Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
OXNARD SCHOOL DISTRICT 1051 SOUTH A STREET OXNARD, CA 93030
ADDENDUM NO. 1
Project: OXNARD SCHOOL DISTRICT HVAC AND CONTROLS DESIGN-BUILD SERVICES FOR (5) SCHOOLS – PHASE 2 RFQ/RFP No. 17-04 Date: March 8, 2018
To any and all concerned parties: This addendum adds to or modifies the contract documents for the above project. This addendum shall supersede all previously issued specifications, addenda and any other written or verbal direction. The modifications within this addendum shall be made part of the contract documents and shall be subject to all applicable requirements thereto:
CHANGES TO THE BID:
Item No. 1.1 Specification Reference: Addendum No. 1 Description: Responses to RFI/Questions
Question #1: Contractors were unclear on whether they are replacing or re‐using existing T‐stat Response #1: Contractors shall use reconnect to existing control strategy. Question #2: Has the existing pipe insulation been tested for the presence of asbestos. Response #2: Asbestos may have been identified in exterior stucco. Reference new Attachment E. Note that OSD will be independently verifying asbestos location included with SOW prior to summer work start. If any abatement is needed, OSD will independently work to abate asbestos prior to scheduled work start. Question #3: Scope of Work Clarification Response #3: Firms to submit proposals that include heating furnace replacement, cooling A-coil, and drain pan replacement for all units. Contractor shall furnish and install ½” brass couplings for A-coils and isolation valves. Question #4: Scope calls out “New gas lines”. Clarify to what extents it is being replaced. Response #4: Flexible gas lines shall be replaced to the point of the connection. No rigid gas piping shall be replaced. Re-use existing rigid male coupling unless deemed necessary by Contractor during pre-construction planning. Male/female coupling location shall be readily accessible for maintenance. Flexible gas lines shall not be kinked to force gas line fit. Contractor shall check for gas leaks at all couplings and threads.
Question #5: Outside air intake louver at enclosure is low and collects debris creating blockage. Should these be relocated higher up?
Response #5: No, intake louver will not be relocated. Prevailing Title 24 outside air and economizer requirements apply. Question #6: Building 7 is less than 10 years old. Is this part of the scope really necessary? Response #6: Building 7, Sterling M/N: E3M unit is NOT included in the scope of work.
Question #7: Equipment schedule is missing from scope of work Response #7: Reference updated [RFQ-RFP No. 17-04 HVAC - Attachment C - Pricing Summary – V2]
Item No. 1.2 Description: Update to Attachment A, Scope of Work, Controls sections Delete Text: “Reuse existing thermostats” Insert Text: “Reuse existing thermostats and reconnect all new CRVs to existing controls.”
Item No. 1.3 Description: Replace Attachment C to account for scope of work clarifications Delete Document: [Attachment C - Equipment List and Pricing Summary] Insert Document: [Attachment C - Equipment List and Pricing Summary V2]
Item No. 1.4 Description: Insert 2016 AHERA Asbestos Report Insert Document: [Attachment E – AHERA Asbestos Report]
Item No. 1.5 Description: Insert HVAC Project Schedule Insert Document: [Attachment F – HVAC RFQ-RFP No. 17-04 Project Schedule]
END OF DOCUMENT
Attachment E
AHERA 3-YEARASBESTOS REINSPECTION REPORT
Oxnard Elementary School District
Prepared for:
Ms. Norma MaganaOxnard Elementary School District
1051 South A StreetOxnard, California 93030
TC Project #: 103037
Prepared by:
Tabbara Corporation350 N. Lantana Street, Suite 224
Camarillo, CA 93010
September 16, 2016
Limitations Statement
Tabbara Corporation (TC) has prepared the enclosed documentation based on a combination ofprevious asbestos inspection data prepared and provided by others, along with limited fieldobservations and interviews with Oxnard Elementary School District staff. TC makes norepresentations regarding the accuracy of the enclosed data and will not be held responsible forany incidental or consequential loss or punitive damages including but not limited to, loss ofprofits or revenues, loss of use of a facility or land, delay in construction or action of regulatoryagencies. The collected data and recommendations are for the exclusive use of the client for thesite described in this report.
AHERA Re-inspection ReportOxnard Elementary School District
TABLE OF CONTENTS
Section 1 General Information
Section 2 Overview and Objectives
Section 3 AHERA Re-Inspection
Section 4Site Specific ACM Information(Current Inventory of ACM)
Section 5 Response Actions
Section 6 Glossary of Terms
Section 7 Inspector information
Section 8 ABCs of Asbestos in Schools
SECTION 1
GENERAL INFORMATION
A. Designated Person Responsibilities:
The AHERA regulation maintains that the overall responsibility for the Asbestos Operationsand Maintenance Program shall be the Designated Person, whose duties are as follows:
1. Oversees activities of Asbestos Coordinators, consultants, Contractors and approvesasbestos removal and replacement projects scope of work.
2. Direct supervision and implementation of the Operations and Maintenance Programincluding:
a. Yearly notification of Management Plan review to building staff and legal guardians,b. Six month periodic surveillance and three year re-inspections recordkeeping,c. Training of custodial staff (minimum 2 hour asbestos awareness training),d. Labeling of ACBMs within mechanical areas,e. Direct responsibility for recordkeeping system regarding training, abatement projects,
air monitoring, renovations that will impact the ACBMs.
B. EPA Category Codes for ACBM:
EPA has formulated a seven (7) category numerical assessment code depending on the typeand condition of ACBM as follows:
1. Damaged or significantly damaged thermal system insulation ACM.2. Damaged friable surfacing ACM.3. Significantly damaged friable surfacing ACM.4. Damaged or significantly damaged friable miscellaneous ACM.5. ACBM with potential for damage.6. ACBM with potential for significant damage.7. Other/any remaining friable ACBM or friable suspected ACBM.
Each ACBM re-inspected in each school is categorized within one of these assessment codes.
ACM Application Types:
Asbestos Containing Building Materials are divided into the following application types:
Thermal system insulation (TSI): Insulation applied to mechanical heat and coolingsystems, including, pipes, boilers, flue breechings, ducts, tanks and fittings.
Surfacing Materials: Material that is spray-applied or trowelled applied to walls, ceilingsor structural components (i.e. plasters, acoustical finishes and fireproofing).
Miscellaneous Materials: All other asbestos materials, including floor tiles, ceiling tiles,transite board and cloth materials.
C. ACBM Assessment Criteria:
1. Damaged ACBM: That material which has deterioration, delamination, water damage,lacks cohesion, is blistered, crumbling, gouged, marred heavily, abraded, or in any wayhas lost its structural integrity over more than 1% but less than 10 % of the surface area ifthe damage is evenly distributed or less than 25%, if the damage is localized in one areaof the homogeneous area. Categorized as fair condition.
2. Significantly Damaged ACBM: That material which has deterioration, delamination,water damage, lacks cohesion, is blistered, crumbling, gouged, marred heavily, abraded,or in any way has lost its structural integrity over at least 10% of the surface area if thedamage is evenly distributed or at least 25% if the damaged is localized. Categorized aspoor condition.
3. Good Condition ACBM: ACBM with no visible damage or deterioration in less than onepercent of the material and/or coverings.
4. ACBM with potential for damage: Pertains to circumstances in which:
a. Friable ACBM is in an area regularly used by building occupants, includingmaintenance workers, currently in intact (good) condition.
b. There are indications that there is a reasonable likelihood that the material or itscovering will become damaged, deteriorated or delaminated due to factors such aschanges in building use, changes in O&M practices, changes in occupancy orrecurrent damage.
Note: All ACBM in good condition is considered to have a potential for damage.
5. ACBM with potential for significant damage: Pertains to circumstances in which:
a. Friable ACBM is in an area regularly used by building occupants, includingmaintenance.
b. Indications show that there is a reasonable likelihood that the material or its coveringwill become damaged, deteriorated or delaminated due to factors such as changes inbuilding use, changes in O&M practices, and changes in occupancy or recurrentdamage.
c. The material is subject to major or continuing disturbance, due to factors including,but not limited to accessibility or under certain circumstances, vibration or airerosion.
D. Recommended Response Actions:
During the re-inspection, Tabbara Corporation did not identify any damaged ACBM. Newlyidentified and assumed ACBMs during the 2016 re-inspections should be sampled andanalyzed for their asbestos content. Materials analyzed to be negative for asbestos could bedeleted from the asbestos inventory for that school.
Damaged materials in the schools should be removed or repaired in order to insure theschools are in compliance with the AHERA regulation. Damaged ACBMs with over threelinear or three square feet listed in the reports should be repaired or removed by a licensedabatement company and final clearance air testing performed in accordance with the AHERAregulations.
AHERA regulations state that the response actions chosen for other than small scale/shortduration repairs (less than 3 square or linear feet), must be designed and conducted bypersons accredited to design and conduct response actions.
Areas containing damaged and significantly damaged thermal system insulation withinmechanical rooms including crawl spaces, boiler rooms, restroom pipe chases and aboveceilings should be accessed only by 16-hour asbestos-trained personnel. ACBMs within thesemechanical areas should be labeled with asbestos warning labels. Proper precautions, workpractices and personal protective equipment should be utilized to perform work within theserestricted areas. At a minimum, each member of the custodial/maintenance staff should have2 hour asbestos awareness training.
Each material listed as ACBM with Potential for Damage (good condition) should bemonitored for any changes in condition during the six-month periodic surveillance. Thesematerials are currently intact and in good condition and should be included in the operationand maintenance plan protocols. No response actions are required at this time. If thesematerials are to be impacted by renovation work, the asbestos material should be removed bya licensed contractor.
SECTION 2
OVERVIEW AND OBJECTIVES
This Re-inspection Report for asbestos management has been prepared by Tabbara Corporation(TC) for Oxnard Elementary School District for the following locations: Chavez ElementarySchool, Curren Elementary School, Driffill Elementary School, Elm Street Elementary School,Harrington Elementary School, Kamala Elementary School, Lemonwood Elementary School,Marina West Elementary School, McKinna Elementary School, Rose Avenue ElementarySchool, Sierra Linda Elementary School, Fremont Middle School, and Haydock Middle School.The purpose of this plan is to describe a program for controlling exposure to asbestos in campusbuildings. The principal elements of this program involve requirements and responsibilities forsurveys, employee notifications, proper work procedures for activities that have the potential todisturb ACM, and proper disposal of asbestos wastes.
Asbestos-containing materials (ACM) have been used widely in the construction industry. Whilethe use of ACM in new building systems has ceased for most major applications, the presence ofACM in older building systems is still widespread. At the above mentioned locations, assumedACM that were observed are: Acoustic ceiling panels, 12" x 12" acoustic ceiling and walltiles & associated mastic, plaster, drywall, joint compound, padded panel mastic, mirrormastic, transite panels, wainscot & associated mastic, baseboard & associated mastic,resilient floor tile & associated mastic, vinyl sheet flooring & associated mastic, resilientsheet flooring & associated mastic, mastic associated with carpet, mastic associated withhardwood flooring, epoxy flooring, window putty, spray applied fire proofing, and stucco.In most cases, these listed ACM do not pose a health hazard if left undisturbed with exception ofthe following schools: McKinna Elementary School - Bldg. 9 Room 901: 12" x 12" GreyResilient Floor Tile & Associated Mastic. Fremont Middle School - PE Bldg. PE Offices &Gym: 9" x 9" Brown Resilient Floor Tile & Associated Mastic. These materials should berepaired or removed by trained personnel to prevent further damage. Furthermore, activities thathave the potential to disturb ACM must be carefully managed to prevent fibers from becomingairborne and creating an inhalation hazard.
AHERA requires that each Local Education Agency (LEA) perform inspections to identify ACMin each of the school under its authority; develop, implement and update asbestos managementplans; take appropriate response actions; safely maintain ACBM; and comply with AHERA’srecord keeping requirements.
Under §763.84 of the AHERA Rule, the LEA have the following responsibilities:
• Ensure that the activities of any persons, who perform inspections, reinspections, andperiodic surveillance, develop and update management plans, develop and implementresponse actions, and conduct operations and maintenance activities that are incompliance with all of the AHERA requirements.
• Ensure that all custodial and maintenance workers are properly trained.• Ensure that workers and building occupants are notified at least annually about activities
related to ACBM
• Ensure that short-term workers who may come in contact with asbestos in the school areprovided with the locations of all ACBM and suspected or assumed ACBM.
• Ensure that warning labels are properly posted.• Ensure that management plans are available for inspection.• Appoint a designated person to ensure proper implementation of the AHERA
requirements.• Ensure that the designated person receives adequate training to perform duties assigned• Consider whether any conflict of interest may arise among personnel undertaking
activities related to the ACBM in the school.
Sections 763.85-763.99 of the AHERA Rule detail the specific responsibilities of the LEA.These responsibilities are listed below:
• Inspections: An accredited inspector must conduct each school building inspection underthe authority of the LEA. This involves a visual inspection of all buildings for friable andnon-friable ACBM, sampling such materials, and having samples analyzed by anaccredited laboratory and/or in accordance with AHERA regulations.
• Reinspections: An accredited inspector must conduct a reinspection of all friable andnon-friable ACBM in each school building at least once every three years.
• Assessment: For each inspection and reinspection, an accredited inspector must provide awritten assessment of all friable ACBM in the school building.
• Management Plan; Each LEA must complete an asbestos management plan for eachschool under its authority. An accredited management planner must prepare themanagement plan based on the results of the inspection. In the management plan, themanagement planner recommends appropriate response actions, prepares cost estimateson the response actions, and schedules the response actions. The management plan mustbe updated on a timely basis.
• Response Actions: Based on the recommendations of the management planner, the LEAmust select the appropriate response actions consistent with the assessment of theACBM. The designated person must see to it that the response actions are carried out in atimely manner and in compliance with AHERA requirements.
• Operations and Maintenance: The LEA must implement an operations and maintenanceprogram whenever any friable ACBM is present in the building under its authority.Where material identified as non-friable ACBM is about to become friable as a result ofactivities performed in the building, it must be treated as friable and thus must also besubject to an O&M program.
• Training: AHERA requires that building inspectors, management planners, projectdesigners, contractors/supervisors, and asbestos workers be accredited before they canperform asbestos-related activities.
• Notification: The LEA must issue the following notifications regarding asbestosidentified in its schools.
o An annual notice to all workers and building occupants, or their legal guardians, of allinspections, reinspections, and activities being conducted to control asbestosexposure, including periodic surveillance and asbestos removal, that are planned or inprogress.
o An annual written notice informing parent, teacher and employee organizations of theavailability of the management plan for their review.
o A notice, to short-term workers (e.g., telephone repair workers, utility workers, orexterminators) who may become in contact with asbestos in a school, identifying thelocation of ACBM in the building
• Periodic Surveillance: The LEA must conduct periodic surveillance in each buildingunder its authority at least once every six months after a management plan is in effect.
• Record keeping: Records involving the inspection of and response to ACBM must bekept in a centralized location in the administrative office of both the school and the LEA.The following records must be kept:
• Descriptions of preventive measures and response actions taken for friable and non-friable ACBM.
o Sampling Informationo Periodic Surveillance informationo Training Informationo Information on initial and additional cleaning performed.o Information on operations and maintenance activities, including information on any
maintenance activities disturbing friable ACBM.o Information on any fiber-release episodes.
• Warning Labels: The LEA must attach a warning label immediately adjacent to anyfriable or non-friable ACBM located in routine maintenance areas (such as boiler rooms)at each school building.
SECTION 3
AHERA REINSPECTION
At the client’s request, TC performed a mandatory AHERA 3-year Reinspection of knownACBMs at the following subject sites between July 11 and 14, 2016:
• Chavez Elementary School• Curren Elementary School• Driffill Elementary School• Elm Street Elementary School• Harrington Elementary School• Kamala Elementary School• Lemonwood Elementary School• Marina West Elementary School• McKinna Elementary School• Rose Avenue Elementary School• Sierra Linda Elementary School• Fremont Middle School• Haydock Middle School
Previous "AHERA Reinspections" for all the schools were conducted in August 2013 byENCORP.
This report contains the results of our 3-year reinspection. All functional areas were surveyed inaccordance with EPA Regulation 40 CFR Part 763, Section 763.85.
