Upload
hizbi7
View
217
Download
0
Embed Size (px)
DESCRIPTION
cigre 3 sabah
Citation preview
PT PLN (Persero)
Sarawak Energy Berhad
AORC-CIGRE TECHNICAL MEETING 16th to 21st August 2015
The Magellan Sutera Resort, Kota Kinabalu, Sabah, MALAYSIA
Outlines
Introduction
Location of the Project
Project Location
Mambong
Bengkayang
Sarawak
West Kalimantan
Serikin
275kV HVAC Transmission Line
128km
The Interconnection
150kV 275kV 275kV 132kV Siluas Serikin
K a l i m a n t a n - S a r a w a k
B o r d e r
West K a l i m ant an Sarawak
82.6km 45.6km
Bengkayang Mambong
K a l i m a n t a n - S a r a w a k
B o r d e r
201 Towers 144 Towers
Initially Power transfer
SEB to PLN
Power Transfer up to
In due course
Background
Kalimantan Power Exchange Agreement between SEB and PLN (PT PERSERO) on 5th
September 2012
Construction started
Expected to be completed by
Target operational by
Technical Specification of the Project
Description PLN SEB
Line Conductor
Conductor type/name
ACSR/AS Zebra ACSR Drake
No. and diameter of Al wire
54/3.18 26/4.44
No. and diameter of St wire
7/3.18 7/3.45
Overall diameter 28.62 mm 28.11 mm
Cross-section 428.9/55.6 mm² 402/65 mm²
Resistance (DC at 20°C)
0.065 Ω/km 0.072 Ω/km
Breaking load 137.8 kN 145 kN
Weight 1,621 kg/km 1,680 kg/km
Description PLN SEB
Tower Design Parameters
Tower height 50.4 m 35 to 37 m
Clearance open country 10.5 m 7.5 m
Clearance over plantations
7 m 4 m
Clearance to highway, roads
11 m 9 m
Clearance to other lines 5 m 4 m
Basic span 400 m 350 m
Insulators Cap and pin Cap and pin
Communication link OPGW OPGW
Surge arresters Class 3 Class 3
Cross arm – Cross arm >7.4m >6.8m
Cross arm – tower body ~6.9m ~6m
Conductor to ground Clearance
~15m ~10m
Right of way 15m on each side of
tower 20m on each side of
tower
Basic Substation Design Parameters Mambong Substation Bengkayang Substation
1. Number of bays required 2 (extension) 2 2. Bay type Line Line
3. Switchgear type Outdoor Outdoor (1½ circuit-breaker
scheme)
4. Environment Heavy Pollution Heavy Pollution
5. Busbar configuration Double Double 6. Busbar rating, A 2000 1600 7. Circuit breaker rating, A 2500 2500*
8. Circuit breaker short-circuit rating, kA 25 (3 sec.) 25 (3 sec.)
9. Busbar short-circuit rating, kA 25 (3 sec.) 25 (3 sec.)
10. Maximum voltage for equipment, kV 300 300
11. Short-duration power frequency withstand, kV
460 460
12.Basic SIL/LIL, kV 850/1050 850/1050
13.Minimum safety clearance, mm 4800 4800
14.Line reactor rating 3x5MVAr 3x5MVAr
15.Teaser reactor rating TBA –
Voltage/Capacity of Capacitor Banks
Mambong Substation
275kV 2×40MVAR 2×80MVAR
132kV 4×20MVAR
Milestone and Progress
Project Milestones at Sarawak
Overall Overall Progress Completion
Mambong Substation 78%
Mambong Transmission Lines 98%
Activity Expected Completion Date
Extension Works at Mambong 275/132kV Substation
Quarter 3, 2015
275kV Double Circuit Transmission Lines
Quarter 3, 2015
Piling works at capacitor bank bays
Cable Trench and Structure foundation
works
Equipment Installation
Line stringing works
Line Checking commence on 27th July
2015
Project Milestones at West Kalimantan
Overall Overall Progress Completion
Bengkayang Substation 85.46%
Transmission Lines 89.33%
Activity Expected Completion Date
Construction Works at Bengkayang 275/150kV Substation
July 2015
275kV Double Circuit Transmission Lines
July 2015
The Sarawak-West Kalimantan Interconnection
• Reduce generation cost for PLN West Kalimantan
• Improve security of supply for both SEB and PLN West Kalimantan
• Improve operational flexibility
• Catalyst for future potential interconnectors