Upload
others
View
5
Download
2
Embed Size (px)
Citation preview
P-8A MMA Configuration
• Common cabinets for ease of access and maintenance• Room for growth—23% more floor space than P-3• Improved power distribution with reserve• Improved ECS for increased electronics MTBF• High speed (.82 Mach) and high altitude (41K max)• Modern open system architecture• Improved crew accommodations
Search Radar
Flight Deck
Life Rafts (2)
Aerial Refueler
Power Distribution Racks (2)
Mission Equipment Racks (4)
Lav B
Sonobuoy Storage Racks (2)Weapons Bay
Automated Rotary Launchers (3)
Tactical Workstations (5)
Mission Planning
Communications RackMission Equipment Rack
Galley G4
INMARSAT Antenna
MAD
Folding StairsCrew Rest
Observer Stations (2)
CFM56-7B 180 kVAIDG Engines (2)
Wing Pylons (2 per Wing)
StorageAccess Hatch
Organic Equipment Space Provision
Storage
Seating/Ditching (6)
Growth Space Provision
Tactical Workstation Growth (1)
Green = Growth (200 ft3, 1,000 lb total)Blue = Deployment
Growth Space Provision
Radar LRU Space Provision
P-8A MMA Acquisition Snapshot
System Integration
System Demonstration
System Dev & Demonstration
Low-RateInitial
Production(LRIP)
Operations& Support
ConceptExploration
ComponentAdvanced
Development
Concept & Tech Development
Full-Rate Production
& Deployment(FRP)
Production & Deployment
C20Mar00
BA 11Jan0228May04
FY07
DRR FRP
FY13FY10
OIPT
22Jun06
FY04-13: SDD• Boeing contract
award 14Jun04• Fleet
involvement thru FIT & ITT
• 7 flight test aircraft
• Total planned inventory – 108
Boeing737-800ERX
FY02-04: CAD• Multiple contracts awarded
for MMA system– Defined MMA system
architecture– Thorough risk analysis– Validated Operational
Requirements Document (ORD)
– Detailed cost analysis
Boeing
LockheedMartin
P-8A Spiral ONE
Boeing
EADS
BAELockheed Martin
UAV’s
FY00-02: CE
BAMS-UAS&
Global HawkMaritime Demo
Raytheon
Component AdvancedDevelopment
2 Yr Risk Reduction Effort
Risk Management
020406080
100120140160180
Program Start Pre-Proposal Milestone B
LowMediumHigh
CAD
ProvisionsFor UAV
Integration
SystemArchitecture Alternative
ConceptStudies
SystemPerformance
RequirementsTo Meet
ORD/CDD
TotalOwnership
CostAnalysis
TechnologyReadiness
Assessment
OverallTest
Strategy
DetailedRisk
AnalysesCAD
ProvisionsFor UAV
Integration
SystemArchitecture Alternative
ConceptStudies
SystemPerformance
RequirementsTo Meet
ORD/CDD
TotalOwnership
CostAnalysis
TechnologyReadiness
Assessment
OverallTest
Strategy
DetailedRisk
Analyses
Key Lessons Learned
• Lack of adequate program maturity at MS B– Ill defined requirements– Lack of robust requirements management– Risky technical approach
• Failure to involve independent technical community at program initiation• Lack of early independent cost analysis (AIR-4.2) in POM/PR
– Ill defined CARD– O&S costs not well understood– Failure to budget for long lead items– Test program correction of deficiencies not adequately planned for
• Lack of technical insight & risk management process– Lack of automated SE tools– Inadequate use of metrics– Lack of appropriate technical expertise
• Government acting as integrator by default• Inadequate program technical staff and future staffing plans• Lack of horizontal/vertical SE integration (i.e., Battlespace Engineering,
Aviation/Ship integration)• Overly optimistic Acq/PM strategy/schedule• Comprehensive use of EVM and TPMs
Back-Up
DAU Program Start-up Workshop• Set the foundation for SDD success
• Many DoD programs struggle or fail due in part to:– Lack of common Vision and plan for success– Lack of supportive environment– Disagreements over program baseline
• Foster sense of trust, teaming, and honest discussions
• Produced useful Workshop products
• Educated Industry on Govt’s Warfighter Requirements
• Educated Government on Industry “Best Practices”Key Accomplishment: Taking the time to have Navy and Boeing Team Lead counterparts sit down with one-another in a relaxed forum to discuss broad
based and team focused challenges.