SECTION 4
SITE SPECIFIC ACM INFORMATION
Chavez Elementary School301 North Marquita Street
Oxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Chavez Elementary School Inspection Date: 07/11/2016
Page 1 of 4
During an inspection performed on July 11, 2016 TC noted that Chavez Elementary School contained the following asbestoscontaining building materials (ACBM):
Main Buildings: 1ST & 2ND Floor
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ PinholeAcoustical Ceiling
Panel
All Classrooms On 1St
& 2ND Floor, MainOffice Area,Throughout
Approximately33,200 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
84,000 SFNon-Friable /
FriableGood Assumed
12”x12” Cream / MultiColored Resilient Floor
Tile & Mastic
All Classrooms On 1St
& 2ND Floor, MainOffice Area,Throughout
Approximately41,600 SF
Non-Friable Good Assumed
4” Brown BaseboardMastic
Main Office, Teacher’sWorkroom, Room 224
Approximately540 LF
Non-Friable Good Assumed
2’x2’ Rough AcousticalCeiling Panel
1St Floor Hallway, 2Nd
Floor Hallway, StairsLanding
Approximately8,400 SF
Friable Good Assumed
4” Black BaseboardMastic
1St Floor Hallway, 2Nd
Floor Hallway, StairsLanding
Approximately1,620 LF
Non-Friable Good Assumed
4” Green BaseboardMastic
Kindergarten, AllClassrooms On 1St &
2ND Floor
Approximately4,800 LF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Chavez Elementary School Inspection Date: 07/11/2016
Page 2 of 4
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Exterior Stucco ExteriorApproximately
28,500 SFNon-Friable Good Assumed
Sprayed OnFireproofing Insulation
1st / 2nd Floor AboveDrop CeilingThroughout
Approximately41,600 SF
Friable Good Assumed
Cafeteria Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Random HolePinhole Acoustical
Ceiling Tile & Mastic
Cafeteria, KitchenOffice
Approximately3,780 SF
Friable Good Assumed
Plaster ThroughoutApproximately
10,500 SFFriable Good Assumed
12”x12” Grey SpeckledResilient Floor Tile &
Mastic
Cafeteria, KitchenOffice, Stage Entrance
Approximately3,780 SF
Non-Friable Good Assumed
4” Black BaseboardMastic
Kitchen Office, StageEntrance
Approximately120 LF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
8,000 SFNon-Friable Good Assumed
Window Putty ExteriorApproximately
660 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Chavez Elementary School Inspection Date: 07/11/2016
Page 3 of 4
Building 3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Random HolePinhole Acoustical
Ceiling Tile & MasticRooms 301-313
Approximately6,500 SF
Friable Good Assumed
Plaster ThroughoutApproximately
7,800 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 301-313Approximately
6,500 SFNon-Friable Good Assumed
6” Blue BaseboardMastic
ThroughoutApproximately
842 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,800 SFNon-Friable Good Assumed
Building 4: (Rooms 401, Restrooms, 402)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panels
Rooms 401 & 402Approximately
1,816 SFFriable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
3,500 SFNon-Friable /
FriableGood Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 301-313Approximately
2,016 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Chavez Elementary School Inspection Date: 07/11/2016
Page 4 of 4
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
6” Blue BaseboardMastic
ThroughoutApproximately
280 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,500 SFNon-Friable Good Assumed
Building 5: Storage
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
ThroughoutApproximately
400 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
350 SFNon-Friable Good Assumed
Curren Elementary School1101 North F StreetOxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 1 of 7
During an inspection performed on July 11, 2016 TC noted that Curren Elementary School contained the following asbestoscontaining building materials (ACBM):
Administration Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ Random HoleAcoustical Ceiling Tile
& Mastic
Administration Office,Rooms 105, 106, 107,
110, Health Office
Approximately1,500 SF
Friable Good Assumed
Plaster ThroughoutApproximately
1,800 SFNon-Friable Good Assumed
12”x12” BeigeResilient Floor Tile &
Mastic
Administration Office,Rooms 105, 106, 107,
110, Health Office,Work Room
Approximately1,500 SF
Non-Friable Good Assumed
12”x12” BrownResilient Floor Tile &
MasticHealth Office Restroom
Approximately25 SF
Non-Friable Good Assumed
6” Black BaseboardMastic
ThroughoutApproximately
140 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,600 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 2 of 7
Buildings: Cafeteria, Kitchen, Library
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
PanelCafeteria & Library
Approximately4,550 SF
Friable Good Assumed
Plaster ThroughoutApproximately
6,700 SFNon-Friable Good Assumed
12”x12” BeigeResilient Floor Tile &
MasticCafeteria
Approximately3,200 SF
Non-Friable Good Assumed
12”x12” GreenResilient Floor Tile &
MasticCafeteria
Approximately50 SF
Non-Friable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
KitchenApproximately
400 SFNon-Friable Good Assumed
2’x4’ DrywallAcoustical Ceiling
PanelKitchen
Approximately350 SF
Friable Good Assumed
6” Black BaseboardMastic
ThroughoutApproximately
620 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
5,600 SFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
LibraryApproximately
1,350 SFNon-Friable Good Assumed
4’x4’ Transite Panels Exterior LibraryApproximately
80 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 3 of 7
Building #3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
PanelRooms 301-304
Approximately3,680 SF
Friable Good Assumed
Plaster ThroughoutApproximately
3,800 SFNon-Friable Good Assumed
12”x12” Blue/ DarkBlue Resilient Floor
Tile & MasticRooms 301-304
Approximately3,680 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
ThroughoutApproximately
560 LFNon-Friable Good Assumed
Exterior Stucco Exterior / OverhangApproximately
5,500 SFNon-Friable Good Assumed
Building #4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
PanelRooms 401-404
Approximately3,680 SF
Friable Good Assumed
Plaster ThroughoutApproximately
3,800 SFNon-Friable Good Assumed
12”x12” Blue/ DarkBlue Resilient Floor
Tile & MasticRooms 401-404
Approximately4,600 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 4 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Blue BaseboardMastic
ThroughoutApproximately
700 LFNon-Friable Good Assumed
Exterior Stucco Exterior / OverhangApproximately
5,500 SFNon-Friable Good Assumed
Building #5:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
PanelRooms 501-505
Approximately4,600 SF
Friable Good Assumed
Plaster ThroughoutApproximately
3,800 SFNon-Friable Good Assumed
12”x12” Blue/ DarkBlue Resilient Floor
Tile & MasticRooms 501-505
Approximately4,600 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
ThroughoutApproximately
700 LFNon-Friable Good Assumed
Exterior Stucco Exterior / OverhangApproximately
5,500 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 5 of 7
Building #6:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ PinholeAcoustical Ceiling
PanelRooms 601-609
Approximately7,200 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
12,500 SFNon-Friable /
FriableGood Assumed
Plaster Custodial, StorageApproximately
850 SFNon-Friable Good Assumed
12”x12” Blue/ DarkBlue Resilient Floor
Tile & MasticRooms 602-609
Approximately6,500 SF
Non-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 601, 604, 605Approximately
400 SFNon-Friable Good Assumed
4’x4’ Transite Panels ExteriorApproximately
192 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,200 SFNon-Friable Good Assumed
Building #7:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ PinholeAcoustical Ceiling
Panel
1ST & 2ND FloorThroughout
Approximately20,000 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 6 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
1ST & 2ND FloorThroughout
Approximately32,500 SF
Non-Friable /Friable
Good Assumed
12”x12” CreamResilient Floor Tile &
Mastic
1ST & 2ND Floor Rooms& Hallways
Approximately20,000 SF
Non-Friable Good Assumed
4” Brown BaseboardMastic
1ST & 2ND FloorHallways, Work RoomsBetween Classrooms,
Storage, Teachers WorkRoom
Approximately1,200 LF
Non-Friable Good Assumed
4” Green BaseboardMastic
1St & 2ND ClassroomsApproximately
2,500 LFNon-Friable Good Assumed
Sprayed OnFireproofing Insulation
Above Dropped Ceiling/ Throughout
Approximately20,000 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
25,000 SFNon-Friable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
Storage 128Approximately
200 SFNon-Friable Good Assumed
Building #8:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
Between Wood PanelsRooms 801 & 802
Approximately2,400 SF
Non-Friable /Friable
Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Curren Elementary School Inspection Date: 07/11/2016
Page 7 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Grey SpeckledResilient Floor Tile &
MasticRooms 801 & 802
Approximately1,800 SF
Non-Friable Good Assumed
Grey Resilient SheetFlooring & Mastic
Room 801 RestroomApproximately
35 SFFriable Good Assumed
Wainscoat Mastic Room 801 RestroomApproximately
120 SFNon-Friable Good Assumed
4” Brown BaseboardMastic
ThroughoutApproximately
240 LFNon-Friable Good Assumed
Driffill Elementary School910 South E StreetOxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 1 of 9
During an inspection performed on July 11, 2016 TC noted that Driffill Elementary School contained the following asbestoscontaining building materials (ACBM):
Main Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
1ST & 2ND FloorApproximately
25,500 SFFriable Good Assumed
2’x4’ AcousticalCeiling Panel
1ST & 2ND FloorApproximately
9,800 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
1ST & 2ND FloorApproximately
1,200 SFNon-Friable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
1ST & 2ND FloorApproximately
20,550 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
1ST & 2ND FloorApproximately
12,275 SFNon-Friable Good Assumed
4” Baseboard Mastic 1ST & 2ND FloorApproximately
1,925 LFNon-Friable Good Assumed
Drywall & JointCompound
1ST & 2ND FloorApproximately
69,600 SFNon- Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
17,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 2 of 9
Cafeteria Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Tile & Mastic
CafeteriaApproximately
3,600 SFFriable Good Assumed
12”x12” YellowResilient Floor Tile &
MasticCafeteria
Approximately2,465 SF
Non-Friable Good Assumed
12”x12” Red ResilientFloor Tile & Mastic
CafeteriaApproximately
800 SFNon-Friable Good Assumed
Drywall & JointCompound
CafeteriaApproximately
4,800 SFNon- Friable /
FriableGood Assumed
6” Black BaseboardMastic
CafeteriaApproximately
50 LFNon-Friable Good Assumed
4” Black BaseboardMastic
OfficeApproximately
15 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
OfficeApproximately
220 SFNon-Friable Good Assumed
Interior Plaster KitchenApproximately
3,700 SFNon-Friable Good Assumed
Red Flooring Material KitchenApproximately
1,100 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
5,000 SFNon-Friable Good Assumed
Window Putty ExteriorApproximately
10 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 3 of 9
Building: #6 Rooms 601-604
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 601-604Approximately
3,500 SFFriable Good Assumed
12”x12” Light BlueResilient Floor Tile &
MasticRooms 601-604
Approximately2,300 SF
Non-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 601-604Approximately
1,400 SFNon-Friable Good Assumed
Drywall & JointCompound
Rooms 601-604,Teachers Lounge,
Restrooms
Approximately5,000 SF
Non- Friable /Friable
Good Assumed
4” Blue/GreenBaseboard Mastic
Rooms 601-604Approximately
120 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,000 SFNon-Friable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
Teachers LoungeApproximately
140 SFNon-Friable Good Assumed
4” Grey BaseboardMastic
Teachers LoungeApproximately
20 LFNon-Friable Good Assumed
Interior Plaster ThroughoutApproximately
700 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 4 of 9
Building: #7 Rooms 701-704
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 701-704Approximately
3,500 SFFriable Good Assumed
12”x12” Light BlueResilient Floor Tile &
MasticRooms 701-704
Approximately2,300 SF
Non-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 701-704Approximately
1,400 SFNon-Friable Good Assumed
Drywall & JointCompound
Rooms 701-704,Restrooms
Approximately5,000 SF
Non- Friable /Friable
Good Assumed
4” Blue/GreenBaseboard Mastic
Rooms 701-704Approximately
120 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,000 SFNon-Friable Good Assumed
Interior Plaster ThroughoutApproximately
700 SFNon-Friable Good Assumed
Building: Kindergarten
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 901& 902Approximately
1,720 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 5 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Light BlueResilient Floor Tile &
MasticRooms 901& 902
Approximately2,800 SF
Non-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 901& 902
Approximately270 SF
Non-Friable Good Assumed
Drywall & JointCompound
Rooms 901& 902Approximately
3,900 SFNon- Friable /
FriableGood Assumed
4” Blue/GreenBaseboard Mastic
Rooms 901& 902Approximately
100 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
3,500 SFNon-Friable Good Assumed
Building: Portables 1207-1210
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 1207-1210Approximately
3,600 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 1207 & 1210Approximately
1,175 SFNon-Friable Good Assumed
12”x12” Light GreyResilient Floor Tile &
MasticRooms 1208 & 1209
Approximately1,800 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 6 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
Rooms 1207-1210Approximately
4,500 SFNon- Friable /
FriableGood Assumed
4” Blue BaseboardMastic
Rooms 1207 & 1210Approximately
60 LFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 1207 & 1210Approximately
50 SFNon-Friable Good Assumed
Building: Portables 1301, 1401, 1402
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Room 1301Approximately
2,700 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 1301, 1402Approximately
1,620 SFNon-Friable Good Assumed
12”x12” Light GreyResilient Floor Tile &
MasticRooms 1401, 1402
Approximately1,100 SF
Non-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
3,600 SFNon- Friable /
FriableGood Assumed
12”x12” White/BlackResilient Floor Tile &
MasticRooms 1401, 1402
Approximately900 SF
Non-Friable Good Assumed
4” Black BaseboardMastic
Room 1401Approximately
35 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 7 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Brown BaseboardMastic
Room 1401Approximately
30 LFNon-Friable Good Assumed
Wainscot Mastic Room 1402 RestroomsApproximately
225 SFNon-Friable Good Assumed
Green Vinyl SheetFlooring & Mastic
Room 1402 RestroomsApproximately
50 SFNon-Friable Good Assumed
4” Grey BaseboardMastic
Room 1402Approximately
30 LFNon-Friable Good Assumed
Building: Portables 1501-1504
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 1501-1504Approximately
3,600 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 1501-1504Approximately
3,575 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Room 1504Approximately
25 SFNon-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
4,500 SFNon- Friable /
FriableGood Assumed
4” Brown BaseboardMastic
Rooms 1502 & 1503Approximately
60 LFNon-Friable Good Assumed
4” Blue/GreenBaseboard Mastic
Room 1501Approximately
30 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 8 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Blue BaseboardMastic
Room 1504Approximately
30 LFNon-Friable Good Assumed
Building: Portables 1500 Restroom Block
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 1507-1510Approximately
460 SFFriable Good Assumed
Drywall & JointCompound
Rooms 1507-1510Approximately
1,200 SFNon- Friable /
FriableGood Assumed
Wainscot Mastic Rooms 1507-1510Approximately
600 SFNon-Friable Good Assumed
Building: Out Of Service Portable (South Of 1200 Block Portable)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
West Unit & East UnitApproximately
1,800 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
West Unit & East UnitApproximately
1,750 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
West Unit & East UnitApproximately
50 SFNon-Friable Good Assumed
Drywall & JointCompound
West Unit & East UnitApproximately
2,300 SFNon- Friable /
FriableGood Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Driffill Elementary School Inspection Date: 07/11/2016
Page 9 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Blue BaseboardMastic
West Unit & East UnitApproximately
60 LFNon-Friable Good Assumed
12”x12” Light GreyResilient Floor Tile &Mastic (Under Carpet
Mastic)
West UnitApproximately
872 SFNon-Friable Good Assumed
Elm Street Elementary School450 E. Elm Street
Oxnard, CA 93033
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Elm Street Elementary School Inspection Date: 07/11/2016
Page 1 of 5
During an inspection performed on July 11, 2016 TC noted that Elm Street Elementary School contained the following asbestoscontaining building materials (ACBM):
Administration:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
1,267 SFFriable Good Assumed
12" x 12" AcousticCeiling Tile &
Associated MasticThroughout
Approximately1,267 SF
Friable Good Assumed
4" Baseboard &Associated Mastic
ThroughoutApproximately
225 LFNon-Friable Good Assumed
12" x 12" Light BrownResilient Floor Tile &
Associated MasticThroughout
Approximately1,270 SF
Non-Friable Good Assumed
Yellow Vinyl SheetFlooring & Associated
MasticRestrooms
Approximately90 SF
Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
2,400 SFFriable Good Assumed
100 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 101 - 103, 105-110, & 112 - 114
Approximately10,980 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Elm Street Elementary School Inspection Date: 07/11/2016
Page 2 of 5
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling Tile &
Associated Mastic
Rooms 101 - 103, 105-110, & 112 - 114
Approximately10,980 SF
Friable Good Assumed
4" Baseboard &Associated Mastic
Rooms 101 - 103, 105-110, & 112 - 114
Approximately1,440 LF
Non-Friable Good Assumed
12" x 12" Light BrownResilient Floor Tile &
Associated Mastic
Rooms 101 - 103, 105-110, & 112 - 114
Approximately10,980 SF
Non-Friable Good Assumed
PlasterRooms 101 - 103, 105-
110, & 112 - 114,Electrical Room
Approximately13,320 SF
Friable Good Assumed
Exterior Stucco Walls & OverhangApproximately
15,000 SFNon-Friable Good Assumed
200 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling Tile &
Associated Mastic
Cafeteria, Storage,Room 202
Approximately2,375 SF
Friable Good Assumed
Plaster ThroughoutApproximately
5,750 SFFriable Good Assumed
6" Baseboard &Associated Mastic
ThroughoutApproximately
275 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Elm Street Elementary School Inspection Date: 07/11/2016
Page 3 of 5
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" GreyResilient Floor Tile &
Associated Mastic
Cafeteria, Storage,Room 202
Approximately2,375 SF
Non-Friable Good Assumed
