Overview of Systematic Occupational Health Enhancement Level Programme (SoHELP)
1
25 & 26 April 2017 |SOCSO REHABILITATION CENTRE
SCOPE
Background
Occupational Disease Statistic
SoHELP Inclusion Criteria
Level of Implementation
SoHELP Methodology
CEP
Output & Outcome
SoHELP Progress Monitoring
2 ITS Management Sdn Bhd
BACKGROUND Inline with OSH MP15 aims:
Prevent the development of occupational diseases
Continue under OSH MP2020 – Strategy 4 re-engineering industrial hygiene
Low level of compliance with IH regulations especially among SME.
IH regulation were seen to be complicated and costly.
Two (2) years target for OH intervention program:
High impact
Simple
Low cost
Can be implemented in all types of industry depending on their resources
High risk workplace
3 ITS Management Sdn Bhd
AIMS
OH Program should be :
High impact
Simple
Low cost
Marketable
Well known
Collaboration between Chemical Management, IH and OH
“SoHELP – Enhance Industrial Hygiene”
4 ITS Management Sdn Bhd
NATIONAL ACCIDENT RATE (2004-2015)
5 ITS Management Sdn Bhd
58365 51829 49598 47469 44918 39448 41467 41593 41540 43795 42148 38753
5.84
5.164.77
4.524.15
3.61 3.683.4 3.31 3.28 3.1
2.81
7.176.93
7.246.95 6.9
6.3 6.456.17
4.64 4.62 4.214.84
0
1
2
3
4
5
6
7
8
0
10000
20000
30000
40000
50000
60000
70000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
total accidents accident rate/1000 workers fatality rate/100000 workers
STATISTIC OF OCCUPATIONAL DISEASE AND POISONING
REPORTED TO DOSH 2005 – 2016 (Jan – Apr)
7 ITS Management Sdn Bhd
OCCUPATIONAL DISEASES AND POISONING REPORTED
ACCORDING TO TYPE OF DISEASES 2015
8 ITS Management Sdn Bhd
Type of Disease No of case reported
Occupational Lung Diseases (OLD) 126
Occupational Skin Diseases (OSD) 46
Occupational Noise Induced Hearing Loss (NIHL) 5366
Occupational Muscular - Skeletal Disorders (OMD) 249
Occupational Poisoning 32
Disease cause by Physical Agent 5
Disease cause by Biological Agent 73
Occupational Cancer 3
Psychosocial Problem 2
Other Types of Occupational Diseases 19
Non Occupational Diseases 39
Total 5960
OCCUPATIONAL HEALTH BEYOND 2 YEARS (beyond 2016)
9 ITS Management Sdn Bhd
Nanomaterials
Mental health
Biological Hazards
CRITERIA FOR INCLUSION OF WORKPLACE
IN THE PROGRAM
11 ITS Management Sdn Bhd
Normal Area
Sub-critical Area
Critical Area
• LOW PRIORITY• Low exposure• Less potential occurrence of OD• Low frequency monitoring
• MODERATE PRIORITY• Medium exposure• Great potential occurrence of OD• High frequency of monitoring
• HIGH PRIORITY• High exposure• High occurrence of OD• Close monitoring
SoHELP MODELDIAGNOSTIC TOOL
CHEMICAL MANAGEMENT
KIT
OTHERS(HEAT STRESS,
LIGHTING, IAQ ETC)
ERGONOMIC INTERVENTION
KIT
KEY PERFORMANCE INDICATOR
HEARING CONSERVATION
KIT
• Health effect• Risk factors• Simplified Ergo
Checklist• Control• CD Ergo Check
point
• USECHH + Checklist
• SIRAC Online• Chemical Reg.• Label & SDS• Control • CLASS
• Intro Noise• Legislation +
Checklist• Audiometric• Control• PPE
• Legislation/Guidelines/ICOP
• Statistic• BOH• IH Inspection• Complaint
PROMOTIONAL ACTIVITIES
15
LEVEL ERGONOMICS CHEMICALS NOISE
5(EXCELL-
ENT)
• Implement all action to be taken identify in the ergonomic checklist
• No new case of health problem related to ergonomic
• Implementation of continuous improvement programmes on ergonomic
• Implement all action to be taken in the CHRA/SiRAC report
• No new case of occupational disease related to chemical
• Implementation of continuous improvement programmes on chemical management
• Implement all action to be taken in the Noise assessment report
• Annual audiometric test• Hearing conservation
campaign• Implementation of continuous
improvement programmes on hearing conservation
4(ADVANCED)
• Implement most (50%) action to be taken identify in the ergonomic checklist
• Reporting/notification of occupational diseases cases related to ergonomic.
• Implement most (50%) action to be taken in the CHRA/SiRAC report
• Good record system• Good ventilation system• Reporting/notification of occupational
diseases cases related to chemicals
• Implement 50% of actions to be taken in the Noise assessment report
• Baseline audiometric test• Reporting/notification of
occupational diseases cases related to noise.
