction of the three new bridges.
C. SCOPE OF LAND ACQUISITION AND RESETTLEMENT
i. Projects Potential Impact
18. This sub-project does not require physical displacement of HHs meaning all bridge
sites have no HHs located within the ROWs. Thee Detailed Measurement Survey (DMS)
confirmed that the State will acquire 6.1863 hectares of land for bridge alignment and road
approach which becomes the ROWs on all three bridge sites as shown in (Appendix III,IV &
IV). The ROWs land currently accommodates: gardens, plants, and a grave yard.
ii. Scope of Land Acquisition
19. Table 3 shows the extent of land to be acquired (refer to details in Appendix VI, VII &
VIII) for full listing of names of DPs and the number crops and plants that will be foregone
(refer to Appendix IX, X & XI) for the full listing specific names of crops and plants and trees).
The following table indicates the summary of the land on which gardens and plants are
grown which will be foregone as a result of the ROW acquisition.
Name of
Bridge
Chainage Bridge
span (m)
2011 Est.
Cost (US$)
2014 Final
Cost Est (US$)
PNG Kina
Dogona 62.7km 25m US$ 6.4m US$ 2.3m K 6.5m
Kokebagu 77.6km 25m US$ 6.4m US$ 4.8m K13.6m
Sivitatana 80.7km 25m US$11.9m US$5.8m K16.4m
Total 75m US$24.7m US$12.9m K36.5m
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
5
Table 3: Scope of Land Acquisition
Bridge
Name
Estimate
d Land
Loss (ha)
Crops/Trees loss No of
DPs Lose
10%+
Dogona 2.0067 Sago, Bush trees,Mango trees, Nonu tree, Breadfruit
tree,Rosewood tree,Kwila tree,Pandanus Nuts trees,palm
trees,Flowers, other herbal plants, vanilla plant,Coconut
tree,Frangipani tree, Banana trees, betel nut tree, mustard,
pineapple, yam,taro, cassava,sugar cane,pawpaw,gum trees,
34
Kokebagu 1.8346Aibika, Banana, Sugar cane,Pawpaw trees,Rain
trees,Mustard plant,Taro Plant,Tomatoe plant,Aupa
Kumu,Coconut tree,Mango trees,Bean plants, betel nut
trees, bush trees, Taro crop,Parchoi plant,water curries,
Kaukau,Ross wood,cassava, guava trees,
80
Sivitatana 2.3450 Banana trees, coconut trees, pawpaw trees,mustard
plant,mango trees, Guva trees, Bush trees,Bread fruit
trees,pine trees,rain trees,palm trees, betel nut
palms,rosewood,sweet potato, gum tree, 1 graveyard
91
Total 6.1863 205
iii. Effects of Assets Lost
20. The loss of land, vegetables, cash crops and other trees will affect DPs daily food
intake and income. The DPs access to the sites to harvest betel nut, vegetables and other
edible crops grown on site will also be affected. Because these items are grown on the bridge
sites, they harvest and sell the extra harvests near each bridge site for the travelling public to
buy on an irregular basis, especially during harvest days. These economic activities will cease
as a result of the construction. Although the affected people have adequate supply of food
for daily consumption their alternative place of gardening will cease forthwith.
21. Extra portions of land will be required by the Contractor on each bridge site for
construction camp, Construction equipment and materials construction materials and
construction workers residential camps. The contractor and the customary landowner will
agree at a particular rental fee to occupy the land and then return it after the completion of
the construction.
22. There is only one mini market located 500 metres east of the Sivitatana bridge site
(refer to appendix XVI) that enables APs to sell their local produce to generate cash income.
This is not in the ROW, therefore will not be removed during the bridge construction. The
other two bridge sites do not have similar markets but some DPs confirmed that they do sell
food crops and betel nuts harvested from their gardens on the respective sites only during
harvest days.
iv. Common Property Resources
23. In these sub project areas, fish is considered the most common resource although the
rivers do not have the capacity to hold fish. Dogona bridge site presented no chance of
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
6
fishing due to its hilly location while the other two presented no signs of fishing. The locals
indicated that fishing is difficult in the rivers. The rain tree in the Kokebagu and Sivitatana
region has just become a common property which is of higher value and yields higher
revenue in the region as a result of two portable saw mills milling timbers to make pallets.
The individual owners are selling directly to saw mill owners those considered to have
communal ownership are sold by clan consensus and proceeds shared equally. Few rain trees
at Kokebagu will be removed.
D. SOCIO-ECONOMIC INFORMATION AND PROFILE
i. Demographic features of affected peoples
24. Users of the Hiritano Highway are mainly the indigenous people of the Rigo and Abau
Districts of the Central Province with a population of 237, 016 people. All these people use
the Magi Highway to commute from the respective districts to and from Port Moresby.
25. It has been identified that a total of 41 households housing 206 persons with an
average household size of 5.0 in these sub-project villages. The number of persons per
household ranges from a high of 5-7 at the Dogona and Sarokaina villages to 9 at the
Sivitatana village. It is however not an uncommon practice for households of 14-16 persons
in the Central Province. This sub-project area has the following demographic composition:
20 years and under - 41.0 %
21 – 40 years - 40.0 %
> above 40 years - 17 .0%
Unkown ages 2.0%
26. It is obvious from the above data that over 80% the population are young people. It
was noted that 45% are comprised of female population in the sub project villages and male
population consist of 55%. The general practice among the communities in the Central
province is that girls get married as early as 17 years. It also became evident that most girls
marry before they complete Grade 10 & 12.
27. The 73% enrolment rate in education indicates the positive attitude to education.
Despite the above enrolment rate 33.65% completed Gr.10. This number was further
reduced to 12.2% completing Gr.12. The drive to further the education prospect drops
among the DPs as they reach the higher pyramid of the education where 12.68% end up in
various colleges and only 4% completing University degrees. It was sad to realise that
attaining higher levels of education is not the desire of households at the bridge sites hence
the low rates of university graduates. This is attributed and constrained by social structures
of the clans and beliefs that all should be equal and subservient to the elders.
28. All HHs are headed by male DPs in this sub project area. Both male and female
population participate in subsistence gardening to support their livelihoods. Every member of
a family ranging from children to adults makes it their customary business to work hard to
provide food on the table for the whole family.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
7
29. The HH membership is usually comprised of extended members from both paternal
and maternal kinship. Distant relatives visit them from time to time but do not reside
permanently. There are two Highlanders, one Bougainvillean and one West New Britain
migrants are residing in Sivitatana village permanently but will not benefit directly because
they moved in fairly recently.
ii. Impacts of Land & Assets Acquisition on affected peoples
30. Income: DPs at the three bridge sites generate cash income from a variety of sources,
primarily from: sale of garden foods, betel nuts, trade stores, PMVs, timber milling and pallet
crafting, and remittance from relatives who work in formal jobs in urban centres. The DPs at
Kokebagu earn a relatively higher income of K20, 000.00 a month through timbers and
crafted pallets and supply regularly to CoCola factory, SP Brewery, and other big companies
like Monier and packaging companies in Port Moresby
31. Annual income per head ranges from K2,033 at Dogona, K6,071 at Kokebagu and K3,
033 at Sivitatana. These annual income levels per year are relatively higher compared to
other villages throughout PNG. The sub-project will also inject a substantially higher amount
of income through wages, purchase of goods at local markets, temporary land rentals and
sub contracts.
32. Benefits for Land acquisition are expected to be paid to the clans through the clan
leaders as indicated in the Contract of Sales Documents (Appendix XII, XIII & XIV). The village
leaders from all bridge sites confirmed their desire of having land acquisition monies paid
directly to them so that they would be responsible for distribution. The Councillors and
village leaders as well as members of the clans expressed their views with no uncertain terms
that they want DOW to pay DPs directly instead of the common practice of making payment
through Central Provincial Administration as they have experienced some bad practices by
officers from the Central Provincial Administration.
33. Compensation payments to individuals with garden plots and cash crops will be paid
directly to owners (see Appendix IX, X & XI). A separate MOA will be signed to formalize the
consent by the DPs to forego improvements and relocate as agreed and to undertake not to
make further demand from the state for compensation payments in the future. These
compensation payments are considered as benefits in lieu of foregoing their assets to pave
way for the construction of the three bridges.
34. DPs will receive compensation for Land purchase and Improvements (crops, planted
and natural trees and a grave yard).
35. Land Ownership: Landownership rights in these bridge sites remain with customary
owners which have been transferred from generation to generation through the patrilineal
lineage system. The female kinship cannot claim ownership rights.That right to claim land
ownership rights remain entirely with male population The Dogona bridge site is owned by
two clans namely Goriga clan and the Gininana clan. The Kokebagu bridge site is owned by
three groups namely: Aboga Kabudo and Tomura Mamaea from the Goina clan, and Mana
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
8
Inia of Dogoro clan. The Sivitatana bridge site is owned by Verave Rubu and Bole Rubu clans
(see appendices XII, XIII & XIV).
36. Livestock: Certain DPs at all bridge sites own between 2 to 4 pigs. Other than pigs,
there have been no visible signs of cattle grazing, goats or sheep farming. There are, however
evidences of people venturing in to chicken broilers at all the sites.
37. Common Property Resources: In these sub project areas, fish is considered the most
common resource although the rivers do not have the capacity to hold fish. Dogona bridge
site presented no chance of fishing due to its hilly location while the other two showed signs
of fishing but people do not fish. The locals indicated that fishing is difficult in the rivers. The
rain tree in the Kokebagu and Sivitatana region has just become a common property which is
of higher value and yields higher revenue in the region as a result of two portable saw mills
milling timbers to make pallets. The individual owners are selling directly to saw mill owners.
The trees that are considered to have communal ownership requires payment to the
community or clan where consensus is very often reached to share the proceeds equally.
38. Estimated total expenditure: The annual income described in paragraph 30 and 31
has not translated into improving living standards but are said to be spent on less important
goods. From the interviews it was noted that about 58% of total annual income is spent on
processed goods, 14% education and health care, 4% one clothes and foot wear,15% on
school fees and clothes and 10% on cultural and religious commitments. As a result of their
cultural believes, the concepts of saving or using such revenue to venture into businesses or
building permanent houses are not considered. Their existence is to make money now and
spent on consumables all at ones without savings for future use. This practice is exacerbated
by their customary believes that any endeavour to construct a permanent house or buying a
PMV truck would lead to death of the principle owner. Everyone in the villages must settle
and remain as equal apart from their paramount chief.
39. Occupational Structure: Most DP households are engaged in subsistence agriculture,
primarily from their garden patches to provide for their daily food consumptions. Commercial
agriculture, especially rubber, coconut and cocoa are not evident in the affected villages.
Small-scale subsistence farming in banana, coconut, and vegetables are mainly for HH
consumption with surplus production sold at mini markets for cash. Betel nut farming is but
not a major farming activity in the sub-project area. There are however about 16.68% of the
total population (both male & female) from the sub-project sites have fulltime occupations
either in the private or public sector in urban centres throughout PNG. DPs are quite excited
that they believe this project will provide windows of opportunity for paid jobs and increased
demand for market produce. It was noted that none of the DPs are involved in artisan or
handicraft production, arguing demand only exists for handicrafts produced in the Highlands,
Sepik regions or Milne Bay Province.
40. Operating trade stores and PMVs are business ventures pursued by some DPs. Three
DPs from Sivitatana own and operate Public Motor Vehicles (PMVs), five PMVs comprising 3
long tray dyna trucks and two 15 seater buses are owned and operated by Sarokeina villages ,
and several from Saroa village serve the Kwikila to Port Moresby travelling public. The PMVs
provide regular income for the drivers and crew members and of course the owners of the
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
9
PMVs. At Sarokeina 4 HHs operate 4 trade stores, five diesel retailers and road side store
goods are also sold by DPs. Saroa village has more than 5 trade stores.
41. Access to Public Services: Health care amenities, though not up to standard, are
within their reach. The DPs from the three bridge sites have access to Kwikila Health Centre,
while for smaller illnesses they get treatment from the respective Aid Posts. Kwikila Health
Centre provides services for immunization, awareness on communicable diseases and
HIV/AIDs. These rural health centres also provide treatments for Malaria, cough, water borne
diseases such as diarrhoea and dysentery and associated skin diseases. Cases of Typhoid, TB
and other chronic deceases are normally referred to Port Moresby General Hospital.
42. Water borne diseases and deaths are prevalent at the Kokebagu and Sivitatana River
bridge sites due to unboiled drinking waters. Water extracted from the rivers is generally not
boiled. DPs reported that the highest rate of death is caused by water-borne deceases like
diarrhoea and dysentery due to drinking dirty water, followed by Malaria, Typhoid and TB.