P-8A MMA Manufacturing Flow
Spirit AeroSystemsWichita, Kansas
MMA Fuselage
Boeing Commercial AirplanesRenton, Washington
MMA wings, empennage, aircraft assembly, engine installations
Boeing Integrated Defense Systems
Seattle, WashingtonMission systems/I&CO
Aircraft delivery
SDD and Production
P-8A MMA Acquisition Strategy
• Structured on an evolutionary systems replacement approach– Established sound program foundation based on an iterative requirements
definition process with warfighters and industry, thorough risk analysis of competing concepts, and detailed cost analysis of evolving concepts
– Provides a transformational product in minimal time to users while promoting evolutionary growth in capabilities through spiral development
• Defined in a capstone document that summarizes individual statutory and regulatory plans in order to communicate to leadership the total discipline approach to acquiring a system that recapitalizes the capabilities now provided by the P-3C
Activity Name1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
FY 2000 FY 2001 FY 2002 FY 2003 FY 2004 FY 2005 FY 2006 FY 2007 FY 2008 FY 2009 FY 2010 FY 2011
MMA
MS-0 CAD DR MS-B DRR MS-CIPROIPTReviews...
PMR-PEO(A)
PMR-Boeing
LRIP#1 LRIP#2Stage-IIAircraft & AP-2 & AP-3SDD AP-1CAD
Contract Awards.
Quantities 3 4 6 8CE CECAD CADSDD System Development & Demonstration
Reviews...
Deliveries PDRSFRIBRSRR CDR
Stage I 1 1 1Stage 2 2 1 1
T&E... T&E
P&D P&D P
Systems Engineering Process Rigor
Naval Systems Engineering Process
• Documented in Naval Systems Engineering Guide
• Uses Industry Standard EIA-632 as a framework, but incorporates elements of MIL-STD-499B, IEEE-1220, ISO15288
• Identifies 13 Processes and 33 Sub-processes for engineering a system
• Provides information regarding inputs, outputs, entry criteria, exit criteria, references, agents, tools and methods that Navy engineering teams may use to accomplish each Sub-process.
Technical Review Timeline
Component Advanced Development Process
CAIVIMPACTS
THREATDOCS
TEMPC4ISP
M&S PLAN
MAAD
CONOPS
OPSITSTACSITS
OTHERS…
IRD
DRAFTSYS
RQTS
ESOH
SOO
MISSION/ SYSTEMSEFFECTIVENESSANALYSIS
COST/PERFORMANCE TRADES
MMA SYSTEM
TRADE SPACE
AFFORDABILITYANALYSIS
DRAFT SYSTEMS
PERFORMANCESPEC
DRAFT
ORD
Integration of Requirements Refinement, Concept Definition, and Cost Analysis
P-8A MMA Requirements EvolutionConcept Exploration Component Advanced Development
INDUSTRY CONCEPT STUDIESANALYSIS OF ALTERNATIVES
DRAFT CAD RFP
CAD RFPCAD AWARDS
INDUSTRY COMMENTS
CAD PHASE MISSION/SYSTEMS EFFECTIVENESSANALYSIS AND COST/PERFORMANCE TRADES
Pre-MS Activities
1998 Requirements Analysis Study
1999 Technical and EconomicFeasibility Assessment
Validated ORD
•Block I•Block II•…•…•Block N
MNSFEB 00
IRD 1OCT 01
IRD 2DEC 01
IRD 3FEB 02
DRAFT ORDJUL 02
COST, TECHNICALSCHEDULE FACTORS
Road to Milestone B:• Source Selection for SDD• Concept Development and Risk analysis/reduction
• Requirements definition, refinement, & validation (Pre-MS B SRRs w/each competitor)
• Concept Cost Analysis
CAD Phase Takeaways
Effective integration of discrete activities, orchestrated to execute in a concurrent, effective manner
Requirementsloop
•SS Specifications
•SCDs•SRSs• ICDs• IDDs•Test plans
Functional model
Requirements analysis
Functionalanalysis
Allocation andsynthesis
•Trade Studies•Program and Technical Plans
Customerrequirementsdatabase
MMA PBS
CONOPSDRM
ORD/CDD
SDD Systems Engineering Process and Major Products
PBSS
Systems Analysis and Control Assessment and Balance of Technical Risk, Cost, and Schedule
Develop, Buy,Produce
•Product Specifications
•Product Drawings• ICDs• IDDs (design)•Design Documents •Verify Plans and
Procedures
Designloop
SRRSFRPDRCDR
Build anddev test loop