3(INTER-
MEDIATE)
• Conduct risk assessment• Conduct training• Establish SOP in Ergonomics• Conduct Ergonomic
Checklist• Warning signs• Provide PPE
• Conduct CHRA/SiRAC• Conduct information, instruction and
training• Implementation PPE programme• Warning signs
• Conduct noise assessment• Provide PPE & control• Identify hearing protection
zone• Warning signs• Provide information• Record keeping• Provide training & supervision
2(BASIC)
• PIC attended SOHELP program
• PIC conduct internal training on SOHELP
• PIC prepare Action Plan
• PIC attended SOHELP program• PIC conduct internal training on SOHELP• Prepare chemical register• Label of CHH & SDS• Availability and maintenance of welfare
facility• PIC prepare Action Plan
• PIC attended SOHELP program• PIC conduct internal training
on SOHELP• PIC prepare Action Plan
1(ENTRY)
• Commitment from management to implement program• Appointment of person- in-charge (PIC) to implement program
SoHELP METHODOLOGY 1. Invitation letter is sent to selected workplaces.
2. SHO will be trained by DOSH and agreement letter by the company to
participate in SoHELP will be issued.
3. SHO will brief Safety and Health Committee as well as workers about
SoHELP.
4. The company will conduct workplace inspection base on SoHELP
checkpoints.
5. The company will plan and implement all SoHELP relevant requirements.
6. DOSH will visit and verify SoHELP level at participating workplaces. If
necessary, coaching programme will be conducted (6 times in 14 months).
7. At the end of each calendar cycle, SHO will be rewarded with CEP base
on the level achieved. All participating companies will be given certificate of
appreciation at the end of SoHELP (14 months).
16 ITS Management Sdn Bhd
17 17
Invitation on involvement in SoHELP
Training for SHO (Enabler)/DOSH Officer (Verifier)
SHO give training to SHC and workers
Workplace Inspection base on SOHELP’s Checkpoint / Checklist
Target:Metal, Chemical and Electronic based Pre-requisite:Have SHOHave SHCAgree to give high commitment by top management (signature)
6 times
FIGURE 1 : METHODOLOGY OF
SOHELP
Implementation model
Role of DOSH Role of Company
Implement intervention programs to follow SOHELP’s criteria
Visit company and decide implementation level (SOHELP checkpoint)
Give CEP to SHO based on level achieved at the end of the year
Coaching/ consultation (level 1 to 5)
Level Verification
1
3
2
7
6
4
5
START
END
18
SoHELP IMPLEMENTATION GANTT CHART (PHASE 1)
ITS Management Sdn Bhd
No. Aktivities2016
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1.Attend SoHELP
training
2. Train SHC members
3.SoHELP Checkpoints Assessment I
4.Develop Detailed Action Plan (AP)
5. Implementation of AP
6.SoHELP Checkpoints Assessment II
7.SoHELP Checkpoints Assessment III
8.SoHELP Checkpoints Assessment IV
9. CEP Collection Y1
10.Compile Proof of Implementation
19
SoHELP IMPLEMENTATION GANTT CHART
ITS Management Sdn Bhd
No. Aktivities2017
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
11. Implentation of AP
12.SoHELP Checkpoints Assessment V
13.SoHELP Checkpoints Assessment VI
14. CEP Collection Y2
15.Obtain certificate of appreciation
16.Compile Proof of Implementation
CEP FOR SoHELP
20
Proposed CEP Points:
This CEP is given base on current level.
SHO can apply for CEP once per calendar year.
SoHELP Level must be higher than previous year. If the higher level cannot be achieved in the next year, CEP may be considered if PIC can provide proof of actions taken in order to improve workplace condition pertaining to SoHELPrequirement.
If the PICs are more than one (1), proof of participation must be provided by each and everyone of PIC.
Verification of each level must be done by SoHELP Verifier.
ITS Management Sdn Bhd
SOHELP Level
SoHELP Components L3 L4 L5
Chemical 5 8 10
Ergonomic 5 8 10
Noise 5 8 10
TOTAL 15 24 30
EXAMPLE OF CEP CALCULATION
21
*Maximum point was given in the previous year
ITS Management Sdn Bhd
SoHELP Components2016 2017
Level CEP Level CEP
Chemical L4 8 L5 10
Ergonomic L3 5 L5 10
Noise L5 10 L5 10*
TOTAL 23 30
OUTPUT of SoHELP
22
Reduction of health risk exposure in relation of ergonomics,
chemicals and noise for around 40,000 workers in the high risk
workplace.
220 X 180 per workplace
Total of 2200 members of Safety and Health Committee
(SHC) successfully trained to implement SHC functions
through SoHELP.
220 X 10 per workplace = 2200
Total of 220 SHO/employer successfully trained as SoHELP
Enabler (SOHELP-E).
Total of 88 DOSH officers successfully trained to be SoHELP
Verifier (SOHELP-V).
ITS Management Sdn Bhd
OUTCOME OF SYSTEMATIC OCCUPATIONAL HEALTH
ENHANCEMENT LEVEL PROGRAMME (SoHELP)
23
Significant improvement in awareness and
implementation of SoHELP in high risk workplaces.