43. Educational facilities from elementary to lower secondary level are located well
within walking distance from the villages. That includes: Saroa Primary School (the oldest of
the three), Sarokaina and Sivitatana primary Schools. Both primary and secondary teachers
are attracted to these schools because the Magi Highway is in an excellent condition and Port
Moresby is not so far away.
44. Access to micro-finance is only available in Port Moresby making it relatively difficult
for DPs to access let alone the stringent collateral requirements of the banks1. Agricultural
extension services has not been provided for years although there is a Community
Development Officer based in Kwikila who literally does nothing due to funding constraints.
iii. Projects Impacts on poor, Different Ethnic groups, and other vulnerable groups
45. Poverty is a relativity term and a monetary definition, therefore does not really apply
in a rural setting. Given the strong culture of extended families caring for each other, it is
difficult to define and label one as being poor at present. What is possible however in the
medium term is to use present data and living standards of the DPs as the base point to
measure increments of attainment such as annual incomes, increased value of assets and
improved health and education conditions of the DPs pre-commencement of the project and
post completion of the project. And maybe then poverty will be more obvious than at
present time.
46. There are a few migrants from other ethnic groups living with the DPs who are very
much likely to benefit from the positive impacts of the bridge program. For example; In the
Dogona bridge there are migrants from Inland Rigo who live among the DPs who are most
likely to have a share of the benefits due to DPs. There are other individuals from Tari, WNB
and Bougainville living in Sivitatana who are also likely to benefit, although not directly.
1 Banks do not accept land at villages as collaterals for micro-financing
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
10
47. Similar to the poor persons, the vulnerable groups could not be easily identified. It is
quite normal for the DPs to cater for persons with disabilities, the elderly, the widows, and
the sick. Again the extended family culture diminishes traits of vulnerability. When asked
about vulnerability and desegregation of persons living with HIV/AIDs, the informants were
reluctant to expose any such stories except in expressing that persons living with HIV/AIDS
reside in Port Moresby, not at the villages impacted by the project. However, women DPs can
be classified as vulnerable groups who may be subjected to abuse by contract workers when
construction commences but presently they are well protected. The project will need to offer
special incentives to women such as job opportunities and scholarships for girls.
iv. Gender & Resettlement Impacts
48. Woman DPs when asked about the management and handling of large amount of
cash during the payment of compensation for land and crops forfeited for the construction of
the bridges, openly expressed their views that management and distribution of income from
any source are responsibilities of men. They expressed that although they would like their
voices heard in the decisions to be made, they would remain silent out of respect for their
custom, and to avoid family conflicts.
49. Being paternalistic societies, decisions relating to family and village welfare are
determined by men and passed on to women and children. It is the view of male DPs that
employment of casual workers be restricted to men however, it should not prevent the
contractor from employing women. Women are equally capable of doing any job whether it
be lifting metals, timbers, stone piling, digging using spades, cooking, washing or security
guards, or any other job because the SIS survey noted that women in all of Central Province
work harder than their male counterparts. Men are generally perceived as boastful and lazy.
Women DPs pointed out that if men folks work hard on their land, all arable land would be
cultivated.
50. The possibilities and incidents of family violence, marital problems, promiscuity and
alcohol related problems are inevitable and cannot be ruled out, as these have been
observed in many other similar projects in PNG. Continuous awareness on the effects and
impacts of these incidences including HIV/AIDs will contribute to mitigating these social and
health problems. Whilst it may be difficult to control these social disorders, preventative and
precautionary measures will be taken to cater for and attend to these social misconducts.
Where incidents relates to a contract worker and a member or members of the local
community, the Community Liaison officer (CRO) will facilitate meetings to ensure amicable
resolutions are reached and there is minimum disruption to construction work.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
11
E. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
i. Project Stakeholders
51. Primary project stakeholders are the Landowners who own and occupy the three
bridge sites. The nearby clans of the same tribe(s) are not regarded as party to this group
although they are members of the broader community in which they share common believes
and values and partake in social events such as cultural shows, church gatherings, and land
matters.
52. Secondary stakeholders are neighbouring clans, commuters from Inland Rigo, Hula,
and Abau District, respective local level governments and Central Provincial Government. The
bridges after construction will have many secondary stakeholders, especially PMV owners,
business houses and commuters.
ii. Consultation & Participation Mechanisms
53. Meetings with individuals and group consultations were the main mechanisms used
for consultation. Several meetings were convened with the DPs at various locations to discuss
the likely impacts of Land acquisition and forfeiture of personal and community assets such
as gardens where food crops, betel nut and coconut trees and cultural establishments are
located. Consultations commenced July, 2013 – April 27, 2014. A meeting was also held with
the Kwikila District Administrator at the District office to discuss management of issues.
54. Additional meetings were held with the Kwikila District Administration Officers at the
district office. The Kwikila District Coordinator for Public Works was working fulltime to assist
in the Land Investigation and Valuation of crops. CPG Lands Officer and Surveyor were invited
to meetings at DOW office and engaged to assist in mapping out each bridge site and to do
Land Investigation Report (LIR). The District management expressed their utmost desire to
assist the contractor to ensure there is no lost time during implementation.
iii. Activities undertaken to disseminate Project Information and Resettlement
Information
55. Disclosure of information of the project, the construction of the bridges and its
implications including loss of land and assets commenced in March 2013. All stakeholders
were aware of the replacement of bridges and the need to forego land and gardens (assets).
Information was disseminated during the PPTA and during the DMS and SIS consultations,
DPs were fully informed of the project and its implications.
56. Details of these meeting dates and times are listed herein:
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
12
Table 4: Key dissemination and resettlement information activities
Dates Bridges Notes Participants11/11/13 Dogona,
Kokebagu and
Sivitatana.
SIS Meetings on site and explanation of the
need to acquire land damage to crops.
DOW & DPs.
14/11/13 Meeting with
Central
Provincial LO
Meeting to discuss Cadastral Plan, LIR,
Valuation of properties & SIS .
Central Prov. Lands
and DOW.
15/11/13 Dogona Bridge
Sivitatana
Kokebagu
Discussed SIS and Land ownership. 2hr at
Sivitatana village.
1 hour discussion with DPs at Dogona bridge
site.
15 minutes at Kokebagu due to bad whether.
DOW & DPs at
Sivitatana village.
Dogona.
25/11/13 DOW Office
Re. Sivitatana
Discussed SIS and equal distribution of Land
compensation among clanmembers & DPs.
Councillor Babaga
& DOW.29/11/14 Dogona
Kokebagu
Sivitatana
9-11am.Meeting with DPs
12-1pm: Meeting with DPs
3-4pm: Meeting with DPs
Meetings on site
25/05/14 Dogona
Kokebagu
Sivitatana
10-11am Meeting with DPs
12-1pm: Meetings on site
2-4pm: Meetings on site
All meetings on site
Effective consultations started in July 2013 and terminated on the 21 April, 2014. All bridge sites were
visited seven times each to conduct Cadastral Mapping, LIR and quantity surveying. Every DP was
informed about the need to acquire land and pay compensation for all assets at replacement cost.
v. Results of Consultations with affected people
57. The Primary stakeholders acknowledged the State’s right to build roads and bridges
for the good and interest of the Public. There was overwhelming support with little objection
to the loss of assets and resettlement. Following are some of the remarks from the DPs at
some of the meetings.
That all Land compensation payments be made to clan leaders. The Leaders will then
discuss with respective beneficiaries and decide whether to distribute evenly,
equitably or invest in small and sustainable businesses.
That all crop payments be made direct to owners of garden plots.
That DOW should handle all cash payments instead of Central Provincial Lands or
Provincial Works due to: mismanagement, demand for commissions, travelling
allowances, or delaying payments. Any deposits into District office for disbursement
to DPs will be a complete disaster. All third parties should be eliminated to ensure
transparency in cash distribution.
Well qualified welders, stone wall builders, carpenters, plumbers, drivers, cooks,
cleaners and all other trades are available in each village. They asked DOW to direct
all contractors to consider employing local labour (both male and females) instead of
recruiting from other places.
Access to clean water supply was a major concern raised by all the DPs. The
provincial and national governments have not provided any assistance over the years
and with the population increase in the area, there has been increased demand for
clean and safe drinking water. DPs were advised that the DOW in collaboration with
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
13
the LLG would facilitate the possibility of the contactor providing assistance in this
regard.
Women expressed their desire to participate in the bridge construction as workers
along-side their male counter parts. They were advised that the contractors will be
obligated to ensure that special considerations be given to women DPs for
employment opportunities.
DPs have been managing the issue on HIV/AIDS at the village level and they said it’s
not a major issue of concern, however, the State expects the Contractor to have a
contingency plan to carry-out awareness campaigns through community meetings,
delivery of pamphlets, posters and erect bill boards and issue condoms on site.
Kwikila District Administration was particularly impressed with the briefing and
pledged their support during construction phase. The District Management also
expressed their desire to decide on the use of old bridges because they know the
priority areas under their district infrastructure plan. DOW and District Management
need to discuss this matter further to reach some compromise.
vi. Disclosure of the Planned Resettlement plan
58. Initial information about the project, its negative and positive impacts including
displacement and resettlement were verbally relayed to the District Administration. They
were also engaged in the detailed Measurement Survey (DMS) which enabled them to know
the exact parcel of land that would be acquired, and subsequently the loss of gardens and
garden crops and other trees of economic value.
59. Relevant information contained in this report has been disclosed to key persons at
each site, especially where it relates to land acquisition, crop and vegetation damage,
payment schedules, and beneficiaries; and strategies involved in providing equal job
opportunities for all gender groups.
60. The Community Liaison officer (CLO) will advise DPs of additional land acquisitions for
the contractor’s site camp office, accommodation and water source. In consultation with the
DOW, the CLO will from time to time inform DPs through brochures and leaflets of progress
of the project.
61. Communication with DPs was less of an issue as nearly all DPs speak and understand
English and pidgin. For the motu speakers, fortunately there were pidgin speakers who were
able to interpret to the motu speakers. The Official languages for this particular component
of the project should be English and pidgin.
vii. Planned information disclosure measures during project implementation
62. Maintaining regular flow of information on progress status of the project and issues
on a regular basis will mitigate disruptions and enable smooth progress. Mechanisms that
will be employed will include newsletters, leaflets, radio announcements, and periodic
consultations with DPs. DOW will endeavour to disclose all necessary information to all
stakeholders through mandatory progress reports.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
14
F. GRIEVANCES REDRESS MECHANISM
63. With regards to Land Disputes, the Central Province DOW will establish a grievance
redress mechanism to receive and address project related concerns and to resolve land
related concerns that may arise during project implementation. DPs will be informed by DOW
on how they can access to the grievance redress mechanism. Other than disputes relating to
landownership rights are legally contestable in a court of law as per the Land Disputes
Settlement Act 2000, it is anticipated that most grievances will be resolved through
traditional mediation process.
64. The Project in collaboration with the Central Province Lands Officer, who may be
assisted by the District Lands Officers, will institute a process to resolve disputes and
grievances based on the accepted procedures of mediation. As required the participation of
the appointed and traditional leaders will be facilitated to achieve a satisfactory resolution of
issues at the local level.
65. In general it is anticipated that customary mediation will yield satisfactory results
although in accordance with the Gender Plan prepared for this project, every attempt will be
made to ensure that women DPs, irrespective of traditional constraints, will be included and
not excluded from the mediation processes outlined here. However, it also needs to be
noted that this process varies from clan to clan including those DPs at the three bridge sites
included in this RP.
66. DPs can also lodge a complaint with the PIU in Port Moresby. Although the DPs on
each bridge site are closer to Port Moresby, they are at liberty to lodge such complaints with
the Project Safeguards Staff and Project Supervision Consultants who will also assist in
registering their complaints with the PIU. This will include assisting aggrieved DPs to prepare
their specific grievances and the PIU Project Manager will consider the complaint and within
15 working days convey a decision to the DPs. The Safeguards Staff as well as Local
Government Officials will assist the Project Manager in reviewing and addressing the
complaint. The Safeguards Team will also facilitate communication between the DPs and PIU
in this process. If the DPs are not satisfied with the decision, they may then take the
grievance to the PNG Judicial system.
67. If the grievance is to be taken to the PNG judicial system as per the Land Disputes
Settlement Act 2000, the following three steps in the dispute resolution are part of this
process:
(a) Local Lands Court (LLC): The case is heard before the Local Court Magistrate for
determination. If the litigants are not successful, they may appeal to a higher court.
(c) District Lands Court (DLC): The case is heard before a District Land Court Magistrate. If
the litigants are not successful, they may appear to a higher court.
