    Optical Network Curriculum

    Development Section

    ISSUE

    OTA105205 OptiX OSN

    1500/2500/3500 Equipment

    Commissioning

    1.0

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    2/62

    2Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Review

    Why do we need to test the

    equipment?

    What type of instrument do we need?

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    3/62

    3Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Objectives

    Carry out the hardware and

    software commissioning of each

    NE successfully

    Connect the NEs topology andconduct the system commissioning

    Upon completion of this course,you will be able to:

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    4/62

    4Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Course Contents

    Chapter 1 prepare for commisssioning

    Chapter 2 Single Station Commissioning

    Chapter 3 System Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    5/62

    5Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    prepare for commissioning

    Prepare tools and instruments

    Understand of engineering document: networking and service

    Confirm external environment: Power, DDF, ODF and Clock

    Install T2000LCT

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    6/62

    6Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Course Contents

    Chapter 1 prepare for commissioning

    Chapter 2 Single Station Commissioning

    Chapter 3 System Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    7/62

    7Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 1 Single Station Commissioning

    Single Station Hardware Check

    Cabinet Power ON Test

    The Sub-rack Power ON Test

    Configuration and Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    8/62

    8Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Installation Check

    Cabinet installation

    Multiple cabinets must be aligned

    Order wire, fiber extractors and wrist straps are not lost

    No other unrelated objects

    Sub-rack installation

    Grounding of the sub-rack

    No screws, broken & bended pins on the backplane etc

    Cabling

    Power supply cables, grounding cables, external alarms wiring

    and pigtail fibers

    Note: grounding is according to the SDH recommendation

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    9/62

    9Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Power Box

    NEG2(-)

    INPUT

    RTN2(+)RTN1(+) NEG1(-)

    SW3/20ASW1/20A SW2/20A SW4/20ASW1/20A SW3/20ASW2/20A SW4/20A

    1. GND 2. PGND 3. RTN1(+)

    4. NEG1(-) 5. RTN2(+) 6. NEG2(-)

    7. INPUT CABLE 8. OUTPUT CABLE(LEFT) 9. OUTPUT CABLE(RIGHT)

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    10/62

    10Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Power Box Test

    Power terminals resistance values (Note: external powercable not connected, because there is not main power switch

    on the power panel)

    Switch OFF: the resistance between NEG1(-)/NEG2(-) and

    RTN1(+)/RTN2(+)/PGND should be infinity;

    Switch ON: the resistance between NEG1(-)/NEG2(-) and

    RTN1(+)/RTN2(+)/PGND should be tens K,if the resistance

    less than 20, short circuit happens and must be eliminated;

    Check the metal piece between (BGND &PGND) terminals

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    11/62

    11Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Cable Check

    All cable including power cable, GND cable, relay cable and

    tail fiber should be nicely put in order and be labeled correctly)

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    12/62

    12Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Boards Appearance Check

    You must affirm:

    All bolts on top and bottom of boards should be tightened and not falling

    off.

    The metal reeds on the two sides of boards should not be warped

    Spans of GXCS/CXL1/4/16 should be buckled (the jiggle switch should be

    closed)

    All boards are screwed well and plugged to the end

    Anytime when in contact with boards, you should wear anti-static wriststrap or anti-static glove

    The RJ-45 interface on AUX should not be mis-plugged

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    13/62

    13Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Dont Forget!

    Engineering document single station part, must

    be done for each sites

    Be sure all power supply switches are OFF

    during the hardware check

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    14/62

    14Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Chapter 1 Single Station Commissioning

    Single Station Hardware Check

    Cabinet Power on Test

    The Sub-rack Power on Test

    Configuration and Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    15/62

    15

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Power Requirements

    Power supply fuse capacity

    Single OptiX OSN 1500 sub-rack = 10 A

    Single OptiX OSN 2500 sub-rack = 15 A

    Single OptiX OSN 3500 sub-rack = 20 A

    The requirement of expansion capabilities should be considered.

    Power supply output voltage

    Optimum value of -48V20% (or -60V20%)

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    16/62

    16

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Cabinet Power is ON Now!

