PT PLN (Persero)

Sarawak Energy Berhad

AORC-CIGRE TECHNICAL MEETING 16th to 21st August 2015

The Magellan Sutera Resort, Kota Kinabalu, Sabah, MALAYSIA

Page 2: P3_Session1A
Page 3: P3_Session1A

Outlines

Page 4: P3_Session1A

Introduction

Page 5: P3_Session1A

Location of the Project

Project Location

Page 6: P3_Session1A

Mambong

Bengkayang

Sarawak

West Kalimantan

Serikin

275kV HVAC Transmission Line

128km

The Interconnection

Page 7: P3_Session1A

150kV 275kV 275kV 132kV Siluas Serikin

K a l i m a n t a n - S a r a w a k

B o r d e r

West K a l i m ant an Sarawak

82.6km 45.6km

Bengkayang Mambong

K a l i m a n t a n - S a r a w a k

B o r d e r

201 Towers 144 Towers

Page 8: P3_Session1A

Initially Power transfer

SEB to PLN

Power Transfer up to

In due course

Page 9: P3_Session1A
Page 10: P3_Session1A

Background

Page 11: P3_Session1A
Page 12: P3_Session1A
Page 13: P3_Session1A
Page 14: P3_Session1A

Kalimantan Power Exchange Agreement between SEB and PLN (PT PERSERO) on 5th

September 2012

Page 15: P3_Session1A

Construction started

Expected to be completed by

Target operational by

Page 16: P3_Session1A

Technical Specification of the Project

Page 17: P3_Session1A
Page 18: P3_Session1A
Page 19: P3_Session1A

Description PLN SEB

Line Conductor

Conductor type/name

ACSR/AS Zebra ACSR Drake

No. and diameter of Al wire

54/3.18 26/4.44

No. and diameter of St wire

7/3.18 7/3.45

Overall diameter 28.62 mm 28.11 mm

Cross-section 428.9/55.6 mm² 402/65 mm²

Resistance (DC at 20°C)

0.065 Ω/km 0.072 Ω/km

Breaking load 137.8 kN 145 kN

Weight 1,621 kg/km 1,680 kg/km

Page 20: P3_Session1A

Description PLN SEB

Tower Design Parameters

Tower height 50.4 m 35 to 37 m

Clearance open country 10.5 m 7.5 m

Clearance over plantations

7 m 4 m

Clearance to highway, roads

11 m 9 m

Clearance to other lines 5 m 4 m

Basic span 400 m 350 m

Insulators Cap and pin Cap and pin

Communication link OPGW OPGW

Surge arresters Class 3 Class 3

Cross arm – Cross arm >7.4m >6.8m

Cross arm – tower body ~6.9m ~6m

Conductor to ground Clearance

~15m ~10m

Right of way 15m on each side of

tower 20m on each side of

tower

Page 21: P3_Session1A
Page 22: P3_Session1A

Basic Substation Design Parameters Mambong Substation Bengkayang Substation

1. Number of bays required 2 (extension) 2 2. Bay type Line Line

3. Switchgear type Outdoor Outdoor (1½ circuit-breaker

scheme)

4. Environment Heavy Pollution Heavy Pollution

5. Busbar configuration Double Double 6. Busbar rating, A 2000 1600 7. Circuit breaker rating, A 2500 2500*

8. Circuit breaker short-circuit rating, kA 25 (3 sec.) 25 (3 sec.)

9. Busbar short-circuit rating, kA 25 (3 sec.) 25 (3 sec.)

10. Maximum voltage for equipment, kV 300 300

11. Short-duration power frequency withstand, kV

460 460

12.Basic SIL/LIL, kV 850/1050 850/1050

13.Minimum safety clearance, mm 4800 4800

14.Line reactor rating 3x5MVAr 3x5MVAr

15.Teaser reactor rating TBA –

Page 23: P3_Session1A

Voltage/Capacity of Capacitor Banks

Mambong Substation

275kV 2×40MVAR 2×80MVAR

132kV 4×20MVAR

Page 24: P3_Session1A
Page 25: P3_Session1A

Milestone and Progress

Page 26: P3_Session1A

Project Milestones at Sarawak

Overall Overall Progress Completion

Mambong Substation 78%

Mambong Transmission Lines 98%

Activity Expected Completion Date

Extension Works at Mambong 275/132kV Substation

Quarter 3, 2015

275kV Double Circuit Transmission Lines

Quarter 3, 2015

Page 27: P3_Session1A

Piling works at capacitor bank bays

Cable Trench and Structure foundation

works

Equipment Installation

Line stringing works

Line Checking commence on 27th July

2015

Page 28: P3_Session1A

Project Milestones at West Kalimantan

Overall Overall Progress Completion

Bengkayang Substation 85.46%

Transmission Lines 89.33%

Activity Expected Completion Date

Construction Works at Bengkayang 275/150kV Substation

July 2015

275kV Double Circuit Transmission Lines

July 2015

Page 29: P3_Session1A
Page 30: P3_Session1A
Page 31: P3_Session1A
Page 32: P3_Session1A
Page 33: P3_Session1A
Page 34: P3_Session1A
Page 35: P3_Session1A
Page 36: P3_Session1A

The Sarawak-West Kalimantan Interconnection

• Reduce generation cost for PLN West Kalimantan

• Improve security of supply for both SEB and PLN West Kalimantan

• Improve operational flexibility

• Catalyst for future potential interconnectors

Page 37: P3_Session1A