(d) Provincial Lands Court (PLC): The case is presided by a Provincial Land Court whose
decision is final.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
15
68. It needs to be noted that if recourse to the PNG judicial system is necessary because
of the failure of other means of grievance redress and the courts at any stage find in favour
of the litigants all costs associated with this form of dispute resolution will need to be paid by
the Project. Therefore this process should only always be used as a very last resort.
69. In the event that grievances that cannot be resolved through legal redress, the DOW
and DLO will hold the compensation amounts in escrow. Compensation will be paid in full
upon final resolution of the case through other means of mediation for an agreed upon
amount by the aggrieved parties (DPs) in accordance with the entitlements of the affected
persons.
70. Grievances with regards to wages, employment opportunities, sub-contracts, and
social issues caused by construction workers will be dealt with at the sub-project level. Any
issue of criminal nature will be referred to Police. The Contractor will deal with such
grievances on site because they have an obligation to address community issues. Usually, DPs
would want to refer grievances through DOW if they are not satisfied with response from the
Contractor. Should such occur, DOW will intervene to mediate and resolve such disputes.
Based on the nature and severity of the case, DOW has the power to direct the contractor to
resolve disputes to ensure construction is completed unhindered.
G. LEGAL FRAMEWORK
i. National & Local Laws & ADB Policy requirements
71. The policy framework and resettlement entitlements are based on the laws and
regulations of the GoPNG and ADB’s Safeguard policy. Appropriate PNG Laws include: (a) the
1996 Lands Act, and (b) the 2000 Land Dispute Settlement Act. The Resettlement Framework
for the project provides description of the relevant laws. Relevant ADB policies include the
2009 Safeguard Policy Statement and the 1998 Gender and Development Policy”.
72. The GoPNG does not have any specific resettlement policies at the National,
Provincial or local level for relocating and resettling people which would apply to the DPs
being relocated. PNG however does have relating to acquisition of land and assets by the
state for public purposes (eminent domain), and related legal procedures, compensation
payable, and the legally defined procedures for receiving and facilitating the resolution of
affected persons’ concerns and grievances are all incorporated in the Land Act of 1996.
73. In this sub-project, land and properties are on customary land tenure for which this
Land Act has processes that address the issue of customary land to be used for development
purposes. The Act covers customary land rights, which includes land owned, used or
occupied by a person or community in accordance with current customary usage. Access to
land and resources are embedded in social relationships and expressed as customary land
rights to utilise resources. Small clan based groups live in the villages, managing their own
resources, and exercising their rights to utilise them. These groups (clans which are
composed of sub-clans, lineage groups, and at the lowest level extended households) are
typically made of “primary right holders” – the leaders of the group – who collectively have
the authority to allocate user rights through their spokesperson. The rest of the lineage
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
16
typically possesses “secondary right”. Such rights maybe inherited or gained through
marriage to a primary rights holder and are strongly influenced by forms of matrilineal
descent.
74. ADB 2009 SPS includes the following policy principles of relevance to a project of this
nature that does not involve the physical displacement of affected persons but rather the
need to relocate some physical structures, and secure suitable replacement land for
gardening based activities, which inter alia will also apply to the sub-project along the Magi
Highway:
(i) Screen the Project early on to identify past, present and future involuntary
resettlement impacts and risks.
(ii) Carry out meaningful consultations with affected persons, host communities, and
concerned non-governmental organizations. Inform all displaced persons of their
entitlements and resettlement options. Ensure their participation in planning,
implementation, and monitoring and evaluation of resettlement programs. Pay
particular attention to the needs of the vulnerable groups, especially those below
the poverty line, landless, elderly, women and children, and indigenous peoples,
and those without legal title to land, and ensure their participation in
consultations. Establish a grievance redress mechanism to receive and facilitate
resolution of the affected persons’ concerns.
(iii) Improve or at least restore, the livelihoods of all displaced persons through (a)
land based resettlement strategies when affected livelihoods are land based
where possible or cash compensation at replacement value for land when the loss
of land does not undermine livelihoods; (b) prompt replacement of assets with
access to assets of equal or higher value; (c) prompt compensation at full
replacement cost for assets that cannot be restored; and, (d) additional revenues
and services through benefit sharing schemes where possible.
(iv) Provide with needed assistance, including the following: (a) secure land use tenure
on land identified for new garden sites and (b) if necessary transitional support
and development assistance such as land development, credit facilities, training or
employment opportunities.
(v) Improve the standards of living of the displaced poor and other vulnerable groups,
including women, to at least national minimum standards and provide access to
land and other resources that is both legal and affordable.
(vi) Develop procedures in a transparent, consistent, and equitable manner if land
acquisition is through negotiated settlement to ensure that those people who
enter into negotiated settlement will maintain the same or better income and
livelihood status.
(vii) Ensure that displaced persons without titles to land or any recognizable legal rights
to land are eligible for resettlement assistance and compensation of loss of non-
land assets.
(viii) Prepare a draft resettlement plan and disclose a resettlement plan elaborating on
displaced persons’ entitlements, the income and livelihood restoration strategy,
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
17
institutional arrangements, monitoring and reporting framework, budget, and time
bound implementation schedule.
(ix) Pay compensation and provide other resettlement entitlements before physical or
economic displacement and implement the resettlement plan under close
supervision throughout project implementation.
(x) Monitor and assess resettlement outcomes, their impacts on the standards of
living of displaced persons, and whether the objectives of the resettlement plan
have been achieved by taking into account the baseline conditions and results of
resettlement monitoring and disclose these monitoring results.
75. The ADB 2009 SPS also states that where there are indigenous peoples their identity,
dignity, human rights, livelihood systems, and cultural uniqueness must be safeguarded so
they can receive culturally appropriate social and economic benefits. However, not all people
living along the Magi highway are indigenous to the region having originated in other regions
of PNG and while indigenous peoples’ development issues might not seem relevant in the
PNG context of this contract package involving the Magi Highway corridor. However, as the
SES to date demonstrates it is the rights of DPs indigenous to the villages of this corridor
whose right to access to land needs to be safeguarded.
76. The other policy of relevance to this project is the ADBs 2003 Policy on Gender and
Development, which requires that all ADB financed projects ensure where possible and
practicable special design features and strategies will be built into projects to facilitate and
encourage women’s involvement and ensure tangible benefits for women.
77. There are some gaps between GoPNG policies and procedures and those of the ADB.
The main gaps relate to: (i) carryout meaning consultations that also ensure people living
below poverty line, landless, elderly, women and children are consulted; (ii) requirement to
improve or at least restore livelihoods of all displaced persons by ensuring all displacement
costs of assets lost is paid; (iii) provision of economically displaced persons with necessary
assistance to improve upon or restore their existing livelihoods at least to national minimum
standards of living; (iv) ensuring that displaced persons without recognizable rights to land
are eligible for compensation for loss of non-land assets; and, (v) monitoring and assessment
of resettlement outcomes.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
18
78. Table 5: Comparison of GoPNG Laws & ADB Policy & Gap – Filling Measures
PNG Laws ADB SPS Requirement Gap Filling Measures
There are no
provisions for
ensuring meaningful
consultations that
include the people
living below the
poverty line, the
landless, elderly,
women and other
vulnerable facilitated.
There is a requirement
that not only must
consultations take
place but evidence is
provided that poorer
and vulnerable people
are informed of their
entitlements and
resettlement options.
RPs will be uploaded on the ADB website, edited and
translated versions translated versions will be available at
the Provincial, district and local level, and local clan
leaders whose members are affected will also receive a
copy of the RP. Also where relevant civil society groups
that agree to participate in the monitoring and evaluation
of the RP will receive full copy of the RP.
There are no
provisions to improve
or at least restore the
livelihoods of all DPs.
It is needed to
improve but at least
restore livelihoods of
all DPs by a range of
strategies targeted at
DPs.
Measures will consist of building upon existing livelihoods
to ideally provide for an improvement in living standards
or if impossible at least to restore to pre-subproject
levels.
There are very limited
provisions to provide
assistance or
compensation to DPs
who lose assets.
(e.g. Valuer Generals
2013 Price Schedule is
applied.)
Requirement by ADB
that DPs are
compensated for loss
of non-land assets at
full replacement costs.
Valuer General has been requested to provide an updated
2011 schedule for garden crops, food trees and timber
trees. Valuer General has provided an updated 2013 Price
Schedule.
There is no
requirement for the
monitoring and
assessment of
resettlement
outcomes.
The ADB requires that
that these outcomes
be monitored and
assessed.
The M & E indicators prepared for this resettlement plan
will enable outcomes to be monitored including their
impacts on living standards of DPs and whether the
objectives of the resettlement plan have been achieved
by taking into account baseline socio-economic
conditions. The monitoring reports will also be disclosed
including to DPs.
Source: RP 2011
ii. Resettlement Policy Principles for the Project
79. DOW as the EA has prepared this RP and hereby unequivocally states that it will abide
by national and local laws applicable to resettlement and the policy requirements of the ADB.
Specifically DOW states that it will ensure affected landowners will be paid fair compensation
for land and other productive assets acquired at agreed upon replacement cost; and be
responsive to grievance processes; and act in an accountable and transparent manner; and
will ensure that women will also be entitled to benefit during the resettlement processes.
The principles on land acquisition, compensation and resettlement that DOW will commit
itself to in the Central Province include:
a) Land acquisition and resettlement has been minimized through careful detailed
engineering design but in accordance with GoPNG policy where, a 40 meter ROW is
required. In the case of Magi Highway only the gardens and economic trees and one
grave yard will be displaced. The displacement is considered necessary as the DPs
have gardens right on the middle of the ROWs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
19
b) DPs were consulted during the inception stage of the project through to the
completion of RP and will continue to be consulted during project implementation
stage. This RP was updated with full participation of the DPs. Effective mechanisms
will be established for hearing and resolving grievances.
c) DPs will receive compensation at replacement cost for their loss of productive assets
and this should ensure they will be as well off if not better off than if the Project did
not proceed.
d) All compensation will be fully paid to DPs prior to the commencement of site
clearance at each of the three bridge sites.
e) Absence of formal title is not a bar to compensation and assistance and particular
attention will be paid to women and other vulnerable people.
f) Land acquisition and the destruction of plants on the ROW will be conceived as part
of the Project and costs related to these forms of involuntary displacement of gardens
will be included in and financed out of the Project cost as part of the GoPNG
contribution to the Project as cost.
g) The impacts of these three sub-project bridges, including unforeseen losses and
damages that may occur during either bridge construction or realignment of the
approaches to these three bridges will be carefully monitored and remedial steps
taken as required.
iii. Principles and Methodologies for Determining Valuations and Compensation Rates
80. DPs co-operated with DOW in identifying land boundaries, land for acquisition and
physically quantified their productive assets list for forfeiture and its estimated cost. A fair
market value was determined by DOW using the DPs estimates, and the 2013 Valuer
Generals price Schedule, the general market and price trend in property development along
the project road corridor, as well as the following information:
information about recent land transactions;
land value by types;
cropping patterns and crop production; and,
availability of land in the sub-project areas.
81. It was anticipated that there would be some disputes but recent consultations and
assessment indicated that disputes were very minor and have been resolved. DOW is obliged
by law to accept the Valuer-General’s assessment and this has already been conveyed to
affected landowners and land-users at each of the three bridge sites.
iv. Description of Land Acquisition Process
82. Based on the 1996 Land Act the DOW has applied the following procedures when
acquiring at least a 40 meter right-of-way at the three bridge sites:
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
20
DOW in consultation with Central Provincial Administration engaged surveyors and
Lands Specialists to determine boundaries, location, size and area of the land to be
acquired in accordance with the detailed design of each of these three bridge sites.
Surveyor-General’s office was requested to vet, approve and register the surveys,
which have already been approved, signed and registered (refer to attachment VII).
DOW had requested the Department of Lands and Physical Planning (DLPP) and Office
of Provincial Administration (OPA) in the Central Province to do the investigation for
land acquisition.
The Central Province Lands Officer was asked to conduct the land investigation and
prepare a Land Investigation Report (LIR) including ownership, genealogy, rights and
interests held in the land, and, estimated value of improvements to land in
consultation with the landowners and Kwikila District Lands Officer and other relevant
government offices.
The Survey Plan and LIR were then submitted to the OPA in Central Province for his
recommendation for the surveyed land to be purchased. The OPA will prepare a
certificate of alienability confirming that there is no impediment to land acquisition.
The LIR was sent to the DOLPP for approval of the land and improvements that
includes physical structures, garden crops, food trees, and other trees. The Valuer-
General vetted the valuation based on the 2013 Valuer Generals Price Schedule.