    Power cable and GND cable are rightly connected into the

    cabinet

    Measure the voltage between NEG1(-)/NEG2(-) and

    RTN1(+)/RTN2(+)/PGND,which should be in scope of-4820%V(or -60V20%)

    Measure the voltage between RTN1(+)/RTN2(+) and PGND,

    which should be less than 0.5V

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    17/62

    17

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Questions

    Do we need to test the voltage

    between the power terminal posts

    after powering?

    What is the value of the resistance

    between BGNDsand PGND?

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    18/62

    18

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 1 Single Station Commissioning

    Single Station Hardware Check

    Cabinet Power on Test

    The Sub-rack Power on Test

    Configuration and Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    19/62

    19

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    The Sub-rack Power on Test

    Check the connection from the power cables to the two PIU

    boards correct and tightened

    Turn ON the power switches at the top of rack, in order tosupply power to the subrack

    Test the function of acoustic alarm and indicators

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    20/62

    20

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Sub-rack Power is ON Now!-1

    Check the running of the fans

    Observe the board indicators

    it should be normal after 2 ~3 min

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    21/62

    21

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Sub-rack Power is ON Now!-2

    Did you test the ASCC ALMCUT switch?

    Short press

    Long press

    OptiX OSN 3500ASCC, OptiX OSN 1500/2500CXL1/4/16

    Test ASCC reset button

    Test alarms externally connected

    Check the order-wire

    Insert the connector for order-wire into interface phone on AUX/SEI

    board

    Set the ringing switch to ON

    Set dial mode to T

    Confirm order-wire has dialing tone when the talk key pressed

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    22/62

    22

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 1 Single Station Commissioning

    Single Station Hardware Check

    Cabinet Power on Test

    The Sub-rack Power on Test

    Configuration and Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    23/62

    23

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Connection Scheme & Testing Command File

    A

    X

    C

    S

    FAN

    Fibre cable area Fibre cable area

    Sub-rack

    A

    X

    C

    S

    S

    L

    O

    1

    S

    L

    1

    6

    S

    L

    6

    4

    S

    L

    6

    4

    IN OUT

    SDH analyzer

    IN

    OUT

    SL

    1

    6

    AU

    X

    /

    S

    A

    P PC

    COM/ETH

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    24/62

    24

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Attention!

    With the network cable (cross/straight), computer is connected to:

    COMof AUX/SAP: the PC IP address should be 192.168.0.X with

    net mask of 255.255.255.0, X refers to board slot number

    ETHof AUX/SAP: the PC IP address should be 129.9.X.X with net

    mask of 255.255.0.0

    Set ID (in scope of 1~49136)IP and subnet mask (if necessary)

    Check the software compatibility (FPGA, board software, BIOS

    and host software)

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    25/62

    25

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test of the service bus

    Configure NEs data, including boards, service (in series), protection

    The service bus test must cover all card plugging slots and VC4 as possible

    Test the service bus

    connect the instrument to the NE

    Monitor the alarms and performance events with T2000none of alarm and error code, pointer adjustment happens at least 1 hour

    If not, try again 2

    M

    TX

    RX

    TX RX

    2M

    Error

    Code

    Instrument

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    26/62

    26

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Bit Errors Test

    Test the working and protection channels when

    The configuration is 2-fiber bidirectional MSP

    The configuration is 4-fiber bidirectional MSP

    The configuration is 1+1 or 1:N linear MSP

    The configuration is 2-fiber unidirectional SNCP

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    27/62

    27

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test of the Interface Indexes

    Measure the transmitted optical

    Measure the received optical, if the system is connected

    Check the attenuation of line fiber and trail fiber(

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    28/62

    28

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test of the cable and fiber

    Test electrical cable in 100% inerrability

    Two states of normal and interrupted

    All E1/T1/E3/T3/E4/155M interfaces

    Test trail fiber in 100% inerrability The optical power on the ODF frame (normal and interrupted)

    Loopback the optical port on the frame

    1. R-LOS ends

    2. Close the laser, R-LOS happens

    3. Open the laser, R-LOS ends

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    29/62

    29

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test LAN Switch Path

    Query the software version of boards:

    All boards should be found

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    30/62

    30

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test TPS

    For OSN 3500:

    E1/T1 TPS(1:8):

    slot 1 protects slots 2~5 and slots 13~16

    E3/DS3/E4/STM-1(e) TPS(2 groups of 1:3):

    slot 2 protects slots 3~5

    slot 16 protects slots 13~15

    For OSN 2500:

