P051 Project Instruction - Approved Rev 3

Embed Size (px)

Citation preview

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    1/24

    P051

    HODARIYAT BRIDGE

    Aconex Project Instruction

    NOTE

    This is a live document.

    It will require periodic updates to reflect the progress of the project.

    Initial authorship by TDIC & Aconex

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    2/24

    TABLE OF CONTENTS

    1.0 INTRODUCTION ........................................................................................................... 3

    1.1 Aconex 31.2 Getting Started with Aconex 31.3 Aconex System Terminology 4

    2.0 ABOUT THIS DOCUMENT .............................................................................................. 5

    2.1 Purpose 52.2 How to Use 52.3 Custodianship 5

    3.0 PROJECT INFORMATION ...............................................................................................6

    3.1 Project Details 63.2 The Project Team 7

    4.0 CONTROLLED DOCUMENTS .......................................................................................... 9

    4.1 Required Document Fields 104.2 Optional Document Fields 114.3 Disciplines 124.4 Numbering Convention 144.5 Title Convention 174.6 Status 174.7 Revision Convention 18

    Other Document Field Values 18

    4.8 Document Distribution 195.0 PROJECT MAIL ........................................................................................................... 20

    5.1 Project Mail Numbering Convention 205.2 Project Mail Type 205.3 Project Mail Attributes 225.4 Time Constrained Project Mail 235.5 Subject Line Conventions 235.6 Project Mail Approval 235.7 Auto Mail Prefix 235.8 Project Correspondence Protocol 24

    CONFIDENTIALITY AND INTELLECTUAL PROPERTY STATEMENT

    The information contains confidential information and uses an Aconex proprietary template. This document must not be used ordisclosed for any purpose other than in connection with the implementation or use of the Aconex system (the Purpose). .

    The intellectual property in this template (and any modification, enhancement, derivation or reproduction of it) is owned by Aconexand licensed solely for the Purpose and the licence of the original or modified document can be terminated by Aconex at any time at

    its absolute discretion. The Aconex name, logos and URLs are the property and/or marks of Aconex.

    Any modification, enhancement, derivation or reproduction of this document must contain this Confidentiality and Intellectual PropertyStatement and any other confidentiality and any other similar markings or legends contained herein.

    Any questions based on the confidentiality or ownership of this document should be directed to [email protected]

    P051-TDI-PW-GEN-PRC-0001 Rev 3 2

    mailto:[email protected]:[email protected]:[email protected]
  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    3/24

    1.0 INTRODUCTION

    1.1 AconexAconex have been engaged on this Project by TDIC as the online collaboration system for this project.

    1.2 Getting Started with AconexTo access Aconex, you require an internet connection, the latest internet browser installed on your computer and toenrol in the Aconex training offered to all project participants.

    Aconex does not require you to install any licensed software to access the system.

    The Aconex Client Operations team will be available to guide the entire project team through Aconex implementationand support all project members throughout the project life.

    1.2.1 Internet Access

    Aconex recommends the use of broadband internet to optimise the Aconex experience, in particular wheredownloading and uploading of large files is required.

    Broadband varies in download and upload speeds or bandwidth capacity. The optimal broadband bandwidth capacityfor your organisation will depend on the number of users and network configurations of your IT systems.

    Please check with your local IT Manager or Internet Service Provider (ISP) to confirm the details of yourOrganisations broadband capacity.

    1.2.2 Internet Browser

    Aconex recommends using the latest version of Internet Explorer or Mozilla Firefox as your internet browser. Thelatest internet browsers are available free to download fromwww.microsoft.com/ie (PC) and www.mozilla.com(PC/Mac OSX).

    Please check with your local IT Manager to confirm the version of your internet browser.

    1.2.3 Implementation ProcessThe implementation process will be facilitated by Aconex. The process will require participation and input from keyproject stakeholders to assist in defining the appropriate system configuration for the project.

    1.2.4 Training

    Ongoing support and training is available to all project participants throughout the project life. To request trainingplease contact Aconex on 800 226639 (ACONEX) or submit details online athttp://www.aconex.com/Contact/Contact-Us/Request-Training.html or email [email protected]

    Aconex provides 24/7 helpdesk support for all members globally. A list of Global Helpdesk numbers and officelocations can be found on www.aconex.com

    The following training courses are available to all users. Please note that, wherever possible, the sessions will becustomised as per project/ group requirements.

    TABLE 1 - ACONEX TRAINING COURSES

    Course Name Course summary Duration

    Basic Documents and Mail

    Designed for new users of Aconex. It covers fundamentalaspects of the system including Aconex overview, generalnavigation project mail and document management withinAconex.