Exterior Stucco ThroughoutApproximately
2,500 SFNon-Friable Good Assumed
300 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Plaster LoungeApproximately
2,400 SFFriable Good Assumed
12" x 12" Light BrownResilient Floor Tile &
Associated MasticLounge
Approximately400 SF
Non-Friable Good Assumed
Tan Vinyl SheetFlooring & Associated
MasticRoom 301 Restroom
Approximately40 SF
Friable Good Assumed
Drywall / JointCompound
Room 301 RestroomApproximately
210 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
760 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Elm Street Elementary School Inspection Date: 07/11/2016
Page 4 of 5
400 Building (Restrooms):
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' GypsumAcoustic Ceiling Panels
ThroughoutApproximately
380 SFFriable Good Assumed
Vinyl Sheet Flooring &Associated Mastic
ThroughoutApproximately
380 SFFriable Good Assumed
Wainscot & AssociatedMastic
ThroughoutApproximately
1,000 SFNon-Friable Good Assumed
500 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Room 501Approximately
1,055 SFFriable Good Assumed
4" Baseboard &Associated Mastic
ThroughoutApproximately
230 LFNon-Friable Good Assumed
Drywall / JointCompound
Room 505, RestroomApproximately
1,185 SFFriable Good Assumed
Plaster Rooms 501 & 502Approximately
1,890 SFFriable Good Assumed
Vinyl Sheet Flooring &Associated Mastic
RestroomsApproximately
90 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
1,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Elm Street Elementary School Inspection Date: 07/11/2016
Page 5 of 5
Portables:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 702 & 703, 801- 807, 901, 902, & 905 -
907
Approximately12,600 SF
Friable Good Assumed
Drywall / JointCompound
Rooms 601 - 604, 702,703, 801 - 807, 901,
902, & 905 - 907
Approximately19,800 SF
Friable Good Assumed
4" Baseboard &Associated Mastic
Rooms 601 - 604, 702,703, 801 - 807, 901,
902, & 905 - 907
Approximately2,240 LF
Non-Friable Good Assumed
Vinyl Sheet Flooring &Associated Mastic
Rooms 602 & 603Restrooms, Restroom
Building
Approximately480 SF
Friable Good Assumed
Wainscot & AssociatedMastic
RestroomsApproximately
1,200 SFNon-Friable Good Assumed
Harrington Elementary School1051 South A StreetOxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 1 of 9
During an inspection performed on July 11, 2016 TC noted that Harrington Elementary School contained the following asbestoscontaining building materials (ACBM):
100 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue/Green Carpet
Office, ConferenceRoom, Principal's
Office
Approximately1,860 SF
Non-Friable Good Assumed
2' x 4' (Faux 2' x 2')Acoustic Ceiling Panels
Office, ConferenceRoom, Principal's
Office
Approximately1,860 SF
Friable Good Assumed
12" x 12" Dark BlueResilient Floor Tile &
Associated Mastic
Entry, Health Office,Work Room
Approximately300 SF
Non-Friable Good Assumed
12" x 12" Light BlueResilient Floor Tile &
Associated MasticWork Room
Approximately400 SF
Non-Friable Good Assumed
12" x 12" YellowResilient Floor Tile &
Associated MasticWork Room
Approximately200 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
325 LFNon-Friable Good Assumed
Exterior Stucco ThroughoutApproximately
10,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 2 of 9
200 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue/Green Carpet
Rooms 206, 208, 251,252, & 253
Approximately4,000 SF
Non-Friable Good Assumed
2' x 4' (Faux 2' x 2')Acoustic Ceiling Panels
Rooms206, 208, 251,252, & 253
Approximately4,500 SF
Friable Good Assumed
12" x 12" Light BlueResilient Floor Tile &
Associated MasticRooms 251, 252, & 253
Approximately384 SF
Non-Friable Good Assumed
12" x 12" YellowResilient Floor Tile &
Associated MasticRooms 251, 252, & 253
Approximately384 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
960 LFNon-Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
12,000 SFFriable Good Assumed
Mastic Associated WithHardwood Flooring
Multi-Purpose RoomApproximately
4,600 SFNon-Friable Good Assumed
2' x 4' Solid AcousticCeiling Panels
Room 202, KitchenApproximately
684 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
10,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 3 of 9
300 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue/Green Carpet
ThroughoutApproximately
15,600 SFNon-Friable Good Assumed
2' x 4' (Faux 2' x 2')Acoustic Ceiling Panels
ThroughoutApproximately
18,000 SFFriable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
28,8000 SFFriable Good Assumed
12" x 12" Light BlueResilient Floor Tile &
Associated MasticThroughout
Approximately2,560 SF
Non-Friable Good Assumed
12" x 12" YellowResilient Floor Tile &
Associated MasticThroughout
Approximately2,560 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
2,500 LFNon-Friable Good Assumed
Exterior Stucco ThroughoutApproximately
10,000 SFNon-Friable Good Assumed
400 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue/Green Carpet
Rooms 401 - 404Approximately
2,800 SFNon-Friable Good Assumed
2' x 4' (Faux 2' x 2')Acoustic Ceiling Panels
ThroughoutApproximately
6,000 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 4 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" BlueResilient Floor Tile
Rooms 401 - 404Approximately
1,584 SFNon-Friable Good Assumed
12" x 12" YellowResilient Floor Tile &
Associated MasticRooms 401 - 404
Approximately1,584 SF
Non-Friable Good Assumed
12" x 12" Dark BlueResilient Floor Tile &
Associated MasticTeacher's Work Rooms
Approximately500 SF
Non-Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
8,600 SFFriable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
720 LFNon-Friable Good Assumed
Exterior Stucco ThroughoutApproximately
10,800 SFNon-Friable Good Assumed
500 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue/Green Carpet
ThroughoutApproximately
4,500 SFNon-Friable Good Assumed
12" x 12" Dark BlueResilient Floor Tile &
Associated MasticRooms 503 & 504
Approximately500 SF
Non-Friable Good Assumed
12" x 12" BlueResilient Floor Tile &
Associated MasticEntry
Approximately200 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 5 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' (Faux 2' x 2')Acoustic Ceiling Panels
ThroughoutApproximately
4,500 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
7,500 SFNon-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
8,000 SFFriable Good Assumed
OLD 100 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling Tile &
Associated MasticThroughout
Approximately1,560 SF
Friable Good Assumed
12" x 12" GreyResilient Floor Tile &
Associated MasticThroughout
Approximately1,560 SF
Non-Friable Good Assumed
6" Black Baseboard &Associated Mastic
ThroughoutApproximately
220 LFNon-Friable Good Assumed
Plaster Walls ThroughoutApproximately
5,000 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
6,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 6 of 9
OLD Rooms 301 & 302:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 301 & 302Approximately
1,750 SFFriable Good Assumed
12" x 12" Light BlueResilient Floor Tile &
Associated MasticRooms 301 & 302
Approximately1,500 SF
Non-Friable Good Assumed
12" x 12" Dark BlueResilient Floor Tile &
Associated MasticRooms 301 & 302
Approximately250 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 301 & 302Approximately
220 LFNon-Friable Good Assumed
Plaster Walls Rooms 301 & 302Approximately
3,000 SFFriable Good Assumed
Exterior Stucco ThroughoutApproximately
2,000 SFNon-Friable Good Assumed
OLD Rooms 303 & 304:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" GreyResilient Floor Tile &
Associated MasticRooms 303 & 304
Approximately1,672 SF
Non-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Rooms 303 & 304Approximately
240 LFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 7 of 9
OLD 400 Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
4,480 SFFriable Good Assumed
Plaster Walls ThroughoutApproximately
10,000 SFFriable Good Assumed
6" Black Baseboard &Associated Mastic
ThroughoutApproximately
600 LFNon-Friable Good Assumed
12" x 12" Light BlueResilient Floor Tile &
Associated MasticThroughout
Approximately3,480 SF
Non-Friable Good Assumed
12" x 12" BlueResilient Floor Tile &
Associated MasticThroughout
Approximately1,000 SF
Non-Friable Good Assumed
OLD Room 801:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling Tile &
Associated MasticRoom 801
Approximately1,100 SF
Friable Good Assumed
Mastic Associated WithBrown Carpet
Room 801Approximately
884 SFNon-Friable Good Assumed
6" Black Baseboard &Associated Mastic
Room 801Approximately
115 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 8 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" GreenResilient Floor Tile &
Associated MasticRoom 801
Approximately16 SF
Non-Friable Good Assumed
OLD Room 803:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithBlue Carpet
Room 803Approximately
836 SFNon-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Room 803Approximately
120 LFNon-Friable Good Assumed
OLD Rooms 802, 804, & 805:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Room 805Approximately
836 SFFriable Good Assumed
Mastic Associated WithRed Carpet
Rooms 802, 804 & 805Approximately
2,500 SFNon-Friable Good Assumed
4" Red Baseboard &Associated Mastic
Rooms 802, 803, & 805Approximately
360 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Harrington Elementary School Inspection Date: 07/11/2016
Page 9 of 9
OLD Building 9:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" GreyResilient Floor Tile &
Associated MasticMeeting Room
Approximately280 SF
Non-Friable Good Assumed
4" Grey Baseboard &Associated Mastic
Meeting RoomApproximately
70 LFNon-Friable Good Assumed
2' x 4' Acoustic CeilingPanel
Meeting RoomApproximately
280 SFFriable Good Assumed
2' x 4' Solid AcousticCeiling Panel
RestroomsApproximately
120 SFFriable Good Assumed
Sheet Flooring &Associated Mastic
RestroomsApproximately
120 SFFriable Good Assumed
Kamala Elementary School634 West Kamala Street
Oxnard, CA 93033
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 1 of 10
During an inspection performed on July 12, 2016 TC noted that Kamala Elementary School contained the following asbestoscontaining building materials (ACBM):
Administration Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Rough AcousticCeiling Panels
Front Desk AreaApproximately
500 SFFriable Good Assumed
12" x 12" RandomHole Acoustic Ceiling
Tile & AssociatedMastic
Principals' Office,Assistant Principal's
Office, Vice Principal'sOffice, Nurse's Office
Approximately900 SF
Friable Good Assumed
Drywall ThroughoutApproximately
2,100 SFNon-Friable Good Assumed
Joint Compound ThroughoutApproximately
2,100 SFFriable Good Assumed
12" x 12" BeigeSpeckled Resilient
Floor Tile &Associated Mastic
Principal's Office,Assistant Principal's
Office, Vice Principal'sOffice, Office, Nurse's
Office
Approximately1,400 SF
Non-Friable Good Assumed
6" Black Baseboard &Associated Mastic
ThroughoutApproximately
260 LFNon-Friable Good Assumed
Stucco ExteriorApproximately
3,600 SFNon-Friable Good Positive O&M Program
12" x 12" BrownResilient Floor Tile &
Associated Mastic
Nurse's OfficeRestroom
Approximately25 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 2 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Nurse's OfficeApproximately
320SFFriable Good Assumed
Cafeteria / Kitchen Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Cafeteria, Lounge,Work Room
Approximately4,150 SF
Friable Good Assumed
2' x 4' DrywallAcoustic Ceiling Panels
Kitchen, Kitchen Hall,Restroom
Approximately400 SF
Non-Friable Good Assumed
Drywall ThroughoutApproximately
6,100 SFNon-Friable Good Positive O&M Program
Joint Compound ThroughoutApproximately
6,100 SFFriable Good Positive O&M Program
12" x 12" GreyResilient Floor Tile &
Associated Mastic
Cafeteria, CafeteriaStorage
Approximately3,350 SF
Non-Friable Good Assumed
Beige Resilient SheetFlooring & Associated
Mastic
Kitchen, KitchenOffice, Hallway,Custodial Room
Approximately800 SF
Friable Good Assumed
Wainscot & AssociatedMastic
KitchenApproximately
650 SFNon-Friable Good Assumed
6" Brown Baseboard &Associated Mastic
ThroughoutApproximately
2,200 LFNon-Friable Good Assumed
Stucco ExteriorApproximately
5,200 SFNon-Friable Good Positive O&M Program
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 3 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
PlasterKitchen Office,
Hallway, CustodialRoom, Room 205
Approximately1,300 SF
Friable Good Assumed
Mastic Associated WithCarpet
Work Room, LoungeApproximately
900 SFNon-Friable Good Assumed
12" x 12" Tan SpeckledResilient Floor Tile &
Associated Mastic
Lounge Entrance,Lounge
Approximately65 SF
Non-Friable Good Assumed
Two-Story Classroom Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Pinhole AcousticCeiling Panels
Throughout AllClassrooms
Approximately23,920 SF
Friable Good Assumed
2' x 2' Pinhole AcousticCeiling Panels
1st & 2nd FloorHallways
Approximately9,000 SF
Friable Good Assumed
DrywallThroughout 1st & 2nd
FloorsApproximately
36,000 SFNon-Friable Good Assumed
Joint CompoundThroughout 1st & 2nd
FloorsApproximately
36,000 SFFriable Good Assumed
12" x 12" Cream &Multi-Colored Resilient
Floor Tile &Associated Mastic
Throughout 1st & 2ndFloor Classrooms &
Hallways
Approximately16,460 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Throughout 1st & 2ndFloor Classrooms
Approximately3,640 LF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 4 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" Brown Baseboard &Associated Mastic
1st & 2nd FloorHallways, ElectricalRooms, Custodial
Room, Work Rooms
Approximately1,900 LF
Non-Friable Good Assumed
Stucco ExteriorApproximately
25,500 SFNon-Friable Good Assumed
Spray On Fire ProofingInsulation
Above Drop Ceiling on1st & 2nd Floors
Approximately32,920 SF
Friable Good Assumed
Building 3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 301 - 305Approximately
4,600 SFFriable Good Assumed
DrywallAll Rooms on the AC
Vent AreaApproximately
500 SFNon-Friable Good Assumed
Joint CompoundAll Rooms on the AC
Vent AreaApproximately
500 SFFriable Good Assumed
Plaster ThroughoutApproximately
5,500 SFFriable Good Assumed
12" x 12" BeigeSpeckled Resilient
Floor Tile &Associated Mastic
Rooms 301 - 305Approximately
4,600 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 5 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" and 6" BeigeBaseboard &
Associated MasticsThroughout
Approximately700 LF
Non-Friable Good Assumed
StuccoExterior Walls &
OverhangApproximately
6,500 SFNon-Friable Good Positive O&M Program
Building 4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 401 - 405Approximately
4,600 SFFriable Good Assumed
DrywallAll Rooms on the AC
Vent AreaApproximately
500 SFNon-Friable Good Assumed
Joint CompoundAll Rooms on the AC
Vent AreaApproximately
500 SFFriable Good Assumed
Plaster ThroughoutApproximately
5,500 SFFriable Good Assumed
12" x 12" BeigeSpeckled Resilient
Floor Tile &Associated Mastic
Rooms 401 - 405Approximately
4,600 SFNon-Friable Good Assumed
4" and 6" BeigeBaseboard &
Associated MasticsThroughout
Approximately700 LF
Non-Friable Good Assumed
StuccoExterior Walls &
OverhangApproximately
6,500 SFNon-Friable Good Positive O&M Program
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 6 of 10
Building 5:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 501 - 505Approximately
4,600 SFFriable Good Assumed
DrywallAll Rooms on the AC
Vent AreaApproximately
500 SFNon-Friable Good Assumed
Joint CompoundAll Rooms on the AC
Vent AreaApproximately
500 SFFriable Good Assumed
Plaster ThroughoutApproximately
6,500 SFFriable Good Assumed
12" x 12" BeigeSpeckled Resilient
Floor Tile &Associated Mastic
Rooms 501 - 505 & 508Approximately
4,900 SFNon-Friable Good Assumed
4" and 6" BeigeBaseboard &
Associated MasticThroughout
Approximately820 LF
Non-Friable Good Assumed
StuccoExterior Walls &
OverhangApproximately
6,800 SFNon-Friable Good Positive O&M Program
Building 6:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 601 & 602Approximately
1,800 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 7 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
DrywallAll Rooms on the AC
Vent AreaApproximately
200 SFNon-Friable Good Assumed
Joint CompoundAll Rooms on the AC
Vent AreaApproximately
200 SFFriable Good Assumed
Plaster ThroughoutApproximately
2,700 SFFriable Good Assumed
12" x 12" BeigeSpeckled Resilient
Floor Tile &Associated Mastic
Rooms 601 & 602Approximately
1,800 SFNon-Friable Good Assumed
4" Beige Baseboard &Associated Mastic
ThroughoutApproximately
240 LFNon-Friable Good Assumed
StuccoExterior Walls &
OverhangApproximately
1,800 SFNon-Friable Good Positive O&M Program
Building 8:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Library, Room 805Approximately
2,100 SFFriable Good Assumed
DrywallBetween Wood Panels
ThroughoutApproximately
2,500 SFNon-Friable Good Assumed
Joint CompoundBetween Wood Panels
ThroughoutApproximately
2,500 SFFriable Good Assumed
Wainscot & AssociatedMastic
Boy's, Girls, and RoomSR808 Restrooms
Approximately1,200 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 8 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithCarpet
Library, Room 805Approximately
1,800 SFNon-Friable Good Assumed
12" x 12" GreenResilient Floor Tile &
Associated Mastic
Library Entrance, Room805 Entrance
Approximately60 SF
Non-Friable Good Assumed
Stucco ExteriorApproximately
1,800 SFNon-Friable Good Assumed
Building 9:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
DrywallBetween Wood Panels
ThroughoutApproximately
2,200 SFNon-Friable Good Assumed
Joint CompoundBetween Wood Panels
ThroughoutApproximately
2,200 SFFriable Good Assumed
12" x 12" GreyResilient Floor Tile &
Associated MasticRooms 901 & 902
Approximately1,800 SF
Non-Friable Good Assumed
Mastic Associated WithCarpet
Room 903Approximately
900 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Rooms 901 & 902Approximately
240 LFNon-Friable Good Assumed
4" Grey Baseboard &Associated Mastic
Room 903Approximately
120 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 9 of 10
San Miguel - Main Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
ThroughoutApproximately
2,500 SFFriable Good Assumed
Drywall ThroughoutApproximately
3,600 SFNon-Friable Good Assumed
Joint Compound ThroughoutApproximately
3,600 SFFriable Good Assumed
12" x 12" Tan SpeckledResilient Floor Tile &
Associated Mastic
Rooms 101 - 104 &114, Play Room,Lounge Room
Approximately600 SF
Non-Friable Good Assumed
Mastic Associated WithCarpet
Rooms 101 - 104 &114, Front Desk
Hallway
Approximately1,500 SF
Non-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
ThroughoutApproximately
360 LFNon-Friable Good Assumed
12" x 12" GreenResilient Floor Tile &
Associated Mastic
Play Room Near WaterFountain
Approximately20 SF
Non-Friable Good Assumed
San Miguel - Rooms 201 & 202:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
DrywallBetween Wood Panels
ThroughoutApproximately
2,400 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Kamala Elementary School Inspection Date: 07/12/2016
Page 10 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Joint CompoundBetween Wood Panels
ThroughoutApproximately
2,400 SFFriable Good Assumed
12" x 12" Cream &Multi-Colored Resilient
Floor Tile &Associated Mastic
