Overstock.com : StrongStart Implementation. July. Project launched Migration plan Integration plan. Deal Signed. August. Challenges Hitting a small window with a big solution Must be live and ready before the holiday shutdown (< 3 months) - PowerPoint PPT Presentation
Citation preview
Proprietary and Confidential
Challenges• Hitting a small window with a big solution• Must be live and ready before the holiday
shutdown (< 3 months)• Integration with existing Teradata/ARM
systems• Maximize real-time data to drive
customer interactions
Results• Live and running in time for holiday rush• 36 IP addresses warmed up• 12 users (technical & marketing) trained• Volume exceeding 275M per month &
growing• 10M messages per hour “burst”
capability• 99% delivery rate
OVERSTOCK.COM: STRONGSTART IMPLEMENTATION
“Very impressed and pleased…concerned that there may not be any bandwidth left for the actual website.” Project Manager—Overstock.com
Deal Signed
Installation
Integration & M
igrationTrainin
gLive
July
August
September
October
Project launchedMigration planIntegration plan
Install/Config hardwareInstall/Config software
Teradata integrationContent migration
End user trainingAdmin training
IP warm-upTestFull production