    2 hours

    Organisation AdministratorThis session covers the setup for a specific organisation ofadditional users, setting security levels and disabling users oncethey are no longer part of the project/ organisation

    1 hour

    Multiple Document UploadAimed at users who are required to upload, register, supersede

    and transmit multiple documents.1.5 hours

    P051-TDI-PW-GEN-PRC-0001 Rev 3 3

    http://www.microsoft.com/iehttp://www.microsoft.com/iehttp://www.mozilla.com/http://www.aconex.com/Contact/Contact-Us/Request-Training.htmlmailto:[email protected]://www.aconex.com/http://www.microsoft.com/iehttp://www.mozilla.com/http://www.aconex.com/Contact/Contact-Us/Request-Training.htmlmailto:[email protected]://www.aconex.com/
  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    4/24

    Course Name Course summary Duration

    Advanced DocumentsCovers the use of more advanced features/ functionality withinthe Documents module. This session is often used inconjunction with the Multiple Document Upload session.

    1 hour

    Bulk Processing

    Bulk processing enables mass uploading of documents and

    linking to the metadata information contained within an Excelspreadsheet. This is very useful where there is a large amountof historical documents to upload or where document numbersneed to be reserved in the register for future documentdeliverables.

    1.5 hours

    When delivering to a specific project team, this document will be referenced to reflect the agreed projectconfigurations are implemented.

    1.3 Aconex System TerminologyAconex staff utilise terms which will also be utilised throughout this document and are specific to the Aconex system,training and implementation. Heavily used Aconex terminology is detailed and defined in the table below.

    TABLE 2 - ACONEX SYSTEM TERMINOLOGY LISTTerminology Definition

    Aconex Client The Organisation that engaged the services of Aconex for the project.

    Controlled Document A document which is registered with multifaceted, searchable metadata and a completedocument, transaction history.

    Document Register An electronic registry of all documents that have been registered by your Organisation orreceived by transmittal from other Organisations.

    Key Contact The primary point of contact for Aconex staff throughout the project lifecycle. This may bethe Aconex Client or an Organisation delegated as key contact by the Aconex Client.

    Mandatory Field A field which requires completion. All fields which require completion and are marked witha red asterisk (*).

    Organisation A registered entity in Aconex who manages their own Organisation members and projectinformation.

    Org Admin An Aconex role which performs administrative functions for their Organisation such ascreating and administrating new member accounts and Organisation security.

    Project Admin An Aconex role which administrates and manages project wide settings and updatesAconex and associated documents with any procedural changes decided upon.

    Aconex ProjectProtocols

    A document created to provide a record of agreed system configuration, protocols andprocedures associated with using Aconex on the project. The document will also be usedto facilitate the implementation process.

    Project Mail Project correspondence which contains searchable metadata to assist with retrieval andreporting of all communication between project participants.

    Register The process of uploading (onto Aconex) and tagging an electronic file with appropriateproperties and categories according to pre-defined fields.

    Supersede The process of updating a previously registered document with the latest version andplacing the previous version in the document history.

    Training Coordinator The Training Coordinator is responsible for organising and scheduling training sessions forproject participants, at either for their Organisation or for all participants on the project.

    Transmittal Method of issuing documents from your Organisations document register to anotherOrganisations document register.

    Unregistered File An electronic file uploaded into the document register (unregistered tab) but not taggedwith metadata as yet.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 4

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    5/24

    2.0 ABOUT THIS DOCUMENT

    2.1 PurposeThe purpose of this document is to assist with the implementation process and record the agreed systemconfigurations, protocols and procedures associated with the use of Aconex on the project.

    2.2 How to UseThis document is specific to the Aconex collaboration system and shall be read in conjunction with but not limited toall other project specific manuals, plans or procedures applicable to the project.

    In general this document is to be used in the following but not limited to the following scenarios:

    Existing and new project participants that wish to familiarize themselves with what system configurationshave been defined for their organization.

    Existing and new project participants that wish to refer to project procedures that have been mapped toAconex.

    Org Admins and Project Admins that are required to perform the initial configuration or make amendments tothe project setup.

    Aconex will also use this document in training situations and when performing periodic health checks.

    2.3 CustodianshipThis document is a live document. It is expected that project information requirements will change over the course ofthe project lifecycle as the project and participants change.

    This document will be required to be updated to reflect changes to system settings, processes, project participantsand procedures.

    The ongoing management of this document will reside with the nominated custodian who is Mia Merrigan from TDICand will be supported by the local Aconex Client Operations team.