DOW will receive the valuation report and certificate of alienability, raises checks and
prepares purchase documents. DOW will use the signed documents and checks for
execution and payment to landowners, because DPs have insisted that DOW must
handle the payments to avoid fraudulent activities.
The DOW, in consultation with Central Province Land Office will make the offer to the
landowners. The forms are executed and money is handed over in accordance with
the requirements of the landowners. If rejected, it then goes to the Minister of Lands
for a negotiated settlement.
83. The DOW acknowledges that where land has been acquired for roads in areas such as
the Highlands region there have been many problems that have delayed project
implementation but on the Magi Highway it does not envisage problems of such magnitude.
H. Entitlements, Assistance and Benefits
i. Displaced Person’s Entitlements and Eligibility
84. Detailed identification of DPs, assessment and valuation of affected assets and
negotiations for land acquisition at the three bridge sites has been completed. Completion
was successful following consistent and effective dialogue between DOW and DPs since 2013
through participatory meetings. The Cadastral survey and LIR was done in coordination with
the District Lands Officers (DLOs) to collect relevant information. The date of signing of the
land investigation report by the DLOs will be the “cut-off” date for eligibility for
compensation and any rehabilitation assistance. The following are the procedures
summarizing eligibility for compensation and other assistance to DPs:
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
21
Landowners and land users that have either documented claims to the affected land or
are able to demonstrate that this land belongs to them to the satisfaction of the DOW as
with the crops, cassava crops, yam plants, banana plants, coconut trees, betel nut plants,
sand miners, and the properties at each Bridge site as of the cut-off date which is May
2014 will be eligible for compensation and/or rehabilitation assistance as per this RP.
Any person or group that occupies or uses the land identified for the Project after the cut-
off date will not be eligible for any compensation and/or assistance. They will be required
to move from the land as per the provisions of the Land Act.
Landowners and land users who have satisfied the DOW that they either have
documented claims to the affected land and/or other productive assets or through the
DOW investigation can demonstrate that they are the rightful owners or users, will
receive compensation for land acquired by the Project. Those DPs who cannot satisfy the
DOW that they are the rightful users but are using the land anyway will receive
compensation for productive assets attached to the land and other assistance as required.
85. Eligibility and entitlement for compensation and other assistance is summarized
below:
Table 6: Entitlement Criteria Matrix
Type of impact Entitled Person (s) Entitlements
Permanent
Acquisition of
Land
Legal owner (s), including
customary Landowners
Landowners will be provided equivalent size and quality of
land, or cash compensation at replacement cost.
DPs will be provided compensation only for their damaged
crops, trees, and structures on project affected land.
Temporary use
of Land
Legal owner(s) of
land, including customary
landowners.
Landowners will be paid rent on terms between them
and the contractor.
Loss of crops
and trees.
All DPs irrespective
of their legal status.
DPs will be given notice to harvest crops and trees before
site clearance or removal from required land. If DPs are
not able to harvest, they will be paid cash compensation at
replacement cost.
In case of perennial crops and trees, the compensation will
also include loss of income for a period until new crops or
trees produce an equivalent income.
Loss of
gardens
DPs whose loss of gardens is
more than 10% loss
livelihoods support.
DPs will be provided with income support based on
number of crops being quantified.
Loss of
commercial
Structures
All DPs (whether have legal
title to land or not).
DPs will be provided compensation at replacement cost
without deductions for depreciation or salvaged material
and assistance in finding an alternative site.
Loss of
livelihoods.
Any vulnerable HHs
identified by additional
social assessment.
Vulnerable HHs will receive priority employment for
project construction and maintenance.
Unforeseen or
unintended
impacts.
Concerned affected persons. This will be determined as per the principles of this RP
and the ADB’s Safeguard policy.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
22
87. As per the above entitlement and eligibility criteria matrix, DOW concluded that DPs are
entitled to receive cash payments in lieu of land acquisition and damage to crops/plants as
per the following table:
Table 7: Entitlements to Entitled Persons
Bridge Name Type of Impact Entitled Person (s) Entitlement
Dogona Land Acquisition
(2.0067 ha)
1.Goriga & Gininana Clans K41,000.00
Kokebagu Clan Land Acquisition
(1.8346 ha)
1.Aboga Kabudo (Goina Clan)
2.Tomura Mamaea (Goina clan)
3.Mania Inia (Uguia Dogoro Clan)
K37,000.00
Sivitatana Land Acquisition Raga & Babaga Babona (Verave Rubu
&
Bugave Lologa & Others (Bole Rubu
Clan)
K47,000.00
Total 7 entitled clans K125,000.00
Dogona Improvements 13 persons K62,808.00
Kokebagu Improvements 17 persons K79,249.30
Sivitatana Improvements 14 persons K44,735.40
Total 44 entitled persons K186,792.70
Total Entitlements to DPs on each bridge site K311,792.70
(For full listings of each recipient of entitlements, see Appendices III – XIV).
ii. Assistance to Vulnerable Groups
86. The SES undertaken for this RP indicates that there are 33 households that are
significantly affected that can be classified as vulnerable as they are displaced from their
current shelters of residence; therefore it is only with careful and focused interventions that
these households quantified below can become worse off than they are at present. DOW
expects the successful bidder to compulsorily undertake to employ at least one to two
members from each HH depending on the population per HH on construction related
activities on a full-time basis.
iii. Opportunities for Affected Persons to Derive Appropriate Development Benefits
87. There are a number of both quantifiable and non-quantifiable development benefits
APs will be able to leverage as a result of this Project. Benefits include:
Employment opportunities can be afforded to DPs by the contractors that not only
ensure a stable waged income over two years but an opportunity to acquire non-
agricultural skills without having to leave the local community.
Women will be offered the same types of employment-based opportunities as men
and of equal importance will be able to actively participate alongside men in other
resettlement-based activities thereby also having an indirect impact upon the
patrilineal structures of male domination in traditional PNG society.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
23
Social risks associated with HIV/AIDS and other STIs will be mitigated to some extent
by employing as many people on bridge construction activities locally as possible
and awareness and prevention programs designed to empower women.
There will be opportunities to provide a range of goods and services to outside bridge
construction workers that will enhance the local economy because such workers will
generally have greater purchasing power than local villagers.
Improvements to overall bridge design, including pedestrian walkways, and changes
to bridge approach alignments geared to improve road safety standards and render
NMT users’ safer than hitherto has been possible.
The opportunity to learn experientially how to diversify crop production possibly with
newer higher yielding varieties or different cropping regimes and improve upon
traditional land management practices.
The bridges as part of a longer term developmental strategy to enhance connectivity
between rural and urban PNG will ultimately result in improved market links and
access to a wider range of goods and services.
The opportunity to invest compensation monies in clan-based activities such as social
support for pre-school children and elderly clan members to ensure greater levels of
social inclusion and maintain clan social cohesiveness.
I. Relocation of Physical Structures
i. Options for Relocating Physical Structures
88. This sub-project does not require physical relocation of HHs, mini-market structures
or any other economic settings that would significantly displace a DP. The initial report
identified Sivitatana market for relocation. Further assessment indicates that it will not be
affected as it is located almost 500 metres away from the bridge. However, 1 grave yard has
been identified for relocation but living relatives did not want to have it relocated.
ii. Consideration of Alternative Relocation Sites
89. The new locations for resettlement are not being identified because there are no
relocations of HHs.
iii. Timetable for Site Preparation and Transfer
90. As per the Implementation Schedule outlined in Table 10 all land must be acquired
between the months of July – August 2014 before civil works commence in September 2014.
DPs will harvest all gardens and relocate any crop that is required for replanting to their new
sites between July and September before construction commences.
iv. Legal Requirements to Regularize Tenure and Transfer Title
91. The Land Act (No. 45 of 1996 and ratified on 20/12/96), specifically Section 13 (6)
states that GoPNG may acquire the land in question and the DOL at the provincial level (in
relation to Magi Highway reference is to Central Province) is able to issue the Native Dealing
Number (NIT) that regularizes tenure and enables title to be transferred. However, the
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
24
process of acquiring customary land and transferring titles to DPs will take at least two years
for the process to be completed. The process is also tenuous and contagious in the sense that
if DOW contemplates land acquisition on behalf of the State and then transfers to the
affected DPs, the very objective of trying to construct the said bridges will be delayed by
years. In other words there will be a diversion of focus from the bridge construction to the
customary land acquisition and title transfer. To avoid this problem, DOW will pay them
compensation fees at market rate and they will relocate to their old gardens as agreed by
DPs identified and consulted.
v. Measures to Assist Displaced Persons
92. The subproject will purchase and supply high yielding crop variety seeds to affected
DPs and training in terms of agriculture and provide training in agriculture and livestock.
J. Income Restoration and Rehabilitation
i. Possible Livelihood Risks
93. APs on all three bridge sites will be temporarily exposed to social and economic risks
as they begin to experience the high cash flow in their villages. They will also experience food
security risks in that part of their source of food supply; particularly garden foods will be
adversely affected. Women DPs and other disadvantaged groups will also be exposed to
other social risks such as HIV/AIDs, sexual harassment by construction workers, and alcohol
abuse by local construction workers due to increased flow of cash income in the project
areas, which is also likely to cause disharmony among family members.
94. Regular income from vegetables sales will be affected as they said but based on
further assessment income earned from sales is not quite significant compared with
compensation payments they will receive. The HHs will have the choice to decide whether to
replant the young betel nut and banana plants in other gardens they have or destroy them
together with medium to matured trees. Note that the State is not obligated to secure a new
location to resettle these vegetables and betel nut trees because the state pays for damages
as per valuation.
95. Apart from the Sivitatana market, there aren’t any other organized markets on the
sub-project sites. DPs are likely to establish temporary markets on all construction sites.
These will enable them to generate more income during construction period because
contract workers will buy items such as betel nuts, coconut, cigarettes, soft drinks, etc.
96. Some livelihood risks that might impact upon clan members who had not experienced
loss of access to productive land might relate to road side gardens shown in the attached
photographs which will be removed during construction. This also relates to the nature of
fishing during actual bridge construction. The impact per se is not on a critical habitat
upstream from the bridges but in close proximity to where fish are typically caught. However,
this indirect impact has not been quantified as part of this RP although by making reference
to the IEE for each of these bridge sites it can be noted that it is thought the impacts will be
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
25
minimal. Nevertheless, this is a livelihood issue that DOW is prepared to flag because it is
seeking to embrace better practices with resettlement planning processes that it implements.
ii. Income Restoration Program
97. Income expected to be generated by the DPs as a result of foregoing land and
vegetation are significantly higher compared to other villages not affected that are in the
same region. With the anticipated income they are able to improve food security and
improve personal hygiene. DPs were unable to feel the impact of income generated from the
sales of vegetables from their gardens at each bridge site but with the payment of land and
crop compensation, they certainly will feel the positive impact of having access to huge
amount of money at any one time.
98. The GAP based on the Social Assessment undertaken as part of the Project concluded
that incomes would be enhanced to purchase local foods at the markets if APs were
employed as construction workers. It is estimated that each of the three bridges will take up
to three years to construct and during this time waged labour opportunities should be made
available as a priority to DPs. Such employment opportunities on their own do not ensure
sustainable livelihoods but being paid at least the minimum wage and enjoying working
conditions as per ILO Core Labour Standards (a recognized requirement for ADB financing of
the Project). DOW is confident that DPs will be considerably better off financially as a result
of the Project. This is the experience DOW has found elsewhere in PNG when waged
employment opportunities are offered locally. It should also be noted that experience with
waged employment on a relatively long-term basis will be a new experience for most of the
DPs based on consultations facilitated as part of preparing this RP.
iii. Special Measures to Support Vulnerable Groups
99. The Contractor will conduct special training and counselling programs that emphasis
on fostering cordial relations with APs. Most important lessons relates to outside workers
relationship to APs where such relations should not disadvantage vulnerable APs. Other
specific vulnerable APs were not identified but the contractor will ensure that strategies are
in place to identify and assist any specific group that needs special attention from the
contractor.
iv. Specific Gender Considerations
100. DOW recognizes that specific gender considerations apply to all public infrastructure
projects it both executes and manages. As part of this RP women DPs have been consulted
both in mixed groups with men DPs but also in groups just consisting of women with
consultations being facilitated by a woman. The measures proposed in this RP to enhance the
positive impact of the Project on women DPs and other women living in the Project area are
as follows:
� Iterative consultations with women at all stages of the Project cycle and
importantly in the preparation of the RP.
� Via the RP ensuring that women clan members not just men clan members are
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
26
compensated for loss of land and other productive assets.
� Facilitating processes whereby women DPs can lodge grievances with the DOW and
ultimately ADB if they are dissatisfied with any aspects of the RP.