•Performance Specifications•Design Trades•Preliminary Product Specs•Preliminary Verification Plans
Legend:
Annex
RTS CSCI SRS
Annex
Annex AnnexAnnexAnnex
AnnexAnnex
Level 1 System Functional Baseline
Level 3 Product Baseline
Level 2 Allocated Baseline
P-8A MMA System Preliminary Design BaselineSpecification Tree (CI/CSCI) in DOORS
Comm SCDs(8)
SMS SCD
MCDS HW SCDs(12)
TOMSCSCI SRS
Mission System Segment Specification
Mission tng sys PIDS
TSSC Sys PIDS
Training System Segment Specification
Acous-tics
SCD
Radar/ IFF
SCDESM SCD
EWSP SCD
MADSCD
Sensors WTT CIDS
WLT CIDS
Com-puting CIDS
OFT CIDS
PTT CIDS
IAT CIDS
Facility reqts
TOFT CIDS
Logistics System Segment Specification
Pilot tng sys PIDS
TS to facility IRS
TS to TSSC IRS
External IRS
Transactional use case analysis
Productiondrawings
Productspecs
PhysicalHW
PhysicalSW
Facility reqtsdocument
External IDD
Core use case analysis
FunctionalDescriptionDocument
Annex AAnnex BAppendix BAppendix JAppendix RAppendix U
PBSS
ORD/CDD
EO/IR SCD
Aircraft System Segment Specification
Supportdocs
IFF inter SCD
Designdocs
Verif/testplans/proc
• Flt mgt cmtr sys/MCDU SW• HMS SW• Display elec unit SW• Enhanced digital flt cont SW• Stall mgt/yaw damper sys• Air data inertial ref sys• Enhanced ground proximity warning sys• Head-up display sys• MMA control panels• Nav IFF transponder• Nav GPS• RTP• FDIU• EGI• IFF transponder• GPS antenna sys
• Weapon pylon, fuselage• Weapon pylon, wing• Ejector, 14 in• Ejector, 30 in• Sonobuoy launching sys • Power distr panel
• Secondary power distr sys• Electrical power gen sys
1,240 requirements31 reqt changes 2.5%=
Requirements Volatility
• CDLS• V/UHF• ICS• BI• INMARSAT
• ACP• HF• OTCIXS• SAT SW unit
• CE-IOB• DVR• NSS• Black IOB• Ordnance panel• Color printer• Secure SW unit• Network accelerator
• FD DP• VIU• Ethernet SW• Time dist sys• LAN cont• SNS• Crew WS
SRRSFRPDR
CDRFuture input to DOORS
Legend:
Maint tng sys PIDS
Air-frame subsysreqts
Flt deck and avionicssubsys reqts
Interiorssubsys reqts
Utility subsystems reqts
Armamentsubsys reqts
Wiringsubsys reqts
Power and propulsionsubsys reqts
Key Processes
• Systems Engineering Plans and Process (SEP and SEMP)• Configuration Management Process• Technology Readiness Assessment (TRA) Process• Trade Study Process• Risk and Opportunity Management Process• Technical Performance Measures (TPMs) Process• Human Systems Integration Plan• Electromagnetic Environmental Effects (EEE) Plans• Contractor Logistics Support (CLS) Plan• System Security Plans• System Safety Plans• Interface Control and Interface Management Plans• Producibility• Quality System Plan
Technology Readiness Assessment
• Conducted during CAD– Independent assessment panel consisting of members from the Naval
Air Systems Command (NAVAIR), Office of Naval Research (ONR), and academia (John Hopkins University Applied Physics Laboratory (JHU-APL)).
• TRA identified four Critical Technology Elements (CTEs) through a comprehensive review of the MMA program work breakdown structure (WBS) reflecting the Boeing CAD phase configuration baseline prior to SDD source selection
1. Integrated Sonobuoy Launcher System2. Electronic Support Measures (ESM) system3. Data Fusion4. Acoustics Subsystem
• None of the P-8A CTE impact ability to meet program Key Performance Parameters (KPP)
Risk Management ProcessWho
ResponsibleFunction orIndividual
Input Output
LEGENDStart orEnd
Task A Connector QRQualityRecord
Decision
Major Process Tasks for: Risk ManagementMMA Program Management
AnyTeam
Member
BoeingCompanyPolicies &
Procedures
MMAProgram
Policies &Procedures
Beginning
Identify and SubmitRisk Candidates
EndingBoundary Task
DocumentsRisk
Closure
ReviewPlan
ReviewStatus of
Risk & Plan
RiskOwner
RiskMitigation
PlanAcceptable?