    All proposed changes/amendments to details or procedures detailed in this document must be submitted to the

    nominated custodian for approval prior to implementation.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 5

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    6/24

    3.0 PROJECT INFORMATION

    3.1 Project DetailsTABLE 3 - PROJECT DETAILS

    Project Name* GG101 Hodariyat Bridge

    Project Short Name* GG101 Hodariyat Bridge

    Phone Number 02 4036200

    Fax Number 02 4061500

    Project Start Date* 1 October 2009

    Estimated Completion Date* 28March 2012

    Project Address

    City/Suburb* Abu Dhabi

    Postcode* 126888

    Country* UAE

    Project Description Cable Stayed Bridge from Abu Dhabi Island to Hodariyat Island

    (*) Mandatory field required for project setup.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 6

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    7/24

    3.2 The Project Team

    3.2.1 Communications Flow Diagram

    The expected flow of communication on the Project is detailed in the figure below.

    FIGURE 1 - PROJECT COMMUNICATIONS FLOW DIAGRAM

    P051-TDI-PW-GEN-PRC-0001 Rev 3

    Client(TDIC)

    Engineer(Parsons)

    Sub-Contractor

    Main Contractor(AVJ)

    General Project Communications/ Mail

    Sub-ContractorSub-Contractor

    ConsultantsConsultants

    7

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    8/24

    3.2.2 Project Key Contacts

    The following table lists the contact details of the key contacts for each organization and the relevant Aconex projectinformation.

    Project participants are to contact their respective key contact for all matters relating to the use of Aconex.

    TABLE 4 PROJECT KEY CONTACTS

    Key Contact Information Aconex Project Information

    Organization Name Role ContactDetails

    Org

    Prefix

    Project

    Role

    AC KC PA TC OA

    TDICMiaMerrigan

    ProjectAdministrator

    02 4061672 TDI CL

    TDICDavid (Dai)Lewis

    SR ProjectManager

    056 1057588 TDI CL

    TDIC Paul WilsonCommercial

    Manager0 2 4 03 65 16

    050 3961207TDI CL

    Aconex Amro RafeeAccountManager

    050 2729551 ACX CN

    AconexTrainingCoordinator

    04 4287474 ACX CN

    OVERSEAS AST /VSL MIDDLEEAST JV

    BrunoThierry

    ProjectDirector

    050 4531097

    AVJ MC

    TBC IBT CN

    TBC TGP CN

    PARSONSINTERNATIONALLIMITED

    Frederic

    Turlier

    Resident

    Engineer

    050 8176087

    PIL-P051 LC

    Code Project Role

    CL Client

    LC Lead Consultant

    CN Consultant

    HC Head Contractor

    SC Subcontractor

    Code Aconex Role

    AC Aconex Client

    KC Key Contact

    PA Project Admin

    TC Training Coordinator

    OA Org Admin

    P051-TDI-PW-GEN-PRC-0001 Rev 3 8

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    9/24

    4.0 CONTROLLED DOCUMENTS

    This section details the fields and values associated with managing project documents using Aconex.

    All project participants when registering documents must apply the appropriate document tags defined by for theproject. The document tags are the key information or metadata fields that are used to identify the document such

    as Number, Title, Date Created. As a minimum Aconex requires all registered documents to be tagged withmandatory fields (denoted by red asterisks).

    FIGURE 2 SAMPLE PROJECT DOCUMENT REGISTRATION FORM

    P051-TDI-PW-GEN-PRC-0001 Rev 3 9

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    10/24

    4.1 Required Document FieldsThe following table details the mandatory Document Fields applicable to the project. When registering a document,all of following fields must be completed.

    TABLE 5 REQUIRED DOCUMENT FIELDS

    Field Label Field Type Description of Use/Application Table/Figure

    Reference

    Search

    Field

    DocumentNo*#

    DocumentNumber

    For tagging a document with the unique numberrequired by the applicable document numberingconvention.

    Figure 3 Y

    Revision*# Text For tagging a document with a revision reference(applicable project convention) when it is updated.

    Y

    Title Text For tagging a document with the applicable titledescription associated with the document.

    Y

    Type*# List (SingleSelect)

    For tagging a document to classify it with anappropriate document type.

    Table 8Y

    Status*# List (Single

    Select)

    For tagging a document with the appropriate status

    reference that is relevant to the document lifecycle. Table 9 Y

    Discipline List (SingleSelect)

    For tagging a document with an appropriatediscipline classification.

    Table 7 Y

    Revision Date Date For tagging a document with a date when therevision was created.

    Y

    DateUploaded*#+

    Date System defined field. Date of when file wasuploaded.

    Y

    Attribute 1 - List (MultiSelect)

    For tagging a document with one or more values ofinformation to assist with categorization. ExampleZones within the project.

    Table 10 Y

    Job Code List (Multi

    Select)

    For tagging a document with one or more values of

    information to assist with categorizationTable 14 Y

    For additional fields to tag your documents please discuss with your Project Administrator or Aconex ClientOperations Representative.