Rooms 201 & 202Approximately
1,800 SFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
ThroughoutApproximately
240 LFNon-Friable Good Assumed
Lemonwood Elementary School2200 Carnegie CourtOxnard, CA 93033
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 1 of 7
During an inspection performed on July 12, 2016 TC noted that Lemonwood Elementary School contained the following asbestoscontaining building materials (ACBM):
Building 1 - Administration:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
4,135 SFFriable Good Assumed
12" x 12" Tan ResilientFloor Tile &
Associated Mastic
Nursery, AdministrationReception, ConferenceRoom, Hallway, Room
102
Approximately1,800 SF
Non-Friable Good Assumed
4" Baseboard &Associated Mastic
ThroughoutApproximately
470 LFNon-Friable Good Assumed
Mastic Associated WithCarpet
Rooms 103, 104, 106,108, & 109
Approximately2,406 SF
Non-Friable Good Assumed
Vinyl Sheet Flooring &Associated Mastic
Nursery RestroomApproximately
40 SFFriable Good Positive O&M Program
Drywall / JointCompound
ThroughoutApproximately
6,000 SFFriable Good Assumed
Building 1 - Multi-Purpose Room & Kitchen:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
2,870 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 2 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall / JointCompound
ThroughoutApproximately
4,800 SFFriable Good Assumed
4" Baseboard &Associated Mastic
Multi-Purpose RoomApproximately
215 LFNon-Friable Good Assumed
Mastic Associated WithCarpet
StageApproximately
560 SFNon-Friable Good Assumed
12" x 12" Off-WhiteResilient Floor Tile &
Associated MasticThroughout
Approximately2,350 SF
Non-Friable Good Positive O&M Program
Building 2:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 204 - 209Approximately
6,600 SFFriable Good Assumed
Drywall ThroughoutApproximately
8,000 SFNon-Friable Good Assumed
Joint Compound ThroughoutApproximately
8,000 SFFriable Good Assumed
12" x 12" BlueResilient Floor Tile &
Associated MasticRooms 204 - 209
Approximately6,600 SF
Non-Friable Good Assumed
6" Blue Baseboard &Associated Mastic
ThroughoutApproximately
860 LFNon-Friable Good Assumed
4' x 4' Transite Panels ExteriorApproximately
96 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 3 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Stucco ExteriorApproximately
6,300 SFNon-Friable Good Assumed
Building 3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 301, 302, & 309- 312
Approximately6,600 SF
Friable Good Assumed
Drywall ThroughoutApproximately
8,000 SFNon-Friable Good Assumed
Joint Compound ThroughoutApproximately
8,000 SFFriable Good Assumed
12" x 12" BlueResilient Floor Tile &
Associated Mastic
Rooms 301, 302, & 309- 312, Work Room
Approximately7,000 SF
Non-Friable Good Assumed
6" Blue Baseboard &Associated Mastic
ThroughoutApproximately
920 LFNon-Friable Good Assumed
4' x 4' Transite Panels ExteriorApproximately
96 SFNon-Friable Good Assumed
Stucco ExteriorApproximately
6,300 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 4 of 7
Building 4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 401 - 404Approximately
4,400 SFFriable Good Assumed
Drywall ThroughoutApproximately
5,500 SFNon-Friable Good Assumed
Joint Compound ThroughoutApproximately
5,500 SFFriable Good Assumed
12" x 12" BlueResilient Floor Tile &
Associated MasticRooms 401 - 404
Approximately4,400 SF
Non-Friable Good Assumed
6" Blue Baseboard &Associated Mastic
ThroughoutApproximately
560 LFNon-Friable Good Assumed
4' x 4' Transite Panels ExteriorApproximately
64 SFNon-Friable Good Assumed
Stucco ExteriorApproximately
3,600 SFNon-Friable Good Assumed
Building 6:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
DrywallBetween Wood Panels
ThroughoutApproximately
2,400 SFNon-Friable Good Assumed
Joint CompoundBetween Wood Panels
ThroughoutApproximately
2,400 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 5 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" BlueResilient Floor Tile &
Associated MasticRooms 601 & 602
Approximately1,800 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
ThroughoutApproximately
240 LFNon-Friable Good Assumed
Black Resilient SheetFlooring & Associated
Mastic
Rooms 601 & 602Restrooms
Approximately60 SF
Friable Good Assumed
Wainscot & AssociatedMastic
Rooms 601 & 602Restrooms
Approximately400 SF
Non-Friable Good Assumed
Building 7:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling and Wall Tiles& Associated Mastic
Rooms 701 - 704Approximately
4,360 SFFriable Good Assumed
Mastic Associated WithCarpet
Rooms 701 - 704Approximately
3,600 SFNon-Friable Good Assumed
12" x 12" Tan ResilientFloor Tile &
Associated Mastic
Rooms 701 - 703,Room 704 (Under
Carpet)
Approximately1,000 SF
Non-Friable Good Assumed
4" Baseboard &Associated Mastic
Rooms 701 - 704Approximately
480 LFNon-Friable Good Assumed
Stucco ExteriorApproximately
2,500 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 6 of 7
Building 8:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" AcousticCeiling and Wall Tiles& Associated Mastic
Room 801Approximately
1,095 SFFriable Good Assumed
Drywall / JointCompound
Room 801Approximately
1,000 SFFriable Good Assumed
4" Baseboard &Associated Mastic
Room 801Approximately
120 LFNon-Friable Good Assumed
Mastic Associated WithCarpet
Room 801Approximately
915 SFNon-Friable Good Assumed
Stucco ExteriorApproximately
1,200 SFNon-Friable Good Assumed
Building 9:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 901 - 912Approximately
10,800 SFFriable Good Assumed
Drywall / JointCompound
Rooms 901 - 912Approximately
13,200 SFFriable Good Assumed
4" Baseboard &Associated Mastic
Rooms 901 - 912Approximately
1,440 LFNon-Friable Good Assumed
Mastic Associated WithCarpet
Rooms 901 - 912Approximately
10,710 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Lemonwood Elementary School Inspection Date: 07/12/2016
Page 7 of 7
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" BlueResilient Floor Tile &
Associated MasticRooms 904 & 908 - 912
Approximately100 SF
Non-Friable Good Assumed
Marina West Elementary School2501 Carob StreetOxnard, CA 93035
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 1 of 9
During an inspection performed on July 12, 2016 TC noted that Marina West Elementary School contained the following asbestoscontaining building materials (ACBM):
Administration / Cafeteria / Kitchen Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Throughout except forKitchen
Approximately4,500 SF
Friable Good Assumed
12" x 12" AcousticWall Tile & Associated
MasticCafeteria
Approximately50 SF
Friable Good Assumed
12" x 12" Pink VinylFloor Tile &
Associated MasticThroughout
Approximately4,500 SF
Non-Friable Good Assumed
6" Black Baseboard &Associated Mastic
AdministrationApproximately
65 LFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Copy/Work RoomApproximately
14 LFNon-Friable Good Assumed
Drywall / JointCompound
Administration, KitchenApproximately
500 SFFriable Good Assumed
Interior Plaster ThroughoutApproximately
4,000 SFFriable Good Assumed
Stucco ExteriorApproximately
3,400 SFNon-Friable Good Assumed
Gold With Black DotsFlooring Material
KitchenApproximately
465 SFNon-Friable Good Assumed
32" x 32" TransitePanels
At Perimeter DoorsApproximately
50 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 2 of 9
Building 2:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 201 & 202Approximately
1,900 SFFriable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 201 & 202Approximately
15 LFNon-Friable Good Assumed
12" x 12" Blue FloorTile & Associated
MasticRooms 201 & 202
Approximately1,900 SF
Non-Friable Good Assumed
6" Blue/GreenBaseboard &
Associated MasticRooms 201 & 202
Approximately100 LF
Non-Friable Good Assumed
Drywall / JointCompound
Rooms 201 & 202Approximately
3,800 SFFriable Good Assumed
Stucco ExteriorApproximately
2,200 SFNon-Friable Good Assumed
Building 3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Tile
Rooms 301 - 306Approximately
6,600 SFFriable Good Assumed
12" x 12" AcousticWall Tile & Associated
MasticRooms 301 - 306
Approximately180 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 3 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" Blue FloorTile & Associated
MasticRooms 301 - 306
Approximately6,600 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 301 - 306Approximately
270 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 301 - 306Approximately
8,100 SFFriable Good Assumed
Stucco ExteriorApproximately
5,800 SFNon-Friable Good Assumed
Transite Panels At Entrance DoorsApproximately
140 SFNon-Friable Good Assumed
Building 4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 401 - 406Approximately
6,600 SFFriable Good Assumed
12" x 12" AcousticWall Tile & Associated
MasticRooms 401 - 406
Approximately180 SF
Friable Good Assumed
12" x 12" Blue FloorTile & Associated
MasticRooms 401 - 406
Approximately6,600 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 401 - 406Approximately
270 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 4 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall / JointCompound
Rooms 401 - 406Approximately
8,100 SFFriable Good Assumed
Stucco ExteriorApproximately
5,800 SFNon-Friable Good Assumed
Transite Panels At Each Perimeter DoorApproximately
140 SFNon-Friable Good Assumed
Building 5:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' FissuredAcoustic Ceiling Panels
Rooms 501 - 506Approximately
6,600 SFFriable Good Assumed
12" x 12" AcousticWall Tile & Associated
MasticRooms 501 - 506
Approximately180 SF
Friable Good Assumed
12" x 12" Blue FloorTile & Associated
MasticRooms 501 - 506
Approximately6,600 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 501 - 506Approximately
270 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 501 - 506Approximately
8,100 SFFriable Good Assumed
Stucco ExteriorApproximately
5,800 SFNon-Friable Good Assumed
Transite Panels At Each Perimeter DoorApproximately
140 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 5 of 9
Buildings 6 & 7:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall / JointCompound
Men & Women'sRestrooms, CustodialRooms, Boy's & Girl's
Restrooms
Approximately3,000 SF
Non-Friable Good Assumed
Building 8:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 801 - 803Approximately
2,760 SFFriable Good Assumed
Mastic Associated WithCarpet
Rooms 801 - 803Approximately
2,200 SFNon-Friable Good Assumed
12" x 12" Grey FloorTile & Associated
MasticRooms 801 & 803
Approximately500 SF
Non-Friable Good Assumed
4" Blue/GreenBaseboard &
Associated MasticRooms 801 - 803
Approximately120 LF
Non-Friable Good Assumed
Drywall / JointCompound
Rooms 801 - 803Approximately
3,850 SFFriable Good Assumed
Vinyl Sheet Flooring &Associated Mastic
Rooms 801 & 803Approximately
120 SFFriable Good Assumed
Wainscot & AssociatedMastic
Rooms 801 & 803Approximately
550 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 6 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Padded Panel Mastic Rooms 801 - 803Approximately
3,850 SFNon-Friable Good Assumed
Building 9:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 901 - 903Approximately
2,800 SFFriable Good Assumed
Mastic Associated WithCarpet
Rooms 901 - 903Approximately
2,600 SFNon-Friable Good Assumed
12" x 12" Blue FloorTile & Associated
MasticRooms 901 - 903
Approximately175 SF
Non-Friable Good Assumed
4" Blue Baseboard &Associated Mastic
Rooms 901 - 903Approximately
95 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 901 - 903Approximately
3,400 SFFriable Good Assumed
Building 10:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" Ceiling andWall Tiles &
Associated MasticRooms 1001 - 1003
Approximately3,200 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 7 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithCarpet
Rooms 1001 & 1002Approximately
1,800 SFNon-Friable Good Assumed
Stucco ExteriorApproximately
2,100 SFNon-Friable Good Assumed
Note: New 12" Vinyl Floor Tile was being installed in Room 1003 at the time of the survey (~900 SF).
Building 11:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 1101 - 1104Approximately
3,700 SFFriable Good Assumed
Mastic Associated WithCarpet
Room 1101 - 1104Approximately
3,700 SFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 1101 - 1104Approximately
5,000 SFFriable Good Assumed
4" Brown Baseboard &Associated Mastic
Rooms 1101 - 1104Approximately
136 LFNon-Friable Good Assumed
Building 12:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
3,500 SFFriable Good Assumed
Mastic Associated WithCarpet
Rooms 1201 - 1203Approximately
2,800 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 8 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Green With BlackVinyl Sheet Flooring &
Associated MasticRoom 1204
Approximately350 SF
Friable Good Assumed
Grey With Black VinylSheet Flooring &Associated Mastic
RestroomsApproximately
400 SFFriable Good Assumed
4" Brown Baseboard &Associated Mastic
Rooms 1201 - 1203Approximately
95 LFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Room 1204Approximately
50 LFNon-Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
5,700 SFFriable Good Assumed
Wainscot & AssociatedMastic
Restrooms, CustodianCloset
Approximately1,400 SF
Non-Friable Good Assumed
Building 13:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12" x 12" Ceiling andWall Tiles &
Associated MasticRoom 1301
Approximately1,140 SF
Friable Good Assumed
Mastic Associated WithCarpet
Room 1301Approximately
960 SFNon-Friable Good Assumed
12" x 12" Blue FloorTile & Associated
Mastic
Room 1301 (UnderCarpet)
Approximately960 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Marina West Elementary School Inspection Date: 07/12/2016
Page 9 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" Brown Baseboard &Associated Mastic
Room 1301Approximately
31 LFNon-Friable Good Assumed
Drywall / JointCompound
Room 1301Approximately
1,150 SFFriable Good Assumed
Building 14:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 1 & 2Approximately
1,310 SFFriable Good Assumed
Blue Vinyl SheetFlooring & Associated
Mastic
Room 2, Room 1Restroom
Approximately925SF
Friable Good Assumed
4" Blue/GreenBaseboard &
Associated MasticRooms 1 & 2
Approximately60 LF
Non-Friable Good Assumed
Drywall / JointCompound
Rooms 1 & 2Approximately
2,100 SFFriable Good Assumed
Padded Panel Mastic Rooms 1 & 2Approximately
2,100 SFNon-Friable Good Assumed
Wainscot & AssociatedMastic
Rooms 1 & 2Approximately
500 SFNon-Friable Good Assumed
Mastic Associated WithCarpet
Room 1Approximately
460 SFNon-Friable Good Assumed
McKinna Elementary School1611 South J StreetOxnard, CA 93033
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 1 of 10
During an inspection performed on July 12, 2016 TC noted that McKinna School contained the following asbestos containing buildingmaterials (ACBM):
Office Buildings #1:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” AcousticalCeiling Tile & Mastic
Office & Staff LoungeApproximately
1,680 SFFriable Good Assumed
12”x12” Tan ResilientFloor Tile & Mastic
Office & Staff LoungeApproximately
1,650 SFNon-Friable Good Positive O&M Program
6” Black BaseboardMastic
Office & Staff LoungeApproximately
230 LFNon-Friable Good Assumed
Plaster Walls Office & Staff LoungeApproximately
2,500 SFNon-Friable Good Assumed
12”x12” BrownResilient Floor Tile &
Mastic
Office Restroom, StaffLounge Restroom
Approximately50 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,220 SFNon-Friable Good Assumed
Buildings #3: (Rooms 301-304)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 301 & 302Approximately
1,680 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 2 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” AcousticalCeiling Tile & Mastic(Above 2’x4’ ACP)
Rooms 301 & 302Approximately
1,680 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 301 & 302Approximately
50 SFNon-Friable Good Assumed
Drywall & JointCompound
Rooms 301-302, UnisexRestroom, Girls & Boys
Restroom
Approximately2,500 SF
Non-Friable /Friable
Good Assumed
6” Blue BaseboardMastic
Rooms 301 & 302Approximately
230 LFNon-Friable Good Assumed
Plaster WallsRooms 301 & 302,
Storage RoomsApproximately
2,500 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,220 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 301 & 302
Approximately50 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 303 & 304Approximately
230 LFNon-Friable Good Assumed
Wainscot Mastic Room 303Approximately
2,500 SFNon-Friable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
Room 303Approximately
50 SFNon-Friable Good Assumed
Vinyl Sheet Flooring &Mastic
Room 303Approximately
1,680 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Room 304Approximately
50 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 3 of 10
Buildings #4: (Rooms 401-405)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 401-405Approximately
4,650 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic(Above 2’x4’ ACP)
Rooms 401-405Approximately
4,650 SFFriable Good Assumed
Plaster Walls Rooms 401-405Approximately
5,100 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 401-405Approximately
2,850 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 401-405
Approximately1,800 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 401-405Approximately
600 LFNon-Friable Good Assumed
Drywall & JointCompound
Boys & Girls RestroomApproximately
700 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
3,700 SFNon-Friable Good Assumed
Window Putty Building #4Approximately
200 LFNon-Friable Good Positive O&M Program
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 4 of 10
Buildings #5: (Rooms 501-505)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 501-505Approximately
4,650 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic(Above 2’x4’ ACP)
Rooms 501-505Approximately
4,650 SFFriable Good Assumed
Plaster Walls Rooms 501-505Approximately
5,100 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 501-505Approximately
2,850 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 501-505
Approximately1,800 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 501-505Approximately
600 LFNon-Friable Good Assumed
Drywall & JointCompound
Boys & Girls RestroomApproximately
700 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
3,700 SFNon-Friable Good Assumed
Window Putty Building #5Approximately
200 LFNon-Friable Good Positive O&M Program
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 5 of 10
Buildings #6: (Rooms 601-605) & Storage Room
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 601-605Approximately
4,650 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic(Above 2’x4’ ACP)
Rooms 601-605Approximately
4,650 SFFriable Good Assumed
Plaster Walls Rooms 601-605Approximately
5,100 SFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 601-605Approximately
3,850 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 601-605
Approximately1,800 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 601-605Approximately
600 LFNon-Friable Good Assumed
Drywall & JointCompound
Storage RoomApproximately
750 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
3,700 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 6 of 10
Buildings #8: Pre-K 801 & Pre –K 802
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 801 & 802Approximately
2,200 SFFriable Good Assumed