Continue withRisk
Plan?
Yes
No
Yes
No
Yes
No
ValidRisk?
RiskMitigated
?
Yes YesProgram-LevelRisk?
Team-LevelRisk
Program
Review Board(PRRB)
IPT
No
Process Owner:
Program
Review Board(PRRB)
or
Team RiskReview Board(as applicable)
Boundry Task
PromoteRisk?
YesIPTLeader
No
No
YesManaged
Risk?
No
WatchItem
END
END
Mitigation
Affordability
Risk
Risk
Control
ImplementPlan
Risk &
Plan HandlingOptions/
Mitigation and Fallback Plan, if necessary
Assess
Likelihood
Consequence
Risk
B
B
A
RiskRejected
RiskMitigated
CWIP
LEAN
Assign /Re-Assign
Owner
A
and
1
2
3
45
6
7
8
9
10
11
12
13
14
15 16
17
• Fully integrated RMB with Industry
• Definition and implementation of process
• Facilitated by Boeing IDE
Opportunity ManagementThe Sister of Risk
OpportunitiesHIGH (Gold) - Major benefit likely. Priority management attention required.
MEDIUM (Silver) - Some benefit. Additional management attention may be required.
LOW (Bronze) - Minimum benefit. Minimum oversightneeded to pursue opportunity.
OpportunitiesHIGH (Gold) - Major benefit likely. Priority management attention required.
MEDIUM (Silver) - Some benefit. Additional management attention may be required.
LOW (Bronze) - Minimum benefit. Minimum oversightneeded to pursue opportunity.
O P P O R T U N I T YO P P O R T U N I T Y
IDENTIFY OpportunityASSESS
• Likelihood & Consequence• 5x5 OpportunityAssessment Matrix
PLAN• Capture, Transfer, Ignore, or Pursue
the Opportunity• Establish Opportunity events,
Responsibilities and SchedulesCONTROL
• Monitor Actions, Correct Deviations,and Re-plan as Appropriate
• Promote or Demote Opportunity as Appropriate
COMMUNICATE• Populate Database, Keep it Current,
and Make it Accessible to All
O P P O R T U N I T YO P P O R T U N I T Y
IDENTIFY OpportunityASSESS
• Likelihood & Consequence• 5x5 OpportunityAssessment Matrix
PLAN• Capture, Transfer, Ignore, or Pursue
the Opportunity• Establish
Responsibilities and SchedulesCONTROL
• Monitor Actions, Correct Deviations,and Re-plan as Appropriate
• Promote or Demote Appropriate
COMMUNICATE• Populate Database, Keep it Current,
and Make it Accessible to All
Consequence1 2 3 4 5-1-2-3-4-5
1
2
3
4
5
Like
lihoo
d
Risks Opportunities
Consequence1 2 3 4 5-1-2-3-4-5
1
2
3
4
5
Like
lihoo
d
Risks Opportunities
Consequence1 2 3 4 5-1-2-3-4-5
1
2
3
4
5
Like
lihoo
d
Risks Opportunities
TPMs(Status as of 14Jul06)
Range
Alt
Interop
Ao
KPPs
ASW wt
nmi
1,135 1,200 1,265 1,330 1,395
A/C Operating Weight Klb
112,648 111,448 110,248 109,078 107,878
Aerodynamic Drag counts383.9 377.9 374.9 371.9 368.9 365.9 362.9 359.9
Operational Availability %
50 55 60 65 70 75 80 85 90
Electrical Power Util kVA
243 226 209 192 175 158 140 124 107
ECS Thermal Utilization kW
97 90 83 76 69
MCDS CPU Utilization(OMI) % of target
70 65 60 55 50 45 40 35 30
MCDS Lan Utilization % of target
55 50 45 40 35 28 21 14 7
MCDS Memory Utilization % of target
55 50 45 40 35 30 25 20 15
MCDS Storage Utilization % of target
120 100 90 40
EMI (cosite margin) counts
33 30 27 24 21 18 15 12 9
Operations & Support Costs normalized
1.10 1.0 .95 .90 .85 .80 .75 .70
Production Unit Cost 04 $ in Mil
1.06 1.03 1.0 .97 .94 .91 .88 .85 .82
Interoperability (# of PBSS IERs)9 24 39 54 69 84 99 114 129
Worst Case PBS Survivabili % Sur.