    (*) System mandatory field and cannot be disabled (i.e they must be used).(#) Field label can not be renamed.(+) Field with specific function controlled automatically by Aconex system.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 10

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    11/24

    4.2 Optional Document FieldsThe following table provides optional document fields available for tagging documents with additional information.When registering a document, the following fields can be completed if required.

    TABLE 6 OPTIONAL DOCUMENT FIELDS

    Field Label Field Type Description of Use/Application Table/FigureReference

    SearchField

    Confidential# ConfidentialityCheck Box

    For defining who can have exclusive access to theregistered document.

    N

    File# File For attaching the electronic file relevant to theregistered document.

    N

    Print Size# Text For detailing the print size requirements to assistusers when printing the document.

    N

    Reference Text For tagging a document with specific referenceinformation relating to the document.

    Y

    Date Created Date For tagging a document with a date when it was first

    created. N

    Author Text For tagging a document with details of the author. Y

    Comments Text Area For entering comments relevant to the document. N

    PackageNumber

    List (MultiSelect)

    For tagging a document with one or more values ofinformation. Example Package Numbers within theproject (subcontractors)

    Table 15 Y

    (*) System mandatory field and cannot be disabled (i.e they must be used).(#) Field label can not be renamed.(+) Field with specific function controlled automatically by Aconex system.

    For additional fields to tag your documents please discuss with your Project Administrator or Aconex Client

    Operations Representative.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 11

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    12/24

    4.3 DisciplinesThe document disciplines in use for this project are detailed in the following table. When registering a document,select discipline most suitable from the drop down list.

    If a discipline does not exist on Aconex and is required by your organisation, submit a request to the Aconex Client.

    TABLE 7 DOCUMENT DISCIPLINESDiscipline Code Application/Use

    Architectural ARC Ceiling Details, Door Schedule, Elevation, Floor Details, Floor Layouts,Reflected Ceiling Plans, Sections, Site Plans, Toilet Details, Wall Details

    Authorities & GovernmentDepartments

    AUT Abu Dhabi Terminals, ADDC, ADNEC, ADNOC, ADSSC, ADWEA, Al AinWildlife, Building Directorate, Chamber of Commerce, Civil Aviation, CrownPrince, Cultural Foundation, Department of Social Services & CommercialBuilding, EAD, EMPOST, Environmental Agency, ETISALAT, ExecutiveAffairs Authority, Executive Council, Finance Department, GASCO, GeneralAuthority for Health Services, License & Traffic Directorate, Military/ArmedForces, Ministry of Economy Under Secretary Office, Ministry of Transport,Petroleum Port Authority,Police Department, Port Authority, Presidential,TEBODIN, Town Planning Department, TRANSCO

    Civil Works, Roads andbridges

    CIV Bridges, Civil, Contours, Grading, Infrastructure, Islands & roundabouts,Krebs, Parking Bays, Ramps, Retaining Walls, Road Centerlines, Roads,Spot Elevation Heights, Survey Equipment & Supply, Survey Information,Traffic Impact Studies, Tunnels.

    Commercial COM Contracts, Variations, Notice of Claim, Variation Orders.

    Contracts Administration CTA Contracts, Variations.

    Design & Master Planning DMP Concept Design, Design Workshops, Development Study, Master Planning,Planning Design Regulations, Satellite Imagery, Tender Presentations,Topographic Mapping Services, Urban Design Review, Urban Planning

    Environment & Ecology ETE Archaeological Studies, Chemical Analysis of Soils, ConstructionEnvironmental Management Plan, Ecological Surveys, Environmental ImpactAssessments, Marine Studies, Traffic Impact Studies

    Financial Management FNM Advance Payment Guarantee, Approved Variations, Control Budget,Employers Instructions, Estimates, Financial Reports, Performance Bond,Proposals/Claims, Valuations, Payment Certs.

    General GEN Meetings, Monthly Reports, Photography, Site Photographs, Transportation,Travel, Weekly Reports

    Hard and Soft Landscape LAN Irrigation, Parking Lots, Pedestrian Paving, Precincts, Roadways, Trees &Plants

    Health & Safety HSE Health, Safety

    Legal LGL Claims, Contract Drafting, Insurance Certificate

    Municipality Liaison MUN Abu Dhabi Municipality, Building Permits, Land Department, Park &Agriculture Section, Permits & Permissions, Roads Department, Saadiyat

    MunicipalityProgram Management PMG Master Schedule, Progress Reports, Project Management Plan, Scheduling,Technical Program