� Ensuring that women DPs and not just men DPs are offered priority waged
employment on the Project and are afforded equal pay and on-the-job training
opportunities.
� Addressing concerns women DPs might have with safety and security issues in
contexts where they have to relocate their gardening activities.
� Ensuring that all livelihood outcomes on socio-economic data is gender
disaggregated to analyse impacts at the intra-household, the intra/inter clan, and
where relevant inter-tribal level.
v. Suggested Training Programs
101. Training of APs will be considered as one of the critical tools of fostering mutual
relations with construction workers. DPs, especially from Sivitatana and Kokebagu queried
whether the project will provide some form of training on agriculture. Although DOW does
not try to duplicate roles of another government function, it will be one of ADB policy to
ensure training is provided to enhance skills and knowledge that they would use to improve
their livelihoods. DOW will work either with agricultural outreach officers from the
government or the NGO sector or both to provide training. The Construction Company will
hire trainers from HIV/AIDS council to provide to APs and Construction workers.
102. DPs that will be offered priority employment on the Project where some of whom
have never been involved in similar projects. The Construction Company will provide on- the-
job training to all DPs recruited to work. Such training will include but not be restricted to
activities such as pile-driving, concreting, and welding and community relations officers;
taking into account occupational health and safety issues and the lack of real experience by
most APs, especially women APs. The contractor will also be required to offer practical
training in bridge maintenance to APs as DOW is considering the employment of local
communities to undertake routine maintenance on bridge assets.
K: Resettlement Budget and Financing Plan
i. Itemized Budget for Resettlement Activities
103. Budget for this sub-project involves the costs for Land purchase, and compensation
for crops, trees and the single graveyard. It is also important to note that a specific budget is
included in consideration of financing the implementation of the RP .
104. The implementation of the RP and construction schedule may progress unhindered if
due care and consideration is given to RP. According to DOW’s valuation of land and crops
the total cost for this sub-project will amount to approximately PGK 311,792.70 or
US$110,312.26 as indicated in table 10. Included also in table 11 is the financing budget for
the implementation of this RP where a total K150, 000. 00 (US$43,070.00). Total cost for this
RP will be K461,792.70, which is inclusive of Tables 8 & 9.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
27
Table 8: Resettlement Budget
No Description Land Area Cost (PGK) Total (US$)
1 Land Acquisition
Dogona 2.0067 ha K41, 000.00 US$14,505.80
Kokebagu 1.8346 ha K37, 000.00 US$13,090.60
Sivitatana 2.3450 ha K 47,000.00 US$16,628.60
Total 6.1863 ha K125,000.00 US$44,225.00
2 Planted Improvements
Dogona K 62,808.00 US$22,221.47
Kokebagu K79,249.30 US$28,038.40
Sivitatana K44,735.40 US$15,827.38
K186,792.70 US$66,087.25
Total K311,792.70 US$110,312.26
Other RP costs include:
a) Any special assistance to vulnerable DPs that might be identified during
construction phase that did not appear during the actual SIS.
b) livelihood enhancement training for women and men;
c) expenses for outreach in agriculture and forestry based activities;
d) purchase of newer and higher yielding seed varieties; and,
e) Monitoring and evaluation.
Table 9: Support Services Budget
Item Cost Centre Amount (PGK) US$
1 Donations to Vulnerable groups K20,000.00 7,076.00
2 Training of DPs K20,000.00 7,076.00
3 Agriculture Extension K20,000.00 7,076.00
4 Monitoring & Evaluation K50,000.00 17,690.00
5 Community Relations Officer K40,000.00 14,152
Total K150,000.00 US$43,070.00
It is likely that items (c) and (d) will be based on cost norms that DOW has applied to other
projects it is implementing that involve resettlement activities.
ii. Flow of Funds
105. Funds earmarked for compensation payments for: Land, Crops and Physical structures
will be paid directly to DPs from DOW once it has been paid to this Office by the Department
of Finance in Port Moresby. DOW prepares the funds for disbursement based on DMS and
the funds will be drawn down as part of the GoPNG contribution to this Project. Payment for
temporary use of land is made directly by the Contractor to local DPs based on an agreement
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
28
between the two parties as to the actual amount. This will not involve the DOW or other
parties unless DPs are dissatisfied with the amounts offered by the contractor.
106. Funds for remaining activities will be paid directly by the DOW once disbursement has
been made by the Department of Finance to DOW in Port Moresby. An alternative
arrangement might be for the DOW Central Province to be paid directly by the Department
of Finance but DOW is not generally agreeable to this alternative because it does not
necessarily guarantee the level of accountability and transparency required as disbursements
are not guaranteed by law unlike the payment of compensation to DPs.
iii. Justification for Calculating Compensation Rates and Other Cost Estimates
107. Compensation rates were based on replacement cost calculated by a registered
Valuer and approved by the Valuer-General. Calculation of these rates took into account the
opinions of DPs, especially the ones that were able to demonstrate rates based on recent
land transactions in land of equivalent value in their village or nearby villages. Replacement
costs also took into account some likely escalation in land values as a result of this Project
contributing to a general rise in land values along the Magi Highway.
108. Other cost estimates will be based on cost norms the DOW has applied to other
infrastructure projects involving the construction of bridges that it is responsible for
implementing. However, some of the cost norms for activities (ii) to (v) inclusive will be based
on consultations with DPs and civil society groups who are more familiar and experienced in
estimating the costs of such activities than the DOW. Government departments familiar with
agricultural and forestry based activities were also consulted in relation to activities (iv) and
(v) prior to deriving at the final figures.
iv. Sources of Financing
109. The GoPNG is financially responsible for all resettlement activities with the exception
of ADB agreeing to the financing of TA Consultant services to oversee the resettlement based
activities during detailed design and RP implementation, monitoring and evaluation of these
resettlement activities.
L: Institutional Arrangements
i. Responsibilities and Mechanisms for Carrying out Resettlement Plan
110. DOW is both the Executing and Implementing Agency for this Project. DOW in
collaboration with Central Province’s Lands Office and DOL day-to-day activities related to
land acquisition and assessment of losses of other productive assets were carried out. These
activities included:
Collaborate with and assisted by District Lands Officer at each of the three
bridge sites to undertake work to comply with the Project’s policies and ADB
requirements.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
29
Provided resources, including where necessary DOW, Central Province Lands Office
and DOL expertise, to carry out the Inventory of Loss (IOL) and Detailed Measurement
Survey (DMS).
Collaborated and assisted by District Lands Officer in negotiations and agreements
with affected landowners or land-users.
Facilitated consultations with affected communities and ensured that all stakeholders
were informed about the Project, its policies and procedures; ensured that all
requirements concerning public disclosure of the provisions for land acquisition and
compensation; and, overseeing and monitoring the grievance redress process.
Reviewed, updated and endorsed the RP prior to submission to the ADB for approval,
ensuring that all matters related to land acquisition and other forms of compensation
were complete and correctly reported upon.
Monitoring the process of allocation and disbursal of funds for compensation at both
the national and provincial levels and ensure that funds are available and
compensation is paid in a timely manner.
Undertake all other activities including the monitoring of land acquisition and other
productive assets’ compensation payments.
111. DOW in consultation with OPA, including the PLO and DLO executed work plan,
implement, and monitor land acquisition activities at the sites of the three bridges. The
responsibilities included:
Undertook cadastral surveys of land required permanently for these three bridges
and measured out the area of land required for acquisition by the Project
Negotiated and signed Memorandum of Agreements (MOAs) for the acquisition/use
of customary land with the clan leaders and affected landowners and/or land-users.
Temporary land leases required for the three bridges will be done by the successful
contractor.
Consulted and advised affected communities about the Project, the policies and
procedures when land is required and the rights and responsibilities of directly
affected people and other indirectly affected peoples.
112. The Provincial Governor and Provincial Administrator have been regularly advised of
the progress on consultation with DPs and they will also be advised of the disbursement of all
funds allocated to pay compensation. Local Level Government Ward Councillors have
assisted in helping DOW to facilitate all consultations with local communities, affected
people, and other stakeholders to pave way for compensation payments. They will also be
able to assist during payment of compensation to DPs and monitoring of project
implementation.
ii. Institutional Capacity Building Program
113. As part of the preparation of the RP it has been concluded by DOW in Port Moresby
that governmental staff who will be involved in implementing this RP require more training in
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
30
the ADB’s social safeguard policies and procedures because this Project will be the first one
to be implemented by DOW after the 2009 Safeguard Policy Statement that became
operational in January 2010. It is also considered necessary by DOW to review GoPNG
policies and procedures for the acquisition of land and other forms of involuntary
resettlement. Finally, while some DOW staff have limited training in survey tools and
techniques that are necessary to prepare a RP there is still considerable room for
improvement. Officials to be targeted will include DOW, PDOL and DDOL, relevant staff of
the Valuer-General’s office, and any other organizations that might be involved in land
acquisition and compensation activities, including civil society groups.
114. A Land Acquisition Officer from DOW was supposed to be assigned within the PIU
based in Port Moresby to implement the RP but did not eventuate due to manpower
shortage. The Project also provided consultancy support via a Safeguards Specialist to build
capacity within DOW and local governments to prepare, implement, and monitor the RP.
iii. Role of Civil Society Groups
115. While there are some civil society groups in the Project area most of them are
religious-based and are less than satisfactory for the purposes required as part of the RP.
However, there are at least two Port Moresby based NGO groups that have worked with
DOW in the past. These two NGOs are the Centre for Environment, Law and Community
Rights (CELCR) and Environment Law Centre (ELC). Both these NGOs are non-sectarian in
nature and have a good understanding of both gender and indigenous people’s development
issues and in the opinion of the DOW are able to work more effectively with local
communities than other NGOs: they are also more cost effective. Subject to satisfactory
negotiations either NGO or both will be contracted by DOW to undertake external
monitoring and evaluation of the RP.
iv. Involvement of Women’s Groups in Resettlement Planning and Management
116. The DOW is mindful of the important role women who are affected by involuntary
resettlement in resettlement plans, and the Gender Action Plan prepared for the Project,
based on consultations during the preparation of this RP, outlines in detail how the
resettlement planning and management processes will be implemented to ensure affected
women are not disadvantaged as a result of the Project. Principally compensation payments
will be made in such a way that affected women rather than simply men will receive an equal
share of compensation payable based on severity of loss and women will also be encouraged
to seek grievance redress if deemed necessary.
M: Implementation Schedule
117. The implementation schedule for resettlement activities to (i) update the RP; (ii)
implement the RP; and, (iii) monitoring activities is arranged as follows:
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
31
Table 9: Implementation Schedule (1)
Item Activities Schedule
Update of Resettlement Plan
1 Confirmation of legally binding Memorandum of Agreement (MOA) with
landowners on use of land (an initial MOAwas signed during the PPTA)
Month 1
2 Confirm land requirements based on detailed engineering design of the three bridges Month 2
3 Securing authorization from the Department of Land for cadastral land Survey. Month 3
4 Follow up consultations with affected communities and agreement on land
use/acquisition.
Ongoing
5 Cadastral survey of land and submission to Surveyor-General for Registration. Month 3
6 Request Provincial Land Office to prepare LIR including valuation of land and
improvement)
Month 3
7 Submission to the Office of Provincial Affairs for Certificate of Alienability to be signed
by the Provincial Administrator.
Month 4
8 Valuer-General verifies the land valuation at the three bridge sites. Month 4
9 Department of Works updates the RP in consultation with landowners, including
agreement on compensation rates and discloses updated RP.
Month 5 & 6
10 Department of Works submits the updated RP for approval and uploading
on the ADB website.
Month 6
11 ADB issues no-objection to the RP. Month 7
Resettlement Plan Implementation
12 Department of Works issues checks to Provincial Land Offices for execution of land
acquisition and payment of compensation
Month 8
13 Provincial Land Offices complete land purchase and issue Native Dealing Number Month 9
14 Payment of compensation and allowances Month 9 & 10
15 Department of Works submits to ADB the Land Acquisition Completion Report. Month 9
16 Award of civil works contract Month 10 & 11
17 Clearance of acquired land. Month 11 & 12
18 Commencement of civil works (contingent on 100% of compensation and allowances
being paid).
Month 13
19 Payment of adjusted compensation, as required, for unforeseen damages and losses. Actual month
of damage
Monitoring Plan
20 Department of Works establishes AP socio-economic baseline. Month 17
21 Department of Works submits progress report to ADB on implementation of the RP. 6 monthly
22 Department of Works conducts post-resettlement survey and final Monitoring report. Month 36
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
32
Table 12: Implementation Schedule (2)
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
33
N. Monitoring and Reporting
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
34
118. DOW will implement and monitor all activities associated with land acquisition and
payment of compensation to DPs. The scope of monitoring includes: (i) compliance with the
agreed policies and procedures for land acquisition; (ii) prompt approval, allocation and
disbursement of compensation payments to DPs, including if necessary supplemental
compensation for additional and/or unforeseen losses; and, (iv) remedial actions, as required.