Drywall & JointCompound
Rooms 801 & 802Approximately
2,600 SFNon-Friable /
FriableGood Assumed
Wainscot Mastic In Between Room 803Approximately
180 SFNon-Friable Good Assumed
6” Black BaseboardMastic
Rooms 801 & 802Approximately
260 LFNon-Friable Good Assumed
12”x12” WhiteResilient Floor Tile &
Mastic
Rooms 801 & 802 &Supply Room
Approximately1,600 SF
Non-Friable Good Assumed
Vinyl Sheet Flooring &Mastic
In Between Room 803Approximately
110 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Room 801Approximately
470 SFNon-Friable /
FriableGood Assumed
Window Putty Building #8Approximately
100 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 7 of 10
Buildings #9: (Rooms 901 & 902)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” AcousticalCeiling Tile & Mastic
Rooms 901 & 902Approximately
1,720 SFFriable
Damaged inRoom 901
Assumed
12”x12” Grey ResilientFloor Tile & Mastic
Room 901Approximately
310 SFNon-Friable Good Assumed
12”x12” BlackResilient Floor Tile &
MasticRoom 901
Approximately570 SF
Non-Friable Good Assumed
6” Brown BaseboardMastic
Rooms 901 & 902Approximately
240 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Room 902Approximately
860 SFNon-Friable /
FriableGood Assumed
Window Putty Building #9Approximately
200 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,320 SFNon-Friable /
FriableGood Assumed
Buildings #10: (Rooms 1001-1007)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 1001-1004Approximately
6,440 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 8 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
Rooms 1001-1007,Boys & Girls
Restrooms, StaffRestrooms
Approximately9,200 SF
Non-Friable /Friable
Good Assumed
4” Black BaseboardMastic
Rooms 1001-1007Approximately
840 LFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 1002-1007Approximately
3,680 SFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Room 1001Approximately
920 SFNon-Friable /
FriableGood Assumed
2’x4’ DrywallAcoustical Ceiling
Panel
Boys & GirlsRestrooms, Staff
Restrooms
Approximately560 SF
Friable Good Assumed
Wainscot MasticBoys & Girls
Restrooms, StaffRestrooms
Approximately1,920 SF
Non-Friable Good Assumed
Vinyl Sheet Flooring &Mastic
Boys & GirlsRestrooms, Staff
Restrooms
Approximately560 SF
Friable Good Assumed
6” Black BaseboardMastic
Boys & GirlsRestrooms, Staff
Restrooms
Approximately200 LF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 9 of 10
Buildings #11: (Rooms 1105-1110)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 1105-1107Approximately
2,700 SFFriable Good Assumed
Drywall & JointCompound
Rooms 1105-1110Approximately
7,320 SFNon-Friable /
FriableGood Assumed
4” Brown BaseboardMastic
Rooms 1105-1110Approximately
780 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 1105-1110Approximately
5,400 SFNon-Friable /
FriableGood Assumed
Buildings #12: Library
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
LibraryApproximately
1,950 SFFriable Good Assumed
Drywall & JointCompound
LibraryApproximately
1,760 SFNon-Friable /
FriableGood Assumed
4” Cream BaseboardMastic
LibraryApproximately
170 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
LibraryApproximately
1,910 SFNon-Friable /
FriableGood Assumed
12”x12” Blue ResilientFloor Tile & Mastic
LibraryApproximately
40 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: McKinna Elementary School Inspection Date: 07/12/2016
Page 10 of 10
Buildings: Cafeteria, Kitchen, Lounge
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” AcousticalCeiling Tile & Mastic
Cafeteria , LoungeApproximately
2,500 SFNon-Friable Good Assumed
Plaster Walls ThroughoutApproximately
2,700 SFNon-Friable Good Assumed
6” Black BaseboardMastic
Lounge, CafeteriaApproximately
300 LFNon-Friable Good Assumed
12”x12” Multi ColoredResilient Floor Tile &
MasticLounge, Cafeteria
Approximately2,500 SF
Non-Friable Good Assumed
Wooden Flooring CafeteriaApproximately
510 SFNon-Friable Good Assumed
Epoxy FlooringKitchen Hallway, Girls
& Boys RestroomApproximately
1,300 SFNon-Friable Good Assumed
Window Putty Cafeteria BuildingApproximately
250 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,000 SFNon-Friable Good Assumed
Rose Avenue Elementary School220 South Driskill Street
Oxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 1 of 8
During an inspection performed on July 12, 2016, TC noted that Rose Avenue Elementary School contained the following asbestoscontaining building materials (ACBM):
Office Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
2,600 SFFriable Good Assumed
12”x12” Grey ResilientFloor Tile & Mastic
ThroughoutApproximately
2,320 SFNon-Friable Good Assumed
6” Black BaseboardMastic
ThroughoutApproximately
280 LFNon-Friable Good Assumed
12”x12” Dark GreyResilient Floor Tile &
MasticTeacher Lounge
Approximately2,800 SF
Non-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
4,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
3,000 SFNon-Friable Good Assumed
Cafeteria Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Tan ResilientFloor Tile & Mastic
ThroughoutApproximately
3,900 SFNon-Friable Good Assumed
6” Black BaseboardMastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 2 of 8
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
3,900 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
WallsApproximately
2,400 SFFriable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
6,000 SFNon-Friable /
FriableGood Assumed
Wood Panel Mastic ThroughoutApproximately
5,000 SFNon-Friable Good Assumed
Cementations Panels Room 127Approximately
268 SFNon-Friable Good Assumed
12”x12” GreenResilient Floor Tile &
MasticRoom 121-122
Approximately180 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,500 SFNon-Friable Good Assumed
Kitchen Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
KitchenApproximately
400 SFFriable Good Assumed
Interior Stucco KitchenApproximately
1,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 3 of 8
Building: #2 Rooms 201-207 & 216-221
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
5,760 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
ThroughoutApproximately
288 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
ThroughoutApproximately
4,800 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticThroughout
Approximately960 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
6,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
2,160 SFNon-Friable Good Assumed
Building: #3 Rooms 301-307 & 210-215
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
5,760 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
ThroughoutApproximately
288 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 4 of 8
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Blue ResilientFloor Tile & Mastic
ThroughoutApproximately
4,800 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticThroughout
Approximately960 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
6,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
2,160 SFNon-Friable Good Assumed
Building: #4 Rooms 401-407 & 204-209
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
5,760 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
ThroughoutApproximately
288 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
ThroughoutApproximately
4,800 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticThroughout
Approximately960 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 5 of 8
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Blue BaseboardMastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
6,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
2,160 SFNon-Friable Good Assumed
Building: #5 Kindergarten
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 201, 202, 203Approximately
6,000 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 201, 202, 203Approximately
5,400 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 201, 202, 203
Approximately2,700 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 201, 202, 203Approximately
400 LFNon-Friable Good Assumed
Drywall & JointCompound
Rooms 201, 202, 203Approximately
3,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
2,000 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 6 of 8
Building: #8
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
ThroughoutApproximately
10,800 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
ThroughoutApproximately
9,072 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticThroughout
Approximately1,728 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
ThroughoutApproximately
800 LFNon-Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
10,000 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
6,000 SFNon-Friable Good Assumed
Building: #9 Portables
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 901 & 902Approximately
1,748 SFFriable Good Assumed
Mastic Associated WithBlue & Black Carpet
MasticRooms 901 & 902
Approximately920 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 7 of 8
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 901 & 902Approximately
825 SFNon-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 901 & 902Approximately
244 LFNon-Friable Good Assumed
Building: #10 Portables
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Room 1001Approximately
8,96 SFFriable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Room 1001Approximately
896 SFNon-Friable Good Assumed
6” Black BaseboardMastic
Room 1001Approximately
117 LFNon-Friable Good Assumed
Drywall & JointCompound
Room 1001Approximately
900 SFNon-Friable /
FriableGood Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Rose Avenue Elementary School Inspection Date: 07/12/2016
Page 8 of 8
Building: #12
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Room 1201Approximately
1,800 SFFriable Good Assumed
Mastic Associated WithGrey Carpet Mastic
Room 1201Approximately
1,800 SFNon-Friable Good Assumed
4” Black BaseboardMastic
Room 1201Approximately
170 LFNon-Friable Good Assumed
Sierra Linda Elementary School2201 Jasmine StreetOxnard, CA 93036
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 1 of 9
During an inspection performed on July 13, 2016 TC noted that Sierra Linda Elementary School contained the following asbestoscontaining building materials (ACBM):
Admin / Cafeteria Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ PinholeAcoustical Ceiling
Panel
Admin Office, WorkRoom, Cafeteria,
Storage
Approximately4,400 SF
Friable Good Assumed
12”x12” Tan ResilientFloor Tile & Mastic
Admin Office Hallway,Work Room, Cafeteria
Approximately350 SF
Non-Friable Good Assumed
2’x4’ FissuredAcoustical Ceiling
PanelNurses
Approximately150 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
4,600 SFNon-Friable /
FriableGood Positive O&M Program
Carpet MasticAdmin Office, Work
RoomApproximately
1,500 SFNon-Friable Good Assumed
12”x12” Tan/GreenResilient Floor Tile and
MasticWorkroom
Approximately50 SF
Non-Friable Good Assumed
Baseboard Mastic WorkroomApproximately
120 LFNon-Friable Good Assumed
2’x4’ GypsumAcoustical Ceiling
PanelKitchen
Approximately50 SF
Non-Friable Good Assumed
PlasterKitchen and Kitchen
StorageApproximately
1,200 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 2 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Baseboard Mastic CafeteriaApproximately
320 SFNon-Friable Good Assumed
12”x12” Gray SpeckledResilient Floor Tile and
MasticCafeteria
Approximately3,200 SF
Non-Friable Good Assumed
Stucco ExteriorApproximately
6,500 SFNon-Friable Good Positive O&M Program
Building #2: (Classrooms 201-202)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
PanelRooms 201, 202
Approximately4,000 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
4,800 SFNon-Friable
/FriableGood Positive O&M Program
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 201, 202 andWorkroom
Approximately4,000 SF
Non-Friable Good Assumed
Mastic with 6” BlueBaseboard
ThroughoutApproximately
480 LFNon-Friable /
FriableGood Assumed
Stucco ExteriorApproximately
3,600 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 3 of 9
Building #3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 301-306 &Workroom
Approximately5,790 SF
Friable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
Rooms 301-306 OnWalls
Approximately250 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
7,700 SFNon-Friable /
FriableGood Positive O&M Program
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 301-306,Workroom
Approximately5,790 SF
Non-Friable Good Assumed
Mastic with 4” BlueBaseboard
ThroughoutApproximately
920 LFNon-Friable Good Assumed
Stucco ExteriorApproximately
6,500 SFFriable Good Positive O&M Program
4’x4’ Transite Panel ExteriorApproximately
385 SFNon-Friable Good Assumed
Building # 4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 401-406 AndWorkroom
Approximately5,790 SF
Friable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
Rooms 401-406 OnWall
Approximately250 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 4 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall and JointCompound
ThroughoutApproximately
7,700 SFNon-Friable /
FriableGood Positive O&M Program
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 401-406 andWorkroom
Approximately5,790 SF
Non-Friable Good Assumed
Mastic with 4” BlueBaseboard
ThroughoutApproximately
920 LFNon-Friable Good Assumed
Stucco ExteriorApproximately
6,500 SFFriable Good Assumed
Transite Panels ExteriorApproximately
385 SFNon-Friable Good Assumed
Building #5:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ FissuredAcoustical Ceiling
Panel
Rooms 501-506 andWorkroom
Approximately5,790 SF
Friable Good Assumed
12”x12” FissuredAcoustical Ceiling Tile
& Mastic
Rooms 501-506 onWall
Approximately250 SF
Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 501-506 onWorkroom
Approximately5,790 SF
Non-Friable Good Assumed
Mastic with 4” BlueBaseboard
ThroughoutApproximately
920 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 5 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
ThroughoutApproximately
7,700 SFNon-Friable /
FriableGood Assumed
Exterior Stucco ExteriorApproximately
6,500 SFNon-Friable Good Assumed
4’x4’ Transite Panels ExteriorApproximately
385 SFNon-Friable Good Assumed
Building #6:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Plaster ThroughoutApproximately
2,200 SFFriable Good Assumed
Stucco ExteriorApproximately
1,500 SFFriable Good Assumed
Wainscot Mastic Boys / Girls RestroomsApproximately
90 SFNon-Friable Good Assumed
Building #7:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Plaster ThroughoutApproximately
2,200 SFFriable Good Assumed
Stucco ExteriorApproximately
1,500 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 6 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Wainscot Mastic Boys / Girls RestroomsApproximately
90 SFNon-Friable Good Assumed
Building #8 (Library / Staff)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’FissuredAcoustical Ceiling
PanelLibrary, Staff
Approximately2,720 SF
Friable Good Assumed
Drywall & JointCompound
Library, StaffApproximately
3,600 SFNon-Friable /
FriableGood Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Library Entrances, StaffEntrance
Approximately100 SF
Non-Friable Good Assumed
12”x12” Tan SpeckledResilient Floor Tile and
MasticLibrary
Approximately25 SF
Non-Friable Good Assumed
Carpet Mastic Library, StaffApproximately
2,400 SFNon-Friable Good Assumed
Mastic with 4” GrayBaseboard
Library, StaffApproximately
360 LFNon-Friable /
FriableGood Assumed
Blue Pattern ResilientFloor Sheeting
Staff Kitchen, StaffRestrooms
Approximately180 LF
Non-Friable Good Assumed
Wainscot Mastic Staff RestroomsApproximately
500 SFNon-Friable /
FriableGood Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 7 of 9
Portables Buildings (901-907):
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 906-907Approximately
1,800 SFFriable Good Assumed
12”x12” AcousticalCeiling Tile and Mastic
902,903 and 904Approximately
3,040 SFFriable Good Assumed
4” Baseboard Mastic Rooms 901-907Approximately
910 LFNon-Friable Good Assumed
12”x12” Gray ResilientFloor Tile & Mastic
Room 901Approximately
650 SFNon-Friable Good Assumed
Vinyl Sheet Flooringand Mastic
Rooms 901 & 902Approximately
110 SFFriable Good Assumed
Carpet Mastic Rooms 901-907Approximately
5,740 SFNon-Friable Good Assumed
Drywall & JointCompound
905, 906, 907Approximately
3,200 SFNon-Friable /
FriableGood Assumed
Exterior StuccoThroughout Exterior of
901-904Approximately
2,000 SFFriable Good Assumed
Portable Buildings (1001-1009 & 1200):
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
1001, 1002, 1003, 1008,1009 & 1200
Approximately5,625 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 8 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Light BlueResilient Floor Tile and
Mastic1200
Approximately1045 SF
Non-Friable Good Assumed
Carpet Mastic 1001-1007 & 1200Approximately
7,320 SFNon-Friable Good Assumed
4” Baseboard Mastic 1001-1009 & 1,200Approximately
395 LFNon-Friable Good Assumed
6” Baseboard Mastic 1200Approximately
140 LFNon-Friable Good Assumed
Vinyl Sheet Flooring &Mastic
1200Approximately
60 SFFriable Good Assumed
Drywall & JointCompound
1001-1009, 1200Approximately
12,430 SFNon-Friable /
FriableGood Assumed
12”x12” Blue ResilientFloor Tile and Mastic
1008, 1009Approximately
1,820 SFNon-Friable Good Assumed
Buildings #11 (Portable 1101):
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Random HoleAcoustical Ceiling Tile
and MasticThroughout
Approximately1,100 SF
Friable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
1,200 SFNon-Friable /
FriableGood Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Sierra Linda Elementary School Inspection Date: 07/13/2016
Page 9 of 9
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Carpet Mastic ThroughoutApproximately
920 SFNon-Friable Good Assumed
Mastic associated With6” Black Carpet Mastic
ThroughoutApproximately
120 LFNon-Friable Good Assumed
12”x12” BeigeResilient Floor Tile and
Mastic
Throughout (UnderCarpet)
Approximately920 SF
Non-Friable Good Assumed
Exterior ExteriorApproximately
1,800 SFNon-Friable Good Assumed
Fremont Middle School1130 North M StreetOxnard, CA 93030
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 1 of 10
During an inspection performed on July 14, 2016 TC noted that Fremont Middle School contained the following asbestos containingbuilding materials (ACBM):
Office Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x2’ AcousticalCeiling Panel
ThroughoutApproximately
5,470 SFFriable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
3,000 SFNon-Friable /
FriableGood Assumed
4” Grey BaseboardMastic
ThroughoutApproximately
300 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
ThroughoutApproximately
5,300 SFNon-Friable Good Assumed
9”x9” Cream ResilientFloor Tile & Mastic
Nurse Office, OfficeApproximately
200 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,850 SFNon-Friable Good Assumed
9”x9” Cream ResilientFloor Tile & Mastic
(Under Carpet Mastic)
Front Office , SecurityDesk
Approximately5,300 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 2 of 10
Library Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
LibraryApproximately
2,520 SFFriable Good Assumed
Drywall & JointCompound
LibraryApproximately
1,010 SFNon-Friable /
FriableGood Assumed