    QA/QC QAC 3rd Party Labs, Audit, Check Lists, Confirmation of Verbal Instruction (CVI),Field Change Request, Forms, Inspection & Test Plan, Material Approval,Method Statements, Mock-ups, Non-Conformance Report (NCR), Notice ofCommencement, On Site Labs, Organization Chart, Project Quality Plan,Project Quality Procedure, QA/QC Procedures, RFI's, Site Instruction,Supervision, Suspensions/Stop of Work, Test Equipments, Water Main

    Site Management SMG Demobilization, Hazardous Waste Remediation, Labour Camps, Mobilization,Security Services, Service Tunnels, Site Administration, Site Clearing, SiteDemolition, Site Earthworks, Site Electrical Items, Site Offices & Facilities,Site Preparation, Site Utilities

    Streetscape STS Landscape Lighting, Street Lighting, Street Signage, Streetscape Furniture,

    Way finding Lighting, Way finding SignageTraffic Control TRF CCTV, Lane Control Systems, Vehicle Management System, Signage, PublicAddress

    P051-TDI-PW-GEN-PRC-0001 Rev 3 12

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    13/24

    Discipline Code Application/Use

    Utility Distribution UDT District Cooling, Gas, HV Electrical, Irrigation Water, LV Electrical, MVElectrical, Potable Distribution, Reservoirs, Sewage Treatment, Sewerage,Storage Tanks, Utility Comms

    P051-TDI-PW-GEN-PRC-0001 Rev 3 13

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    14/24

    4.4 Numbering ConventionAll documents registered in Aconex are required to have a unique number assigned (i.e no duplicate numbers can beregistered).

    The Aconex document number field is flexible and can support a variety of numbering conventions commonly

    adopted on projects. The document number field supports text, numbers and characters permitted by MicrosoftWindows operating system.

    Please consult with your Aconex representative for additional information or assistance on how to implement asuitable document numbering convention.

    4.4.1 Numbering String

    All documents produced on this project must be numbered in accordance with the number string defined below.Please refer to the relevant reference tables for codes applicable to the number string.

    FIGURE 3- DOCUMENT NUMBER STRING

    ProjectCode

    - OrganisationCode

    - Location - Discipline - Document - UniqueNumber

    P051 PIL U1 ADM MOM 000x

    See Table 4 See Table 10 See Table 7 See Table 8

    4.4.2 Drawing, Calculations, Bar Bending Schedule Numbering

    FIGURE 4 DRAWING NUMBER STRING

    ProjectCode

    - OrganisationCode

    - Location - DetailedDoc Type

    - Scope - Element - UniqueNumber

    P05

    1

    PIL U1 C CO AB 001

    See Table 4 SeeTable 10

    See tablebelow

    See tablebelow

    See tablebelow

    P051-TDI-PW-GEN-PRC-0001 Rev 3 14

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    15/24

    DetailedDocument Type Abrev Element (Structure Pieces) Abrev Scope (Sub Structure) Abrev

    Calculations C Abutments AB Concrete outline CO

    Drawing D Barriers & Curbs BR External Tendons ET

    Method Statement M Expansion Joints & Bearings EB Longitudinal Tendons LT

    Bar Bending B Footings FO Reinforcement RFGeneral G Pier Columns PR Transverse Tendons TT

    Reports & Manuals R Piles PI Incremental Launching IL

    Standard Details ST Vertical Tendon VT

    Superstructure SP Precast Marine Footings PF

    Temporary Works TW Travellers TV

    Formwork FW Plan & Profile PP

    Existing EX Cross Sections CS

    Lighting LG Alignment Data AL

    Stormwater/Drainage SW Pavement Markings & Signs PM

    Future Utilities FU Cable Stay CT

    General Notes GN Bridge Building Equipment BB

    Pylon PY Structural Steel SS

    Pier Segment PS Kinematics KN

    Pier Caps PC Precast Units PU

    Pier Table PT

    Document & drawing numbers to be generated by originators and not auto numbering

    4.4.3 File Types

    Whilst native files are required for coordination at certain stages/phases of the project the agreed project documentdistribution format is PDF.

    Where more than one file extension with the same document number is required, it must be registered as a new

    document number with a file format acronym appended to the end of the document number string (refer to the belowfigure for a sample).

    4.4.4 File Name Recognition

    Files named and saved in local/network drives in accordance with the project document numbering convention areable to capitalize on the file name recognition feature in Aconex. The figure below provides examples of appropriatefile names and how the elements of the file name will be imported into Aconex as the document number and revision.