The monitoring will also cover the social impacts of the three bridges and whether DPs are
able to restore, and preferably improve, their pre-project living standards, incomes, and
productive capacity. A monitoring and evaluation program utilizing the following indicators
has been drafted on the understanding it can be subject to change, including by DPs who will
be afforded the opportunity to suggest indicators they consider of more relevance to their
livelihoods than are considered relevant by other stakeholders. These draft monitoring and
evaluation indicators are shown in Table 10.
119. The SIS undertaken of DPs for this RP together with the Social Assessment undertaken
for the Corridor of Influence along the Magi Highway will be used as the baseline to monitor
and evaluate the above indicators. They will also be used in conjunction with monitoring and
evaluation indicators prepared for both the GAP and EMP for these three bridges. The DOW
will prepare and submit semi-annual progress reports to ADB as part of project performance
monitoring. The DOW will also submit a subproject land acquisition completion report to ADB
when compensation has been paid.
120. To ensure that there is adequate accountability and transparency with monitoring
and evaluating the outcomes of this RP, an external Consultant paid for by DOW will be
appointed to undertake independent monitoring and evaluation. Such reports together with
those prepared by DOW will be submitted to ADB at six monthly intervals as per the
Implementation Schedule. On completion of the sub-projects this external Consultant will
prepare a report highlighting its assessment of resettlement outcomes for all three sub-
projects in the Magi Highway Corridor.
Table 12: Draft Monitoring and Evaluation Indicators
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
35
Type of
Indicator
Indicator Examples of Variables
Process
Indicators
Staffing
Consultation,
participation,
and Grievance Resolution
Procedures in Operation
No. of PIU staff by job functions. Engagement of Safeguards
Staff and Training
No of other agency officials available for tasks. No of
consultation and participation programs held with various
Stakeholders.
No of field visits by PIU Staff,
No of civil society groups participating in Project
Effectiveness of compensation / assistance delivery system
Coordination between PIU and other GoPNG agencies,
project supervision consultants, and civil society groups.
Output
Indicators
Households Structures
Economic Trees and Crops
Assistance to APs
No. of households affected, No. of community structures, if
any, moved out,
No of households receiving agreed compensation for trees
and crops,
No of households that have participated in income
restoration and livelihood enhancement measures.
No of special assistance programs to vulnerable households.
Assistance for income
Restoration and Livelihood Training and assistance in agriculture and forestry.
Impact
Indicators
Enhancement of
Household Earning
Capacity
Special Assistance to
Women
Other Livelihood
Indicators
No of households participating in income restoration and
livelihood enhancement programs.
Employment status of households having a formal job.
Employment status of households being self- employed.
No of households receiving income enhancement skills
training,
No. of women engaged as waged workers by the Project, Type of
Project-related skills women received training in. Average wage
of women employed on Project compared to that of men.
No of women receiving income enhancement skills training.
Increase in market- based incomes of women traders.
Increase in ownership of household assets.
Increased access to schooling and health services. Increase
in visits by GoPNG service providers.
Appendix 1
Socio-Economic Survey Questionnaire
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
36
Household Composition
Household Numbers
2. Ages of HHMembers
3. Genders of HHMembers
4. Relationship to Other HH Members
5. Ethnicities of HHMembers
6. Education Levels
Social Characteristics of Households1. Family Structure
2. Lineage Affiliations
3. Clan Membership
4. Community Organizations
5. Class Background
6. Religious Affiliation
Income, Assets and Expenditure
. Individual Income
2. Corporate/collective Income
3. Land Ownership
4. Livestock
5. Common Property Resources
6. Estimated Total Expenditure
Occupational Background
1. Subsistence Agriculture
2. Commercial Agriculture
3. Rural Waged Employment
4. Other Waged Employment
5. Small and Medium Enterprise
6. Public Sector Official
Access to Public Services
1. Health Care Amenities
2. Water Supply and Sanitation
3. Educational Facilities
4. Motorized Transport
5. Micro-Finance
6. Agricultural Extension
Gender Roles and Issues
1. Control of HH Finances
2. HH Decision-Making Responsibility
3. Membership of Village Organization
4. Maintenance of Public Goods
5. Interaction at Supra Village Level
Attitudes and Preferences of Affected people
1. Project Generally Beneficial
2. Exacerbates HIV/AIDS
3. Increase in Traffic Accidents
4. Negative Environmental Impacts
5. Prepared to Gift Land
6. Willingness to Work on Project
7. Commitment to Maintain Asset
Appendix II PUBLIC INFORMATION BULLETIN
PNG BRIDGE PROJECT: IMPROVING RURAL ACCESS
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
37
1. GOAL
TO IMPROVE THE RURAL ACCESS AND BOTH DIRECTLY AND INDIRECTLY IMPROVE THE LIVING STANDARDS OF
LOCAL COMMUNITIES. IT WILL BE FINANCED BY THE GOVENRMENT OF PAPUA NEW GUINEA AND A LOAN FROM
THE ASIAN DEVELOPMENT BANK HEADQUARTERED IN MANILA, PHILIPPINES.
2. INTERVENTIONS
BRIDGES ALONG NATIONAL HIGHWAYS TO BE REPLACED BECAUSE THEY ARE TOO OLD AND CANNOT MEET LONG-
TERM GROWTH IN MOTORIZED TRAFFIC. THEY WILL BE TWO-LANE INSTEAD OF ONE LANE. THE DISMANTLED
BAILEY BRIDGES WILL BE REASSEMBLED ALONG FEEDER ROADS THAT DIRECTLY SERVE LOCAL COMMUNITIES AT
RIVER OR STREAM CROSSINGS WHERE EITHER BRIDGES DO NOT EXIST AT PRESENT OR IF THEY DO THEY ARE IN
POOR CONDITION.
3. LANDACQUISITION
TEMPORARY LAND ACQUISTION MAY BE NECESSARY TO ENABLE BRIDGE CONSTRUCTION TO GET UNDERWAY.
PERMANENT LAND ACQUISTION WILL BE NECESSARY WHERE THE HIGHWAY NEEDS TO BE ALIGNED TO ENSURE
SAFE PASSAGE ACROSS THE CARRIAGE-WAY.
4. COMPENSATION ISSUES
GOVERNMENT OF PAPUA NEW GUINEA AND ASIAN DEVELOPMENT BANK HAVE POLICIES AND PROCEDURES TO
ENSURE THAT IF YOU LOSE ACCESS TO YOUR LAND EITHER TEMPORARILY OR PERMANENTLY YOU WILL BE
COMPENSATED AT REPLACEMENT COST BASED ON FAIR MARKET VALUES.
SHOULD YOU DECIDE TO GIFT YOUR LAND IN THE INTEREST OF THE PUBLIC GOOD AT THE LOCAL LEVEL THAT IS
ACCEPTABLE BUT YOU ARE UNDER NO OBLIGATION TO DO SO AND REFUSAL TO DO SO WILL NOT HAVE ANY
ADVERSE IMPACT UPON YOU OR THE REASSEMBLY OF BAILEY BRIDGES ON RIVER OR STREAM CROSSINGS IN
FEEDER ROADS THAT SERVE YOUR COMMUNITY.
5. ACTIVITIES
A SOCIO-ECONOMIC SURVEY AND INVENTORY OF LOSS OF AFFECTED HOUSEHOLDS (THOSE WHOSE LAND WILL BE
ACQUIRED) WILL BE UNDERTAKEN AND A RESETTLEMENT PLAN PREPARED. YOUWILL BE ENTITLED TO REVIEW THIS
RESETTLEMENT PLAN IN YOUR LANGUAGE OF CHOICE AND SUGGEST AMEMNDMENTS. IT WILL NOT BE FINALIZED
BEFORE YOUR FREE AND INFORMED CONSENT IS PROVIDED BYWAY OF A SIGNED MEMORANDUM OF AGREEMENT
BETWEEN YOU AND A PROVINCIAL REPRESENTATIVE OF THE GOVERNMENT OF PAPUA NEW GUINEA.
6. MITIGATION MEASURES
AS AFFECTED WOMEN AND MEN YOU WILL BE OFFERED FIRST CHOICE OF PAID EMPLOYMENT DURING BRIDGE
CONSTRUCTION AND FOR PERIODIC MAINTENANCE ACTIVITIES ON THESE NEW BRIDGES (GRASS CUTTING AND
PAINTING) IF THESE ACTIVITIES ARE SUB-CONTRACTED BY THE PROVINCIAL DEPARTMENT OFWORKS.
CONTACTS
� MR/MS………………….. DISTRICT LAND OFFICER TELEPHONE………………
� LAND MANAGEMENT UNIT PROVINCIAL DEPARTMENT OFWORKS ADDRESS:
TELEPHONE:
EMAIL:
� SAFEGUARDS UNIT PROJECT IMPLEMENTATION UNIT ADDRESS:
TELEPHONE:
EMAIL:
ASIAN DEVELOPMENT BANK, ADB AVENUE, MANDALUYONG CITY
1550 METRO MANILA, PHILIPPINES, TEL: +63 2 683 1912; FAX: +63 2 636 2446 www.adb.org
Appendix III: Land Acquisition Cadastral Survey: Dogona River Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
38
Appendix IV: Land Acquisition Cadastral Survey: Kokebagu River Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
39
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
40
Appendix V: Land Acquisition Cadastral Survey: Sivitatana Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
41
Appendix VI: Land Investigation Report and Land Valuation: Dogona Bridge
DOGONA RIVER BRIDGE
1. Description : Portion 2719C Milinch Rigo.Fourmil of Moresby Central Province.
2. Date : 22nd April 2014.
3. Land area : 2.0067 hectares
4. Status : Customary Land.
5. Survey : Registered survey Plan # 49/3246
6. Valuation : Forty One Thousand Kina (K41,000.00)
7 Ownership : Two customary land owners;
Tribe # 1 : Mr Goriga Forekodo of Goriga Clan, Saroa TribeClan leader and chief land owner owns the southern side.
Tribe # 2 : Mr Limau Lega of Gininana Clan, Saroa Tribe.
Chief land owner owns the northern end of the bridge.
The two Chiefs are sole decision makers for all land matters.
Appendix VII: Land Investigation Report & Land Valuation: Kokekbagu Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
42
E. KOKEBAGU RIVER BRIDGE
1. Description : Portion 2718C Milinch Rigo.Fourmil of Moresby Central Province.
2. Date : 22nd April 2014.
3. Land area : : 1.8346 hectares
4. Status : Customary Land.
5. Survey : Registered survey Plan # 49/3245
6. Valuation : Thirty Seven Thousand Kina (K37,000.00)
7. Ownership : Three Clans and three landowner groups.Two Land owner groups from Goina Dogoro
Clan, Kauvako Tribe and one owner from UguiaDogoro Clan of Saroakeina Village, RigoDistrict, Central Province.
Clan # 1 : Aboga Kabudo of Goina Dogoro Clan, KauvakoTribe, Clan leader and chief land owner owns the
north side of the bridge.
Clan # 2 : Tomura Mamaea of Goina Dogoro Clan,Kauvako Tribe and clan members own the south
eastern side of the bridge.
Clan # 3 : Mana Inia and Uguia Dogoro Clan membersown the south western end of the bridge land.
The three Leaders represent their people in all land matters. They are the chiefnegotiators and rulers/decision makers for land matters.
Appendix VIII: Land Investigation Report & Land Valuation: Sivitatana Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
43
SIVITATANA RIVER BRIDGE
1. Description : Portion 2720C Milinch Rigo.Fourmil of Moresby Central Province.
2. Date : 22nd April, 2014.
3. Land area : 2.3450 hectares
4. Status : Customary Land.
5. Survey : Registered survey plan # 49/3247
6. Valuation : Forty seven thousand kina (K47,000.00)
7 Ownership : Two customary land owners;
Tribe # 1 : Bugave Lologa Family Of Bole Rubu Clan,Tubulamo Tribe.
Clan leader and Chief land owner/decision maker owns the southernside of the Sivitatana bridge..ribe # 2 Raga and Babaga Babona of Verave Rubu Clan ,Tubulamo Tribe.
Two Clan leaders and chiefs land owner/decisionMaker and own the northern side of the SivitatanaBridge land.