.96 .98 1.0 1.02 1.04 1.06 1.08 1.10 1.12
Vulnerability Av %
1.2 1.1 1 .9 .8 .7 .6 .5 .4
Fusion Track Accuracy Heading
1.2 1.1 1 .9 .8 .7 .6 .5 .4
C31SR Initial On Station Alt. Ft 15,000 25,000 30,000 35,000 45,000 55,000
ASW Weapon Loadout In work
80 60
Mission Perf./ Radius of Action
1,3561,300
108,445109,660
371372.6
77.5 80
151155
71.8 71.8
65 65
53 53
7783
.91 88
54 54
1.03 1.1
.52 .52
under review
36,64336,402
19 19
11 IOC = 0
7 / 7
SRR Lessons Learned
• Joint team attitude to address issues openly and overtly and proactively run actions to ground as a high priority during and after review will continue to serve program well. Critique acceptance and addressal will assist in successful execution and maintains credibility
• System Specification had moderate instability post-SRR due to Segment SRRs and the decomposition and allocation of requirements as the functional baseline was established (expected in the SE iterative loop, level of System Spec stability a good indicator of solid CAD phase and SRR)
• A robust requirements management tool (i.e., DOORS) with clear, clean links from top-level (CDD/Performance) requirements down through all levels of the specification tree to detailed requirements (at PDR/CDR) is essential
SFR Lessons Learned
• Derived Mission Functions and associated architectural flow needs to be kept alive under change control as a living part of the design baseline
• Functions and associated allocations must be used by product teams to identify and reconcile gaps in requirements
• Product team System Use Cases and associated functions must be linked to Transactional Mission Use Cases to identify and reconcile functional gaps (Software functional areas in particular)
• Trade Studies and Design Changes must consider the specification tree from top to bottom including the linked functions (DOORS extracts used at CCBs)
• SFR preparation improved intra and cross team communication• SFR preparation led to customer ‘buy in’ on technical approach and
maturity• SFR preparation led to an exponential increase in the number of
System Level Requirements experts, and Mission Usage experts
PDR Lessons Learned
• EVM implementation and team utilization is a continual study and refinement process to ensure proper CAM focus and Team Lead expectations are understood
• IDE is a productivity multiplier for team communications and insight into program status
• Value of design reviews is the build up and incremental review preparation process leading to the early identification of risks and issues to program execution
• Government teams expend considerable energy working processes and communications with the Prime contractor; the same needs to occur between the Prime and subcontractors
• Efficient budget execution is the best defense for budget development and prioritization
A Quality Team
Prime ContractorSub Contractors
A Rock Solid FoundationOf Respect and Trust
Firmly Supporting an EnvironmentOf Common Goals
Transition into SDD
• Contract award – 14 June 2004– Required completion of Source Selection prior to Milestone B– Approval from MDA to enter SDD through the Milestone B DAB
• Approval of Acquisition Strategy• Determination of fully funded program based on CAIG assessment• Approval of Acquisition Program Baseline
• Teaming with Industry – Program Start-up Workshop
• Management by Metrics– Risk Management Process– Opportunity Management– Technical Performance Measurement – Earned Value Management
Program Best Practicesfor SDD
Earned Value Management Reporting
ControlAccountSchedulesTier IV
Earned Value Management Reporting Via Tier IV IMS
Product ScheduleTier III
ProgramElement ScheduleTier II
ProgramMaster ScheduleTier I
IntegratedMaster Plan(IMP)
CAMS CAMS CAMS
• Program summary• Major milestones
• Major program elements• Customer and ACA
interfaces
• Cross-functional integrated baseline
• Key interface milestones
• Detailed, measurable tasks
• Vertically linked: IMP, IPTs
• Horizontally linked: account
CAMS
IMS from contract award through PDR:20,141 tasks resource loaded (labor-hours)
Integrated Baseline Review
Purpose – Achieve mutual understanding of baseline plan and relationship to underlying EVMS and processes during contract execution
Objectives – Evaluate the performance measurement baseline to ensure:
• Entire technical scope of work captured• Sufficient contract budget and schedule• Budget properly allocated at the right level• Resources adequately assigned• Proper implementation of management processes
Gain insight into cost and schedule risk areas associated with contract Develop confidence in the program’s operating plans