    FIGURE 5 MULTIPLE FILE FORMAT & FILE NAME RECOGNITION EXAMPLE

    File Format Examples of Computer file name Registered Number on Aconex Rev

    PDF (Default) P051-TDI-U1-C-AB-CO -0001_B.pdf P051-TDI-U1-C-AB-CO -0001 B

    AutoCADDWG

    P051-TDI-U1-C-AB-CO -0001-DWG_B.dwg P051-TDI-U1-C-AB-CO -0001-DWG B

    Word P051-TDI-U1-C-AB-CO -0001-DOC_B.doc P051-TDI-U1-C-AB-CO -0001-DOC B

    P051-TDI-PW-GEN-PRC-0001 Rev 3 15

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    16/24

    Types & File Formats

    The following tables detail the Document Types available for use on the project relevant to their organizations role onthe project. When registering a document, select most suitable type from the drop down list.

    If a document type does not exist on Aconex and is required by your organisation, submit a request to the AconexClient.

    TABLE 8 DOCUMENT TYPES

    Document

    Type

    Code Suggested Documents TDI PIL AVJV SC CN

    As BuiltDrawing

    ASD Final As Built

    Certificate CER For all certificates except payment

    Bar BendingSchedule

    BBS For Bar Bending Schedule

    Bill of quantitiesBOQ Quantity and unit price listed for

    materials and labour

    Calculation CAL All calculations sheets

    Contract CON For Contracts between any partiesrelevant to the project

    Drawing DWG For all drawings except shop & As built

    Form FRM Any Forms

    Invoice INV For all Invoices

    Manual MAN All operating and maintenance manuals

    MethodStatement

    MET All method statements

    PaymentCertificates

    PCT All Payment Certificates

    Permits PER All project related permits

    PlanPLN For all plans i.e. safety, ITP,

    environmental.

    Presentations PRS For all presentations

    Procedure PRC For all procedures

    ProgramPRG All project programmes, project

    scheduling

    Purchase Order LPO For all LPO

    Report REP Reports including but not limited toDaily, Weekly, Flash, Monthly, PCG,

    Cost reports, Test Report

    Sketch SKH All sketch design documentation

    Snag List SNG All Snag List

    Statement STT All Statements

    Shop Drawing SPD All working and shop drawings

    P051-TDI-PW-GEN-PRC-0001 Rev 3 16

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    17/24

    4.5 Title ConventionThe Document Title is important and all team members must use coherent titles when registering documents. Thisfield is an important element in searching for and retrieval of historical information within the database. The followingare guidelines on good practice use of the title field:

    DO make the title the same as the hardcopy

    Titles should typically be very specific, e.g.Building A Ground Floor Reflected Ceiling Layout or Design TeamMeeting Minutes.

    DONT duplicate document titles

    DONT use vague titles like: Drawing 1, Drawing 2, Drawing 3 etc.

    4.6 StatusThe following table details the document status available for use on the project relevant to their organizations role onthe project. When registering a document, select most suitable type from the drop down list.

    If a document status does not exist on Aconex and is required by your organisation, submit a request to the AconexClient.

    TABLE 9 DOCUMENT STATUS

    Document Status Use/Explanation TDI PIL AVJV SC CN

    Approved For documents which have been approved inaccordance with project approval procedures

    Approved withcomments

    For documents which have been approved inaccordance with project procedures. Thesehave been approved in principle with somecomments

    As Built For As Built Documents

    Cancelled For cancelled documents

    Issued for Approval For documents to be issued for Approval

    Issued forConstruction

    For documents ready for construction stage.

    Issued forInformation

    For documents to be issued for informationonly

    Issued for Review For documents requiring review by one ormore parties

    Rejected For documents which have been reviewed inaccordance with project procedures and havebeen rejected

    Reviewed For documents reviewed

    Reviewed WithComments

    For documents reviewed with comments

    Revise andResubmit

    P051-TDI-PW-GEN-PRC-0001 Rev 3 17

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    18/24

    4.7 Revision Convention

    The document revision practices adopted on the project are detailed in the following table.

    TABLE 10 - REVISION CONVENTION

    Revision Convention ApplicableDocument Status

    Revision Triggers

    Numeric Approved 01, 02, 03, Numeric

    Approved withcomments

    01, 02, 03,

    Numeric Rejected 01, 02, 03, Numeric Cancelled 01, 02, 03, Numeric For Approval 01, 02, 03, Numeric For Construction 01, 02, 03,

    Numeric For Information01, 02, 03,

    Numeric For Coordination 01, 02, 03,

    Numeric For Review 01, 02, 03,

    Alpha As-Built A, B, C

    Other Document Field ValuesAll documents must be tagged with the appropriate metadata/information. This section details the metadata in use onthis project.