    E1/T1 TPS(1:4):

    slot 5 protects slots 6~7 and slots 12~13

    E3/DS3/E4/STM-1 TPS(2 groups of 1:3):

    slot 6 protects slot 7

    slot 13 protects slot 12

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    31/62

    31

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test TPS

    Test step:

    1. Configure boards, service and TPS protection group, PRI and WTR

    2. Connect electrical interfaces in series (T1R2, T2R3T31R32)

    3. Connect 2M instrument with R1 and T32

    4. Pull out and hard reset the active board

    5. TPS should happen (TPS-ALM and ACT indicator)

    6. Restore TPS

    7. Test priority TPS and cancel one by one

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    32/62

    32

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test TPS

    EU08

    R2

    T2

    R3

    T3

    R4

    T4

    R1

    T1

    R6

    T6

    R7

    T7

    R8

    T8

    R5

    T5

    Send by SDH analyzer

    Received by SDH analyzer

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    33/62

    33

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test active/standby GXCSA and SCC switch

    Test steps (For OSN 3500):

    1. Configure boards and services, MSP

    2. Connect equipment with instrument

    3. GXSC/SCC switch(3 methods):

    Issuing switch command by T2000

    Hard reset active board by T2000

    Pull out active board (jiggle switch)

    4. VC4 services and clock should be good,VC12 services are momently broken

    5. Test MSP switch. It should succeed

    6. Early MSP switches, late active/standby SCC. Service should be protected

    Notice:

    The interval of active/standby switch should be done after 1 min at least

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    34/62

    34

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Test active/standby CXL1/4/16 switch

    Test steps (For OSN 2500):

    1. Configure boards and services, MSP

    2. Connect equipment with instrument

    3. Active/standby switch(3 methods):

    Issuing switch command by T2000

    Hard reset active board by T2000

    Pull out active board (jiggle switch)

    4. VC4 services and clock should be good,VC12 services are momently broken

    5. Test MSP switch. It should succeed

    6. Early MSP switches, late active/standby switch. Service should be protected

    Notice:

    The interval of active/standby switch should be done after 1 min at least

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    35/62

    35

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Final Work to Do!

    Correctly configure the equipment according to user's need

    Confirm services and alarm

    Backup the FDB0 and FDB1

    Test ECC function

    Single station power off test (for 10 minutes)

    What else?

    ASCC ALMCUT is correctly set

    Order wire handset switch is ON

    All hardware and software loop backs are removed

    All single station information are recorded (Engineering

    Documents)

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    36/62

    36

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Course Contents

    Chapter 1 prepare for commissioning

    Chapter 2 Single Station Commissioning

    Chapter 3 System Commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    37/62

    37

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    38/62

    38

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Request of System commissioning

    1. Connect separate NEs and form networking

    2. Test services and confirm configuration correctness

    3. Test the networking function of ECC, order-wire and protection

    4. Test the long-term quality of the network

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    39/62

    39

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    40/62

    40

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Are the System Fibers Connected well?

    Pigtails labeling

    The value of the received optical power (higher than the receiver

    sensitivity 3dB and less than the overload optical power 5dB)

    Fibers connection based on the actual network topology structure

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    41/62

    41

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    42/62

    42

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    What is ECC

    Login to the all network elements

    Automatic routing of the ECC

    Whether the network elements connected to each other with the

    shortest ECC route

    Long/Short ECC route test

    ECC pass through test

    Ethernet expanding ECC between two NEs (if itsrequired)

    Automatic

    Manual

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    43/62

    43

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    44/62

    44

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Send Your Actual Configuration

    Check the correctness of each NEsconfiguration

    Alarms checking (no abnormal alarms)

    End-to-end instrument test (normal and interrupted)

    1. Compare instruments

    2. loopback

    NE

    NE

    NE

    NESDH analyzer

    Loop-back

    of the

    SDH Port

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    45/62

    45

    Confidential Information of Huawei.