9”x9” Cream ResilientFloor Tile & Mastic
LibraryApproximately
2,520 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
2,000 SFNon-Friable Good Assumed
Plaster Walls RestroomsApproximately
140 SFNon-Friable Good Assumed
Kitchen, Cafeteria, Staff Lounge Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Staff Lounge, CafeteriaApproximately
11,650 SFFriable Good Assumed
2’x2’ AcousticalCeiling Panel
KitchenApproximately
1,640 SFFriable Good Assumed
Drywall & JointCompound
ThroughoutApproximately
7,000 SFNon-Friable /
FriableGood Assumed
4” Baseboard Mastic Cafeteria, Staff LoungeApproximately
560 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 3 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” CreamResilient Floor Tile &
MasticCafeteria, Kitchen
Approximately12,120 SF
Non-Friable Good Assumed
Vinyl Sheet Flooring &Mastic
Staff LoungeApproximately
550 SFFriable Good Assumed
Mastic Associated WithCarpet Mastic
Staff LoungeApproximately
620 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
6,000 SFNon-Friable Good Assumed
6” Black BaseboardMastic
KitchenApproximately
170 LFNon-Friable Good Assumed
P.E. & Locker Rooms Building:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
PE Offices, Boys &Girls Locker Rooms,Hallways In PE Gym,
Boys & GirlsRestrooms
Approximately6,000 SF
Friable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
PE GymApproximately
2,800 SFFriable Good Assumed
Drywall & JointCompound
PE Offices & PE GymApproximately
2,500 SFNon-Friable /
FriableGood Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 4 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Plaster WallsBoys & Girls Locker
RoomsApproximately
4,000 SFNon-Friable Good Assumed
9”x9” Brown ResilientFloor Tile & Mastic
PE Offices & PE GymApproximately
3,250 SFNon-Friable Poor Assumed
Window Putty ExteriorApproximately
480 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
5,600 SFNon-Friable Good Assumed
Building: #2 (202, 203, 205, 206, 207)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 202, 203, 205,206, 207
Approximately2,100 SF
Friable Good Assumed
Drywall & JointCompound
Rooms 202, 203, 205,206, 207
Approximately4,000 SF
Non-Friable /Friable
Good Assumed
4” Baseboard Mastic Rooms 206 & 207Approximately
260 LFNon-Friable Good Assumed
6” Baseboard MasticRooms 203, 205, 206,
207Approximately
480 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 207Approximately
400 SFNon-Friable Good Assumed
12”x12” AcousticalCeiling Tile & Mastic
Rooms 203, 205, 206,207
Approximately450 SF
Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 5 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” CreamResilient Floor Tile &
MasticRooms 206
Approximately830 SF
Non-Friable Good Assumed
12”x12” BrownResilient Floor Tile &
MasticRooms 203 & 205
Approximately800 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
6,000 SFNon-Friable Good Assumed
Building: #3 (301-305 & 307)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 301-305 & 307Approximately
8,690 SFFriable Good Assumed
Drywall & JointCompound
Rooms 301-305 & 307Approximately
8,000 SFNon-Friable /
FriableGood Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 301-305 & 307Approximately
7,765 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 301-305 & 307
Approximately800 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 301-305 & 307Approximately
800 LFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,300 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 6 of 10
Building: #4 (401, 401A, 402, 403)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 401, 401A, 402,403
Approximately6,600 SF
Friable Good Assumed
Drywall & JointCompound
Rooms 401, 401A, 402,403, Boys & Girls
Restrooms
Approximately10,000 SF
Non-Friable /Friable
Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 401, 401A, 402,403
Approximately5,220 SF
Non-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 401, 401A, 402,403
Approximately900 SF
Non-Friable Good Assumed
4” Blue BaseboardMastic
Rooms 401, 401A, 402,403
Approximately1,200 LF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,300 SFNon-Friable Good Assumed
Plaster StorageApproximately
1,200 SFNon-Friable Good Assumed
Building: #6 (601-609)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 601-609Approximately
10,800 SFFriable Good Positive O&M Program
Drywall & JointCompound
Rooms 601-609Approximately
11,340 SFNon-Friable /
FriableGood Positive O&M Program
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 7 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4” Blue BaseboardMastic
Rooms 601-609Approximately
1,170 LFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 601-604, 606,608, 609
Approximately9,720 SF
Non-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 601-604, 606,608, 609
Approximately1,080 SF
Non-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 605 & 607Approximately
2,400 SFNon-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,200 SFNon-Friable Good Positive O&M Program
Plaster StorageApproximately
1,500 SFNon-Friable Good Assumed
Building: #7 (701-710)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 701-710, StaffLounge
Approximately13,000 SF
Friable Good Assumed
Drywall & JointCompound
Rooms 701-710, StaffLounge, Boys & Girls
Restrooms
Approximately14,500 SF
Non-Friable /Friable
Good Positive O&M Program
4” Blue BaseboardMastic
Rooms 701-710, StaffLounge
Approximately1,250 LF
Non-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 701-710, StaffLounge
Approximately11,500 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 8 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
12”x12” Dark BlueResilient Floor Tile &
Mastic
Rooms 701-710, StaffLounge
Approximately1,300 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,300 SFNon-Friable Good Assumed
PlasterStorage & Electrical
RoomApproximately
500 SFNon-Friable Good Assumed
Building: #8 (801-810)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 801-810Approximately
12,000 SFFriable Good Assumed
Drywall & JointCompound
Rooms 801-810, Boys& Girls Restrooms
Approximately14,000 SF
Non-Friable /Friable
Good Assumed
4” Blue BaseboardMastic
Rooms 801-810Approximately
1,200 LFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 801-810Approximately
10,500 SFNon-Friable Good Assumed
12”x12” Dark BlueResilient Floor Tile &
MasticRooms 801-810
Approximately1,250 SF
Non-Friable Good Assumed
Exterior Stucco ExteriorApproximately
4,160 SFNon-Friable Good Assumed
PlasterStorage & Electrical
RoomApproximately
350 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 9 of 10
Building: #9 (901-908)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2’x4’ AcousticalCeiling Panel
Rooms 901-908Approximately
7,360 SFFriable Good Assumed
6” Black BaseboardMastic
Rooms 901-908Approximately
1,040 LFNon-Friable Good Assumed
Mastic Associated WithCarpet Mastic
Rooms 901-908Approximately
7,360 SFNon-Friable Good Assumed
Building: Portables (1201-1205)
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Drywall & JointCompound
Rooms 1201-1204Approximately
2,670 SFNon-Friable /
FriableGood Assumed
Wainscot Mastic Rooms 1201-1204Approximately
560 SFNon-Friable Good Assumed
4” Black BaseboardMastic
Rooms 1201-1205Approximately
460 LFNon-Friable Good Assumed
12”x12” Blue ResilientFloor Tile & Mastic
Rooms 1201-1204Approximately
2,680 SFNon-Friable Good Assumed
12”x12” BeigeResilient Floor Tile &
MasticRoom 1205
Approximately20 SF
Non-Friable Good Assumed
Vinyl Sheet FlooringMastic
Rooms 1201-1204Approximately
120 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Fremont Middle School Inspection Date: 07/14/2016
Page 10 of 10
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithCarpet Mastic
Room 1205Approximately
900 SFNon-Friable Good Assumed
Haydock Middle School647 West Hill StreetOxnard, CA 93033
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 1 of 11
During an inspection performed on July 13, 2016 TC noted that Haydock Middle School contained the following asbestos containingbuilding materials (ACBM):
Building 1 - Administration:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
2,300 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
ThroughoutApproximately
2,200 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
ThroughoutApproximately
140 LFNon-Friable Good Assumed
Yellow Vinyl SheetFlooring & Associated
MasticRestrooms
Approximately200 SF
Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
5,000 SFFriable Good Assumed
Wainscot & AssociatedMastic
RestroomsApproximately
290 SFNon-Friable Good Assumed
Plaster Mechanical RoomApproximately
500 SFFriable Good Assumed
StuccoExterior Including FrontEntrance Gateway Arch
Approximately2,900 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 2 of 11
Building 2 - Cafeteria:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
ThroughoutApproximately
3,600 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Main Rooms, Stage,Office Area
Approximately3,200 SF
Non-Friable Good Assumed
12" x 12" Rose FloorTile & Associated
MasticTeacher's Lounge
Approximately650 SF
Non-Friable Good Assumed
Tan & Black VinylSheet Flooring &Associated Mastic
KitchenApproximately
1,300 SFFriable Good Assumed
4" Burgundy Baseboard& Associated Mastic
Main Room, Stage,Office
Approximately130 LF
Non-Friable Good Assumed
6" Brown Baseboard &Associated Mastic
Teacher's LoungeApproximately
27 LFNon-Friable Good Assumed
Drywall / JointCompound
Stage, OfficeApproximately
250 SFFriable Good Assumed
Panel Mastic Main RoomApproximately
145 SFNon-Friable Good Assumed
Wainscot & AssociatedMastic
KitchenApproximately
1,120 SFNon-Friable Good Assumed
StuccoExterior Including
WalkwaysApproximately
4,900 SFNon-Friable Good Assumed
Plaster ThroughoutApproximately
4,400 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 3 of 11
Building 3:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 1 - 5Approximately
4,800 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Rooms 1 - 5Approximately
4,800 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Rooms 1 - 5Approximately
150 LFNon-Friable Good Assumed
Plaster Rooms 1 - 5Approximately
3,700 SFFriable Good Assumed
StuccoExterior Including
Walkway and ColumnsApproximately
4,100 SFNon-Friable Good Assumed
Building 4:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 6 - 10Approximately
4,800 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Rooms 6 - 10Approximately
4,800 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Room 6 - 10Approximately
150 LFNon-Friable Good Assumed
Drywall / JointCompound
Room 10Approximately
440 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 4 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Wainscot & AssociatedMastic
Room 10Approximately
260 SFNon-Friable Good Assumed
Plaster Rooms 6 - 10Approximately
3,700 SFFriable Good Assumed
StuccoExterior Including
Walkway & ColumnsApproximately
4,100 SFNon-Friable Good Assumed
Building 5:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 11 - 15Approximately
4,800 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Rooms 11 - 15Approximately
4,800 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Rooms 11 - 15Approximately
150 LFNon-Friable Good Assumed
Plaster Rooms 11 - 15Approximately
3,700 SFFriable Good Assumed
StuccoExterior Including
Walkway & ColumnsApproximately
4,100 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 5 of 11
Building 6:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 16 - 20Approximately
4,800 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Room 16 - 20Approximately
4,800 SFNon-Friable Good Assumed
4" Black Baseboard &Associated Mastic
Rooms 16 - 18Approximately
90 LFNon-Friable Good Assumed
PlasterRooms 19 & 20, Old
Heater ClosetsApproximately
3,900 SFFriable Good Assumed
StuccoExterior Including
Walkway & ColumnsApproximately
5,600 SFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Rooms 19 & 20Approximately
60 LFNon-Friable Good Assumed
Building 7:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 701 - 703Approximately
2,800 SFFriable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Room 701 - 704Approximately
400 SFNon-Friable Good Assumed
6" Burgundy Baseboard& Associated Mastic
Room 702 - 704Approximately
75 LFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 6 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" Burgundy Baseboard& Associated Mastic
Rooms 701 & 704Approximately
40 LFNon-Friable Good Assumed
Drywall / JointCompound
Room 704Approximately
660 SFFriable Good Assumed
Plaster Rooms 701 - 704Approximately
3,500 SFFriable Good Assumed
StuccoExterior Including
WalkwayApproximately
3,600 SFNon-Friable Good Assumed
Mastic Associated WithCarpet
Rooms 701 - 703Approximately
2,750 SFNon-Friable Good Assumed
Building 8:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 801 & 802Approximately
2,500 SFFriable Good Assumed
Mastic Associated WithCarpet
Room 801Approximately
1,350 SFNon-Friable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Room 802Approximately
1,300 SFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Rooms 801 & 802Approximately
90 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 801 & 802Approximately
3,900 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 7 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
StuccoExterior Including
Overhang & WalkwaysApproximately
4,000 SFNon-Friable Good Assumed
Building 9:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 8 & 9, WorkRoom, Study Room
Approximately3,500 SF
Non-Friable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Rooms 8 & 9, WorkRoom, Study Room
Approximately4,000 SF
Non-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Rooms 8 & 9, WorkRoom, Study Room
Approximately130 LF
Non-Friable Good Assumed
Drywall / JointCompound
Room 8, Work RoomApproximately
1,200 SFFriable Good Assumed
PlasterRooms 8 & 9, WorkRoom, Study Room
Approximately4,700 SF
Friable Good Assumed
StuccoExterior Including
WalkwayApproximately
3,520 SFNon-Friable Good Assumed
Building 10:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 1, 5, 7, & 10Approximately
4,250 SFFriable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 8 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Mastic Associated WithCarpet
Rooms 5 & 7Approximately
1,900 SFNon-Friable Good Assumed
12"x 12" Rose WithGreen Floor Tile &Associated Mastic
Room 10, Store RoomApproximately
1,210 SFNon-Friable Good Assumed
4" Burgundy Baseboard& Associated Mastic
Rooms 1, 5, & 7Approximately
92 LFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Room 10Approximately
55 LFNon-Friable Good Assumed
6" Black Baseboard &Associated Mastic
Room 5Approximately
13 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 5, 7, & 10Approximately
2,600 SFFriable Good Assumed
StuccoExterior Including
WalkwaysApproximately
4,900 SFNon-Friable Good Assumed
Wainscot & AssociatedMastic
Room 5 RestroomApproximately
140 SFNon-Friable Good Assumed
Building 11 - Library:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanel
ThroughoutApproximately
4,200 SFFriable Good Assumed
12" x 12" WhiteSpeckled Floor Tile &
Associated MasticThroughout
Approximately4,200 SF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 9 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Green Vinyl SheetFlooring & Associated
MasticRestrooms
Approximately100 SF
Friable Good Assumed
4" Burgundy Baseboard& Associated Mastic
ThroughoutApproximately
97 LFNon-Friable Good Assumed
Drywall / JointCompound
ThroughoutApproximately
3,000 SFFriable Good Assumed
Wainscot & AssociatedMastic
RestroomsApproximately
260 SFNon-Friable Good Assumed
StuccoExterior Including
OverhangsApproximately
3,600 SFNon-Friable Good Assumed
Building 12 - PE:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Boys' & Girl's LockerRooms, Boy's & Girl's
Activity Rooms
Approximately5,800 SF
Friable Good Assumed
12" x 12" White WithGreen Floor Tile &Associated Mastic
Boy's & Girl's ActivityRooms
Approximately1,800 SF
Non-Friable Good Assumed
6" Burgundy Baseboard& Associated Mastic
Boy's & Girl's ActivityRoom, Girl's Locker
Room
Approximately90 LF
Non-Friable Good Assumed
6" Black Baseboard &Associated Mastic
Boy's & Girl's LockerRooms
Approximately26 LF
Non-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 10 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" Burgundy Baseboard& Associated Mastic
Girl's Activity RoomApproximately
12 LFNon-Friable Good Assumed
Mirror Mastic Girl's Activity RoomApproximately
240 SFNon-Friable Good Assumed
Plaster ThroughoutApproximately
12,000 SFFriable Good Assumed
StuccoExterior Including
Walkways & OverhangApproximately
9,300 SFNon-Friable Good Assumed
Buildings 13 & 14 - Restrooms Blocks:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
Plaster ThroughoutApproximately
3,000 SFFriable Good Assumed
Stucco ExteriorApproximately
2,100 SFNon-Friable Good Assumed
Building 17:
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
2' x 4' Acoustic CeilingPanels
Rooms 1701 - 1703Approximately
2,900 SFFriable Good Assumed
Mastic Associated WithCarpet
Rooms 1701 - 1703Approximately
2,900 SFNon-Friable Good Assumed
Tabbara Corporation350 N. Lantana Street, Suite 224, Camarillo, CA 93010 Tel: 805-484-3388, Fax: 805-426-8119
3 Year AHERA Reinspection ReportDistrict: Oxnard Elementary School DistrictSchool: Haydock Middle School Inspection Date: 07/13/2016
Page 11 of 11
Materials Location(s) QuantityFriable/Non-
FriableCondition Asbestos
RecommendedAction
4" Green Baseboard &Associated Mastic
Rooms 1701 & 1702Approximately
62 LFNon-Friable Good Assumed
4" Brown Baseboard &Associated Mastic
Room 1703Approximately
31 LFNon-Friable Good Assumed
Drywall / JointCompound
Rooms 1701 - 1703Approximately
3,500 SFFriable Good Assumed
Padded Panel Mastic Rooms 1701 - 1703Approximately
3,500 SFNon-Friable Good Assumed
SECTION 5
RESPONSE ACTIONS
Response Action: There are primarily five response action options which may be applied by theLEA to any friable ACBM.
1. Removal2. Repair3. Encapsulation4. Enclosure5. Maintain
Based on the technician’s observations, some damage was observedand was listed in Section 1 Overview and Objectives; therefore, aresponse action is required.
The Management Plan directs the LEA to apply one or more of these methods to each functionalspace with friable ACBM. By no means do these descriptions waive the requirement forcontacting an EPA-accredited Project Manager prior to initiating major asbestos activities(activities involving greater than three square linear feet of ACBM); nor do these descriptionsrepresent specifications for project performance. Rather, they are provided to describe in detailwhat is meant by the Management Planner’s recommendation.
1. Removal – Removal as described herein is equivalent to the abatement method prescribedand regulated under the OSHA standard Title 29 CFR Part 1926 Subpart A, section1926.58 (Asbestos Standard for Construction Industry). Under this regulation, quantity ofmaterial is not a variable for determining the removal technique employed. This isconsistent with the Management Plan’s intent, in that, when removal of friable ACBMwas recommended, the functional space with friable ACBM must be handled in such away as to reduce exposure potential to the lowest possible level using a range of availableremoval techniques.