    4.7.1 Attribute 1 [Location]The primary attributes applicable to this project are detailed in the following table.

    TABLE 10 ATTRIBUTE 1 LOCATION

    Primary Attribute Description Code

    Connection Road Connection to existing roads on Abu Dhabi CR

    Laydown Area Site Compound LA

    Earthworks All Earthworks on site EW

    Traffic Management Traffic Mgmt on existing roads TM

    Project Wide Entire Project PW

    Unit 1 - Substructure South Approach Substructure (A1 to P9) U1

    Unit 1 - Superstructure South Approach Superstructure (A1 to P9) U1

    Unit 2 - Substructure Cable Stayed Bridge Substructure (P9 to P12) U2

    Unit 2 - Superstructure Cable Stayed Bridge Superstructure (P9 to P12) U2

    Unit 3 - Substructure North Approach Substructure (P12 to P21) U3

    Unit 3 - Superstructure North Approach Superstructure (P12 to P21) U3

    Unit 1 - Approach South Approach Sub/Superstructure (A1 to P9) UA

    Unit 3 Approach North Approach Sub/Superstructure (P12 to A21) UB

    Units 1, 2, 3 Cable Stayed Bridge, South & North Approach UXUnit 2 Cable Stayed Bridge Cable Stayed Bridge Sub/Superstructure (P9 to P12) UM

    P051-TDI-PW-GEN-PRC-0001 Rev 3 18

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    19/24

    4.7.2 Attribute 2

    The secondary attributes applicable to this project are detailed in the following table.

    TABLE 11 ATTRIBUTE 2 [TBD]

    Secondary Attribute Description Code

    TBC

    4.7.3 Job Code

    The Job Number values in use on the project are detailed in the following table.

    TABLE 14 JOB CODE

    Job Code Description Code

    Hodariyat Bridge P051

    4.7.4 Package Numbers

    The Package Numbers applicable to this project are detailed in the following table

    TABLE 15 PACKAGE NUMBER

    Package Number Description

    A01 All Govt. Authorities

    C01 Bridge Construction

    C02 Geotech Invest, Topo & Bathymetric Surveys

    C03 Pre construction Works - Tunnel

    C04 Construction of Bridge

    C05 Temp. Power to Laydown Area

    C06 Main Construction Works

    D01 Design

    D02 Environmental Impact Assessment

    D03 Tunnel Access Feasibility Study

    D04 Design & Construction Supervision

    D05 Design Check

    I01 Invoices for Finance Department (LPO)

    O01 Security Services to HB Laydown Area

    4.8 Document Distribution

    4.8.1 Transmittal Reason for Issue

    The applicable Reason for Issue for transmittals on the project are detailed in the following table.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 19

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    20/24

    TABLE 16 TRANSMITTAL REASON FOR ISSUE

    Reason for Issue Definition of Use

    Issued for Approval Issuing documents which require approval from authorised project participants

    Issued for Information Documents which are to be used for information purposes.

    Issued for Review Documents which require review by another project participant

    Issued for Comment Documents issues for comments

    5.0 PROJECT MAIL

    This section details the specifications for the use of the Project Mail module on Aconex, for this project.

    5.1 Project Mail Numbering ConventionAll Project Mail generated in Aconex is automatically assigned with the next available number associated with the

    selected project mail type.

    5.2 Project Mail TypeThe authorised Project Mail types which an Organisation may initiate are detailed in the following table. For additionalProject Mail types please seek approval from the Aconex Client.

    TABLE 17 CONTRACTUAL MAIL

    Project Mail Type Use TDI PIL AVJV SC CN

    Letter For general informal communication betweenparticipants from different organizations.

    Transmittal Cover sheet to notify when documents i.e.drawings are issued to organisations updating

    their registers.

    Claim For Time & Cost implications due to additionalwork, NOD, expense

    Confirm VerbalInstruction

    For confirmation on site verbal instructions.

    Request ForInformation

    For construction queries

    Response to RFI For answer queries for information.

    Inspection & TestingRequest

    For inspection / testing requests

    Inspection Record For all Inspection checklist & records

    Meeting Minutes For all meeting minutes

    Material ApprovalRequest

    For material submittals

    Non ConformanceReport

    For all NCRs

    Variation Order All variation to contract.

    Site ModificationSheet

    All site modification sheets

    Employers Instruction To send Instruction from TDIC

    Engineers Instruction To send site verbal advice

    P051-TDI-PW-GEN-PRC-0001 Rev 3 20

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    21/24

    TABLE 18 GENERAL MAIL

    Project Mail Type Use TDI PIL AVJV SC CN

    Memorandum For general informal communication betweenproject participants within own organization.

    Informal MailFor informal correspondence

    Project InvitationTo Send Project Invitations

    P051-TDI-PW-GEN-PRC-0001 Rev 3 21

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    22/24

    5.3 Project Mail AttributesThe following tables detail the attributes applicable to the project. All project mail must be tagged with the followingattributes, as appropriate to the project mail.

    5.3.1 Attribute 1

    The attribute 1 values in use on the project are detailed in the following table.