    No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    46/62

    46

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Protection Switch Test

    The purpose is to test the reliability of the equipment and services

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    47/62

    47

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test switch of 2 fibers MSP ring

    Query the switch state, when the fiber normal

    1. The APS protocol should be started

    2. The switch state should be normal

    Test switch

    1. Connect the equipment with the instrument

    2. Loopback the services

    3. Pull out the fiber or close the laser, switch should successfully happen

    S SII

    P

    PP P

    P

    P

    EB

    C D

    A

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    48/62

    48

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test switch of 2 fibers MSP ring

    The switch states should be correct

    Switch completion in 50ms

    After switching, errors should not happen

    Each NE should report APS-INDI

    4. Test restoring

    5. Test switch for each section repeatedly

    6. Test switch and restore when power OFF

    Tests for other functions1. Test force switch and clear function

    2. Test switch time

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    49/62

    49

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test switch of other MSP

    4 fiber MSP ring

    Same 2 fiber MSP ring, but

    1. Test the section switch

    2. Test the ring switch

    1+1/1:n line MSP chain

    Same 2 fiber MSP ring, but

    1. Test switch of each section in turn

    2. Test restoration, if necessary

    3. Avoid to interrupt the ECC route

    4. Test force switch and clear function, etc

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    50/62

    50

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test switch of SNCP ring

    Query the switch state, when the fiber normal

    Test switch

    1. Connect the equipment with the instrument

    2. Loopback the services

    3. Pull out the fiber or close the laser, switch should successfully happen

    The switch state should be right

    Services is not interrupted

    Test restoration

    Test switch of each section repeatedly

    Delay time=0

    EB

    C D

    A

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    51/62

    51

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test switch of VP ring

    same as the previous case

    Notice:

    1. Secondary switch and errors should happen

    2. Can restore normally

    3. Query switch state

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    52/62

    52

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    53/62

    53

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Test clock protection

    Clock protection should be started

    Test by fiber broken

    1. Successfully switch, and trace the right clock source

    2. SYNC-LOSS is normal and LTI is abnormal

    3. After switching, pointer adjustment should not happen

    Test restoration

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    54/62

    54

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Observe performance of clock track

    If clock source is not configured, when normal:

    Test by breaking fiber

    1. Clock mode is tracing and does not switch to Hold-Over or to free-run

    2. Synchronous source does not switch

    3. Pointer count adjustment is less than 6 for 24 hours

    Test other target

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    55/62

    55

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Observe performance and alarm of full networking

    Request:

    No error in 24 hours

    less than 6 times pointer adjustment counts in 24 hours

    Notice:

    Identical data and time of T2000 and each NE

    Using performance monitoring of 15m and 24h

    O i ?

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    56/62

    56

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    What Are The Other Functions?

    Electrical protection switching (EPS)

    AXCS active/standby switchover test

    Clock protection test

    Network management system test

    Whole network order wire test

    Software compatibilityThe remote maintenance test

    Ch 2 S C i i i

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    57/62

    57

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Chapter 2 System Commissioning

    Request of System commissioning

    Fiber connection

    ECC

    Service testing

    Network protection function test

    Other functions test

    Alarm and performance monitoring test

    S Th N k El P f

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    58/62

    58

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Set The Network Elements Performance

    1. The receivable J1&C2 bytes

    and instrument should have thesame setting when performing

    performance monitoring

    2. Date and time of each network

    element should be set

    3.Dont forget to start 15m and

    24h performance monitoring

    Bit E T t

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    59/62

    59

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Bit Errors Test

    Service Connection/Disconnection Test ensures all service

    connections are correct

    Multiple signals (155M/622M/2.5G) can be connected in

    series during the test

    The bit error test of the working channel should be done for

    24 hours. Then, the protection channel for 12 hour

    Opening the performance monitoring of T2000 also helps to

    locate faults

    S d Y A t l C fi ti

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    60/62

    60

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Send Your Actual Configuration

    Check the correctness of each NEsconfiguration

    Alarms checking (no abnormal alarms)

    End-to-end instrument test

    NE

    NE

    NE

    NESDH analyzer

    Loop-backof the

    SDH Port

    S

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    61/62

    61

    Confidential Information of Huawei.No Spreading without Permission. Security Level: Internal

    Summary

    The need for single and system

    commissioning

    Items that should be covered during thecommissioning

    Self-healing function is very important

    Alarm performance monitoring is the key for

    successful commissioning

  • 7/25/2019 OTA105205 OptiX OSN 150025003500 Equipments Commissioning Is

    62/62