ITS Management Sdn Bhd
SoHELP TARGET VS. ACHIEVEMENT
24
PROPOSED TARGET NUMBER OF SHO
ITS Management Sdn Bhd
State No. of SHO
Johor & Selangor20 SHO X 2
= 40 pax
WPKL, Pulau Pinang, Kedah, Sarawak,Sabah, Perak, Terengganu, Pahang, Melaka, & Negeri Sembilan
15 SHO x 10= 150 pax
Kelantan, Perlis, & Labuan10 SHO X 3
= 30 pax
TOTAL NO. OF SHO 220 pax
SoHELP PARTICIPATION STATISTICS
25
PROPOSED TARGET NUMBER OF SHO
ITS Management Sdn Bhd
State TargetAchie
ved
% Participati
on
Number of OSH PractitionersNo Of
Workers Benefited
AvgWorkers / WorkplaceSHO Assessor Others
Sarawak 15 16 107 18 2 0 9,989 624
Sabah 15 16 107 8 1 7 3,050 190Melaka 15 16 107 22 1 16 20,187 1261
Johor 20 20 100 17 1 3 17,807 890Perak 15 15 100 16 1 0 16,000 1066
WPKL 15 15 100 11 0 4 3,150 210Kedah 15 15 100 25 1 1 10,369 691
Terengganu 15 15 100 15 0 0 1,948 130Pahang 15 15 100 20 0 2 5,000 333Kelantan 10 10 100 7 0 3 2293 229
Selangor 20 19 95 18 0 1 23,912 1,258
Negeri Sembilan 15 14 93 11 0 0 10,350 739
Pulau Pinang 15 11 73 15 1 0 10,850 986Labuan 10 7 70 7 0 0 1980 282
Perlis 10 6 60 4 0 2 3,000 500
Overall 220 210 94 214 8 39 139,855 666
SOHELP: NOISE IMPROVEMENTS
27 ITS Management Sdn Bhd
Loud noise emitted
Signage at machines according to Noise
Mapping – PPE provided
Provide housing with double layer wall protection –
reduced around 10 dB
AFTERBEFORE
Level 4
SOHELP: CHEMICAL IMPROVEMENTS
28 ITS Management Sdn Bhd
AFTERBEFORE
Level 4
Re-serviced & changed defected parts
Waste drums on the roadside Build Waste Store with containment
Rusted & disorderly Pumps for Eyewash/Eyeshower
SOHELP: ERGO IMPROVEMENTS – PACKING SECTION
29 ITS Management Sdn Bhd
AFTERBEFORE
Level 5
Manual Cassette Packing
Messy and difficult cart transfer process
Installed overhead conveyor direct link to supply from
production
30
SoHELP PROMOTION- 2016
ITS Management Sdn Bhd
ILO –KOREA OCCUPATIONAL SAFETY AND HEALTH (OSH) PROJECT
12 – 16 July 2016
SEMINAR ON CHEMICAL SAFETY AND SECURITY MANAGEMENT FOR MEMBER STATES OF SAARS AND ASEAN
MEMBER STATES 17 – 20 October 2016
REPUBLIC PEOPLE’S OF
BANGLADESH
OSH WEEK1
2
3
FMM OSH CONFERENCE 19-20 April 2016
24th IUPAC INTERNATIONAL CONFERENCE ON CHEMISTRY EDUCATION (ICCE)
15 – 20 Ogos 2016
MIHA INTERNATIONAL CONFERENCE & EXHIBITION20 – 21 Oktober 2016
NATIONWIDE
MYANMAR
SARAWAK
KUALA LUMPUR
PETALING JAYA
RADIO SALAM FM, BERITA HARIAN, DOSH WEBSITE JNATIONWIDE
4
5
6
7
SoHELPCONTINUNITY
Nov2016
SoHELP Multi Location Org. (FELDA, IOI, Sime Darby)
Dec2016
SoHELP Year End Achievement Report
Apr2017 SoHELP Convection
Mei2017
SoHELPPhase 2
Nov 2017
OSH Award SoHELPCategory
Jan 2018
Integration SoHELPin Curriculum (SHO,
CHRA , 3S)
Feb 2018
SoHELPInternational Level (OIC OSHnet, MCTP)
June 2018
SoHELP Interactive Tools (*Depending On Allocation)
CONCLUSION
32
Result for the first 6 months SoHELPimplementation : 211/220 (96%) workplace participate in this programme
National GPS 2.4/5 achieved ( 2.3, 2.5,2.5)
214 SHO, 7 assessors and 39 involved
135,085 workers will be benefited in phase 1
Synergetic DOSH – Industry cooperation and Industry – Industry cooperation is crucial to enhance workplace occupational hygiene standard.
After April 2017, SoHELP will be continued under Strategy 4 OSHMP 2020.
ITS Management Sdn Bhd
For Choosing ITS Management Sdn Bhd
As Your Training Provider
If you have questions or require further assistance later, please email to
Email Subject: “Attn: Trainer’s Name”
Other inquiries, please email to
33 ITS Management Sdn Bhd