Appendix IX: Improvement Valuation Report: Dogona Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
44
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
45
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
46
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
47
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
48
Appendix X: Improvement Valuation Report: Kokebagu Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
49
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
50
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
51
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
52
Appendix XI: Improvement Valuation: Sivitatana Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
53
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
54
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
55
Appendix XII: Contract of Sale: Dogona Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
56
CONTRACT OF SALE
AN AGREEMENT made on the 22nd Day of April 2014, between GORIGA FOREKODO AND THE
CLAN DIRECTORS OF GORIGA CLAN, Gidobade Village, Rigo District, Central Province
(hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,
National Capital District (hereinafter referred to as the “purchaser”) of the other part:
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1. The vendor sells and the purchaser buys all that piece of land being Portion 2719CMilinch Rigo Fourmil Moresby, Central Province (Dogona Creek bridge). and beingthe whole of the land more particularly comprised in Native Land Dealing (NLD) #
_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
2. The total land area on both sides of the river is 2.0067 hectares.
3. Mr Doriga’s Clan owns the portion of land located on the southern side of Dogona bridge
towards Kwikla Station.
PURCHASE PRICE.
4. The purchase price shall be Twenty One Thousand Kina (K21,000.00) which shall bepaid on completion to the Vendor or in such manner the Vendor may direct.
5. The property is sold free of encumbrances except those disclosed in this Agreement or onthe NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
6. The Purchaser shall pay in addition to the purchase price:-
(a) Legal cost and
the Vendor shall pay all outstanding fees including:-
(b) Legal costs.7. The property is sold subject to the reservations, exceptions, covenants and conditions
contained or implied in the Customary Lease referred to in this agreement.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
57
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
58
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
59
THE FIRST SCHEDULE
ITEM 1:
Date: The 22nd Day of April, 2014.
ITEM 2 (a):
Vendors: Goriga Forekodo and others of Goriga Clan
ITEM 2 (b):
Address : Gidobade Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2719C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K21,000.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
60
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
61
CONTRACT OF SALE
AN AGREEMENT made on the 22nd Day of April 2014, between LIMAU LEGA AND THE CLAN
DIRECTORS OF GININANA CLAN, Gidobade Village, Rigo District, Central Province (hereinafterreferred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1 The vendor sells and the purchaser buys all that piece of land being Portion 2719C
Milinch Rigo Fourmil Moresby, Central Province (Dogona Creek bridge). and beingthe whole of the land more particularly comprised in Native Land Dealing (NLD) #_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
8. The total land area of the bridge is 2.0067 hectares.
9. Mr Lega’s Clan owns the portion of land located on the northern side of Dogona bridgetowards Port Moresby City.
PURCHASE PRICE.
10. The purchase price shall be Twenty Thousand Kina (K20,000.00) which shall be paid oncompletion to the Vendor or in such manner the Vendor may direct.
11. The property is sold free of encumbrances except those disclosed in this Agreement or onthe NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
12. The Purchaser shall pay in addition to the purchase price:-
(b) Legal cost and
the Vendor shall pay all outstanding fees including:-
(b) Legal costs.13. The property is sold subject to the reservations, exceptions, covenants and conditions
contained or implied in the Customary Lease referred to in this agreement.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
62
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
63
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
64
THE FIRST SCHEDULE
ITEM 1:
Date: The 22nd Day of April, 2014.
ITEM 2 (a):
Vendors: Limau Lega and others of Gininama Clan
ITEM 2 (b):
Address : Gidobade Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2719C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K20,000.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
65
Appendix XIII: Contract of Sale: Kokebagu Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
66
CONTRACT OF SALE
AN AGREEMENT made on the 23rd Day of April, 2014, between ABOGA KABUDO AND THECLAN DIRECTORS OF GOINA CLAN, Saroakeina Village, Rigo District, Central Province
(hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,
National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1. The vendor sells and the purchaser buys all that piece of land being Portion 2718CMilinch Rigo Fourmil Moresby, Central Province (Kokebagu River Bridge) andbeing the whole of the land more particularly comprised in Native Land Dealing
(NLD) # _________ being a vacant and unimproved land (hereinafter referred to asthe ”property”).
2. The total land area of the whole bridge site is 1.8346 hectares.
3. Aboga Kabudo and others own the portion of land located on the western side ofKokebagu River bridge towards Kwikla Station.
PURCHASE PRICE.
4. The purchase price shall be Eighteen Thousand Kina (K18,000.00) which shall be paid
on completion to the Vendor or in such manner the Vendor may direct.
5. The property is sold free of encumbrances except those disclosed in this Agreement or on
the NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
6. The Purchaser shall pay in addition to the purchase price:-
(a) Legal cost and the Vendor shall pay all outstanding fees including:-
(b) Legal costs.
7. The property is sold subject to the reservations, exceptions, covenants and conditions
contained or implied in the Customary Lease referred to in this agreement.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
67
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
68
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
69
THE FIRST SCHEDULE
ITEM 1:
Date: The 23rd Day of April, 2014.
ITEM 2 (a):
Vendors: Aboga Kabudo and others of Goina Clan
ITEM 2 (b):
Address : Saroakeina Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2718C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K18,000.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
70
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
71
CONTRACT OF SALE
AN AGREEMENT made on the 23rd Day of April, 2014, between TOMURA MAMAEA AND THECLAN DIRECTORS OF GOINA CLAN, Saroakeina Village, Rigo District, Central Province
(hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1. The vendor sells and the purchaser buys all that piece of land being Portion 2718CMilinch Rigo Fourmil Moresby, Central Province (Kokebagu River Bridge) and being
the whole of the land more particularly comprised in Native Land Dealing (NLD) #_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
2. The total land area of the whole bridge site is 1.8346 hectares.
3. Tomura Mamaea and others of Goina Clan own the portion of land located on the eastern
side of Kokebagu River bridge towards Kupiano Station.
PURCHASE PRICE.
4. The purchase price shall be Nine Thousand Five Hundred Kina (K9,500.00.00) which
shall be paid on completion to the Vendor or in such manner the Vendor may direct.
5. The property is sold free of encumbrances except those disclosed in this Agreement or on
the NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
6. The Purchaser shall pay in addition to the purchase price:-
(a). Legal cost and the Vendor shall pay all outstanding fees including:-
(b) Legal costs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
72
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
73
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
74
THE FIRST SCHEDULE
ITEM 1:
Date: The 23rd Day of April, 2014.
ITEM 2 (a):
Vendors: Tomura Mamaea and others of Goina Clan
ITEM 2 (b):
Address : Saroakeina Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2718C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K9,500.00
TEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
75
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
76
CONTRACT OF SALE
AN AGREEMENT made on the 23rd Day of April, 2014, between MANA INIA AND THE CLAN
DIRECTORS OF UGUIA DOGORO CLAN, Saroakeina Village, Rigo District, Central Province(hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1. The vendor sells and the purchaser buys all that piece of land being Portion 2718C
Milinch Rigo Fourmil Moresby, Central Province (Kokebagu River Bridge) and beingthe whole of the land more particularly comprised in Native Land Dealing (NLD) #_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
2. The total land area of the whole bridge site is 1.8346 hectares.
3. Mana Inia and others of Uguia Dogoro Clan own the half portion of land located on theeastern side of Kokebagu River bridge towards Kupiano Station.
PURCHASE PRICE.
4. The purchase price shall be Nine Thousand Five Hundred Kina (K9,500.00) which
shall be paid on completion to the Vendor or in such manner the Vendor may direct.
5. The property is sold free of encumbrances except those disclosed in this Agreement or onthe NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
6. The Purchaser shall pay in addition to the purchase price:-
(a). Legal cost and the Vendor shall pay all outstanding fees including:-
(b) Legal costs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
77
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
78
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
79
THE FIRST SCHEDULE
ITEM 1:
Date: The 23rd Day of April, 2014.
ITEM 2 (a):
Vendors: Mana Inia and others of Uguia Dogoro Clan
ITEM 2 (b):
Address : Saroakeina Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2718C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K9,500.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy: Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
80
Appendix XIV: Contract of Sale: Sivitatana Bridge
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
81
CONTRACT OF SALE
AN AGREEMENT made on the 23rd Day of April 2014, between RAGA & BABAGABABONA AND THE CLAN DIRECTORS OF VERAVE RUBU CLAN, TUBULAMO TRIBE
Sivitatana Village, Rigo District, Central Province (hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,
National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
1. The vendor sells and the purchaser buys all that piece of land being Portion 2720CMilinch Rigo Fourmil Moresby, Central Province (Sivitatana River Bridge) andbeing the whole of the land more particularly comprised in Native Land Dealing (NLD) #
_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
2. The total land area of 2.3450 hectares is located on both sides of the river.
3. Raga & Babaga Babona and others own the portion of land located on the northern side of
the Sivitatana River towards Kwikla Station.
PURCHASE PRICE.
4. The purchase price shall be Twenty Four Thousand Kina (K24,000.00) which shall bepaid on completion to the Vendor or in such manner the Vendor may direct.
5. The property is sold free of encumbrances except those disclosed in this Agreement or onthe NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
6. The Purchaser shall pay in addition to the purchase price:-
(a). Legal cost and
the Vendor shall pay all outstanding fees including:-
(b) Legal costs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
82
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
83
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
84
THE FIRST SCHEDULE
ITEM 1:
Date: The 23rd Day of April, 2014.
ITEM 2 (a):
Vendors: Raga & Babaga Babona and others of Verave Rubu Clan
ITEM 2 (b):
Address : Sivitatana Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2720C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K24,000.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
85
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
86
CONTRACT OF SALE
AN AGREEMENT made on the 23rd Day of April 2014, between BUGAVE LOLOGAAND THE CLAN DIRECTORS OF BOLE RUBU CLAN, TUBULAMO TRIBE Sivitatana Village,
Rigo District, Central Province (hereinafter referred to as the “vendor”) of the one part;
And THE INDEPENDENCE STATE OF PNG (DEPARTMENT OF WORKS), PORT MORESBY,
National Capital District (hereinafter referred to as the “purchaser”) of the other part.
WHEREBY IT IS AGREED AND DECLARED AS FOLLOWS:-
SALE AND PURCHASE.
7. The vendor sells and the purchaser buys all that piece of land being Portion 2720CMilinch Rigo Fourmil Moresby, Central Province (Sivitatana River Bridge) andbeing the whole of the land more particularly comprised in Native Land Dealing (NLD) #
_________ being a vacant and unimproved land (hereinafter referred to as the ”property”).
8. The total land area of 2.3450 hectares is located on both sides of the river.
9. Bugave Lologa and others own the portion of land located on the southern side of the
Sivitatana River towards Kupiano Station.
PURCHASE PRICE.
10. The purchase price shall be Twenty Three Thousand Kina (K23,000.00) which shall bepaid on completion to the Vendor or in such manner the Vendor may direct.
11. The property is sold free of encumbrances except those disclosed in this Agreement or onthe NLD documents.
COUNCIL RATES, STAMP DUTY AND GOVERNMENT RENTALS.
12. The Purchaser shall pay in addition to the purchase price:-
(a). Legal cost and the Vendor shall pay all outstanding fees including:-
(b) Legal costs.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
87
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
88
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
89
THE FIRST SCHEDULE
ITEM 1:
Date: The 23rd Day of April, 2014.
ITEM 2 (a):
Vendors: Bugave Lologa and others of Bole Rubu Clan
ITEM 2 (b):
Address : Sivitatana Village, Rigo District, Central Province..
ITEM 3 (a):
Purchasers: Department of Works (Independent State of PNG)
ITEM 3 (b):
Address: P O Box 1108,
BOROKO. NCD.
ITEM 4:
Property Portion 2720C, Milinch Rigo Fourmil Moresby.
Description: Being the whole of the land comprised and described in NLD
#______________. .