    TABLE 19 - PROJECT MAIL ATTRIBUTE 1 (AREA)

    Primary Attribute Description Code

    Connection Road Connection to existing roads on Abu Dhabi CR

    Laydown Area Site Compound LA

    Earthworks All Earthworks on site EW

    Traffic Management Traffic Mgmt on existing roads TM

    Project Wide Entire Project PW

    Unit 1 - Substructure South Approach Substructure (A1 to P9) U1

    Unit 1 - Superstructure South Approach Superstructure (A1 to P9) U1

    Unit 2 - Substructure Cable Stayed Bridge Substructure (P9 to P12) U2

    Unit 2 - Superstructure Cable Stayed Bridge Superstructure (P9 to P12) U2

    Unit 3 - Substructure North Approach Substructure (P12 to P21) U3

    Unit 3 - Superstructure North Approach Superstructure (P12 to P21) U3

    Approach for Unit 1 South Approach Sub/Superstructure (A1 to P9) UA

    Approach for Unit 3 North Approach Sub/Superstructure (P12 to A21) UB

    All Approaches & Units Cable Stayed Bridge, South & North Approach UX

    Main Bridge Cable Stayed Bridge Sub/Superstructure (P9 to P12) UM

    5.3.2 Attribute 2

    The attribute 2 values in use on the project are detailed in the following table.

    TABLE 21 - ATTRIBUTE 2 (DISCIPLINE)

    Attribute 2 Description Code

    Architectural ARCAuthorities & Government Departments AUT

    Civil Works, Roads and bridges CIV

    Commercial COM

    Contracts Administration CTADesign & Master Planning DMP

    Environment & Ecology ETE

    Financial Management FNM

    General ADM

    Hard and Soft Landscape LAN

    Health & Safety HSE

    Legal LGL

    Municipality Liaison MUN

    Program Management PMG

    QA/QC QAC

    Site Management SMG

    P051-TDI-PW-GEN-PRC-0001 Rev 3 22

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    23/24

    Attribute 2 Description Code

    Streetscape STS

    Traffic Control TRF

    Utility Distribution UDT

    5.4 Time Constrained Project MailProject mail which have time constraints (eg RFIs) can be managed by using response required and setting a duedate when creating project mail. It is recommended where time constraints apply the project team should define theapplicable types and agree on the timeframe to respond.

    5.5 Subject Line ConventionsIt is vitally important that all team members use coherent titles when preparing Project Mail and Transmittals. TheSubject Line field is an important element in Searching for & Retrieval of historical information within the projectdatabase. Please avoid the following vague Subject Lines:

    "Query"

    "Re: Drawings"

    "Clash" etc.

    Please use meaningful subject lines to facilitate efficient Project Mail retrieval and reporting in Aconex.Example of subject line convention

    Design Team Meeting Request

    5.6 Project Mail ApprovalAconex allows organizations to implement mail approval to prevent unauthorized distribution of selected project mailtypes to other organizations. This feature allows the nominated approvers to view the mail before it is issued

    externally.

    Mail approval is configured by each organisation on the project. Please contact your Aconex Client OperationsRepresentative to assist with setting up this function.

    5.7 Auto Mail PrefixAconex will automatically add an organisational prefix to each mail item created (see section 3.2 for a list of theparticipating organisations). This helps to distinguish correspondence from each organisation. This prefix ismanaged by each organisation administrator and must be setup by each organisation for this project.Additionally, each mail item has an additional code to indicate what the mail type is.

    FIGURE 4 - MAIL USING ORG PREFIX OPTION

    Organisation Prefix Mail type Unique number

    TDI - MEMO - 000001

    Refer to Table 4 Refer to Table 17 & 18

    The Aconex system will automatically assign the unique number for each piece of mail that is created and sent.

    P051-TDI-PW-GEN-PRC-0001 Rev 3 23

  • 8/2/2019 P051 Project Instruction - Approved Rev 3

    24/24

    5.8 Project Correspondence ProtocolThis table notes any special requests by an organisation of where specific mail should be addressed to in order forthem to be actioned appropriately.

    FIGURE 5 - PROTOCOAL

    Organisation Mail/Doc Type Users

    TDIC Project related

    (Financial)

    TO

    CC

    Andrew Seymour

    David Lewis

    TDIC Project related

    (Construction)

    TO

    CC

    David Lewis

    Andrew Seymour

    TDIC Commercial TO

    CC

    CC

    Paul Wilson

    David Lewis

    Andrew Seymour

    Organisation Mail/Doc Type Users

    PIL Project related

    (Construction)

    TO

    CC

    CC

    Frederic Turlier

    Eddie Scott

    Victor Hamlig

    PIL Commercial TO

    CC

    CC

    Frederic Turlier

    Paul Marsh

    Christopher Round