Removal is usually accomplished with the confines of a “regulated area” as defined in theabove referenced standard. However, as long as airborne asbestos fiber concentrations arecontrolled using approved techniques in accordance with OSHA standards, the workpractices used for removal are not strictly mandated. The method(s) employed to removefriable ACBM must be sufficient to meet all applicable clearance standards outline inSubpart E, section 76.90 (in addition of meeting OSHA worker protection standards.)
Additionally, the selected technique(s) should be governed by principles of “state-of-the-art” work practices as well as the most recent and stringent regulatory authority(s) inforce. This means that simple regulatory compliance may not be sufficient to ensureproper abatement.
The selected removal techniques should be weighed carefully against the exposurepotentials and the liability associated with initiating an action. A discussion of “state-of-the-art” work practices is provided in 29 CFR 1926.58 Appendix F (non-mandatory)“Work Practices and Engineering Controls for Major Asbestos Removal, Renovation, andDemolition Operations.”
Any ACBM remaining following the completion of a removal response action must beincluded in the O&M Program.
2. Repair – Repair of friable ACBM is a method of restoring the material’s structuralintegrity. In cases where repairing ACBM will require a limited amount of removal,repair may also involve the installation of replacement materials.
In the context of small scale, short-duration O&M activities, repair should not involve thedisturbance of greater than three square linear feet of ACBM and should only beaccomplished with the authorization of a qualified representative of the LEA through thePermit System.
Major repair activities (greater than three square or linear feet of ACBM) must bedesigned by an EPA-accredited Project Manager.
Thermal system insulations are commonly repaired through the application of repair clothwith a bridging encapsulant and re-applying a cover or jacket. Surfacing materials areonly rarely repaired (e.g. applying patching compounds to surfacing or miscellaneousmaterials.)
Any ACBM which remains after completing an encapsulation response action must beincluded in the O&M Program.
3. Encapsulation: Encapsulation of friable ACBM is a method of restoring or reinforcing thematerials structural integrity. It may be used in concert with repair activities as a meansof stabilizing damaged friable materials. Encapsulation is also employed as a means oflocking residual fibers to polyethylene sheeting following “regulated area” removalprojects. The EPA has estimated that true encapsulation is appropriate in only 20% ofabatement contexts.
There are two primary types of encapsulation; bridging agents and penetrating agents. Astheir names imply, bridgers coat the surface of friable ACBM to provide impactresistance, while penetrants coat and penetrate to increase the cohesive (and sometimesadhesive) strength of the material’s internal matrix. Penetrants are commonly applied tofriable Surfacing or Miscellaneous ACBM (e.g. sprayed acoustical ceiling materials)while bridgers are used to repair TSI. Both are used for post-removal encapsulation(residual fiber lockdown) in different contexts.
Any ACBM which remains after completing an encapsulation response action must beincluded in the O&M Program.
4. Enclosure/Encasement: in some rare circumstances, the LEA may elect to enclose orencase friable ACBMs_ Enclosure involves the construction of airtight, impermeable,permanent barriers around the ACBM. Encasement (or spray applied enclosure) methodinvolves low-pressure spray application of a one-to-two layer shell which is then boltedinto structural elements.
This is not usually an appropriate alternative and, consequently should only be prescribedby a Management Planner upon visitation to the site and evaluation of the methods’efficacy (suitability for protecting human health and the environment) in each proposedcontext. Any ACBM which remains after completing an enclosure/encasement responseaction must be included in the O&M Program.
5. Maintain: Inclusion of a material in the O&M Plan is the minimum response actionoption allowed for any functional space with friable ACBM. Also, inclusion in the O&MPlan is mandatory for any friable ACBM which remains after completing any of theabove major asbestos activities.
O&M Program inclusion requires the initiation of a number of activities or preventivemeasures with the goal of reducing a material’s fiber release potential on an ongoingbasis until the material can be removed.
SECTION 6
GLOSSARY OF TERMS
Air erosion: the passage of air over friable ACBM which may result in the release of asbestosfibers.
Asbestos: the asbestos forms varieties of Chrysotile (serpentine); crocidolite (riebeckite); amosite(cummingtonite grunerite); anthophyllite; tremolite; and actinolite.
Asbestos-containing material (ACM): any material or product which contains more than 1percent asbestos.
Asbestos-containing building material (ACBM): surfacing ACM, thermal system insulationACM, or miscellaneous ACM that is found in or on interior structural members or other parts ofa school building.
Asbestos debris: pieces of ACBM that can be identified by color, texture, or composition, ormeans dust, if the dust is determined by an accredited inspector to be ACM.
Damaged friable miscellaneous ACM: friable miscellaneous ACM which has deteriorated orsustained physical injury such that the internal structure (cohesion) of the material is inadequateor, if applicable, which has delaminated such that its bond to the substrate (adhesion) isinadequate or which for any other reason lacks fiber cohesion or adhesion qualities. Suchdamage or deterioration may be illustrated by the separation of ACM into layers; separation ofACM from the substrate; flaking, blistering, or crumbling of the ACM surface; water damage;significant or repeated water stains, scrapes, gouges, mars or other signs of physical injury on theACM. Asbestos debris originating from the ACBM in question may also indicate damage.
Damaged friable surfacing ACM: friable surfacing ACM which has deteriorated or sustainedphysical injury such that the internal structure (cohesion) of the material is inadequate or whichhas delaminated such that its bond to the substrate (adhesion) is inadequate, or which, for anyother reason, lacks fiber cohesion or adhesion qualities. Such damage or deterioration may beillustrated by the separation of ACM into layers; separation of ACM from the substrate; flaking,blistering, or crumbling of the ACM surface; water damage; significant or repeated water stains,scrapes, gouges, mars or other signs of physical injury on the ACM. Asbestos debris originatingfrom the ACBM in question may also indicate damage.
Damaged or significantly damaged thermal system insulation ACM: thermal system insulationACM on pipes, boilers, tanks, ducts, and other thermal system insulation equipment where theinsulation has lost its structural integrity, or its covering, in whole or in part, is crushed, water-stained, gouged, punctured, missing, or not intact such that it is not able to contain fibers.Damage may be further illustrated by occasional punctures, gouges or other signs of physicalinjury to ACM; occasional water damage on the protective coverings/jackets; or exposed ACMends or joints. Asbestos debris originating from the ACBM in question may also indicatedamage.
Encapsulation: the treatment of ACBM with a material that surrounds or embeds asbestos fibersin adhesive matrix to prevent the release of fibers, as the encapsulant creates a membrane overthe surface (bridging encapsulant) or penetrates the material and binds its components together(penetrating encapsulant).
Enclosure: an airtight, impermeable, permanent barrier around ACBM to prevent the release ofasbestos fibers into the air.
EPA Worker Protection Rule: extends the protection afforded by OSHA to all employees inasbestos abatement who may have been excluded from protection by OSHA.
Fiber release episode: any uncontrolled or unintentional disturbance of ACBM resulting invisible emission.
Friable: when referring to material in a school building means that the material, when dry, maybe crumbled, pulverized, or reduced to powder by hand pressure, and includes previouslynonfriable material after such previously nonfriable material becomes damaged to the extent thatwhen dry it may be crumbled, pulverized, or reduced to powder by hand pressure.
Friable asbestos-containing material (ACM): any material containing more than one percentasbestos which has been applied on ceilings, walls, structural members, piping, duct work, or anyother part of a building, which when dry, may be crumbled, pulverized, or reduced to powder byhand pressure. Includes non-friable asbestos-containing material after such previously non-friable material becomes damaged to the extent that when dry it may be crumbled, pulverized, orreduced to powder by hand pressure.
Friable asbestos-containing building material (ACBM): any friable ACM that is in or oninterior structural members or other parts of a school or public and commercial building.
Functional space: a room, group of rooms, or homogeneous area (including crawl spaces or thespace between a dropped ceiling and the floor or roof deck above), such as classroom(s), acafeteria, gymnasium, hallway(s), designated by a person accredited to prepare managementplans, design abatement projects, or conduct response actions.
High-efficiency particulate air (HEPA): refers to a filtering system capable of trapping andretaining at least 99.97 percent of all monodispersed particles 0.3 rim in diameter or larger.
Homogeneous area: an area of surfacing material, thermal system insulation material, ormiscellaneous material that is uniform in color and texture.
Inspection: an activity undertaken in a school building, or a public and commercial building, todetermine the presence or location, or to assess the condition of, friable or non-friable asbestos-containing building material (ACBM) or suspected ACBM, whether by visual or physicalexamination, or by collecting samples of such material. This term includes reinspections offriable and non-friable known or assumed ACBM which has been previously identified. Theterm does not include the following:
1) Periodic surveillance of the type described in 40 CFR 763.92(b) solely for the purpose ofrecording or reporting a change in the condition of known or assumed ACBM;
2) Inspections performed by employees or agents of Federal, State, or local governmentsolely for the purpose of determining compliance with applicable statutes or regulations;Or
3) Visual inspections of the type described in 40 CFR 763.90(i) solely for the purpose ofdetermining completion of response actions.
Local education agency:1) Any local educational agency as defined in section 198 of the Elementary and Secondary
Education Act of 1965 (20 U.S.C. 3381).2) The owner of any nonpublic, nonprofit elementary or secondary school building.3) The governing authority of any school operated under the defense dependents’ education
system provided for under the Defense Dependents’ Education Act of 1978 (20 U.S.C.921, et seq.).
Major fiber release episode: any uncontrolled or unintentional disturbance of ACBM, resultingin a visible emission, which involves the falling or dislodging of more than 3 square or linear feetof friable ACBM.
Management Plan: a site-specific guidance document that the LEA designated person mustfollow in managing the ACBM present in a school building.
Minor fiber release episode: any uncontrolled or unintentional disturbance of ACBM, resultingin a visible emission, which involves the falling or dislodging of 3 square or linear feet or less offriable ACBM.
Miscellaneous ACM: other, mostly nonfriable ACM, products and materials (found on structuralcomponents, structural members or fixtures) such as floor tile, ceiling tile, construction masticfor floor and ceiling materials, sheet flooring, fire doors, asbestos cement pipe and board,wallboard, acoustical wall tile, and vibration damping cloth.
Miscellaneous material: interior building material on structural components, structural membersor fixtures, such as floor and ceiling tiles, and does not include surfacing material or thermalsystem insulation.
Non-friable: material in a school building which when dry may not be crumbled, pulverized, orreduced to powder by hand pressure.
Operations and maintenance program: a program of work practices to maintain friable ACBMin good condition, ensure clean up of asbestos fibers previously released, and prevent furtherrelease by minimizing and controlling friable ACBM disturbance or damage.
Potential damage: circumstances in which:1) Friable ACBM is in an area regularly used by building occupants, including maintenance
personnel, in the course of their normal activities.
2) There are indications that there is a reasonable likelihood that the material or its coveringwill become damaged, deteriorated, or delaminated due to factors such as changes inbuilding use, changes in operations and maintenance practices, changes in occupancy, orrecurrent damage.
Potential significant damage: circumstances in which:• Friable ACBM is in an area regularly used by building occupants, including maintenance
personnel, in the course of their normal activities.• There are indications that there is a reasonable likelihood that the material or its covering
will become significantly damaged, deteriorated, or delaminated due to factors such aschanges in building use, changes in operations and maintenance practices, changes inoccupancy, or recurrent damage.
• The material is subject to major or continuing disturbance, due to factors including, butnot limited to, accessibility or, under certain circumstances, vibration or air erosion.
Preventive measures: actions taken to reduce disturbance of ACBM or otherwise eliminate thereasonable likelihood of the material’s becoming damaged or significantly damaged.
Public and commercial building: the interior space of any building which is not a schoolbuilding, except that the term does not include any residential apartment building of fewer than10 units or detached single-family homes. The term includes, but is not limited to: industrial andoffice buildings, residential apartment buildings and condominiums of 10 or more dwelling units,government-owned buildings, colleges, museums, airports, hospitals, churches, preschools,stores, warehouses and factories. Interior space includes exterior hallways connecting buildings,porticos, and mechanical systems used to condition interior space.
Removal: the taking out or the stripping of substantially all ACBM from a damaged area, afunctional space, or a homogeneous area in a school building.
Repair returning damaged ACBM to an undamaged condition or to an intact state so as toprevent fiber release.
Response action: a method, including removal, encapsulation, enclosure, repair, operations andmaintenance that protect human health and the environment from friable ACBM.
Routine maintenance area: an area, such as a boiler room or mechanical room that is notnormally frequented by students and in which maintenance employees or contract workersregularly conduct maintenance activities.
School: any elementary or secondary school as defined in section 198 of the Elementary andSecondary Education Act of 1965 (20 U.S.C. 2854).
School building:1) Any structure suitable for use as a classroom, including a school facility such as a
laboratory, library, school eating facility, or facility used for the preparation of food.
2) Any gymnasium or other facility which is specially designed for athletic or recreationalactivities for an academic course in physical education.
3) Any other facility used for the instruction or housing of students or for the administrationof educational or research programs.
4) Any maintenance, storage, or utility facility, including any hallway, essential to theoperation of any facility described in this definition of “school building” underparagraphs (1), (2), or (3).
5) Any portico or covered exterior hallway or walkway.6) Any exterior portion of a mechanical system used to condition interior space.
Significantly damaged friable surfacing ACM: damaged friable surfacing ACM in a functionalspace where the damage is extensive and severe.
Small-scale, short-duration activities (SSSD): tasks such as, but not limited to:1) Removal of asbestos-containing insulation on pipes.2) Removal of small quantities of asbestos-containing insulation on beams or above
ceilings.3) Replacement of an asbestos-containing gasket on a valve.4) Installation or removal of a small section of drywall.5) Installation of electrical conduits through or proximate to asbestos-containing materials.
SSSD can be further defined by the following considerations:1) Removal of small quantities of ACM only if required in the performance of another
maintenance activity not intended as asbestos abatement.2) Removal of asbestos-containing thermal system insulation not to exceed amounts greater
than those which can be contained in a single glove bag.3) Minor repairs to damaged thermal system insulation which do not require removal.4) Repairs to a piece of asbestos-containing wallboard.5) Repairs, involving encapsulation, enclosure, or removal, to small amounts of friable
ACM only if required in the performance of emergency or routine maintenance activityand not intended solely as asbestos abatement. Such work may not exceed amountsgreater than those which can be contained in a single prefabricated mini-enclosure. Suchan enclosure shall conform spatially and geometrically to the localized work area, inorder to perform its intended containment function.
Surfacing ACM: interior ACM that has been sprayed on, toweled on, or otherwise applied tosurfaces (structural members, walls, ceilings, etc.) for acoustical, decorative, fireproofing, orother purposes. Surfacing material that is ACM.
Surfacing material: material in a school building that is sprayed-on, troweled-on, or otherwiseapplied to surfaces, such as acoustical plaster on ceilings and fireproofing materials on structuralmembers, or other materials on surfaces for acoustical, fireproofing, or other purposes.
Thermal system insulation: material in a school building applied to pipes, fittings, boilers,breeching, tanks, ducts, or other interior structural components to prevent heat loss or gain, orwater condensation, or for other purposes.
Thermal system insulation ACM: insulation used to control heat transfer or preventcondensation on pipes and pipe fittings, boilers, breeching, tanks, ducts, and other parts of hotand cold water systems; heating, ventilation, and air-conditioning (HVAC) systems; or othermechanical systems that is ACM.
Vibration: the periodic motion of friable ACBM which may result in the release of asbestosfibers.
SECTION 7
INSPECTOR INFORMATION
AHERA Certified Inspectors, Certified Site Surveillance Technicians or Certified AsbestosConsultant:
• AHERA trained Building Inspectors, Certified Asbestos Consultants (CACs) or SiteSurveillance Technicians (SSTs) will participate in conducting periodic inspections andO&M program maintenance (if needed).
• May or may not be members of the in-house custodial or maintenance staff, but will beavailable to support and consult with the Asbestos Program Manager and MaintenanceSupervisor as necessary for proper implementation and operation of the O&M program.
• Properly trained and certified individuals will be used to collect samples of suspectmaterials, perform monitoring and clearance sampling of abatement work, and performperiodic re-inspection of all asbestos materials per the terms of the O&M Program.
• They may also provide training and consulting services to in-house staff as required, tomaintain compliance with the O&M Program.
Certified Asbestos Consultant:
Company Name: Tabbara Corporation
Certified Asbestos Consultant: Ivan Dean Meyers
Certification Number: 02-3228
Signature:
Certified Site Surveillance Technician:
Company Name: Tabbara Corporation
Certified Site Surveillance Tech: Antonio Chavez
Certification Number: 04-3632
Signature:
Licensed Asbestos Abatement Contractor
• The Asbestos Program Manager shall maintain a list of local, qualified asbestosabatement contractors who will perform Class I and Class II abatement activities, and beon call for emergencies or other situations where in-house Maintenance Staff are notqualified or equipped to respond.
• The Asbestos Program Manager shall pre-screen local contractors to ensure they areproperly insured and licensed. Each contractor shall provide documentation of training,insurance, licensing, etc. upon request.
Employees
• Custodial and Maintenance staff should clear any work that may disturb ACM with theO&M Program Manager or Maintenance Supervisor before work begins.
• Only trained and qualified maintenance staff shall perform tasks where asbestos may bedisturbed or contacted.
• Shall avoid sanding or stripping floor tiles that contain asbestos or asbestos-containingmastic underneath.
• Shall report any damage to suspected or known ACM to their supervisor or the ProgramManager.
SECTION 8
ABCs OF ASBESTOS IN SCHOOLS
United States Revised Environmental Protection August 2003 Agency
Office of Pollution Prevention and Toxics
The ABCs Of Asbestos In Schools
EPA-745-K93-017
IntroductionIntroductionIntroductionIntroductionIntroduction • When is asbestos a problem? • What should my school and school
district be doing about asbestos? • What can I do to help?