ITEM 5:
Purchase Price: K23,000.00
ITEM 6:
Deposit: Nil
ITEM 7:
Stakeholder: Nil
ITEM 8:
Details of tenancy:Nil
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
90
Appendix XV: List of Displaced Persons at all Bridge Sites
Dogona Bridge Site LandOwners
N0 NAME GENDER AGE TRIBE CLAN EDUC OCCUPT
1 Goriga Forekodo M 65 Alauna Goriga Clan University Sub.Farmer
2 Nomoka Forekodo F 61 “ “ Nil “
3 Ubi Goriga F 43 “ “ Gr.6 Sub.Frmr
4 Vagi Goriga M 39 “ “ Gr.10 Sub.Farmr
5 David Goriga M 30 “ “ Gr.10 Sub.farmr
6 Alan Goriga M 28 “ “ Gr.8 Sub.Farmer
7 Garo Goriga M 25 “ “ Gr.6 “
8. Rodney Garo M 5 “ “ Elementary Child
9 Variraga Garo M 2 “ “ Infnt Infant
10 Lega Goriga M 50 “ “ Gr.6 Sub.Farmr
11 Didia Goriga F 47 “ “ Gr.10 “
12 Ano Goriga M 38 “ “ Gr.12 Sub.Frmr
13 Venao N.Goriga M 22 “ “ Gr.10 Student
14 Babagani Goriga F 19 “ “ Gr.10 Student
15 Joshua Togi M 25 GR.6 Sub.farmer
16 Peni Togi M M 6 Elementary student
17 Kilarogea Togi F 22 Gr.7 Wife
18 Didia Togi F 5 Child child
19 GauginiWaibo F 54 Ginana Clan
20 Gwaibo Goriga M 60 “ Nil
21 Tanu Gwaibo M 34 “ Nil
22 Geof Goriga Gwaibo M 30 “ Gr.12 University
23 Koiogurei Gwaibo F 28 “ College Teacher
24 Gogina Kwaibo M 25 “ College Carpenter
25 Gwaibo Gwaibo M 22 “ College Nurse
26 Ronny Gwaibo M 17 “ Gr.10 Student
27 Buana Bagu Saina M 55 Alauna Ginana Clan Nil Sub.farmer
28 Kilakamali Bagu F 43 “ Nil “
29 Violet Bagu F 32 “ Gr.12 Accounts
30 Babagibi Bagu F 27 “ College Teacher
31 Boio Bagu F 24 “ College Teacher
32 Joyce Bagu F 16 “ Gr.10 Student
33 Sheroll Bagu F 13 “ Gr.6 Student
34 Nonoga Bagu F 9 “ Gr.4 student
KOKEBAGUBRIDGE
No. Name Gender Age Relationship Clan Education Occupation
35 Nune Goi M 36 Father Nil Farmer
36 Kuro Nune M 8 son Gr. 2 Sudent
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
91
37 Diari Nune F 27 Wife Gr.8 House Wife
38 Mamae'a Nune M 5 Son child Child
39 Goru Nune M 2 Son child
40 John Gani M 58 Father nil Farmer
41 Cathy John F 11 Daughter Gr.3 Student
42 Esther John F 30 Wife Gr.10 Teacher
43 Kila John F 8 Daughter Gr.2 Student
44 Emma John F 1 Daughter
45 Oka Aboga 55 Father Farmer
46 KamonaOka M 30 Son Gr.10 Farmer
47 Saidi Oka F 48 Wife House Wife
48 Kenina Oka F 28 Daughter Gr.8
49 Bua Oka F 26 Daughter Gr.10
50 Fase Oka F 24 Daughter Gr.10
51 Airi Oka M 20 Son Gr.10 Student
52 Kovete Oka M 18 Son Gr.8 Student
53 Bugave Oka M 13 Son Gr.5 Student
54 Vele Aboga M Father Farmer
55 Stan Aboga M 14 Son Gr.5 House Wife
56 Majory Aboga F 24 Wife Gr.9 Student
57 Edna Aboga F 7 Daughter Gr.1 Student
58 Aboga Aboga M 34 Father Farmer
59 Mou Aboga M 10 Son Gr.2 Student
60 Geua Aboga F 28 Wife House Wife
61 Lusy Aboga F 5 Daughter
62 Cristhina Aboga F 5 Daughter
63 MogamaMagera M Farmer
64 MageraMogama M 14 Son Gr6 Student
65 KilaMogama F 30 Wife House Wife
66 VaraMogama F 18 Daughter Gr9 Student
67 AviaMogama F 12 Daughter Gr4 Student
68 MaduMogama M 7 Son Gr1 Student
69 EvangelineMogama F 5 Daughter
70 KilaMogama M 1 Son
71 Tunu Daba M Farmer
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
92
72 Henao Tunu M 36 Son Gr10 Sub-Farmer
73 Gari Tunu F 57 Wife House Wife
74 Girana Tunu M 38 Son Sub-Farmer
75 Beria Tunu M 32 Son Sub-Farmer
76 Lilona Tunu F 30 Daughter
77 Malaki Tunu M 28 Son Sub-Farmer
78 Neki Tunu M 20 Son Student
79 Henao Tunu M Farmer
80 Judah Henao M 11 Son Gr3 Student
81 Eileen Henao F 32 Wife Gr10 Teacher
82 GounaHenao M 8 Son Gr1 Student
83 David Henao M 5 Son Gr1 Student
84 Komana Aboga M Farmer
85 Mero Kamona M 24 Son Gr6 Farmer
86 Bou Kamona F 49 Wife House Wife
87 Eileen Komana F 32 Daughter Gr10 Teacher
88 Nancy Komana F 30 Daughter Gr10 Nurse
89 Kila Komana F 28 Daughter
90 Lincos Komana F 20 Daughter Gr10 Student
91 Aisi Komana F 18 Daughter Gr8 Student
92 Manu Komana M 12 Son Gr4 Student
93 Borana Daba M Farmer
94 Winnie Borana M 22 Son Gr8 Sub-Farmer
95 Bugi Borana F 51 Wife House Wife
96 Ivon Borana F 28 Daughter Gr8
97 Kadoi Borana F 18 Daughter
98 Gibson Borana M 17 Son Gr6 Student
99 Gabriel Borana M 13 Son Gr4 Student
100 Alu Borana F 11 Daughter Gr2 Student
101 Samuel Borana M 10 Son Gr1 Student
102 Girana Tunu M Farmer
103 Vetari Girana M 20 Son Gr11 Student
104 Iavina Girana F 38 Wife Gr5 House Wife
105 Ali Girana M 18 Son Sub-Farmer
106 UgonaGirana F 16 Daughter Gr6 Student
107 Lucy Girana F 8 Daughter Gr2 Student
108 Deta Girana F 4 Daughter
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
93
109 Duba Aboga M Gr10 Farmer
110 Kennedy Aboga M 5 Son Sub-Farmer
111 Dagoda Aboga F 31 Wife Gr6 House Wife
112 Ailo Aboga F 2 Daughter
113 Paul Aboga M 1 Son
114 Raga Medani M Farmer
115 Eddie Raga M 9 Son Gr2 Student
116 Kumana Raga F 21 Wife House Wife
117 Rexy Raga M 3 Son
118 Gabi Raga M 1 Son
119 Raga Kubudo M 42 nil Farmer
120 Gevo Raga M 18 Son Gr8 Student
121 Doga Raga F 33 Wife Gr8 House Wife
122 M3isi Raga F 12 Dauhter Gr4 Student
123 JonJon Raga M 9 Son Gr2 Student
124 Lester Raga M 5 Son Gr1 Student
125 Steven Raga M 1 Son
Sivitatana Bridge Site Landowners List
NO NAME GENDER AGE CLAN OCCUPATION EDUCATION
126 Babona Vaiuma M 75 Galirubu Subsistence Farmer Grade 6
127 Bouna Vali F 65 “ “ Gr.3
128 Divio Verave F 32 “ “ Gr.6
139 Vali Babona M 35 “ “ Gr.8
130 Kepsy Vali M 21 “ Student Gr.11
131 Win Vali M 18 “ Student Gr.10
132 Bouna Vali F 16 “ Student Gr.10
133 Mekere Vali M 10` “ “ Gr. 4
134 Pony Vali F 8 “ “ Gr. 2
135 Guena Babona F 33 “ Housewife Gr.6
136 Dadau Babona F 31 “ “ Gr. 6
137 Bole Babona M 29 “ Sub. Farmer Gr. 10
138 Matilda Bole F 27 “ “ Gr.12
139 Misi Bole M 3 “ Child Child
140 Bano Bole M 1 “ “ “
141 Gamonga Babona M 26 “ Chef Gr.12
142 Gini Babona M 22 “ Mechanic Gr.10
143 Gabaki Gini F 20 “ House wife Gr.10
144 Taubada Gini M 2 “ Child Child
145 Gobakai Bole F 19 “ House wife Gr.8
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
94
146 Gabriel Garo Gagala M 65 “ Councilor Ex.Soldier
147 Raga Dauma F 60 “ House wife Gr.6
148 Raymong GAro M 31 “ Fireman (PNG Fire) GR.12
149 Hisa Leo F 29 “ Housewife Gr.6
150 Leo Garo M 2 “ Child Child
151 Mavela Garo F 28 “ Sub.Farmer Gr.12
152 Ande LAfe F 8 “ Student Gr.2
153 Kulona Garo M 10 “ Student Gr.3
154 Avit Lafe F 2 “ Child
155 Gagala Garo F 26 “ Hotel Attendant Gr.10
156 Vini Gagala M 7 Galirubu Child Child
157 Henry Garo M 24 “ Agriculturalist College
158 Gabi Gagala M 55 “ Accountant University
159 Heloi Elave F 40 “ Accounts Clerk College
160 Geffery Gabi M 35 “ Carpenter Gr.10
161 Ilave Gabi M 33 “ Mechanic GR.10
162 Molly Gabi F 31 “ Teacher College Dip.
163 Gegeva Gabi F 29 “ Accounts Clerk College
164 Rosa Gagala F 50 “ Evangalist College
165 Hanet Kepo F 35 “ Accountant University
166 Betty Kepo F 33 “ Uni Lecturer University
167 Vicky Kepo F 33 “ Student Diploma
168 Simon Gagala M 55 “ Sub.Farmer Gr.10
169 Koio Babaga F 53 “ Sub.Farmer Gr.10
169 Iaga Simon F 30 “ House wife Gr.10
170 Namoka Simon M 27 “ Student University
172 Julie Simon F 25 “ Housewife Gr.8
173 Isabel Simon F 24 “ Sub.Farmer Gr.8
174 Kiri Simon F 22 “ Sub.Farmer Gr.8
175 Rosa Simon F 20 “ Student Gr.10
176 Meli Simon F 12 “ Student Gr.5
177 Raga Babona M 78 “ Sub.Farmer Nil
178 Kalovo Raga F 55 “ Sub.Farmer Villager
179 Iaga Raga M 35 “ Sailor Gr.10
180. Bugave Raga M 33 “ Policeman Gr.10
181 Aboga Raga M 31 “ Sub.farmer Gr.10
182 Tom Raga F 28 “ Sub.Farmer Gr.6
183 Walo Raga M 24 “ Student Gr.10
184 Avei Raga M 22 “ Student Gr.10
185 Gai Babaga M 55 “ Carpenter Gr.10
186 Bali Gabi M 55 Makora Rubu Admin.Officer Gr.10
187 Tiko Iarana M 53 “ Sub.Farmer Gr.10
188 Sio Vavine M 35 “ “ Gr.10
189 Babona Vavine M 32 “ “ Gr.10
190 Keiroko Bali F 51 “ Housewife Gr.6
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
95
191 Makora Bali M 30 “ Banker College Dip.
192 MogonaMakora F 30 “ Accountant College Dip.
193 Daube Bali M 28 “ Mechanic Gr.10
194 Gigiro Gelema F 36 ‘ Sub.Farmer Gr.6
195 Waigo Botau F 34 “ “ “
196 Repso Tiko M 22 “ “ Gr.10
197 Misina Iarana F 51 “ “ Gr.6
198 Veira Iarana F 56 “ Housewife Gr.6
199 Pini Iarana M 48 “ Sub.Farmer Gr.6
200 Kamona Iarana M 46 “ “ Gr.6
201 Tovo Iarana M 44 “ CID Police Officer Police College
202 Bugave Lologa M 70 “ Carpenter Gr. 6
203 Gutuma Lologa M 65 “ Architecture College
204 Kitiro Lologa M 62 “ Carpenter Gr.10
205 Kila Lologa M 60 “ Carpenter Gr.6
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
96
Appendix XVI: PHOTOGRAPHS OF DPs
Photographs of Dogona Bridge
From the Bridge to POM From the Bridge to POM
South side (Downstream) View to POM direction
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
97
From the Bridge to POM Meeting with Local clan
Kokebagu Bridge
From POM to the Bridge Bridge condition
Upstream Down stream
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
98
Upstream Downstream
Sivitatana Bridge
From Bridge to POM Bridge condition from upstream
Upstream Downstream
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
99
Meeting with Land owner clan 24 hour Market 500m north of Bridge
Meeting at Sivitatana Village Meeting at Dogona Village
bove: Local Timber Miling for pallets and building materials. Above: Photo taken after interviews.
L 2783/2784 PNG: BRIDGE REPLACEMENT FOR IMPROVED RURAL ACCESS PROJECT (BRIRAP)
100
Above Left: Fruit Trees as source of income. Above Right: Typical Latrine Pit Shelter.
Above: Type of permanent village Houses at Sivitatana
Below: Participants of Land Investigation and Socio-Economic Studies