The Environmental Protection Agency (EPA) is releasing this updated document in conjunction with the National Parent Teacher Association (PTA) and the National Education Association (NEA) due to an ongoing concern about asbestos in elementary and secondary schools nationwide.
This pamphlet can help parents and teachers answer questions and learn the facts about asbestos in schools. It also outlines the responsibilities of school boards and other school officials to protect school children and employees from possible exposure to asbestos.
1
Aa Bb Cc Dd Ee Ff G
sbestos fibers can cause serious health problems. If inhaled, they can disrupt the
normal functioning of the lungs. Three specific diseases – asbestosis, lung cancer, and another cancer known as mesothelioma – have been linked to asbestos exposure. These diseases do not develop immedi-ately after inhalation of asbestos fibers; it may be 20 years or more before symptoms appear.
In general, as with cigarette smoking, the more asbestos fibers a person inhales, the greater the risk of developing an asbestos-related disease. The most severe health problems from asbestos exposure have been experienced by some workers who held jobs in industries such as shipbuilding, where they were exposed to very high levels of asbestos in the air. These employees worked directly with asbestos materials on a regular basis as a part of their jobs. Much uncer-tainty surrounds the risk from
exposure to low levels of asbestos fibers.
Nevertheless, the risk of school children being exposed to even low levels of asbestos is a concern. Acting on this concern, Congress passed the Asbestos Hazard Emergency Response Act (AHERA) in 1986 to protect school children and school employees from exposure to asbestos in school buildings. This pamphlet describes key parts of these federal asbestos require-ments for schools.
The Asbestos IssueThe Asbestos IssueThe Asbestos IssueThe Asbestos IssueThe Asbestos Issue
A
2
What Exactly IsWhat Exactly IsWhat Exactly IsWhat Exactly IsAsbestos?Asbestos?Asbestos?Asbestos?
Where IsWhere IsWhere IsWhere IsAsbestos LikelyAsbestos LikelyAsbestos LikelyAsbestos Likelyto Be Found?to Be Found?to Be Found?to Be Found?
g Hh Ii Jj Kk Ll Mm Nn What Exactly Is Asbestos?
A sbestos is a mineral found in certain types of rock formations. When mined and processed, it
takes the form of very small fibers which are usually invisible to the naked eye. A typical asbestos fiber is 1,200 times smaller than a strand of human hair. These individual fibers are generally mixed with a material which binds them together so that they can be used in many different products. Because the fibers are so small and light, they can remain in the air for many hours if they are released from asbestos-containing material. This increases the chance that someone will inhale them.
Asbestos became a popular commercial product because it is strong, won’t burn, resists corrosion, and insulates well. Its commercial use in the United States began in the early 1900s, when it was used as insulation in steam engines. Since then asbestos has been used to create about 3,000 different products, including insulation and fireproofing. The peak years of asbestos use in schools were from World War II until the 1970s.
Where Is Asbestos Likely to Be Found?
E PA estimates that there are asbestos-containing materials in most of the nation’s primary,
secondary and charter schools. Asbestos is most commonly used in schools as insulation and in building materials. It has also been used in floor and ceiling tile, cement asbes-tos pipe, corrugated paper pipe wrap, acoustical and decorative insulation, pipe and boiler insulation, and spray-applied fireproofing. The fluffy white substance you may find above a dropped ceiling, for ex-ample, is one type of spray-applied material. The amount of asbestos in
3
When IsWhen IsWhen IsWhen IsAsbestos aAsbestos aAsbestos aAsbestos aProblem?Problem?Problem?Problem?
Aa Bb Cc Dd Ee Ff G these products varies widely, from less than 1 to 100 percent, depending on the use. Pipe and boiler insulation typically contains more asbestos than other building materials. The precise amount of asbestos in a product cannot always be deter-mined from labels – since most products used in the past were not labeled – or by asking the manufac-turer. Instead, positive identification of asbestos requires analysis of samples by a qualified laboratory.
When Is Asbestos a Problem?
I ntact and undisturbed asbestos materials generally do not pose a health risk. Asbestos
materials, however, can become hazardous when, due to damage or deterioration over time, they release fibers. If the fibers are inhaled, they can lead to health problems.
The potential for an asbestos-containing material to release fibers depends primarily on its condition. If the material, when dry, can be crumbled by hand pressure – a condition known as “friable” – it is more likely to release fibers, particu-larly when damaged. The fluffy spray-applied asbestos fireproofing material is generally considered “friable.” Pipe and boiler insulation materials can also be “friable,” but they often are enclosed in a Continued on p. 6
4
g Hh Ii Jj Kk Ll Mm Nn What Is the Government DoingWhat Is the Government DoingWhat Is the Government DoingWhat Is the Government DoingWhat Is the Government Doing about Asbestos In Schools?about Asbestos In Schools?about Asbestos In Schools?about Asbestos In Schools?about Asbestos In Schools?
he federal government has been regulating asbestos for a
number of years. Progress is being made to limit the uses of asbestos and to identify substitute materials.
AHERA required EPA to develop regulations creating a comprehensive framework for dealing with asbestos in public and nonprofit private elemen-tary and secondary schools. The regulations were published on October 30, 1987.
The AHERA schools rule requires all public school districts and private schools, known as local education agencies or LEAs, to inspect all school buildings for both friable and nonfriable asbes-tos; to develop plans to manage asbestos in schools; and to carry out the plans in a timely fashion. The rule also provides an opportunity for parents, teachers, and other
school employees to become familiar with and involved in their school’s asbestos management program. School officials are required to notify parent, teacher and employee groups about asbestos-related activities. For more information contact theTSCA Hotline at (202) 554-1404 or the asbestos hotline at (800) 471-7127. You can also visit our website at http:// www.epa.gov/asbestos/ asbestos_in_schools.html.
T
5
What Are the Proper Methods forWhat Are the Proper Methods forWhat Are the Proper Methods forWhat Are the Proper Methods forManaging Asbestos?Managing Asbestos?Managing Asbestos?Managing Asbestos?
Aa Bb Cc Dd Ee Ff G protective casing which prevents fiber release unless the casing is damaged. Some materials, which are considered “nonfriable,” such as vinyl-asbestos floor tile, can also release fibers when sanded,
sawed or otherwise disturbed. Materials such as asbestos cement pipe can release asbestos fibers if they are broken or crushed when buildings are demolished, reno-vated or repaired.
What Are the Proper Methods for Managing Asbestos?
M ost asbestos-contain-ing material can be properly managed where it is. In fact,
asbestos that is managed properly and maintained in good condition appears to pose relatively little risk to students and school employ-ees. Accordingly, the AHERA schools rule rarely requires the removal of asbestos materials.
Proper asbestos management begins with a comprehensive inspection by qualified, trained and experienced inspectors, accredited through an EPA or state-approved training course. Inspecting the condition of asbestos materials – initially with AHERA-accredited inspectors and at least semi-annually with trained custodial or maintenance staff – is extremely important so that changes in the material’s condition, such as
damage or deterioration, can be detected and corrected before the condition worsens. Sometimes normal school or maintenance activities can damage asbestos material and cause fiber release, particularly if the material is “friable.” A thorough initial inspection and regular surveillance can prevent accidental exposure to high levels of asbestos fibers.
The methods (see page 7), in AHERA terminology, are asbestos “response actions.” The last three methods of response actions – encapsulation, enclosure, and removal – and sometimes the second method – repair – must be done by accredited asbestos professionals.
The final response action, asbestos removal, is generally necessary only when the material damage is extensive and severe,
6
How THow THow THow To Respond?o Respond?o Respond?o Respond?
::::
g Hh Ii Jj Kk Ll Mm Nn How To Respond? Proper methods for dealing with asbestos are:
• Developing and carrying out a special
containing materials are kept in good condition. This is the most common method when the materials are in good condition at the time of initial inspection.
•
• Spraying the material with a sealant to prevent fiber release – a process called encapsulation.
• Placing a barrier around the materials, which is known as an enclosure.
• Removing asbestos – under special procedures.
maintenance plan to insure that asbestos-
Repairing damaged pipe or boiler covering, which is known as thermal system insulation.
and other actions will not control fiber release. Although the AHERA schools rule does not prohibit schools from removing any asbestos materials, removal decisions should not be made lightly. An ill-conceived or poorly conducted removal can actually increase rather than eliminate
risk. Consequently, all school removal projects must be de-signed, supervised, and conducted by accredited professionals and should be performed in accor-dance with state-of-the-art procedures. In addition, schools may wish to hire an experienced and qualified project monitor to
7
What Should My School &What Should My School &What Should My School &What Should My School &School District Be Doing?School District Be Doing?School District Be Doing?School District Be Doing?
Aa Bb Cc Dd Ee Ff G oversee the asbestos contractor’s work to make sure the removal is conducted safely.
Only an AHERA-accredited management planner – an asbestos professional with proper training, qualifications, and experience – is
authorized to advise school officials on which response action is appro-priate for a particular situation. The final selection of the proper method is up to school officials after they receive the advice of the school’s accredited management planner.
What Should My School &School District Be Doing?
U nder the AHERA schools rule, each local education agency (LEA, which
means a school district or private school) must take the following asbestos-related actions:
1 Designate and train a person to oversee asbestos-related activities in the school system.
2 Inspect every school building for “friable” and “nonfriable” asbestos-containing building materials.
3 Prepare a management plan for managing asbestos and controlling exposure in each school.
4 Consult with accredited inspec-tion and management professionals
to identify and carry out whatever asbestos actions are necessary and appropriate to protect health and the environment. These actions or methods must be documented in the management plan.
5 Notify the public about the asbestos inspection and the availability of the asbestos man-agement plan for review.
6 Use only properly accredited persons to conduct inspections, to develop the asbestos management plan, and to carry out the appropri-ate response actions.
7 Keep records of all asbestos related activities in the plan and make them available for public review.
8
g Hh Ii Jj Kk Ll Mm Nn
School officials may choose a consultant or one of their own employees to oversee their asbes-tos program. This designated person must meet certain training requirements, and serves as the single point of contact for public information about asbestos-related activities in the LEA. He or she is responsible for: • Ensuring that initial asbestos
inspections, re-inspections every three years, and semi-annual surveillance activities are conducted properly by qualified personnel.
• Including results of the inspec-tion in the management plan. The plan must identify all asbestos-containing building materials found in schools and recommend actions for dealing with asbestos hazards.
• Preparing a management plan (for schools built after October 12, 1988) for submission to the appropriate state Agency prior to the school being used as a school building. ment plan should be maintained and updated with records of response actions, periodic
What Does the LEAWhat Does the LEAWhat Does the LEAWhat Does the LEAWhat Does the LEA Designated Person Do?Designated Person Do?Designated Person Do?Designated Person Do?Designated Person Do?
surveillance of asbestos containing materials (ACM) and all re-inspections.
• Making sure that custodial and maintenance workers receive required safety training and information about the location of asbestos-containing materials in their school. Warning labels must be posted in all routine maintenance areas, such as boiler rooms, where asbestos-containing building materials are found.
• Ensuring that response actions specified in the management plan are carried out according to the plan’s timetables. The regula-tions require that all LEAs were to begin to carry out their management plans no later than July 9, 1989.
• Seeing that all asbestos records required by the regulations are accurately maintained.
• Informing all teacher, parent and employee organizations at least once a year about the asbestos activities in each school and about the availabil-ity of the management plan for their review.
The manage-
9
What Can I Do to Help?What Can I Do to Help?What Can I Do to Help?What Can I Do to Help?
Step One:Step One:Step One:Step One:AwarenessAwarenessAwarenessAwareness
Aa Bb Cc Dd Ee Ff G What Can I Do to Help?
A s a parent, teacher, student, service worker or other school employee,
the most important thing you can do first is to learn about your school’s asbestos activities. As you do so, remember that the mere presence of asbestos in a school doesn’t necessarily mean that the health of its occupants is endangered. Again, asbestos that is managed properly and maintained in good condition poses relatively little risk. Federal regulations do not require the removal of all friable asbestos from schools until the building is demolished. In fact, during the life of the building, other methods of dealing with the material are often preferable to removal.
In those cases when removing asbestos is deter-mined to be the appropriate
decision, the work must be done under strict controls by trained, qualified and experi-enced asbestos professionals who are properly accredited under AHERA.
Step One: Awareness
Your first step is to make sure your school has prepared an asbestos management plan as required by AHERA. By becom-ing familiar with this plan, you will know if asbestos materials are in the school, what plans the school has for managing this asbestos, and when these activities are scheduled to occur.
10
g Hh Ii Jj Kk Ll Mm Nn objects are thrown up against it. Students and others who use the gym should be warned to avoid such activities.
Step TStep TStep TStep TStep Two:wo:wo:wo:wo: MinimizeMinimizeMinimizeMinimizeMinimize DisturbanceDisturbanceDisturbanceDisturbanceDisturbance
There are several simple things you can do to minimize your exposure to asbestos. The most important one is to find out which materials in your school contain asbestos; you should be able to get this information from your LEA’s designated person or from the school’s management plan.
Once you know where asbestos is, use special care to insure that any day-to-day activities, such as repair or maintenance work, do not disturb the material. In fact, special training is required to participate in any maintenance activities which might disturb asbestos. In schools, asbestos-containing materials can also be damaged by student activi-ties. For example, an asbestos ceiling in a gym may be dis-turbed if basketballs or other
AHERA MANAGEMENT
PLAN FOR MY SCHOOL
11
Aa Bb Cc Dd Ee Ff G
ll of us are respon-sible. Making the AHERA schools rule work to protect the
nation’s school children and employees is a joint responsibility of the LEA and its officials, school employees, parents, students,
federal and state governments, and asbestos control professionals.
EPA conducts compliance inspections of a sample of schools each year to make sure they are obeying the law. The Agency is responsible for insuring that schools comply with AHERA and it will investigate reported violations. Since the AHERA schools rule is inten-tionally designed to involve parent, teacher and other school employee organizations, it is impor-tant that you work with your school to make sure that its asbestos program is properly conducted.
Who IsWho IsWho IsWho IsWho Is ResponsibleResponsibleResponsibleResponsibleResponsible for Makingfor Makingfor Makingfor Makingfor Making AHERA Work?AHERA Work?AHERA Work?AHERA Work?AHERA Work?
A
12
Where Can I GetWhere Can I GetWhere Can I GetWhere Can I GetMore Information?More Information?More Information?More Information?
g Hh Ii Jj Kk Ll Mm Nn Where Can I Get More Information?
U nder AHERA, citizens have the opportunity to be-come informed about
asbestos activities in their schools. If you have a question or concern about those activities, you should first contact your LEA designated person. This person knows the most about the asbestos situation in your school. When you find out who this person is, ask him or her what steps your school has taken, and will continue to take, to meet the requirements of the AHERA schools rule.
The LEA designated person also can tell you which agency in your state government is respon-sible for state AHERA activities. The same agency usually is responsible for reviewing the LEA’s asbestos management plan. This LEA designated person also should be aware of any local asbestos control requirements.
State AHERA designees also are a good source of information. These officials can help you better understand the AHERA schools rule
and can answer questions about your school’s asbestos activities.
Local, state, and national parent and teacher organizations are other good sources of information about asbestos in schools. Many of these
13
groups worked with EPA in devel-oping the AHERA schools rule, and some have started their own educational efforts to improve understanding of the AHERA requirements and proper asbestos control practices.
The EPA Toxic Substances Control Act (TSCA) Hotline is available to answer your questions about the new AHERA regulations and about asbestos in general. You can obtain a variety of information by calling the TSCA Hotline at (202) 554-1404 or the asbestos hotline at (800) 471-7127. You can also visit our website at http://www.epa.gov/ asbestos/asbestos_in_schools.html.
Finally, EPA has an asbestos ombudsman to help citizens with asbestos-in-schools issues, ques-tions, and complaints. This office can be reached through a toll-free number at (800) 368-5888.
14
Attachment F
PROP 39 OXNARD SCHOOL DISTRICT HVAC DESIGN BUILD SERVICES PROJECT BID/CONSTRUCTION SCHEDULE
Start Stop Notes
RFP 2/7/2018 4/19/2018
Request to VC Star Deadline 2/9/2018 2/9/2018
Public Advertisement 1 2/14/2018 2/14/2018
Invitation Email 2/15/2018 2/15/2018 1 day after first ad
Public Advertisement 2 2/21/2018 2/21/2018 1 week after first ad
Bidder Conference/Job Walk 2/22/2018 2/22/2018 2 days after second ad
Bidder Questions 2/23/2018 2/28/2018 1 week after job walk
Q&A Response 3/1/2018 3/5/2018 3 days Q's due
Proposals Due 3/6/2018 3/12/2018 1 week after RFI Response
Bid Scoring 3/19/2018 3/26/2018
NPA 3/30/2018 4/6/2018 Draft to Supt. 4/6/18
Board Meeting 4/18/2018 4/18/2018
Notice of Approval 4/19/2018 4/19/2018
Construction 4/19/2018 8/15/2018
Pre-Construction Meeting 4/23/2018 4/23/2018
NTP 4/23/2018 4/23/2018
Material Submittal 4/23/2018 5/3/2018 10 days after NTP
Submittal Review 5/3/2018 5/7/2018
Design Approval 5/7/2018 5/7/2018
Equipment Lead Time 5/7/2018 6/15/2018
Last Day of School 6/14/2018 6/14/2018 8 weeks for installation
Construction 6/18/2018 8/10/2018 Construction ends Friday before first week of school
Staging and Mobilization 6/15/2018 6/18/2018
Substantial Completion 8/3/2018 8/3/2018
Punch List and Commissioning 8/6/2018 8/14/2018
First Day of School 8/15/2018 8/15/2018